August 29, 2002
Mr. James K. Haney, P.E.
HDR Engineering, Inc.
2211 South IH 35, Suite 300
Austin, TX 78738
Dear Mr. Haney:
The Round Rock City Council approved the following two Resolutions at
their regularly scheduled meeting on August 8, 2002:
• Resolution No. R- 02- 08- 08 -11G1 which approves Amendment No. 3
for a change in the scope of services concerning the 1998 -1999 Water
System Improvements Project.
• Resolution No. R- 02- 08- 08 -11G2 which approves Amendment No. 3
for a change in the scope of services concerning the Lake Creek Pump
Station Improvements Project.
Enclosed are copies of the resolutions and original amendments for your
files. If you have any questions, please do not hesitate to contact Tom
Clark at 218 -6617.
Sincerely,
Christine R. Marti nez
City Secretary
Enclosure
CITY OF ROUND ROCK 221 East Main Street • Round Rock. Texas 78664
RESOLUTION NO. R- 02- 08- 08 -11G1
WHEREAS, the City of Round Rock has previously entered into a
Contract for Engineering Services ( "Contract ") with HDR Engineering,
Inc. for the 1998 -1999 Water System Improvements, and
WHEREAS, HDR Engineering, Inc. has submitted Amendment No. 3 to
the Contract for Engineering Services for a change in the scope of
services, and
WHEREAS, the City Council desires to enter into said Amendment
No. 3 to the Contract for Engineering Services with HDR Engineering,
Inc., Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Amendment No. 3 to the Contract for Engineering
Services with HDR Engineering, Inc. for a change in the scope of
services, a copy of said amendment being attached hereto as Exhibit "A"
and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended.
..DOHA \WORLDO% \0: \WOO % \RESOLUTI \RE00 WPD /cm
ATTEST:
RESOLVED this 8th day of August, 2002.
CHRISTINE R. MARTINEZ, City Secreta
- F
„ 0" Mayor
ity of Rock, Texas
2
AMENDMENT No. 3
To the
CONTRACT FOR ENGINEERING SERVICES between
THE CITY OF ROUND ROCK and
HDR ENGINEERING, INC.
Dated July 5, 2002
GENERAL
This constitutes an Amendment to the Contract for Engineering Services — 1998/1999
Water System Improvements Project for PROFESSIONAL SERVICES between the
City of Round Rock, Texas (City) and HDR Engineering, Inc. of Austin, Texas
(Engineer). The scope of services to be provided by the Engineer as listed in Attachment
B of the Contract has been directly influenced by the following out of scope work items:
For the Construction Phase, additional engineering services were required to administer
approximately 1,500 feet of 16 -inch pipeline that was installed as part of the 81 -South
Elevated Water Storage Tank Project. In addition, additional engineering services were
required due to the delay in the property acquisition for the construction of the High
Country Elevated Water Storage Tank. Due to the additional work required for the
Construction Phase of the 1998/1999 Water Systems Improvements Project, an additional
Engineering Fee is required to complete the construction and contract close -out of
Contract No. 6 — 81 South Standpipe Demolition and Elevated Water Storage Tank
Construction.
The scope of engineering services performed by the Engineer for Contract Completion is
as follows:
1. Monthly progress meetings, payment applications, project administration services,
and miscellaneous expenses for a scheduled final completion of the construction
work in August 2002.
2. Review remaining shop drawings and submittals including site work, electrical,
paint shrouding plan, demolition plan, and lead compliance plan.
3. Perform project close -out tasks including final walk through, punch list, and
administer warranty bonds and other close -out documents.
4. Completion of project As -Built Drawings by October 2002.
The above listed services will be completed on a reimbursable, Per Diem basis in the
amount not to exceed Ten Thousand Seven Hundred and Fifty Dollars ($10,750.00).
The services, as authorized by the City, shall be reimbursed based upon Direct Salary
Cost ($ per hour) times an overhead factor of 3.20 for the Engineer. All direct non -labor
expenses will be billed at the invoice cost plus ten percent (10 %) service charge. (Note:
Billing rates are revised each January to reflect salary increases.)
EXHIBIT
The term of this Amendment shall commence on the signing date and continue in effect
until such time as terminated in writing by either party.
The undersigned signatory on signatories for the Engineer hereby represents and warrant
that the signatory is an officer of the organization for which he or she has executed this
Contract and that he or she has full and complete authority to enter into this Contract on
behalf of the firm. The above- stated representations and warranties are made for the
purpose of entering into this Contract with the City.
IN WITNESS HEREOF, the City and the Engineer have executed these presents in
duplicate.
HDR Engineering, Inc.
By:
Jtrues K. (Ken) Hardy, P.E.
Executive Vice President
City of Round Rock, Texas
By:
Nyle Maxwell
Mayor
Date:
SIGNATURE WARRANTY
July 5, 2002
Mr. Don Rundell, P.E.
Chief Utility Engineer
City of Round Rock
2008 Enterprise Drive
Round Rock, TX 78664
RE: TRANSMITTAL
City of Round Rock — 1998/1999 Systems Improvements
Amendment No. 3 to the Contract for Engineering Services
Dear Mr. Rundell:
HDR Engineering, Inc.
Employee Owned
ha 1
Enclosed please find two original copies of Amendment No. 3 for the above referenced
project. We are submitting this proposed Amendment for additional Construction Phase
Services that we have provided.
As you recall, this contract has covered the Construction Phase Services for several
projects including:
• Southeast Elevated Pump Station & Site Improvements
• Chisholm Valley Standpipe Demolition
• Chisholm Valley Elevated Tank Construction
• High Country Elevated Tank Construction
• 81 South Standpipe Demolition
• 81 South Elevated Tank Construction.
In addition, we have performed construction Phase Services to administer the
construction of a new 16 -inch pipeline as part of the 81 South Tank Project. The contract
between the City and HDR for our services on the Lake Creek Pump Station Project was
amended to cover the design of this pipeline, but no fee was adjusted for the associated
Construction Phase Services.
As you well know, this project has been underway for several years, and the schedule for
several of the projects has slipped significantly Most notable was the construction of the
High Country Elevated Tank, which was delayed 481 days while the City completed
acquisition of the required property. During this time, the construction contractor was
delayed, and HDR provided additional services to maintain the contractor and negotiation
the resulting change orders.
It has been our intent to complete the Construction Phase Services for all the projects
without exceeding the contractual maximum fee. However, the additional services we
have provided to administer the 16 -inch line construction, our additional services for
coordination/negotiation during the project delays, and the inflation in our reimbursable
billing rates over time will make this impossible
Suite 300 Telephone
2211 South IH 35 512 912 -5100
Austin,Texas Fax
78741 512 912 -5158
Mr. Don Rundell
July 5, 2002
Page 2
For your reference, the City Council Resolution authorizing the Contract with HDR is
No. R- 98- 06- 11 -13B4. If the Amendment meets with the City's approval, please return
an executed copy to me for our records.
We appreciate your consideration of this request and look forward to completing
construction of the 1998/1999 Water System Improvement Projects. Please call Jason
Jones or me if you have any questions.
Sincerely,
HDR Engineering, Inc.
Neil A. Graff, P.E.
Vice President
Enclosure: Amendment No. 3
South 81 Elevated Tank
�i'111 AIN:R _
S1GRAPHICSICOUNCIL AGENDA fTEMSIENGINEERING.81 S. ELEVATED TANK
DATE: August 2, 2002
SUBJECT: City Council Meeting — August 8, 2002
ITEM: *11.G.1. Consider a resolution authorizing the Mayor to execute Amendment
No. 3 to the Contract for Engineering Services with HDR
Engineering, Inc. for the 1998 -1999 Water System Improvements.
Resource: Jim Nuse, Chief of Operations /Assistant City Manager
Tom Clark, Director of Utilities
History: The South 81 Elevated Tank and Standpipe Demolition Projects are the last of six
projects under the 1998/1999 Water System Improvements Contract with HDR.
The other four were the Southeast Elevated Pump Station & Site Improvements,
Chisholm Valley Elevated Tank and Standpipe Demolition, and the High Country
Elevated Tank.
The general scope of work under this contract amendment is for work related to
the Construction Phase Service of the contract associated with the South 81
Elevated Tank and Demolition Project. These services include monthly progress
meetings, construction site visits, review shop drawings, and final walk through
and preparing Record Drawings to name just a few.
Staff feels this work and the associated fee of $10,750.00 is just and recommends
approval.
Funding:
Cost: $10,750.00
Source of funds: Self- Financed Utility Fund
Outside Resources: HDR Engineering, Inc.
Impact/Benefit: The successful completion of the South 81 Elevated Tank Project
Public Comment: N/A
Sponsor: N/A
AMENDMENT No. 3
To the
CONTRACT FOR ENGINEERING SERVICES between
THE CITY OF ROUND ROCK and
HDR ENGINEERING, INC.
Dated July 5, 2002
GENERAL
This constitutes an Amendment to the Contract for Engineering Services — 1998/1999
Water System Improvements Project for PROFESSIONAL SERVICES between the
City of Round Rock, Texas (City) and HDR Engineering, Inc. of Austin, Texas
(Engineer). The scope of services to be provided by the Engineer as listed in Attachment
B of the Contract has been directly influenced by the following out of scope work items:
For the Construction Phase, additional engineering services were required to administer
approximately 1,500 feet of 16 -inch pipeline that was installed as part of the 81 -South
Elevated Water Storage Tank Project. In addition, additional engineering services were
required due to the delay in the property acquisition for the construction of the High
Country Elevated Water Storage Tank. Due to the additional work required for the
Construction Phase of the 1998/1999 Water Systems Improvements Project, an additional
Engineering Fee is required to complete the construction and contract close -out of
Contract No. 6 — 81 South Standpipe Demolition and Elevated Water Storage Tank
Construction.
The scope of engineering services performed by the Engineer for Contract Completion is
as follows:
1. Monthly progress meetings, payment applications, project administration services,
and miscellaneous expenses for a scheduled final completion of the construction
work in August 2002.
2. Review remaining shop drawings and submittals including site work, electrical,
paint shrouding plan, demolition plan, and lead compliance plan.
3. Perform project close -out tasks including final walk through, punch list, and
administer warranty bonds and other close -out documents.
4. Completion of project As -Built Drawings by October 2002.
The above listed services will be completed on a reimbursable, Per Diem basis in the
amount not to exceed Ten Thousand Seven Hundred and Fifty Dollars ($10,750.00).
The services, as authorized by the City, shall be reimbursed based upon Direct Salary
Cost ($ per hour) times an overhead factor of 3.20 for the Engineer. All direct non -labor
expenses will be billed at the invoice cost plus ten percent (10 %) service charge. (Note:
Billing rates are revised each January to reflect salary increases.)
The term of this Amendment shall commence on the signing date and continue in effect
until such time as terminated in writing by either party.
The undersigned signatory on signatories for the Engineer hereby represents and warrant
that the signatory is an officer of the organization for which he or she has executed this
Contract and that he or she has full and complete authority to enter into this Contract on
behalf of the firm. The above - stated representations and warranties are made for the
purpose of entering into this Contract with the City.
IN WITNESS HEREOF, the City and the Engineer have executed these presents in
duplicate.
HDR Engineering, Inc.
By:
James K. (Ken) Hapfey, P.E.
Executive Vice President
City of
ound Rock, Texa
y e Maxwell
Mayor
Bv:
Date: 8 /3
SIGNATURE WARRANTY