CM-2026-106 - 4/17/2026 STATE OF TEXAS §
COUNTY OF WILLIAMSON §
SUPPLEMENTAL CONTRACT NO. 9
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: BROWN & GAY ENGINEERS,INC. ("Engineer")
ADDRESS: 101 West Louis Henna Boulevard,Suite 400,Austin,TX 78728
PROJECT: Gattis School Road Segment 6
This Supplemental Contract No. 9 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and Brown & Gay Engineers, Inc.,
hereinafter called the"Engineer."
WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter
called the "Contract," on the 1 lth day of February, 2016 for the Gattis School Road Segment 6
Project in the amount of$482,439.90; and
WHEREAS,the City and Engineer executed Supplemental Contract No. 1 to the Contract on May
10, 2018 by Resolution No. R-2018-5420 modifying the scope of services and increasing the
compensation by $401.872.25 for a total of$884,312.15; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 2 to the Contract on
October 1, 2018 to modify the provisions for the scope of services and to increase the
compensation by $8,540.00 for a total of$892,852.15; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 3 to the Contract on
September 12, 2019 to modify the provisions for the scope of services and to increase the
compensation by $177,053.00 to a total of$1,069,905.15; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 4 to the Contract on
January 23, 2020 to modify the provisions for the scope of services and to increase the
compensation by $119,914.00 to a total of$1,189,819.15; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 5 to the Contract on
December 2, 2020 to modify the provisions for the scope of services and to increase the
compensation by $216,816.50 to a total of$1,406,635.65; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 6 to the Contract on
March 26,2021 to modify the provisions for the scope of services and to increase the compensation
by $25,190.00 to a total of$1,431,825.65; and
Supplemental Contract Rev.06/16
O1_ 0n (,4(20
_ / 84275
V" '�2 aL.l/�1 1�Q�j�
1
WHEREAS, the City and Engineer executed Supplemental Contract No. 7 to the Contract on
March 10,2022 to modify the provisions for the scope of services and to increase the compensation
by $88,390.00 to a total of$1,520,215.65; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 8 to the Contract on
November 16, 2023 to modify the provisions for the scope of services and to increase the
compensation by $125,704.00 to a total of$1,645,919.65; and
WHEREAS,it has become necessary to amend the Contract to modify the provisions for the scope
of services and to increase the compensation by $69,710.00 to a total of$1,715,629.65;
NOW THEREFORE,premises considered,the City and the Engineer agree that said Contract is
amended as follows:
I.
Article 2,Engineering Services and Exhibit B,Engineering Services shall be amended as set forth
in the attached Addendum to Exhibit B. Exhibit C, Work Schedule shall be amended as set forth
in the attached Addendum to Exhibit C.
II.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$69,710.00 the lump sum amount payable under the Contract for a total of$1,715,629.65,as shown
by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF,the City and the Engineer have executed this Supplemental Contract
in duplicate.
[signature pages follow]
Supplemental Contract Rev.06/16
0199.1602 84275
2
BROWN & GAY ENGINEERS,INC.
By: /erv{ .d,
Printed Name: Erin Gonzales
Title: Vice President
Date Signed: 4/13/2026
Supplemental Contract Rev.06/16
0199.1602 84275
3
CITY OF ROUND ROCK APPROVED AS TO FORM:
By:
Stephanie L. Sandre, City Attorney
Printed Name: 6Ib0S / VV.,f(
Title: n7/1/Date Signed:
Supplemental Contract Rev.06/16
0199.1602 84275
4
Gattis School Road City of Round Rock
From Red Bud Lane to Via Sonoma Trail Exhibit B-9
Services to be Provided by the Engineer
ADDENDUM TO EXHIBIT B
ENGINEERING SERVICES
The work to be performed by the ENGINEER under this contract consists of providing
engineering services required for the development of construction plans for the widening and
reconstruction of Gattis School Road from Red Bud Lane to Via Sonoma Trail and along Red
Bud Lane approximately 500' south of Gattis School Road. The project consists of
reconstructing approximately 0.65 miles of the existing 4-lane roadway section to a 6-lane
divided facility and adding a right turn lane on Red Bud Lane. This project involves surveying,
engineering analyses, and associated details necessary to produce PS&E to a 100%design,
including bidding& award services, and construction phase support.
The ENGINEER shall perform all work and prepare all deliverables in accordance with the latest
version of the City of Round Rock criteria.
The ENGINEER shall perform quality control and quality assurance(QA/QC)on all deliverables
associated with this project.
The ENGINEER shall provide traffic control in accordance with the Texas Manual on Uniform
Traffic Control Devices (TMUTCD)when performing onsite activities associated with this
contract.
CONSTRUCTION PHASE SUPPORT SERVICES(Function Code 309)
A. Engineer shall provide construction support services, including assistance with
responding to contractor questions,attend pre-construction meeting,and prepare
minutes. Agenda will be prepared by the City.
B. Assist City with Shop Drawing and material review and approval (assume 2 shop
drawing submittals and 12 additional material submittals)
C. Assist City with preparation of Change Orders,Alternate Design or Additional
Design Details
D. Respond to Questions related to the Plans -The Engineer shall be available to
respond to questions related to the plans and specifications as needed throughout the
duration of the construction. The Engineer will document each question in sufficient
detail, formulate a response and submit a written version of the response to the City
for distribution to all involved parties. Estimate assumes no more than forty(40)
additional Requests for Information.
E. The Engineer representative to attend weekly meetings as needed at the request of the
City, estimated at 75%of 20 month estimated construction duration.
F. At the completion of pond construction,the City will provide survey information for
the pond locations or modifications. With the City survey information,the Engineer
Sheet I of 2
Gattis School Road City of Round Rock
From Red Bud Lane to Via Sonoma Trail Exhibit B-9
Services to be Provided by the Engineer
will provide certification that the ponds were constructed per plan.
G. Assist City with Pay Application review and approval (assume 16 pay applications)
H. Utility Coordination in accordance with attached Halff Scope of Services(Exhibit A)
I. The Engineer shall not at any time supervise, direct, control, or have authority over
any contractor's work,nor shall Engineer have authority over or be responsible for
the means, methods,techniques, sequences, or procedures of construction selected or
used by any contractor, or the safety precautions and programs incident thereto, for
security or safety at the construction site,nor for any failure of a contractor to comply
with Laws and Regulations applicable to such contractor's furnishing and performing
of his work. The Engineer will not bear any responsibility or liability for defects or
deficiencies of the contractor.
Sheet 2 of 2
.•: half UTILITY COORDINATION/ENGINEERING
SCOPE OF SERVICES(EXHIBIT A)
Client:BGE City/County Name:Round Rock/W illiamson County
Project: Gattis School Rd Seg.6
Project Limits
• Within the existing ROW Gattis School Rd from Via Sonoma to Red Bud Lane
Level of Effort
Review and Respond RFI's
• Continued coordination for up to 12 months with previously identified utility owners:
• Altice/Suddenlink
• AT&T
• Spectrum
• Google Fiber
• Astound
• MCI Verizon
• Zayo
• Manville Water
• Southwest Water
• City of Round Rock Water/Wastewater
• Atmos
• Review and respond to RFIs submitted to Halff directly from prime consultant BGE related to utility
coordination,existing utility conflicts. Any technical RFI's to be routed to engineer of record or utility
representative when necessary.
• Coordinate timely conflict resolution with utilities already identified within the project limits
Meetings&Site Meeting with Utility Representatives
• Attend CORR re-occurring monthly meeting and provide updates on utility coordination activities
• Provide a representative at weekly site meeting for duration of 12 months to ensure utility issues are
communicated and followed up.
UC/UE Deliverables
• Meeting Minutes in Excel and Pdf format
• RFI Response Log
• Monthly Progress Reports Summarizing Utility Activities
Assumptions
• 12 months contract duration for utility coordination services
Exclusions
• Coordination with New Utilities or Privately Owned Utilities
• Utility Agreement Assemblies
• Utility Relocation Design
1
ffGEM 1 laL Subsurface Utility Engineering/ Utility Coordination
• Buy America Build America(BABA)Compliance Verification or Inspection
• Permitting
• Utility Relocation Inspection and Verification
Location:
.r„
Det.•Seneei "' GeM.e-Heee,'_I.t"'/ r
e!• r
2
ADDENDUM TO EXHIBIT C
WORK SCHEDULE
DATE MILESTONE
April 2026—October 2027 Construction Phase Services
ADDENDUM TO EXHIBIT D
FEE SCHEDULE
Attached Behind This Page
PROJECT NAME: GATTIS SCHOOL RD EXHIBIT D-9-FEE SCHEDULE
FROM RED BUD LN TO VIA SONOMA TRL
FC DESCRIPTION BGE Half Inland TOTAL
FC 110 ROUTE AND DESIGN STUDIES $0.00 $0.00
FC 120 ENVIRONMENTAL $0.00 $0.00
FC 130 ROW $0.00 $0.00
FC 145 GENERAL MANAGEMENT/COORDINATION $0.00 $0.00
FC 150 FIELD SURVEYING AND PHOTOGRAMMETRY $0.00 $0.00
FC 160 ROADWAY DESIGN CONTROLS $0.00 $0.00
FC 161 DRAINAGE $0.00 $0.00
FC 162 SIGNING, PAVEMENT MARKINGS,AND SIGNALIZATION $0.00
FC 163 MISCELLANEOUS ROADWAY $0.00 $0.00
FC 170 BID PHASE SERVICES $0.00 $0.00
FC 309 CONSTRUCTION PHASE SUPPORT SERVICES $44,391.00 $ 24,850.00 $69,241.00
EXPENSES $0.00 $ 469.00 $469.00
TOTAL $44,391.00 $25,319.00 $0.00 $69,710.00
BROWN GAY ENGINEERS,INC. EXHIBIT D-1-FEE SCHEDULE
PROJECT NAME: GATTIS SCHOOL RD
FROM RED BUD LN TO VIA SONOMA TRL
TASK DESCRIPTION Senior Project Project EIT Senior Senior Senior ENV Admin/ Total TOTAL LABOR
Project Mgr Manager Engineer Engineer Tech CADD Op ENV Scientist Clerical HRS.&COSTS
FC 110 ROUTE AND DESIGN STUDIES 0 $0.00
$0.00
FC 120 ENVIRONMENTAL COMPLIANCE AND PUBLIC INVOLVEMENT 0 $0.00
O $0.00
FC 130 RIGHT OF WAY DATA 0 $0.00
O $0.00
FC 145 PROJECT MANAGEMENT $0.00
O $0.00
FC 160 ROADWAY DESIGN CONTROLS $0.00
FC 161 DRAINAGE _ $0.00
0 $0.00
FC 162 SIGNING,PAVEMENT MARKINGS,AND SIGNALIZATION $0.00
FC 163 MISCELLANEOUS(ROADWAY) $0.00
0 $0.00
FC 170 BID PHASE SERVICES $0.00
FC 309 CONSTRUCTION PHASE SUPPORT SERVICES $44,391.00
Weekly Meetings(75%of 20 months) 90 90 $17,550.00
Shop Drawings Review(2 ea) 2 4 4 10 $1,530.00
Submittals Review(12 ea) 6 12 18 $2,460.00
Change Orders review and processing(5 ea 5 10 15 $1,665.00
Respond to RFIs(40 ea) 20 40 30 30 120 $18,250.00
Pay Application Review(16 ea) 8 24 32 $2,936.00
HOURS SUB-TOTALS 0 117 58 46 ' 30 0 r 0 0 34 285 285
CONTRACT RATE PER HOUR $225.00 $195.00 $160.00 $125.00 $140.00 $90.00 $220.00 $135.00 $69.00
TOTAL LABOR COSTS $0.00 $22,815.00 $9,280.00 $5,750.00 $4,200.00 $0.00 $0.00 $0.00 $2,346.00 $44,391.00
SUBTOTAL $44,391.00
TOTAL TOTAL Senior Project Project Senior Senior Senior ENV Admin/
FUNCTION CODE TOTAL COSTS DIRECT LABOR Project Manager Engineer EIT Engineer CADD ENV Scientist Clerical TOTAL MH BY FC
EXPENSE _ COSTS Manager Tech Operator
$44,391.00 $0.00 $44,391.00 0 117 58 46 30 0 0 0 34 285 285
0
SUBTOTAL LABOR HOURS 0 117 58 46 30 0 0 0 34 285 285
SUBTOTAL LABOR EXPENSES $44,391.00 $0.00 $44,391.00 0.0% 41.1% 20.4% 16.1% 10.5% 0.0% 0.0% 0.0% 11.9%
OTHER DIRECT EXPENSES QUANTITY UNIT RATE
Mileage 0 mile $ 0.56 $0.00
Photocopies B/W(11"X 17") 0 each $ 0.20 $0.00
Photocopies Color(8 1/2"X 11") 0 each $ 0.75 $0.00
Photocopies Color(11"X 17") 0 each $ 1.25 $0.00
Geosearch(hazmat) 0 each $ 500.00 $0.00
Large Format Plotting 0 SF $ 2.25 $0.00
SUBTOTAL DIRECT EXPENSES $0.00
SUMMARY
TOTAL LABOR COSTS $44,391.00
NON-SALARY(OTHER DIRECT EXPENSES) $0.00
GRAND TOTAL I $44,391.00
Highway:Gattis School Seg.6A EXHIBIT D-FEE SCHEDULE
Specified Rate
Is,.S 055.m 5 I15.m$ us.m S sss.m$ 1rt.m S tm.m 5 tsa m 5 13000 5 110.m 5 13000$ 11000$ US®$ m.0D$ 350.00$ WOO
a sz a 2 g g § 1 1 -
1.3
a yTotal Sod
Mika Ceo1Y,.11.0
A Obloy Coortbnalton l0000,uuwn maw Walcott 2. 100 6 10 5 30,05000
g
$
f
• f
$
$
SW*Oat Noon: a 30 0 a im 0 0 0 0 e a e L Im
of Subtotal
l LameCOM $ - f a1ID.m $ - $ - $ • .f 1),Om.m $ n0.m $ - f - 5 - $ - $ - $ - $ - $ - '.$ aaeA f 1115000
uqunubtwn Hour.: a n � 1m a o 0 0 j o a o e 10101
CTu5 Subtotal 5.50,Cost: $ - $ a,ll0.m 5 $ $ • IS 11.m0.00 $ 730.00 $ - I f - s - I f - 1f -1$ - s -AS - IS 550.00 S 20.510 o0
•
Halff Associates,Inc. Exhibit B
Highway:Gattis School Seg.6A EXHIBIT D-FEE SCHEDULE
Specified Rate
OTHER Expenses to he Required UNIT FIXED/MAR UNIT COST T EXPENSES
QUANTITY COST
Masse mile feted Current late $ 0.6I >00 $
Rate
Subtotal Other Dire.Expenses. $ 469.00
Halff Associates,Inc. Exhibit B
A i'�,l + r �'AR
~ ..,.. +• 4, to �i a4 4 ..'r fi; . . .. ,• y ..
It „
N ;. 'Ee '�'. .— y��►, is �{� e�E4)R `` 'r 1 r '" i . }o: �_—
n. - j" l 40- „' + •�. .� �%• _( LAKE PL . Il_+J.. Lr. { i IV `�_'
P..i` rt
a Ate. 3 ::i, ,;.♦ ., '+•� ,_` d 1 -ice--i �Y -Jir 4,w� so, _
r
k • ,.,..., ' S �• q;A ,. 1. 1 J , 'j� d y •v t t :TJ
���' +'
•
ot
° �4 :.1 MP''s. T ,' mayit
' '..
y i' t{ .. +� �, ram' `
sg
.
A, -.,.....ei Ka/P 4 4-4,-‘'. " ' ,._- , .-i4i/U., 1/?•••• .. 1 V 1,r-rill-. : .--'4'
irr; +
. . •, a � .it�rp.4s',•.•anr ti':R:W.,�4�. .."A 4 � �'tl►. o�RD --'� '� �d
lir .•...,i•• - CNO
,
.1 4 \ 4 „. P f
r a/M •
V I , 'ir d a
i
•
- •
+�,Ff 4i. i Y-tt 4 wa L •- i :;; Ig*. i. -A� Vr
rrYY:. -!, + ;, „rM r4 4 '''�P,Op " L "JS`LK TREE l
1 + l AM 1, < • t=. J { -, a a a - ** • '. ''.. , -- a. `' 1 1PN. •C� ►� , 1 1 t
,y1 a t + W R l...t 4„,....• , pas°11
i_' • n f -,ern y _. c ` * .$ A1i
rf t s F ;in 1
-,rl
,, o- i — .� ' � * W Legend S
A ',' ' A,: i �'k , ' . -mac, - , , 'a_ ._ Gattis School Road Segment 6
� ,/� 7 +;S+F 4*••�'a +f/, . :.L�' 0�,c• •r •r • -, 'm.0 \ ` i
kt, .Ne.ir:r�' �.r �'� F rt'.. Via, ..� -.sr .44'�a , N .1:�. ./ a
Gattis School Road Segment 6 N
Round Rock Public Works Department
ROUND ROCK TEXAS
September 2024 500 , 1,000 Feet