R-00-05-11-14C8 - 5/11/2000CITY OF ROUND ROCK
t p
..:rrrd
Mayor
Robert A. Stanka, Jr.
Mayor Pro-tem
Marsha A. Chavez
Council Members
Tom Nielson
Earl M. Hairston
Rick Stewart
Earl Palmer
Jimmy Joseph
City Manager
Robert L Bennett, Jo.
City Attorney
Stephan L Sheets
June 23, 2000
Mr. John Spivey
Smith Contracting Company
15308 Ginger Street
Austin, TX 78728
Dear Mr. Spivey:
The Round Rock City Council approved Resolution No. R- 00- 05- 11 -14C8 at their
regularly scheduled meeting on May 11, 2000. This resolution approves Change Order
No. 1 for the Mesa Ridge Drainage Channel Improvements Project.
Enclosed is a copy of the resolution and change order for your files. If you have any
questions, please do not hesitate to contact Jim Nuse at 218 -5555.
Sincerely,
Enclosures
Fax: 512 -218 -7097
Christine Martinez
Assistant City Secretary
e dV!/t.Jre6
1-800-735-2989 TDD 1- 800 -735 -2988 Voice
www.ci round- rock.tx.us
221 East Main Street
Round Rock. Texas 78664
512. 218.5400
O
CITY OF ROUND ROCK
• tt
... •
Mayor
Robert A. Stluka, Jr
Mayor Pro -tem
Martha A. Chavez
Council Members
Tom Nielson
Earl M. Hairston
Rick Stewart
Earl Palmer
Jimmy Joseph
City Manager
Robert L Bennett, Jo.
City Attorney
Stephan L Sheets
June 15, 2000
Mr. Mack Smith
Smith Contracting Company
15308 Ginger Street
Austin, TX 78728
Dear Mr. Smith:
221 East Main Street
Round Rock, Texas 78664
. 512- 218 -5400
The Round Rock City Council approved Resolution No. R- 00- 05- 11 -14C8 at their
regularly scheduled meeting on May 11, 2000. This resolution approves Change Order
No. 1 for the Mesa Ridge Drainage Channel Improvements Project.
Enclosed is a copy of the resolution and Change Order for your files. If you have any
questions, please do not hesitate to contact Jim Nuse at 218 -5555.
Sincerely,
Christine Martinez
Assistant City Secretary
Enclosures
Fax: 512- 218 -7097
1-800.735-2989 TDD 1 -800- 735 -2988 Voice
www.ct.round- rock.tx.us
RESOLUTION NO. R- 00- 05- 11 -14C8
WHEREAS, the City of Round Rock has previously entered into a
contract ( "Contract ") with Smith Contracting Company for the Mesa Ridge
Drainage Channel Improvements Project, and
WHEREAS, it has been determined that it is necessary to change
said Contract in accordance with the attached Contract Change Order No.
1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Contract Change Order No. 1 to the Contract with
Smith Contracting Company for the Mesa Ridge Drainage Channel
Improvements Project.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended, and the Act.
RESOLVED this llth day of May,
ANNE LAND, City Secretar
C' f1RIST/NE in germiEZ, A55T.
K.\ RPDOCS \RRSOLDT1\R00511CS.WPD /eC
CHANGE
ORDER
Distribution to.
OWNER sO
ARCHITECT ❑
CONTRACTOR LE
FIELD ❑
OTHER ❑
PROJECT: Mesa Ridge Drainage CHANGE ORDER NUMBER: 1
Channel Improvements
City of Round Rock INITIATION DATE:
TO:
Smith Contracting Company ENGINEER'S PROJECT NO: 97118 -CO
15308 Ginger Street
Austin, TX 78728 CONTRACT FOR: Drainage Improvements
CONTRACT DATE: 11/29/99
You are directed to make the following changes in this Contract:
See Attached
Not valid untd signed by both the Owner and Engineer.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time:
The original (Contract Sum) (Guaranteed Maximum Cost) was 5448,528.30
Net change by previously authorized Change Orders 5 -0-
The Contract Sum will be decreased
by this Change Order ... 5285,337.43
The new Contract Sum including this change order will be . 5163,190 87
The Contract Time will be increased by . ( 14) Days
The Date of Substantial Completion as of the date of this Change Order therefore
Smith Contracting Co
CONTRACTOR
15308 Ginger Street
Fisher Hagood, Inc.
ENGINEER
One Chisholm Trail, Suite 5200
Address Address
Rout r Rock, TX 7868 C ` Austin, TX 78728
BY d `.'�7_ BY—
Date
Authorized:
March 11, 2000
City of Round Rock
OWNER
2008 Enterprise
Address
MESA RIDGE DRAINAGE CHANNEL IMPROVEMENTS
CHANGE ORDER NO. 1
Item Description and Unit Price of Item
No. In Words ADD DEDUCT
I Delete 1 EA stabilized construction entrance, $1,000 00
complete and in place, per each, @ $1,000.00
2 Delete 1,000 LF Temporary silt fence, $1,500 00
complete and in place, per linear foot, @ $1.50 LF
3 Delete 200 LF Temporary Rock Benn,
complete and in place, per linear foot, @ $10.00 LF
10 Delete 1,100 LF Barbed wire fencing,
complete and in place, per linear foot, @ $1.00 LF
$2,000 00
51,100.00
11 Delete 14 Sta Clearing and Grubbing $16,098.88
complete and in place, per station, @ $1,149.92 Sta
13A Deduct400 LF for usingHDPE $4,500.00
Inlieu of RCP @ $11.25 LF
15A Deduct 149 LF for using BDPE
Inlieu of RCP @ $30.00 LF
18A Add 564 LF 36 "RCP Class III, including bedding, backfilltng,
compaction, and finish grading, (Sta. 1 +57.89 to Sta. 11 +00)
complete and in place, per linear foot, @ S90.00 LF
$50,760.00
$4,470.00
18B Deduct 941 LF for using HDPE $18,820.00
Inlieu of RCP @ $20.00 LF
20 Delete Item $8,000.00
21A Delete Item $29,993.20
21B Delete Item $6,245.80
23 Delete Item $7,500.00
24 Delete Item $14,000.00
25 Delete Item $2,000.00
26 Delete Item $2,100.00
27A Delete Item 511,623.50
27B Delete Item $1,496.25
28 Delete Item S40,000.00
29 Delete Item $5,250.00
30 Delete Rem $2,925.00
PAGE 1
MESA RIDGE DRAINAGE CHANNEL IMPROVEMENTS
CHANGE ORDERNO. 1
Item Description and Unit Price of Item
No. In Words ADD DEDUCT
31 Delete Item $36,920.00
32 Delete Item $12,768.00
33 Delete Item $91,016.55
34 Delete 1,100 LF 5' strand barbed wire with 5' steel "T" posts, S3,300 00
complete and in place, per linear foot, @ 53.00 LF
35 Delete 54,000 SY Hydromulch all distrubed areas and establish growth $27,000.00
per City of Round Rock requirements,
complete and in place, per square yard, ® $0.50 SY
36 Add 1 LS Remove and replace 600' $ 7,549.75
chain link fence for storm sewer
Const. Install temporary fence @ S7,549.75 LS
37 Add 912 CY Imported fill to cover pipe @ $8.75 CY $ 7,980.00
Note: Items deleted are not included in Phase I construction.
Total Deduct $285,337.43
PAGE
$ 66,289.75 $351,627.18
- DATE: May 5, 2000
SUBJECT: City Council Meeting — May 11, 2000
ITEM: 14.C.8. Consider a resolution authorizing the Mayor to execute
Contract Change Order No. 1 to Smith Contracting Company
for the Mesa Ridge Drainage Channel Improvements Project.
This change order provides for the decrease in the contract amount
and for a 14 -day extension of the contract period. This change is
for reducing the scope of work, and using the alternate HDPE
piping material. With this change order the original contract was
divided into Phase I and Phase II. This change order is to remove
Phase II from this contract. This change order, which is a
decrease of $285,337.43 or 64 %, which makes the current contract
amount $163,190.87. Staff recommends approval. Staff Resource
Person: Jim Nuse, Public Works Director.