Contract - Braun & Butler Construction, Inc. - 6/11/2026 Page I of 2
Contract Quantity Adjustment/Change Order
ROUND ROLR i i -
rev,01/16
Department: General Services
Project Name: Fire Station#10 Date: 5/1/26
Change Order/Quantity
City Project ID Number FS10 Adjustment No. 1
Vendor Braun&Butler Construction Inc. 300 Hazelwood St. Ste. 100,Leander,Texas 78641 512-837-2882
Company Name Address Phone No.
Justification
Line Item#1:Backflow preventer(BFP)was included on Civil Drawings at time of bid.CORR Engineers directed for the BFP to be removed from Civil Drawings.A BFP is
required either outside the building or at the fire riser.A BFP was not accounted for and needed to be added at the riser to meet code. Line Item#2: During plan review
the City Electrical Inspector called out need for(8)AFCI breakers and tamper resistant receptacles.Line Item#3:CORR FD requested dual swing traffic doors for the
Bunker Gear Storage Room during design for FS11.They requested we incorporate this add into FS10.CORR FD requested that exterior station number on the watch
tower be back lit during design for FS11.They requested we incorporate this add into FS10.Line Item#4:CORR FD requested#10 sign be added to South Exterior Wall
(facing Old Settlers Blvd.). Due to this,we needed to change the exterior light fixture to also capture this.CORR FD requested that wall mounted oscillating fans be added
to Bunker Gear Storage room.Architect recommended that we do mounted locker tag name plates be added to all lockers in lieu of adhesive.This change will prevent
damage to cabinet veneer.Line Item#S: Due to access easement with shared drive with the neighboring Exxon Gas Station and the shared drive with the neighboridng
day care,it was determined that CORR would have to dictate sequencing of concrete drive tear up and replacement work.Due to sequencing this required that a portion
of sub grade work(South Drive)had to be reworked. Line Item#6:The 100 gallon water heater(WH)at FS1 recently had to be replaced.It was extremely difficult to
get this size of equipment replaced in the mezzanine with finished fall,access via ship ladder,etc.CORR Facilities requested that we switch to(2)60 gallon WHs in lieu of
a single 100 gallon WH.This change will also benefit the station because if one of the 60 gallon WH tanks were to go out,the station would still have another working 60
gallon WH to operate the station off of.
The$99,519.89 will replenish the Owner's Betterment Allowance.
SUMMARY Amount O/o Change
Original Contract Price: $9,149,947.00
Previous Quantity Adjustment(s):
This Quantity Adjustment: $0.00
Total Quantity Adjustment(s): $0.00
Total Contract Price with Quantity Adjustment(s): $9,149,947.00
0%
Previous Change Order(s):
This Change Order: $99,519.89 1%
Total Change Order(s)To Date: $99,519.89 1%
Adjusted Contract Price [Original Contract Price Plus Quantity
Adjustment(s)Plus Change Order(s)]: $9,249,466.89
Difference between Original and Adjusted Contract Prices: $99,519.89
Original Contract Time:
Time Adjustment by previous Quan.Adj./Change Order:
Time Adjustment by this Quan.Adj./Change Order:
New Contract Time: 0
Approvals ���
Contractor: o4- J Matt Harton, Senior Project Manager, Braun&Butler Construction, Inc. Zo
S'gna r Printed Name,Title,Company Date
City Representative: Hayden Schiller, Project Manager
ature Z Printed Name,Title Date
Mayor/City Manager Craig Morgan, Mayor —1I- ue
�Ignfititre Printed Name,Title Date
— Zo2�- f58
Page 2 of 2
Project Name: Fire Station#10
Quan.Adj./Change Order No.: 1
Chan a Order Data
Contract
Time Adjustment
(Days)
Item# Item Description Unit Qty. Unit Price Amount
deto iser Due to Vault Removed
1 from Civil Drawings After Bid LS 1 $17,635.25 $17,635.25
Added AFCI Breakers,Tamper Resistant
2 Receptacles per City Inspector LS 1 $8,653.00 $8,653.00
3 Traffic Doors&Exterior#10 Station Sign LS 1 $15,257.00 $15,257.00
xtenor ig t fixture,Bunker Fans,Locker
4 Tags LS 1 $9,915.53 $9,915.53
5 South Drive Sub Grade-Rework LS 1 $28,924.11 $28,924.11
6 Water Heater Change-(2)60 gallon WHs LS 1 $19,135.00 $19,135.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS: $99,519.89 0
Braun&Butler
CONSTRUCTION
City of Round Rock Fire Station 10
Allowance Adds — Fire Sprinkler Backflow and Additional Gate
Date: 0413012026
Subject: Allowance Adds
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden,
Attached is pricing for the work to install an RPZ Backflow Preventer on the fire sprinkler riser and to install an
additional sliding gate and operator at the parking area... If approved,please sign this page and issue a field
change order contingency charge approval in the amount of$41,523.35
- RPZ Backflow on Fire Riser $17,635.25
Sliding Gate and Operator $23,888.10
Total $41,523.35
Sincerely,
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 1 office(512)837.2882 1 fax(512)837-5115 I braun-butler.com
r
itol
Capitol Sprinkler and Fire Systems LLC
Ca
1750 County Road 269, Suite l3
Leander, TX 78641
Sprinkler & Fire Systems (512)960-2628
REQUEST FOR CHANGE ORDER
W-1474 DG 001
Braun & Butler Re: 0
0 0
0 0
Attn: Matt Harton 0
Description of additional work: Add 8" backflow preventer to riser room. Backflow to be 8"to make sure
hydraulics calc safety factor is not reduced from original. Redesign and resubmit plans
LOG DESC. I New backflow preventer inside riser room
We are requesting a Change Order to be added to the original contract amount of the above referenced project. Pending approval,we
will perform additional items that were not included in the original scope of work.
Description Units Unit Price Total
Labor 24.00 $85.00 $2,040.00
Project Management 2.00 $105.00 $210.00
Material 1.00 $11,680.00 $11,680.00
Equipment Rental 0.00 $501.82 $0.00
Design 8.00 $105.00 1 $840.00
Permit 1.00 $500.00 1 $500.00
Misc 1.00 $65.00 $65.00
$0.00
Sub-Total $15,335.00
15% OH&P $2,300.25
Taxes 8.25%
Total $17,635.25
Please call if you have any questions.
Thank you for your assistance,
Authorized by:�
Print Name
Mike I Project Manager Date.
Braun&Butler
CONSTRUCTION
City of Round Rock Fire Station 10
PR 06 Site Elect Revs, Extractor Change, Baby Box
Date: 04/0112026
Subject: PR 06 Site Elect Revs, Extractor Change, Baby Box
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden„
Attached is pricing for the work outlined in PR-06.. The extractor change was rejected by the FD. We are staying
with original specified extractor. No pricing for the extractor included in this proposal.
-Electrical—additional controls circuits $7,573.00
-Baby Box install labor. $1.080.00
$8,653.00
Sincerely,
Ad 4:4`_
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 I office(512)837-2882 1 fax(512)837-5115 I braun-butler.com
111,Inc.dba State Electrical Contractor No. 17161
B. 1. Electric Company Master License No. 24035
1509 Three Points Road Phone: 512-990-5500
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley@bjelectric-inc.com
January 28, 2026
Braun&Butler Construction
300 Hazelwood Street., Ste 100
Leander, Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-Chancre Proposal#12—PR 06
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on drawings dated 8/01/2025. We propose to furnish materials and
labor for this change:
Scope:
— Provide and install conduit and wiring for one added`B"fixture.
— Provide and install added`B"fixture.
— Provide and install(8)AFCI breakers as shown.
— Change receptacles in Dorm rooms to Tamper Resistant.
Change Proposal#12—Total Add: $7,573.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any chanlie order without written approval.
Verbal direction on chance orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
Please feel free to give me a call with any questions.
Jerry Lilley
Project Manager
1/28/2026 12:46:23 PM Paye 1
Round Rock FS:PR O6
Job Number:CO822-8
Bid Summary:Default
Extension By Phase
Item# Description Quantity Price U Ext Price Labor Hr U Ext Lab Hr
---02 Underground Branch Raceway---
1183 1"PVC Conduit 15 8119 C 1202. 227 C 0.34
2076 1"PVC Male Adaptor 2 89.39 C 1.79 0.08 E 0.16
2130 1"PVC Coupling 5 70.82 C 3.88 0.05 E 027
---02 Underground Branch Raceway Total- 17.69 0.77
---04 Above Ground Branch Raceway---
1345 1"GRC Elbow 4 2.036.12 C 81.44 0.47 E 1.88
1596 1"Locknut 2 75.39 C 1.51 0.10 E 0.20
--04 Above Ground Branch Raceway Total- 82.95 2.08
---05 Feeder Wire---
2662 #8 THHN CU Stranded Wire 60 875.58 M 52.20 8.13 M 0.48
---05 Feeder Wire Total--- 5220 0.48
---06 Brach Wre---
2682 #10 THHN CU Solid Wire 16 517.53 M 8.05 8.13 M 0.13
---06 Brach Wire Total--- 8.05 013
---07 Switchgear---
4115 20A 1P Bolt-On Circuit Breaker 8 QUOTE 2 0.00 0.52 E 4.16
---07 Switchgear Total--- 0.00 4.16
---08 Lighting---
22078 L.E.D..Bollard Fixture 1 QUOTE 1 0.00 5.98 E 5.98
---08 Lighting Total--- 0.00 5.98
---09 Trim---
4703 20A/125V Spec Grade Dup Rcpt(5-20R) -60 3.04 E -182.40 0.33 E -19.80
47061 20A/1 25V Tamper Resistant Decora Rcpt(5-20R) 60 9.85 E 591.00 0.33 E 1980
--09 Trim Total- 408.60 0.00
Job Total 569.49 13.60
•Target,Labor column 2
1/28/2026 12:47:42 PM Page 1
Round Rock FS: PR 06
Totals(Summary)-Bid Summary: Default
Material
Non-Quoted $569.49
Quotes 4,426.00
Sales Tax(0.00%) 0.00
Total Material $4,995.49
Labor
Direct(13.60 hours @$65.00) $884.00
Non-Productive Labor 88.40
Total Labor (13.60 hours) $972.40
Direct Job Expenses $470.36
Tools and Miscellaneous Materials 146.99
Subcontracts 0.00
Job Subtotal(Prime Cost) $6,585.24
Overhead(0.00%) 0.00
Profit(15.00%) 987.79
Job Total $7,573.03
Actual Bid Price $7,573.03
Material to Direct Labor ratio: 0.85
Prime Cost per square foot $0.47
Job Total per square foot $0.54
Actual Bid Price per square ft $0.54
Labor cost per square foot $0.07
Labor hours per square foot 0.00
Gross Profit% 13.04
Gross Profit$ $987.79
Net Profit% 13.04
B&L Construction CHANGE ORDER PROPOSAL # 3
39 Fairview Dr. Prepared by
Round Rock, TX 78665-9428
OFFICE# 248-0772 FAX#248-0786
*Metal stud framing *Drywall *Acoustical Ceilings
GENERAL CONTRACTOR: Braun& Butler Construction ATTENTION : Matt
PROJECT: City of Round Rock Fire Station No.10 DATE : 4/1/26
1) PR#6
Labor to install owner supplied baby box S 1,080.00
TOTAL AMOUNT OF CHANGE ORDER S 1,080.00
EXCLUSIONS AND QUALIFICATIONS
1) Emailed copy to serve as the original
2) Sales tax excluded on all materials.
1 C_43>
Braun&Butler
CONSTRUCTION
City of Round Rock Fire Station 10
PR 13
Date: 0410112026
Subject: PR 13 Traffic Doors, Hardware, Signage, Electrical, Light Fixtures
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden„
Attached is pricing for the work outlined in PR-13.. This includes the traffic doors, signage change,electrical
changes,and lighting fixture change.
-Traffic doors and HM Frame change(materials) $8247.00
-Signage changes $2945.00
-Electrical— $4065,00
$15,257.00
Sincerely,
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 I office(512)837-2882 1 fax(512)837-5115 I braun-butler.com
ELECTRONIC
LAFORCEOw SECURITYSYSTEMS
powered by LAFORCE
Email Quote
Date: March 20,2026 Total Pages: 1
To: Matt Harton From: McKenzie Johnson
Company: Braun&Butler Phone: (920)490-2368
(800)672-6795 ext. 236801
E-mail: mckenzie.johnsonnu,laforceinc.com
Re: Double Acting Doors
City of Round Rock Fire Station #10
LaForce Joh#: 50507
Matt,
Please see below for the cost impact to add the traffic doors and frames from PR 10 to the City of
Round Rock Fire Station#10 project.
Double Actine Doors
• ADD (2)3'0" W x 7'-8"H Traffic Doors
o Honeycomb Polymer Core with ABS Face
o Color: Red
o Window: 16"x 16"
o 36"H Stainless Steel Plates(Front&Back)
• ADD (2) Steel Frames
o Welded
COST IMPACT (ADD) $8,247 (no tax)
Once approval is received and all information is gathered,the materials can be ordered. Until
approval is received, materials will not be ordered. For accounting purposes,adjust your contract
order with LaForce.
If you have any questions,please contact us.
Sincerely, --�••__ ,,__,A� Authorized by:
J �v Company name:
Date:
McKenzie Johnson
Division 10 Project Manager
LaForce
This quote is subject to prompt acceptance within 30 calendar days from the date of this quote first noted above.
If not accepted by that date it may be withdrawn or modified by LaForce.
1.800.236.8858 • www.laforceine.com
Executive Signs Enterprises,Inc. Proposal
5621 Central Texas Dr.San Marcos,TX 78666
Phone(512)292-9936 Due to material volatility,quotes are only valid for 30 days.
Phone(210)492-9436
RIMEFax(210)492-9483
www.executivesigns.com ACCOUNT REP E-MAIL
TSCL#18330 Kacey Brewer kacey@executivesi ns.com
PROPOSAL SUBMITTED TO PHONE FAX DATE
Braun & Butler Aril 1, 2026
STREET CONTACT E-MAIL
CITY,STATE,ZIP CODE JOB LOCATION
CORR FS10
EXECUTIVE SIGNS ENTERPRISES, INC.WILL FURNISH THE FOLLOWING:
ST-9 Produce and install (1) T-3/4""10"front lit and back lit set of channel letters. Channel letter faces will
be white with red translucent vinyl, in order to back light in white they cannot be red acrylic. Letter returns are a
standard painted with uv clear coat.
Additional permit at cost from the city could be needed or this one set. Not sure until we submit all for permitting.
permitting.
50%draw required for samples and to begin production.
—Progress payments will be requested if the sign is ready to install and we are waiting on the client to schedule installation—
WE PROPOSE HEREBY TO FURNISH MATERIAL AND LABOR COMPLETE IN ACCORDANCE WITH
THE ABOVE SPECIFICATIONS,FOR THE SUM OF:
DOLLARS $2,945.00 SUBTOTAL
TAX
$2,945.00 TOTAL
PAYMENT TO BE MADE AS FOLLOWS:
50%when contract is signed and the remainder when the job is complete
Signs permit(s)if required will be added to the final invoice at the actual cost of the permit(s)plus$200.00 for administration time. Cost of
Structural Engineering,if required,will also be added to the Final Invoice.
THE ABOVE PRICING IS BASED ON MAUFACTURING FOR 120 VOLT ELECTRICAL POWER, CUSTOMER IS RESPONSIBLE FOR PROVIDING
ELECTRICAL POWER TO THE SIGN LOCATION,AS WELL AS,ANY TIME CLOCK OR OTHER LIGHTING CONTROL. PER NATIONAL AND
ORDINANCE,A DEDICATED CIRCUIT,INCLUDING NEUTRAL WIRE WITH GROUND IS REQUIRED FOR ALL SIGN LOCATIONS. COSTS INCURRED
FROM ROCK OR OTHER OBSTRUCTIONS DURING EXCAVATION OR DRILLING OF THE STRUCTURAL FOUNDATIONS WILL BECOME AN EXTRA
CHARGE AND APPLIED TO THE FINAL INVOICE. THE PURCHASER AGREES TO ACCEPT RESPONSIBILITY FOR ANY DAMAGES INCURRED
BENEATH THE SURFACE WHERE DRILLING OR EXCAVATION IS REQUIRED.
THIS PROPOSAL IS SUBJECT TO YOU PROVIDING LANDLORD OR OWNERS APPROVAL,AND A SIGN PERMIT FROM THE CITY. NO WORK WILL
BE STARTED UNTIL A PERMIT HAS BEEN RECEIVED. WE WILL NEED YOUR C OF O TO EXPEDITE THIS.
ALL MATERIALS ARE GUARANTEED TO BE AS SPECIFIED,AND THE ABOVE WORK IS TO BE PERFORMED IN ACCORDANCE WITH CUSTOMER
APPROVED DRAWINGS AND COMPLETED IN A SUBSTANTIAL WORKMANLIKE MANNER. ANY ALTERATIONS OR DEVIATION FROM THE ABOVE
SPECIFICATIONS INVOLVING EXTRA COSTS WILL BE EXECUTED ONLY UPON WRITTEN ORDERS,AND WILL BECOME AN EXTRA CHARGE
OVER AND ABOVE THE ESTIMATE. ALL AGREEMENTS ARE CONTINGENT UPON STRIKES OR DELAYS BEYOND OUR CONTROL.ALL MATERIAL
PROVIDED REMAIN THE PROPERTY OF EXECUTIVE SIGNS ENTERPRISES,INC.,UNTIL CONTRACT AMOUNT IS PAID IN FULL. ALL SUMS DUE
EXECUTIVE SIGNS ENTERPRISES,INC.UNDER THIS CONTRACT SHALL BE DUE AND PAYABLE AT 5621 CENTRAL TEXAS DR.SAN MARCOS,TX
78666. ANY AND ALL ACTION TO ENFORCE,INTERPRET,OR OTHERWISE ADJUDICATE THE RIGHTS OF THE PARTIES HERTO SHALL BE
BROUGHT ONLY IN HAYS COUNTY,TEXAS.
ACCEPTANCE OF PROPOSAL--THE ABOVE PRICE SPECIFICATIONS AND CONDITIONS ARE SATISFACTORY AND ARE HEREBY ACCEPTED.
YOU ARE AUTHORIZED TO DO THE WORK AS SPECIFIED.PAYMENT WILL BE MADE AS OUTLINED ABOVE. THIS PROPOSAL MAY BE
WITHDRAWN IF NOT ACCEPTED IN 30 DAYS
AUTHORIZED EXECUTIVE
SIGNATURE SIGNS
BY: BY:
DATE: DATE:
Electrical Sign Contractor License#: 18330
Regulated by the Texas Department of Licensing and Regulation PO Box 12157,Austin, TX 78711, 1-800-803-9202,
512-463-6599;www.license.state.tx.us/complaints
1111, Inc.dba State Electrical Contractor No. 17161
B. 1. Electric Company Master License No. 24035
1509 Three Points Road Cell Phone: 512-845-9187
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley@bjelectric-inc.com
February 5, 2026
Braun&Butler Construction
300 Hazelwood Street., Ste 100
Leander, Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-Chanee Proposal#10-PR 13
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on PR 13, drawings dated 11/18/2025. We propose to furnish
materials and labor for this change:
Scope:
- Provide and install one type N fixture in room 138.
Add one dimmer switch for this N fixture.
- Change type H4 fixtures, in room 112, from(6) individual fixtures to one continuous row
fixture.
- Make multiple lighting controls zone changes.
Change Proposal#10—Total Add: $4,065.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any chance order without written approval.
Verbal direction on chance orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
Please feel free to give me a call with any questions.
Jerry Lilley
Project Manager
HC AUSTIN TX(1501) Quote
4801 Freidrich Ln WES-020526-344
Austin,TX 78744
Electrical Solutions
Job Name: CORR FIRE STATION 10 PR13 ADDER Quote Date: Feb 05, 2026
Expires: Mar 07, 2026
To:BJI INC dba B1 ELECTRIC From:JOANN PIGNATARO
Email:joann.pignataro@wescodist.com
PRICESUPPLIER LINE 4 QTY TYPE MFR PART NUMBER UNIT
-6 H4 LUMENWERX ALC-APO-LED-80-550-35-2FT-
UNV-DI-1-COVH-W
1 H4 LUMENWERX ALC-APO-LED-80-550-35-
24FT-UNV-DI-1-COVH-W
SUBTOTAL ADDER FOR ABOVE
CHANGE FROM(6)2FT
SECTIONS TO(1)24FT $850.00
SECTION
ESSF0604U9527930WWF1 ED
1 N VC-ARCH ESPR06024010120-277 $750.00 $750.00
Notes:QUOTING 95" FIXTURE-
CLOSEST TO 8FT LENGTH
1 CONTROLS COOPER CONTROLS WW3-RL $95.00 $95.00
NOTES
FREIGHT IS ADDITIONAL
TOTALGRAND •0
Pricing&Estimated Ship Dates(ESD)and Lead Times provided for all manufacturers are subject to change without notice.
Prices do not include sales tax
BY ACCEPTING THIS QUOTE,YOU AGREE THAT THE WESCO TERMS AND CONDITIONS OF SALE PUBLISHED AT
WWW.WESCO.COM/TERMSOFSALE ARE EXPRESSLY INCORPORATED INTO AND SHALL GOVERN THIS TRANSACTION.
WESCO MAY ASSESS STORAGE AND TRANSPORTATION FEES IF YOU DO NOT TAKE OR ACCEPT DELIVERY WITHIN 45 DAYS OF
PRODUCT AVAILABILITY.WESCO MAY ALSO UPDATE THIS QUOTE OR PRICING ABOVE DUE TO CHANGES IN DUTIES,FREIGHT,TARIFFS,
SUPPLIER PRICING,SURCHARGES,COMMODITY AND METAL ADJUSTMENTS,OR EXCHANGE RATE FLUCTUATIONS.
PRICING IS VALID FOR 24 HOURS.PRICES MAY BE SUBJECT TO METAL ADJUSTMENTS BASED ON PO ISSUANCE AND RELEASE(S).
JOANN PIGNATARO
Wesco Distribution,Inc.
Page 1/1
2/5/2026 11:44:09 AM Page I
Round Rock FS:RR FS#10-PR 13
Job Number:CO822-7
Bid Summary:Default
Extension By Phase
Item# Description Quantity Price U Ext Price Labor Hr U Ext Lab Hr-
---04 Above Ground Branch Raceway---
2425 1/2"T-Bar Wire Conduit Clip 1 106.19 C 1.06 0.08 E 008
2469 4"Square Box(1/2&3/4 KO's) 1 282.96 C 2.83 0.23 E 023
2470 4"Square x 1-1/2"Deep Box w/bkt(1/2&3/4 KO's) 1 539.51 C 5.40 0.26 E 026
2858 3/8"MCBX Connector 2 50.67 C 1.01 0.07 E 0.14
4897 4"Square-1G Plaster Ring-5/8"D 1 670.83 C 6.71 0.09 E 009
6133 Red V'Arenuts 9 192.45 M 1.73 2.27 C 0.21
---04 Above Ground Branch Raceway Total--- 18.74 1 01
---06 Brach Wre--
2801 122 Aluminum Clad MC Cable Solid 15 1,041.87 M 15.63 14.30 M 0.21
---06 Brach Wire Total--- 1563 0.21
--08 Lighting---
5257 Seismic wire 4 3.00 E 1200. 0.04 E 0.16
5294 Manufactured Fixture Whip(14/3) 1 633 E 633 020 E 0.20
5300 Flexible Conduit Hanger(Caddy KX) 3 129.66 C 3.89 005 E 0.15
48628 Ceiling/Surface Mtd.L D Fixture 1 QUOTE 1 000 1 95 E 1 95
62884 30'Recessed Linear LED 1 QUOTE 1 0.00 15.60 E 15.60
---08 Lighting Total--- 2222 1806
---09 Trim--
5079 4"Square Flat Blank Cover 1 330.71 C 3.31 0.09 E 0.09
62695 1 Relay On/Off 0-10V Dimming Room Controller 1 QUOTE 11 0.00 0.25 E 025
--09 Trim Total-- 3.31 0.34
---10 Voice/Data/Video-
2933 Plenum Cat 5e 24gauge 4pair 40 511.01 M 2044 11 50 M 0.46
---10 Voice/Data/Video Total--- 2044 0.46
Job Total 8034 2008
Target,Labor column 2
2/5/2026 11:56:09 AM Page 1
Round Rock FS: RR FS#10-PR 13
Totals(Summary)-Bid Summary: Default
Material
Non-Quoted $80.34
Quotes 1,695.00
Sales Tax(0.00%) 0.00
Total Material $1,775.34
Labor
Direct(20.08 hours @$65.00) $1,305.20
Non-Productive Labor 130.52
Total Labor (20.08 hours) $1,435.72
Direct Job Expenses $24644
Tools and Miscellaneous Materials 77.01
Subcontracts 0.00
Job Subtotal(Prime Cost) $3,534.51
Overhead(0.00%) 0.00
Profit(15.00%) 530.18
Job Total $4,064.69
Actual Bid Price $4,064.69
Material to Direct Labor ratio: 0.58
Prime Cost per square foot $0.25
Job Total per square foot $0.29
Actual Bid Price per square ft $0.29
Labor cost per square foot $0.10
Labor hours per square foot 0.00
Gross Profit% 13.04
Gross Profit S $530.18
Net Profit% 13.04
�$3
Braun&Butler
CONSTAuc:i c
City of Round Rock Fire Station 10
PR 12
Date: 0410112026
Subject: PR 12 — Wall fans, strip lighting, name tags, alerting strobe, hardware, signage
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden„
Attached is pricing for the work outlined in PR-12.. This includes the fans, name tags, alerting strobe,hardware,
signage,electrical light fixture revisions costs.
-Fans and strip lighting Electrical $5851.00
-Signage changes $634.00
-Added Alerting strobe in Fitness $920.53
-Millwork locker tags $1904.00
$9,309.53
Sincerely,
_, tv,IALX�-
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 1 office(512)837-2882 1 fax(512)837-5115 braun-butler.com
Bll,Inc.No State Electrical Contractor No. 17161
B. 1. Electric Company Master License No. 24035
1509 Three Points Road Phone: 512-990-5500
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley@bjelectric-inc.com
January 27,2026
Braun&Butler Construction
300 Hazelwood Street., Ste 100
Leander, Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station #10-Change Proposal #8—PR 12
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on drawings dated 10/24/2025. We propose to furnish materials and
labor for this change:
Scope:
— Provide and install conduit and wiring for three added wall fans.
— Provide and install three model#WB292451 wall fans.
— Relocate three type N1 fixtures in corridor.
— Add rough-in only for added strobe in Fitness 149.
— All rough-in to be surface mount on CMU,unless CMU cut and patch by others.
Change Proposal#08—Total Add: $5,851.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any change order without written approval.
Verbal direction on change orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
— Any cut and patch of CMU walls.
— Any fishing down CMU walls.
Please feel free to give me a call with any questions.
Jerry Lilley—Project Manager
Q�j��, Quotation
HILL COUNTRY ELECTRIC SUPPLY QUOTE DATE QUOTE NUMBER
.�i 4801 FREIDRICH LANE
BLDG 2 STE 200 01/20/2026 S102870708
AUSTIN,TX 78744
512-428-9300 HILL COUNTRY ELECTRIC SUPPLY PAGE NO.
Electric Supply Fax 512-428-9830 BLD FRSTE 20H LANE
BLDG 2 STE 200
512-428-9300 AUSTIN TX 8744 1 of 1
Fax 512-428-9830
QUOTE TO. SHIP TO:
BJI INC dba BJ ELECTRIC BJI, INC dba BJ ELECTRIC-SHOP
1509 THREE POINTS ROAD SHOP
PFLUGERVILLE TX 78660 1509 THREE POINTS RD.
PFLUGERVILLE, TX 78660
CUSTOMER NUMBER CUSTOMER PO NUMBER JOB NAME/RELEASE NUMBER SALESPERSON
2682 BLAKE CHANCE
WRITER SHIP VIA TERMS SHIP DATE FREIGHT ALLOWED
Randon Grametbaur NORTH ROUTE 2% 10th Net 25th 02/06/2026 No
ORDER QTY DESCRIPTION UNIT PRICE EXT PRICE
3ea VVB292451 455.947/ea 1367.84
BLOBAL INDUSTRIAL 30" OUTDOOR
RATED FAN 2 SPEED 8,400 CFM, 3/10HP
""STOCK IN TEXAS
3-4 DAY LEAD TIME
CONDITIONS OF SALE PUBLISHED AT WWW.WESCO COM/TERMSOFSALE ARE
EXPRESSLY INCORPORATED INTO AND SHALL GOVERN THIS TRANSACTION.Wesco Subtotal 1367.84
may assess storage and transportation fees if you do not take or
accept delivery within 45 days oarf product availability.Wesco may S&H Charges 0.00
also update this quote or pricing above due to changes in duties, g
freight,tariffs,supplier pricing,surcharges,commodity and metal
adjustmentsor exchange rate Fluctuations.
Pricing is valid for 24 hours.Prices may be subject to metal
adjustments based on PO issuance and release(s) Amount Due 1367.84
Printed By.RANGRA on 1/20/2026 124259 PM
1/27/202612:21:37 PM Page 1
Round Rock FS:RR FS#10-PR#12
Job Number:CO822-6
Bid Summary:Default
Extension By Phase
Kem N Description Quantity Price U Ext Price Labor Hr U Ext Lab Hr
---04 Above Ground Branch Raceway---
1001 3/4"EMT 190 130.61 C 247.62 7.15 C 1356
1465 3/4"Set Screw Steel Insul Throat Conn 10 109.13 C 10.91 0.08 E 080
1515 3/4"Comp Steel Insul Throat Conn 24 0.57 E 13.68 0.17 E 4.08
1545 3/4"Set Screw Steel Cplg 19 103.95 C 19.71 0.08 E 1.52
2423 3/4"Metal Stud Conduit Clip 24 423.52 C 103.02 5.53 C 1 35
2469 4"Square Box(1/2&3/4 KO's) 5 282.96 C 14.15 0.23 E 1.15
2471 4"Square x 2-1/8"Deep Box(1/2&3/4 KO's) 2 321.91 C 6.44 0.23 E 0.46
2479 1G WP Bell Box-(3)1/2"Hubs 5 1,112.05 C 55.60 0.65 E 3.25
4901 4"Square-2G Plaster Ring-1/2"D 1 255.98 C 2.56 0.09 E 0.09
6133 Red Wirenuts 35 192.44 M 6.74 2.28 C 0.80
---04 Above Ground Branch Raceway Total--- 480.43 27.06
---06 Brach Wire--
2660 #12 THHN CU Stranded Wire 546 304.87 M 166.44 7.15 M 3.90
---06 Brach Wire Total--- 16644 3.90
---09 Trim---
4703 20AI125V Spec Grade Dup Rcpt(5-20R) 5 9.75 E 48.75 0.33 E 1 65
5059 1G WP In Use Cover 4 16.50 E 66.00 0.16 E 0.64
5061 1G WP In Use GFI Cover(Vertical) 1 16.50 E 16.50 0.16 E 0.16
5080 4"Square Flat Blank Cover w/KO 5 355.40 C 17.77 0.09 E 0.45
--09 Trim Total-- 149.02 2.90
-18 Misc.--
T0001 FAN MODEL#WB292451 1 QUOTE 13 0.00 2.60 E 2.60
T0002 FAN MODEL#WB292451 2 QUOTE 13 0.00 2.60 E 5.20
---18 Misc.Total--- 0.00 7.80
Job Total 795.89 41.66
Target,Labor column 2
1/27/2026 1:16:23 PM Page 1
Round Rock FS: RR FS#10-PR#12
Totals(Summary)-Bid Summary: Default
Material
Non-Quoted $795.89
Quotes 1,368.00
Sales Tax(0.00%) 0.00
Total Material $2,163.89
Labor
Direct(41.66 hours @$65.00) $2,707.90
Non-Productive Labor 216.39
Total Labor (41.66 hours) $2,924.29
Direct Job Expenses $0.00
Tools and Miscellaneous Materials 0.00
Subcontracts 0.00
Job Subtotal(Prime Cost) $5,088.18
Overhead(0.00%) 0.00
Profit(15.00%) 763.23
Job Total $5.851.41
Actual Bid Price $5,851.41
Material to Direct Labor ratio: 0.44
Prime Cost per square foot $0.36
Job Total per square foot $0.42
Actual Bid Price per square ft $0.42
Labor cost per square foot $0.21
Labor hours per square foot 0.00
Gross Profit% 13.04
Gross Profit$ $763.23
Net Profit% 13.04
rA
0A 1p,
Date: 3/16/26
To: Braun & Butler
From: Kacey Brewer
Re: City of Round Rock Fire Station #10
Please accept this as our proposal to do the following:
Produce and install-
ST-13 Locker Tags— (6) ADA SIGN - 10 x 2 x 0.063 SUBSTRATE (321-601) - ADA Alternative - RED/
APPLIQUE (311-304) - ADA Alternative - SILVER DIGITALLY PRINT LOGO NO Braille. NO ADHESIVE,
STRAIGHT EDGES, SQUARE CORNERS 5
636-10-S - 10" X 2" SILVER SLIDE-IN WALL HOLDER $554
Fuel/Trip- $80
Total: $634
50% DRAW REQUIRED TO PURCHASE MATERIALS AND BEGIN PRODUCTION. ANY ADDITIONAL
TRIPS WILL BE ADDITIONAL. QUOTE VALID FOR 15 DAYS.
Executive Signs, Enterprises Inc. Approved
By Kacey Brewer By
Electrical Sign Contractor License#: 18330
Regulated by the Texas Department of Licensing and Regulation PO Box 12157, Austin, TX 78711
1-800-803-9202, 512-463-6599, www.license.state.tx.us/complaints
Executive Signs Enterprises, Inc. 5621 Central Texas Dr San Marcos,Texas 78666 (210)492-9436 Fax(210)492-9483
Custom systems Designs Inc . Estimate
**' CSDI •
Date Estimate#
1108 Sherwood Dr. Canyon Lake,TX 78133 3/31/2026 4460
Customers Name/Address
Braun&Butler Construction.Inc.
300 Hazelwood St.,Ste. 100
Leander.Texas 78641
Terms Rep Project
Due on receipt GSV Fire Station 10
Item Description Qty Cost Total
Round Rock Texas New Construction Fire Station 10
USDD STR-2 USDD G2 Strobe Light/Red LED 1 635.53 635.53
Labor Installation of additional G2 strobe light in Fitness Room 149 1 285.00 285.00
Subtotal $920.53
ALL INVOICES ARE SUBJECT TO 1 1/2%INTEREST Cl IARGF, PER MON11I Sales Tax (0.0%) $0.00
IF NOT PAID WITHIN TERMS
Total $920.53
Custom Systems Design, Inc.
Phone# Fax# Contact:George Vigue Web Site
210-363-6800 george.ri csdisa.com www.csdisa.com
TRAVIS CAP Number: 1
MILLWORK
Project: Round Rock Fire Station No.10 Date Sent: 3/12/2026
Location: 4400 E.Old Settlers Blvd.
Round Rock,TX
78665
Detail Ref. Repeats Scope/Description
Name Plate Holder 29 Supply and attached 2x10 name plate holder to locker doors.Name plate to be provided by others.
CAP Total: $1,904.00
The following are Qualifications to our bid:
Pricing on this CAP is valid for 15 calendar days from day sent.
Schedule of additional work provided in this CAP may fall outside original project schedule.
Matthew Williamson
Senior Estimator
Travis Millwork
(512)272-WOOD(9663)
matt.wi II iamson Ptraviscomoan ies.com
CHAMPION SITE PREP
63O 1 N INTERSTATE 35
GEORGETOWN,TX 78633
OFFICE(51 2)863-3453/FAX l51 21863-3463
ADDITIONAL WORK / CHANGE AUTHORIZATION
BRANDONO.1 DI GDI RT.COM
CITY OF ROUND ROCK FIRE STATION 10/T&M PER ATTACHED REPORTS
DATE: 03/12/26 JOB NAME: CORR FIRE STATION 10
TO: BRAUN&BUTLER CONSTRUCTION ESTIMATOR: BT
ATTN: MATT HARTON LOCATION: ROUND ROCK
DESCRIPTION QTY UNIT RATE
1. BH-24 W/OPERATOR 53 HR $148.00 $7,844.00
2. SKID-23 W/OPERATOR 48 HR $131.00 $6,288.00
3. XRNTDOREK-19 W/OPERATOR 53 HR $123.00 $6,519.00
4. HAUL OFF 14 LOA $128.00 $1,792.00
S. SELECT FILL IMPORT 183 TON $14.80 $2,708.40
SUBTOTAL: $25,151.40
OH/P 15% $3,772.71 $3,772.71
TOTAL: $28,924.11
Description of Work:PRICING ABOVE FOR T&M WORK COMPLETED PER ATTACHED SIGNED REPORTS.
The scope items above include items not part of overhead including:FUEL,OIL,GREASE,
MAINTENANCE,INSURANCE,SMALL TOOLS,LIGHT TRUCKS,SURVEY/CAD EQUIPMENT,AND
OVERTIME IF APPLICABLE.
NOTE: Pricing per GC REQUEST.Scope not listed above is not included.Price is valid for 30 days.
ACCEPTANCE OF PROPOSAL-The above prices,specifications and conditions are satisfactory and are hereby accepted.
AUTHORIZED SIGNATURE DATE OF ACCEPTANCE
Page 1 of 1
Daily Time and Materials (T&M) Report
Date: 2/18/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Began re-working/excavating the small piece of remaining paving section to the south of the building...in front of the GC's trailer
Began making the necessary cuts to re-establish the sub grade...stockpiled material to be hauled off tomorrow
T&M
Backhoe w/operator: 5 hours
Skid steer w/operator: 5 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 3 2 5
JUAN MORALES-Juan M. Morales 3 2 5
Total Labor Hours: 10
Equipment Hours
BH-24-Cat 416 C4SX-#1580 5
SKID-23-CAT 265-#4903 5
XRNTDDREK19-Sakai SW354U-#0449 5
Total Equipment Hours: 15
Rc ��-
Daily Time and Materials (T&M) Report
Date: 2/19/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building...in front of the GC's
trailer
Continued making the necessary cuts to re-establish the sub grade...
- Began hauling off the contaminated select material... hauled off 12 loads
T&M
Backhoe w/operator: 10 hours
Skid steer w/operator: 5 hours
L.ahor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M. Morales 3 2 5
Total Labor Hours: 15
Equipment Hours
BH-24-Cat 416 C4SX-#1580 10
SKID-23-CAT 265-#4903 5
XRNTDDREKI9-Sakai SW354U-#0449 10
Total Equipment Hours: 25
� 0----
Daily Time and Materials (T&M) Report
Date: 2/20/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building...in front of the GC's
trailer
Finished making the necessary cuts to re-establish the sub grade...
- Continued hauling off the contaminated select material... hauled off 2 loads
Survey came out to blue top the sub grade at the bottom of 12" select...
Moisture conditioned the sub grade and compacted for testing...
Terracon came out this afternoon to test the sub grade...moisture/density tests failed due to low compaction
Imported select material: 6 loads (101.25 tons)
T&M
Backhoe w/operator: 10 hours
Skid steer w/operator: 10 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M. Morales 8 2 10
Total Labor Hours: 20
Equipment Hours
BH-24-Cat 416 C4SX-#1580 10
SKID-23-CAT 265-#4903 10
XRNTDDREKI9-Sakai SW354U-#0449 10
Total Equipment Hours:30
Daily Time and Materials (T&M) Report
Date: 2/21/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building.in front of the GC's
trailer
Re-moisture conditioned the sub grade and compacted for testing.
Terracon came out this afternoon to test the subgrade. moisture/density tests passed
-The lab was supposed to be onsite this morning but failed to show up due to double booking the time slot we were setup for.
They did not get to the site to test until 4:00 p.m this afternoon
- Kept the crew onsite to keep moisture on the sub grade throughout the day and compact to assure that we got all of the tests
passed
T&M
Backhoe w/operator: 8 hours
Skid steer w/operator: 8 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 0 8 8
JUAN MORALES-Juan M. Morales 0 8 8
Total Labor Hours: 16
Equipment Hours
BH-24-Cat 416 C4SX-#1580 8
SKID-23-CAT 265-#4903 8
XRNTDDREK19-Sakai SW354U-#0449 8
Total Equipment Hours: 24
Daily Time and Materials (T&M) Report
Date: 2/23/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF ROUND ROCK • 1
2401 -T&M Quantity: 0
Notes:
Continued re-working/excavating the small piece of remaining paving section to the south of the building...in front of the GC's
trailer
Terracon came out Saturday afternoon around 4:30 p.m...all moisture/density tests in the sub grade passed
Proceeded with placing and processing the first 6" lift of select on the small piece of paving currently being reworked
-Terracon came out this afternoon around 3:00 p.m to test the first lift of select...all moisture/density tests passed
Began placing and processing the second (final) 6" lift of select...we will finish the final lift in the morning and have it tested
Imported select material: 2 loads (34.93 tons)
Survey is setup to be onsite first thing tomorrow morning to blue top the finished sub grade in the reworked section of paving
T&M
Backhoe w/operator: 10 hours
Skid steer w/operator: 10 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M. Morales 8 2 10
Total Labor Hours:20
Equipment Hours
BH-24-Cat 416 C4SX-#1580 10
SKID-23-CAT 265-#4903 10
XRNTDDREK19-Sakai SW354U-#0449 10
Total Equipment Hours:30
Daily Time and Materials (T&M) Report
Date: 2/24/2026
Foreman: Chad Simpson (CHAD SIMPSON)
Champion Site Prep, Inc.
1 OF •UND ROCK FIRE STATION1
2401 -T&M Quantity: 0
Notes:
Finished re-working the small piece of remaining paving section to the south of the building...in front of the GC's trailer
Finished placing and processing the second (final) 6" lift of select...
-Terracon came out this afternoon to test the second (final) lift of select...all moisture/density tests passed
Imported select material: 3 loads (47.83 tons)
Survey came out this morning to blue top the finished sub grade in the reworked section of paving
- Fine graded the finished select per the blue tops set by survey
This section of paving is 100% complete...turned over to the concrete sub
T&M
Backhoe w/operator: 10 hours
Skid steer w/operator: 10 hours
Labor Hours Overtime Hours Total Hours
BRYAN DELGAD-Bryan Delgado 8 2 10
JUAN MORALES-Juan M. Morales 8 2 10
Total Labor Hours: 20
Equipment Hours
BH-24-Cat 416 C4SX-#1580 10
SKID-23-CAT 265-#4903 10
XRNTDDREKI9-Sakai SW354U-#0449 10
Total Equipment Hours:30
1$3
Braun&Butler
CONSTRUCTION
City of Round Rock Fire Station 10
PR 15 Water Heaters
Date: 0410112026
Subject: PR 15 Water Heaters
From: Matt Harton
Company: Braun & Butler Construction, Inc.
To: Hayden Schiller
Company: City of Round Rock
Hayden,
Attached is pricing for the work outlined in PR-15 Water Heater Changes. This includes the water heaters
and additional electrical control circuits needed. This also includes the change to an aluminum ladder at
no cost.
-Plumbing—(2)60 gals in lieu of(1)100 =$16,872.00
-Electrical—additional controls circuits $2,263.00
$19,135.00
Sincerely,
Matt Harton
Senior Project Manager
Architect Signature Owner Signature
Date Date
Page 1 of 1
300 Hazelwood STE.100 Leander,Texas 78641 office(512)837-2882 1 fax(512)837-5115 I braun-butler.com
HVAC • PLUMBING • UTILITIES • MED GAS • BACK FLOW TESTING
Texas Quality Services LLC Office:512.243.5335
322 Southland Dr Fax:512.243.6425
Burnet,TX 78611 info@texasqualityservices.com
..
SUBCONTRACTOR REQUEST FOR CHANGE ORDER
Date: 3/12/2026 Subcontractor C.O.#: 2
Project: Round Rock Firestation
General Contractor,Braun-Butler
TQS Contact: Justin Stevens Phone: 512-715-0271
Description of Work or Discrepancy on Drawing:
This is per request to change 1-100 gallon propane water heater to 2-60 gallon propane water heaters.PLEASE NOTE:The gas water heater schedule item
#2 states water heater shall be provided with factory supplied insulation blanket per manufactuere's specification.This is not included as per A.O. Smith they
do not offer this on BTH models. Please note:The below cost does include a credit for orginal water heater.
Change Order Breakdown:
How many crews 1 How many hours 8.00 Cost per hour $55.00
How many plumbers 1 How many hours 8.00 Cost per hour 75.00
Total Cost $1,040.00
Material
Item: 2 60 gallon water heaters, venting and accessories Cost: $23,990.00
Total Material Cost $23,990.00
Credit 100 Gallon Water Heater Deduction Credit $9,692.00
Total Credit $9,692.00
Subtotal $15,338.00
Overhead 10% $1,533.80
Total Change Order Request $16,871.80
The conditions hereinbefore referred to are as follows:
. The aforementioned changes, and work affected thereby shall be performed under the same terms and conditions that are
included in the original contract unless stated otherwise.
. This change order includes all materals, labor, tools, equipment, supervision and related taxes necessary to perform the
above-mentioned work.
Submitted by: Mike Stiles Title: Project Manager Date: 3/12/2026
Approved by: Title: Date:
11,11,Inc.ddb State Electrical Contractor No. 17161
B. 1. Electric Company Master License No. 24035
1509 Three Points Road Cell Phone: 512-845-9187
Pflugerville,TX 78660 Fax: 512-990-5567
email: jlilley@bjelectric-inc.com
March 31,2026
Braun&Butler Construction
300 Hazelwood Street., Ste 100
Leander,Texas 78741
Attn: Matt Harton
City of Round Rock Fire Station#10-ChanIze Proposal 416- PR 15
Per your request, we offer the following proposal based upon our understanding of the scope of
work. This proposal is based on PR 13, drawings dated 12/19/2025. We propose to furnish
materials and labor for this change:
Scope:
- Provide and install one switch and wiring to control light fixture at panel rack on
mezzanine.
- Add two 120v circuits for added WH-2.
- Provide and install additional disconnect switches and connection as shown.
Change Proposal 416—Total Add: $2,263.00
Clarifications:
— This proposal is good for 30 days. After 30 days a new proposal will be required.
— BJ Electrical will NOT proceed with any chance order without written approval.
Verbal direction on chance orders is not acceptable.
Exclusions
— Sales tax.
— Overtime
— Bond.
Please feel free to give me a call with any questions.
Jerry Lilley
Project Manager
till
----------
--------- -