R-2025-087 - 3/27/2025 RESOLUTION NO. R-2025-087
WHEREAS, the Round Rock Transportation and Economic Development Corporation
("RRTEDC") has previously adopted a Transportation Capital Improvement Program ("TCIP"), and
WHEREAS, the RRTEDC wishes to amend said TCIP, and
WHEREAS, the bylaws of the RRTEDC require that said amendments to the TCIP be
approved by the City Council, and
WHEREAS, the City Council wishes to approve said amendments to the TCIP, Now
Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the amendment to the Transportation Capital Improvement Program approved by the
Round Rock Transportation and Economic Development Corporation, which is attached hereto as
Exhibit"A," is hereby approved.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 27th day of March, 2025.
ZM/
CRAIG ORG , Mayor
City of Round 06ck,Texas
ATTEST:
- ( '�
AMR FR IN, City Clerk
0112.20252;4913-3647-8759
EXHIBIT
01
TCIP Amendment#54
New Projects
Project Name Cost Transaction Description
Chisholm Trail Road at Brushy Creek Sidewalk Connection $ 1,500,000 Engineering Services
Northeast Downtown Improvements Phase 2 (Sheppard St) $ 2,500,000 Engineering Services
Total Budget for New Projects $ 4,000,000
Existing Projects Adjustments
Project Name Cost Transaction Description
County Road 118 Widening (University Blvd to SH 130) (A) $ 2,500,000 Budget Increase - Right-of-Way Acquisition
Gattis School Road Segments 4 & 5 (Double Creek Dr to Meister
$ 1,500,000 Budget Increase - Right-of-Way Acquisition
Lane & Rusk Rd to Via Sonoma Trail) (A)
Greenlawn Boulevard Improvements (B) $ 11,000,000 Budget Increase - Construction & Contingency
Sam Bass Road & Hairy Man Road Intersection Improvements (A) $ 1,000,000 Budget Increase - Right-of-Way Acquisition
Total Adjustments $ 16,000,000
Total Type B Impact $ 20,000,000
(A) Budget approved on prior TCIP amendment covered design. Additional budget required to start ROW acquisitions.
(B) Construction budget included in prior TCIP amendments during the design phase of the project. Additional budget required due to updated
engineer's estimate with 100% design plans.
Note: Additional budget needs are covered by the "Transportation Planned Projects" section of the 2025-2029 Funds Allocation Plan.