THIS AGREEMENT FOR PASS-THROUGH WATER AND WASTEWATER
SERVICE ['WILLIAMSON COUNTY REGIONAL PARK] (this "Agreement') is entered
into effective as of the Effective Date (defined below), by and among VISTA OAKS
MUNICIPAL UTILITY DISTRICT, a political subdivision of the State of Texas operating
under Chapters 49 and 54 of the Texas Water Code and formerly known as Williamson County
Municipal Utility District No. 9 (the"District"),WILLIAMSON COUNTY, TEXAS, a political
subdivision of the State of Texas(the"County"), and the CITY OF ROUND ROCK,TEXAS,a
home rule municipality located in Williamson County,Texas (the"Cid"). The City, the County,
and the District are sometimes referred to individually in this Agreement as a "Party" and
collectively as the"Parties".
RECITALS:
A. The District receives wholesale water and wastewater service from the City under
the Vista Oaks Municipal Utility District Amended and Restated Wholesale Water and
Wastewater Agreement dated effective August 29, 2011 (the"Wholesale Agreement").
B. The County previously entered into a Water and Wastewater Service Contract
dated effective April 25, 2002 (the "Original City Service Contract") with the City of Round
Rock, Texas (the "C�t1") and an Agreement Between Williamson County Municipal Utility
District No. g and Williamson County for Pass-Through Water and Wastewater Service dated
effective May 13, 2002 (the "Original Pass-Through Agreement"), with the District providing
for retail water and wastewater service from the City to the property described on
EXHIBIT"A", which has now been developed as the Southwest Williamson County Regional
Park(the"Park"), using the District's water and wastewater systems on a pass-through basis.
C. After the Original City Service Contract and the Original Pass-Through
Agreement expired, the City and the District renewed their respective commitments to provide
water and wastewater service to the Park using the District's water distribution and wastewater
collection systems on a pass-through basis pursuant to (i)the Water and Wastewater Service
Contract dated December 7, 2012 between the City and the County (the "Renewed 2012 Cita
Service Contract"); and (ii)the Agreement for Pass-Through Water and Wastewater Service
dated effective January 14, 2013 between the District and the County (the "2013 Pass-Through
Agreement"), which was subsequently amended and restated in its entirety pursuant to that
certain Amended and Restated Agreement for Pass-Through Water and Wastewater Service
[Southwest Williamson County Regional Parkl dated effective June 11, 2015 between the City,
the County, and the District(the"2015 Pass-Through Agreement").
E. The Counn the City have entered into a Water and Wastewater Service
Contract dated effective Z (the "Renewed City Service Contract") pursuant to
which the City has renewed it agreement to provide water and wastewater service to the Park.
F. The 2015 Pass-Through Agreement has expired and the County, the City, and the
District now desire to renew the terms and conditions of the 2015 Pass-Through Agreement as
more particularly set forth herein.
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2o26 Renewal)
zau- `�1 1
4920-6722-5977,v.4 (� l�
AGREEMENT
For and in consideration of the mutual promises,covenants, obligations, and benefits of
this Agreement,the District,the City,and the County contract and agree as follows:
Section 1. Recitals. The above and foregoing recitals are incorporated herein by
reference.
Section 2. Pass-Through Water and Wastewater Service.
A. Authorization of Pass-Through Service. Subject to the terms and
conditions of this Agreement and the Renewed City Service Contract, the City may
continue during the Term(defined below)to: (i)subject to the limitations and conditions
of service set forth in Section 2.B below, connect the City's 8-inch water line along that
runs along Sam Bass Road from the intersection of FM 1431 to the Park(such water line
being depicted on EXHIBIT"C-2" and being defined herein as the "City Water Line
Segment') to the County's water distribution system within the Park at the point of
connection identified on EXHIBIT"C-2" (the "County Water Point of Connection")
and to the District's water distribution system at the point of connection identified on
EXHIBIT"C-2" (the "District Water Point of Connection") to provide up to 52 living
unit equivalents ("LUEs") of potable retail water service to the Park under the Renewed
City Service Contract using the District's water system on a pass-through basis; and
(ii)connect the City's segment of wastewater line constructed to serve the Park (such
segment being depicted on EXHIBIT"C-1" and being defined herein as the " tt
Wastewater Line Segment") to the County's wastewater collection system within the
Park at the point of connection identified on EXHIBIT"C-1" (the"County Wastewater
Point of Connection") and to the District's wastewater collection system at the point of
connection identified on EXHIBIT"C-i" (the "District Wastewater Point of
Connection")to provide up to 52 LUEs of retail domestic wastewater service to the Park
under the Renewed City Service Contract using the District's water and wastewater
systems on a pass-through basis. The City Water Point of Connection and the District
Water Point of Connection are referred to in this Agreement individually as a "Water
Point of Connection"and collectively as the"Water Points of Connection". Similarly,the
County Wastewater Point of Connection and the District Wastewater Point of
Connection are referred to in this Agreement individually as a "Wastewater Point of
Connection"and collectively as the"Wastewater Points of Connection".
B. Limitations and other Conditions of Service.
1. Pass-through service under this Agreement is subject to the
capacity of the District's facilities to provide such service after meeting all needs
within the District and any contractual obligations existing as of the Effective
Date. Further, notwithstanding anything else in this Agreement to the contrary,
in no event will (a)the City or the County, without the prior written consent of
the District, take more than 250,000 gallons per day, averaged over any
consecutive 30-day period, of water from the District's water distribution system
as measured at the water meter at the District Water Point of Connection, or
(b)the City or the County, without the prior written consent of the District,
deliver through the City Wastewater Line Segment or the District's wastewater
collection system more than 52 LUEs of wastewater from the Park measured at
each Wastewater Point of Connection. The District's Board of Directors will have
the discretion to waive the limitations set forth in this Subsection upon written
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2026 Renewal)
2
4920-6722-5977,v.4
i
I
request of the County and the City. Water service to the Park will be subject to,
and the County agrees to be bound and abide by, the District's Water
Conservation and Drought Contingency Plan,as amended from time to time.
2. The District will continue to have a guaranteed reservation and
commitment of Moo LUES of water and wastewater capacity from the City under
the Wholesale Agreement. None of the LUEs of capacity guaranteed and
reserved to the District under the Wholesale Contract will be utilized to serve the
Park under this Agreement. Instead, the City is committing 52 LUEs of water
and wastewater capacity directly to the Park and will simply be using the
District's systems to provide retail water and wastewater service to the Park on a
pass-through basis.
3. To the extent that the County desires to make improvements to the
Park that would impact water usage and/or wastewater generation, the County
must submit all plans and specifications for such improvements to the District
prior to construction of such improvements so that the District may confirm that
water utilized and wastewater generated from such improvements will not exceed
the maximum limits set forth in this Agreement. Each submission must include
an engineer's calculation of LUES of water and wastewater service proposed and
the peak wet weather wastewater flows that will be generated by the
improvements, and such calculation will be subject to confirmation and approval
by the District. Further, within ten days after approval by the City, the County
will provide the District with a copy of all approved site plans, and amendments
thereto. The County will be solely responsible for the cost of any infrastructure
improvements to the County's or the City's water or wastewater systems that are
necessary to enable the City to provide retail water and wastewater service to the
Park.
4. The County and the City will be responsible for ensuring that all
discharges of industrial waste from the Park comply with federal, state, and
municipal requirements regarding pretreatment and monitoring of industrial
waste and other prohibited waste. Any compliance or enforcement efforts or
pretreatment requirements will be established and monitored by the City in
accordance with the City's ordinances; however, the District will be entitled to
inspect the facilities constructed to serve the Park and the connections at the
Wastewater Points of Connection and to test the wastewater received at the
Wastewater Points of Connection. If any test reflects that any wastewater other
than domestic wastewater is being received at the Wastewater Points of
Connection, pretreatment of such wastewater will be required, in accordance
with the City's ordinances, at the expense of the discharging party. The City will
not impose any fee, charge, or fine upon the District for any violation of any
ordinance, rule, regulation, or agreement caused by wastewater received at the
Wastewater Points of Connection, nor will the City impose upon the District any
surcharge that is caused by wastewater received at the Wastewater Points of
Connection.
5. Except as expressly authorized by this Agreement for pass-through
water and wastewater service to the Park, neither the County nor the City may
connect,or allow any other person or entity to connect, directly or indirectly(for
example, to the City Water Line Segment, the City Wastewater Line Segment, or
to the water or wastewater systems in the Park), any facilities, persons, or
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2026 Renewal)
3
4920-6722-5977,v.4
i
i
property to the District's water or wastewater utility systems without the prior
tyritten consent of the District. If the County or the City does so,the District may
immediately terminate this Agreement and/or require the County or the City, as
applicable,to immediately terminate service to the facilities,persons,or property
that have been connected in violation of this Agreement. The District reserves
the right to deny for any reason any request by the County or the City to increase
the level of service under this Agreement or to serve any facilities, persons, or
property outside of the Park.
C. Wastewater Lift Station Operation and Maintenance Payment. On or
before October 31st of each year during the term of this Agreement, the County will pay
the District an annual fee of $2,340, representing $3.75 per LUE per month for the
operation and maintenance of the District's lift station used to provide pass-through
wastewater service to the Park under this Agreement. This payment will be in addition
to any other payments required by this Agreement. Interest charges for any overdue
payment shall be paid by County in accordance with Texas Government Code
Section 2251.025. The $3.75 per LUE charge may be adjusted by the District annually to
reflect the actual reasonable and necessary costs of operating and maintaining the lift
station; provided,however, the District shall provide written notice to the County of any
adjustment at least 3o days prior to the effective date of such adjustment.
D. Water Metering. The amount of water passed through the District's water
system will be measured by meters at the District Water Point of Connection and the
County Water Point of Connection capable of measuring and recording the amount of
water that passes through the meters in a 24-hour period of time. As of the date of this
Agreement, metering equipment and related facilities required to properly measure the
quantity of water delivered to the Park have been designed, installed,and constructed at
the District Water Point of Connection. As of the date of this Agreement, metering
equipment and related facilities required to properly measure the quantity of water
delivered to the Park at the County Water Point of Connection have been designed,
installed, and constructed by the City. Any nes,*and/or additional metering equipment
and related facilities must be approved by the District's engineer and the City's Water
and Wastewater Department prior to installation and construction. Any existing
metering equipment may not be moved or relocated without the District's consent. The
City will operate and maintain the metering equipment. The District will have the right
to install a flow regulator to better facilitate the enforcement of this Agreement.
Installation of the flow regulator will be at the sole discretion of the District.
E. Payment for Retail Seivicg, The County will pay the City directly for retail
water and wastewater services furnished to the Park pursuant to the Renewed City
Service Contract.
F. 'Early Termination of Pass-Through Water Service to the Park. The City is
currently working on a plan to construct improvements to its water distribution system
that will allow the City to provide the Park with water service directly from City-owned
water facilities without the necessity of using the District's water system on a pass-
through basis. Therefore, as the aforementioned improvements near final completion,
City will provide the District and Countywith written notice of such fact and, upon the
date that is 6o days after the District and the County's receipt of such notice,the City will
no longer be able to utilize any District facilities to provide water service to the Park, all
provisions in this Agreement regarding pass-through water service will be terminated,
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2026 Renewal)
4
4920.8722-5977,v.4
t
F
i
I
and all other provisions of this Agreement shall otherwise continue in full force and
effect.
Section 3. Default. In the event of default by a Party,each nondefaulting Party may
give to the defaulting Party written notice of such default specifying the failure or default in
question. If the defaulting Party fails to fully cure the default specified in such notice within
thirty days after receipt of such notice, each nondefaulting Party will have the right to terminate
this Agreement as of the date of the event of the default and/or pursue all other legal or
equitable remedies. Each nondefaulting Party may employ attorneys to pursue its legal rights
and, if it prevails before any court or agency of competent jurisdiction, the defaulting Party will
be obligated to pay all expenses incurred by the nondefaulting Party, including reasonable
attorneys' fees. In addition to all other remedies available to the District, if, for any reason, the
County or the City violates any provision of this Agreement,the District will,after the notice and
opportunity to cure period described above, have the right to disconnect the County from the
District's systems and to terminate this Agreement if, in which event, the County will be solely
responsible for all actual costs and standard District fees related to disconnection from the
District's systems.
Section 4. Severability. The provisions of this Agreement are severable, and if any
provision or part of this Agreement or the application thereof to any person or circumstance is
ever be held by any court of competent jurisdiction to be invalid or unconstitutional for any
reason, the remainder of this Agreement and the application of such provision or part of this
Agreement to other persons or circumstances will not be affected thereby.
Section 5. Modification. This Agreement will be subject to change or modification
only with the mutual written consent of all Parties.
Section 6. Assignability. This Agreement will not be assignable by the County or
the City, in whole or in part, without the prior written consent of the Board of Directors of the
District.
Section 7. Applicable Law. This Agreement will be governed by,and construed in
accordance with the laws of the State of Texas. All of the obligations contained in this
Agreement are performable in Williamson County,Texas.
Section 8. Parties at Interest. This Agreement will be for the sole and exclusive
benefit of the Parties hereto and will never be construed to confer any benefit to any third party.
Section 9. Waiver. Each Party may specifically, but only in writing, waive any
breach of this Agreement by another Party, but no such waiver will be deemed to constitute a
waiver of similar or other breaches by such other Party.
Section io. Notices. All notices to the District must be in writing and mailed by
Certified Mail,Return Receipt Requested,addressed to:
Vista Oaks Municipal Utility District
c/o Armbrust&Brown,PLLC
Attn:Jenn Scholl
loo Congress Avenue,Suite 1300
Austin,Texas 78701
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2026 Renewal)
5
4920.6722-5977,v.4
with a copy to:
Vista Oaks Municipal Utility District
c/o Crossroads Utility Services LLC
Attn: Ben Ingallina
26oi Forest Creek Drive
Round Rock,TX 78665
All notices to the County must be in ATiting and mailed by Certified Mail, Return Receipt
Requested, addressed to:
Williamson County
c/o: Steven Snell, County Judge
710 Main Street,Suite ioi
Georgetown,Texas 78626
with a copy to:
Williamson County
c/o: T. W. Dieckmann,Williamson County Parks Director
219 Perry Mayfield
Leander,TX 78641
All notices to the City must be in writing and mailed by Certified Mail, Return Receipt
Requested, addressed to:
City of Round Rock
c/o City Manager
221 East Main Street
Round Rock,Texas 78664
with a copy to:
City of Round Rock
c/o: Sheets&Crossfield, PLLC
Attn: Steve Sheets
309 East Main Street
Round Rock,TX 78664
Any Party may change its address by giving written notice of such change to the other Parties.
Section ii. Term. This Agreement commence as of the Effective Date and
remain in effect until August 29, 2051 (the "Initial Term"). Upon the expiration of the Initial
Term, this Agreement will continue from month-to-month (each, a "Renewal Term") until
either Party gives 6o days' written notice of such Party's desire to terminate this Agreement to
the other Party. The Initial Term, together with any Renewal Terms are referred to collectively
as the"Term".
Section i2. Effective Date. The effective date of this Agreement (the "E ective
Date") be the 7th day of December, 2022.
VO—Agreement for Pass-Through Water and Wastewater Sen ice Williamson County Regional Park(2026 Renewal)
6
4920-6722-5977,v.4
i
Section 13. Multiple Originals. This Agreement may be executed in a number of
counterparts, each of which will for all purposes, be deemed to be an original, and all such
counterparts will together constitute and be one and the same instrument.
Section 14. Entire Agreement. This Agreement,including Exhibits, constitutes the
entire agreement of the Parties and, upon the Effective Date, supersedes all prior agreements
and understandings related to the subject matter hereof, including,without limitation,the 2015
Pass-Through Agreement; provided, however, that the Renewed City Service Agreement will
continue in effect in accordance with its terms.
Section 15. Authority. Each Party represents and warrants that it has the full right,
power, and authority to execute this Agreement and all related documents. Each person
executing this instrument on behalf of a Party represents that he or she is an authorized
representative of and has the authority to sign this document on behalf the respective Party.
IN WMESS WHEREOF, the parties have caused this Agreement to be executed
effective as of the Effective Date.
[counterpart signature pages follow]
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2026 Renewal)
7
4920-6722-5977,v.4
COUNTERPART SIGNATURE PAGE TO
AGREEMENT FOR PASS-THROUGH WATER AND WASTEWATER SERVICE
ISOUTInVEST WILLIAMSON COUNTY REGIONAL PAW
DISTRICT:
VISTA OAKS MUNICIPAL UTILITY
DISTRICT
_#At�5�
Heath Reed-Green,President
Board of Directors
VO—Agreement for Pass-Through Water and Wastewater 5enice Williamson County Regional Park(2026 Renewal)
8
4920-6722-5977.v.4
COUNTERPART SIGNATURE PAGE TO
AGREEMENT FOR PASS-THROUGH WATER AND WASTEWATER SERVICE
[SOUTHWEST WILLIAMSON COUNTY REGIONAL PARK]
COUNTY:
WILLIAMSON COUNTY,TEXAS
By:
Steven Snell,County Judge
VO—Agreement for Pass-Through Water and Wastewater Service Williamson County Regional Park(2026 Renewal)
9
4920-6722-5977,v.4
COUNTERPART SIGNATURE PAGE TO
AGREEMENT FOR PASS-THROUGH WATER AND WASTEWATER SERVICE
[SOUTHWEST WILLIAMSON COUNTY REGIONAL PARKI
CITY:
CITY OF ROUND ROCK, TEXAS
By: �4' N /
Craig Morg n, Aia v
r
VO—Agreement for Pass-Through Water and Wastewater Sen ice Williamson County Regional Park(2026 Renewal)
10
4926-6722-5977,v.4
CCC 1 qR•�� r'Ii t �` � q -�t '!
t
3 1 • �s ..�+� F,.��,R� Yost• �,�� ♦ �
,1{ it \ < ',.i(��t++, '�'tilt;4. ` 4 1.•1�� ( ,°.,•V�eA .V , •�1�1` F As
':yy `'Rt•.s_qtr'•�)„ ��5 ,+ ►- 'lY"s.L O>;'r ♦��- t�- �'t''CrLI �. 'L« t '•• J t,l'.=.•...
•s TCS°:,t 'v ` , L". 1� j�"' t!"ryy/ �i �+,>��j, i � �� '1 +
_" f� l i .{�t� !r'• gyp Y'�{ - �l'{•,�+l� a���-. ,�-1,, ' .� '� ��'1:..
4. .r. �• \I t, IF : I, ..,i,�t .,, r• Mf-. _• r ,_' j ;�ys..
lirp
, 7.¢F"r�v l � - "1 i� 'rexrj• � r 'k �[y• •pro���(f.1
t ati Ij!~
��t ��� r ,�i t �SY, ► 11,a•iitlt �� i '.i;{t t"���. `j a'+�•��q,� •=+l:ii 'Y� zh � ;fix
',t -.�.! ;•� I til.t'S yt i'1Nttf � iLi '`' t � �t'�+' �sj '.-,�) •. f ,��••
'A1� �"-
_ t S/� +a . {r`.�l torr♦�t J•t1 iCrt\�1 �: it S' } 1�+r t
IN. �',�,! �t y rr•<{�� tl l{, !'Rr l.•o*! s i Jr?7 !�r ���'..�N-�. hLs�,�.'�1 , t5
1 r£c���{}��i�'r j /!�1 1i ...�•, r 15, �� S 1 2�,'
4: . •,1 Y .1: . .tt ty+:y.\•3� �r � t � N tl .>t! ,,j_1 d
` 1 } �l � 1, r ��✓ i � Y;t'
`, r Z►y..�. }�'. , �?••�y,�1�si`�',t •1;��i�•t.• ��S�r..;1 �� 3
qsiowai.• �r r t r4 t Y �.0.• '
,
IKIII
Y
�I•.,Ir�s "r.•� ` .r- \\ `r. � ��r'�.v, k.ti �.' 7 -!• d�tl� �c� yr s���,
5 i ♦ 1 ��
01 f. r_rft? p�,� ✓//1'la r 1.•e'
ft.<., �'•rY. iS 1s �y.,SV� 4 i♦ ` /;`y F� .�...•i`d tr •i ,! - .�
:� ; 111 Q •tl , `t�•`yti _ �'�.� �.'` 7!� �t�1�}3 ilv� �
l J'✓ '•1 At •, y
Southwest • • Boundary
•l\'-• �•if .Iter �W t !' h
1
EXHIBIT"B"
RENEWED CITY SERVICE CONTRACT
Exhibit"B" — Page 1 of
4920-6722-5977,v.4
EXHIBIT "C-1"
WASTEWATER EXHIBIT
DISTRICT WASTEWATERI
�POINT OFCONNECnON�
WILLIAMSON COUNTY i
I WASTEWATER POINT OF.
CONNECTION 93
a,
;
CITY WASTEWATER
s=t I
LINE SEGMENT
91 s,'f
.4 �s
VISTA OAKS ,tj
Ps ,.
MUD
s
Legend
Wastewater Line ,� - Aw f`
—� City of Round Rock
MUD
o Manholes
System Meters
13 Master Meter
13 Emergency Cnonedian
sucv�a
N CITY WASTEWATER LINE SEGMENT &
WASTEWATER POINTS OF CONNECTION ouNukocKuxas
Exhibit"C-i"— Page 1 of 1
4920-6722-5977,v.4
EXHIBIT "C-2"
WATER EXHIBIT
Legend
Vain MSON COUNTY WATER`
PoINT OF CONNECTION System Meters
(METER LOCATION)
13 Master Meter
i ( Emergency Connection a
Water Line -
C4 of Rowd Rock
— MUD
Private r
TSTA A "
x � D
Y� ,�,y •�` �J Cil:
CTfY WATER LINE SEGMENTI
-� `- iWATERLINEf
DISTRICT TO CITY POINT!, {
OF CONNECTION(METER);
5'•
N CITY WATER LINE SEGMENT &
WATER POINTS OF CONNECTION aouNo. ao«itxAs
r..,w
Exhibit"C-2" —Page i of i
4920-6722-5977,v.4