R-2026-268 - 11/5/2026 RESOLUTION NO. R-2026-268
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with
Cash Construction Company, Inc. for the Gattis School Road Segment 3 Project, and
WHEREAS,the Council has determined that it is necessary to make adjustments/changes to the
quantity of work to be performed or materials,equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 3, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 3 to the Contract with Cash Construction Company, Inc. for the Gattis
School Road Segment 3 Project, a copy of said quantity adjustment/change order being attached hereto
as Exhibit"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date,hour,place and subject
of the meeting at which this Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and the subject matter hereof were
discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551,
Texas Government Code, as amended.
RESOLVED this 5th day of November, 2026.
C G MO AN, Mayor
City of Ro d Rock,Texas
A ST:
FRANKLIN, City Clerk
0112.20262
EXHIBIT
A
Page 1 of 3
Contract Quantity Adjustment/Change Order
rev,01/16
Department: Public Works
Project Name: Gattis School Road Segment 3 Date: 9/17/26
City Project ID Change Order/Quantity
Number Adjustment No. 3
Vendor Cash Construction Company 2171Gngston Lacy Blvd 512-251-7872
Company Name Address Phone No.
Justification
Addition of improvements to existing HOA sign,addition of irrigation sleeves,removal of a median and paving added where the median was shown to be placed but not needed for
Clay Madsen center,and relocate a hydrant on Windy Park not shown in the plans. The change order also includes additional 8 mix HMAC due to plan quantity being incorrect,
driveway access needed to be added,additional HMAC was needed along AW Grimes not shown for detouring to keep traffic moving and not bottlenecked,TCP revisions causing more
B mix due to the existing pole line not being removed timely by Oncor,additional B mix for areas where poles were still remaining,overbuild of curb and gutter and medians caused
overrun,as well as general yield of HMAC due to all these added factors in placing the HMAC.
SUMMARY Amount %Change
Original Contract Price: $26,735,973.35
Previous Quantity Adjustment(s): $170,651.20
This Quantity Adjustment: $457,841.50
Total Quantity Adjustment(s): $628,492.70
Total Contract Price with Quantity Adjustment(s): $27,364,466.05
Previous Change Order(s): $250,358.86 1%
This Change Order: $39,919.77 0%
Total Change Order(s)To Date: $290,278.63 1%
Adjusted Contract Price [Original Contract Price Plus Quantity Adjustments)Plus Change Order(s)): $27,654,744.68
Difference between Original and Adjusted Contract Prices: $918,771.33
Original Contract Tree: 700
Time Adjustment by previous Quan.Adj./Change Order: 28
Time Adjustment by this Quan.Adj./Change Order: 15
New Contract Time: 743
Submitted for Approval
Prepared By: Scott Blanda,Project Manager,Cash Construction 9/17/26
Signature Printed Name,Title,Company Date
Approvals
Contractor: [ . Scott Blanda,Project Manager,Cash Construction 9/17/26
Signature Printed Name,Title,Company Date
City Project $r - 1511 S- 1�
Manager: � i �lh (Q ` 12 '2C
Signature Printed Name,Title Date
Mayor/City
Manager
Signature Printed Name,Title Date
Contract Quantity Adjustment/Change Order
Project Name:Gattis School Road Segment 3
Quan.Adj./Change Order No.: 3
Change Order Data
Contract
Time
Adjustment
Item# Item Description Unit Qty. Unit Price Amount (Days)
1 CPR#27-Enclave HOA Sign Improvement-Landscaping LS 1 $10,917.57 $10,917.57 0
2 CPR#27-Enclave HOA Sign Improvement-Electrical LS 1 $5,209.18 $5,209.18' 0
3 CPR#29-Turtle Creek Irrigation Sleeves LS 1 $4,859.52 $4,859.52 1
4 CPR#30-Demo Clay Madsen Median LS 1 $4,761.92 $4,761.92 1
CPR#31-Fire Hydrant Relocation(Same Bid Item Price as CPR#8 on CO
5 #2) EA 1 $1,328.51 $1,328.51 0
6 CPR#32-Dry Stack Rock Wall LS 1 $2,832.62 $2,832.62 1
7 CPR#33-Concrete Curb Cuts LS 1 $10,010.45 $10,010.45 2
TOTALS: S39,919.77 5
l' Contract Quantity Adjustment/Change Order
Project Name:Gattis School Road Segment 3
Quan.Adj./Change Order No,- 3
Quantity Adjustment Data
Contract
Time
Adjustment
Bid Item# Item Description Unit Qty. Unit Price Amount 1Dava1
CPR#26
3076-6003 D-GR HMA TV-B PG64-22 Tons 3995.22 $125.00 $499,402.50 10
I CPR#30
3076-6079 D-GR HMA TV-C PG70-22(EXEMPT) Tons 10 $129.00 $1,290.00 0
CPR#31
531-6002 CONC SIDEWALKS(5") SY 59 $76.00 $4,484.00 1
—
530-6004 DRIVEWAYS(CONC) SY - 20 — $102.00 $2,090.00 _ 0
529-6008 CONC CURB&GUTTER(TY II) LF 15 $21.00 $315.00 0
CPR#34
474-6022 PRE-CAST TRENCH DRAIN(IN CONC PAVEMENT) LF -30 $467.00 -$14,010.00 -1
WW-35(510) PRESSURE TAP(6-IN DIA X 16-IN DIA) EA , -1 $8,580.00 -$8,580.00. 0
WW-37(510) INSTL OR RECON LAT SVC TO REP PIPE(1.5-IN SVC X 16-IN PIPE) EA -10 $2,710.00 -$27,100.00 0
TOTALS: S457,841.50 10