CM-2026-062 - 3/6/2026 Page I of 3 Contract Quantity Adjustment/Change Order rev,01/16 Department: General Services Project Name: 901 Emmanuel Street Building Demolition Date: 2/12/26 City Project Change Order/Quantity ID Number CM-2026-032 Adjustment No. 1 Vendor Rise Up Construction, LLC PO Box 350 Chandler,TX 75258 254-644-4008 Company Name Address Phone No. Justification During the abatement of hazardous materials,a buried propane tank was discovered on the property. It has been confirmed that the tank is empty.The tank must be removed to allow for future property development.The cost to excavate and dispose of the tank is$3,000. SUMMARY Amount %Change Original Contract Price: $51,040.00 Previous Quantity Adjustment(s): This Quantity Adjustment: $0.00 Total Quantity Adjustment(s): $0.00 Total Contract Price with Quantity Adjustment(s): $51,040.00 Previous Change Order(s): 0% This Change Order: $3,000.00 6% Total Change Order(s)To Date: $3,000.00 60/0 Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s)Plus Change Order(s)]: $54,040.00 Difference between Original and Adjusted Contract Prices: $3,000.00 Original Contract Time: Time Adjustment by previous Quan.Adj./Change Order: Time Adjustment by this Quan.Adj./Change Order: New Contract Time: 0 Contractor: CaMey(Feb18,2026 06 36 47C5T) Rance Cathey Owner Rise Up Construction LLC 02/18/2026 Signature Printed Name,Title,Company Date City Robert G Lomas 02/18/2026 Representative: Robert Lomas(Feb 16,2026 09 24:23 CST) Signature Printed Name,Title Date Mayor/City 6rtx , CA ' • nil r• 03/06/2026 Manager Brooks Bennett(Mar 6,2026 14 46'06 CST) Signature Printed Name,Title Date Page 2 of 3 Project Name: 901 Emmanuel Street Building Demolition Quan. Adj./Change Order No.: 1 Change Order Data Contract Time Item # Item Description Unit Qty. Unit Price Amount Ad(ustm;nt Excavate and dispose of one 1 underground propane tank. 1 $3,000.00 $3,000.00 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -- $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $3,000.00 0 Page 3 of 3 Project Name: 901 Emmanuel Street Building Demolition Quan. Adj./Change Order No.: 1 Quantity Adjustment Data Contract Time Bid Item # Item Description Unit Adjustment p Qty. Unit Price Amount rna..cl $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $0.00 0