Contract - Plummer Associates, Inc. - 9/10/2026 (2) STATE OF TEXAS §
COUNTY OF WILLIAMSON §
SUPPLEMENTAL CONTRACT NO. 3
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: PLUMMER ASSOCIATES,INC. ("Engineer")
ADDRESS: 8911 N. Capital of TX Hwy,Building 1, Suite 1350,Austin, TX 78759
PROJECT: BCRWWS East Wastewater Treatment Plant Expansion to 40MGD
This Supplemental Contract No. 3 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and Plummer Associates, Inc.,
hereinafter called the"Engineer."
WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter
called the "Contract," on the 2nd day of November, 2023 for the BCRWWS East Wastewater
Treatment Plant Expansion to 40 MGD Project in the amount of$6,072,849.00; and
WHEREAS,the City and Engineer executed Supplemental Contract No. 1 on November 7, 2024
to amend the scope of services and to increase the compensation by $1,256,618.00 to a total of
$7,329,467.00; and
WHEREAS, the City and Engineer executed Supplemental Contract No. 2 on July 24, 2025 to
amend the scope of services and to increase the compensation by $567,307.00 for the 40 MGD
Expansion ($338,513.00) and Rehabilitation ($228,794.00) for a project total of$7,896,774.00;
and
WHEREAS,it has become necessary to amend the Contract to modify the provisions for the scope
of services and to increase the compensation by $149,061.00 to a total of$8,045,835.00;
NOW THEREFORE,premises considered, the City and the Engineer agree that said Contract is
amended as follows:
I.
Article 1, City Services and Exhibit A, City Services shall be amended as set forth in the attached
Addendum To Exhibit A.
II.
Article 2, Engineering Services and Exhibit B,Engineering Services shall be amended as set forth
in the attached Addendum to Exhibit B. Exhibit C, Work Schedule shall be amended as set forth
in the attached Addendum to Exhibit C.
Supplemental Contract Rev.06/16
0199.202334 84275
III.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$149,061.00 the maximum amount payable under the Contract for a total of$8,045,835.00, as
shown by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF,the City and the Engineer have executed this Supplemental Contract
in duplicate.
[signature pages follow]
Supplemental Contract Rev.06/16
0199.202334 84275
2
PLUMMER ASSOCIATES, INC.
By: L/1/7
Printed Name: Mary Portillo, PE, PMP
Title: Principal
Date Signed: d' /940.2 6
Supplemental Contract Rev.06/16
0199.202334 84275
3
CITY OF ROUNDOCK APPROVED AS TO FORM:
By: 0 C2ti
Crai Mo an, Mayor Stephanie L. Sandre, City Attorney
&fierrliOer /9 21224
Date
Supplemental Contract Rev.06/16
0199.202334 84275
4
Brushy Creek East Regional WWTP
40 MGD Expansion Project
• t~ PLUMMER Supplemental Contract#3
(0982-018-01)
ADDENDUM TO EXHIBIT A
City Services
The City of Round Rock will furnish to the Engineer the following items/information:
• Attend kickoff meeting and progress meetings.
• Designate a person to act as City's representative with respect to the services to be
performed or furnished by the Engineer. This representation will have authority to
transmit instructions, receive information, interpret, and define City's policies and
decisions with respect to engineering services.
• Provide criteria and full information as to City's requirements for the project, including
objectives and constraints and furnish copies of standards which City will require to be
included in the project.
• Assist Engineer by placing available information pertinent to the Project, including
previous information and other data relative to the Project at the Engineer's disposal.
Engineer will reasonably rely upon the accuracy, timeliness, and completeness of the
information provided by the City.
• City will give prompt notice to Engineer whenever City observe or become aware of
development that affects the scope or timing of Engineer's services.
• Provide digital design files or records available which would assist in the completion of
the project development.
• Governmental review fees, submittal fees, recordation fees, and other fees associated
with the project shall be paid for directly by the City.
• Timely review and comment,within 10 business days, on the deliverables.
Brushy Creek East Regional WWTP
40 MGD Expansion Project
Supplemental Contract#3 0982-018-01
ADDENDUM TO EXHIBIT B
Engineering Services
Engineering Services to be provided for the ILS improvements and BCE Structure Evaluations(Supplemental
Contract#3) of the 40 MGD Expansion project:
Background
The Brushy Creek East Regional Wastewater Treatment Plant (Plant) is owned by the Brushy Creek Regional
Wastewater System (BCRWWS), who are the Cities of Round Rock, Cedar Park, Leander and Austin
(Partners).The engineering team, led by Prime consultant Plummer Associates, and sub consultants Freese
& Nichols and Lochner (Engineer) designed the most recent 10 MGD expansion, increasing the Plant's
capacity from 30 MGD to 40 MGD.This Supplemental Contract is adding services to the 40MGD Expansion
design project.
SCOPE —Additional Services
The purpose of this scope of services is to provide additional services for:
1. ILS 1 and 2 Ragging Issues Review
2. BCE Structure Flood Risk Evaluations
Task 1:ILS 1 and 2 Ragging Issues Review(Preliminary Report)
Due to persistent ragging and clogging issues at ILS 1, the City of Round Rock has requested a preliminary
evaluation of mitigation alternatives. The goal of this task is to identify and compare feasible solutions to
include upstream screening, improve pump reliability, reduce maintenance frequency, and improve the
operability of the lift station.
Tasks:
The scope of work for Task 1 is further defined in the following sub-tasks including:
A. Project Management
B. Quality Management
C. Data Collection and Existing Conditions Review
D. Technical Memorandum
E. Review Workshop
A. Project Management
The ENGINEER includes PM effort for this under the budget for communication and coordination
with the City and internal team coordination, scope, schedule and budget management, monthly
invoicing, status reports and other activities associated with project management.
B. Quality Management
ENGINEER will perform QA/QC reviews on the draft and final ILS Ragging Issues Technical
Memorandum and incorporate internal review comments prior to submission to the City.
Page 1 of 5
Brushy Creek East Regional WWTP
40 MGD Expansion Project
Supplemental Contract#3 0982-018-01
C. Data Collection and Existing Conditions Review
ENGINEER will review available record drawings, pump data sheets, and system layout, conduct
and coordinate with City staff to identify maintenance constraints, operational concerns and
priorities.
Meetings: N/A
Deliverables:N/A
D. Technical Memorandum—ILS Ragging Issues
Feasible alternatives to mitigate ragging and system performance will be evaluated.They include:
• Upstream coarse screening — high level evaluation of up to two (2) screen types and
placement and consideration of constructability and maintainability.
• Pump upgrades—evaluate up to two (2) options to mitigate ragging, including a review of
manufacturer recommendations, compatibility with existing pumps and motors, hydraulic
performance implications, and anticipated maintenance and reliability impacts.
• Electrical and structural review—coordinate with the electrical and structural engineering
design team to discuss impacts associated with alternatives evaluated, including available
power capacity, starter/VFD compatibility, control logic modifications, structural
implications and feasibility.
• Review available hydraulic and operational data to assess potential impacts to system head
conditions, wet well operations, and pump performance associated with the project.
Prepare a technical memorandum documenting the existing conditions and description of ragging
issues and operational impacts,a comparative analysis on the alternatives,available power supply,
structural implications, Class 5 OPCC, and a recommendation to inform a decision on next steps.
Meetings:N/A
Deliverables: One (1) draft Technical Memorandum (soft copy) and one (1)final ILS Ragging
Issues Technical Memorandum (soft copy)
A. Review Workshop
One (1) virtual review workshop with the City and the design team to present findings, review
alternatives and Class S OPCC and obtain feedback on the draft technical memorandum.
Meetings:One(1) Virtual Client Review Workshop, up to 1 hour
Deliverables:Meeting notes
Task 2:BCE Structure Flood Risk Evaluation
Because portions of the BCE WWTP are located within the 100-year floodplain, the City of Round Rock has
requested an evaluation of critical facilities and structures to assess potential flood risk.This task will provide
a site plan exhibit that identifies structures and equipment vulnerable to flooding based on a comparison of
available elevation data with the applicable 100-year flood elevation.
Page 2 of 5
Brushy Creek East Regional WWTP
40 MGD Expansion Project
Supplemental Contract#3 0982-018-01
Tasks:
The scope of work for Task 2 is further defined in the following tasks including:
A. Project Management
B. Quality Management
C. Data Collection and Existing Conditions Review
D. Site Plan Exhibit
A. Project Management
The ENGINEER includes PM effort for this under the budget for communication and coordination
with the City and internal team coordination, scope, schedule and budget management, monthly
invoicing, status reports and other activities associated with project management.
B. Quality Management
ENGINEER will perform QA/QC reviews on the draft and final site plan exhibit and incorporate
internal review comments prior to submission to the City.
C. Data Collection and Existing Conditions Review
ENGINEER will obtain and review available data, including record drawings, plan sets and floodplain
data. Identify key structures and equipment for evaluation, including electrical buildings, pump
stations and process structures and outdoor equipment.
D. Site Plan Exhibit
ENGINEER will extract and compile elevations from available documentation and drawings
including:
• Finished floor elevations
• Top of wall elevations for process structures
• Equipment pad elevations and electrical equipment elevations
Compare the elevations to the 100-year flood elevation and perform a screening-level assessment
to identify structures at or below the 100-year flood elevation, identify structures with limited
freeboard and highlight critical assets with elevated risk exposure.
A risk categorization framework(High/Moderate/Low Risk)will be developed based on the relative
elevation to the 100-year flood elevation. Key vulnerabilities such as electrical and control systems
will be identified.
A Site Plan Exhibit including structure locations, annotated elevations, 100-year flood elevation
reference and a graphical representation of relative flood risk will be drafted for the City's review.
Incorporation of feedback from the City will be included in the Final Site Plan Exhibit.
Meetings:One(1)internal coordination meeting(Plummer and FNI),up to 1 hour
Deliverables: One(1) Draft Site Plan Exhibit(soft copy), One (1) Final Site Plan Exhibit(soft and
hard copy)
Page 3 of 5
Brushy Creek East Regional WWTP
40 MGD Expansion Project
Supplemental Contract#3 0982-018-01
LIST OF ASSUMPTIONS
The following assumptions were used when developing the scope of service and estimating the
compensation to CONSULTANT:
1. No design work and construction services work is included in the above-mentioned scope of
services.
2. The following professional services are not included in this phase of work: Geotechnical
investigations, environmental assessments, architectural design, and subsurface utility
investigations.
3. Roadway and/or access route design to each process/structure are not in the scope of work.
4. GIS mapping services or assistance with these services are not in the scope of work.
5. Site visits and field verification are not in the scope of work.
6. Additional effort associated with preparing bid packages or equipment selection for the ongoing 40
MGD/Rehabilitation work is not included.
Page 4 of 5
Brushy Creek East Regional WWTP
40 MGD Expansion Project
Supplemental Contract#3 0982-018-01
Summary table—List of meetings and deliverables
Task Meetings Deliverables
v, • One(1)client virtual review • Meeting materials and notes
^' workshop • Draft ILS Ragging Issues Technical Memorandum
c '^
a, (soft copy)
N .� cc
• Final ILS Ragging Issues Technical Memorandum
OD
(soft copy)
cc
a)
• One(1)virtual internal • Meeting materials and notes
o coordination meeting • One (1) Draft Site Plan Exhibit (soft copy)
u • One (1) Final Site Plan Exhibit (soft and hard copy)
o
w O >
U w w
m
Refer to Exhibit C for the tentative proposed schedule.
Refer to Exhibit D for the fee schedule.
Page 5 of 5
ADDENDUM TO EXHIBIT C
Work Schedule
Attached Behind This Page
Exhibit C-ILS Pump Evaluation and Screen and Flood Elevation(Supplemental Contract 3)Project Schedule
!ID Task Task Name Duration Stan Finish Predecessors May31,26 lun].'2fi Jun la,'26 Ihn 21'2♦ lung4'26 Ju15,'26 Jul 12.'2fi lUlto 26 10126.'2fi Aug 2.'26 Aug 9.'26 Aug 16.'26 Augll.26 Aug 10,26 Sep 6.26
1 A Project Management 71 days Mon 8/3/26 Mon 11/9/26
0 Mode _ S I S I s T W r F S S M S W T F S 5 M T W I T I F I S I S IMI T T I F I S S IMI T Yn T I F I S I S IM T W(T I F I S S IMI T Fs T F 5 5 M T W 1 i S S M I WI I S S M T W r F 5$M T W 1'F S S M T W T F 5 5 M 1 W 1 I S S M 1 1/4-F S S M 1 WI
•
2 0 ILS 1 and 2 Ragging Issues Review 71 days? Man 8/3/26 Mon 11/9/26 i
'.,I 3 ♦ DraftTM 50 days Mon 8/3/26 Fri 10/9/26 I •ten>^-
4 ♦ Review Workshop 1 day Mon 10/12/26 Mon 10/12/26
11
5 ♦ City Review 10 days Mon 10/12/26 Fri 10/23/26 3
6 0 Update TM 10 days Mon 10/26/26 Fri 11/6/26 5
7 ♦ Final TM to City 1 day? Mon 11/9/26 Mon 11/9/26 6
8 0 BCE Structure Flood Risk Evaluatic46 days? Man 8/3/26 Man 10/5/26 t - -- - -- ..... . .
9 .1 DraftSite Exhibit 24 days Tue 8/4/26 Fri 9/4/26 I I
10 0 City Review 10 days Mon 9/7/26 Fri 9/18/26 9 I-
11 ♦ Update Site Exhibit 10 days Mon 9/21/26 Fri 10/2/26 10
12 ,< Final Site Exhibit to City 1 day? Mon 10/5/26 Mon 10/5/26 11 •
•
Task Summary t--I Inattrve Mtlestme Duauon-only Sun-only C External Mikstone ' Manual Progress
Project:Amendment 3 Project S
Date:Fri 6/5/26rq«
6 Sold Pt Summaryr------T ware summary Manual Summary xalvP F.msnonly 3 Deadkne
M estone ♦ Inattrve Task Manual Task Manual Summary r� External Tasks Progress
Page 1
ADDENDUM TO EXHIBIT D
Fee Schedule
Attached Behind This Page
City of Round Rock
Brushy Creek East Expansion to 40 MGD EXP-ILS2 Pump Evaluation&Outfall Modifications
Principal/CIA QC Sr.Elec Eng. Proj Mgr I Proj Engr i ER I CAD Clerical Total Labor Sub consultant($) Total Fee Percent of
(hrs) (hn) (hn) (hrs) 1 (hn) i (hn) ' (hn) Hours Fe.(3) KFA FNI (S) Total Fee
2 ILS 1 and 2 Ragging Issues Review 10 65 60 4 159 $ 39,330 $ 41,096 S 35,564 $ 116,010 77.9%
Project Management 30 4
Quality Management 10
Data Collection and Existing Conditions Review 15
Tech Memo 30 80
Review Workshop 5 5
3 BCE Structure Flood Risk Evaluation 15 25 30 10 4 64 S 21,160 $ 11,641 6 32,821 22.1%
Project Management 15 4
Quality Management 15
Data Collection and Existing Conditions Review 10
Site Plan Exhibit 10 20 10
TOTAL LABOR
Total Plummer Labor Hours 25 0 90 110 0 10 8 243 60,510 41,096 47,225
Total Amounts by Labor Category S 9,000 S - $ 24,300 $ 24,200'$ - $ 1.850 3 1,160 S 60,510 S 41,096 S 47,225 5 148,831
Labor Category Percent of Total Labor 14.9% 0.0% 40.2% 40.0% 0.0% 3.1% 1.9% 41% 28% 32%
TOTAL EXPENSES In..breakdown below)
Total Subconsuitams S 88.321
Total Reimbursables $ 230
TOTAL S 149,001 1[FEE IS BASED ON A LUMP SUM AMOUNT]
(41 1120 S.Capital of Texas Highway Austin,TX 78746
Lochner CityView 2,Suite 100, 512.338.1704 hwlochner.com
®egis
SCOPE OF SERVICES
Brushy Creek East Regional WWTP 40 MGD Expansion Detailed Design
Amendment 3 -ILS#1 and ILS #2 Influent Ragging Evaluation
The Brushy Creek East Regional Wastewater Treatment Plant (Plant) is owned by the Brushy Creek
Regional Wastewater System (BCRWWS), who are the Cities of Round Rock, Cedar Park, and Austin
(Partners). The City of Leander will become a part owner on completion of the current expansion from
20 MGD to 30 MGD, which is currently under construction. Lochner is a subconsultant to Plummer
Associates for this expansion to 30 MGD, and also for the design of the next expansion to 40 MGD.The
expansion to 40 MGD is currently at the final engineering phase and is expected to be advertised for
public bidding in late 2026.
The purpose of this scope of services is to provide additional detailed designed services for the
evaluation of mitigation measures for the ragging issues currently being experienced at ILS#1 and ILS
#2. The evaluation will review existing pump equipment, wet well configuration, operating conditions,
and relevant maintenance and performance history. Lochner will evaluate different options for
mitigating the ragging issues, such as replacement of the existing impellers, installation of upstream
grinders/choppers in addition to the submersible ILS pumps, or other potential mitigation measures.
Lochner will evaluate up to two(2)viable mitigation measures.Plummer will be evaluating the feasibility
of upstream screening to remove rags, and Lochner will coordinate with Plummer to develop a
summary of findings and recommendations that will be provided in a Technical Memorandum.
The following details Lochner's scope of services, schedule, fee, and assumptions for the Project.
SCOPE OF SERVICES:
1. Project Management — This task includes routine communication and coordination with the
Partners; managing manpower, budgets, and schedules; monthly invoicing and status reports;
implementing and monitoring of QA/QC efforts;and other activities associated with managing
the project.
2. Quality Management — Lochner will conduct Project Design Team (PDT) and Independent
Technical Review Team (ITRT) QA/QC reviews for all materials to be submitted to the Partners.
3. Existing Conditions Review — Lochner will review available pump data, operations and
maintenance records, and recent ragging-related maintenance events at ILS#1 and ILS #2.
4. Ragging Mitigation Evaluation— Lochner will evaluate up to two (2) options for mitigating
ragging, including a review of manufacturer recommendations, compatibility with existing
pumps and motors, hydraulic performance implications, and anticipated maintenance and
reliability impacts.
5. Electrical Coordination — Lochner will coordinate with the electrical engineering design team
to discuss impacts associated with options evaluated, including available power capacity,
starter/VFD compatibility, and control logic modifications.
6. Cost Estimating — Lochner will prepare a preliminary cost estimate for up to two (2) viable
options evaluated.
7. Technical Memorandum — Lochner will prepare and submit a technical memorandum
consisting of a summary of the feasibility of the mitigation measures, cost estimates, and a
recommendation for the Partners to evaluate.
8. Review Workshop— Lochner will attend one (1) virtual review workshop with the Partners and
the design team to review the recommendations in the technical memorandum, and finalize a
decision on how to proceed with ILS#1 and ILS#2 influent ragging mitigations.
Amendment 3 1 June 3,2026
dD. Lochner
®egis
SCHEDULE:
Lochner proposes completing the project according to the following schedule, assuming a Notice to
Proceed (NTP) is issued on August 3, 2026:
• Draft submittal to Partners—October 9th, 2026
• Comments from Partners—October 23rd, 2026
• Final submittal to Partners— November 9th, 2026
FEE:
The estimated fee for the basic services described above is a lump sum of$37,360.00.A fee
breakdown by task is included herein.
ASSUMPTIONS:
• No design is included in this scope of services and Lochner will be performing feasibility
analyses only. If the Partners elect to move forward with detailed design, additional services
will be required.
• Plummer will be performing an evaluation of upstream screening for the ILS#1 and ILS#2
Influent Ragging Evaluation. Lochner will coordinate with Plummer to evaluate all influent
ragging mitigation measures and to provide a final recommendation to the Partners.
• The Partners will provide to Lochner all available data in the Partners' possession relating to
Lochner's services on the Project. Lochner will reasonably rely upon the accuracy, timeliness,
and completeness of the information provided by the Partners.
• The Partners will give prompt notice to Lochner whenever the Partners observes or becomes
aware of any development that affects the scope or timing of Lochner's services.
• The Partners shall examine information submitted by Lochner and provide written comments
and decisions in a timely manner.
• All governmental review fees, submittal fees, recordation fees, and other fees associated with
the project shall be paid for directly by the Partners.
• The project will be performed in a continuous manner without significant work stoppages or
delays.
• The following professional services are not included in this phase of work: Geotechnical
investigations, structural engineering, electrical engineering, environmental assessments,
architectural design, and subsurface utility investigations.
2
MANPOWER/BUDGET ESTIMATE-AMENDMENT 3
BRUSHY CREEK REGIONAL WASTEWATER TREATMENT FACILITY-EAST PLANT
EXPANSION TO 40 MGD
Project QA/QC Senior Project Senior Labor Total
Task Principal Manager Engineer Engineer Engineer EIT Techniciar Admin Total Cost Expenses Cost
Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs $ $ $
1 Project Management 4 4 8 $1,320 $1,320
2 Quality Management 2 10 12 $3,600 $3,600
3 Existing Conditions Review 2 2 4 4 12 $2,460 $2,460
4 Ragging Mitigation Evaluation 10 6 16 32 64 $12,380 $12,380
5 Electrical Coordination 2 4 4 10 $1,910+ $1,910
6 Cost Estimating 2 2 6 10 20 $3,850 $3,850
7 Technical Memorandum 6 4 12 20 42 $8,150 $8,150
8 Review Workshop 2 4 6 6 18 $3,690 $3,690
Total Amendment 3 4 30 10 14 48 76 0 4 186 $37,360 $0 $37,360
Lochner
6/11/2026 eafe
FR E E S E Innovative approaches
II ?NICHOLS Presults
> ', t gat; .\ ,t
June 11, 2026
Plummer, Inc.
8911 N CAPITAL OF TX HWY,Suite 1250
Austin, Texas, 78759
Re: Brushy Creek East Regional WWTP 40 MGD Expansion Amendment#3—ILS#2 Pump Evaluation &
Outfall Modifications
Dear Sheryl Chia,
Freese and Nichols, Inc. (FNI) is pleased to submit this proposal to provide professional structural and
electrical engineering services to Plummer Associates, Inc. (Client) in support of Amendment#3 for the
Brushy Creek East Regional Wastewater Treatment Plant (BCE WWTP)40 MGD Expansion project.
PROJECT UNDERSTANDING
It is our understanding that Client will serve as the Prime consultant to the Brushy Creek Regional
Wastewater System Partners (Owner). H.W. Lochner(Lochner) and FNI will be sub-consultants to
Client on this project.
FNI will provide additional design and bid phase services for electrical and structural engineering in
relation to the following items:
• ILS 2/ILS1 Screening Studies: The Owner has requested evaluation of options to address influent
ragging issues at ILS1 and ILS2. Plummer is evaluating the installation of new course screen
structures upstream from each lift station and related improvements that could potentially be
implemented as part of the 40 MGD/Rehabilitation project. Lochner will be providing review of
additional grinder pumps and impeller replacements.FNI will provide electrical and structural
study support to assist in general feasibility, evaluating power needs, structural implications, and
planning-level cost impacts associated with the additions under consideration.
• 100-year Flood Risk Assessment: 100-Year flood criteria previously applicable to the site is being
updated which may pose a risk to existing assets at BCE Trains 1/2 and 3.The Owner has
requested a site plan exhibit and supporting summary information to better understand flood
risk for existing plant structures, buildings, and select outdoor equipment relative to the 100-
year flood elevation. FNI will provide electrical review of existing Train 1/2/3 equipment using
available drawings and elevation information provided by the Client and/or City.
Page 2
SCOPE OF SERVICES
ARTICLE I - BASIC SERVICES
FNI will render the following professional services in connection with the development of Amendment
#3:
TASK 1 - PROJECT MANAGEMENT
1. Provide additional project management, quality assurance, and quality control for Structural and
Electrical services.
2. Monitor and maintain scope, schedule, and budget for Structural and Electrical tasks.
3. Participate and support one (1) virtual review workshop with the Client and Owner in relation to
the preliminary engineering findings.
TASK 2-ILS 2/ILS1 SCREENING STUDIES
1. Provide a high-level electrical review of available site power for screening equipment proposed
by Lochner and the Client to address influent ragging issues at ILS1 and ILS2. Electrical study
services will be provided for one (1)equipment option set based on the Client's/Lochner's
selections. Additional alternatives are not included as part of the evaluation.
2. Review of available power consumption information and identify, at a planning level, likely
points from which power could be drawn for proposed screening equipment. FNI will provide
high level recommendations for possible electrical work required to provide additional power.
3. Provide a structural feasibility review of up to two (2) coarse screens (one at each lift station)
based on dimension requirements provided by Plummer. FNI will also review the feasibility of
additional structural modifications, access improvements, or support being considered by
Plummer. Large improvements or rehabilitation not explicitly mentioned such as additional
structures, major demolition, or large structural modifications are not included as part of this
review.
4. Support Lochner/Client in the electrical evaluation of up to two (2) pump selections as an
alternative to screening. It is understood that the ultimate horsepower decision will fall within
the capacity of the existing electrical system so as not to require any analysis or redesign of the
existing electrical system.
5. Prepare a Class 5 OPCC for structural and electrical items being considered under this study. It is
our understanding that Plummer will coordinate and compile the complete OPCC for the
Owner's review.
6. Provide input to a short memorandum or report, as prepared by Plummer, summarizing
structural and electrical considerations, implementation constraints, and order-of-magnitude
cost implications.
7. Detailed design of screening facilities,grinder pumps, impeller replacements, structural
modifications, or electrical upgrades is not included under this Task.
Deliverables:Structural/Electrical OPCC input, Input to a technical memorandum or report.
TASK 3- 100-YEAR FLOOD RISK ASSESSMENT
1. Review current plans and available elevation information provided by the Client and/or City and
assist the Client with development of a site plan exhibit depicting possible risk to select site
electrical equipment relative to new 100-year flood elevation. This review will be performed
using existing drawings and information provided by the Client and/or City. Surveying,field
verification of elevations, hydrologic/hydraulic analysis,floodplain modeling, and floodplain
permitting are not included.
Page 3
2. Attend one (1) internal coordination meeting with the Client regarding the 100-year flood risk
assessment.
3. Assist the Client with preparation of a summary table identifying the electrical equipment
reviewed and their relative flood risk based on available elevation information.
Deliverables: Electrical site plan exhibit, Equipment flood risk summary table
ARTICLE II-ADDITIONAL SERVICES/EXCLUSIONS
Any services performed by FNI that are not included in the Basic Services described above are Additional
Services. Additional Services to be performed by FNI, if authorized by Client upon negotiated fees, are
described as follows:
1. Construction services such as response to RFIs, review contractor's submittals, attend pre-
construction meetings, site visits, record drawings, etc. during construction.
2. Develop Civil and site work except providing electrical power distribution equipment, electrical
duct banks, and light poles as needed.
3. Design of the interface between motor controllers/control panels and System Integrator supplied
instrumentation,SCADA, and networking cabinets.
4. Obtain local and state permits.
S. Roadway and/or access route design to each process/structure.
6. Evaluate the existing structures.
7. Provide hard copies of the deliverable.
8. Design for other disciplines except structural and electrical.
9. Site visits except those listed in this proposal.
10. Field investigation work such as Geotechnical exploration, Geotechnical report, topographic
survey and SUE.
11. Value engineering.
12. GIS mapping services or assistance with these services.
13. Making property, boundary and right-of-way surveys, preparation of easement and deed
descriptions, including title search and examination of deed records.
14. Preparing applications and supporting documents for government grants, loans, or planning
advances and providing data for detailed applications.
15. Providing environmental support services including the design and implementation of ecological
baseline studies, environmental monitoring, impact assessment and analyses, permitting
assistance, and other assistance required to address environmental issues.
16. Design services in relation to any task included herein.
17. Additional equipment selections or revisions to said selections beyond those established or
identified under basic services.
18. Additional effort associated with preparing a bid/permitting package separate from the ongoing
40 MGD/Rehabilitation set of drawings and specifications.
PROJECT SCHEDULE
Final schedule will be determined as agreed between Plummer, Owner, and FNI.We estimate the
completion of the scope will span 3 months.The following tentative schedule is proposed:
• ILS1/2 Screening Study and Flood Risk Assessment Reports
o Draft Submittal to Partners-September/October 2026
o Final Submittal to Partners-October/November 2026
Page 4
COMPENSATION
FNI proposes to provide services as described herein for the lump sum fee of Forty-Two Thousand Nine
Hundred Thirty-Two Dollars ($42,932).
Task Fee
BASIC SERVICES
ILS 1/2 Screening Study
PM $ 2,795
Structural $ 12,610
Electrical $ 16,944
100-year Flood Risk Assessment
PM $ 1,274
Electrical $ 9,309
TOTAL FOR SERVICES $42,932
We appreciate this opportunity to submit this proposal. If additional information or clarification is
desired, please do not hesitate to contact us. If you agree with the services described above and wish for
us to proceed with this assignment, please initiate contract proceedings.
Sincerely,
FREESE AND NICHOLS, INC.
Scott Hubley, PE
Principal,Assistant Division Manager
Project Fee Summary
BCE 40 MGD/Rehab Aid 03-ILS7/2 Screening&100-YR Flood Assessment Basic Services $ 42,932
6/12/2026 Special Services $ -
Detailed Cost Breakdown Additional Services $ -
Total Project $ 42,932
I Labor
Miguel Marroguin Van Cameo Juan-Pablo Cantu Kassandre Pere John Manning MaZIW Mehdan Nan Siva Brad Watson John Rinacke
Task Description Suvlllaga Total Hours
PM OC PE EIT QC PE EIT QC Estimev
Task 1-Project Management
Kickoff 1 1
Virtual Workshop 1 1
Maintain and monitor scope 8 2 10
One Page Reports 2 2
Tech Memos 2 ----- 2
Project General 3 � 3
Task 3-ILS 2/ILS 1 Screening Studies
Gathering Data --_ 2 4 _.__-_ 1 4 11
Tech Memo Production(Draft Phase&Final Phase) 6 12 1 12 24 2 57
OPCC 5 10 1 6 2 24
QC 1 1 5 2 9
Virtual Workshop(1) 1 1 1 3
Pump Evaluation(2 pumps) 2 8 10
Submit Final Memo 3 5 3 11
Task 4-100-Year Flood Risk Assessment
Gathering Data&Analysis 5 10 1 16
Elec Equip.Summary Table Production 3 5 1 9
Site Exhibit(Draft&Final) 3 8 1 12
Virtual Meeting w/Client(1) 1 1 2
17 - 2 - 32 65 11 - 13 37 4 - 2 - 183