Loading...
Contract - Plummer Associates, Inc. - 8/13/2026 STATE OF TEXAS § COUNTY OF WILLIAMSON § SUPPLEMENTAL CONTRACT NO. 4 TO CONTRACT FOR ENGINEERING SERVICES FIRM: PLUMMER ASSOCIATES,INC. ("Engineer") ADDRESS: 1320 S. University Drive, Suite 300, Fort Worth,TX 76107 PROJECT: BCRWWS East WWTP Expansion (Construction Phase Services) This Supplemental Contract No. 4 to Contract for Engineering Services is made by and between the City of Round Rock, Texas, hereinafter called the "City" and Plummer Associates, Inc., hereinafter called the"Engineer." WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract," on the 9th day of April, 2020 for the BCRWWS East WWTP Expansion (Construction Phase Services) Project in the amount of$4,931,846.00; and WHEREAS, the City and Engineer executed Supplemental Contract No. 1 on the 14th day of September 2023 to amend the scope of services and to increase the compensation by$144,715.11 to a total of$5,076,561.11; and WHEREAS, the City and Engineer executed Supplemental Contract No. 2 on the 22nd day of February 2024 to amend the scope of services and to increase the compensation by $250,000.00 to a total of$5,326,561.11; and WHEREAS, the City and Engineer executed Supplemental Contract No. 3 on the 24th day of July, 2025 to amend the scope of services and to increase the compensation by$1,456,058.00 to a total of$6,782,619.11; and WHEREAS,it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $1,427,698.00 to a total of$8,210,317.11; NOW THEREFORE,premises considered,the City and the Engineer agree that said Contract is amended as follows: I. Article 2. Engineering Services and Exhibit B.Engineering Services shall be amended as set forth in the attached Addendum to Exhibit B. Exhibit C. Work Schedule shall be amended as set forth in the attached Addendum to Exhibit C. Supplemental Contract Rev.06/16 0199.2026(0199.20209) 84275 �_ 2Z2-(Q-_2DK l II. Article 4. Compensation and Exhibit D. Fee Schedule shall be amended by increasing by $1,427,698.00 the maximum amount payable under the Contract for a total of$8,210,317.11, as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF,the City and the Engineer have executed this Supplemental Contract in duplicate. [signature pages follow] Supplemental Contract Rev.06/16 0199.2026(0199.20209) 84275 2 PLUMMER ASSOCIATES, INC. By: _A4C4, &I& Printed Name: m4 2 r Title: -T rs2C T Pd 10 c g-r s -e- Date Signed: Y/Zd 2 h Supplemental Contract Rev.06/16 0 199.2026(0199.20209) 84275 3 CITY OF RO ROCK APPROVED AS TO FORM: By: AA „r�� ,L• Craig or n, Mayor Step anie L. Sandre, City Attorney 3 z Date Supplemental Contract Rev.06/16 0199.2026(0199.20209) 84275 4 ADDENDUM TO EXHIBIT B Engineering Services Attached Behind This Page PLUMMER Exhibit B Scope of Services CITY OF ROUND ROCK Brushy Creek Construction Phase Services Supplemental Services Request 4 The services to be provided under this Supplemental Services Request are organized into the following tasks,which include Construction Management(CM), Resident Project Representative (RPR), engineering support, and PLC/HMI programming and field verification services.This supplemental scope is required to provide continued support during the extended construction period resulting from the contractor's delay in achieving completion of the Work. Under the contractor's bid,the Work was to be completed by February 1, 2023, and this Supplemental Services Request No.4 is required to continue services associated with completion of the remaining Work. For budgeting purposes, project completion is assumed to be August 31, 2026. Task 1 -Construction Management and RPR Services During construction of the Brushy Creek Expansion project, Plummer shall provide Construction Management(CM) and Resident Project Representative (RPR) services as described in this task. The contractor remains solely responsible for performing the work in accordance with its contract with the City of Round Rock, and Plummer's CM and RPR services do not relieve the contractor of any of its contractual obligations. 1.1 -Construction Management Services 1.1.1 -Project Coordination and Meetings Plummer will support overall project coordination by preparing weekly meeting agendas and minutes, attending weekly meetings and site visits, and coordinating with the City and project team regarding project status, outstanding items, and next steps. 1.1.2-Project Controls and Progress Tracking Plummer will review and maintain project controls documentation, including submittal, RFI, and schedule logs used to track project progress. Services will also include continued tracking of punch list items documented in Projectmates and support for weekly monitoring of remaining work through coordination and site walks, as needed. 1.1.3-Contract Administration and Closeout Support Plummer will support the City of Round Rock with final pay estimates, project closeout documentation, and final change order assistance, as required by the contract. Construction management services will also include leadership and contractor coordination intended to ,�� Page 1 Brushy Creek Expansion 30MGD Construction Phase Services—Supplemental Request 4 facilitate completion of the contractor's remaining obligations,with items tracked weekly through site walks and ongoing follow-up. Brushy Creek Construction Services construction management support is anticipated at an average of 24 hours per week through the project completion date, and EIT support is anticipated at an average of 24 hours per week through the project completion date. 1.2—RPR Services 1.2.1 —Correspondence The RPR will serve as the primary point of contact for project communications among the City, contractor, and project team on the Brushy Creek Expansion project.The RPR shall have access to the Work whenever it is in preparation or in progress. Brushy Creek Construction Services RPR support is anticipated at an average of 48 hours per week through the project completion date. 1.2.2—Project Documentation The RPR will maintain daily reports documenting project progress, observations, photos, and videos for each site visit. Each daily report will include notes on onsite personnel, equipment, observed construction activities, and testing agencies.A sample RPR report is attached to this scope of work. 1.2.3—Field Observation The onsite RPR will provide field observation to assess the contractor's conformance with the plans and specifications and will notify the contractor and the City of Round Rock of any observed nonconforming work,while monitoring the progress of the contractor's corrective actions.The onsite RPR shall not be responsible for the means, methods,techniques, sequences, or procedures of construction selected by the contractor, or for the safety precautions and programs incident to the contractor's work. Task 2—Engineering Support 2.1 —Engineering Project Management Support Plummer will provide engineering support through the project completion date.The Engineering Project Manager will be available for an average of 8 hours per week to support coordination, technical input, and issue resolution, as needed. 2.2—Electrical/Structural/Architectural Subconsultant Support Plummer's electricaUstructuraUarchitectural subconsultant will provide engineering support and technical assistance, as identified in the Fee Schedule and as requested by the City and project team. 2.3—Site Civil and Mechanical Subconsultant Support Plummer's site civil and mechanical subconsultant will provide engineering support and technical assistance, as identified in the Fee Schedule and as requested by the City and project team. Task 3—PLCs and HMI Programming and Field Verification Services Page-2 Brushy Creek Expansion 30MGD Construction Phase Services—Supplemental Request 4 Plummer will provide PLC and HMI programming modifications,field checkout, startup, and related technical support for the remaining areas of work associated with the Brushy Creek Expansion project, as described in this task. 3.1 —PLC and HMI Modifications Services under this subtask will include PLC and HMI programming modifications required to support field checkout, startup, and commissioning of the remaining project systems.Work may include debugging PLC logic, updating HMI screens and database links, restoring proper system addressing, and making other programming changes necessary to support system functionality. 3.2—Field Checkout and Startup Services Plummer will provide field checkout and startup services for the remaining areas of work. Services may include establishing communications with mixers,VFDs, PLCs, instrumentation, and other ethernet devices;testing inputs and outputs; configuring VFDs;testing control loops;verifying data availability to the HMI; and supporting field testing and commissioning activities necessary to place the systems into operation. 3.3—Areas of Work • Area 400—Train 1 Aeration, Basins 1 and 2:field checkout services, including communications with mixers, 1/0 testing,VFD configuration,control loop testing, PLC logic debugging, and HMI updates. • Area 400—Train 1 Aeration, Basins 3 and 4:field checkout services, including communications with mixers, 1/0 testing,VFD configuration, control loop testing, PLC logic debugging, and HMI updates. • Area 400—Train 2 Aeration, Basins 1 and 2:field checkout services, including communications with mixers, 1/0 testing,VFD configuration, control loop testing, PLC logic debugging, and HMI updates. • Area 400—Train 2 Aeration, Basins 3 and 4:field checkout services, including communications with mixers, 1/0 testing,VFD configuration, control loop testing, PLC logic debugging, and HMI updates. • Area 500—Influent Lift Station ILS2: communications for replaced or repaired VFDs, decommissioning of temporary motor starters, and HMI database updates to restore proper system addressing. • Area 550—Alum Feed Systems at the Chemical Building:field testing of 1/0,VFD configuration, ethernet device configuration and tie-in, PLC code testing and debugging, and verification of HMI database and screens. • Area 650—RAS/WAS: no items are currently identified under this task. • Area 750—Reuse System: no items are currently identified under this task. • Area 800—East Electrical Building: 1/0 field testing,VFD configuration for PLC communications, ethernet instrumentation configuration and testing, control loop field testing, PLC code changes, and HMI data and link updates. • Area 1100—Sludge Storage Tanks: no items are currently identified under this task. Page-3 Brushy Creek Expansion 30MGD Construction Phase Services-Supplemental Request 4 • Area 1350-Dewatering Building: 1/0 field testing, including confirmation of hopper level signals and flowmeter level signals on belt presses 3 and 4, and verification that HMI data is reported correctly. • Area 1500-Chemical Building: no items are currently identified under this task. Task 4-Project Work List and OPCC 4.1 -Remaining 30 MGD Expansion Project Work List Plummer will provide the City of Round Rock with a comprehensive list of remaining items on the 30 MGD Expansion Project after the contractor has ended their work, including incomplete work, deficient work, or incorrectly installed work by the contractor that will need to be completed as part of the 40 MGD Design Package. 4.2-Opinion of Probable Construction Cost This deliverable will also include an associated Class 3 Opinion of Probable Construction Cost (OPCC). Page-4 ADDENDUM TO EXHIBIT C Work Schedule Attached Behind This Page ID -Taste Task NarM - BasNine Sint 6""Finish Baseln.3 Finish Finish Vanance 1.1020 NO 2.M20 Hae I.2021 H}g j,7,011 NFII 1�}j NFM j,2022 W M I.2023 HaM 2.2023 Hart 1.20N 1r j,-4 HFII 1,�OQS 11FM j,M25 NFM 1.QOM NNf Made M A M I l A 5 0 N D/ F M g M 1 I A S O�N�0 1 F�M A M�1 I A S.0 N D I F M P M 1 1 A S 0 N D IIFIMIAIMII l AA�M�1 l l�A 1 >♦ Construction Project Management Mon 3/30/20 Toe 9/26/23 Mon 8/31/26 0 days 2 2r 0.Pre-Construction Activities Mon 3/30/20 Mon 6/1/20 NA 0 days masmig 3 Engineers Notice to Proceed from City Council Mon 3/30/20 Man 3/30/20 NA 0 days ♦3/30 4 0% Pre-Construction Meeting Tue 3/31/20 Tue 3/31/20 NA 0 days ;3/31 5 General Contractors Mobilization Wed 4/1/20 Mon 6/1/20 NA 0 days 1 1 6 1.Engineering Services During Construction Wed 4/15/20 Tue 1/31/23 Mon 8/31/26 0 days 7 Monthly Engineer Site Visits Thu 5/28/20 Thu 1/26/23 Mon 8/31/26 0 days 41 Special Engineer Inspections(as arranged by CM) Fri 5/1/20 Fri 3/31/23 NA 0 days 55 all, Preselected Equipment Coordination(as directed by Fri 5/1/20 Thu 4/7/22 NA 359 days 1 CM) 56 >♦ Engineer assistance with Submittal Reviews and any Wed 4/15/20 Sun 4/3/22 Mon 8/31/26 370 days ana�q associated document control or processing(RFIs,CMRs and PCMB) 57 )r 2.Onsite Management&Admin services Mon 3/30/20 Tue 1/31/23 Mon 8/31/26 0 days 58 /► Submittal Reviews and any associated document Mon 3/30/20 Sat 10/1/22 Mon 8/31/26 1197 days 1� r control or processing(RFIs,CMRs and PCMB) 59 Site Visit Coordination Mon 3/30/20 Sat 10/1/22 Mon 8/31/26 1211 days 60 Construction Observation Documentation Mon 3/30/20 Sat 10/1/22 Mon 8/31/26 0.13 days 61 MOnthfy Construction Progress Meetings Wed 5/6/20 Fri 2/30/23 Mon 8/31/26 243 days 1 1 1 11 111111 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 97 Monthly Progress Reports Fri 4/24/20 Tue 3/28/23 NA 461 days n 00 000 101 000 100 000 00 0000 000 00 000 000 00 135 Monthly Pay Estimate Reviews Mon 5/4/20 Fri 3/3/23 Mon 8/31/26 486 days 11 I I 1 1 11 I 1 I I I I I I III II 1 1 1 1 1 1 1 11 1 1 1 1 1 1 172 Ills Testing&Special Inspections Mon 6/1/20 Fri 11/5/21 Mon 8/31/26 1422 days 173 { Milestone Substairltial Completion Reviews Mon 6/1/20 Tue 1/31/23 NA 0 days 174 NTP Construction Activities on Site Mon 6/1/20 Mon 6/1/20 NA 0days 1 -------- ----- ---- - - 175 Phase 1-Early Improvements Mon 6/1/20 Mon 5/31/21 NA 0 days j 5/31 176 Phase 21b-New Treatment Train&Associated Mon 6/1/20 Wed 8/31/22 NA 0 days ♦0 8)31 Facilities substaintial completion 177 Phase 3-Modification to Aeration Basin Train 2 Mon 6/1/20 Fri 8/19/22 NA 620 days 178 Phase 4-Project substaintial completion except for Mon 6/1/20 Sat 11/12/22 NA 1053 days j 9/30 phase 5 179 Phase 5-Mods t0 Aeration Basin Train 1 and Mon 6/1/20 Wed 1/4/23 NA 1000 days 9/30 conversion from gas to liquid Cl feed 180 Final Completion Mon 6/1/20 Tue 1/31/23 Mon 8/31/26 1308 days 181 3.Post Construction Services Mon 6/1/20 Tue 9/26/23 Mon 8/31/26 0 182 Engineer Substantial Review NA NA Mon 8/31/26 0 days 183 1Ry Engineer Final Completion Review Mon 8/31/26 1491 days i 1 154 Start-up Services Mon 6/1/20 Tue 9/26/23 Mon 8/31/26 247 days 185 Phase 1-Early Improvements Mon 6/1/20 Mon 6/1/20 NA 0 days) 6/1 _._........_._..... 186 Phase 2a-New Treatment Train&Associated Mon 6/1/20 Tue 5/17/22 NA 0 days) j S/17 Facilities 187 1I Phase 3-Modifications to Aeration Basin Train 2& Mon 6/1/20 Tue 9/26/23 NA 0 daysi 9/26 New U V 168 Phase 4-Project substaintial Completion Mon 6/1/20 Sat 11/12/22 NA 1053 days� 9/30 189 s► Phase 5-Modifications to Areation Basin Train 1 and Tue 6/2/20 Thu 1/5/23 NA 999 days. 9/30 conversion from gaseous to liquid chemical feed 190 A Final Completion Mon 6/1/20 Tue 1/31/23 Mon 8/31/26 1308days 191 0 Record"As-built"Drawings Fri 1/6/23 Mon 3/6/23 Wed 9/30/26 1030 days 192 1I O&M Manual Assembly Fri 1)6/23 Mon 3/6/23 Wetl 9/30/26 1038 days. 193 A 4.Project Management and Quality Assurance Mon 3/30/20 Fri 3/31/23 Mon 8/31/26 456.13 days ii Project,Plummer Construction li tart Summary 1�1 Inactive Mi�ea,nne Duratron-Doty Sun only C Eternal 144,­ Manual Pr,,-, Date:Thu 6/11/26 SP." ............ Props Summary Manual Summary aoeup 1-1,-1, ] N,ohn. Milestone ♦ Nuttrve ias4 Manual cast �awlall Manual Summary l�1 Etternal Tasty Progreso Page 1 ADDENDUM TO EXHIBIT D Fee Schedule Attached Behind This Page ■5t�2,!<!;i . ! ■i:�#�##■,& ( \ ■#z■;!■7:#■! ■ .,:z. -._®-�� | ■ • . ■ .! . ■ ! ! - ■kkIs • ! ! _ .■!;,! � § !$5■■#■r#■4¥ !; �;�,�_�;�,�� : !• ! ) ; �l.�2■z�■#• ; e | ! .,_.��■§l�-- N i `! . . . . � � \ §,!-������_ ■ ! �4 � / # ■!!-�����-s: B ! �§ . . .. —— i� . . .. if ��,■!l���it7 | ® (■ § ;{ le �- !�!}f�$�!�« !I! M_|)|) !■!||!■!!•.) � � �� \� � } rFREESE MASTER PROFESSIONAL SERVICES AGREEMENT aNICHOLS TASK AUTHORIZATION AMENDMENT#2 PLUMMER AND ASSOCIATES, INC. FNI Project: PLU20452 1320 South University Drive;Suite 300 Client Contract: 0982-003-06 Fort Worth,Texas 76107 Date: 6/29/2026 Project Name: Brushy Creek Regional East Wastewater Treatment System East Plant Expansion to 30 MGD—Construction Phase Services Description of Services: Additional Services for Electrical Site Visits, Meetings, and Coordination with Contractor Deliverables: Site Visit Reports, Responses to RFls, and Record Drawings Schedule: May 1, 2026 to August 31, 2026 Compensation Type: Cost Plus Expenses, Not to Exceed Fee Current Contract Amount: $959,980 Amount of this Amendment: $140,430 Revised Total Amount Authorized: $1,100,410 The services described above shall proceed as amended upon execution of this Amendment. All other provisions, terms, and conditions of the Master Professional Services Agreement which are not expressly amended shall remain in full force and effect. PLUMMER AND ASSOCIATES, INC. FREESE AND ICHOLS, INC. By: By: ~` l \� Name: Name: Jason Ward, PE Title: Title: Principal &Vice President Date: Date: June 29, 2026 Master Professional Services Agreement Task Authorization Page 1 of 1 Rev 07/22 ATTACHMENT SC SCOPE OF SERVICES AMENDMENT 2 BRUSHY CREEK REGIONAL EAST WASTEWATER TREATMENT SYSTEM EAST PLANT EXPANSION TO 30 MGD CONSTRUCTION PHASE SERVICES A. PROJECT UNDERSTANDING Plummer Associates, Inc. (Client) retained Freese and Nichols, Inc. (FNI Team) to provide construction phase services for the Brushy Creek Regional East Wastewater Treatment System East Plant Expansion to 30 MGD. Substantial completion of the project was anticipated in September 2023. Several delays, including the receipt and installation of electrical equipment and Contractor turnover, have extended the Substantial Completion of some key components of the electrical work. It is currently estimated that Substantial Completion will occur by August 31, 2026. To cover the additional effort for General Site Representative, Site Visits, Bi-Weekly Meetings, Record Drawings, and Project Management, FNI is requesting Additional Fee to cover the effort through August 31, 2026. Should the actual date of Substantial Completion of the electrical aspects of this project extend past August 31, 2026, FNI will submit a request for additional funds to cover our efforts to complete the project if the schedule is extended further. SC-1 Task 1: ENGINEERING SERVICES DURING CONSTRUCTION Table 1—Additional Services Summary Item Scope Cost Task 2.1—General FNI personnel to provide General Project Rep services as Site Representative needed to achieve project completion on or before August $55,466 31, 2026 Task-2.3 Site FNI personnel to attend virtual Bi-Weekly meetings with Visits the Contractor and Electrical Subcontractor to achieve $34,139 project completion on or before August 31, 2026 Task 2 Subtotal $89,605 TASK 3: POST CONSTRUCTION SERVICES Table 2—Additional Services Summary Itern Scope Cost Task—3.2 Project FNI personnel to complete project record drawings Record Drawings $32,648 Task 3 Subtotal $32,648 TAKS 6: PROJECT MANAGEMENT AND QUALITY ASSURANCE: Table 3—Additional Services Summary 'Item Scope Cost Task 4.3 - Project Provide Project Management services to achieve project Management completion on or before August 31, 2026 $13,118 Develop OPCC Develop Opinion of Probable Cost for uncompleted work by Contractor $5,059 Task 6 Subtotal $18,177 Total Authorization $140,430 SC-2 ARTICLE IV TIME OF COMPLETION: FNI Team is authorized to commence work on the Project upon execution of this Agreement and agrees to complete the services in accordance with the schedule presented in Table 3. Table 3—Schedule Milestones Milestone Date Notice to Proceed May 1, 2026 Completion August 31, 2026 If FNI Team's services are delayed through no fault of FNI Team, FNI Team shall be entitled to adjust contract schedule consistent with the number of days of delay. These delays may include but are not limited to delays in Client or regulatory reviews, delays on the flow of information to be provided to FNI Team, governmental approvals, etc. SC-3 Brushy Creek Regional East WWTP East Plant Expansion Amendment 2 - Construction Phase Services June 29, 2026 ProWitiort IF Surnmary Basic Services $ 140 430 Besic Smlcs: Special Services $ - Special Servlc Additional Servlces $ Additional Sar Total Project $ 140.430 Total Project Labor E Tobei Gerie H— icaeel Schvnler Jenel FrerN Baena-- iea Here q Grafi-- Brae walaon J—Rlnecke Task Task Description Total Houro Total Labor Tech Charge Total Expense Total Effort Effort Effort 5366 f]fir Sn4 F"r 5244 5114 Sam Sr06 2.1 General Site Rep 60 86 30 20 27 223 $ 53,571 223 $ 1.896 $ 55,466 2.3 Site Visits 48 48 11 11 i6 134 $ 33,000 134 $ 1,139 $ 34,139 3.2 Record Drawings 80 90 170 $ 31,203 170 $ 1,445 $ 32,648 4.3 Project Management 35 35 $ 12,821 35 E 298 E 13,118 Develop OPCC for Uncomplete Work by Contractor 4 22 2 2 8 20 $ 4,890 20 $ 170 $ 5,060 Total Hours/Quantity 35 112 80 228 43 33 45 a 562 582 Total Effortl$ 12,8211$ 32,1311$ 17,0961$ 35,4231$ 10,4821$ 7,7301$ 18,1341$ 1,687 $ 135,483 1 E 4,947 1$ 4,947 1$ 140,430 6/2912025 ,?- Lochner 1120 S Capital of Texas Highway Austin,TX 78746 CityView 2,Suite 100, 512.338.1704 hwlochner.com ®egis SCOPE OF SERVICES Brushy Creek East Regional WWTP 30 MGD Expansion Amendment 4—Additional Construction Phase Services The Brushy Creek East Regional Wastewater Treatment Plant (Plant) is owned by the Brushy Creek Regional Wastewater System (BCRWWS), who are the Cities of Round Rock, Cedar Park, and Austin (Partners).The City of Leander will become a part owner on completion of the current expansion from 20 MGD to 30 MGD, which is currently under construction. Lochner is a subconsultant to Plummer Associates for this expansion to 30 MGD, which is currently under construction and has experienced significant delays due to the Contractor. The purpose of this scope of services is to provide additional construction phase services to account for the delays. The original scope of services assumed a 36- month construction period; however, the actual construction is more than 36 months behind schedule for a total assumed duration of 72 months. This scope of services assumes the construction and/or services will continue through August 31, 2026. The following details Lochner's scope of services, fee, and assumptions for the Project. SCOPE OF SERVICES: 1. Project Management — This task includes routine communication and coordination with Plummer and the Partners; managing manpower, budgets, and schedules; monthly invoicing and status reports; and other activities associated with managing the project for an additional five (S) months. 2. Site Visits— Lochner has made site visits throughout the duration of the construction phase, including multiple visits to perform substantial walk-throughs. Lochner will make an additional six (6)visits to the construction site to monitor the progress and quality of the work and to perform substantial and final walk-throughs to make a determination that the work has been completed in accordance with the contract documents. 3. Construction Progress Meetings— Lochner will participate in weekly progress meetings that are held virtually. A total of sixteen (16) two-hour construction progress meetings have been assumed.Travel to the site is not included. 4. RFI Review— Lochner will respond to Contractor's request for information (RFI). An additional five (S) RFI's are assumed to be submitted. S. Start-up Services — Lochner has previously assisted with start-up services for the Influent Lift Station #2 (ILS #2); however, the previous attempts at start-up were unsuccessful by the Contractor. Lochner will support the start-up for ILS #2 when the submersible pumps are repaired and reinstalled, including office consulting, virtual start-up calls, and a full-day site visit to witness pump testing and full start-up. 6. Opinion of Probable Construction Cost(OPCC)—An OPCC for unfinished work within Lochner's design responsibilities will be developed. FEE: The estimated fee for the basic services described above, on a Time and Materials basis, is $43,000.00. A fee breakdown by task is included herein. Amendment 4 1 July 2,2026 �'- Lochner ®egis ASSUMPTIONS: • This scope of services assumes that construction and/or services will continue through August 31, 2026. If additional delays are encountered, future amendments may be required. • The fee is based on the site visits, meetings, and RFIs assumed above. If additional reviews are necessary, this will be considered an additional service. • Inspection services will be provided by the City and/or Plummer. Lochner will perform routine site visits as described above; however, Lochner will not be responsible for detailed inspection of the Contractor's work. • Plummer will lead coordination with the City and Contractor, and Lochner will support Plummer as necessary. • No design is included in this scope of services. • The Partners will give prompt notice to Lochner whenever the Partners observes or becomes aware of any development that affects the scope or timing of Lochner's services. • The project will be performed in a continuous manner without significant work stoppages or delays. z MANPOWER/BUDGET ESTIMATE -AMENDMENT 4 BRUSHY CREEK REGIONAL WASTEWATER TREATMENT FACILITY - EAST PLANT EXPANSION TO 30 MGD Task Project Senior Labor Total Manager Engineer EIT Admin Total Cost Expenses Cost Hrs Hrs Hrs Hrs Hrs $ $ $ 1 Project Management 12 8 20 $4,440 $4,440 2 Site Visits 16 24 40 $8,760 $500 $9,260 3 Construction Progress Meetings 16 32 1 48 $10,080 $10,080 4 RFI Review 6 8 14 $3,120 $3,120 5 Start-up Services 16 24 40 $8,760 $100 $8,860 6 OPCC-Unfinished Work 8 1 8 1 16 32 $7,240 $7,240 Total Amendment 4 74 1 8 104 8 194 $42,400 600 $43,000 Cf. Lochner 6/29/2026 VeLs