Contract - Austin Underground, Inc. - 1/9/2025 Page I of 3
Contract Quantity Adjustment/Change Order
Department: UES
Project
Name: Lake Creek Wastewater Line Replacement Date: 11/27/24
City Project Change Order/Quantity
ID Number LCiPI Adjustment No. 5
Vendor Austin Underground, Inc P.O. Box 5650-Lago Vista,Texas 78645 (512)535-3285
Company Name Address Phone No.
Justification
Change Order/Quantity Adjustment No 5 is for the additional reimbursement for rail tine inspection and rail line survey during installation of the wastewater under the
railroad track This change order also includes the addition of 180-feet of split-steel encasement pipe to protect the wastewater line from the proposed Lake Creek Trail.
SUMMARY Amount %Change
Original Contract Price: =$40,541.25
Previous Quantity Adjustment(s):
This Quantity Adjustment Total Quantity Adjustment(s):Total Contract Price with Quantity Ad;ustment,s)
Previous Charge Order(s). $66,148.63 2%
This Change Order: $403,31459 11%
Total Change Order(s)To Date: $469,463.22 13%
Adjusted Contract Price (Original Contract Price Plus Quanhty Adjustment(s)Pius Change
Order(s)] $4,193.9S6.9
Ddlerence betweer Ong nal and Adjusted Contract Prices $602,786.97
Original Contract Time: 240
Time Adjustment by prey ous Quan.Adj./Change Order. 360
Time Adjustment by this Quan Adj/Change Order: 160
New Contract Time: 760
Prepared By. Christopher Perkins Principal Engineer,Round Rock 'z p
Signature Printed Name, Title,Company Date
Valentin 1 Gomez, o-r••n ro».++.K
Contractor: 1r o•xi. :,,i.%o.w Valentin J Gomez,Jr-Sr PM-Austin Underground Inc
Signature Printed Name,Title,Company Date
City Project '
Marager. (� �� Christopher Perkins,Principal Engineer,Round Rock Z/ (O I z-gra: Printed Name,Title Date
Mayor/City
Manager (2-ML-4 Wfeaj Maq 0 2 U5
s,g to Printed Na e,Title J JDat
a 0 as- 003
Page 2 of 3
Contract Quantity Adjustment/Change Order
Project Name. lake Creek Wastewater line Replacement
Quar Ad1/Change Order No.: 5
Change Order Data
Contract
Time
Adjustment
Item X Item Description Unit Unk Price Amount
Addition of I80ft of split-steel encasement,including restaints and casing
CO 5-1 Ispacers LS 1 $403,314.59 $403,314.59 160
Contract Quantity Adjustment/Change Order
o..ao•e.,.
Project Name: Lake Creek Wastewater Line Replacement
Quart.Adj./Change Order No.: 5
Quantity Adjustment Data
Contract
Time
Bid Item i Item Description Unit Qty. Unit Price Amount Adjustment
Cost for RatlYros for Rad Line Inspection during Installation of the Steel
Encasement Pipe under Rail Road ROW Reimbursement to pay RatlPros
28 Invoice Plus I54. LS 1 $22,473.73 $22,473.73
Cost for UPRR Certified Rad Survey to provide surveying of Centerline
of Track during installation of the Steel Encasement Pipe under Rail
29 Road ROW.Reimbursement to be paid Invoice plus 15% LS 1 $18,067.52 $18,067.52