Contract - Dan Williams Company - 10/22/2026 Page I of 1 Contract Quantity Adjustment/Change Order ROUND ROCK TEXAS NN 0605 Department: PUBLIC WORKS Date: 8/14/26 Project Name: CR 112 East City Project ID Change Order/Quantity Number: IFB 24-416 Adjustment No. 1 Vendor: DAN WILLIAMS COMPANY I N.CAPITOL OF TX HWY, BUILDING 3, SUITE 380,AUSTIN,TX 7 512-320-1410 Company Name Address Phone No. Justification Changes per Enginner on Record and City Staff. Storm Sewer inlets incorrectly labeled in the plan set and not caputred in item summary. Adjusting of manholes; due to change in roadway grades per existing site conditions. Also,includes quantities for constructing a detour connection between the East and West segments of CR 112. SUMMARY Amount %Change Original Contract Price: $20,434,128.40 Previous Quantity Adjustment(s): $0.00 This Quantity Adjustment: $71,321.05 Total Quantity Adjustment(s): $71,321.05 0% Total Contract Price with Quantity Adjustment(s): $20,505,449.45 Previous Change Order(s): $0.00 This Change Order: $0.00 Total Change Order(s)To Date: $0.00 0% Adjusted Contract Price: [Original Contract Price Plus Quantity Adjustments)Plus Change Order(s)) $20,505,449.45 Difference between Original and Adjusted Contract Prices: $71,321.05 0% Onginal Contract Time: Time Adjustment by previous Quan.Adj./Change Order: Time Adjustment by this Quan.Adj./Change Order: New Contract Time: 0 Submitted for Approval Prepared By: CLAYTON SWANSON,PROJECT ENGINEER,DAN WILUAMS COMPANY (-1 / �•/?-1 G Printed Name,Title,Company Signature Date Approvals Contractor: CLAYTON SWANSON,PROJECT ENGINEER,DAN WILUAMS COMPANY 7-12 LG Printed Name,Title,Company Signature Date City Project II 11 Manager: r�� A LL b\4\�,. PfrA 12^ cY - 17 Printed Name,Title Si ture Date Mayor/City //itf Manager: r ' \ AA°. /6722/24 rinted Narrte, le Sig re Date 1L Page 2 of 3 Contract Quantity Adjustment/Change Order ROILS POCK I!■.5 TI.06/25 Project Name: CR 112 East Change Order/Quantity Adjustment No. 1 Change Order Data Contract Time Bid Item # Item Description Unit Qty. Unit Price Amount Adjustment(Days) $0.00 0 $0.00 0 $0.00 0 $0.00 .$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 _ $0.00 _ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00- $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 ' $0.00 TOTALS: $0.00 0 Page 3 of 3 Contract Quantity Adjustment/Change Order ■ano!MX f E xA5 rev.ONZS Project Name: CR 112 East Change Order/Quantity Adjustment No. 1 Quantity Adjustment Data Contract Time Bid Item# Item Description Unit Qty. Unit Price Amount Adjustment(Days) 496-6008 REMOV STR(BOX CULVERT) LF 12 $250.00 $3,000.00 465-6015 -INLET (COMP) PCO 3 FT(RIGHT) EA 2 $5,500.00 $11,000.00 465-6017 INLET (COMP)PCO 4 Fr(NONE) EA 1 $6,000.00 $6,000.00 465-6018 INLET (COMP)PCO 4 FT(LEFT) EA 1 $6,500.00 $6,500.00 465-6019 INLET (COMP)PCO 4 FT(RIGHT) EA 1 $6,000.00 $6,000.00 479-6001 ADJUSTINT MANHOLES EA 2 $2,500.00 $5,000.00 508-6001 CONSTRUCTING DETOURS SY 157 $110.00 $17,270.00 512-6001 PORT CTB(FUR&INST)(LOW PRO)TY 1 LF 320 $20.00 $6,400.00 512-6010 PORT CTB(FUR&INST)(LOW PRO)TY 2 LF 160 $20.00 $3,200.00 662-6093 WK ZN PAV MRK REMOV(Y)4"(SLD) LF 2009 $1.20 $2,410.80 403-6001 TEMPORARY SPL SHORING SF 165.1 $27.50 $4,540.25 $0.00 $0.00 $O.OU $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0,00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $71,321.05 0