Loading...
CM-2025-232 - 9/26/2025 STATE OF TEXAS § COUNTY OF WILLIAMSON § SUPPLEMENTAL CONTRACT NO.3 TO CONTRACT FOR ENGINEERING SERVICES FIRM: FREESE AND NICHOLS,INC. ("Engineer") ADDRESS: 10431 Morado Circle,Suite 300,Austin,TX 78759 PROJECT: Addition of a 2' Electric Utility Feed to the Reuse Facility This Supplemental Contract No. 3 to Contract for Engineering Services is made by and between the City of Round Rock, Texas, hereinafter called the "City" and Freese and Nichols, Inc., hereinafter called the"Engineer." WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter called the"Contract,"on the 27th day of April, 2023 for the Addition of a 2nd Electric Utility Feed to the Reuse Facility Project in the amount of$307,001.00; and WHEREAS,the City and Engineer executed Supplemental Contract No. 1 on March 29, 2024 to amend the scope of services and to increase the compensation by $23,662.00 to a total of $330,663.00; and WHEREAS, the City and Engineer executed Supplemental Contract No. 2 on June 7, 2024 to amend the scope of services and to increase the compensation by $45,229.00 to a total of $375,892.00; and WHEREAS,it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $28,539.00 to a total of$404,431.00; NOW THEREFORE,premises considered,the City and the Engineer agree that said Contract is amended as follows: Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum to Exhibit B. I1. Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by $28,539.00 the maximum amount payable under the Contract for a total of$404,431.00, as shown by the attached Addendum to Exhibit D. Supplemental Contract Rev.06/16 0199.202303,4897-2864-3908 84275 ��I - 2025 -231 1 IN WITNESS WHEREOF,the City and the Engineer have executed this Supplemental Contract in duplicate. FREESE AND NICHOLS,INC. By: b -A--1' 512t / lo'LS Date Supplemental Contract Rev.06/16 0199.202303;4897-2864-3908 84275 2 CITY OF ROU D R C APPROVED AS TO FORM: By: Stephanie L. Sandre, City Attorney Printed Name: BIZXJkSt 8-enn2i - Title: ety Marayr Date Signed: 9121012025 Supplemental Contract Rev.06/16 0199.202303;4897-2864-3908 84275 3 Reuse Pump Station Second Utility Feed and Innovative approaches Pump Addition — PSSA #3 FREESE a� CHOPS Practical Outstandingresults ' service 10431 Morado Circle,Suite 300 • Austin,Texas 78759 • 512-617-3100 • fax 512-617-3101 www.freese.com ADDENDUM TO EXHIBIT "B" ENGINEERING SERVICES Project Understanding The City of Round Rock(City) desires to incorporate PLC and HMI programming services for Transfer Pump No. 3 by Plummer Associates, Inc. into the Reuse Pump Station 2nd Utility Feed and Pump Addition Project. Based on discussions with the City,this amendment will include the following major work elements: 1. Updating the transfer pump operation control narrative to include Transfer Pump No. 3. 2. PLC programming changes to the existing Reuse PLC to include new transfer pump control logic. 3. Submittals reviews associated with Transfer Pump No. 3. 4. On-site testing and checkout of the programming changes. ARTICLE I Basic Services: Project Management Services: 1. Coordination with subconsultants. Construction Phase Provide the following construction phase services associated with the additional design scope noted above. 1. Draft revised control narrative for the transfer pump operation will be finalized and submitted to the owner(by Subconsultant). 2. PLC programming changes will be made to the existing Reuse PLC to include the new transfer pump control logic. Updates to the HMI configuration screens will be made to remove the clouded (future) areas and make configuration links to the new PLC program logic (by Subconsultant). 3. PLC programming change will be enabled and tested on-site. Once the contractor has installed and wired up the pump motor,tested rotation, and pump vendor has run the commissioning checks, PLC wiring will be validated and the program logic will be tested. The PLC and HMI functions will be enabled and tested in both Local/Remote and Automatic/Manual (by Subconsultant). 4. Site visit to support Transfer Pump Programming and review operation (by Subconsultant). 5. Submittal review for control narrative, PLC, and Transfer Pump (by Subconsultant). 6. Verify proper electrical connections with contractor (by Subconsultant). 7. Verify Transfer Pump installation and pump curves with manufacturer(by Subconsultant) 8. Miscellaneous support for transfer pump programming changes by Freese and Nichols (FNI). .x: FREESE Reuse Pump Station Second Utility Feed and Pump Add z s Amendment Number 3 April 10, 2025 Page 2 of 2 ARTICLE II Revisions to Additional Services: Any services performed by FNI that are not included in the Basic Services described above are Additional Services. Additional Services to be performed by FNI associated with this PSSA, if authorized by City, are described as follows: 1. More than 1 round of comment review for the Final Control Narrative will be an additional service. 2. Additional site visits by Subconsultant beyond 2 will be an additional service. 3. Additional site visits by FNI beyond 1 to support programming or testing will be an additional service. 4. Revisions to the construction drawings or specifications will be an additional service. 5. Additional programming services beyond those described above will be an additional service. ARTICLE III TIME OF COMPLETION: FNI is authorized to commence work on the Project upon execution of this Agreement and agrees to complete the services in accordance with the following extension of the project schedule and Exhibit C. • Construction Phase Services No additional time is anticipated. If FNI's services are delayed through no fault of FNI, FNI shall be entitled to adjust contract schedule consistent with the number of days of delay. These delays may include but are not limited to delays in City or regulatory reviews, delays on the flow of information to be provided to FNI, governmental approvals, etc. These delays may result in an adjustment to compensation as outlined on the face of this Agreement and in Attachment CO. ADDENDUM TO EXHIBIT D FEE SCHEDULE Attached Behind This Page Project Fee Summary Reuse PS Second Utility Feed&Pump Addition-PSSA•3 Basic Services $ 28,539 EXHIBIT D - FEE SCHEDULE 4/10/2025 Special Services $ Detailed Cost Breakdown Total Project $ 28,539 Tasks I Labor Start Date End Dane Effort curve BST Task(for (Lookup from(Lookupfrom (Lookup from Basic or Michael tan.nr cn.a Barn. Adam cow Task Task Description -- -- -- --------- Total Hours Total Labor Project Setup) BST10 Tasks B5T10 Tasks BST10 Tasks Special Effort tab) tab) tab) - - - $219 $193 $170 CONSTRUCTION PHASE S - Basic Subconsultant Coordination 4 4 $_ Project Management _ S _ - __ ' 876 I I Construction Phase Support S - 'Basic Transfer Pump Programming and Testing $ - Transfer Pump Submittal Review $ - • Transfer Pump No.3 Troubleshooting $ - Miscellaneous Support for Transfer Pump Programming 4 6 6 16 $ 3.054 and Startup Total Hours/Quantity 8 6 6 20 Total Effort $ 1,752 $ 1,158 I$ 1,020 $ 3,930 1 of 3 L\CfenttOLCR\R\Round Rock.City ot)Reuse Pump Station Second Utility Feed\PSSA 3\3-Amendments for RevaofCORR 2nd Utility Feed PSSA 3 Fee Spreadsheet_2025-03-27.1dsm 4/10/2025 8.5 Reuse PS Second Utility Feed 8 Pump Addition-PSSA#3 Basic Services 4/10/2025 Special Services Detailed Cost Breakdown Total Project Tasks Expenses Start Data Env oats Effort Curve 1 I BST Task(for (Lookupfrem(Lookup from (Lookup from Basic or Task Task Description Tech Charge Miles Total Expense Project Setup) i BST1O Tasks BSTlO Tasks BSTIO Tasks Special Effort tab) tab) tab) (CONSTRUCTION PHASE - $ - Project Management - $ _ - _ 1 Basic Subconsultant Coordination 4 $ - _ l __ Construction Phase Support . 5 - Basic Transfer Pump Programming and Testing - 5 - Transfer Pump Submittal Review - $ Transfer Pump No 3 Troubleshooting - I $ - Miscellaneous Support for Transfer Pump Programming and Startup 16 100 $ 70 Total Hours/Quantity 20 100 Total Effort S - $ 70 $ 70 2 of 3 L.\Client\OLCR\R\Round Rock,Crty oftReuse Pump Station Second Utility Feed\PSSA 3\3-Amendments for RevlewACORR 2nd Utility Feed PSSA 3 Fee Spreadsheet_2025-03-27.xlsm 4/10/2025 Project Fee Summary Reuse PS Second Utility Feed 8 Pump Addition-PSSA#3 Basic Services 28 539 4/10/2025 Special Services - Detailed Cost Breakdown Total Project 28.539 Tasks Subconsultants Total Start Data End Data Effort Curve BST Task(for (Lookup from(Lookup horn (Lookup from Basic or Task Task Description Hinton, BCE Total Sub Total Effort Project Setup) B8T10 Tasks BST70 Tasks BST70 Tasks Specurl Effort tab) tab) tab) CONSTRUCTION PHASE S - S - _ _ Project Management $ - $ - ' Basic Subconsultanl Coordination $ - $ 876 — Construction Phase Support --- $ - $ Basic Transfer Pump Programming and Testing 9 120 $ 9,578 $ 9,576 _. Transfer Pump Submittal Review 5 000 $ 5,250 $ 5 250 Transfer Pump No.3 Troubleshooting 9.250 5 9,713 $ 9 713 Miscellaneous Support for Transfer Pump Programming and Startup S - 5 3.124 Total Hours/Quantity $ 9,120 $ 14,250 $ - $Total BMW$ 9,67e $ 14,983 $ - $ - $ 24,539 $ 28,539 3 of 3 L:\Cfiert\OLCR\R\Round Rock,Crty ohReuse Pump Station Second Utility Feed\PSSA 3\3-Amendments for Review\CORR 2nd Utility Feed PSSA 3 Fee Spreadsheet_2025-03-27.idsrn 4/10/2025