R-00-06-08-11A5 - 6/8/2000RESOLUTION NO. R- 00- 06- 08 -11A5
WHEREAS, §8.610(4) Code of Ordinances (1995 Edition) provides
for the reimbursement for the oversizing of water mains, and
WHEREAS, 3406, Ltd. has submitted a reimbursement request for
the oversizing of water mains associated with the Wood Glen, Section 5,
Phases 1 and 2 subdivision improvements, and
WHEREAS, the City Council wishes to approve said reimbursement,
Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the City Council hereby approves of the reimbursement to
3406, Ltd. of $6,720.00, which is the cost of oversizing water mains
associated with the Wood Glen, Section 5, Phases 1 and 2 subdivision
improvements.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended, and the Act.
RESOLVED this the 8th day of June, 2000.
ST:
/. .I 4L.I
Y
K:\ WPDOCS \RSSOLIIPI \R00608A6.WPD /sc
, City Secretary
-e T A. LUKA,
A. S LUKA,
City of Round Rock,
Mayor
Texas
E OCKWOOD
NGINEERS, INC.
CIVIL ENGINEERING & PLANNING (512) 451 -7092
FAX (512) 377 -5402
May 16, 2000
Mr. Danny Halden, P.E.
Department of Public Works
City of Round Rock
2008 Enterprise
Round Rock, Texas 78664
Re: Wood Glen, Section 5, Phase II LE # 99 -710
Statement of Oversize Credit
Dear Mr. Heiden:
The Wood Glen owner was required by the Public Works Department to oversize an 8-
inch diameter wastewater line to a 12 -inch diameter wastewater line in the above
referenced project in order to provide wastewater service to an upgradient tract. An 8-
inch diameter line would have provided adequate service to this project. The calculation
of the oversize credit due to the owner is as follows:
(12" — 8 ") = 4" oversize
Oversize Credit = (4" x 1,428 LF x $2.60 /IN /LF) = $ 14,851.20
Wood Glen, Section 5, Phase II contains 29 single - family lots and 2 lots (13/B, 20 /A)
which are restricted to uses other than residential. The oversize fees are as follows:
Water
29 lots x $150 /lot $ 4,350.00
Wastewater
29 lots x $ 150 /lot $ 4,350.00
1501 -A W. ANDERSON LN., SUITE 102 • AUSTIN, TEXAS 78757
Mr. Danny Halden Page 2
Statement of Oversize Credit #99 -710
The amount of oversize fees due by the owner are as follows:
Please verify the above calculations. A copy of the wastewater collection plan for the
project is attached for your use.
Water Oversize Fee
Wastewater Oversize Fee
Wastewater Oversize Credit
Total Oversize Fee Credit
OCKWOOD ENGINEERS, INC.
Fred C. Lockwood, P.E.
cc: 3406, Ltd.
Mr. Paul Heiligenthal
s5 p2 oversize fee.doc
$ 4,350.00
4,350.00
< 14,851.20>
$ 6,151.20
OCKWOOD
NGINEERS, INC.
CIVIL ENGINEERING & PLANNING (512) 451 -7092
FAX (512) 377 -5402
February 10, 2000
Mr. Danny Heiden, P.E.
Department of Public Works
City of Round Rock
2008 Enterprise
Round Rock, Texas 78664
Re: Wood Glen, Section 5, Phase I LE # 99 -702
Statement of Oversize Credit
Dear Mr. Heiden:
The Wood Glen owner was required by the Public Works Department to oversize an 8-
inch diameter wastewater line to a 12 -inch diameter wastewater line in the above
referenced project in order to provide wastewater service to an upgradient tract. An 8-
inch diameter line would have provided adequate service to this project. The calculation
of the oversize credit due to the owner is as follows:
(12" — 8 ") = 4" oversize
Oversize Credit = (4" x 372 LF x $2.60 /IN /LF) = $ 3,868.80
Wood Glen, Section 5, Phase 1 contains 11 single - family lots. The use of lot 4, block 'A'
is limited by restrictive covenant to TNRCC requirements which do not allow the
construction of a residence on the lot. The oversize fees are as follows:
Water
/ 11 lots x $150 /lot
Wastewater
11 lots x $ 150 /lot
$ 1,650.00
$ 1,650.00
C Z / P � � o to 604 4)
1501 -A W. ANDERSON LN., SUITE 102 • AUSTIN, TEXAS 78757
Mr. Danny Heiden
Statement of Oversize Credit
The amount of oversize fees due by the owner are as follows:
Please verify the above calculations. A copy of the wastewater collection plan for the
project is attached for your use.
Sincere
Water Oversize Fee
Wastewater Oversize Fee
Wastewater Oversize Credit
Total Oversize Fee Credit
cc: 3406, Ltd.
Mr. Paul Heiligenthal
s5 p1 oversize fee.doc
CKWOOD ENGINEERS, INC.
Fred C. Lockwood, P.E.
FRED C. LOCKWOOD
9 i 50141
co . % i f
1 �08AL �
$ 1,650.00
1,650.00
< 3,868.80>
$ 568.80 ✓
Page 2
#99 -702
DATE: June 2, 2000
SUBJECT: City Council Meeting — June 8, 2000
ITEM: 11.A.5. Consider a resolution authorizing an oversize reimbursement in
the amount of $6,720 to 3406, Ltd. for the construction of a 12-
inch wastewater main in conjunction with Wood Glen, Section 5,
Phase 1 and Wood Glen, Section, 5, Phase 2 subdivision
improvements. The oversizing was necessary to provide
wastewater service for properties upstream of the Wood Glen
development. Staff Resource Person: Jim Nuse, Public Works
Director.