CM-2026-236 - 9/18/2026 A PROFESSIONAL CONSULTING SERVICES AGREEMENT
BETWEEN THE CITY OF ROUND ROCK
AND PLUMMER ASSOCIATES,INC.
RELATED TO THE COMPLETION OF CRITICAL ITEMS FOR THE
BRUSHY CREEK REGIONAL WASTEWATER SYSTEM
EAST WASTEWATER TREATMENT PLANT 30MGD EXPANSION PROJECT
THE STATE OF TEXAS §
THE CITY OF ROUND ROCK § KNOW ALL BY THESE PRESENTS
COUNTY OF WILLIAMSON §
COUNTY OF TRAVIS §
THIS AGREEMENT(the "Agreement") for professional consulting services, specifically
services related to the completion of critical items for the Brushy Creek Regional Wastewater
System East Wastewater Treatment Plant 30MGD Expansion Project is made on this 18 day
of lembe( , 2026, by and between the CITY OF ROUND ROCK, a Texas home-rule
municipal corporation with offices located at 221 East Main Street, Round Rock, Texas 78664-
5299 (the"City"), and PLUMMER ASSOCIATES, INC., located at 8911 North Capital of Texas
Highway, Suite 1350, Austin, Texas 78759 ("Consultant"). City and Consultant shall
individually be referred to as a"party,"and collectively referred to as the "parties."
RECITALS:
WHEREAS, City has determined that it has a need for professional consulting services
related to the completion of critically items remaining for the Brushy Creek Regional
Wastewater System East Wastewater Treatment Plant 30MGD Expansion Project ("Consulting
Services"); and
WHEREAS,City desires to contract with Consultant for the Consulting Services; and
WHEREAS, the parties desire to enter into this Agreement to set forth in writing their
respective rights, duties and obligations hereunder;
NOW, THEREFORE, in consideration of the mutual promises contained herein and
other good and valuable consideration, the sufficiency and receipt of which are hereby
acknowledged, it is mutually agreed between the parties as follows:
1.0 EFFECTIVE DATE,DURATION,AND TERM
A. This Agreement shall be effective on the date set forth in the introductory
paragraph above and shall remain in full force and effect unless and until it expires by operation
of the term indicated herein, or is terminated as provided herein.
CM -2021,-2 31
B. This Agreement shall expire upon successful completion of the services,
estimated to be no later than July 31, 2027.
C. City and the Consultant reserve the right to review the Agreement at any time and
may elect to terminate the Agreement with or without cause.
2.0 CITY SERVICES
City shall provide services set forth in the attached proposal attached as Exhibit "A,"
incorporated herein by reference for all purposes.
3.0 CONSULTING SERVICES
Consultant shall satisfactorily provide all Consulting Services described herein and as set
forth in Exhibit "B," attached hereto and incorporated herein for all purposes, pursuant to the
Work Schedule set forth in Exhibit "C," attached hereto and incorporated herein by reference
for all purposes. Consultant's undertaking shall be limited to performing Consulting Services for
City and/or advising City concerning those matters on which Consultant has been specifically
engaged. Consultant shall perform the Consulting Services in accordance with this Agreement in
a professional and workmanlike manner.
4.0 LIMITATION TO CONSULTING SERVICES
Consultant and City agree that the Consulting Services to be performed are enumerated in
Exhibit"B," and may only be modified by a written Supplemental Agreement executed by both
parties as described in Section 10.0.
5.0 CONTRACT AMOUNT
A. In consideration for providing the Consulting Services, Consultant shall be paid in
accordance with the rates and fees included in the attached Exhibit "D," attached hereto and
incorporated herein by reference for all purposes.
B. Consultant's total compensation for Consulting Services hereunder shall not
exceed $100,000.00. This amount represents the absolute limit of City's liability to Consultant
hereunder unless same shall be changed by Supplemental Agreement, and City shall pay, strictly
within the not-to-exceed sum recited herein, Consultant's fees for work done on behalf of City.
6.0 INVOICE REQUIREMENTS AND TERMS OF PAYMENT
A. Invoices: To receive payment, Consultant shall prepare and submit detailed
invoices to the City, in accordance with the delineation contained herein, for Consulting Services
rendered. Such invoices for Consulting Services shall detail the services performed, along with
documentation for each service performed. Payment to Consultant shall be made on the basis of
the invoices submitted by Consultant and approved by the City. Such invoices shall conform to
2
the amounts set forth in Exhibit"D."
B. Backup Material. Should additional backup material be requested by the City
relative to Consulting Services, Consultant shall promptly comply. In this regard, should the City
determine it necessary, Consultant shall make all records and books relating to this Agreement
available to the City for inspection and auditing purposes.
C. Payment of Invoices: The City reserves the right to correct any error that may be
discovered in any invoice that may have been paid to Consultant and to adjust same to meet the
requirements of this Agreement. Following approval of an invoice,the City shall endeavor to pay
Consultant promptly, but no later than the time period required under the Texas Prompt Payment
Act described in Section 8 herein.
D. Taxes. The City is exempt from Federal Excise and State Sales Tax. Therefore,
such taxes shall not be included in Consultant's invoices.
7.0 INSURANCE
Consultant shall meet all City of Round Rock Insurance Requirements set forth at:
https://www.roundrocktexas.gov/wp-content/uploads/2024/12/CORR-Insurance-08-2024.pdf
8.0 PROMPT PAYMENT POLICY
In accordance with Chapter 2251, V.T.C.A., Texas Government Code, any payment to be
made by the City to Consultant will be made within thirty (30) days of the date the performance
of the Consulting Services under this Agreement are completed, or the date the City receives a
correct invoice for the Consulting Services, whichever is later. Consultant may charge interest on
an overdue payment at the "rate in effect" on September 1 of the fiscal year in which the
payment becomes overdue, in accordance with V.T.C.A., Texas Government Code, Section
2251.025(b). This Prompt Payment Policy does not apply to payments made by the City in the
event:
(1) There is a bona fide dispute between the City and Consultant, a contractor,
subcontractor, or supplier about the service performed that cause the payment
to be late; or
(2) There is a bona fide dispute between Consultant and a subcontractor or
between a subcontractor and its supplier about the service performed that
causes the payment to be late; or
(3) The terms of a federal contract, grant, regulation, or statute prevent the City
from making a timely payment with federal funds; or
(4) The invoice is not mailed to the City in strict accordance with any instruction
on the purchase order relating to the payment.
3
9.0 NON-APPROPRIATION AND FISCAL FUNDING
This Agreement is a commitment of the City's current revenues only. It is understood and
agreed that the City shall have the right to terminate this Agreement at the end of any City fiscal
year if the governing body of the City does not appropriate funds sufficient to purchase the
Consulting Services as determined by the City's budget for the fiscal year in question. The City
may affect such termination by giving Consultant a written notice of termination at the end of its
then-current fiscal year.
10.0 SUPPLEMENTAL AGREEMENT
The terms of this Agreement may be modified by written Supplemental Agreement
hereto, duly authorized by City Council or by the City Manager, if the City determines that there
has been a significant change in (1) the scope, complexity, or character of the Consulting
Services to be performed; or (2) the duration of the work. Any such Supplemental Agreement
must be executed by both parties within the period specified as the term of this Agreement.
Consultant shall not perform any work or incur any additional costs prior to the execution, by
both parties, of such Supplemental Agreement. Consultant shall make no claim for extra work
done or materials furnished unless and until there is full execution of any Supplemental
Agreement, and the City shall not be responsible for actions by Consultant nor for any costs
incurred by Consultant relating to additional work not directly authorized by Supplemental
Agreement.
11.0 TERMINATION AND DEFAULT
A. Termination: It is agreed and understood by Consultant that the City may
terminate this Agreement for the convenience of the City, upon written notice to Consultant (the
"Date of Termination,") with the understanding that immediately upon receipt of said notice all
work being performed under this Agreement shall cease. Consultant shall invoice the City for
work satisfactorily completed and shall be compensated in accordance with the terms hereof for
work accomplished prior to the Date of Termination. Consultant shall not be entitled to any lost
or anticipated profits for work terminated under this Agreement. Unless otherwise specified in
this Agreement, all data, information, and work product related to this Project shall become the
property of the City upon termination of this Agreement and shall be promptly delivered to the
City in a reasonably organized form without restriction on future use. Should the City
subsequently contract with a new consultant for continuation of service on the Project,
Consultant shall cooperate in providing information.
Termination of this Agreement shall extinguish all rights, duties, and obligations of the
terminating party and the terminated party to fulfill contractual obligations. Termination under
this section shall not relieve the terminated party of any obligations or liabilities which occurred
prior to termination.
Nothing contained in this section shall require the City to pay for any work which it
deems unsatisfactory,or which is not performed in compliance with the terms of this Agreement.
4
B. Default: Either party may terminate this Agreement, in whole or in part, for
default if the Party provides the other Party with written notice of such default and the other fails
to satisfactorily cure such default within ten (10) business days of receipt of such notice (or a
greater time if agreed upon between the Parties).
If default results in termination of this Agreement, then the City shall give consideration
to the actual costs incurred by Consultant in performing the work to the date of default. The cost
of the work that is useable to the City,the cost to the City of employing another firm to complete
the useable work, and other factors will affect the value to the City of the work performed at the
time of default. Neither party shall be entitled to any lost or anticipated profits for work
terminated for default hereunder.
The termination of this Agreement for default shall extinguish all rights, duties, and
obligations of the terminating Party and the terminated Party to fulfill contractual obligations.
Termination under this section shall not relieve the terminated party of any obligations or
liabilities which occurred prior to termination.
Nothing contained in this section shall require the City to pay for any work which it
deems unsatisfactory, or which is not performed in compliance with the terms of this Agreement.
12.0 NON-SOLICITATION
Except as may be otherwise agreed in writing, during the term of this Agreement and for
twelve (12) months thereafter, neither the City nor Consultant shall offer employment to or shall
employ any person employed then or within the preceding twelve (12) months by the other or
any affiliate of the other if such person was involved, directly or indirectly, in the performance of
this Agreement. This provision shall not prohibit the hiring of any person who was solicited
solely through a newspaper advertisement or other general solicitation.
13.0 INDEPENDENT CONTRACTOR STATUS
Consultant is an independent contractor and is not the City's employee. Consultant's
employees or subcontractors are not the City's employees. This Agreement does not create a
partnership, employer-employee, or joint venture relationship. No party has authority to enter
into contracts as agent for the other party. Consultant and the City agree to the following rights
consistent with an independent contractor relationship:
(1) Consultant has the right to perform services for others during the term hereof.
(2) Consultant has the sole right to control and direct the means, manner and method
by which it performs its Consulting Services required by this Agreement.
(3) Consultant has the right to hire assistants as subcontractors, or to use employees
to provide the services required by this Agreement.
5
(4) Consultant or its employees or subcontractors shall perform Consulting Services
required hereunder, and the City shall not hire, supervise, or pay assistants to help
Consultant.
(5) Neither Consultant nor its employees or subcontractors shall receive training from
the City in skills necessary to perform Consulting Services required by this
Agreement.
(6) City shall not require Consultant or its employees or subcontractors to devote full
time to performing the Consulting Services required by this Agreement.
(7) Neither Consultant nor its employees or subcontractors are eligible to participate
in any employee pension, health, vacation pay, sick pay, or other fringe benefit
plan of the City.
14.0 CONFIDENTIALITY AND MATERIALS OWNERSHIP
Any and all programs, data, or other materials furnished by the City for use by Consultant
in connection with the Consulting Services to be performed under this Agreement, and any and
all data and information gathered by Consultant, shall be held in confidence by Consultant as set
forth hereunder. Each party agrees to take reasonable measures to preserve the confidentiality of
any proprietary or confidential information relative to this Agreement, and to not make any use
thereof other than for the performance of this Agreement, provided that no claim may be made
for any failure to protect information that occurs more than three (3) years after the end of this
Agreement.
The parties recognize and understand that the City is subject to the Texas Public
Information Act and its duties run in accordance therewith.
All data relating specifically to the City's business and any other information which
reasonably should be understood to be confidential to City is confidential information of City.
Consultant's proprietary software, tools, methodologies, techniques, ideas, discoveries,
inventions, know-how, and any other information which reasonably should be understood to be
confidential to Consultant is confidential information of Consultant. The City's confidential
information and Consultant's confidential information is collectively referred to as "Confidential
Information." Each party shall use Confidential Information of the other party only in
furtherance of the purposes of this Agreement and shall not disclose such Confidential
Information to any third party without the other party's prior written consent, which consent
shall not be unreasonably withheld. Each party agrees to take reasonable measures to protect the
confidentiality of the other party's Confidential Information and to advise their employees of the
confidential nature of the Confidential Information and of the prohibitions herein.
Notwithstanding anything to the contrary contained herein, neither party shall be
obligated to treat as confidential any information disclosed by the other party (the "Disclosing
Party") which: (1) is rightfully known to the recipient prior to its disclosure by the Disclosing
6
Party; (2) is released by the Disclosing Party to any other person or entity (including
governmental agencies) without restriction; (3) is independently developed by the recipient
without any reliance on Confidential Information; or (4) is or later becomes publicly available
without violation of this Agreement or may be lawfully obtained by a party from any non-party.
Notwithstanding the foregoing, either party will be entitled to disclose Confidential Information
of the other to a third party as may be required by law, statute, rule or regulation, including
subpoena or other similar form of process, provided that (without breaching any legal or
regulatory requirement) the party to whom the request is made provides the other with prompt
written notice and allows the other party to seek a restraining order or other appropriate relief.
Subject to Consultant's confidentiality obligations under this Agreement, nothing herein shall
preclude or limit Consultant from providing similar services for other clients.
Notwithstanding the foregoing, either party will be entitled to disclose Confidential
Information of the other to a third party as may be required by law, statute, rule or regulation,
including subpoena or other similar form of process, provided that (without breaching any legal
or regulatory requirement)the party to whom the request is made provides the other with prompt
written notice and allows the other party to seek a restraining order or other appropriate relief.
Subject to Consultant's confidentiality obligations under this Agreement.
Neither the City nor Consultant will be liable to the other for inadvertent or accidental
disclosure of Confidential Information if the disclosure occurs notwithstanding the party's
exercise of the same level of protection and care that such party customarily uses in safeguarding
its own proprietary and confidential information.
Notwithstanding anything to the contrary in this Agreement, the City will own as its sole
property all written materials created, developed, gathered, or originally prepared expressly for
the City and delivered to the City under the terms of this Agreement (the "Deliverables"); and
Consultant shall own any general skills, know-how, expertise, ideas, concepts, methods,
techniques, processes, software, or other similar information which may have been discovered,
created, developed or derived by Consultant either prior to or as a result of its provision of
Consulting Services under this Agreement (other than Deliverables). Consultant shall have the
right to retain copies of the Deliverables and other items for its archives. Consultant's working
papers and Consultant's Confidential Information (as described herein) shall belong exclusively
to the Consultant. "Working papers" shall mean those documents prepared by Consultant during
the course of performing the Project including, without limitation, schedules, analyses,
transcriptions, memos, designed and developed data visualization dashboards and working notes
that serve as the basis for or to substantiate the Project. In addition, Consultant shall retain sole
and exclusive ownership of its know-how, concepts,techniques,methodologies, ideas,templates,
dashboards, code and tools discovered, created or developed by Consultant during the
performance of the Project that are of general application and that are not based on City's
Confidential Information hereunder(collectively, "Consultant's Building Blocks"). To the extent
any Deliverables incorporate Consultant's Building Blocks, Consultant gives City a non-
exclusive, non-transferable, royalty-free right to use such Building Blocks solely in connection
with the deliverables. Subject to the confidentiality restrictions mentioned above, Consultant
may use the deliverables and the Building Blocks for any purpose. Except to the extent required
7
by law or court order, City will not otherwise use, or sublicense or grant any other party any
rights to use, copy or otherwise exploit or create derivative works from Consultant's Building
Blocks.
City shall have a non-exclusive, non-transferable license to use Consultant's Confidential
Information for City's own internal use and only for the purposes for which they are delivered to
the extent that they form part of the Deliverables.
15.0 WARRANTIES
Consultant represents that all Consulting Services performed hereunder shall be
performed consistent with generally prevailing professional or industrial standards and shall be
performed in a professional and workmanlike manner. Consultant shall re-perform any work not
in compliance with this representation.
16.0 LIMITATION OF LIABILITY
Should any of Consultant's services not conform to the requirements of the City or of this
Agreement, then and in that event the City shall give written notification to Consultant;
thereafter, (a) Consultant shall either promptly re-perform such Consulting Services to the City's
reasonable satisfaction at no additional charge, or (b) if such deficient Consulting Services
cannot be cured within the cure period set forth herein, then this Agreement may be terminated
for default.
In no event will Consultant be liable for any loss, damage, cost or expense attributable to
negligence, willful misconduct or misrepresentations by the City, its directors, employees or
agents.
Neither party's liability, in contract, tort (including negligence) or any other legal or
equitable theory, (a) shall exceed the professional fees paid or due to Consultant pursuant to this
Agreement or (b) include any indirect, incidental, special, punitive or consequential damages,
even if such party has been advised of the possibility of such damages. Such excluded damages
include,without limitation, loss of data, loss of profits and loss of savings of revenue.
17.0 INDEMNIFICATION
Consultant shall save and hold harmless City and its officers and employees from all
claims and liabilities due to activities of his/her/itself and his/her/its agents or employees,
performed under this Agreement, which are caused by or which result from the negligent error,
omission, or negligent act of Consultant or of any person employed by Consultant or under
Consultant's direction or control.
Consultant shall also save and hold City harmless from any and all expenses, including
but not limited to reasonable attorneys' fees which may be incurred by City in litigation or
otherwise defending claims or liabilities which may be imposed on City as a result of such
8
negligent activities by Consultant, its agents, or employees.
18.0 ASSIGNMENT AND DELEGATION
The parties each hereby bind themselves, their successors, assigns and legal
representatives to each other with respect to the terms of this Agreement. Neither party may
assign any rights or delegate any duties under this Agreement without the other party's prior
written approval, which approval shall not be unreasonably withheld.
19.0 LOCAL,STATE,AND FEDERAL TAXES
Consultant shall pay all income taxes, and FICA (Social Security and Medicare taxes)
incurred while performing Consulting Services under this Agreement. The City will not do the
following:
(1) Withhold FICA from Consultant's payments or make FICA payments on its
behalf;
(2) Make state and/or federal unemployment compensation contributions on
Consultant's behalf; or
(3) Withhold state or federal income tax from any of Consultant's payments.
If requested, the City shall provide Consultant with a certificate from the Texas State
Comptroller indicating that the City is a non-profit corporation and not subject to State of Texas
Sales and Use Tax.
20.0 COMPLIANCE WITH LAWS,CHARTER,AND ORDINANCES
A. Consultant, its consultants, agents, employees and subcontractors shall use best
efforts to comply with all applicable federal and state laws, the Charter and Ordinances of the
City of Round Rock, as amended, and with all applicable rules and regulations promulgated by
local, state and national boards, bureaus and agencies. Consultant shall further obtain all permits,
licenses, trademarks, or copyrights required in the performance of the Consulting Services
contracted for herein, and same shall belong solely to the City at the expiration of the term of this
Agreement.
B. In accordance with Chapter 2271, Texas Government Code, a governmental entity
may not enter into a contract with a company for goods and services unless the contract contains
written verification from the company that it: (1)does not boycott Israel; and(2)will not boycott
Israel during the term of a contract. The signatory executing this Agreement on behalf of
Consultant verifies Consultant does not boycott Israel and will not boycott Israel during the term
of this Agreement.
C. In accordance with Chapter 2274, Texas Government Code, a governmental entity
may not enter into a contract with a company with at least ten (10) full-time employees for a
9
value of at least One Hundred Thousand and No/100 Dollars ($100,000.00) unless the contract
has a provision verifying that it: (1) does not have a practice, policy, guidance, or directive that
discriminates against a firearm entity or firearm trade association; and (2) will not discriminate
during the term of the contract against a firearm entity or firearm trade association. The signatory
executing this Agreement on behalf of Consultant verifies Consultant does not have a practice,
policy, guidance, or directive that discriminates against a firearm entity or firearm trade
association, and it will not discriminate during the term of this Agreement against a firearm
entity or firearm trade association.
D. In accordance with Chapter 2274, Texas Government Code, a governmental entity
may not enter into a contract with a company with at least ten (10) full-time employees for a
value of at least One Hundred Thousand and No/100 Dollars ($100,000.00) unless the contract
has a provision verifying that it: (1) does not boycott energy companies; and (2) will not boycott
energy companies during the term of this Agreement. The signatory executing this Agreement on
behalf of Consultant verifies Consultant does not boycott energy companies, and it will not
boycott energy companies during the term of this Agreement.
21.0 FINANCIAL INTEREST PROHIBITED
Consultant covenants and represents that Consultant, its officers, employees, agents,
consultants and subcontractors will have no financial interest, direct or indirect, in the purchase
or sale of any product, materials or equipment that will be recommended or required hereunder.
22.0 DESIGNATION OF REPRESENTATIVE
The City hereby designates the following representative authorized to act on its behalf
with regard to this Agreement:
Rebecca Vento
Senior Engineer—Public Works Department
(512) 341-3129
rvento(a,roundrocktexas.gov
23.0 NOTICES
All notices and other communications in connection with this Agreement shall be in
writing and shall be considered given as follows:
(A) When delivered personally to recipient's address or email address as below; or
(B) Three (3) days after being deposited in the United States mail, with postage
prepaid to the recipient's address as stated below.
10
Notice to Consultant:
Plummer Associates, Inc.
8911 North Capital of Highway Texas
Suite 1350,
Austin, Texas 78759
Notice to City:
City Manager, City of Round Rock
221 East Main Street
Round Rock, TX 78664
AND TO:
Stephanie L. Sandre, City Attorney
309 East Main Street
Round Rock, TX 78664
(C) Nothing contained in this section shall be construed to restrict the transmission of
routine communications between representatives of the City and Consultant.
24.0 APPLICABLE LAW, ENFORCEMENT,AND VENUE
This Agreement shall be enforceable in Round Rock, Texas, and if legal action is
necessary by either party with respect to the enforcement of any or all of the terms or conditions
herein, exclusive venue for same shall lie in Williamson County, Texas. This Agreement shall be
governed by and construed in accordance with the laws and court decisions of Texas.
25.0 EXCLUSIVE AGREEMENT
The terms and conditions of this Agreement, including exhibits, constitute the entire
agreement between the parties and supersede all previous communications, representations, and
agreements, either written or oral,with respect to the subject matter hereof. The parties expressly
agree that, in the event of any conflict between the terms of this Agreement and any other
writing,this Agreement shall prevail.No modifications of this Agreement will be binding on any
of the parties unless acknowledged in writing by the duly authorized governing body or
representative for each party.
26.0 DISPUTE RESOLUTION
The City and Consultant hereby expressly agree that no claims or disputes between the
parties arising out of or relating to this Agreement, or a breach thereof shall be decided by any
arbitration proceeding, including without limitation, any proceeding under the Federal
Arbitration Act(9 USC Section 1-14)or any applicable state arbitration statute.
11
27.0 SEVERABILITY
The invalidity, illegality, or unenforceability of any provision of this Agreement or the
occurrence of any event rendering any portion of provision of this Agreement void shall in no
way affect the validity or enforceability of any other portion or provision of this Agreement. Any
void provision shall be deemed severed from this Agreement, and the balance of this Agreement
shall be construed and enforced as if this Agreement did not contain the particular portion of
provision held to be void. The parties further agree to amend this Agreement to replace any
stricken provision with a valid provision that comes as close as possible to the intent of the
stricken provision. The provisions of this Article shall not prevent this entire Agreement from
being void should a provision which is of the essence of this Agreement be determined void.
28.0 STANDARD OF CARE
Consultant represents that it is specially trained, experienced and competent to perform
all of the Consulting Services, responsibilities and duties specified herein and that such
Consulting Services, responsibilities and duties shall be performed, whether by Consultant or
designated subconsultants, in a manner acceptable to the City and according to generally
accepted business practices.
29.0 GRATUITIES AND BRIBES
City, may by written notice to Consultant, cancel this Agreement without incurring any
liability to Consultant if it is determined by City that gratuities or bribes in the form of
entertainment, gifts, or otherwise were offered or given by Consultant or its agents or
representatives to any City Officer, employee or elected representative with respect to the
performance of this Agreement. In addition, Consultant may be subject to penalties stated in
Title 8 of the Texas Penal Code.
30.0 RIGHT TO ASSURANCE
Whenever either party to this Agreement, in good faith, has reason to question the other
party's intent to perform hereunder, then demand may be made to the other party for written
assurance of the intent to perform. In the event that no written assurance is given within the
reasonable time specified when demand is made,then and in that event the demanding party may
treat such failure an anticipatory repudiation of this Agreement.
31.0 MISCELLANEOUS PROVISIONS
(A) Time is of the Essence. Consultant agrees that time is of the essence and that any
failure of Consultant to complete the Consulting Services for each Phase of this Agreement
within the agreed Project schedule may constitute a material breach of the Agreement.
12
Consultant shall be fully responsible for its delays or for failures to use reasonable efforts
in accordance with the terms of this Agreement. Where damage is caused to City due to
Consultant's failure to perform in these circumstances, City may withhold, to the extent of such
damage, Consultant's payments hereunder without a waiver of any of City's additional legal
rights or remedies. City shall render decisions pertaining to Consultant's work promptly to avoid
unreasonable delays in the orderly progress of Consultant's work.
(B) Force Majeure. Notwithstanding any other provisions hereof to the contrary, no
failure, delay or default in performance of any obligation hereunder shall constitute an event of
default or breach of this Agreement, only to the extent that such failure to perform, delay or
default arises out of causes beyond control and without the fault or negligence of the party
otherwise chargeable with failure, delay or default; including but not limited to acts of God, acts
of public enemy, civil war, insurrection, riots, fires, floods, explosion, theft, earthquakes, natural
disasters or other casualties, strikes or other labor troubles, which in any way restrict the
performance under this Agreement by the parties.
(C) Section Numbers. The section numbers and headings contained herein are
provided for convenience only and shall have no substantive effect on construction of this
Agreement.
(D) Waiver. No delay or omission by either party in exercising any right or power
shall impair such right or power or be construed to be a waiver. A waiver by either party of any
of the covenants to be performed by the other or any breach thereof shall not be construed to be a
waiver of any succeeding breach or of any other covenant. No waiver of discharge shall be valid
unless in writing and signed by an authorized representative of the party against whom such
waiver or discharge is sought to be enforced.
(E) Multiple Counterparts. This Agreement may be executed in multiple
counterparts, which taken together shall be considered one original. The City agrees to provide
Consultant with one fully executed original.
[Signatures on the following page.]
13
IN WITNESS WHEREOF, the parties have executed this Agreement on the dates
hereafter indicated.
City of Ro nd Rock, T xas Plummer Associates, Inc.
By: By: Perran Sean Hutton o-`".. m.,..:..mm
Printed Name: 11LdC.S C++ Printed Name: Perran S. Hutton, PE
Title: CII'-1-I1 Wove% Title: Team Leader
Date Signed: q t$/2O2. , Date Signed: 9/15/2026
For City,Attest:
By: (/-0)/M.4)&k.a
Ann Franklin, City Clerk
For City,Approved as to Form:
BY:
tephanie L. Sandre, City Attorney
14
Exhibit"A"
City Services
Brushy Creek East Regional WWTP
• ti� 30 MGD Incomplete Items Work Packages
ttiPLUMMER
098203201
Exhibit A
City Services
The City of Round Rock will furnish to the Engineer the following items/information:
• Attend kickoff meeting and progress meetings.
• Designate a person to act as City's representative with respect to the services to be
performed or furnished by the Engineer. This representation will have authority to
transmit instructions, receive information, interpret, and define City's policies and
decisions with respect to engineering services.
• Provide criteria and full information as to City's requirements for the project, including
objectives and constraints and furnish copies of standards which City will require to be
included in the project.
• Assist Engineer by placing available information pertinent to the Project, including
previous information and other data relative to the Project at the Engineer's disposal.
Engineer will reasonably rely upon the accuracy, timeliness, and completeness of the
information provided by the City.
• City will give prompt notice to Engineer whenever City observe or become aware of
development that affects the scope or timing of Engineer's services.
• Provide digital design files or records available which would assist in the completion of
the project development.
• Governmental review fees, submittal fees, recordation fees, and other fees associated
with the project shall be paid for directly by the City.
• Timely review and comment, within 10 business days, on the deliverables.
Exhibit"B"
Consulting Services
Brushy Creek East Regional WWTP
30 MGD Incomplete Items Work Packages
0982-032-01
EXHIBIT B
Engineering Services
Engineering/Professional Services to be provided for priority items from the 30 MGD expansion
construction project.These incomplete items require working into"packages"for reassigning.
Background
The Brushy Creek East Regional Wastewater Treatment Plant(Plant)is owned by the Brushy Creek Regional
Wastewater System (BCRWWS), who are the Cities of Round Rock (City), Cedar Park, Leander and Austin.
The engineering team, led by Prime consultant Plummer Associates, and sub consultants Freese& Nichols
and Lochner/Egis(Engineer)designed the most recent 10 MGD expansion, increasing the Plant's capacity
to 30 MGD. The Engineer has also been providing construction administration services. On August 27th,
2026,the City of Round Rock terminated the general contractor(Thalle Construction Company)for multiple
breaches of its contract with the City. As a result, the current 30 MGD construction project has not been
completed per the design documents originally conformed by the Engineer in April 2020. The City is
coordinating with the bond surety to complete the original scope of work and intends to hire a replacement
contractor to complete the project as soon as possible.The Engineer will assist the City by providing review
of the remaining "priority" scope items and creating work packages for an alternative contractor to price
and ultimately execute.
The City has retained the services of the Engineer to perform miscellaneous/engineering tasks on an "as
needed" basis, for tasks deemed necessary by the City staff to assist in the planning, review, assessment,
and preparation of the above referenced work packages for the incomplete construction scope.
Basic Services:
The purpose of this scope of services is to provide additional services for:
1. Review and assessment of the current incomplete work list [Attachment 1]
2. Field/site visits accompanying the City staff and potential general contractor(s)or their subs.
3. Coordination with current equipment suppliers.
4. Re-packaging of existing drawings and specifications to outline incomplete work for perspective
contractors.This may also include field photographs and descriptive reports.
5. Assistance with producing bid forms.
6. Review of pricing and work plans submitted by prospective contractor.
7. Engineering administration support during the execution of the work packages, such as responding
to RFIs and submittal review and approval.
Meetings/Site Visits:
Attendance in-person within the Central Texas area by staff based in Plummer Austin office(If'local' staff
are unavailable Plummer,or their subconsultants will provide expertise from other Texas offices to an
equivalent level of experience and qualifications). Attendance can be virtual if required or preferred by the
City.Take meeting minutes and summaries,then share with the City.The Engineer will inform the City on
which staff plan to attend the meeting in advance.
Administration and Status Reporting:
Monthly status reports and invoices will be submitted electronically to City for review and approval.
Page 1 of 3
Brushy Creek East Regional WWTP
30 MGD Incomplete Items Work Packages
0982-032-01
Deliverables:
Work packages of existing drawings with appendices of supporting data, in pdf format.
Subconsultant:
The same subconsultants as named in above agreement will be utilized based on their specialty and the
required work that needs addressing. If additional subconsultants are required an amendment to this
agreement will be required.
Time of Completion:
The Engineer expects the initial basic services to continue and last for approximately 3 months, until a
contractor is ready to perform the work.The schedule for actual construction work completion is unknown
currently, but the City expects to complete all priority work by July 2027. Plummer will provide
deliverables in a timely manner and respond to City's requests accordingly. Engineer and the City shall
agree on reasonable deliverable dates,once specific work is identified, and Engineer has received all
required information to begin the task(s).
Compensation:
Basis of Payment—Hourly Rates Plus Reimbursable Expenses
City shall pay Engineer for Services as follows:
1. An amount equal to the monthly cumulative hours charged to the Project by each class of Engineer
employees times standard hourly rates for each applicable billing class, plus reimbursement of monthly
expenses incurred in connection with providing the Services and Engineer consultants'charges, if any.This
also applies to all subconsultants hours.
2. Engineers Standard Hourly Rates are attached as Exhibit D (including subconsultants).
3.The total compensation for services and reimbursable expenses will be agreed in each task order set
forth by the City, under this agreement a maximum combined total of not to exceed$100,000 shall be
authorized.
Insurance:
See attached certifies of insurance for Prime and subconsultant Engineer, Exhibit E.
Page 2 of 3
Brushy Creek East Regional WWTP
30 MGD Incomplete Items Work Packages
0982-032-01
LIST OF ASSUMPTIONS
The following assumptions were used when developing the scope of service and estimating the
compensation to Engineer:
1. No design work and construction services work is included in the above-mentioned scope of services
[Exhibit B].
2. All previous calculations, sizing, materials and equipment specifications / suitability have been
performed and are not required to be reassessed as part of this scope of work.
3. The following professional services are not included in this phase of work: Geotechnical
investigations, environmental assessments, architectural design, and subsurface utility
investigations.
4. The list of incomplete work which the Engineer is to assess, and package is attached to this
agreement as [Attachment 1]. If additional items are requested by the City,then an amendment to
this agreement maybe be required.
5. GIS mapping services or assistance with these services are not in the scope of work.
6. Additional effort associated with preparing bid packages or equipment selection for the ongoing 40
MGD/Rehabilitation work is not included.
7. No further cost estimating than already provided AACE Class 3 OPCC.
8. Because the original design is not being modified and the work is being undertaken under
emergency circumstances without a public bidding process, it is assumed that re-sealing of the
existing drawings and specifications is not required, as this agreement is between the city and the
engineer of record.
Page 3 of 3
Attachment 1
Discipline Location Area Detail Observation of Correction Needed Status Indicators Needed for Need Estimated Cost Priority
Substantial ed for
Architectural Blower Blower Door latching mechanism missing throw at top of Door#502C.See Yes Yes Priority 2
$1,400.00
Building Building Figure 8. liArchitectural Blower Blower Doors 501A and 502A do not close properly.Figure 9 and Figure 10 Yes Yes $30,000.00 Priority 2
Building Building
Architectural Blower Blower Door 501A.See Figure 5.Weatherstripping needs to be installed. Yes Yes Priority 2
Building Building
Architectural Blower Blower Door 501A.See Figure 5.Door does not close properly. Yes Yes Priority 2
Building Building
Architectural Blower Blower Exterior stone veneer grout shows signs of cracking.See Figure 29- Yes Yes Priority 3
Building Building Figure 30.Provide and install color-matching sealant at affected $300.00
locations to address cracking.
Architectural East Electrical East Electrical Door 1600A.SeeFigure 1 57,Figure 59 Yes Yes Priority 2
Building Building $6,000.00
Architectural East Electrical East Electrical Door 1600A.Install threshold. Yes Yes Priority 2
Building Building
Architectural East Electrical East Electrical Door 1600A.Finish installing Door hardware. Yes Yes Priority 2
Building Building
Architectural North North Sealant at scuppers does not match color of roof.See Figure 36. Yes Yes Priority 3
Electrical Electrical $200.00
Building Building
Architectural North North/East Roof material has not been applied per Specification Section 07 52 Yes Yes Priority 1
Electrical and Central 16,3.09.See $350,000.00
Building Electrical Figure 35-Figure 38.
Building
Architectural North North Extensive loss of mineral granules near scuppers.See Figure 35- Yes Yes Priority 1
Electrical Electrical Figure 38.
Building Building
Architectural North North Door 1602A.SeeFigure 1 Yes Yes Priority 2
Electrical Electrical $250.00
Building Building
Architectural North North Door 1602A.Install.weatherstripping. Yes Yes Priority 2
Electrical Electrical
Building Building
Architectural North North Finish installing door hardware at Door 101 B.See Figure 44-Figure Yes Yes Priority 2
Electrical Electrical 45. $4,500.00
Building Building
Architectural Blower Blower Standing water observed on roof. Yes Yes Priority 1
Building Building
Architectural Blower Blower Roof seam sealant is cracked and separating throughout. Yes Yes Priority 1
Building Building
Architectural Blower Blower Cracking observed in stone at ladder bolt. Yes Yes $1,200.00 Priority 1
Building Building
Architectural Blower Blower Steel angle at corner does not conform to Detail 2/A-1903;gap Yes Yes Priority 1
Building Building between stone and angle to be sealed to match adjacent
conditions(not filled with concrete). $1,500.00
Architectural North North Standing water observed on roof. Yes Yes $2,500.00 Priority 1
Electrical Build Electrical
Building
Architectural North North Punctures in roofing require proper repair Yes Yes $3,500.00 Priority 1
Electrical Build Electrical
Building
Architectural North North Missing stone at building corner Yes Yes $1,100.00 Priority 2
Electrical Build Electrical
Building
Architectural North North Cracking in stone at Door 1602Alamb Yes Yes $1,000.00 Priority 3
Electrical Build Electrical
Building AZ,
Architectural North North Threshold missing recessed pocket for door throw. Verification Yes Yes Priority 2
Electrical Build Electrical Required $1,000.00
Building
Architectural North North Threshold not installed. Verification Yes Yes Priority 2
Electrical Build Electrical Required $1,000.00
Building
Architectural East Electrical East Electrical Standing water observed on roof. Yes Yes $3,500.00 Priority 1
Building Building
Architectural East Electrical East Electrical Ladder bolts are not properly secured;washers/shims required Yes Yes $2,500.00 Priority 1
Building Building
Architectural East Electrical East Electrical Railings and stairs remain uninstalled. Yes Yes $6,000.00 Priority 1
Building Building
Civil Sludge Sludge Finish testing 12"drain between MH 15 and 43. Yes Yes Priority 2
receiving receiving $5,000.00
station station
Civil Site wide Site wide Complete Final Paving Yes Yes $425,000.00 Priority 3
Civil North Swale North Swale Complete Swale on North end of site. Yes Yes $10,000.00 Priority 3
Civil UV 2 UV 2 Install sidewalk around east electrical building. Yes Yes $5,000.00 Priority 3
Civil UV 2 UV 2 Install fencing around east end of UV2. Yes Yes $2,000.00 Priority 1
Electrical Relift Transfer Relift Transfer Local control station communications conductor currently run in Yes Yes Priority 3
Pump Pump same conduit as power conductors.***Retift pump work was not
needed.A credit is needed for the VFD in the reuse pump station ' $ 100,000.00
electrical building MCC that was not submitted/installed and
the wiring that was not pulled and terminated.
Electrical Relift Transfer Relift Transfer Motor thermostat not wired.***Relift pump work was not needed. Yes Yes Priority 3
Pump Pump A credit is needed for the VFD in the reuse pump station
electrical building MCC that was not submitted/installed and $ 2,500.00
the wiring that was not pulled and terminated.
Electrical Relift Transfer Relift Transfer Early break contacts from disconnect switch not wired.**"Relift Yes Yes Priority 3
Pump Pump pump work was not needed.A credit is needed for the VFD in the
reuse pump station electrical building MCC that was not $ 2,500.00
submitted/installed and the wiring that was not pulled and
terminated.
Electrical Sludge Storage Sludge Control panels were shown to be located beneath the blower Yes Yes None None
Blowers Storage canopies,confirm okay to have overhead exposure.***FNI
Blowers clarified this and it is okay.Remove from list.
Electrical Sludge Storage Sludge Blower 3 has a different,large junction box for the conduit to the Yes Yes None None
Blowers Storage north of the blower whereas the other blowers have full length
Blowers flexible conduit.***FNI clarified this and it is okay.Remove from
list.
Electrical Sludge Storage Wire Labeling Verify blower labeling and wiring match.The numbering is different Yes Yes Priority 3
Blowers than plans.`"'Update nameplates on front of Blowers. $1,000.00
Electrical ABT 3 ABT 3 Lightning protection system not completed/missing UL master Yes Yes $20,000.00 Priority 1
label.
Electrical ABT 3 ABT 3 Strain relief for mixers missing.Many of the hooks that were Yes Yes Priority 1
installed have been $20,000.00
pulled out of the walls.A more robust solution is needed.
Electrical ABT 3 ABT 3 Provide 3rd party testing and startup for equipment. Yes Yes $50,000.00 Priority 1
Electrical Aeration General Grounding needed at the southwest corner Yes Yes $3,500.00 Priority 1
Basins
Electrical Aeration Aeration No lightning protection system installed. Yes Yes $50,000.00 Priority 1
Basins Basin
Electrical Aeration Aeration ABT1 mixers do not have strain relief connectors for the mixer Yes Yes $20,000.00 Priority 1
Basins Basin cable.
Electrical Aeration Aeration Anaerobic Mixer disconnect switches have loose and unsupported Yes Yes Priority 1
Basins Basin conduit.Seal off $5,000.00
fitting missing on conduits in these areas.
Electrical Alum Storage&Lightening Grounding needs completion and lightening protection Yes Yes Priority 1
Feed Protection $15,000.00
System
Electrical Sludge Pump BFP Feed Local control panel 5 lacking label/tag. Yes Yes Priority 3
Station Pump Station $10,000.00
Electrical Blower Electrical LS-2 Alternating Panel has wire pulled to cabinet 2022-RWP-2101 Verification Yes Yes Priority 1
Building and others,but Alterman did not terminate in the panel(s). Prime Required
design is LS-2 Panel specifies connection,but Alterman cites
Plummer or Eaton drawing as not connecting,so didn't connect.
Needs to be connected.
Floats not working properly,so alternating panel(emergency float
nanell has h•en off for annrnximately 1 sear $50,000.00
Electrical Blower Electrical Main Huber control panel0320-MCP-1001 has never functioned Yes Yes Priority 1
Building properly since installation.Always some form of alarm messaging.
Needs to be resolved and function properly.
$50,000.00
Electrical Blower Electrical LS-2 Alternating panel has never been tested/used. Yes Yes $750.00 Priority 1
Building
Electrical Blower Electrical Main Huber control panel 0320-MCP-1001 has never functioned Yes Yes Priority 1
Building properly since installation. Always some form of alarm messaging.
Needs to be resolved and function properly.
$50,000.00
Electrical Chemical Chemical 2 fixtures mounted to ceiling should be wall mounted near tanks. Yes Yes $3,000.00 Priority 3
Building Storage
Electrical Chemical Chemical Heat trace for chemical piping missing. Yes Yes $6,000.00 Priority 1
Building Storage
Electrical Chemical Chemical Heat trace for the eyewash station missing. Yes Yes $5,000.00 Priority 1
Building Storage
Electrical East Electrical East Electrical Mixer VFD Gutter box(East Electrical Bld)has wires spliced with Yes Yes Priority 3
Building Building wire nuts.Contract $5,000.00
documents state no splices are to be permitted.
Electrical East Electrical Interior Install Cover.See Figure 60. Yes Yes Priority 3
Building $500.00
Electrical East Electrical Interior Finish installing wiring or cap off conduit.See Figure 60. Yes Yes Priority 3
Building $1,000.00
Electrical General/All All Areas Multiple locations:the number of conductors and size conductors Yes Yes Priority 3
Areas spliced with wirenuts is not allowed by the manufactured product.
At final walkthrough,the contractor wilt be required to remove $20,000.00
Electrical General/All All Areas UL Master Label for Lightning Protection Yes Yes $500.00 Priority 1
Areas
Electrical General/Alt All Areas Manholes around the Site.The top concrete lid of the manholes is Yes Yes Priority 1
Areas not aligned with the ring.This creates tight access to enter the
manholes.These need to be aligned with one another.We found a
junction box with a wire splice inside a manhole.Splicing is not
permitted for these types of circuits,and underground splices like
this are a major issue.This is dangerous as manhole can fill with
water,shorting out the splice and potentially damaging electrical
and process equipment.The manholes are dirty with debris,soil,
trash,etc.The cable racks do not currently support wire and are
missing insulators.Several wires are pulled tight and not trained
around the walls as specified.There are manholes where circuits
are routed in a common conduit instead of seperated per the
drawings.I do not know what the contractor did since they did not
follow the drawings. $150,000.00
Electrical ILS 2 ILS 2 Corrosion Found inside control/power panel.Terminal blocking, Yes Yes Priority 1
conductors and backplanes will not be approved in this state.Seal
off fittings missing.Grounding inside panel insufficient.Grounding
bar is needed. $500.00
Electrical EMH/IMH EMH EMH-56:Ground rod to be welded,all grounds bonded.Lid is offset, Yes Yes Priority 1
Manholes new ramneck needed.Conductor insulators missing. $3,500.00
Electrical EMH/IMH EMH EMH-67:Remove conductors from floor.Lid offset,new ramneck Yes Yes Priority 1
Manholes needed.Missing ground rod and bonding. $3,500.00
Electrical EMH/IMH EMH EMH-69:Grounding missing.Cleanup debris. Yes Yes Priority 1
Manholes $2,000.00
Electrical EMH/IMH EMH EMH-71:Missing ground rod.Cleanup debris.Lid offset,new Yes Yes Priority 1
$4,500.00
Manholes ramneck needed.
Electrical EMH/IMH EMH EMH-60:Ground missing.Cleanup debris. Yes Yes Priority 1
Manholes $3,500.00
Electrical EMH/IMH EMH EMH-59:Lid offset,new ramneck needed.Splice present,splices Verification Yes Yes Priority 1
Manholes notpermitted.Install ground rod.Cleanup debris. :•uired $3,500.00
Electrical EMH/IMH EMH EMH-60:Conduit not flush to watt.Ground rod missing.Missing Yes Yes Priority 1
Manholes insulators.Conductor arms broken.Remove conductors from floor. $3,500.00
Electrical EMH/IMH EMH EMH-70:Missing ground rod.Clean debris. Verification Yes Yes Priority 1
Manholes Required $3,500.00
Electrical North Interior Grounding Verification Yes Yes Priority 1
Electrical Required $3,000.00
Building
Electrical Plant Plant Multiple locations:the number of conductors and size conductors Yes Yes $ 25,000.00 Priority 3
spliced with wirenuts is not allowed by the manufactured product.
At final walkthrough,the contractor will be required to remove
multiple covers to expose conductor splices to verify they have
been corrected.
Electrical Plant Plant UL Master Label for Lightning Protection. Yes Yes Priority 1
Electrical PTU PTU Heat trace along grit lines not properly installed.Multiple wraps Yes Yes Priority 1
around valve bodies not complete.Coordinate with heat trace $5,000.00
manufacturer.
Electrical PTU PTU Lightning protection system not completed/missing UL master Yes Yes $5,000.00 Priority 1
label.
Electrical PTU PTU 3rd Party Testing Yes Yes Priority 1
Electrical PTU PTU Permanant Labels need to be installed for the following:Grit Pump Yes Yes Priority 3
Disconnects
Termination Cabinets
Slide Gate disconnects and E-Stop $1,250.00
Electrical PTU PTU Ductbank 56(Sheet E-121)seemingly missing three 1"Spare and Yes Yes Priority 3
two 2"Spare conduits.Contractor needs to label spare conduit and
install missing conduits. $30,000.00
Electrical PTU PTU Pole light west of Screen 1 missing. Yes Yes $8,500.00 Priority 1
Electrical PTU PTU Pole light east of grit chamber 4 missing.Contractor to provide pole Yes Yes Priority 1
fight at north stairwell.
Electrical PTU PTU Heat trace circuits are wired temporarly to 120V receptacles.Heat Yes Yes Priority 1
$5,000.00
trace to be wired per contract.
Electrical PTU Upper Grit The feed pipe have clamps to support the grounding wire but the Yes Yes Priority 3
Level Dewatering clamps are metal-to metal with the exterior face of the pipe.This
has caused damage to pipe coating.Repair coating and provide
pad between clamp and pipe
Electrical RAS/WAS-3 Disconnect Several conductors inside the RAS and WAS disconnect switches -., -j Yes Yes
$1,500.00 Priority 1
,
Switches had nicks in the copper wiring.
Electrical RAS/WAS-3 Heat Trace Hose bib piping not heat traced. Complete Yes Yes $4,000.00 Priority 2
Electrical RAS/WAS-3 Heat Trace Heat trace routed on WAS pump body.Heat trace should not be ,Comple Yes Yes Priority 1
$3,500.00
installed exposed.Remove from pump body.
Electrical RAS/WAS-3 Heat Trace Heat trace routed within conduit.Heat trace should be routed to ' Compl • Yes Yes Priority 1
splice kit then XHHW routed within conduits. $3,000.00
Electrical RAS/WAS-3 Arc Flash Arc flash labels needs to be added.Conduit tags are missing. .•'.t Comple Yes Yes Priority 1
Label
Electrical RAS/WAS-3 Heat Trace No heat trace thermostats observed. Not Complete Yes. Yes $4,500.00 Priority 1 _
Electrical RAS/WAS-3 Heat Trace Heat trace installed on valve bodies incorrectly.Install per Not Comple,!; Yes Yes Priority 1
$4,000.00
manufacturer's recommendations.
Electrical RAS/WAS-3 Flow Meter Substitute flow meter does not have any power?See electrical CompletL Yes Yes Priority 1
punchlist.
Electrical RAS/WAS-3 Hot Box Heat box and power socket not wired in,box has no heat and risks i Complete Yes Yes $1,700.00 Priority 1
freezing.
Electrical Scum Pump Scum Pit PLC has no programing. , Complete ' Yes Yes Priority 1
Station
Electrical Scum Pump Scum Pit Heat trace missing thermostat and exposed. i.Complete Yes Yes Priority 1
Station $1,000.00
Electrical Scum Pump Scum Pit Level transducer has been reading incorrectly.Conduit feeding .`Complete Yes Yes Priority 1
Station transducer is
damaged.
Electrical Scum Pump Scum Pump PLC at scum pump needs programming :-')Complete Yes Yes Priority 1
Station Station "'.
Electrical Scum Pump Scum Pump Level transfucer not reading correctly Yes Yes Priority 1
Station Station
Electrical Site Lighting Light Poles Light Pole Skirt Bases Yes Yes $1,000.00 Priority 3
Electrical Site Lighting Light Poles Light Pole Hand Hole Covers Yes Yes $1,000.00 Priority 3
Electrical Site Lighting Light Poles Repair Broken Pipe in Keeley Area Yes Yes Priority 2
Electrical Site Lighting Site Plan-B 2 Lights are currently not working and need to be corrected. Yes Yes Priority 2
(Final
Clarifiers
1-4)
Electrical Site Lighting Site Plan-B Perform testing on existing light pole that has not been tested. Yes Yes Priority 2
(Transfer
Pump
Station)
Electrical Site Lighting Site Plan-D 9 Lights are currently not working and need to be corrected. Yes Yes Priority 2
(SST 1&2)
Electrical Site Lighting Site Plan-F 3 Lights are currently not working and need to be corrected. Yes Yes Priority 2
(Alum
Storage)
Electrical Sludge Storage SST 1 Pull box on south side of Sludge Storage Blower Canopy 1 has Yes Yes Priority 3
spliced wires.These wires are also run in single conduit,drawings
show individual conduit for each circuit.Repull wire so that no
splices are present and install new wire in individual conduits. •
$4,000.00
Electrical Sludge Storage Sludge Confirm the control panel locations and wiring are depicted _ Yes Yes Priority 3
Blowers Storage correctly in the contractor as-builts since the control panels are not
Blowers installed in the locations as shown on the plans.Apply physical
labels/tags to all panels. .,
Electrical SST 2 Tags Tag at all circuits Complete Yes Yes $2,500.00 Priority 3
Electrical UV 1 UV 1 Spare conduits need to be labeled. Complete Yes Yes $1,000.00 Priority 3
Electrical UV 2 UV 2 3rd Party Testing Complete_: Yes Yes Priority 1
Electrical ABT 1 Aeration Basin 3 DO transmitter conduit is loose. '.h Compl_,,, Yes Yes $250.00 Priority 2
Basin Train 1 _ .
Electrical ABT 2 Aerobic Zone Electrical conduit line without any equipment connection ',Compl:tl Yes Yes $1,000.00 Priority 2
Electrical ABT 2 Aeration PLC rack receptacles wired through PLC cabient.This is not '''Complete ' Yes Yes $1,250.00 Priority 2
Basin Train 2 allowed. .
Electrical ABT 3 Electrical Electrical wiring is disconnected and sitting on concrete in multiple )Complete Yes Yes $1,250.00 Priority 2
places.
Electrical ABT 3 AB 3 Electrical conduit is mounted to foul air piping support Compld,t.; Yes Yes $1,000.00 Priority 2
Electrical ABT 3 AB 3 Overload not installed .,.)._Complete ' Yes Yes $4,500.00 Priority 2
Electrical Aeration Aeration Anoxic Zone DO analyzer conduits longer then needed and are not ,i Complex:' Yes Yes Priority 2
Basins Basin properly ` $35,000.00
supported.
Electrical Aeration Aeration Several lighting and receptacle are loose and are a place for water Yes Yes Priority 2
Basins Basin ingress.The plant has requested that this not be deferred to the
final punchlist since they use those
circuits to maintain and operate the plant. $4,500.00
Electrical Sludge Pump BFP Feed Sump pumps wires and junction box exposed. Yes Yes Priority 2
Station Pump Station $2,500.00
Electrical Sludge Pump BFP Feed Motor wiring flex conduit is inconsistent.Needs attention,see Yes Yes Priority 2
Station Pump Station photos. $2,500.00
Electrical Blower Blower Room Electrical conduit leading to equipment is disconnected,exposing Yes Yes $50,000.00 Priority
Building wiring
Electrical Central Central Remove cardboard within MCC-SST. Yes Yes Priority 2
Electrical Electrical $1,250.00
Building Building
Electrical Dewatering North BFPs New control panels are lacking sludge feed gpm readout. Yes Yes Priority 2
Building $5,000.00
Electrical Dewatering North BFPs Wiring and E-stop fixes/adjustments are in process with Alfa Laval Yes Yes Priority 2
Building per Javi.Need confirmation of corrections and completeness in
writing from contractor.
Electrical Dewatering Hopper 2 Level instrument signals are interfered by support strut and beam. Yes Yes Priority 2
Building Need to relocate to better Location for better readings of sludge
level without conflicts. $5,000.00
Electrical Dewatering Hopper 2 Wires exposed. Yes Yes $5,500.00 Priority 2
Building
Electrical Dewatering Dewatering Hoppers overflowing.Level is not being measured so system Yes Yes Priority 2
$10,000.00
Building Building cannot run in auto.
Electrical Dewatering Dewatering New press control panels no operating.City believes cable that Yes Yes Priority 2
Building Building was to be run to the $2,500.00
control panels was terminated in PLC 1350-PLC-1001.
Electrical Dewatering Dewatering Signals for hopper levels not wired to displays or control panels. Yes Yes Priority 2
Building Building Hopper currently
cannot run in Auto.
Electrical Dewatering Lower Level Electrical wiring and support attached to concrete barrier Yes Yes Priority 2
Building $5,000.00
Electrical Dewatering Lower Level Wiring not connected at compressor,due to no breaker Yes Yes $4,500.00 Priority 2
Building
Electrical Filters Building Filters Circuit breaker used is not GFEP. Yes Yes $3,000.00 Priority 1
Electrical PTU PTU Conduit for grounding of 350-SG-1101 too low,needs to beat Yes Yes Priority 2
minimum of 7'-0"AFF.
Electrical PTU PTU Level transducers at PT are set at approx.81"but zero set point is Yes Yes Priority 2
set to 81.5".Program need to be adjusted so flow can be calculated
correctly.
Electrical RAS/WAS-3 Float&Pump Float and pump wiring for sump pumps needs properly securing per Yes Yes Priority 2
standard details $3,500.00
Electrical RAS/WAS-3 Flow Meter All sockets in flow meter control panels missing front face(check Yes Yes Priority 2
electrical punchlist) $3,500.00
Electrical Sludge Storage Sludge Exposed wires need to be replaced.Wiring will not be accepted Yes Yes Priority 2
Blowers Blowers
Electrical Sludge Storage SST 1 Install seals in seal off fittings before equipment startup. Yes Yes Priority 2
Electrical Sludge Storage Sludge Small blowers panels,lots of exposed wire,missing junction box Yes Yes Priority 2
Blowers Storage cover.
Blowers
Electrical Sludge Storage Sludge Confirm the thermostats for each of the large blowers and small Yes Yes Priority 2
Blowers Storage blowers are installed and wired correctly.There was some
Blowers discussion of unknown terminations or signal wiring locations.
$2,500.00
Electrical Sludge Storage Sludge Air flow meters(typ 3):Sensor wire hung without clips/support, Yes Yes Priority 2
Blowers Storage excess wire just looped around strut.Susceptible to damage. $2,500.00
Blowers
Electrical Thickening Thickening Conduits to be sealed. Yes Yes $1,600.00 Priority 2
Building Building
Electrical UV 1 UV 1 Outlets have no power(check breakers) Yes Yes Priority 2
Electrical Aeration Aeration Aluminum conduit poured in the concrete sidewalk and directly Yes Yes Priority 3
Basins Basin buried below grade.This conduit must be PVC coated conduit
when passing through concrete $35,000.00
Electrical Blower Blowers 3&4 Conduit running along wall in place of future Blower LCPs.Conduit Yes Yes Priority 3
Building /Mechanical needs rerouting(see electrical for further details) $40,000.00
Electrical EMH/IMH IMH IMH-56:Lid is offset,new ramneck needed.Pullstrings for spare Yes Yes Priority 3
Manholes conduits to be added.Conductor insulators missing. $3,500.00
Electrical EMH/IMH EMH EMH-44:Lid is offset,new ramneck needed.Missing conductor Yes Yes Priority 3
Manholes insulators.Debris and dirt is excessive,remove dirt and debris from
manhole. $3,500.00
Electrical EMH/IMH EMH EMH-45:Lid is offset,new ramneck needed.Missing conductor Yes Yes Priority 3
Manholes insulators.Debris and dirt is excessive,remove dirt and debris from
manhole. $3,500.00
Electrical EMH/IMH IMH IMH-34:Missing insulators.Lid is offset,new ramneck needed. Yes Yes Priority 3
Manholes Debris needs to be removed. $1,000.00
Electrical EMH/IMH EMH EMH-47:Lid is offset,new ramneck needed.Missing insulators. Yes Yes Priority 3
Manholes $2,500.00
Electrical EMH/IMH EMH EMH-12:.Remove bracket blocking spare conduit.Conductor arms Yes Yes Priority 3
Manholes loose,in the way.Conductors resting on the floor.
$2,500.00
Electrical EMH/IMH IMH IMH-36:Lid is offset,new ramneck needed.Missing insulators. Yes Yes Priority 3
$1,500.00
Manholes Clean debris.
Electrical EMH/IMH EMH EMH-49:Lid offset,new ramneck needed. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH IMH IMH-37:Lid offset,new ramneck needed,missing insulators. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH EMH Resuse EMH:Controls from HOA in power conduit. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH IMH Resuse IMH:Not used when called for. Yes Yes $3,500.00 Priority 3
Manholes
Electrical EMH/IMH IMH IMH-38:Missing insulators.Lid offset,new ramneck needed. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH IMH IMH-67:Clean debris.Remove from conductors from floor.Lid Yes Yes Priority 3
Manholes offset,new ramneck needed. $3,500.00
Electrical EMH/IMH EMH EMH-27:Manhole was to be demo'd. Yes Yes Priority 3
Manholes $250.00
Electrical EMH/IMH IMH IMH-69:Missing insulator.Cleanup debris. Yes Yes Priority 3
Manholes $1,500.00
Electrical EMH/IMH EMH EMH-18:Removeconductors from floor,properly fasten to arms. Yes Yes $1,500.00 Priority 3
Manholes
Electrical EMH/IMH IMH IMH-71:Missing sump cover.Missing insulators. Yes Yes Priority 3
Manholes $500.00
Electrical EMH/IMH EMH EMH-65:Lid offset,new ramneck needed. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH IMH IMH-40:Missing insluators. Yes Yes Priority 3
Manholes $3,500.00
lliiiiIIII
Electrical EMH/IMH IMH IMH-61:Cleanup debris.Missing inuslators. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH EMH EMH-58:Missing insulators.Lid offset,new ramneck needed. Yes Yes Priority 3
Manholes $3,500.00
Electrical EMH/IMH IMH IMH-42:Missing insluators.Lid is offset,new ramneck needed. Yes Yes Priority 3
Manholes _. $3,500.00
lied
Electrical EMH/IMH IMH IHM-43:Lid offset,new ramneck needed.Insulators missing. Yes Yes Priority 3
Manholes $4,500.00
Electrical EMH/IMH IMH IMH-57:Missing pullstrings for spares.Provide missing spare m Yes Yes Priority 3
Manholes conduits.Lid is offset,new ramneck needed. $3,500.00
Electrical EMH/IMH IMH IMH-60:Conduits not flush.Missing insulators.Cleanup debris. Yes Yes Priority 3
Manholes Patch exposed rebar. $3,500.00
Electrical EMH/IMH EMH EMH-53:Missing insulators. Yes Yes $3,500.00 Priority 3
Manholes
Electrical Plant Plant Manholes around the Site The top concrete lid of the manholes is Yes Yes Delete Delete
not aligned with the ring.This creates tight access to enter the
manholes.These need to be aligned with one another.We found a
junction box with a wire splice inside a manhole.Splicing is not
permitted for these types of circuits,and underground splices like
this are a major issue.This is dangerous as manhole can fill with
water,shorting out the splice and potentially damaging electrical
and process equipment.The manholes are dirty with debris,soil,
trash,etc.The cable racks do not correctly support wire and are
missing insulators.Several wires are pulled tight and not trained
around the walls as specified.There are manholes where circuits
are routed in a common conduit instead of separated per the
drawings.I do not know what the contractor did since they did not
follow the drawings.
HVAC Blower Blower Room HVAC needs servicing Yes Yes Priority 2
Building
HVAC Blower Roof RTU condensate piping is routed to downspout rather than dry well. Yes Yes Priority 2
Building See Figure 1.
HVAC Blower Interior RTU-1 fan has noisy operation.Manufacturer has been on site and Yes Yes Priority 2
$30,000.00
Building confirmed a replacement is needed.
HVAC Central Interior None of the wall mounted AC units have condensate piping.See Yes Yes Priority 2
Electrical Figure 6. $13,500.00
Building
HVAC Central Interior Thermostats"B"and"A"are not functioning.See Figure 8. Yes Yes Priority 2
Electrical
$4,400.00
Building
HVAC East Electrical Roof RTU condensate piping is routed to downspout rather than dry well. Yes Yes Priority 2
Building See Figure 9. $6,000.00
HVAC North Roof RTU condensate piping is routed to downspout rather than dry well. Yes Yes Priority 2
Electrical See Figure 4.
Building
Mechanical ABT 1 Aeration Cable hooks that were installed are not sufficient for strain relief. Yes Yes Priority 1
$3,618.00
Basin Train 1 Many of the hooks have broken and are missing
Mechanical ABT 2 General ARV plate covering doesn't have any identification tag or labeling Yes Yes Priority 2
(Mud Valve Cover-CM) $80.00
Mechanical ABT 2 General Equipment wiring is not properly secured Yes Yes $50.00 Priority 1
Mechanical ABT 3 Anerobic and Submersible mixers haven't been installed Yes Yes Priority 1
Anoxic Zones
Mechanical ABT 3 ABT 3- Heat trace circuit left sitting out and not wired in. Yes Yes $412.00 Priority 1
Electrical
Mechanical Aeration General Many mixers were installed with galvanized cables Yes Yes Priority 1
Basins
Mechanical Alum Storage&Alum Feed The safety shower was not functioning and did not have any heat Yes Yes Priority 2
Feed Building tracing. Heat tracing was being installed at the time of the $100.00
System inspection.
Mechanical Alum Storage&Alum Feed Housekeeping items need to be addressed before final punchlist. Yes Yes Priority 2
Feed Building
System
Mechanical Sludge Pump BFP Feed Missing pipe labels Yes Yes Priority 2
Station Pump Station $1,000.00
Mechanical Sludge Pump BFP Feed Contractor to provide surveyed as-builts for 6"pipes leaving the Yes Yes Priority 3
Station Pump Station pump station and traveling to the Dewatering Building.As-builts
shall include which pump is piped to which BFP and where the pipe
alignments differ from the original contractor drawings.
$3,200.00
Mechanical Sludge Pump BFP Feed Install valve tags,equipment name plates,and pipe labels.Paint Yes Yes Priority 2
Station Pump Station and label exposed NPW and sump pump discharge PVC. $1,125.00
Mechanical Sludge Pump BFP Feed Progressive cavity pumps are missing equipment pads(house Yes Yes Priority 3
Station Pump Station keeping pads). $10,000.00
Mechanical Sludge Pump BFP Feed Insulation on north end of common discharge header is missing. Yes Yes Priority 1
Station Pump Station $1,100.00
Mechanical Sludge Pump BFP Feed Confirm in writing that start-up comments from SD 388 have been Yes Yes Priority 2
Station Pump Station addressed.
New guards needed on 2 units.
Seal pressure gauges not working(inspect,and flush...could be
olu66ed)Run dry alarm not functioning. $480.00
Mechanical Chemical Chlorine Insulate emergency eye wash station(repair leak at the stainless Yes Yes $275.00 Priority 1
Building Building fitting)
Mechanical Chlorine Chlorine Signs located on doorways and tanks are paper or spray painted. Yes Yes Priority 1
System Building Signs and labels need to be permanent or stenciled per Section 10 $563.00
09 00.
Mechanical Chlorine Chlorine All chemical piping,including piping on the skids,needs to have Yes Yes Priority 1
System Building correct paint with banding.Sodium Bisulf needs yellow banding
$1,000.00
Mechanical Chlorine Chlorine Inside safety shower potable pipe requires to be painted light blue Yes Yes $400.00 Priority 1
System Building
Mechanical Clarifiers Clarifier 5/ Solenoid valve 0600-SV-3101 is not working Yes Yes $1,200.00 Priority 2
Mechanical&
Ele
Mechanical Clarifiers Clarifier 5/ Meter vault is not sealed and has dirt water getting in,needs Yes Yes Priority 3
$940.00
Mechanical cleaning out and new lids to secure.
Mechanical Clarifiers Clarifier 5/ Chlorine Pipe required to be coated with yellow safety coating. Yes Yes $1,000.00 Priority 2
Mechanical
Mechanical Clarifiers Clarifier 6/ Chlorine Pipe required to be coated with yellow safety coating. Yes Yes $1,000.00 Priority 2
Mechanical
Mechanical Clarifiers Clarifier 6/ Chlorine Pipe needs adjusting so chlorine falls into tough during full Yes Yes Priority 1
Mechanical rotation(appears spout is too long which creates discharge onto
metal structure). $6,250.00
Mechanical Clarifiers Final Clarifier Insulation on was removed from 2"NPW piping.Insulation to be Yes Yes Priority 1
$7,700.00
1-4 reinstalled at this portion of piping
Mechanical Filters Building Cloth Media The guardrail gate located above Cloth Media Disc Filter 2 is Yes Yes $1,100.00 Priority 1
Disc Filter 2 missing.
Mechanical Filters Building Piping Piping is missing heat trace and the pipe jacketing has damages. Yes Yes $1,100.00 Priority 1
Mechanical Filters Building Filters Heat trace not installed per specifications.Exposed heat trace Yes Yes Priority 1
present.Heat trace terminated to wire using wire nuts inside a
pullbox.No thermostat present. $200.00
Mechanical ILS 2 ILS 2 Pump has pressure issues Yes Yes $23,175.00 Priority 1
Mechanical ILS 2 Pump#3 Pump#3 needs to be cleaned and placed back into service Yes Yes $11,587.00 Priority 1
Mechanical ILS 2 Pump#1 Pump#1 needs to be sent back to shop for known issues Yes Yes $85,000.00 Priority 1
Mechanical ILS 2 Pump#5 Pump#5 needs to be cleaned and placed back into service Yes Yes $11,587.00 Priority 1
Mechanical ILS 2 Odor Control Missing vacuum relief damper on top of lift station,see sheet M- Yes Yes $2,060.00 Priority 3
201.
Mechanical Odor Control Biotower Repair coating scratch on the southeast side of the biotower Yes Yes $100.00 Priority 2
sidewall.
Mechanical Odor Control NPW Yard Missing yard hydrant Yes Yes Priority 3
Piping
Mechanical PTU Upper Level Damage to FRP cover plate,required patch repairs.(Multiple Yes Yes Priority 3
locations)
Mechanical PTU Lower Level Insulation removed from Grit Piping in various places Yes Yes $125.00 Priority 1
Mechanical PTU Lower Level Basket strainer rmoved from NPW Pipe,unsure if this is spare or Complete Yes Yes ?
only one?
Mechanical PTU Bug screen missing on vent caps for classifiers „'F- Yes Yes $725.00 Priority 2
Mechanical PTU-Odor Upper Level Many of the foul air dampers which are beneath the PTU channel ;Complete Yes Yes ?
Control covers were discovered to be fully closed.Confirm all dampers are
operable.Set all dampers to 50°/0 o.en. $480.00
Mechanical PTU-Odor Upper Level The 6"and 8"foul air drops on the northeast face of the PTU(in Yes Yes Priority 3
Control between the 18"and 20"drops)just end with a cut pipe and are
lacking a manual balancing damper.See SD 227,contract drawing
PIDs,and contract drawingvalve list. $7,000.00
Mechanical PTU-Odor FA Pipe Provide sample ports and plugs for foul air duct. Yes Yes Priority 3
Control $12.00
Mechanical PTU Lower Heat Trace Heat trace wire to be installed on all lower level piping,if not Yes Yes Priority 1
$600.00
Level already installed
Mechanical PTU Lower Insulation& Install insulation and jacketing on all exposed piping for DIP Yes Yes $750.00 Priority 1
Level Jacketing
Mechanical PTU Upper Foul Air Pipes Did anyone observe the foul air piping and dampers that are Yes Yes ?
Level installed beneath the cover system downstream of the grit vortex
units
Mechanical PTU Upper Compactor Compactor#2 actuator not working Verification Yes Yes Priority 1
Level R=.uired
Mechanical RAS/WAS-3 Lower Level Insulation present around all piping but is not present here Yes Yes $1,100.00 Priority 1
Mechanical RAS/WAS-3 Heat Trace Heating and Insulation repairs required on all 4"WAS piping Yes Yes $1,320.00 Priority 1
Mechanical RAS/WAS-3 Valve Valving arrangement is not correct,valves require moving.Isolation Yes Yes Priority 1
Arrangement valves are needed outside the flow meter and check valve.
Mechanical RAS/WAS-3 Heat Trace PVC piping outside of cabinet requires heat tracing and insulation. Yes Yes $375.00 Priority 1
Mechanical Scum Pump Scum Pump 30 day testing can begin once SST are online and scum can be Yes Yes Priority 1
Mechanical Scum Pump Scum Pump Confirm flushing valve once pumps are in opertation Yes Yes Priority 1
Station Station
Mechanical Scum Pump Scum Pump Require testing reports of the pumps and signoff from Zone Yes Yes Priority 1
Station Station Industries
Mechanical Sludge Storage Sludge Large blower area=82.5 dB recorded.Small blower area=85 dB Verification Yes Yes Priority 2
Blowers Storage recorded.Big blowers should be 80 dB and small blowers should be Required
Blowers 78 dB per the original preselection bid.Spec says 80 dB max at 5-ft
distance.Although there could've been some ambient noise,these
recordings exceed the maximum noise level.Confirm the noise-
attenuating enclosures are installed correctly to do their job.
$240.00
Mechanical Sludge Storage Insulation Air head piping is missing insulation(Note 3,M-1201).Needed to Yes Yes Priority 2
Blowers prevent burns. $2,500.00
Mechanical Sludge Storage Sludge Missing pipe labels Yes Yes Priority 2
Tanks Storage Tanks $375.00
Mechanical Sludge Storage Sludge Missing valve tags Yes Yes Priority 2
Tanks Storage Tanks $250.00
Mechanical Sludge Storage SST 2 Need valve labels for submerged plug valve and flap gate valve. Yes Yes Priority 1
Tanks Submerged plug valve needs open/close indicator on top of $150.00
walkway.
Mechanical Sludge Storage Odor Control Foul air pipe missing pressure relief damper.Pressure relief damper erification Yes Yes Priority 3
Tanks also missing from eastern stairs access area. Required $4,120.00
Mechanical SST 2 East Pipes 6"WAS and 8"TWAS missing HTI.Need credit to owner Yes Yes Priority 1
Mechanical UV 1 UV 1 Airline not reconnected after construction in the area Yes Yes $240.00 Priority 2
Mechanical Post Aeration Effluent Missing 4"BFV on drop legs. Yes Yes Priority 1
•
Basin Aeration Plan
M $1,360.00
840
Mechanical Post Aeration Effluent Missing attachement points for lifting without need for tank drain. Yes Yes Priority 1
Basin Aeration Plan
M $20,000.00
840
Mechanical Post Aeration Effluent Missing hand wheel actuators and valve stems. Yes Yes Priority 2
Basin Aeration Plan
M $100.00
840/M-841
Mechanical AB-Train 1 Basin 3 Broken diffuser grid section at minimum 5 heads needing Yes Yes $3,219.00 Priority 1
Diffusers replacement
Mechanical AB-All Trains All Basins All IMLR piping needs primer and epoxy coating Yes Yes $114,900.00 Priority 1
Mechanical AB-All Trains All Basins Submersible mixers needing repair/installation(14) Yes Yes $48,972.00 Priority 1
Mechanical AB-All Trains All Basins Submersible RCPs needing repair/installation(4) Yes Yes $20,606.50 Priority 1
Mechanical AB-All Trains All Basins LPA pipe supports not installed correctly Yes Yes $6,180.00 Priority 1
Mechanical AB-All Trains All Basins Fixed pipe supports incorrectly installed Yes Yes Priority 2
Mechanical AB-Train 2 Basin x Phosphax analyzer Unit 2 needs recalibration,repair or Yes Yes $1,200.00 Priority 1
replacement
Mechanical AB-All Trains All Basins Submersible mixers needing replacement(17) Yes Yes $455,906.00 Priority 1
Mechanical AB-All Trains All Basins Submersible RCPs needing replacement(3) Yes Yes $118,486.00 Priority 1
Mechanical AB-Train 2 Basin 5 Air leak needing investigation and repair Yes Yes $720.00 Priority 1
Diffusers
Mechanical AB-Train 3 Basin 11 Mud valve needing repair Yes Yes $768.50 Priority 1
Mechanical Chemical Chemical Level instrument repairs-tank 4 Yes Yes $450.00 Priority 1
Building Tanks
Mechanical Chemical Chemical Level instrument repairs-tank 2 Yes Yes $20.00 Priority 1
Building Tanks
Mechanical Chemical Chemical Leak investigation and recalibration on tank 1 Yes Yes $240.00 Priority 1
Building Tanks
Structural ABT 3 Effluent Scum gate missing(0400-WG-3001) Yes Yes Priority 3
Splitter Box
Structural East Electrical East Electrical Complete door installation,including threshold Yes Yes Priority 2
Building Doorway
Structural North Interior Both the single and double doors are opening on their own and do Yes Yes Priority 2
Electrical not have any Latching mechanism
Building
Structural North Interior Double Doors Yes Yes Priority 2
Electrical
Building
Structural North Interior Roof Deteriorating Yes Yes Priority 1
Electrical
Building
Structural RAS/WAS-3 RAS/WAS Duct Tape used instead of insulation at this segment of piping. Yes Yes Priority 1
Piping Insulation to be replaced
Structural UV 2 UV Channel grating missing along banks. Yes Yes Priority 1
Disinfection M
801
Structural UV 2 UV Stairs missing. Yes Yes Priority 1
Disinfection M
801
Structural Parshalt Flume Effluent Stairs missing and final grading needed. Yes Yes Priority 1
Aeration Plan
M-
840/M-841
Structural Parshall Flume Parshall Stairs and stair landing not installed. Yes Yes $7,000.00 Priority 1
Flume M-880
Structural Blower The CMU construction joints have been properly constructed in the Yes Yes Priority 1
Building electrical room.However,six construction joints are missing in the
blower room,Figure 30.Due to the nature of the issue and
because implementing corrective modifications would be costly
and time consuming,the Contractor shall provide an extended
warranty for this building in lieu of the proposed modifications.
The Contractor shall be responsible for the repair of any CMU
cracking attributable to the identified construction deficiencies
throughout the extended warranty period.
Structural UV Building There are missing railings and stairs around the blower and Yes Priority 1
transformer area and around the west side entrance of the building,
Figure 31 and 32
Structural East Electrical Exterior Install missing railings and stairs around the blower and Yes Priority 1
Building transformer area and around the west side entrance of the building,
Figure 31 and 32.
Exhibit"C"
Work Schedule
Exhibit C-Priority Incomplete Items from 30 MGD Expansion
ID Task Task Name Duration Start Finish Predecessors I Sep•26 I Oct'26 5II Nov'26 I Dec'26 I Jan'27 I Feb'27 I Mar'27 I Apr'27 I May'27 I Jun'27 I Jul'27
0 Mode 30[6 11 312 01271 4I11118I251118 11c4221291 61131211271 3 1101171241311711412112817114211281411111812512 19116123130161131201271411111814
1 fr Project Management 235 days Mon 9/7/26 Fri 7/30/27 i
2 1 Site visits 15 days Mon 9/7/26 Fri 9/25/26 MIN
3 fr Review&assessment of 26 days Fri 9/25/26 Fri 10/30/26
incomplete work list
4 Jr Coorindation with equipment 26 days Fri 9/25/26 Fri 10/30/26
suppliers
5 Jr Work packet production 79 days Tue 9/22/26 Fri 1/8/27 I
6 OP' Review of Pricing 11 days Fri 1/8/27 Fri 1/22/27 I I
I
7 * Constructon Admin of packages 146 days Fri 1/8/27 Fri 7/30/27 I
l
DRAFT Task 111111111111111111111M1111 Project Summary 1 -7 Manual Task L' I Start-only C Deadline G
Project: Split Inactive Task Duration-only illikaltallairgillat Finish-only ] Progress
Date:Tue 9/8/26 Milestone ♦ Inactive Milestone Manual Summary Rollup External Tasks i?r;5#>08elk:;:`•?.^ Manual Progress
Summary ll • Inactive Summary I I Manual Summary • • External Milestone 9
Page 1
Exhibit"D"
Fee Schedule
Y1
�. PLUMMER
..
-.....
EXHIBIT D
PLUMMER ASSOCIATES, INC
HOURLY FEE SCHEDULE
2026
Category Rate Category Rate
Administration Engineers/Scientists
Al $ 100.00 ESO $ 95.00
A2 $ 110.00 ES1 $ 155.00
A3 $ 125.00 ES2 $ 170.00
A4 $ 145.00 ES3 $ 190.00
ES4 $ 220.00
Category Rate ES5 $ 250.00
CAD Designers ES6 $ 270.00
Cl $ 130.00 ES7 $ 325.00
C2 $ 140.00 ES8 $ 360.00
C3 $ 165.00 ES9 $ 390.00
C4 $ 185.00
C5 $ 210.00 Category Rate
Geospatial
Category Rate LS1 $ 130.00
Resident Project Representatives LS2 $ 135.00
RR1 $ 140.00 LS3 $ 150.00
RR2 $ 150.00 LS4 $ 175.00
RR3 $ 160.00 LS5 $ 220.00
RR4 $ 180.00 LS6 $ 265.00
LS7 $ 280.00
Category Rate
Construction Managers Category Rate
CM1 $ 160.00 Telecommunication Designers
CM2 $ 170.00 TD1 $ 130.00
CM3 $ 185.00 TD2 $ 140.00
CM4 $ 210.00 TD3 $ 160.00
CM5 $ 230.00 TD4 $ 175.00
CM6 $ 270.00
CM7 $ 320.00 Category Rate
CM8 $ 340.00 Professional
P1 $ 140.00
Category Rate P2 $ 160.00
Electrical Engineers and Specialists P3 $ 220.00
EE1 $ 155.00 P4 $ 300.00
EE2 $ 170.00 P5 $ 375.00
EE3 $ 195.00
EE4 $ 230.00 Billing rates may be adjusted up to 5 percent
annually(at the beginning of each calendar
EE5
$ 260.00 year)during the term of the agreement.
EE6 $ 300.00
EE7 $ 350.00 A mulitiplier of 1.15 will be applied to all
EE8 $ 370.00 direct expenses.
EE9 $ 390.00
Fleet vehicles charge at$1,500 per month,
$150 per day.
raNICHOLS
Name Position Hourly Rate
Alex Kavanaugh Professional4 $244
Blane McGee Professional 2 $157
Brad Watson Professional 6 $403
David Hunn Professional 5 $366
Greg Gaskie Professional 4 $234
Janet Frantz CAD Technician/Designer 3 $214
John Manning Professional6 $361
John Rinacke Professional 3 $208
Maziar Mandavi Professional4 $266
Michael Schuster Professional 5 $287
Miguel Marroquin Professional 3 $204
These ranges and/or rates will be adjusted annually in February. Last updated 2026.
360022026
®egis
Egis Billing Rate Schedule-2026
Title Rate
Principal I $ 348.00
Principal II $ 456.00
Project Manager I (8-10) $ 196.00
Project Manager II (10-12) $ 212.00
Project Manager III (12-15) $ 228.00
Project Manager IV(15-20) $ 282.00
Project Manager V(20-25) $ 293.00
Project Manager VI (25+) $ 315.00
Professional Engineer I (5-8) $ 168.00
Professional Engineer II (8-10) $ 185.00
Professional Engineer III (10-12) $ 206.00
Professional Engineer IV(12-15) $ 217.00
Professional Engineer V(15-20) $ 239.00
Professional Engineer VI (20-25) $ 283.00
Professional Engineer VII (25+) $ 293.00
Engineer in Training I (0-2) $ 130.00
Engineer in Training II (3-4) $ 141.00
Engineer in Training III (5+) $ 147.00
Engineering Technician Entry $ 125.00
Engineering Technician Mid $ 163.00
Engineering Technician Senior $ 196.00
GIS Technician Entry $ 109.00
GIS Technician Mid $ 152.00
GIS Technician Senior $ 174.00
GIS Administrator Senior $ 217.00
CAD Technician Entry $ 98.00
CAD Technician Mid $ 141.00
CAD Technician Senior $ 163.00
CAD Administrator Senior $ 217.00
Planner I (0-5) $ 125.00
Planner II (5-10) $ 174.00
Administrative Specialist I (0-5) $ 76.00
Administrative Specialist II (5-10) $ 87.00
Administrative Specialist III (10-15) $ 98.00
Administrative Specialist IV(15-20) $ 109.00
Administrative Specialist V(20-25) $ 120.00
Administrative Specialist VI (25+) $ 130.00