Loading...
Contract - Royal Vista, Inc. - 5/28/2026 Page 1 of 3 '"•'��'� Contract Quantity Adjustment/Change Order rev.04/25 Department: Public Works Date: 4/23/26 Project Name: Cycle 4-Basins 1&2 Wastewater Main Rehabilitation City Project ID Change Order/Quantity Number: C4612 Adjustment No. 1 Vendor: Royal Vista, Inc. 350 CR 260, Liberty Hill,TX 78642 512-515-6824 Company Name Address Phone No. Justification Due to the adverse conditions of manhole#1434334,additional repair methods are necessary, including cementitious buildback,grout to stop infiltration,and Spraywall. It was also necessary to lift an additional 50 linear feet of pvc pipe to re-establish slope and maintain proper draininage along Mays Street. SUMMARY Amount %Change Original Contract Price: $1,646,653.61 Previous Quantity Adjustment(s): $0.00 This Quantity Adjustment: $19,028.50 Total Quantity Adjustment(s): $19,028.50 1% Total Contract Price with Quantity Adjustment(s): $1,665,682.11 Previous Change Order(s): $0.00 This Change Omer: $61,720.00 Total Change Order(s)To Date: $61,720.00 4% Adjusted Contract Price: [Original Contract Price Plus Quantity Adjustment(s)Plus Change Order(s)] $1,727,402.11 Difference between Original and Adjusted Contract Prices: $80,748.50 5% Original Contract Time: 260 Time Adjustment by previous Quan.Adj./Change Order: Time Adjustment by this Quan.Adj./Change Order: 7 New Contract Time: 267 Submitted for Approval Prepared By: Kaitlyn Saucedo, Engineer Associate&Project Manager Printed Name,Title,Company Signature Date Approvals Contractor: Steven R. Green (Vice President) Royal Vista, Inc. Q26 Printed Name,Title,Company Signature Date City Project Manager: Kaitlyn Saucedo,Engineer AssociatePrinted Name,Name,Title Signatu a Date Mayor/City Manager. (`( n Printed Nle,Titld I Signa) l5ake Page 2 of 3 �►. Contract Quantity Adjustment/Change Order rev.06!25 Project Name: Cycle 4- Basins 1&2 Wastewater Main Rehabilitation Change Order/Quantity Adjustment No. 1 Change Order Data Contract Time Bid Item# Item Description Unit Qty. Unit Price Amount Adjustment(Days) 1 Rehab for the existing manhole#1434334 LS 1 $61,720.00 $61,720.00 7 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $61,720.00 7 Page 3 of 3 _ Contract Quantity Adjustment/Change Order nw.06/[5 Project Name: Cycle 4-Basins 1&2 Wastewater Main Rehabilitation Change Order/Quantity Adjustment No. 1 Quantity Adjustment Data Contract Time Bid Item# Item Description Unit Qty. Unit Price Amount Adjustment(Days) Furnish all materials,equipment, tools& labor necessary to eliminate 10" wastewater line, including pre-videoing to determine defect location,post-videoing to confirm repair, backfill**per standard details,ad surface restpration to existing 16 conditions LF 50 $380.57 $19,028.50 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 _ $0.00 $0.00 TOTALS: $19,028.50 0 Royal Vista, Inc. 350 C.R.260,Liberty Hili,Texas 78642 Phone.(512)515.6824 Date: 3130/4026 Proposal To: City of Round Rock Attn.: Kaitlyn Saucedo From: Stevan DeLeon Project:CORR-Cycle 4-Basin 3 8 4 WIN Rehab Rehab Existing Manhole CID!#1434334 Royal Wsta Proposes the Following: Description Bid QTY Units Amount Sub Total Prop of Existing Manhole 1 IS 7,746.00 $7,746.00 "Comentitious Bullildbock LS $15,564.00 $15,584.00 230 Mill ftraywall of Existing Manholls 1 LS $15,400.00 $15,400.00 Chemical rout to Stop Infiltration co Based on 10 Gallons of Grout and 10 Manhours to Stop Infiltration) 1 LS $5,040.00 $5,040.00 Bypass Pumping 1 LS $35,000.00 $35,000.00 Additional Overhead and Project Management for Added Subcontract work not Included in original contract 1 LS $3,125.00 $3,125.00 Credit of Manhole From Original Bid 1 LS ($20,175.00) ($20,175.00) Additional Grout Needed to Stop Infiltration GAL $295.00 $0.00 Additional Man Hour MR $210.00 $0.00 clays no 555501 W- our contract for this proposal. Total $61,720.00 THANK YOU! Submitted By: I � Accepted By: Printed NameTtle:Stevan DeLeon/Project Manager Printed NameTtle: Date: 03/30/2026 Date: steved Pagel 3/30/2026 Royal Vista, Inc. 350 CR 260 Liberty Hill,Texas 78642 (512)515-6824 Fax(512)515-6829 REQUEST FOR INFORMATION RFI NO.: 2503-004 DATE: 4/9/2026 PROJECT: CYCLE 4 BASIN 1 &2 RESPONSE REQUESTED BY DATE: As Soon As Possible TO: Hayden Mattke REFERENCE: UID#1960361 ISSUE: Plan Page WW-14 calls to lift bursted pipe to re-establish proper slope @ 50-117 from MH#1960360.But the manhole is full from 0-20.Need to grade from 0-117 to achive proper drainage. Please advise. Recommended Solution: Stevan De Leon, Project Manager RESPONSE: Please proceed with the additional 50' of rehabilitation to establish proper slope of the 10" main. 1 4/10/2026 Responder Date