Webber Waterworks, LLC - 10/19/2026 Change Order
No. 001
Date of Issuance: 10/9/2026 Effective Date:
Project BCRUA Phase 2A WTP Expansion Uwner.BCRUA Owner's Contract No.:NA
Contract Date of Contract December 15,2025
contractor Webber Waterworks,LLC Engineer's Project No.:3-00867
The Contract Documents are modified as follows upon execution of this Change Order.
See attached summary for the following Change Proposals: RCP-001 (CPR-001),TSC Admin
CPR-002,TSS Potholing;CPR-003, Filter Gallery Changes;and CPR-004,Direct Costs for TSS
Over-Excavation of Non-Native Material and Backfill.
Attachments: (List documents supporting change):
Change Proposal Summary Sheet,RCP-001,CPR-002,CPR-003,and CPR-004
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract Times: ❑Working days X Calendar days
Substantial completion(days or date):June 12,2028(910 Calendar Days)
$97.619.149.00 Ready for final payment(days or date):September 10.2028(1.000 Calendar Days)
[Increase][Decrease]from previously approved Change Orders [Increase][Decrease] from previously approved Change Orders
No. NLA to No. N/A No. N/A to No. N/A
Substantial completion(days):910
$0.00 Ready for final payment(days):90
Contract Price prior to this Change Order. Contract Times prior to this Change Order.
Substantial completion(days or date):910
$97,619.149.00 Ready for final payment(days or date):90
(Increase](D..cn.a,..]of this Change Order. [Increase][Decrease]of this Change Order.
Substantial completion(days or date):0
$398.570.17 Ready for final payment(days or date):0
Contract Price incorporating this Change Order. Contract Times with all approved Change Orders:
Substantial completion(days or date):June 12-2028
$98.017.719.17 Ready for final payment(days or date):Septem bee 10.2028
RECOMMENDED: ACCEPTED: ACCEPTED:
TeteYT. $ate
By: By: � a By:Peter T.Ballay(Oc1ey,12,Presid 6ent00'OS CDT)
Peter T.Bail -Webber Waterworks
eer orized Signature) " Owner(Authorized Signature) Contractor(Authorized Signature)
Date:10/9/2026 Date: 1 o j Zo1 U Date: 10/12/2026
Approved by Funding Agency(if applicable): _ __ Date:
CHANGE PROPOSAL SUMMARY SHEET
Client: Brushy Creek Regional Utility Authority
Project: BCRUA Phase 2A Water Treatment Plant Expansion
Contractor: Webber Waterworks,LLC
CO No.: 001
Date: 10/9/2026
CONTRACT AMOUNT BEFORE THIS CHANGE: $ 97,619,149.00
QUANTITY CONTRACT UNIT ADJUSTED UNIT
ITEM No. (Add/Deduct) UNIT DESCRIPTION PRICE PRICE UNIT PRICE AMOUNT
1 1 LS RCP-001,CPR-001,TSC Admin Network N/A N/A $ - $ -
2 1 LS CPR-002,TSS Potholing N/A N/A $ 2,304.72 $ 2,304.72
3 1 LS RCP-002,CPR-003,Filter Gallery Changes N/A N/A $ 19,408.45 $ 19,408.45
RFI-045,CPR-004,TSS Over-Excavation of
4 1 LS Non-Native Material and Backfill(Direct N/A N/A $ 376,857.00 $ 376,857.00
Charges Only)
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
GRAND TOTAL THIS CHANGE: $ 398,570.17
REVISED CONTRACT AMOUNT AFTER THIS CHANGE: $ 98,017,719.17
Request for Change Proposal (Not a Change Order)
Request No. 001
Date of Issuance: February 16,2026 Initiated by: Owner/Engineer
Owner:BCRUA Owner's Contract No.:NA
Project:Phase 2A WTP Expansion Date of Contract: 12/15/2026
Contractor:Webber Waterworks,LLC Engineer's Project No.:3-00867
Please submit an itemized proposal for changes in the Contract Sum and/or Contract Times for the proposed
modifications to the Contract Documents described herein:
Description:
Remove the Administrative network components from Treatment Structure Central including router,network switches,SFP,
wireless access points,and associated CAT6 cabling.This system has already been installed and is functioning.The requirement
for updating IP addressing scheme on the Admin network has not been removed.
The Moxa IKS series network switches were originally specified for the SCADA,camera,and access control networks.To match
with the Phase 2 projects and understanding that the IKS series is late in its lifecycle the network switches will be changed to
Moxa RKS series.Provide 8 port Gigabit Ethernet option cards for all the ports shown in the updated drawings.
Attachments:
RCP-001 drawings
This is not a Change Order. All work shall be in accordance with terms and conditions of original
Contract Documents.
CHANGE WILL: CHANGE WILL:
[Increase][Decrease]Contract Price by: [Increase][Decrease]Contract Time by:
$ Calendar Days
• No Change to Contract Price ■ No Change to Contract Time
• RECOMMENDED ■ ACCEPTED
p ❑ NOT RECOMMENDED ❑ NOT ACCEPTED
By: Sew 11/ 90ir By: By:
Contractor(Authorized Signature) Eng' er( orized Signature) Owner(Authorized Signature)
Date: 6/9/26 Date: 6/25/2026 Date: 6/29/2026
Change Proposal (Not a Change Order)
Request No. 002
Date of Issuance: June 25,2026 Initiated by: Contractor
Owner:BCRUA Owner's Contract No.:NA
Project:Phase 2A WTP Expansion Date of Contract: 12/15/2025
Contractor:Webber Waterworks,LLC Engineer's Project No.:3-00867
Please submit an itemized proposal for changes In the Contract Sum and/or Contract Times for the proposed
modifications to the Contract Documents described herein:
Description(Insert written description of the Work):
Field Directive to perform pothole excavation of Treatment Structure South(TSS)to determine extent of non-native material
located below planned treatment structures.Work performed as Time and Material tracking of additional excavation effort.
Attachments:(List attached documents that support description):
See Approved CPR-002.
This is not a Change Order. All work shall be in accordance with terms and conditions of original
Contract Documents.
CHANGE WILL: CHANGE WILL:
[Increase][Decrease]Contract Price by: [Increase][Decrease]Contract Time by:
$2,304.72 0 Calendar Days
❑ No Change to Contract Price • No Change to Contract Time
• RECOMMENDED • ACCEPTED
❑ NOT RECOMMENDED 0 NOT ACCEPTED
Teter T. Bailey
By: Peter T Bailey(Oct 12 2026 16 00 05 con By: By:
Contractor(Authorized Signature) E eer orized Signature) Owner(Authorized Signature)
Peter T.Bailey,President-Webber Waterworks
Date: 10/12/2026 Date: 10/9/2026 Date:
Change Proposal (Not a Change Order)
Request No. 003
Date of Issuance: August 27,2026 Initiated by: Owner
Owner:BCRUA Owner's Contract No.:NA
Project:Phase 2A WTP Expansion Date of Contract: 12/15/2025
Contractor:Webber Waterworks,LLC Engineer's Project No.:3-00867
Please submit an itemized proposal for changes in the Contract Sum and/or Contract Times for the proposed
modifications to the Contract Documents described herein:
Description(Insert written description of the Work):
Request for Change Proposal No.002(RCP-002)clarified filter gallery piping modifications and added additional steel pipe
changes to the 36-inch Waste Backwash Line(WBW)to accommodate future phases of the Treatment Plant.Webber's proposal
(CPR-003)is acceptable.
Attachments:(List attached documents that support description):
See Approved CPR-003 and RCP-002.
This is not a Change Order. All work shall be in accordance with terms and conditions of original
Contract Documents.
CHANGE WILL: CHANGE WILL:
flncrease][Decrease]Contract Price by: [Increase][Decrease]Contract Time by:
$19,408.45 0 Calendar Days
❑ No Change to Contract Price ■ No Change to Contract Time
• RECOMMENDED • ACCEPTED
0 NOT RECOMMENDED 0 NOT ACCEPTED
?etaT. Barley
By: Peter T Ballet/(Oct a 6 16 c By: By:
Contractor(Authorized Signature) E eer u orized Signature) Owner(Authorized Signature)
Peter T.Bailey,President-Webber Waterworks
Date: 10/12/2026 Date: 10/9/2026 Date:
Change Proposal (Not a Change Order)
Request No. 004
Date of Issuance: September 8,2026 Initiated by: Owner
Owner:BCRUA Owner's Contract No.:NA
Project:Phase 2A WTP Expansion Date of Contract: 12/15/2025
Contractor:Webber Waterworks,LLC Engineer's Project No.:3-00867
Please submit an itemized proposal for changes in the Contract Sum and/or Contract Times for the proposed
modifications to the Contract Documents described herein:
Description(Insert written description of the Work):
RFI-045 directed additional excavation of non-native materials in the Treatment Structure South(TSS)excavation and additional
backfill of the over-excavated areas to facilitate construction of the treatment structure. CPR-004 includes approved Time and
Material timesheets from Contractor and Subcontractor for the additional work.Delay associated with the additional work is
currently under review and will be handled as a separate Change Proposal.
Attachments:(List attached documents that support description):
See RFI-045 response and approved CPR-004.
This is not a Change Order. All work shall be in accordance with terms and conditions of original
Contract Documents.
CHANGE WILL: CHANGE WILL:
[Increase][Oecr ace]Contract Price by: [Increase][Decrease]Contract Time by:
$376,857.00 0 Calendar Days
❑ No Change to Contract Price ■ No Change to Contract Time
• RECOMMENDED ■ ACCEPTED
❑ NOT RECOMMENDED 0 NOT ACCEPTED
Teter7:Bane
By: Ballet'(Oct 12 202 6 00 05 CD'I By: By:
Contractor(Authorized Signature) E eer u orized Signature) Owner(Authorized Signature)
Peter T.Bailey, President-Webber Waterworks
Date: 10/12/2026 Date: 10/9/2026 Date:
BCRUA Ph2A WTP_CO 001 _RCP-001 ,
CPR-002, CPR-003, and CPR-004
Final Audit Report 2026-10-12
Created: 2026-10-12
By: Lori Brown(Ibrown@wwebber.com)
Status: Signed
Transaction ID: CBJCHBCAABAAfMJW2x19T_C_hPd3gAZPTuYoX536FT9n
"BCRUA Ph2A WTP_CO 001_RCP-001 , CPR-002, CPR-003, an
d CPR-004" History
Document created by Lori Brown (lbrown@wwebber.com)
2026-10-12-7:43:01 PM GMT-IP address: 144.125.240.237
Document emailed to peter.bailey@wwebber.com for signature
2026-10-12-7:45:33 PM GMT
4'1 Email viewed by peter.bailey@wwebber.com
2026-10-12-8:54:22 PM GMT-IP address: 104.47.11.62
Signer peter.bailey@wwebber.com entered name at signing as Peter T. Bailey
2026-10-12-9:00:03 PM GMT-IP address: 144.125.240.237
Document e-signed by Peter T. Bailey(peter.bailey@wwebber.com)
Signature Date:2026-10-12-9:00:05 PM GMT-Time Source:server-IP address: 144.125.240.237-Signature Appearance Selected:
TYPE
O Agreement completed.
2026-10-12-9:00:05 PM GMT