Contract - Hensel Phelps Construction Company - 5/28/2026 Document G701 - 2017
Change Order
PROJECT:(Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
Bob Bennett Phases II,III and IV Contract For:CM as Constructor Change Order Number:02
3400 Sunrise Rd. Date:09/12/2024 Date:03/24/2026
Round Rock,Texas 78665
OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address)
City of Round Rock Jacobs Engineering Group,Inc. Hensel Phelps Construction Company
221 East Main St. 1999 Bryan Street 8326 Cross Park Dr.
Round Rock,Texas 78664 Suite 3500 Austin,Texas 78754
Dallas,Texas 75201
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and,if applicable,attach or reference specific exhibits.Also include agreed upon adjustments
attributable to executed Construction Change Directives.)
This Change Order#02 includes a decrease in contract sum and no change in contract time. Scope purchasing for Phase 2 improvements has
concluded. This deductive change removes the buyout savings from the GMP contract sum.
The original Contract Sum was $ 45,446,821.00
The net change by previously authorized Change Orders $ 0.00
The Contract Sum prior to this Change Order was $ 45,446,821.00
The Contract Sum will be decreased by this Change Order in the amount of $ 1,104,720.00
The new Contract Sum including this Change Order will be $ 44,342,101.00
The Contract Time will be unchanged by Zero(0)days.
The new date of Substantial Completion will be 01/29/2027
NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have
been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which
case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.
Jacobs Engineering Group,Inc. Hensel Phelps Construction Co. City qJ Round Rock
ARCHITECT(Firm name CONT CTOR(Firm name) OW
I r/
(F�oil
-OSIGNATLTAE SIGNATURE Or SIGN U E
Kris Kunkel,Sr Project Architect Philip Goertz,Project Manager Craig Morga ,Mayor
PRINTED NAME AND TITLE PRINTED NAME AND TITLE PNTED NAME AND TITLE
AV 0, '),
3 2oUv 2 s/ zG
DAT DAT DATE
Q_ 202(i- 131
AIA Document G701—2017.Copyright 0 1979,1987,2000,2001 and 2017.All rights reserved.'The American Institute of Architects,""American Institute of
Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are trademarks of The American Institute of Architects.This document was produced at 08:55:11
MT on 03/24/2026 under Order No.4104248843 which expires on 12/30/2026,is not for resale,is licensed for one-time use only,and may only be used in
accordance with the AIA Contract Documents*Terms of Service.To report copyright violations,e-mail docinfo@aiacontracts.com.
User Notes: (3139ADA56)