R-02-06-27-9B1 - 6/27/2002 RESOLUTION NO. R-02-06-27-9B1
WHEREAS, §8.610(4) and 98.611(10) , Code of Ordinances (1995
Edition) provide for the reimbursement for the oversizing of water and
wastewater mains, and
WHEREAS, Bon Terre Lake Forest has submitted a reimbursement
request for the oversizing of water and wastewater mains associated
with the Lake Forest II, Village I development, and
WHEREAS, the City Council wishes to approve said reimbursement,
Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the City Council hereby approves of the reimbursement to Bon
Terre Lake Forest of $8,593.42, which is the cost of oversizing water
and wastewater mains associated with the Lake Forest II, Village I
development.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended.
i ODM\WORLOOX\0:\W00%\RESOLD l\R2027BI-WPD/.c
RESOLVED this the 27th day of June, 2002.
L WELL, d ayor
City of Round Rock, Texas
AT EST:
CHRISTINE R. MARTINEZ, City Secr ary
2
FEPNEPPING DMVE
LOOL PIVEP LWP
P
�m5
S Polo
8
N LAKE FOREST PHASE 2
wE VILLAGE 1J`
s
BAKER-AICKLEN
6 ASSOCIATES,INC.
Engineers/Surveyors
February 12,2002
Mr.Danny Halden,P.E.
City of Round Rock
Department of Public Works
2008 Enterprise Drive
Round Rock,TX 78664
RE: Lake Forest II,Village I,Subdivision improvements
Reimbursement Fee for Water&Wastewater Line Oversize
Job#1056-2-003-26
Dear Mr.Halden:
On behalf of Mr.Joel Robuck,we are submitting this request for reimbursement for the
following line oversizing associated with the referenced project. Attached you will find a
copy of the contractor's bid difference between the 8"vs. 12"water line connection at
Gattis School Road.
12"Wastewater 05.29 LF x 4 in.x$2.60/in.-LF = $7,335.02
12"Water&Connection �,�•
TOTAL $�2 4i `78—
If you have any questions abo t this reimbursement amount,please give me call at 244-
9620.
Since el 1Z1 L.F. x 4-j^ X 2.6o/;„-t.f- 11258,40 a.
)a.slw� 7,33S,oz
H.D. o�P E. r L -4 el o Tel
HDR/vmb
Attachment
b�r�
Cc: Mr.Joel Robuck a� 81 Sq 3,Bri pQ�-,
0:\1056-2-003-26\dhaldm oversize talcs ltr 2.12-02 �`”
a��
203 E. Mein St.. Suite 201 •Round Rock.Texas 713664- 512/244-9620 FAX 512/244-9623
DATE: June 21,2002
SUBJECT: City Council Meeting—June 27,2002
ITEM: 9.B.1. Consider a resolution approving the reimbursement to Bon
Terre Lake Forest of$8,593.42,for the cost of oversizing
water and wastewater mains associated with the Lake Forest
II, Pillage I development
Resource: Jim Nuse,Chief of Operations/Assistant City Manager
Danny Halden,City Engineer
History: Water and wastewater mains were oversized in Lake Forest II,Village I for future
service to serve future development in the same vicinity.
Funding:
Cost: $8,593.42
Source of funds: Oversize account established in Chapter 8 of the Round Rock City
Code.
Outside Resources: Baker-Aicklen and Associates Inc.
Impact: Minimal. To date approximately$139,000.00 has been paid in to the oversize
account by the entire Lake Forest development and the City has reimbursed
approximately$85,000.00.
Benefit: Helps reduce possibility of constructing parallel mains in the future.
Public Comment:N/A
Sponsor:N/A