Loading...
CM-2026-121 - 4/24/2026 Page 1 of 3 Contract Quantity Adjustment/Change Order ROUND ROCK TEXAS rev.06/25 Department: Public Works Date: 4/9/26 Project Name: West Transmission Main Valve Replacment Project City Project ID Change Order/Quantity Number: 2601 Adjustment No. 1 Vendor: Patin Construction LLC 3800 W. 2nd Street,Taylor,Tx 76574 512-269-1071 Company Name Address Phone No. Justification Demobilizaton and Remobilization for a work delay until November 2026.The pricing includes the following: Utility crew and equipment at all three sites,valves and other pipe materials to be hauled to secure storage from all three sites. SUMMARY Amount %Change Original Contract Price: $1,463,470.00 Previous Quantity Adjustment(s): $0.00 This Quantity Adjustment: $0.00 Total Quantity Adjustment(s): $0.00 0% Total Contract Price with Quantity Adjustment(s): $1,463,470.00 Previous Change Order(s): $0.00 This Change Order: $48,600.00 Total Change Order(s)To Date: $48,600.00 3% Adjusted Contract Price: [Original Contract Price Plus Quantity Adjustment(s)Plus Change Order(s)] $1,512,070.00 Difference between Original and Adjusted Contract Prices: $48,600.00 3% Original Contract Time: 160 Time Adjustment by previous Quan.Adj./Change Order: 0 Time Adjustment by this Quan.Adj./Change Order: 20 New Contract Time: 180 Submitted for Approval Z - Mark Hurd 3 2447: b RnuaR�ammcw.upo..dory Prepared By: Mark Hurd,Project Manager,CORK ""moms "'"""" 4/9/26 Printed Name,Title,Company Signature Date Contractor: Todd Keltgen, Project Manger, Patin Construction LLC. 4-cf-g E Printed Name,Title,Company / Sign (. Date City Project _ Manager: Mark Hurd, Project Manager,CORR Mark Hurd' ,;':21 m---^ '" 4/9/26 �K1 Printed Name,TTitle M n n�'n Signature Date Mayor/City el Manager: trook_S 'Julnekt C,i-y Mom+ ct , '� I2M/2J, Printed Name,Title �J Signature Date CM-1O2 o — 12- I Page 2 of 3 Contract Quantity Adjustment/Change Order ROUND ROCK TCXA5 rev.06/25 Project Name: West Transmission Main Valve Replacment Project Change Order/Quantity Adjustment No. 1 Change Order Data Contract Time - Bid Item # - Item Description - Unit Qty. Unit Price Amount Adjustment(Days) } V5##�-�," .'r-' ra ds HRv�. 7 Ss6r �Ma", +? 3n. WL tbl Demobiliation LS- 1 $24,300.00 $24,300.00 10 2 Remobilization-w/clearance from city LS 1 $24,300.00 $24,300.00 10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 '$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 NMEVAMPitg `T ip:ai,: gar{ . TOTALS: $48,600.00 20 Page 3 of 3 Contract Quantity Adjustment/Change Order ROUND ROCK TEXAS rev.05/25 Project Name: West Transmission Main Valve Replacment Project Change Order/Quantity Adjustment No. 1 Quantity Adjustment Data q} �y 6ybyg� p C39 '`.`v:'h- "k ':=J.'' tt'? ,.ram-'(�; • ��°µ.' r_fii s s F:' Contract Time Bid Item # - Item Description Unit Qty. Unit Price Q�yy Amount Adjustment(Days) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 - -. $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $0.00 0