R-2025-162 - 6/26/2025 RESOLUTION NO. R-2025-162
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with
Capital Excavation Company for the Wyoming Springs Segment 1Project, and
WHEREAS, the Council has determined that it is necessary to make adjustments/changes to
the quantity of work to be performed or materials, equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 1 to the Contract with Capital Excavation Company for the Wyoming
Springs Segment 1Project, a copy of said quantity adjustment/change order being attached hereto as
Exhibit"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 26th day of June, 2025.
CRAA MOR9(0, Mayor
City of Rou Oock, Texas
ATTEST:
Q.4,,,,.&,
ANI<FRANKLIN, City Clerk
0112.20252;4925-5783-0990
EXHIBIT
Page 1 of 3
A
Contract Quantity Adjustment/Change Order
reouNaaoatxn;
rev,01/16
Department:
Project
Name: Wyoming Springs Date: 5/1/25
City Project Change Order/Quantity
ID Number Adjustment No. 1
Vendor Capital Excavation 2967 Business Park Dr, Buda,TX 512-440-1717
Company Name Address Phone No.
Justification
Adding items for ATMOS gas line cover, 30"waterline split restraints,8"waterline wet connect and curb inlet modification. These items were
not included in the original bid estimate. Added items for the Brushy Creek Bridge redesign to alleviate dead loads and prolong the life of the
bridge while maintaining aesthetic appeal. Added item for C153 Fittings Credit,switched from C110 fittings to C153 to shorten lead times and
reduce cost.
SUMMARY Amount %Change
Original Contract Price: $25,917,630.47
Previous Quantity Adjustment(s): $0.00
This Quantity Adjustment: $130,471.00
Total Quantity Adjustment(s): $130,471.00
Total Contract Price with Quantity Adjustment(s): $26,048,101.47
Previous Change Order(s): 0%
This Change Order: $329,947.50 1%
Total Change Order(s)To Date: $329,947.50 1%
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s)Plus Change Order(s)]: $26,378,048.97
Difference between Original and Adjusted Contract Prices: $460,418.50
Original Contract Time: 450
Time Adjustment by previous Quan.Adj./Change Order:
Time Adjustment by this Quan.Adj./Change Order:
New Contract Time: 450
Submitted far App"!
Prepared By: Joshua LittleJoshua Little, Sr. Project Manager 5/1/25
Signature Printed Name,Title,Company Date
Approvals
oe chesne `g�,
Contractor: ) y � �� Joe Chesney,VP Operations 5/1/25
Signature Printed Name,Title,Company Date
City Project ?MMa"�pe� Gerald Pohlmeyer 05/28/2025
Manager:
Signature VPrinted Name,Title Date
Mayor/City
Manager
Signature Printed Name,Title Date
Page 2 of 3
Contract Quantity Adjustment/Change Order
It NOO[TEXAS
rev,01/16
Project Name: Wyoming Springs
Quan.Adj./Change Order No.: 1
Chan a Order Data
Contract
Time
Adjustment
Item # Item Description Unit Qty. Unit Price Amount (Days)
Atmos Gas Cap CY 116.5 $1,468.00 $171,021.56
C153 Fittings Credit LS 1 -$22,178.06 -$22,178.06
Brushy Creek Bridge Redesign LS 1 $96,642.00 $96,642.00
30"Split Bell Joint Restraints EA 4 $7,100.00 $28,400.00
Cap Exc Accelertation Crew for 30"
Waterline LS 1 $23,665.00 $23,670.00
Multi Inlet Connection,Curb Inlets EA 15 $1,574.00 $23,610.00
8"Wet Connect EA 1 $8,782.00 $8,782.00
TOTALS: $329,947.50 0
Page 3 of 3
Contract Quantity Adjustment/Change Order
RDUNO NOO[rExP'�
rev,01/16
Project Name: Wyoming Springs
Quan. Adj./Change Order No.: 1
Quantity Adjustment Data
Contract
Time
Adjustment
Bid Item # Item Description Unit Qty. Unit Price Amount
Ductile Iron Fittings TN 3.19 $40,900.00 $130,471.00
--
TOTALS:J $130,471.0010