Loading...
BCRUA_R-22-05-18-6A - 5/18/2022BCRUA_R-22-05-18-6A BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement 1.0 THE WORK OF THIS CONTRACT Unless otherwise provided in the Contract Documents, the CONTRACTOR shall be responsible for performing or causing to be performed all Worl< including labor and materials, necessary to build, construct, erect and equip the Project in accordance with the Contract Documents and, at its own cost and expense, to furnish all the materials, supplies, machinery, equipment, tools, superintendence, labor, insurance, and other accessories and services necessary to complete the said construction,in accordance with the Contract Documents and for the Contract Price defined in Section 3.0 of this Agreement . The Contract Documents for this Project include this Agreement and the following documents: i 3 i • Modifications • General Conditions • Specifications bearing the title BCRUA Phase 2 Raw Water Delivery System, Volume 1—Technical Specifications, consisting of Divisions as listed in the Table of Contents of the Project Manual, dated November 3, 2021 • Geotechnical Data Report bearing the title BCRUA Phase 2 Raw Water Delivery System, Volume 2—Geotechnical Data Report, dated July 2021 • Geotechnical Baseline Report bearing the title BCRUA Phase 2 Raw Water Delivery System, Volume 3—Geotechnical Baseline Report, dated July 2021 • Drawings consisted of the following sheets and volumes: o Sheets numbered G-0 to TC-45 and bearing the title BCRUA Phase 2 Raw Water Delivery System, Volume 1 — General, Raw Water Intake, Maintenance Building and Raw Water intake Tunnel o Sheets numbered AD-1 to ID-28 and bearingthe title BCRUA Phase 2 Raw Water Delivery System, Volume 2—Raw Water Pump Station i o Sheets numbered CD-1 to CD-31 and bearing the title Brushy Creek Regional Utility Authority Raw Water Pump Station, Volume 3 — Raw Water Pump Station o Sheets numbered CE-1 to CL-1 and bearing the title BCRUA Phase 2 Raw Water Delivery System, Volume 4 — Cedar Park WTP, Raw Water Transmission Tunnel and Pipeline, Leander Delivery Facilities - Sandy Creek WTP, and Jackson Street Extension • Addenda 01 through 07 • Proposal Form (Section 00300) • Conflict of Interest Questionnaire (Section 00300-A) • Certificate of Interested Parties (Section 00300-B) • Pump Proposal (Section 00400-A) • Vendor Compliance with Reciprocity of Non-Resident Bidders (TWDB-0459) • Contractor's Act of Assurance (ED-103) I Page 2 of 10 Issued for Bid(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement • Contractor's Act of Assurance Resolution (ED-104) • Notice of Award (Section 00510) • Notice to Proceed (Section 00520) 0 Performance Bond (Section 00610) • Payment Bond (Section 00620) Contractor's Certificate of Insurance 46 All other documents listed in the Project Manual dated November 3, 2021 not i listed above In addition to the provisions set forth in other Contract Documents, including but not limited to Section 3.03 of the General Conditions, in the event that a conflict between any of the provisions within the Contract Documents exist, OWNER shall determine which provision controls. If CONTRACTOR identifies the conflict, CONTRACTOR shall notify Owner's representative of the conflict, in writing. The Contract Documents are forms adopted by Owner and are not subject to negotiation, I modification or change unless Owner, in its sole discretion, agrees to do so. 2.0 CONTRACT TIME AND COMPLETION § 2.1 The date of commencement of the Work shall be stated in a Notice to Proceed issued by the OWNER. § 2.2 Contract Time §2.2.1 The Contract Time shall be measured from the date of commencement. §2.2.2 Time is of the essence in all phases of the Work. Additionally, time limits and periods of time stated in the Contract Documents are of the essence. It is specifically understood and agreed to by and between OWNER and CONTRACTOR ' that time is of the essence in the substantial and final completion of the Work, and that failure to substantially complete or finally complete the Work within the designated period, or as it may be extended,shall be construed as a breach of this Agreement. i i § 2.3 Substantial Completion The CONTRACTOR shall achieve Substantial Completion, as that term is defined in the Contract Documents, of the entire Work not later than 1740-Galendar-days 1700 calendar days (AD-05) from the date of commencement, subject to any adjustments of this Contract Time as provided in the Contract Documents. Page 3 of 10 Issued for Bid(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement §2.4 Liquidated Damages The CONTRACTOR acknowledges and recognizes that the OWNER is entitled to full and beneficial occupancy and use of the completed Work following expiration of the Contract Time. The CONTRACTOR further acknowledges and agrees that, if the CONTRACTOR fails to achieve Substantial Completion of any portion of the Work within the Contract time,the OWNER will sustain actual damages as a result of such failure. OWNER and CONTRACTOR agree that the exact amount of such damages will be difficult, if not impossible, to ascertain. Therefore, the OWNER and CONTRACTOR agree that, if the CONTRACTOR should fail, or refuse to achieve Substantial Completion ofthe Work bythedate of Substantial Completion,subject to extensions of the Contract Time granted bythe OWNER,then the CONTRACTOR agrees to pay the OWNER the sum of Eighteen thousand dollars ($18,000) for each Calendar Day in which such Work is not Substantially Complete, not as penalty, but as a reasonable estimation of the damages ("Liquidated Damages") that would be suffered by OWNER as a result of delay for each and every calendar day that the CONTRACTOR shall have failed to achieve Substantial Completion of the Work as required herein. The Liquidated Damages shall be in lieu of any and all other damages which may be incurred by OWNER as a result of the failure of CONTRACTOR to achieve Substantial Completion of the Work within the Contract Time. § 2.5 Final Completion § 2.5.1 Timely Final Completion is an essential condition of this Agreement. CONTRACTOR agrees to achieve Final Completion of the Work within 60 calendar days of the designated or extended date of Substantial Completion. { § 2.5.2 Final Completion means actual completion of the Work, including any extras or Change Orders reasonably required or contemplated under the Contract i Documents other than warranty work that may be required pursuant to the Contract Documents. 3.0 CONTRACT PRICE § 3.1 The OWNER shall pay the CONTRACTOR the Contract Price in current funds for the CONTRACTOR's proper and complete performance of the Work and all of CONTRACTOR's obligations under the Contract Documents. The Contract Price shall be Two hundred twenty-four million seven hundred eighty-six thousand eight hundred thirty-five dollars and no cents ($224,786,835.00), subject to additions and deductions as provided in the Contract Documents. Page 4 of 10 Issued for Bid(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement BASE PROPOSAL: Item No Quantity Unit Item Description Unit Price Amount Bonds, Mobilization, 1. 1 LS $12,500,000.00 $12,500,000.00 Demobilization, and Insurance ? 5,000 LF Trench Safety $5.00 $25,000.00 Cost for demolition of the existing Owner and Cedar Park 3 1 LS raw water intake barges and $250,000.00 $250,000.00 appurtenances per the applicable Drawings Construction of all Work as specified and detailed, i 1 LS complete and in place,except $198,475,000.00 $198,475,000.00 for Work included in other Proposal Items 5 2 LS Commissioning and Start-up $275,000.00 $275,000.00 Allowance for SCADA 6 1 LS Programming and $3,974,610.00 $3,974,610.00 Instrumentation TOTAL BASE PROPOSAL AMOUNT $215,499,610.00 Page 5 of 10 Issued for Bid(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement § 3.2 The Contract Price is based upon the following alternates which are described in the Contract Documents and are hereby accepted by the OWNER: ALTERNATE PROPOSAL ITEM: i I Indar Submersible Turbine Pumps and Motors Item No. Quantity Unit Item Description Unit Price Amount Furnish four(4) sets of complete and operable Cedar Park pumps, motors, piping, Indar-1 1 LS spare parts and $2,377,000.00 $2,377,000.00 appurtenances compliant with the requirements of the Contract Documents. Furnish four(4) sets of complete and operable BCRUA Initial pumps, motors, Indar-2 1 LS piping,spare parts and $3,618,000.00 $3,618,000.00 appurtenances compliant with the requirements of the Contract Documents. Furnish one(1) unit of a complete and operable BCRUA Ultimate pump, Indar-3 1 LS motor, piping,spare parts $1,862,000.00 $1,862,000.00 and appurtenances compliant with the requirements of the Contract Documents. TOTAL INDAR SUBMERSIBLE TURBINE PUMPS AND MOTORS ! $7,857,000.00 AMOUNT i 1 Page 6 of 10 Issued for Bid(Revised by AD-05) SCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement ADDITIVE ALTERNATE PROPOSAL ITEMS: Item No Quantity Unit Item Description Unit Price Amount EA Additional spot bolts $68.00 $3 740.00 AA _i 5`i , ' in the Main Shaft Additional spot bolts AA-; 20 EA in the Suction and $78.00 $1,560.00 Temporary Chambers AA-3 225 EA Additional spot bolts $29.00 $6,525.00 in the Tunnels Additional Type ll AA-4 400 LF ground support in the $35.00 $14,000.00 Intake Tunnel Additional Type fl AA 5 150 LF ground support in the $30.00 $4,500.00 Transmission Tunnel Additional AA-6 2 EA Mobilization for $8,000.00 $16,000.00 probe drilling to the Intake Tunnel heading Additional Mobilization for AA-7 1 EA probe drilling to the $8,000.00 $8,000.00 Transmission Tunnel heading Additional probe AA-8 440 J drilling in the Intake $68.00 $29,920.00 Tunnel Additional probe AA 9 220 LF drilling in the $68.00 $14,960.00 Transmission Tunnel Page 7 of 10 Issued for Bid(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement Item No. Quantity Unit Item Description Unit Price Amount Additional tunnel AA-10 1 Time& grouting inclusive of $400,000.00 $400,000.00 Materials the Intake and Transmission Tunnels Lake level flooding AA-11 15 Days above Elevation 690,0 $50,000.00 $750,000.00 feet above mean sea level AA-12 59,600 Pounds 40%Sodium $1.50 $89,400.00 Permanganate AA-13 51,000 Pounds 18.25-21.7S%Copper :1.50 $76,500.00 Sulfate Pentahydrate AA-14 100,800 Pounds 10.0—12.S%Sodium $15,120.00 Hypochlorite TOTAL ADDITIVE ALTERNATE AMOUNT $1,430,225.00 4.0 PAYMENT §4.1 APPLICATIONS FOR PAYMENT Subject to any applicable provisions set forth in other Contract Documents, each Application for Payment shall be based on the most recent schedule of values ("Schedule of Values") submitted by the CONTRACTOR in accordance with the Contract Documents, The Schedule of Values shall allocate the entire Contract Price among the various portions of the Work. The Schedule of Values shall be prepared in such form and supported by such data to substantiate its accuracy as the ENGINEER and OWNER may require. The Schedule of Values, as approved by the ENGINEER or OWNER, shall be used as a basis for reviewing the CONTRACTOR's Applications for Payment. As the Work progresses the Schedule of Values may be revised as the OWNER and ENGINEER, in their sole discretion, may deem appropriate to reflect the sequencing of the Work and the values to be assigned to each portion of the Work included in the Schedule of Values. Page 8 of 10 Issued for Bio(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section 00500—Agreement §4.1.1 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. Subject to the provisions of the General Conditions, the CONTRACTOR shall prepare its Application for Payment for a progress payment as of the last day of each calendar month and submit it, with the required number of copies, to the Engineer for review. The total value of work completed to date shall be based on the actual or estimated quantities of Work completed and, if applicable, on the unit prices contained in the Agreement (or approved schedule of values relating to lump sum bids)and adjusted by approved Change Orders. The value of materials properly stored on the Site shall be based upon the estimated quantities of such materials and the invoice prices. Copies of all invoices shall be available for inspection by the ENGINEER. §4.1.2 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: .1 Take that portion of the Contract Price properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Contract Price allocated to that portion of the Work in the Schedule of Values, less retainage of Five percent (5.00%). Pending final determination of cost to the OWNER of changes in the Work, amounts not in dispute shall be included; j i .2 Add that portion of the Contract Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction(or, if approved in advance by the OWNER, suitably stored off the site at a location agreed upon in writing), less retainage of Five percent (5.00%); .3 Subtract the aggregate of previous payments made by the OWNER;and .4 Subtract amounts, if any,for which the ENGINEER has withheld or nullified an Application for Payment. § 4.1.3 The Contractor shall be responsible for the care and protection of all materials and Work upon which payments have been made until final acceptance of such Work and materials by the Owner. Such payments shall not constitute a waiver of the right of the Owner to require the fulfillment of all terms of the Contract Documents and the delivery of all improvements embraced in Contract Documents complete and satisfactory to the Owner in all respects. §4.1.4 Reduction or limitation of retainage, if any, shall be as follows: Reduction or limitation of retainage shall be at the OWNER's sole discretion. Page 9 of 10 Issued for Bid(Revised by AD-05) BCRUA—Phase 2 Raw Water Delivery System Section OOS00—Agreement §41.1.5 Except with the OWNER's prior approval, the CONTRACTOR shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. § 4.2 FINAL PAYMENT § 4.2.1 Final payment, constituting the entire unpaid balance of the Contract Price,shall be made by the OWNER to the CONTRACTOR when: .1 the CONTRACTOR has fully performed its obligations under the Contract Documents, except for the CONTRACTOR's responsibility to correct Work as provided in the General Conditions, and to satisfy other requirements, if any,which extend beyond Final Payment; and I .2 a letterof Final Acceptance has been issued bythe ENGINEER and accepted i by the OWNER. .3 CONTRACTOR has satisfied all of the conditions to receipt of Final Payment as set forth in the General Conditions. §4.2.2 The OWNER's final payment to the CONTRACTOR shall be made no later than 30 days after the Work has been completed and accepted by the OWNER, in writing, following the issuance of the ENGINEER's final Certificate for Payment: i This Agreement is entered into as of the day and year written above ("The Date of Execution" or"Effective Date of the Agreement"): OWNER CONTRACTOR BRUSHY CREEK REGIONAL UTIL.TY AUTHORITY THAL.LE/SAK J INT VENTURE By: By: —_ - .. rrephen E. Kohler Name: StEK N� �e1 ,r� Name: _ Title: iDCFL0c ;rd IR-C, Title: President and COO Page 10 of 10 Issued for Bid(Revised by AD-05)