R-2026-158 - 6/11/2026 RESOLUTION NO. R-2026-158
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with
Braun & Butler Construction, Inc. for the Fire Station No. 10 Project, and
WHEREAS,the Council has determined that it is necessary to make adjustments/changes to the
quantity of work to be performed or materials, equipment,or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 1 to the Contract with Braun & Butler Construction, Inc. for the Fire
Station No. 10 Project, a copy of said quantity adjustment/change order being attached hereto as Exhibit
"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date,hour,place and subject
of the meeting at which this Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and the subject matter hereof were
discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551,
Texas Government Code, as amended.
RESOLVED this 1 lth day of June, 2026.
AAZ
CRAIGORG , Mayor
City of tound Yck,Texas
ATTEST:
ANN FRANKLIN, City Clerk
0112.20262
EXHIBIT
A Page I of
Contract Quantity Adjustment/Change Order
rev,01/16
Department: General Services
Project Name: Fire Station x10 _ Date: 5/1/26
Change Order/Quantity
City Project ID Number FS10 Adjustment No. 1
Vendor Braun&Butler Construction,Inc. 300 Hazelwood St.,Ste. 100,Leander,Texas 78641 512-837-2882
Company Name Address Phone No.
Justification
Une Item*1:Backflow preventer(BFP)was included on Civil Drawings at time of bid.CORR Engineers directed for the BFP to be removed from Civil Drawings.A BFP is
required either outside the building or at the fire riser.A BFP was not accounted for and needed to be added at the riser to meet code.Une Item*2:During plan review
the City Electrical Inspector called out need for(8)AFCI breakers and tamper resistant receptacles.Une Item*3:CORR FD requested dual swing traffic doors for the
Bunker Gear Storage Room during design for FS11.They requested we incorporate this add into FS10.CORR FD requested that exterior station number on the watch
tower be back lit during design for FS 11.They requested we incorporate this add into FS10.Une Item*4:CORR FD requested#10 sign be added to South Exterior Wall
(facing Old Settlers Blvd.).Due to this,we needed to change the exterior light fixture to also capture this.CORR FD requested that wall mounted oscillating fans be added
to Bunker Gear Storage room.Architect recommended that we do mounted locker tag name plates be added to all lockers in lieu of adhesive.This change will prevent
damage to cabinet veneer.Une Item*S:Due to access easement with shared drive with the neighboring Exxon Gas Station and the shared drive with the neghboncing
day care,it was determined that CORR would have to dictate sequencing of concrete drive tear up and replacement work.Due to sequencing this required that a portion
of sub grade work(South Drive)had to be reworked Une Item*6:The 100 gallon water heater(WH)at FSl recently had to be replaced.it was extremely difficult to
get this size of equipment replaced in the mezzanine with finished fall,access via ship ladder,etc.CORR Facilities requested that we switch to(2)60 gallon WHs in lieu of
a single 100 gallon WH.This change will also benefit the station because if one of the 60 gallon WH tanks were to go out,the station would still have another working 60
gallon WH to operate the station off of.
The$99,519.89 will replenish the Owner's Betterment Allowance.
SUMMARY Amount %C
Original Contract Price: $9,149 947.00
Previous Quantity Adjustment($):
This Quantity Adjustment: $0.00
Total Quantity Adjustment($): 0.00
Total Contract Price with Quantity Adjustment(s): 9 149 947.001
0%
Previous Change Order($):
This Change Order: $99,519.89 1%
Total Change Order(s)To Date: $99,519.89 1%
Adjusted Contract Price [Original Contract Price Plus Quantity
Adjustment($)Plus Change Order(s)j: $9,249,466.891
Difference between Original and Adjusted Contract Prices: $99,519.89
Original Contract Time:
Time Adjustment by previous Quan.Adj./Change Order:
Time Adjustment by this Quan.Adj./Change Order:
New Contract Time: 0
Contractor: Matt Harton, Senior Project Manager, Braun&Butler Construction, Inc. 2-0 7A
S gna r Printed Name,Title,Company Date
City Representative: Hayden Schiller,Project Manager —�
ature Printed Name,Title Date
Mayor/City Manager Craig Morgan, Mayor
Signature Printed Name,Title Date
Project Name: Fire Station #10
Quan.Adj./Change Order No.: t
Change Order Data
Contrail
Time Adjustment
(Days)
Item JJ Item Description Unit _ (fit Unit Price Amount
8-BFP Added to Riser Due tr,Vault Removev
1 from Civil Drawings After Bid LS 1 S;%,635.25 $17,635.25
Added AFCI Breakers,Tamper Resistant
2 Receptacles per City Inspector LS 1 $8,653.00 $8,653.00
3 Traffic Doors&Exterior x10 Station Sign LS 1 $15,257.00 $15,257.00
Exterior Light Fixture, n er ans, er _
4 Tags LS 1 $9,915.53 $9,915.53
5 South Drive Sub Grade-Rework LS 1 $28,924.11 $28,924.11
6 Water Heater Change-(2)60 gallon WHs LS 1 $19,135.00 $19,135.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$o.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
so 00
TOTALS: $99'519.0-9i-- 0 I
Braun&Butler
City of Round Rock Fire Station 10
Allowance Adds - Fire Sprinkler Backflow and Additional Gate
Date. 0413012026
Subject: Allowance Adds
From: Matt Harlon
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden,
Attached is pricing for the work to install an RPZ Backflow Preventer on the fire sprinkler riser and to install an
additional sliding gate and operator at the parking area .. If approved,please sign this page and issue a field
change order contingency charge approval in the amount of$41,523.35
- RPZ Backflow on Fire Riser $17,635.25
- Sliding Gate and Operator $23,888.1
- Total $41,523.35
Sincerely,
1
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page Iof1
300 Hazelwwd STE 100 Leander,Texas 78641 1 office(512)837-2882 I fax(512)837-5115 I bfaun-boler com
Capitol Sprinkler and Fire Systems LLC
Capito 1750 County Road 269, Suite E
Leander, TX 78641
Sprinkler Fire Systems (512)960-2628
REQUEST FOR CHANGE ORDER
W-1474 DG 001
Braun & Butler Re 0
0 0
0 0
Attn' Matt Harlon 0
Description of additional wo.-k Add 8' backflow preventer to riser room Backflow to be 8"to make sure
hydraulics talc safety factor is not reduced from orginal. Redesign and resubmit plans
LOG DESC. I New backflow preventer inside riser room
We are requesting a Change Order to be added to the original contract amount of the above referenced project Pending approval,we
will perform additional items that were not included in the original scope of work
Description Units Unit Price Total
Labor 24.00 $85.00 $2,04000
Project Management 2.00 $10500 $210.00
Material 1.00 $11,680.00 $11,680.00
E u pment Rental 0.00 $501 82 $000
Design _ 8.00 $105.00 $840.00
Permit 1 0C $50000 $500.00
Mist 1.00 $65.00 $65.00
$0.00
Sub-Total $15,335.00
15% OH&P $2,300.25
Taxes 8 25".-
Totall $17,635.25
Please call if you have any questions.
Thank you for your assistance,
Authorized by
Print Name _
Mike I Project Manager Date
1$3
Braun&Butler
C'ONSTRUCTTIN
City of Round Rock Fire Station 10
PR 06 Site Elect Revs, Extractor Change, Baby Box
Date: 0410112026
Subject: PR 06 Site Elect Revs, Extractor Change, Baby Box
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden„
Attached is pricing for the worts outlined in PR-06.. The extractor change was rejected by the FD. We are staying
with original specified extractor. No pricing for the extractor included in this proposal.
-Electrical—additional controls circuits $7,573.00
-Baby Box install labor. $1.080.00
$8,653.00
Sincerely,
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 1 office(512)837-2882 1 fax(512)837-5115 1 braun-butler.com
BJ1,Inc.dba State Electrical Contractor No. 17161
B. J. Electric company Master License No. 24035
1509 Three Points Road Phone: 512-990-5500
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley(a bjelectric-inc.com
January 28,2026
Braun&Butler Construction
300 Hazelwood Street.,Ste 100
Leander,Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-Chanee Proposal#12—PR 06
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on drawings dated 8/01/2025. We propose to furnish materials and
labor for this change:
Scope:
— Provide and install conduit and wiring for one added"B"fixture.
— Provide and install added"B"fixture.
— Provide and install(8)AFCI breakers as shown.
— Change receptacles in Dorm rooms to Tamper Resistant.
Change Proposal#12—Total Add: $7,573.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any change order without written approval.
Verbal direction on chance orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
Please feel free to give me a call with am questions.
Jerry Lilley
Project Manager
1'2812026 12.4623 PM Pape 1
Round Rock FS PR 06
Job Number C0822-8
Bid Summary Default
Extension By Phase
Item Description Quantity Price U EdPrko Labor Mr U Est Lab Hr
---02 Underground Branch Raceway---
1•a:'. I PV' 15 6, 19 C 12 02 227 C 034
2076 1"PVC Male Adaptor 2 8939 C 1 79 008 E 016
217;'.- Fv"_�upung _ 082 C 388 005 E 027
-`02 Underground Branch Raceway Total- 1769 077
--.04 AwX a Ground Branch Raceway—
1345 1 GRC Elbow 4 2 036 12 C 81 44 04' E +88
15% V Locknut 2 75 39 C 151 010 E 020
- 04 Above Ground Branch Raceway Total--- 82 95 208
--05 Feeder vMre--
2662 98 THHN CU Stranded Wire 60 875 58 M 5220 813 M 048
---05 Feeder.^,re T.3!a- 52 20 048
06 Brach'Aare
2682 010 THHN CU Solid VVire 16 517 53 M 805 813 M 013
._06 Brach'/'fire Tcta. 805 0 13
--07 Switchgear
4115 20A 1P Bolt-On C'roud Breaker 8 QUOTE 2 0.00 052 E 416
S.!chgear'ra 000 4 16
—08 UgMahg—
22078 L E 0 Bollard Fixture 1 QUOTE 1 0.00 598 E 598
--08 Lghorlg Total-- 0 00 598
---09 Trim
4703 20A/125V Spec Grade Dup Rcpt(5-20R) •80 304 E -182.10 0.33 E -1980
47061 20AII25V Tamper Resistant Decora Rcpt 15-20R i 60 985 E 591 00 033 E 1980
---09 Tran Total— 40680 000
Job Total 56949 1360
Target Labor column 2
112812026 12:47:42 PM Page 1
Round Rock FS:PR 06
Totals(Summary)-Bid Summary:Default
Material
Non-Quoted $56949
Quotes 4,426.00
Sales Tax 10 00%) 000
Total Material $4.99549
Labor
Direct(13.60 hours @ S65 00) $88400
Non Productive Labor 8840
Total Labor (13.60 hours) $97240
Direct Job Expenses $47036
Tools and Miscellaneous Materials 14699
Subcontracts 000
Job Subtotal(Prime Cost) $6 58524
Overhead(0 00%) 000
Profit(15.00%) 98779
Job Total S7 573 03
Actual Bid Price $7.57303
Material to Direct Labor ratio 0.85
Prime Cost per square foot $047
Job Total per square foot $054
Actual Bid Price per square ft $054
Labor cost per square foot $0.07
Labor hours per square foot 000
Gross Profit% 1304
Gross Profit$ $98779
Net Profit% 13,04
B&L Construction CHANGE ORDER PROPOSAL # 3
39 Fairtnew Dr. Prepared by
Round Rock, TX 78665-9428
OFFICE M 248-0772 FAX M 248-0786
•Metal stud Gaming •Drywall •Acoustical Ceilings
GENERAL CONTRACTOR: Braun& Butler Construction ATTENTION : Matt
PROJECT : City of Round Rock Fire Station No.10 DATE : 4 11,26
1) PR96
Labor to install owner supplied baby box S 1.080.00
TOTAL AMOUNT OF CHANGE ORDER S 1.080.00
EXCLUSIONS AND QUALIFICATIONS
1) Emailed copy to serve as the original
2) Sales tar excluded on all materials.
1 C_43>
Braun&Butler
City of Round Rock Fire Station 10
PR 13
Date: 04/0112026
Subject: PR 13 Traffic Doors, Hardware, Signage, Electrical, Light Fixtures
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden„
Attached is pricing for the work outlined in PR-13.. This includes the traffic doors,signage change,electrical
changes,and lighting fixture change.
-Traffic doors and HM Frame change(materials) $8247.00
-Signage changes $2945.00
-Electrical— $4065,00
$15,257.00
Sincerely,
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of t
300 Hazelwood STE.100 Leander,Texas 78641 1 office(512)837-2882 1 fax(512)837-5115 I braun-buder.com
�, ELECTRONIC
LAFORCE S. SECURITY'SYSTEMS
powered by tAFORCE
Email Quote
Date: March 20, 2026 Total Pages: I
To: Matt Harton From: McKenzie Johnson
Company: Braun & Butler Phone: (920)490-2368
(800)672-6795 ext.236801
E-mail: mckenzie.iohnsonalaforeeinc.com
Re: Double Acting Doors
Cit of Round Rock Fire Station #10
LaForce Joh#: 50507
Matt,
Please see below for the cost impact to add the traffic doors and frames from PR 10 to the City of
Round Rock Fire Station#10 project.
Double Acting Doors
• ADD(2)3'0"W x 7'-8"H Traffic Doors
o Honeycomb Polymer Core with ABS Face
o Color: Red
o Window: 16"x 16"
0 36"H Stainless Steel Plates(Front& Back)
• ADD(2)Steel Frames
o Welded
COST IMPACT (ADD)58,247 (no tax)
Once approval is received and all information is gathered,the materials can be ordered. Until
approval is received,materials N\i I I not be ordered. For accounting purposes,adjust your contract
order with LaForce.
If you have any questions,please contact us.
Sincerely, Authorized by:
MOP) Company name: _
McKenzie Johnson Date:
Division 10 Project Manager
LaForce
This quote is subject to prompt acceptance within 30 calendar days from the date of this quote first noted above
If not accepted by that date it may be withdrawn or modified by LaForce
1.M.23LS e • www.laforesine.com
Executive Signs Enterprises Inc Proposal
5621 Central Texas Dr San Marcos TX 76666
Phone(512)292-9936 Due to material volatility quotes are only valid for 30 days
r J.�.� ,.APhone(210)492-9436
sI .� -A Fax(210)492-9483
SiGpis.., www executiyeSignS com ACCOUNT REP E-MAIL
TSCL#18330 Kacey Brewer k ceexecutives) ns com
PROPOSAL SUBMITTED TO PHONE FAX DATE
Braun & Butler Aril1 2026
STREET CONTACT E-MAIL
CITY STATE ZIP CODE JOB LOCATION
CORR FS10
EXECUTIVE SIGNS ENTERPRISES INC WILL FURNISH THE FOLLOWING
ST-9 Produce and install (1) T-3/4" "10"front lit and back lit set of channel letters Channel letter faces well
be white with red translucent vinyl. in order to back light in white they cannot be red acrylic Letter returns are a
standard painted with uv clear coat.
Additional permit at cost from the city could be needed or this one set Not sure until we submit all for permitting
permitting
50%draw required for samples and to begin production
"'Progress payments will be requested if the sign is ready to instill ,,r;we are wading r, schedule Installation—
WE
nstallat on—WE PROPOSE HEREBY TO FURNISH MATERIAL AND LABOR COMPLETE IN ACCORDANCE WITH
THE ABOVE SPECIFICATIONS.FOR THE SUM OF
DOLLARS $2.945 00 SUBTOTAL
TAX
$2.945.00 TOTAL
PAYMENT TO BE MADE AS FOLLOWS
50%when contract is signed and the remainder when the job Is complete
Signs permrtlsl if required will be added to the final invoice at the actual cost of the pernnt(s)plus$200 00 for administration time Cost of
Structural Engineering if required will also be added to the Final Invoke
THE ABOVE PRICING IS BASED ON MAUFACTURING FOR 120 VOLT ELECTRICAL POWER CUSTOMER IS RESPONSIBLE FOR PROVIDING
ELECTRICAL POWER TO THE SIGN LOCATION AS WELL AS ANY TIME CLOCK OR OTHER LIGHTING CONTROL PER NATIONAL AND
ORDINANCE A DEDICATED CIRCUIT INCLUDING NEUTRAL WIRE WITH GROUND IS REQUIRED FOR ALL SIGN LOCATIONS COSTS INCURRED
FROM ROCK OR OTHER OBSTRUCTIONS DURING EXCAVATION OR DRILLING OF THE STRUCTURAL FOUNDATIONS WILL BECOME AN EXTRA
CHARGE AND APPLIED TO THE FINAL INVOICE THE PURCHASER AGREES TO ACCEPT RESPONSIBILITY FOR ANY DAMAGES INCURRED
BENEATH THE SURFACE WHERE DRILLING OR EXCAVATION IS REQUIRED
THIS PROPOSAL IS SUBJECT TO YOU PROVIDING LANDLORD OR OWNERS APPROVAL,AND A SIGN PERMIT FROM THE CITY NO WORK WILL
BE STARTED UNTIL A PERMIT HAS BEEN RECEIVED WE WILL NEED YOUR C OF O TO EXPEDITE THIS
ALL MATERIALS ARE GUARANTEED TO BE AS SPECIFIED AND THE ABOVE WORK IS TO BE PERFORMED IN ACCORDANCE WITH CUSTOMER
APPROVED DRAWINGS AND COMPLETED IN A SUBSTANTIAL WORKMANLIKE MANNER ANY ALTERATIONS OR DEVIATION FROM THE ABOVE
SPECIFICATIONS INVOLVING EXTRA COSTS WILL BE EXECUTED ONLY UPON WRITTEN ORDERS AND WILL BECOME AN EXTRA CHARGE
OVER AND ABOVE THE ESTIMATE ALL AGREEMENTS ARE CONTINGENT UPON STRIKES OR DELAYS BEYOND OUR CONTROL ALL MATERIAL
PROVIDED REMAIN THE PROPERTY OF EXECUTIVE SIGNS ENTERPRISES INC UNTIL CONTRACT AMOUNT IS PAID IN FULL ALL SUMS DUE
EXECUTIVE SIGNS ENTERPRISES,INC UNDER THIS CONTRACT SHALL BE DUE AND PAYABLE AT 5621 CENTRAL TEXAS DR SAN MARCOS TX
78666 ANY AND ALL ACTION TO ENFORCE INTERPRET OR OTHERWISE ADJUDICATE THE RIGHTS OF THE PARTIES HERTO SHALL BE
BROUGHT ONLY IN HAYS COUNTY TEXAS
ACCEPTANCE OF PROPOSAL-THE ABOVE PRICE SPECIFICATIONS AND CONDITIONS ARE SATISFACTORY AND ARE HEREBY ACCEPTED
YOU ARE AUTHORIZED TO DO THE WORK AS SPECIFIED PAYMENT WILL BE MADE AS OUTLINED ABOVE THIS PROPOSAL MAYBE
WITHDRAWN IF NOT ACCEPTED IN 30 DAYS
AUTHORIZED EXECUTIVE
SIGNATURE SIGNS
BY: BY:
DATE: DATE:
Electrical Sign Contractor License# 18330
Regulated by the Texas Department of Licensing and Regulation PO Box 12157 Austin, TX 78711 1-800-803-9202
512-463-6599 www license state tx us/complaints
&,ft ft State Electrical Contractor No. 17161
B.J. Electric company Master License No. 24035
1509 Three Points Road Cell Phone: 512-845-9187
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley@bjelectric-inc.com
February 5,2026
Braun 8c Butler Construction
300 Hazelwood Street., Ste 100
Leander,Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-Change Proposal#10-PR 13
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on PR 13, drawings dated 11/18/2025. We propose to furnish
materials and labor for this change:
Scope:
- Provide and install one type N fixture in room 138.
- Add one dimmer switch for this N fixture.
- Change type H4 fixtures, in room 112, from (6)individual fixtures to one continuous row
fixture.
- Make multiple lighting controls zone changes.
Change Proposal#10—Total Add: $4,065.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any change order without written approval.
Verbal direction on change orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
Please feel free to give me a call with any questions.
Jerry Lilley
Project Manager
HC AUSTIN TX(1501) Quote
4801 Freidrich Ln WES-020526-344
Austin,TX 78744
ENctrkW Sakothm
Job Name:CORR FIRE STATION 10 PR13 ADDER Quote Date: Feb 05, 2026
Expires: Mar 07,2026
To:B11 INC dba BJ ELECTRIC From:JOANN PIGNATARO
Email:joann.pignataro@wescodistcom
SUPPLIER
-6 H4 LUMENWERX ALC-APO-LED-80-550-35-2FT-
UNV-DI-1-COVH-W
1 H4 LUMENWERX ALC-APO-LED-80-550-35-
24FT-UNV-DI-1-COVH-W
SUBTOTAL ADDER FOR ABOVE
CHANGE FROM(6)2FT
$85000
SECTIONS TO(1)24FT
SECTION
ESSF0604U9527930WWF1 ED
1 N VC-ARCH ESPR06024010120-277 $750.00 $75000
Notes:QUOTING 95"FIXTURE-
CLOSEST TO 8FT LENGTH
1 CONTROLS COOPER CONTROLS WW3-RL $95.00 195.00
NOTES
FREIGHT IS ADDITIONAL
TOTALGRAND
Pricing&Estimated Ship Dates(ESD)and Lead Times provided for all manufacturers are subject to change without notice.
Prices do not include sales tax
BY ACCEPTING THIS QUOTE,YOU AGREE THAT THE WESCO TERMS AND CONDITIONS OF SALE PUBLISHED AT
WWW.WESCO.COM/TERMSOFSALE ARE EXPRESSLY INCORPORATED INTO AND SHALL GOVERN THIS TRANSACTION.
WESCO MAY ASSESS STORAGE AND TRANSPORTATION FEES IF YOU DO NOT TAKE OR ACCEPT DELIVERY WITHIN 45 DAYS OF
PRODUCT AVAILABILITY.WESCO MAY ALSO UPDATE THIS QUOTE OR PRICING ABOVE DUE TO CHANGES IN DUTIES,FREIGHT,TARIFFS,
SUPPLIER PRICING,SURCHARGES,COMMODITY AND METAL ADJUSTMENTS,OR EXCHANGE RATE FLUCTUATIONS.
PRICING IS VALID FOR 24 HOURS.PRICES MAY BE SUBJECT TO METAL ADJUSTMENTS BASED ON PO ISSUANCE AND RELEASE(S).
JOANN PIGNATARO
Wesco Distribution,Inc.
Page 1/1
2/6/2026 11:44:09 AM Page 1
Round Rock FS RR FS s10 PR 13
Job Number COb22 7
Bid Summary.Default
Extension By Phase
nem a Description Quantity Price U Ext Price Labor Hr U Ext Lab Hr
-- 04 Above Ground Branch Raceway---
2425 12"T-Ba,Wre Conduit Cim 1 106 19 C 1 06 008 E 008
2469 4'Square Box(12 6 314 KO'e) 1 282.96 C 283 023 E 023
2470 4 Square x 1 1/2'Deep Box wlbld(1/28314 KO'sl 1 53951 C 540 026 E 026
2858 318-MCIBX Cornsclor 2 50.67 C 101 007 E 014
4897 4 Square IG Plaster Rep-5/8-D 1 67083 C 6 71 0 D9 E 009
6133 Red VNrerxAs 9 19245 M 1 73 227 C 021
--04 Above Ground Branch Raceway Total-- 18 74 1 01
---06 Brach Wre---
2801 122 AYmnm Cleo MC Cable Solid 15 1.D41 87 M 1563 1430 M 021
--06 Brach Wre Total--- 1563 021
---08 L,gh6ng—
5257 Seismic wee 4 3 DO E 12 DO 004 E 016
5294 Manufactured Fixture 7Yhp 14(3) r 633 E 633 020 E 020
5300 Flexible Conduit Hanger(Caddy KX) 3 12966 C 389 005 E 015
48628 Ce,linq/Surface li L E D Fixture 1 QUOTE 1 000 1 95 E 1 95
62884 30'Recessed Linear LED 1 QUOTE 1 000 1560 E 15 60
08 L ignong Total— 22 22 1806
-09 Tnm
5079 4"Square Rat Blank Cover 1 330 71 C 331 009 E 009
62695 1 Relay On/Off 0-10V Dimming Room Controller 1 QUOTE 11 0 Do 025 E 025
---09 Trim Total--- 331 034
---10 Voxce/DatafVrdeo--
2933 Plenum C.a!5e 24gauge 4pae 40 511 01 M 2044 11 50 M 046
---10 Vorce/DausN.deo Total-- 20 44 046
Job Total 80 34 20 D8
'Target Labor column 2
2/5/2026 11:56:09 AM Paye 1
Round Rock FS: RR FS 1110-PR 13
Totals(Summary)-Bid Summary:Default
Material
Non-Quoted $8034
Quotes 1,695.00
Sales Tax(0 00°!x) 000
Total Material $1.775.34
Labor
Direct(20.08 hours @$65 00) $1,305.20
Non-Productive Labor 13052
Total Labor (20.08 hours) $1.435.72
Direct Job Expenses $24644
Tools and Miscellaneous Materials 7701
Subcontracts 000
Job Subtotal(Prime Cost) $3,534.51
Overhead(0 00%) 000
Profit(15.00%) 530.18
Job Total $4,06469
Actual Bid Price $4.06469
Material to Direct Labor ratio. 0.58
Prime Cost per square foot $025
Job Total per square foot $0.29
Actual Bid Price per square ft S029
Labor cost per square foot $0.10
Labor hours per square foot 0.00
Gross Profit% 1304
Gross Profit S $530 18
Net Profit% 13.04
1 C-43)
Braun&Butler
CONSTRUCTION
City of Round Rock Fire Station 10
PR 12
Date: 0410112026
Subject: PR 12 — Wall fans, strip lighting, name tags, alerting strobe, hardware, signage
From: Matt Harlon
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden„
Attached is pricing for the work outlined in PR-12 This includes the fans,name tags,alerting strobe,hardware,
signage,electrical light fixture revisions costs
-Fans and strip lighting Electrical $5851.00
Signage changes $634.00
Added Alerting strobe in Fitness $920.53
Millwork locker tags $1904.00
$9,309.53
Sincerely,
4r'�
I
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 1 office(5 12)837-2882 1 fax(512)837-5115 I braun-butler.com
BA,Inc.dba State Electrical Contractor No. 17161
B. 1. Electric company Master License No. 24035
1509 Three Points Road Phone: 512-990-5500
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley@bjelectric-inc.com
January 27, 2026
Braun&Butler Construction
300 Hazelwood Street.,Ste 100
Leander,Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-Change Proposal#8—PR 12
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on drawings dated 10/24/2025. We propose to furnish materials and
labor for this change:
Scope:
— Provide and install conduit and wiring for three added wall fans.
— Provide and install three model#WB292451 wall fans.
— Relocate three type N 1 fixtures in corridor.
— Add rough-in only for added strobe in Fitness 149.
— All rough-in to be surface mount on CMU,unless CMU cut and patch by others.
Change Proposal#08—Total Add: $5,851.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any chance order without written approval.
Verbal direction on change orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
— Any cut and patch of CMU walls.
— Any fishing down CMU walls.
Please feel free to give me a call with any questions.
Jerry Lilley—Project Manager
11111111111111111111 WIN iii
Quotation
HILL COUNTRY ELECTRIC SUPPLY QUOTE DATE QUOTE NUMBER
4801 FREIDRICH LANE
BLDG 2 STE 200 01/20/2026 S102870708
AUSTIN.TX 78744
512-428-9300 HILL COUNTRY ELECTRIC SUPPLY PAGE NO.
Fax 512-428-9830 4801 FREIDRICH LANE
BLDG 2 STE 200
P�
AUSTIN.
USTI.TX 787" 1 of 1
Fax 512-428-9830
QUOTE TO SHIP TO:
BJI INC dba BJ ELECTRIC BJI.. INC dba BJ ELECTRIC-SHOP
SHOP
1509 THREE POINTS ROAD
RD
PFLUGERVILLE TX 78660 PFL THREE POINTS FLUGERVILLE. TX 78660
CUSTOMER NUMBER CUSTOMER PO NUMBER JOB NAME/RELEASE NUMBER SALESPERSON
2682 BLAKE CHANCE
WRITER SHIP VIA TERMS SHIP DATE FREIGHT ALLOWED
Randon Grametbaur NORTH ROUTE 2% 10th Net 25th 02/06/2026 No
ORDER QTY DESCRIPTION UNIT PRICE EXT PRICE
3ea WB292451 455.947/ea 136784
BLOBAL INDUSTRIAL 30" OUTDOOR
RATED FAN 2 SPEED 8,400 CFM, 3/10HP
STOCK IN TEXAS""
3-4 DAY LEAD TIME
CONDITIONS OF SALE PUBLISHED AT WWW WESCO COM/TERMSOFSALE ARE
EXPRESSLY INCORPORATED INTO AND SHALL GOVERN THIS TRANSACTION Wesco Subtotal 1367.84
may assess storage and transportation fees If you do not take or
accept delivery within 45 days of product availability Wesco may S&H Charges 0 00
also update this quote or prong above due to changes In duties 9
freight tanffs supplier pricing surcharges commodity and metal
adlustments or exchange rate fluctuations
Pncing Is valid for 24 hours Prices may be subject to metal
adjustments based on PO Issuance and release(s) Amount Due 1367.84
Printed By RANGRA on 120/2026 12 42 59 PM
1127/2026 12:21:37 PM Papa 1
Round Rock FS RR FS N10 PR N12
Job Number CO822 6
Bid Summary Default
Extension By Phase
Kam N Description Quantity Price U Eat Price Labor Hr U Eat Lab Hr
04 Above Ground Branch Raceway--
1001 3/4'EM' 190 13061 C 24762 7 15 C 1356
1465 3/4'Sat Screw Steal Insu1 Thros1 Com 10 10913 C 1091 008 E 0 90
1515 34-Comp Steel Insul Throat Conn 24 0 57 E 1368 0 17 E 408
1545 34'Set Screw S"Cplp 19 10395 C 1971 008 E 1 52
2423 3r4Meta Stud Conduit Clip 24 42352 C 10302 553 C 1 35
2469 4-Square Boa(1/2&314 KO's) 5 28296 C 14 15 023 E 1 15
2471 4-Square x 2.118`Deep Box(1/2 6 314 KO's} 2 121 91 C 6 44 023 E 046
2479 1 G VVP Bell 8oz{3)1/2"Hubs 5 1.112 05 C 5560 066 E 325
4901 4 Sq:are-2G Piaster Ring.12-0 1 25598 C 256 0 D9 E 009
8133 Red Klrarxaa 35 19244 M 674 228 C 0 a0
.-04 Above Ground Branch Raceway Total-- 48C 43 27 06
- 06 Brach Wire--
2660 012 THHN CU Stranded VMn1 548 304.87 M 188 44 7 15 M 390
--06 Brach W1re Total--- 166 44
390
--09 Trim
4703 20A1125V Spec Grade Dup Rcpt(5-20R) 5 975 E 4875 033 E 165
5059 1G WP ir Use Cover 4 16 50 E 6600 0 16 E 064
5081 1G WP In Use GFI Cover(Verttca) 1 1850 E 1650 018 E 018
5080 4'Square Flat Blank Cover*/KO 5 35540 C V 77 009 E 045
--09 Tnm Total--- 14902 2 90
18 Msc: —
T0001 FAN MODEL OWS292451 1 QUOTE 13 000 260 E 260
T0002 FAN MODEL NVAM451 2 QUOTE 13 000 280 E 520
---18 M.sc Total - 000 780
Job Total 795 89 41 66
'Targel Labor column 2
1/27/2026 1:16:23 PM Page 1
Round Rock FS:RR FS#10-PR#12
Totals(Summary)-Bid Summary:Default
Material
Non-Quoted S79589
Quotes 1,36800
Sales Tax(0 001/.) 000
Total Material $2,16389
Labor
Direct(41 66 hours ®$65.00) $2.70790
Non-Productive Labor 21639
Total Labor (41 66 hours) $2,924 29
Direct Job Expenses $000
Tools and Miscellaneous Materials 000
Subcontracts 0 00
Job Subtotal(Prime Cost) $5,088 18
Overhead(0 00%) 000
Profit(15 00%) 763.23
Job Total $5851 41
Actual Bid Price $5.851 41
Material to Direct Labor ratio 0 44
Prime Cost per square toot S036
Job Total per square foot $042
Actual Bid Price per square ft S042
Labor cost per square foot $021
Labor hours per square foot 000
Gross Profit% 13.04
Gross Profit S $76323
Net Profit% 13.04
9
Date 3/16/26
To: Braun & Butler
From: Kacey Brewer
Re: City of Round Rock Fire Station #10
Please accept this as our proposal to do the following:
Produce and install-
ST-13 Locker Tags—(6) ADA SIGN - 10 x 2 x 0.063 SUBSTRATE (321-601) - ADA Alternative - RED/
APPLIQUE (311-304) - ADA Alternative - SILVER DIGITALLY PRINT LOGO NO Braille, NO ADHESIVE,
STRAIGHT EDGES, SQUARE CORNERS 5
636-10-S - 10" X 2" SILVER SLIDE-IN WALL HOLDER $554
Fuel/Trip- $80
Total: $634
50% DRAW REQUIRED TO PURCHASE MATERIALS AND BEGIN PRODUCTION. ANY ADDITIONAL
TRIPS WILL BE ADDITIONAL. QUOTE VALID FOR 15 DAYS.
Executive Signs, Enterprises Inc. Approved
By Kacey Brewer By
Electrical Sign Contractor License#: 18330
Regulated by the Texas Department of Licensing and Regulation PO Box 12157. Austin, TX 78711
1-800-803-9202, 512-463-6599, www license state tx us/complaints
Executive Signs Enterprises,Inc. 5621 Central Texas or San Marcos,Texas 78666 (210)492-9436 Fax(210)492-9483
*Custom systems Designs Inc . Estimate
**'
i w,�, SP
IC :
..M
Date Estimate#
3/31/2026 4460
1108 Sherwood Dr. Canyon Lake,TX 78133
Customers Name/Address
Braun&Butler Construction.Inc.
300 Hazelwood St.,Ste. 100
Leander,Texas 78641
Terms Rep Project
Due on receipt GSA' Fire Station 10
Item Description Qty Cost Total
Round Rock Texas New Construction Fire Station 10
USDD STR-2 USDD G2 Strobe Light/Red LED 1 635.53 635.53
Labor Installation of additional G2 strobe light in Fitness Room 149 1 285.00 285.00
Subtotal $920.53
ALL INVOICES ARE SUBJECT TO 1 1/2%INTEREST CHARGE PER MONTH Sales Tax (0.0%) $0.00
IF NOT PAID WITHIN TERMS
Total $920.53
Custom Systems Design,Inc.
Phone# Fax# Contact:George Vigue Web Site
210-363-6800 george+_csdisa.com www.csdisa.com
TRAVIS CAP Number: 1
MILLWORK
Project: Round Rock Fire Station No.10 Date Sent: 3/12/2026
Location: 4400 E.Old Settlers Blvd.
Round Rock,TX
78665
Detail Ref. Repeats Scope Description
Name Plate Holder 29 Supply and attached 2x10 name plate holder to locker doors.Name plate to be provided by others.
CAP Total: $1,904.00
The following are Qualifications to our bid:
Pricing on this CAP is valid for 15 calendar days from day sent.
Schedule of additional work provided in this CAP may fall outside original project schedule.
Matthew Williamson
Senior Estimator
Travis Millwork
(512)272-WOOD(9663)
matt.will iamson Cdtraviscomuanies.com
VCHAMPION SITE PREP
6301 N INTERSTATE 35
GEORGETOWN.TX 78633
OFFICE(512)863-3453/FAX(51 2)863-3463
ADDITIONAL WORK / CHANGE AUTHORIZATION
BRAND ON(811 DI GD I RT.COM
CITY OF ROUND ROCK FIRE STATION 10/T&M PER ATTACHED REPORTS
DATE: 03/12/26 JOB NAME: CORR FIRE STATION 10
TO: BRAUN&BUTLER CONSTRUCTION ESTIMATOR: BT
ATTN: MATT HARTON LOCATION: ROUND ROCK
DESCRIPTION QTY UNIT RATE
1. BH-24 W/OPERATOR 53 HR $148.00 $7,844.00
2. SKID-23 W/OPERATOR 48 HR $131.00 $6,288.00
3. XRNTDDREK-19 W/OPERATOR 53 HR $123.00 $6,519.00
4. HAULOFF 14 LOA $128.00 $1,792.00
S. SELECT FILL IMPORT 183 TON $14.80 $2,708.40
SUBTOTAL: $25,151.40
OH/P 15% $3,772.71 $3,772.71
TOTAL: $28,924.11
Description of Work:PRICING ABOVE FOR T&M WORK COMPLETED PER ATTACHED SIGNED REPORTS.
The scope items above Include items not part of overhead including:FUEL,OIL,GREASE,
MAINTENANCE,INSURANCE,SMALL TOOLS,LIGHT TRUCKS,SURVEY/CAD EQUIPMENT,AND
OVERTIME IF APPLICABLE.
NOTE: Pricing per GC REQUEST.Scope not listed above is not included.Price is valid for 30 days.
ACCEPTANCE OF PROPOSAL-The above prices,specifications and conditions are satisfactory and are hereby accepted.
AUTHORIZED SIGNATURE DATE OF ACCEPTANCE
Page 1 of t
Daily Time and Materials (T&M) Report
Date: 2/18/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity:0
Notes:
Began re-working/excavating the small piece of remaining paving section to the south of the building in front of the GC's trailer
Began making the necessary cuts to re-establish the sub grade stockpiled material to be hauled off tomorrow
T&M
Backhoe w/operator 5 hours
Skid steer w/operator: 5 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 3 2 5
JUAN MORALES-Juan M Morales 3 2 5
Total Labor Hours: 10
Equipment Hours
BH-24-Cal 416 C4SX-#1580 5
SKID-23-CAT 265-#4903 5
XRNTDDREK19-Sakai SW354U-#0449 5
Total Equipment Hours: 15
� i `
�d � �
Daily Time and Materials (T&M) Report
Date: 2/19/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building in front of the GC's
trailer
Continued making the necessary cuts to re-establish the sub grade
- Began hauling off the contaminated select material hauled off 12 loads
T&M
Backhoe w/operator. 10 hours
Skid steer w/operator 5 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M Morales 3 2 5
Total Labor Hours: 15
Equipment Hours
BH-24-Cat 416 C4 SX-#1580 10
SKID-23-CAT 265-#4903 5
XRNTDDREK19-Sakai SW354U-#0449 10
Total Equipment Hours: 25
R� '�-
Daily Time and Materials (T&M) Report
Date:2/20/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building in front of the GC's
trailer
Finished making the necessary cuts to re-establish the sub grade
- Continued hauling off the contaminated select material hauled off 2 loads
Survey came out to blue top the sub grade at the bottom of 12" select
Moisture conditioned the sub grade and compacted for testing
Terracon came out this afternoon to test the sub grade moisture/density tests failed due to low compaction
Imported select material 6 loads (101.25 tons)
T&M
Backhoe wloperator 10 hours
Skid steer w/operator 10 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD•Bryan Delgado 8 2 10
JUAN MORALES-Juan M Morales 8 2 10
Total Labor Hours: 20
Equipment Hours
BH-24-Cat 416 C4SX-#1580 10
SKID-23-CAT 265 -#4903 10
XRNTDDREK19 Sakai SW354U-#0449 10
Total Equipment Hours 30
Daily Time and Materials (T&M) Report
Date: 2/21/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building.in front of the GC's
trailer
Re-moisture conditioned the sub grade and compacted for testing.
Terracon came out this afternoon to test the subgrade moisture/density tests passed
The lab was supposed to be onsite this morning but failed to show up due to double booking the time slot we were setup for.
They did not get to the site to test until 4:00 p.m this afternoon
- Kept the crew onsite to keep moisture on the sub grade throughout the day and compact to assure that we got all of the tests
passed
T&M
Backhoe w/operator: 8 hours
Skid steer w/operator: 8 hours
Labor HOUrS OVE'IUMO Hours Total HO Urs
BRYAN DELGAD-Bryan Delgado 0 8 8
JUAN MORALES-Juan M Morales 0 8 8
Totai Labor Hours 16
Equipment Hours
BH-24-Cat 416 C4SX-#1580 8
SKID-23-CAT 265-#4903 8
XRNTDDREK19-Sakai SVV354U-#0449 8
Total Equipment Hours 24
Daily Time and Materials (T&M) Report
Date: 2/23/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building...in front of the GC's
trailer
Terracon came out Saturday afternoon around 4:30 p.m . all moisture/density tests in the sub grade passed
Proceeded with placing and processing the first 6" lift of select on the small piece of paving currently being reworked
-Terracon came out this afternoon around 3 00 p.m to test the first lift of select. .all moisture/density tests passed
Began placing and processing the second (final)6" lift of select...we will finish the final lift in the morning and have it tested
Imported select material: 2 loads(34.93 tons)
Survey is setup to be onsite first thing tomorrow morning to blue top the finished sub grade in the reworked section of paving
T&M
Backhoe w/operator: 10 hours
Skid steer w/operator: 10 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M Morales 8 2 10
T>t i' i at:,-i, 11 u,; S 20
Equipment HOO rs
BH-24-Cat 416 C4SX -#1580 10
SKID-23-CAT 265 #4903 10
XRNTDDREK19-Sakai SW354U-#0449 10
Total Equipment Hours 30
Daily Time and Materials (T&M) Report
Date: 2/24/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Finished re-working the small piece of remaining paving section to the south of the building in front of the GC's trailer
Finished placing and processing the second (final)6" lift of select
- Terracon came out this afternoon to test the second (final) lift of select all moisture/density tests passed
Imported select material 3 loads (47 83 tons)
Survey came out this morning to blue top the finished sub grade in the reworked section of paving
- Fine graded the finished select per the blue tops set by survey
This section of paving is 100% complete turned over to the concrete sub
T&M
Backhoe w/operator 10 hours
Skid steer w/operator 10 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M Morales 8 2 10
Total Labor Hours: 20
Equipment Mnu s
BH-24-Cat 416 C4SX-#1580 10
SKID-23-CAT 265-#4903 10
XRNTDDREKI9-Sakai SW354U #0449 10
Total Equipment Hours:30
1 C143)
Braun&Butler
CONSTRUCTION
City of Round Rock Fire Station 10
PR 15 Water Heaters
Date: 0410112026
Subject: PR 15 Water Heaters
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden,
Attached is pricing for the work outlined in PR-15 Water Heater Changes. This includes the water heaters
and additional electrical control circuits needed. This also includes the change to an aluminum ladder at
no cost.
-Plumbing-(2)60 gals in lieu of(1) 100 = $16,872.00
-Electrical-additional controls circuits $2,263.00
$19,135.00
Sincerely,
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 1 office(512)837.2882 1 fax(512)837-5115 I Braun-butler.com
HVAC - PLUMBING - UTILITIES - MED GAS - BACK FLOW TESTING
Texas Quality Services LLC Office: 512.243.5335
322 Southland Dr Fax: 512.243.6425
Burnet,TX 78611 4* info a texasqualityservices.com
SUBCONTRACTOR REQUEST FOR CHANGE ORDER
Date: 3/12/2026 Subcontractor C.O. #: 2
Project: Round Rock Firestatlon
General Contractor Braun-Butler
TQS Contact: Justin Stevens Phone: 512-715-0271
Description of Work or Discrepancy on Drawing:
This is per request to change 1- 100 gallon propane water heater to 2-60 gallon propane water heaters PLEASE NOTE The gas water heater schedule item
#2 states water heater shall be provided with factory supplied insulation blanket per manufactuere's specification This is not included as per A 0 Smith they
do not offer this on BTH models Please nate The below cost does include a credit for orginal water heater
Change Order Breakdown:
How many crews 1 How many hours 800 Cost per hour $55.00
How many plumbers 1 How many hours 8.00 Cost per hour $7500
Total Cost $1.040.00
Material
Item 2 60 gallon water heaters, venting and accessories Cost $23.99000
Total Material Cost $23.990.00
Credit 100 Gallon Water Heater Deduction Credit 59.692.00
Total Credit $9.69200
Subtotal $15,33800
Overhead 10% $1.53380
Total Change Order Request $16.871 80
The conditions hereinbefore referred to are as follows
. The aforementioned changes, and work affected thereby shall be performed under the same terms and conditions that are
included In the original contract unless stated otherwise
. This change order includes all materals, labor. tools equipment. supervision and related taxes necessary to perform the
above-mentioned work
Submitted by. Mike Stiles Title Project Manager Date 3/12/2026
Approved by Title Date
BJI,Inc.dba State Electrical Contractor No. 17161
B. 1. Electric Company Master License No. 24035
1509 Three Points Road Cell Phone: 512-845-9187
Pllugerville,TX 78660 Fax: 512-990-5567
email: jlilley�dbjelectric-inc.com
March 31,2026
Braun&Butler Construction
300 Hazelwood Street., Ste 100
Leander,Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-Chanee Proposal#16-PR 15
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on PR 13, drawings dated 12/19/2025. We propose to furnish
materials and labor for this change:
Scone:
Provide and install one switch and wiring to control light fixture at panel rack on
mezzanine.
Add two 120v circuits for added WH-2.
Provide and install additional disconnect switches and connection as shown.
Change Proposal.#16-Total Add: S2,263.00
Clarifications:
- This proposal is good for 30 days. After 30 days a new proposal will be required.
- BJ Electrical will NOT proceed with any chanee order without written approval.
Verbal direction on chane orders is not acceptable.
Exclusions
- Sales tax.
- Overtime
- Bond.
Please feel free to give me a call with any questions.
Jerry Lilley
Project Manager
,.. . __
� _...._.. ....— _. _ _ _._ _._._._.._____.. .__._. ____. _ _ Hwy •iaw iT
w
....� .,.
.:::
�.:-.r�