R-2026-142 - 5/28/2026 RESOLUTION NO. R-2026-142
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract') with
Royal Vista, Inc. for the Cycle 4 Basins 1 & 2—Wastewater Main Rehabilitation Project, and
WHEREAS,the Council has determined that it is necessary to make adjustments/changes to the
quantity of work to be performed or materials,equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 1 to the Contract with Royal Vista, Inc. for the Cycle 4 Basins 1 & 2 —
Wastewater Main Rehabilitation Project,a copy of said quantity adjustment/change order being attached
hereto as Exhibit "A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date,hour,place and subject
of the meeting at which this Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and the subject matter hereof were
discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551,
Texas Government Code, as amended.
RESOLVED this 28th day of May, 2026.
1,4
CRArqMORfAN,Mayor
City of Roun Rock, Texas
ATTEST:
-6Lawg
ANr4 Pk.,kNkiIN, City Clerk
0112.20262
EXHIBIT
A Page 1 of 3
Contract Quantity Adjustment/Change Order
.4,.o.a.,,x.-
rev.OW25
Department: Public Works Date: 4/23/26
Project Name: Cycle 4-Basins 1&2 Wastewater Main Rehabilitation
City Project ID Change Order/Quantity
Number: C4612 Adjustment No. 1
Vendor: Royal Vista,Inc. 350 CR 260, Liberty Hill,TX 78642 512-515-6824
Company Name Address Phone No.
Justification
Due to the adverse conditions of manhole#1434334,additional repair methods are necessary, including cementitious buildback,grout to stop
infiltration,and Spraywall.It was also necessary to lift an additional 50 linear feet of pvc pipe to re-establish slope and maintain proper
draininage along Mays Street.
SUMMARY Amount %Change
Original Contract Price: $1,646,653.61
Previous Quantity Adjustment(s): $0.00
This Quantity Adjustment: $19,028.50
Total Quantity Adjustment(s): $19,028.50 1%
Total Contract Price with Quantity Adjustment(s): $1,665,682.11
Previous Change Order(s): $0.00
This Change Order: $61,720.00
Total Change Order(s)To Date, $61,720.00 4%
Adjusted Contract Price: (Original Contract Price Plus Quantity Adjustment(s)Plus Change
Order(s)]
$1,727,402.11
Difference between Original and Adjusted Contract Prices: $80,748.50 5%
Original Contract Time: 260
Time Adjustment by previous Quan.Adj./Change Order:
Time Adjustment by this Quan.Adj./Change Order: 7
New Contract Time: 267
Submitted for Approval
Prepared By: Kaitlyn Saucedo, Enqineer Associate&Project Manager �>
Printed Name,Title,Company Signature Date
Approvals
Contractor: Steven R. Green (Vice President) Royal Vista, Inc. __-04124L2026
Printed Name,Title,Company Signature Date
City Project I/
G
Manager: Kaitlyn Saucedo,Engineer Associate I�_' �—
Printed Name,Title Signature Date
Mayor/City
Manager:
Printed Name,Title Signature Date
Page 2 of 3
Contract Quantity Adjustment/Change Order
rev.*25
Project Name: Cycle 4-Basins 1&2 Wastewater Main Rehabilitation
Change Order/Quantity Adjustment No. 1
Change Order Data
contract Time
Bid Item# Ibem Description Unit Qty. Unit Price Amount Adjusb+eit(Dap)
1 Rehab for the existing manhole#1434334 LS 1 $61,720.00 $61,720.00 7
$0.00
- $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS:l $61,720.00 7
Page 3 of 3
Contract Quantity Adjustment/Change Order
rev.OBR5
Project Name: Cycle 4-Basins 1&2 Wastewater Main Rehabilitation
Change Order/Quantity Adjustment No. i
Quantity Adjustment Data
on Unit tontiactTime
Bid Item# Item Descripti
Qty. Unit Price /!mount Adiusenerrt(Days)
Furnish all materials,equipment,tools&
labor necessary to eliminate 10"
wastewater line,Including pre-videoing to
determine defect location,post-videoing to
confirm repair,backfill**per standard
details,ad surface restpration to existing
16 conditions LF 50 $380.57 $19,028.50 0
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
- $0.00
$0.00
$0.00
$0:00
$0.00
$0.00
$0.00
$0.00
^_ $0.00
$0.00
$0.00
$0.00
$0.00
TOTALS: $19,028.50L__ 0
Royal Vista, Inc.
350 C.R.260,Liberty Hill,Texas 78642
Phone (512)515-6824
Date. 3!3012028
Proposal
To: City of Round Rock
Attn.: Kaitlyn Saucedo
From: Stevan DeLeon
Project.CORR-Cycle 4-Basin 3 &4 WW Rehab
Rehab Existing Manhole CID##1434334
Royal Vista Proposes the following:
Description Bid QTY Units Amount Sub Total
rep of Existing Manhole 1 LS $7,746.00 $7,746.00
1^Cementitious Buildback 1 LS 515,564.00 $15,584.00
50 Mil Spraywall of Existing Manhole 1 LS $15,400.00 $15,400.00
Chemical rout to Stop infiliration(Price Based on 10
Gallons of Grout and 10 Manhours to Stop Infiltration) 1 LS $5,040.00 $5,040.00
Bypass Pumping 1 LS $35,000.00 $35,000.00
Additional Overhead and Project Management for Added
Subcontract work not included in original contract 1 LS $3,125.00 $8,125.00
Credit of Manhole From Original Bid 1 LS ($20,175,00)
Additional Grout Needed to Stop Infiltration GAL $295.00 $0.00
Additional Man Hour MR $210.00 $0.00
oyo al v1st �equ�7iWditianai"0a-Tendar— ays be aadd-to
our contract for this proposal.
Total $61,720.00
THANK YOU! 7 - /
Submitted By: �/�L-�� _Accepted By:
Printed NameMtle:Stevan Deleon/Project Manager Printed Name/Title:
Date: 03/30/2026 Date:
steved Page 1 3/30/2026
Royal Vista, Inc.
350 CR 260
Liberty Hill, Texas 78642
(512)515-6824 Fax(512)515-6829
REQUEST FOR INFORMATION
RFI NO.: 2503-004 DATE: 4/912026
PROJECT: CYCLE 4 BASIN 1 &2 RESPONSE REQUESTED BY
DATE: As Soon As Possible
TO: Hayden Mattke
REFERENCE: UID#1960361
ISSUE:
Plan Page WW-14 calls to lift bursted pipe to re-establish proper slope @ 50-117 from MH#1960360. But
the manhole is full from 0-20.Need to grade from 0-117 to achive proper drainage.
Please advise.
Recommended Solution:
Stevan De Leon, Project Manager
RESPONSE: Please proceed with the additional 50' of rehabilitation to establish
proper slope of the 10" main.
i
4/10/2026