R-02-08-08-11G5 - 8/8/2002 }
BA AICKLEN
6
ASSOCIATES,INC.
• r MENONEERS/SURVEYORS - Date:6/26/02
Page 1 of 4
Job No.0601-2-074-22
CONTRACT CHANGE ORDER NO.1
Contract For: City of Round Rock Historic Downtown Sidewalks Improvements
Owner: City of Round Rock
Contractor: Chasco Contracting
You are hereby requested to comply with the following changes from the contract plans and specifications:
DECREASE INCREASE
Description of Changes Contract Price Contract Price
C01-Dl Delete 2'concrete valley gutter,294 SF
@$5.60/SF. $1,646.40
C01-D2 Delete street pavers,including 1"sand cushion,
1428 SF @$3.50/SF. $4,998.00
C01-D3 Delete 7"concrete sub-base(street),including
sub-grade preparation,1,428 SF @$4.70/SF.
$6,711.60
C01-D4 Delete 6"x 10"concrete ribbon curb(street),
338 LF @$7.40/LF. $2,501.20
C01-D5 Delete 6"ductile iron,CL 200,43 LF @$42/LF. $1,806.00
C01-D6 Delete 6"schedule 40 PVC,117 LF @$37/LF. $4,329.00
C01-D7 Delete 6"schedule 40 PVC,clean out,2 EA,@
$180/EA. $ 360.00
C01-D8 Delete 2'Trench Drain,44 LF @ 149/1,17 $6,556.00
C01-D9 Delete core existing concrete flume,1 LS
@$600. $ 600.00
C01-D10 Delete concrete encasement,24 LF @$34/L.F $ 816.00
C01-D12 Delete 4"wastewater SDR 26(pressure rated),
159 LF @$32/LF. $5,088.00
COI-D13 Delete 4"schedule 40 PVC clean out,
2 EA @$150/EA. $ 300.00
BA AICKLEN
&ASSO SSOCIATES,INC.
I!�ENGINEERS/SURVEYORS Date:6/26/02
Page 2 of 4
Job No.0601-2-074-22
DECREASE INCREASE
Description of Changes Contract Price Contract Price
C01-D13 Delete bore and jack 18"RCP,including bore
pits,44 LF @ 340/LF. $14,960.00
COI-1314 Delete relocate two streets light poles including
all appurtenances,l LS @$2400. $ 2,400.00
COI-1315 Delete 3'x 3'concrete junction box with cast iron
inlet,3 EA @$3,400/EA. $10,200.00
C01-Al Add lightning protection repair for Library
(Cadweld/Repair),4 welds @$173/Weld,
complete in place. $ 692.00
COI-A2 Add replace copper wire for light pole in front
of Library,15 LF @$1.73/LF,complete in place. $ 25.95
COI-A3 Add demolition of concrete rip-rap,trickle channel,
and curb and gutter at the corner of Liberty&
Lampasas,1 LS @$810,complete in place. $ 810.00
C01-A4 Add Manhole ring and cover,1 EA @$870/EA,
complete in place. $ 870.00
COI-A5 Add relocate/rebuild light poles including all
appurtenances,5 @$1,200/EA,complete in place. $ 6,000.00
C01-A6 Add concrete textured overlay,350 SF including
mobilization 1 LS @$1,955,complete in place. $ 1,955.00
COI-A7 Add Non-ADA curb ramp at the east entrance of
Library,1 LS @$730,complete in place. $ 730.00
COI-A8 Add an additional 403 LF of 18"RCP,class III,
@$42/LF,complete in place. $16,926.00
C01-A9 Add 18"RCP WYE,3 EA @$274/EA,complete in
place. $ 822.00
COI-AIO Add 18"RCP BEND,4 EA @$198/EA,complete in
place. $ 792.00
INBAKER-AICKLEN
&ASSOCIATES.INC.
• ENGINEERS/SURVEYORS Date:6/26/02
Page 3 of 4
Job No.0601-2-074-22
DECREASE INCREASE
Description of Changes Contract Price Contract Price
C01-All Add standard curb and gutter @ the intersection
of Liberty and Lampasas,50 LF @$10/LF,
complete in place. $ 500.00
C01-Al2 Add tie to existing wastewater manhole,including
Preco grout,IEA @$1,500/EA,complete in place. $ 1,500.00
C01-A13 Add 4'diameter standard wastewater manhole,2 EA
@$2,000/EA,complete in place. $ 4,000.00
COI-A14 Add 6"SDR 26,412 LF @$42/LF,complete in place $17,304.00
C01-A15 Add 6"schedule 40 service,180 LF @$35/LF,
complete in place. $ 6,300.00
COI-A16 Add double clean out including tie to existing service
line,4 EA @$300/EA,complete in place. $ 1,200.00
C01-A17 Add demolition of 71 LF of curb and gutter at Mays
And Main Street,including 1 lane closure and removal
of dirt,concrete,and debris,1 LS @$1,450,complete
in place. $ 1,450.00
COI-AI8 Add supply additional pallet(s)of 6 cm pavers
(cast stone)(103 SF),including delivery to City
storage yard,2 EA$160/EA,complete in place. $ 320.00
COI-A19 Add supply additional pallet(s)of 6 cm pavers
(river red)including delivery to City storage yard,
4 EA @$150/EA,complete in place. $ 600.00
C01-A20 Add 3'x 2'concrete junction box with cast iron
curb inlet,9 EA @$3,400/EA,complete in place. $30,600.00
C01-A21 Add removal,wastewater manhole,including
removal of base&delivery to City storage yard,
stabilized backfill,salvage of ring with cover,
spoils disposal,etc.,complete in place. $ 750.00
C01-A22 Add traffic control-single lane closure on
Main Street,10 days @$200/day,complete
in place. $ 2,000.00
WBAKER-AICKLEN
6 ASSOCIATES,INC.
ENGINEERS/SURVEYORS Date:6/26/02
Page 4 of 4
Job No.0601-2-074-22
SUBTOTALS $63,272.20 $96,146.95
Net Changes in Contract Price: S 0.00 $32,874.75
Justification: City Requested
The amount of the Contract before this Change Order is
Five Hundred Twenty Two Thousand,One Hundred Seventy and 30/100 Dollars $522,170.30
The Amount of the Contract will DECREASE/INCREASE by the sum of
Thirty Two Thousand Eight Hundred Seventy Four and 75/100 Dollars $ 32,874.75
The CONTRACT TOTAL including this Change Order will be
Five Hundred Fifty Five Thousand,Forty Five and 051100 Dollars $555,045.05
The Contract Completion Date has been extended 14 days.
his documegbec pplement to the Contract and all provisions will apply hereto.
B-oz--
Chasco Conctor) Date
G 2,6-oL aker- (Engineer) Date
8-13-0z
C' and ck (Owner) Date
oA0601-074-2Zcnaogc omR NI 6-2"2.dm
'ROUND ROCK,TEXAS
PURPOSE.PASSION.PROSPERITY.
August 29,2002
Mr. Temple Aday
Chasco Contracting, Inc.
P.O.Box 1057
Round Rock,TX 78680
Dear Mr.Aday:
The Round Rock City Council approved Resolution No. R-02-08-08-11G5
at their regularly scheduled meeting on August 8,2002.This resolution
approves Change Order No. 1 for the Downtown Sidewalk Improvements
Project.
Enclosed is a copy of the resolution and the original Change Order No. 1
for your files.If you have any questions,please do not hesitate to contact
William Dobrowolski at 218-6601.
S' cerely,
MaY-
Nyle Maxwell
Christine R. Martinez
Mayor Pro-tern City Secretary
Tom Nielson
council Members
Alan McGraw Enclosure
Carrie Pitt
Scot Knight
Isabel Callahan
Gary Coe
City Manager
Dbert L.Bennett,Jr.
City Attorney
Stephan L Sheets
CITY OF ROUND ROCK221 East Main Street•Round Rock Texas 78664
Phone:512.218.5400•Fax.512.218 7097•Voice:1800.735.2988•1.800.735.2989 TDD•www.ci.round-rock.tx.us
ROUND ROCK,TEXAS
PURPOSE.PASSION.PROSPERITY.
August 29, 2002
Mr.Bill Waeltz, P.E.
Baker-Aicklen Sa Associates,Inc.
203 E.Main Street, Suite 201
Round Rock,TX 78664
Dear Mr. Waeltz:
The Round Rock City Council approved Resolution No. R-02-08-08-11GS
at their regularly scheduled meeting on August 8,2002.This resolution
approves Change Order No. 1 with Chasco Contracting, Inc. for the
Downtown Sidewalk Improvements Project.
Enclosed is a copy of the resolution and original Change Order No. 1 for
your files. If you have any questions,please do not hesitate to contact
William Dobrowolski at 218-6601.
Sincerely,
Mayor
Nyle Maxwell
Christine R. Martinez
Mayorero-rem City Secretary
Tom Nielson
Council Members
Alan McGraw Enclosure
Carrie Pitt
Scot Knight
Isabel Callahan
Gary Coe
City Manager
tbert I.Bennett,Jr.
City Attorney
Stephan I.Sheets
CITY OF ROUND ROCK 221 East Main Street•Round Rock Texas 78664
Phone:512,218-5400•Fax:512.218 7097•Voice:1.800.735.2988-1,800.775.z989 TDD•www.ct.round-rock.tx.us
RESOLUTION NO. R-02-08-08-11G5
WHEREAS, the City of Round Rock has previously entered into a
contract ("Contract") with Chasco Contracting, Inc. for the Downtown
Sidewalk Improvements Project, and
WHEREAS, the Council has determined that it is necessary to make
changes to the quantity of work to be performed or materials,
equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to change
said Contract in accordance with the attached Contract Change Order No.
1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Contract Change Order No. 1 to the Contract with
Chasco Contracting, Inc. for the Downtown Sidewalk Improvements
Project.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended.
::ODMA\wORLDOX\O:\WDGX\RBSGLUTI\R30BOBG5.WPD/sc
RESOLVED this 8th day of August, 2002.
;Oz-ez�
L, Mayor
City of Round Rock, Texas
AT M
CHRISTINE R. MARTINEZ, City Secreta
2
BAKER-AICKLEN
6 ASSOCIATES,INC.
ENGINEERS/SURVEYORS Date:6/26/02
Page 1 of 4
Job No.0601-2-074-22
CONTRACT CHANGE ORDER NO.1
Contract For: City of Round Rock Historic Downtown Sidewalks Improvements
Owner: City of Round Rock
Contractor: Chasco Contracting
You are hereby requested to comply with the following changes from the contract plans and specifications:
DECREASE INCREASE
Description of Changes Contract Price Contract Price
COI-D1 Delete 2'concrete valley gutter,294 SF
@$5.60/SF. $1,646.40
C01-132 Delete street pavers,including 1"sand cushion,
1428 SF @$3.50/SF. $4,998.00
COI-133 Delete 7"concrete sub-base(street),including
sub-grade preparation,1,428 SF @$4.70/SF.
$6,711.60
C01-D4 Delete 6"x 10"concrete ribbon curb(street),
338 LF @$7.40/LF. $2,501.20
C01-D5 Delete 6"ductile iron,CL 200,43 LF @$42/LF. $1,806.00
COI-D6 Delete 6"schedule 40 PVC,117 LF @$37/LF. $4,329.00
COl-D7 Delete 6"schedule 40 PVC,clean out,2 EA,@
$180/EA. $ 360.00
C01-138 Delete 2'Trench Drain,44 LF @ 149/LF $6,556.00
C01-139 Delete core existing concrete flume,1 LS
@$600. $ 600.00
COI-D10 Delete concrete encasement,24 LF @$34/L.F $ 816.00
COI-D12 Delete 4"wastewater SDR 26(pressure rated),
159 LF @$32/LF. $5,088.00
C01-1313 Delete 4"schedule 40 PVC clean out, EXHIBIT
2 EA @$150/EA. $ 300.00
nAn
BAKER-AICKLEN
S ASSOCIATMINC.
ENGINEERS/SURVEYORS Date:6/26/02
Page 2 of 4
Job No.0601-2-074-22
DECREASE INCREASE
Description of Changes Contract Price Contract Price
COI-D13 Delete bore and jack 18"RCP,including bore
pits,44 LF @ 340/1,17. $14,960.00
COI-D14 Delete relocate two streets light poles including
all appurtenances,l LS @$2400. $ 2,400.00
C01-D15 Delete 3'x 3'concrete junction box with cast iron
inlet,3 EA @$3,400/EA. $10,200.00
COI-Al Add lightning protection repair for Library
(Cadweld/Repair),4 welds @$173/Weld,
complete in place. $ 692.00
COI-A2 Add replace copper wire for light pole in front
of Library,15 LF @$1.73/LF,complete in place. $ 25.95
COI-A3 Add demolition of concrete rip-rap,trickle channel,
and curb and gutter at the comer of Liberty&
Lampasas,1 LS @$810,complete in place. $ 810.00
COI-A4 Add Manhole ring and cover,1 EA @$870/EA,
complete in place. $ 870.00
COI-A5 Add relocate/rebuild light poles including all
appurtenances,5 @$1,200/EA,complete in place. $ 6,000.00
COI-A6 Add concrete textured overlay,350 SF including
mobilization 1 LS @$1,955,complete in place. $ 1,955.00
COI-A7 Add Non-ADA curb ramp at the east entrance of
Library,1 LS @$730,complete in place. $ 730.00
COI-A8 Add an additional 403 LF of 18"RCP,class III,
@$42/LF,complete in place. $16,926.00
COI-A9 Add 18"RCP WYE,3 EA @$274/EA,complete in
place. $ 822.00
COI-A10 Add 18"RCP BEND,4 EA @$198/EA,complete in
place. $ 792.00
BAKER-AICKLEN
►/ &ASSOCIATES,INC.
•�ENGINEERS/SURVEYORS Date:6/26/02
Page 3 of
Job No.0601-2-074-22
DECREASE INCREASE
Description of Changes Contract Price Contract Price
C01-All Add standard curb and gutter @ the intersection
of Liberty and Lampasas,50 LF @$10/LF,
complete in place. $ 500.00
COI-Al2 Add tie to existing wastewater manhole,including
Preco grout,IEA @$1,500/EA,complete in place. $ 1,500.00
COI-A13 Add 4'diameter standard wastewater manhole,2 EA
@$2,000/EA,complete in place. $ 4,000.00
C01-A14 Add 6"SDR 26,412 LF @$42/LF,complete in place $17,304.00
COI-A15 Add 6"schedule 40 service,180 LF @$35/LF,
complete in place. $ 6,300.00
COI-A16 Add double clean out including tie to existing service
line,4 EA @$300/EA,complete in place. $ 1,200.00
COI-A17 Add demolition of 71 LF of curb and gutter at Mays
And Main Street,including I lane closure and removal
of dirt,concrete,and debris,1 LS @$1,450,complete
in place. $ 1,450.00
C0I-A18 Add supply additional pallet(s)of 6 cm pavers
(cast stone)(103 SF),including delivery to City
storage yard,2 EA$160/EA,complete in place. $ 320.00
COI-A19 Add supply additional pallet(s)of 6 cm pavers
(river red)including delivery to City storage yard,
4 EA @$150/EA,complete in place. $ 600.00
COI-A20 Add 3'x 2'concrete junction box with cast iron
curb inlet,9 EA @$3,400/EA,complete in place. $30,600.00
COI-A21 Add removal,wastewater manhole,including
removal of base&delivery to City storage yard,
stabilized backfill,salvage of ring with cover,
spoils disposal,etc.,complete in place. $ 750.00
COI-A22 Add traffic control-single lane closure on
Main Street,10 days @$200/day,complete
in place. $ 2,000.00
BAKER-AICKLEN
/ 6 ASSOCIATES,INC.
ENGINEERS/SURVEYORS Date:6/26/02
Page 4 of 4
Job No.0601-2-074-22
SUBTOTALS $63,272.20 $96,146.95
Net Changes in Contract Price: $ 0.00 $32,874.75
Justification: City Requested
The amount of the Contract before this Change Order is
Five Hundred Twenty Two Thousand,One Hundred Seventy and 30/100 Dollars $522,170.30
The Amount of the Contract will DECREASE4NCREASE by the sum of
Thirty Two Thousand Eight Hundred Seventy Four and 75/100 Dollars $ 32,874.75
The CONTRACT TOTAL including this Change Order will be
Five Hundred Fifty Five Thousand Forty Five and 05/100 Dollars $555,045.05
The Contract Completion Date has been extended 14 days.
s document will bee e a supplement to the Contract and all provisions will apply hereto.
8-oL
Chase Contr cting. (C tractor) Date
G-Z6-oL
aker-Aicklen& sso ates,Inc., (Engineer) Date
City of Round Rock (Owner) Date
o:w601-074-22NChangeOrder#]&2&02.dm
N
�s
lB
� o
v � M
OUND ROC A� � g
o
2 Y
� .1R
fir' i
w .r Downtown Sidewalks ��jj
DATE: August 2,2002
SUBJECT: City Council Meeting—August 8,2002
ITEM: 11.G.5. Consider a resolution authorizing the Mayor to execute Change
Order No.I with Chasco Contracting for the Downtown Sidewalk
Improvements Project.
Resource: Jim Nuse,Chief of Operations/Assistant City Manager
William J.Dobrowolski III,Senior Engineer
History: During the process of locating existing utilities, for the possible conflicts with
underground storm sewer, an active failing wastewater line was found. The
failing infrastructure was investigated by City Crews and determined there could
be total failure in the future. A plan for the replacement of this segment of the
collection system was prepared.
Funding:
Cost: $32,874.75
Source of funds: Self finance wastewater utility funds
Outside Resources: Baker—Aicklen&Associates,Inc.and Chasco
Impact: Avoid having to replace after failure.
Benefit: Avoid having to remove new construction
Public Comment:N/A