Loading...
Contract - Tetra Tech, Inc. - 8/28/2025 STATE OF TEXAS § COUNTY OF WILLIAMSON § SUPPLEMENTAL CONTRACT NO. 4 TO CONTRACT FOR ENGINEERING SERVICES FIRM: TETRA TECH, INC. ("Engineer") ADDRESS: 4801 Southwest Parkway, Pkwy 1,Suite 185,Austin,TX 78735 PROJECT: CR 112 Improvements from A.W. Grimes Boulevard to CR 117 This Supplemental Contract No. 4 to Contract for Engineering Services is made by and between the City of Round Rock,Texas,hereinafter called the"City"and Tetra Tech, Inc.,(formerly known as RPS Infrastructure, Inc.) hereinafter called the "Engineer." WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter called the"Contract,"on the 5th day of December,2019 for the CR 112 Improvements from A.W. Grimes Boulevard to CR 117 Project in the amount of$347,442.39; and WHEREAS, the City and Engineer executed Supplemental Contract No. 1 on July 22, 2021 to amend the scope of services and to increase the compensation by $663,281.84 to a total of $1,010,724.23; and WHEREAS,the City and Engineer executed Supplemental Contract No.2 on December 21,2022 to amend the scope of services and to increase the compensation by $38,850.00 to a total of $1,049,574.23; and WHEREAS, the City and Engineer executed Supplemental Contract No. 3 on March 8, 2024 to amend the scope of services and to increase the compensation by $39,700.00 to a total of $1,089,274.23; and WHEREAS,it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by$103,722.00 to a total of$1,192,996.23; NOW THEREFORE,premises considered, the City and the Engineer agree that said Contract is amended as follows: I. Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum to Exhibit B. Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum to Exhibit C. Supplemental Contract Rev.06/16 0199.1958;4897-7562-4282 84275 1 II. Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by $103,722.00 the lump sum amount payable under the Contract for a total of$1,192,996.23, as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF,the City and the Engineer have executed this Supplemental Contract in duplicate. [signature pages follow] Supplemental Contract Rev.06/16 0199.1958;4897-7562-4282 84275 2 TETRA TECH,INC. By: y: Kevin Hoffman, RegioA1 Transportation Director 8/ 8/ 2025 Date Supplemental Contract Rev.06/16 0199.1958;4897-7562-4282 84275 3 CITY OF ROUND ROCK APPROVED AS TO FORM: By: Craig Mo an', Mr p ie L. San re, City Attorney V2e/Z025 Date Supplemental Contract Rev.06/16 0199.1958;4897-7562-4282 84275 4 ADDENDUM TO EXHIBIT B Engineering Services SCOPE OF WORK-Supplemental for Roadway Improvements on CR 112 from A.W.Grimes Blvd to CR 117 Round Rock,Texas From: A.W.Grimes Blvd To: Approximately 400' east of CR 117 Length: 1.18 miles County: Williamson City: Round Rock PROJECT STATEMENT The roadway improvements for CR 112 from A.W. Grimes Blvd to approximately 400' east of CR 117 are to widen this 1.18-mile section from a two-lane roadway to six-lane divided roadway and add pedestrian facilities. The City's Transportation Master Plan indicates this section of CR 112 should be enhanced to six-lanes. This supplemental is for additional design work to address 95% comments, developer coordination and continued utility coordination. The additional work required is described below according to each task to be performed. PROJECT MANAGEMENT A. Managing Contracted Services(Project Management) a. Coordination: The ENGINEER shall continue coordination with the CITY beyond the original scope of the contract related to additional design comments, developer coordination, future utilities, waterline easements, and utility relocations along the project for an additional 6 months. b. Subconsultant Coordination: The ENGINEER shall continue coordination with subconsultants (Survey/SUE) beyond the original scope of the contract related to the waterline easement and ongoing utility relocations. c. Project Management and Progress Report: The ENGINEER shall continue to meet with the internal design team and coordinate plan modifications across design disciplines for additional design CR 112—Round Rock,TX Page 1 of 3 Exhibit B modifications. The ENGINEER shall continue to prepare monthly progress reports with invoicing to the City for review and approval for an additional 6 months. ROADWAY DESIGN A. Intersection Layouts: The ENGINEER shall prepare additional intersection layouts in conjunction with developer coordination for access at Colony Drive and Ekvall Drive and update other design sheets accordingly to include the intersection details. SIGNING,PAVEMENT MARKINGS AND TRAFFIC SIGNAL B. Signal Upgrade: The ENGINEER will update the existing signal detection AN construction plan details at A.W.Grimes and CR 112 per comments received at the 95%submittal. Signal detection modification was not part of the original scope of work. MISCELLANEOUS A. Plan Updates for Additional Design Changes: The ENGINEER shall update the Traffic Control, Drainage, Signing and Pavement Markings, Utility, and Erosion Control plans to accommodate the new intersecting streets(Colony Drive and Ekvall Drive). The ENGINEER shall also develop additional design sheets including traffic signs and summaries, cross street plan and profile layouts, culvert hydraulic sheets, 100-yr hydraulic calculation sheets,and pipe/box connection details. B. Utility Coordination: The ENGINEER shall continue to attend monthly utility coordination meetings with the City and private utility providers. The ENGINEER shall review design relocation plans, attend site visits to coordinate/verify relocations,and attend separate design coordination meetings to mitigate impacts with the proposed design. C. Developer Coordination and Utility Accommodations: The ENGINEER shall coordinate improvements to adjacent design projects to address access management and connection of future utilities across the CR 112 project. The engineer shall prepare conduit and utility casing details and update design drawings, quantities, and specifications to include conduit for future utilities. D. Update Standards, Summary of Quantities,and Cost Estimates: The ENGINEER shall update relative roadway, drainage, signing and striping standards and associated plan details or bid items following most recent City or TxDOT standards. The engineer shall update the summary of quantity sheets and cost estimate to include the latest design modifications and update the construction cost estimate to include the latest bid items. CR 112—Round Rock,TX Page 2 of 3 Exhibit B CONSTRUCTION PHASE SERVICES A. Construction Meetings: The ENGINEER attend in-person weekly construction meetings at the onset of construction and transition to bi-weekly meetings as construction progresses. Anticipated additional twenty-six(26) construction meetings for the duration of the project. B. Notice of Design Changes: The ENGINEER shall prepare additional design details for requested design modifications from the City or Contractor required to mitigate conflicts or incorporate new design items into the project. Anticipate an additional five(5)notices or request for design changes. C. Utility Review and Verification: The ENGINEER shall evaluate additional utility relocation design and confirm locations for new utilities being constructed within the project limits. D. Pay Application Review: The ENGINEER shall evaluate contractor pay applications in accordance with work completed or stockpiled on site for each monthly billing period. CR 112—Round Rock,TX Page 3 of 3 Exhibit B ADDENDUM TO EXHIBIT C Work Schedule Attached Behind This Page Pram Schedule 10 "'Name N."' P" r— P"""°" :.t,it„1:1el:t,,I=I:cr1=itrixritrtr,tmlx,1=,C11,IzW,larrltrltr1.ci ri:cramis1:t7,1m.1=1:cd.. I;r t-ritrizu stri :t:1:c,ltdiol ,l'eteriz i:cri rlirktt1.A;1:rLI: ,InFlt,l:rl:rritti-lraE1 2 1 011u391Ma.b to In* tan? MMNnt Mon 6nn1 ,-- —9..1.1M . MI6.6 •.61/22/11 all 10/11n4 1 — awn CUMnNncn 160a.p Mar Wllnrnlnl/ll to I2N061 Way•canton Man. MM1/ytl.n 12/9/22 1..51 days * 61.316 na•ay Acquisnion — uwr.rmemai Documents Ooau. 7*yWW/t1 Mon 12ry/21 1.6.10 nays 1 1 0rMM0.a..... a u1 n o*ron 40 an. Mmll/ll/i1r,10AUla a uu1Mrr+ee.n.n 3 a oft.*l .Phase 104a.. 3.0/1/11 Fril1n+n1 1 • — 301 . 111 a .4,1/l1 mu W3/21 1 11 twK m n 1 — 9ow5renantl Inn .n1lnnl Fri1lnrs1 6 `119*wYrrrnM 40 M110na1MMlw ,6 1S nays Mon 9 1k 19wa.MMlw1` 1. 91...drwr 1306.0 Mar Wv/lm 1/11/11 1 1 12 MM.. 154 nays Mon 13/lln3a.1n4n1 10 1 Plan. a 60165d*mma/ lays 1117129ru inl/l9nl 12 aaminal is M a60960no.6 Pa.�a. 1Saays Men0/1/ll nis/19/ll t3 x1M611...w. IS 60.,n rdubude 1)3 a. Oa Liar... l 6 M 9016 Mans 156days Mon 1/»/laMon 3nl/l3 14 90,6 n.. Malulmin.i 1day *re 3n1n33.3ne/23 16 4,0.4 300n'041 10 9016013 a11.P.m 20days Wad l/l3/23nedn9/l3 11 90.[try o u Ray ww a 10019 O.Y*a..9 nldna w44/Wll1317/WM a 1 1 a 10016P511 Sal days WeaanMl3lrp6n0na 18 -100a P686 a WPM 5.6m1nal 1d„ Fri 6/21/24.n6nlna m 4,00.0 506m414i a 10096 City oa..Reel. 1s drys Man 6n0/233n l/tln. 31 ry an anw. a W M. uass Too MOM Tl01/11/1. a !WIMepn9 Ida, "re>n0na aye 3n0/24 12F5.11 an a r1M1.mw 110431 wMl/l1/lawealn./la la a Ma Oa..ry 0 Pe.wnmen1on 6dns nue/t5/M lnua/ll/la 15 n 1:m4ruabn rms. 141.a w.v3a/l3wen 4/13/31 a a.0aevun.o,rn.e 9 lays nu l0/u/vl..u/10/l. 3MS.346.ys a antral.sw•Onn 360a.n .n10/11/14 Thu 1n9n6 a 1 1 a .p 011 11 asp al1nMarna0/l6 Ma 14 L� P.}x 01113P516wahsar la • aged annoy 1� wad. — M...aa...3+e.ro aa.e.a •[ • r.nys law SO SAGAS SW1a....., . . ..d.sr w.........r 1 - I ...ass >011•1111101111f ....sa...r 0 inn ma 1 MY... • nave P.9.1 ADDENDUM TO EXHIBIT D Fee Schedule Attached Behind This Page EXHIBIT D 6/27/2025 Project:CR 112 Final Design Fee Schedule-Lump Sum Firm Provider:Tetra Tech(RPS) S'"'Pro1rA s'nhm Pn,Jret A'''''""'Ennineer Admin/ Work Tyra 1'i6 ril�nl Engineer Project EnEngineerL'ni�n lh.iener Inrd \,i nl I.n x,r ln.Ile, Amount Mower III Clerical lunar. DWGS I.sheet mount Project Management Coordination with City _ 12 x __ $5,710.00 SubconaWlar0 Coordination Deliverables Review and Invoices ! I A I' f2,560.01 Progress Reports and Updates o 12 $2,280.00 Subtotal: S10,550.00 Roadway Design Roadw:IN Design Intersection Layouts(Update all sheets) I .. I 2 1 I 1 2 I I x I I I it, I 2 I 28 I $10.2E0.00 Subtotal: S10,280.00 Signing,Pavement Markings,Signalization(Permanent) Traffic Signal Traffic Signal Design MoliOcation(I Location) I _ I I I? I 12 I I I 2,, I 2 I 13 I $4,160./0 Subtotal: $4,16001 Miscellaneous Plan Updates for Additional Design Changes 1 16 4 12 ,n 2 18 $6,960.01 Utility Coondnabon 4 Ix 8 311 _ I5 S6,200.00 Developer Coordination and Utility Accomrodatwns _ 16 4 12 34 I 34 $6.400.00 Update Standards,Summary of Quantities,and Cost Estimates _ x _ 8 20 3 7 $3,760.0(1 Subtotal: $23,32001 Construction Phase Services Construction Meetings(26 Additional) 12 'x 24 114 $23,880.01 Notice of Design Changes x Ix I x 24 18 86 $15,320.I81 Utility Review and Verification x I8 - IS 18 62 $11,600.00 Pay Application Review 16 16 $3,520.00 Subtotal: S54,320.10) HOURS SUB-TOTALS _ 66 224 52 140 36 6 526 Rate S295.00 S280.00 $220.00 $160.00 $140.00 $160.00 $100.00 SUBTOTAL $590.00 $18,480.00 $49,280.00 $8,320.00 $19,600.00 $5,760.00 $600.00 S102,630.00 DESCRIPTION FOTAL COSTS BY RC Project Management a 10,550.00 Roadway Design $ 111.280.00 Signing,Pavement Markings,Signalization(Permanent) $ 4.16000 Miscellaneous t 23,320.00 Construction Phase Services 9, 54,320.00 SI 11 O1_A I.LABOR EXPENSES S IO2,6301111 0171t:R DIRECT EXPENSES P OF UNITS COST)UNIT Mileage(nunber x current state rate) 1,560 $ 0.70 Nlrl_uu SUBTOTAL DIRECT EXPENSES S1 mrz.uo SUMMARY TOTAL COSTS S 102,630.00 TOTAL EXPENSES S 1,092.00 GRAND TOTAL S 103,72200 Page 1 of 1