Loading...
Bushy Creek Wasterwater Interception - 12/1/1985e h ESPEY, HUSTON & ASSOCIATES, INC. Document No. 85705 EH &A Job No. 6565 • BRUSHY CREEK 54-INCH WASTEWATER INTERCEPTOR Prepared for: City of Round Rock Z14 E Main Street Round Rock, Texas 78664 Prepared by: Espey, Huston & Associates, Inc. 110 South Brown Street P.O. Box 1269 Round Rock, Texas 78680 December, 1985 ANY DISPUTE ARISING OUT OF THESE CONTRACT DOCUMENTS MAY BE SUBJECT TO ARBITRATION UNDER THE TEXAS GENERAL ARBITRATION ACT, ARTICLE 224, V.A.C.S., AS AMENDED. THE ARBITRATION PROCEDURES ARE SET FORTH IN THE GENERAL AND SUPPLEMENTARY CONDITIONS. TABLE OF CONTENTS PAGE BIDDING AND CONTRACT REQUIREMENTS Table of Contents TC Invitation to Bid IB -1 Instructions to Bidders IB -2 Bid Schedule B-1 Agreement A -1 Performance Bond PB -1 Payment Bond PB -3 General Conditions of Agreement GC -1 Supplementary Conditions (Modifications) 0800 -1 DIVISION 1 GENERAL REQUIREMENTS 01000 -1 Summary of Work 01010 -1 Work Sequence 01014 -1 Contractor Use of Premises 01015 -1 Owner Furnished Items 01018 -1 Special Project Procedures 01030 -1 Regulatory Requirements 01060 -1 Reference Standards 01090 -1 Measurement and Payment 01150 -1 Project Meetings 01200 -1 Shop Drawings, Product Data and Samples 01340 -1 Temporary Construction Facilities and Utilities 01510 -1 Work Space Fence r 01531 -1 Tree Protection 01532 -1 Protection of Work, Property and Persons 01540 -1 Workspace, Access Roads, 'Yards and Protected Areas' 01550 -1 TC Temporary Erosion Controls and Environmental Protection 01560 -1 Sandbag Berms 01561 -1 Silt Fences 01562 -1 Stabilized Construction Entrance 01564 -1 Traffic Regulation 01570 -1 Material and Equipment 01600 -1 DIVISION 2 - SITE WORK 02000 -1 Trenching, Embedment, Backfill and Compaction 02225 -1 Dewatering 02401 -1 Revegetation of Grasses 02480 -1 Trees 02491 -1 Sewer Manholes 02601 -1 Reinforced Concrete Wastewater Pipe 02612 -1 Texting of Pipeline 02650 -1 TC PAGE ESPEY, HUSTON & ASSOCIATES, INC. 110 South Brown Street P.O. Box 1269 Round Rock, Texas 78680 (512) 244 -3885 INVITATION TO BID Brushy Creek 54 -Inch Wastewater Interceptor Project No. 6565 December, 1985 You are invited to bid on the Brushy Creek Wastewater Interceptor. This project consists of approximately 10,332 LF of reinforced concrete wastewater pipe complete with all appurtenances. The Base Bid shall be for 54 inch diameter pipe and appurtenances. Alternates numbered 1 and 2; shall be for 60 inch and 66 inch diameter pipe and appurtenances, respectively. 4 -. Project to be substantially completed within 200 calendar days from date of The Notice to Proceed. • The City Manager, City of Roun Rock will receive bids for Brushy Creek 54 -Inch Wastewater Interceptor until 2:00 p.m., January 16, 1986, at the Municipal Building, 214 East Main Street, Round Rock, Texas. Bids received after this time will not be accepted. All interested parties are invited to attend. Bids will be opened publicly and read aloud immediately after specified closing time. Drawings and Specifications may be examined without charge at the Engineer's office at 110 South Brown Street, Round Rock, Texas 78680. Copies of the above documents may be obtained at the office of the Engineer in accordance with the Instructions to Bidders upon receipt of a one -time nonrefundable charge of $40.00. Bid security in the amount of five percent (5 %) must accompany each Bid in accordance with the Instructions to Bidders. The Owner reserves the right to waive irregularities and to reject bid. IB -1 INSTRUCTIONS TO BIDDERS Brushy Creek 54 -Inch Wastewater Interceptor Project No. 6565 1. Defined Terms. Terms used in these Instructions to Bidders which are defined in the Standard General Conditions of the Construction Contract have the meanings assigned to them in the General Conditions. The term "bidder" means one who submits a Bid directly to Owner, as distinct from a sub - bidder, who submits a bid to a Bidder. The term 'Successful Bidder' means the lowest, qualified, responsible and responsive Bidder to whom Owner (on the basis of Owner's evaluation as hereinafter provided) makes an award. The term "Bidding Documents" includes the Advertisement or Invitation to Bid, Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). 2. Copies of Bidding Documents 2.1 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the Advertisement of Invitation to Bid may be obtained from Engineer. Z.2 Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor Engineer assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. Z.3 Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use. 3. Qualifications of Bidders To demonstrate qualifications to perform the Work, each Bidder must be prepared to submit within five days of Owner's request written evidence, such as financial data, previous experience, present commitments and other such data as may be called for by the OWNER. Each Bid must contain evidence of Bidder's qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the contract. 4. Examination of Contract Documents and Site 4.1 It is the responsibility of each Bidder before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to become familiar I6-2 with local conditions that may affect cost, progress, performance or furnishing of the Work, (c) consider federal, state and local Laws and Regulations that may affect cost, progress, performance or furnishing of the Work, (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents. 4.1.1 Bidders shall not enter any portion of the site within private property unless accompanied by a representative of the OWNER. Bidders shall notify the OWNER at least two business days prior to the date that the Bidder wishes to visit the site within private property. The OWNER shall coordinate the site visit and shall accompany the Bidder at the site. 42 Reference is made to the Supplementary Conditions for identification of: 42.1 those reports of explorations and tests of subsurface conditions at the site which have been utilized by Engineer in preparation of the Contract Documents. Bidder may rely upon the accuracy of the technical data contained in such reports but not upon non - technical data, interpretations or opinions contained therien or for the completeness thereof for the purposes of bidding or construction. 4.2.2 those drawings of physical conditions in or relating to existing surface and subsurface conditions (except Underground Facilities) which are at or contiguous to the site which have been utilized by Engineer in preparation of the Contract Documents. Bidder may rely upon the accuracy of the technical data contained in such drawings but not upon the completeness thereof for the purposes of bidding or construction. Copies of such reports and drawings will be made available by Engineer to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the technical data contained therein upon which Bidder is entitled to rely as provided in Paragraphs 4.2.1 and 4.2.2 are incorporated therein by reference. Such technical data has been identified and established in the Supplem ent ary Conditions. 4.3 Information and data reflected in the Contract Documents with respect to Underground Facilities at or contiguous to the site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities or others, and Owner does not assume responsibility for the accuracy or completeness thereof unless it is expressly provided otherwise in the Supplementary Conditions. 4.4 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders on subsurface conditions, underground facilities and other physical conditions, and possible changes in the Contract Documents due to differing conditions appear in Paragraphs 4.2 and 4.3 of the General Conditions. IB -3 4.5 Before submitting a Bid, each Bidder will, at Bidder's own expense, make or obtain any additional examinations, investigations, explorations, tests and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface and Underground Facilities) at or contiguous to the site .or otherwise which may affect cost, progress, performance or furnishing of the Work and which Bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price and other terms and conditions of the Contract Documents. a 9 4.6 On request in advance, Owner will provide each Bider access to the site to conducet such explorations and, tests as each Bidder deems necessary for submission of a Bid. Bidder shall fill all holes, clean up and restore the rte to its former condition upon completion of such explorations. 4.7 The lands upon which the Work is to be performed, rights - of-way and easements for access thereto and other lands designated for use by Contractor in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by Contractor. Easements for permanent structures or permanent changes in existing structures are to be obtained and paid for by Owner unless otherwise provided in the Contract Documents. 4.8 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 5. Interpretations and Addenda. 5.1 All questions about the meaning or intent of the Contract Documents are to be directed to Engineer. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda mailed or delivered to all parties recorded by Engineer as having received the Bidding Documents. Questions received less than ten days prior to the date for opening of Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 52 Addenda may also be issued to modify the Bidding Documents as deemed advisable by Owner or Engineer. I5-4 6. Bid Security. 6.1 Each Bid must be accompanied by Bid security made payable to Owner in an amount of five percent of the Bidder's maximum Bid price and in the form of a certified check or a Bid Bond (on form attached, if a form is prescribed) issued by a surety meeting the requirements of Paragraph 5.1 of the General Conditions. 62 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Agreement and furnished the required contract security, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Agreement and furnish the required contract security within fifteen days after the Notice of Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of the seventh day, after the Effective Date of the Agreement or the ninety-first day after the Bid opening," whereupon Bid security furnished by such Bidders will be returned. Bid security with Bids which are not competitive will be returned within seven days after the Bid opening. 7. Contract Time. The numbers of days within which, or the dates by which, the Work is to be substantially completed and also completed and ready for final payment (the Contract Time) are set forth in the Bid Form and the Agreement. 8. Liquidated Damages. Provisions for liquidated damages, if any, are set forth in the Agreement. 9. Substitute or 'Or-Equal" Items. The Contract, if awarded, will be on the basis of materials and equipment described in the Drawings or specified in the Specifications without consideration of possible substitute or "or- equal" items. Whenever it is indicated in the Drawings or specified in the Specifications that a substitute or 'or- equal" item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by Engineer is set forth in Paragraphs 6.7.1, 6.72 and 6.7.3 of the General Conditions and may be supplemented in the General Requirements. I13-5 10. Subcontractors, Suppliers and Others. 103 The Bidder shall submit a tabulation of subcontractors with the Bid an the form provided, in addition to other data as follows: 102 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers and other persons and organizations (including those who are to furnish the principal items of material and equipment) to be submitted to Owner in advance of the specified date prior to the Effective Date of the Agrement, the apparent Successful Bidder, and any other Bidder so requested, shall within seven days after the Bid opening submit to owner a list of all such Subcontractors, Suppliers and other persons and organizations proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an : experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, person or organization if requested by Owner. If Owner or Engineer after due investigation has reasonable objection to any proposed Subcontractor, Supplier, other person or organization, either may, before the Notice of Award, is given request the apparent Successful Bidder to submit an acceptable substitute without an increase in Bid price. If apparent Successful Bidder declines to make any such substitution, Owner may award the contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers and other persons and organizations. The declining to make requested substitutions will not constitute grounds for sacrificing the Bid security of any Bidder. Any Subcontractor, Supplier, other person or organization listed and to whom Owner or Engineer does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.8.2 of the General Conditions. 103 In contracts where the Contract Price is on the basis of Cost-of -the- Work Plus a Fee, the apparent Successful Bidder, prior to the Notice of Award, shall identify in writing to Owner those portions of the Work that such Bidder proposes to subcontract and after the Notice of Award may only subcontract other portions of the Work with Owner's written consent. 10.4 No Contractor shall be required to employ any Subcontractor, Supplier, other person or organization against whom Contractor has reasonable objection. 11. Bid Form. 112 The Bid Form is included with the Bidding Documents. All blanks on the Bid Form must be completed in ink or by typewriter. IB-6 11.3 Bids by corporations must be executed in the corporate name by the president or vice -president (or other corporate officer accompanied by evidence of authority to sign) and the corporate seal must be affixed and attested by the secretary or an assitant secretary. The corporation `address and' state of incorporation must be shown below the signature: 11.4 Bids by partnerships must be ; executed in , the partnership name and signed by a partner, whose title must appear under the signature and the. official address of the partnership must be shown below the signature. 4 11.5 AU names must be typed or printed below the signature. 11.6 The Bid shall contain an acknowledgement of receipt of all Addenda (the numbers of which must be filled in on the Bid Form). 11.7 The address and telephone number for communications regarding the Bid must be shown. 1Z. Submission of Bids Bids shall be submitted at the time and place indicated in the Advertisement or Invitation to Bid and shall be enclosed in an opaque sealed envelope, marked with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted) and name and address of the Bidder and accompanied by the Bid security and other required documents. If the Bid is sent through the mail or other delivery system the sealed envelope shall be enclosed in a separate envelope with the notation 'BID ENCLOSED" on the face of it. 13. Modification and Withdrawal of Bids. 13.1 Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. 132 If, within twenty -four hours after Bids are opened, any Bidder files a duly signed, written notice with Owner and promptly thereafer demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid and the Bid security will be returned. Thereafter, that Bidder will be disqualified from further bidding on the Work to be provided under the Contract Documents. IB-7 14. Opening of Bids. Bids will be opened and (unless obviously non-responsive) read aloud publicly. An abstract of the amounts of the base Bids and major alternates (if any) will be made available to Bidders within seven days after the date of opening. 15. Bids to Remain Subject to Acceptance. The apparent successful bid and the next two lowest bids will remain subject to acceptance for ninety days after the day of the Bid opening. All other bids will be released and the Bid security returned within seven days. Owner may, in its sole discretion, release any Bid and return the Bid security prior to that date. 16. Award of Contract. 16.1 Owner reserves the right to reject any and all Bids, to waive any and all informalities not involving price, time or changes in the Work and to negotiate contract terms with the Successful Bidder, and the right to disregard all nonconforming, nonresponsive, unbalanced or conditional Bids. Also, Owner reserves the right to reject the Bid or any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by Owner. Discrepancies in the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. 162 In evaluating Bids, Owner will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award. 16.3 Owner may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Supplementary Conditions. Owner also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award. 16.4 Owner may conduct such investigations as Owner deems necessary to asist in the evaluation of any Bid and to establish the responsibility, qualifications and financial ability of Bidders, proposed Subcontractors, Suppliers and other IB-8 persons and organizations to perform and furnish the Work in accordance with the Contract Documents to Owner's aatisifaction within the prescribed time. 16.5 If the contract is to be awarded, it will be awarded to the lowest Bidder whose evaluation by Owner indicates to Owner that the award will be in the best interests of the Project. 16.6 if the contract is to be awarded, Owner will give the Successful Bidder a Notice of Award within ninety days after the day of the Bid opening. 17. Contract Security. Paragraph 5.1 of the General Conditions and the Supplementary conditions set forth Owner's requirements as to performance and payment Bonds. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by the required performance and payment Bonds. 18. Signing of Agreement When Owner gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement with all other written Contract Documents attached. Within 10 days thereafter Contractor shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner with the required Bonds. Within ten days thereafter Owner shall deliver one fully signed couterpart to contractor. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification. 19. Sales and Use Taxes. Owner is exempt from certain State and Local Sales Taxes on materials and equipment to be incorporated in the work. Said taxes shall not be included in the Contract price. Refer to Supplementary Conditions SC -6.15 for additional information. 20. Retainage. Provisions concerning retainage and Contractors' rights to deposit securities in lieu of retainage are set forth in the Agreement. IB-9 • THIS BID 1S SUBMITTED TO Mayor and City Council The City of Round Rock 214 E Main Street Round Rock, Texas 78680 PROJECT IDENTIFICATION: Brushy Meek 54 - 1nch Wastewater Interceptor CONTRACT IDENTffiCATION AND NUMBER: 656 � A 1. The undersigned BIDDER proposes and agrees, if this Bid h accepted, to enter into an Agreement with OWNER in the form included in the Contract Documents to complete all Work as specified or indicated in the Contract Documents for the Contract Price and within the Contract Time indicated in this Bid and in accordance with the Contract Documents. 2. BIDDER accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid Security. This Bid will remain open for thirty (30) days after the day of Bid opening. BIDDER will sign the Agreement and submit the Contract Security and other documents required by the Contract Documents within ten (10) days following its presentation. 3. In submitting this Bid, BIDDER represents, as more fully set forth in the Agreement, that: (a) BIDDER has examined copies of all the Contract Documents and of the following addenda: Date JAS 10, (receipt of all of which is hereby acknowledged and also copies of the Advertisement of Invitation to Bid and the Instructions to Bidders; (b) BIDDER has examined the site and locality where the Work is to be performed, the legal requirements (federal, state and local laws, ordinances, rules and regulations) and the conditions affecting cost, progress or performance of the Work and has made such indepen- dent investigations as BIDDER deems necessary; Numb 1 (c) Thia Bid is genuine and not made in the of or any undisclosed person, ' firm or corporation e and t is nor submitted in conformity with any agreement or rules of any group, association, organisation or corporation; BIDDER has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not solicited or induced any person, firm or corpora- tion to refrain from bidding; and BIDDER has Dot *sought by collusion to obtain for himself any advantage over any other BIDDER or over OWNER; and 4. BIDDER will complete the Work for the following price(s). (a) UNIT PRICES AS INDICATED IN BID SCHEDULE. R_7 5. BIDDER agrees that the pork will be substantially completed within Z00 calendar days from the date of the Notice to Proceed and completed within 230 calendar days after the date when the Contract Time commences to run. BIDDER accepts the provisions of the Agreement as to Liquidated Damages in the event of failure to complete the Work on time. 6. The following documents are attached to and made • condition of this Bid: SUBMITTED on (a) Required Bid Security to the form of (Cashier's or Certified Check or Bid Bond) . (b) A tabulation of Subcontractors and other persons and organizations required to be identified in this Bid. (c) Required Bidders Qualification Statement with supporting data. 7. Communications concerning this Bid shall be addressed to: The address of BIDDER indicated below. .t 8. The terms used in this Bid which are defined in the General Conditions of the Construction Contract included as part of the Contract Documents bave,the meanings assigned to them in the General Conditions. B -3 ,198(0.: '• 1- 1 . 1 . 1• 1_ 1 , 1 1 1 1 1 1 1 1 1 . 1 1 e If BIDDER is: An Individual By 6 tiPCY, HUSTON 0 ASSOCIATES, INC doing business as Business address: Phone No. A Partnership By Business address: Phone No. By dividual's Name) (Firm Name) (General Partner) A Corporation By �itf) tkiE C. (4t SC L /}'rFh .1 (Corporation Name) (S ate of Incorporation) a of ;- . •n Authorized to Sign 1 9 9 Iuk VIC NES /D tti7 s tle) B-4 OST ,fivv70 „.M. (SEAL) (SEAL) 1. 1 . 1 . 1 1 1 1 1 1 1 1 1 - 1 1 1 1 e h I$KY, HUSTON a ASSOCIATES, INC. (Corporate Sea Attest Business address: Phone No. A Joint Venture By By secretar '776r Cht f ' CA.gc e / a - `7 7- 788Y (Name) (Address) (Name) Address B -5 (Each joint venturer must sign. The manger of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above.) Mayor and City Council City of Round Rock 214 E Main Street Round Rock, Texas 78680 c/o Espey, Huston & Associates, Inc. 110 South Brown Street P.O. Box 1269 Round Rock, Texas 78680 Dear Sir: BID SCHEDULE December, 1985 The undersigned, in compliance with your invitation for bids for con- struction of Brush Creek 54 inch Wastewater Interceptor, having examined the plans, specifications and bidding documents, the site of the proposed work, and being familiar with all of the conditions surrounding construction of the proposed project; proposes to furnish all labor, materials and equipment and perform all work required for construction of the project in accordance with the plans, specifications and contract documents for the following prices: B -6 • WI NM NM MI MI OM • • MO • MI • NM MN • No. 1. 2. 3. Estimated Quantity BID SCHEDULE Written Price and Description 47 LF 60" RCP wastewater pipe, ASTM C76, Class III, 0' - 6' deep, complete in place, per linear foot for One Hundred Seventeen Dollars No Cents 218 LF 60" RCP wastewater pipe, ASTM C76, Class III, 6' - 8' deep, complete in place, per linear foot for One Hundred Eighteen Dollars No Cents 289 LF 60" RCP wastewater pipe, ASTM C76, ", ' Class III, 8' - 10' deep, complete in place, per linear toot for One Hundred Twenty Dollars No Cents Unit Total Price Price $ 117.00 $ 5,499.00 118.00 25,724.00 120.00 34,680.00 MI MI • OM • M - - -= MI NM • NM MO MB OM • No. 4. 6. Estimated Quantity BID SCHEDULE (Cont'd) Written Price and Description 905 LF 60" RCP wastewater pipe, ASTM C76, Class III, 10' - 12' deep, complete in place, per linear foot for One Hundred Twenty Two Dollars No Cents 5. 2,107 LF 60" RCP wastewater pipe, ASTM C76, Class III, 12' - 14' deep, complete in place, per linear foot for One Hundred Twenty Four Dollars No Cents 790 LF 60" RCP wastewater pipe, ASTM C76, Class W, 14' - 16' deep, complete in place, per linear foot for One Hundred Twenty Six Dollars No Cents Unit Total Price Price $ 122.00 $110,410.00 124.00 126.00 261,268.00 .�x a 99,540.00 " No. 7. 8. Estimated Quantity BID SCHEDULE (Cont'd) Written Price and Description 38 LF 60" RCP wastewater pipe, ASTM C76, Class III, 16' - 18' deep, complete in place, per linear foot for One Hundred Thirty Dollars No Cents 189 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 8' - 10' deep, complete in place, per linear foot for One Hundred Forty Five Dollars No Cents 9. 228 LF 60" RCP wastewater pipe, ASTM C76, 147.00 33,516.00 Class IV, 10' - 12' deep, complete in place, per linear foot for One Hundred Forty Seven Dollars No Cents Unit Total Price Price $ 130.00 $ 4,940.00 145.00 Z7,405.00 • N— M M• - -- M MI MN MI MN O' IMP No. 11. Estimated Quantity BID SCHEDULE (Cont'd) Written Price and Description 10. 20 LF 60" RCP wastewater pipe, ASTM C76, $ 149.00 $ 2,980.00 Class IV, 12' - 14' deep, complete in place, per linear foot for One Hundred Forty Nine Dollars No Cents 455 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 14' - 16' deep, complete in place, per linear foot for One Hundred Fifty One Dollars No Cents Unit Total Price Price 151.00 68,705.00 12. 1,246 LF 60" RCP wastewater pipe, ASTM C76, 155.00 193,130.00 Class IV, 16' - 18' deep, complete in place, per linear foot for One Hundred Fifty Five Dollars No Cents IMMI MI — MN • I MI — — I I r WM I• NM MI • No. Estimated Quantity BID SCHEDULE (Cont'd) Written Price and Description 13. 1,518 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 18' - 20' deep, complete in place, per linear foot for One Hundred Sixty Dollars No Cents 14. 1,063 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 20' - 22' deep, complete in palce, per linear foot for One Hundred Sixty Six Dollars No Cents 107 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 22' - 24' deep, complete in place, per linear foot for One Hundred Seventy Seven Dollars No Cents Unit Total Price Price $ 160.00 $242,880.00 166.00 • 176,458.00 177.00 18,939.00 .r — — — — — f— — • NM — —W — — — • — — No. Estimated Quantity BID SCHEDULE (Cont'd) Written Price and Description 16. 497 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 24' - 26' deep, complete in place, per linear foot for One Hundred Eighty Three Dollars No Cents 17. 75 LF 60" RCP wastewater pipe, ASTM C76, 201.00 15,075.00 Class IV, 26' - 28' deep, complete in place, per linear foot for Two Hundred One Dollars No Cents 18. 136 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 28' - 30' deep, complete in place, per linear foot for Two Hundred Thirty Seven Dollars No Cents Unit Total Price Price $ 183.00 $ 90,951 :00 237.00 32,232.00 • • i MI — — O' I — I MN MI • MN MI -- = No. Estimated Quantity BID SCHEDULE (Cont'd) Written Price and Description 19. 346 LF 60" RCP wastewater pipe, ASTM C76, Class IV, 30' - 32' deep, complete in place, per linear foot for Three Hundred Forty Six Dollars No Cents 20. 58 LF 60" RCP wastewater pipe, ASTM C76, 564.00 32, 712.00 Class IV, 32' - 34' deep, complete in place, per linear foot for Five Hundred Sixty Four Dollars No Cents 21. 29 EA Precast Type -T manhole, with service "eyes" 4,700.00 136, 300.00 bolted cover, complete in place, per each for Four Thousand Seven Hundred Dollars No Cents Unit Total Price Price $ 346.00 $119,716.00 • I I — • - -= N I E - -- MI OM NM I No. 22. * 250 VF Precast 48 Inch manhol riser, complete in $ 100.00 $ 25, 000.00 place, per vertical foot for Estimated Quantity One Hundred Dollars No Cents 23. 345 LF Concrete encasement for 60 Inch RCP, complete in place per linear foot for One Hundred Seventy Five Dollars No Cents ' 24. 400 LF Sandbag dike, complete in place per linear foot for Forty Dollars No Cents BID SCHEDULE (Cont'd) Written Price and Description Unit Total Price Price 175.00 60,375.00 40.00 16,000.00 NM N•• MI MN NM OM MI • NM = MN NM IN NM MI MN No. GRAND TOTAL Estimated Quantity Three Dollars Fifty Cents BID SCHEDULE (Concluded) Written Price and Description 25. 2,100 LF Silt fence, complete in place per linear $ 3.50 $ 7,350.00 foot for 26. 21 EA Tree protection collar, complete in place per each for Three Hundred Dollars No Cents 300.00 6,300.00 Thirty Thousand Dollars No Cents Unit Total Price Price 27. LS All other temporary and permanent erosion 30,000 30,000 control items, complete in place per lump sum for One Million Eight Hundred Seventy Eight Thousand Eight Five Dollars And No Cents $ 1, 878, 085.00 (In case of discrepancy between the Bid Price in words and figures above, the Price in words shall govern.) t, ANY DISPUTE ARISING OUT OF THESE CONTRACT DOCUMENTS MAY BE SUBJECT TO ARBITRATION UNDER THE TEXAS GENERAL ARBITRATION ACT, ARTICLE 224, V.A.C.S., AS AMENDED. THE ARBITRATION PROCEDURES ARE SET FORTH IN THE GENERAL AND SUPPLEMENTARY CONDrrIONS. THE STATE OF TEXAS 1 COUNTY OF WILLIAMSON I Article 1. WORK Article 2. ENGINEER AGREEMENT KNOW ALL MEN BY THESE PRESENTS: THIS AGREEMENT is dated as of the day of in the year 19 _by and between the City of Round Rock A - 1 City of Round Rock (hereinafter called OWNER) and Sabine Consolidated, Inc. (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: Brushy Creek Wastewater Improvements consisting of approximately 10,332 L.F. of wastewater pipe with all appurtenances complete and in place. The Project has been designed by: Espey, Huston & Associates, Inc., Round Rock, Texas. who is hereinafter called ENGINEER and who will assume all duties and respon- sibilities and will have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. Article 3. CONTRACT TIME 3.1 The Work will be substantially completed within 200 calendar days after the date when the Contract Time commences to run as provided in paragraph 2.3 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.13 of the General Conditions within 230 calendar days after the date when the Contract Time commences to run. 3.2 Liquidated Damages. OWNER AND CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not substantially complete within the time specified in paragraph 3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by OWNER if the Work is not substantially complete on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER Five Hundred dollars ($500.00) for east day that expires afer the ime specified in paragraph 3.1 for substantial completion until and Work is substantially complete. Article 4. CONTRACT PRICE 4.1 OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: See Attached Bid Schedule. Article 5. PAYMENT PROCEDURES .. x • Contractor shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1 Progress Payments. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Applications for Payment as recommended by ENGINEER, on or about the 10th day of each month during construction as provided below. All progress pay- ments will be on the basis of the progress of the Work measured by the A -2 5.1.1 Prior to Substantial Completion progress payments will be in an amount equal to: 90% of the Work completed unless otherwise stated in Division 1 General Requirements, Section 01150 Measurement and Payment, and 90% of materials not incorporated in the Work but delivered and suitably stored, less in each case the aggregate of payments previously made. 5.1.2 Upon Substantial Completion, OWNER shall pay an amount sufficient to increase total payments to CONTRACTOR to 90% of the Contract Price, less such amounts as ENGINEER shall determine in accordance with paragraph 14.7 of the General Conditions. 5.2 Final Payment. Upon final completion and acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.13. Article 6. INTEREST schedule of values provided for in paragraph 14.1 of the General Conditions. All moneys not paid when due as provided in Article 14 of the General Conditions shall bear interest at the rate of ten percent (10%) per year, provided, however, that in no event shall the interest due be at a rate higher than the maximum rate allowed by law at the place of the project. Article 7. CONTRACTOR'S REPRESENTATIONS In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following representations: 7.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents, Work, locality and with all local conditions and federal, state and local laws, ordinances, rules and regulations that in any manner may affect cost, progress or performance of the Work. 72 CONTRACTOR has studied carefully all reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress or performance of the Work which were relied upon by ENGINEER in the preparation of the Drawings and Specifica- tions and which have been identified in the Supplementary Conditions. 7.3 • ..CONTRACTOR has made or caused to be made examinations, investiga- tions and tests and studies of such reports and related data in addition to those referred to in paragraph 72 as be deems necessary for the : z _ .A-3 7.6 performance of the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract, Documents; and no additional examinations, investigations, tests, reports or similar data are or will be required by CONTRACTOR for such purposes. 7.4 CONTRACTOR has correlated the results of all such observations, examinations, investigations; tests, reports and data with the terms and conditions of the Contract Documents. 7.5 CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Docu- ments and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. Article 8. CONTRACT DOCUMENTS The Contract Documents which comprise the entire agreement between OWNER and CONTRACTOR are attached to this Agreement, made a part hereof and consists of the following: 8.1 This Agreement (pages A -1 to A -6, inclusive). 82 Exhibits to this Agreement: Bid Schedule. 8.3 Performance and other Bonds. 8.4 Notice of Award. 8.5 General Conditions (pages GC -i to GC -53, inclusive). 8.6 Supplementary Conditions. 8.7 Specifications either attached or referenced. 8.8 Drawings, consisting of a cover sheet and sheets with each sheet bearing the general title as stated in Article 1 of this Agreement. 8.9 Addenda numbers to , inclusive). 8.11 Documentation submitted by CONTRACTOR prior to Notice of Award. 8.12 Any Modification, including Change Orders, duly delivered after execu- tion of Agreement. A-4 Wit HUSTON 6 ASSOCIATES. INC. There are no Contract Documents other than those listed above in this Article 8. The Contract Documents may not be altered, amended or repealed by a Modification (as defined in Section 1 of the General Conditions). Article 9. MISCELLANEOUS 9.1 Terms used in this Agreement which are defined in Article 1 of the General Conditions shall have the meanings indicated in the General Conditions. 9.2 No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to any assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents. 9.3 OWNER and CONTRACTOR each binds himself, his partners, successors, assigns and legal representatives to the other party hereto, his partners, successors, assigns and legal representatives in respect to all coavenants, agreements and obligations contained to the Contract Documents. D WITNESS WHEREOF, the parties hereto have signed this Agreement in triplicate. One counterpart each has been delivered to OWNER, CONTRACTOR and ENGINEER. All portions of the Contract Documents have been signed or identified by OWNER and CONTRACTOR or by ENGINEER on their behalf. A -5 This Agreement will be effective on 73/ j,,, 19 1�p , �,� City of Rcund Rock OWNER BY 7 /12/ (CORPORATE SEAL) Address for giving notices cif e Malin &wind / ,72'2 I (lf OWNER is a public body attach evidence of authority to sign and resolution or other document authorizing execution of Agreement.) License No. A -6 Sabine Consolidated, Inc. CONTRACTOR EPA/ �zza (CORPORATE SEAL) Address giving notice 0 � ' � * 77Do .�, i7 7fZ&R Agent for service of process 1 1 1 1 1 1 1 1 1 1 1 1 • e ii ESPEY, HUSTON a ASSOCIATES, INC. STATE OF TEXAS COUNTY OF 6 r er-- .— PERFORMANCE BOND KNOW ALL MEN BY THESE PRESENTS: That of the ity of County of , and State of _ as principal, and � i' f - _ / /" it �. _ , authorized under the law /of the State of e t •f ae,f a s sur ty f principals, are held and firmly boun. unt • _ . L �.; Owner) the p . sum of P `/ V ; .�J /Gppgl�)J%rl r7J� �1/` ' ,.�.�! t i■ Dollars (S o.'.. 0 o ■ ) the payment whey f, 'e said Principal and Surety bind 'emse ves, and their heirs, administrators, executors, successors and assigns, jointly and severally, by these presents: WHEREAS, the Principal has entered into a certain written contract with the Owner, dated the day of , 19 , to which contract is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein. NOW THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall faithfully perform said Contract and shall in all respects duly and faithfully observe and perform all and singular the covenants, conditions and agreements in and by said contract agreed and covenanted by the principal to be observed and performed, and according to the true intent and meaning of said Contract and the Plans and Specifications hereto annexed, then this obligation shall be void; otherwise to remain in full force and effect; 8 • 'PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of (Article 5160 for Public Work) (Article 5472d for Private Work)* of the Revised Civil Statutes of Texas as amended and all liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein.' *Not applicable for federal work. See 'The Miller Act,' 40 U.S.C.S270. Copyright 1954, 1962, 1971 By, and Reprinted with, Permission of TS -ASCE. PB -1 COMPLAINT NOTICE SHOULD ANY QUESTION OR DISPUTE ARISE ABOUT YOUR PREMIUMS OR A CLAIM YOU HAVE PREVIOUSLY FILED, FIRST CONTACT THE AGENT WHO ISSUED THIS POLICY OR WRITE THE COMPANY. IF THE PROBLEM IS NOT RE. SOLVED, YOU MAY ALSO WRITE THE STATE BOARD OF INSURANCE, DEPT. C, 1110 SAN JACINTO, AUSTIN, TEXAS 78786. N,, e [SPEY. HUSTON a ASSOCIAT[S, INC. Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract, or to the work performed thereunder, or the plans, specifications, or drawings accompanying the same, shall in anyway affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract, or to the work to be performed thereunder. IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this instrument this day of , 19 . The name and address of the Resident Agent of Surety is: x } Contractors Bond & Insurance Agency, Inc. 3111 'O est f�iabama, Suite 200 Houston, Texas 77098 523 -3610 Surety n �I .4. PB -2 I By Attorney -in-Fad, Title $131 West Alabama, Suite 200 Houston, Texas 77098 Address e ll tint HUSTON & ASSOCIATES, INC. STATE OF TEX 5 COUNTY OF( PAYMENT BOND KNOW ALL MEN BY THESE PRESENTS: That i- / (. of the ity of % Alm County of , •d State of _ as principal, and f/T_� � % ,, _ authorized under the laws /1 the State of Te f : . principals, are held and firmly bound unt / , f __._ �� or Owner), n in es the a al sum i /� ♦ �' "` •Gat c.. ipo Dollars ($ ! , •; ( CO ) for the p ment where c, e said Principal and Sure bin themselves, and their heirs, administrators, executors, successors and assigns, jointly and severally, by these presents: WHEREAS, the Principal has entered into a certain written contract with the Owner, dated the day of , 19 , to which contract is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein. NOW THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall pay all claimants supplying labor and material to him or a subcontractor in the prosecution of the work provided for in said contract, then this obligation shall be void; otherwise to remain in full force and effect; PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas as amended and all liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein. ' Copyright 1954, 1962, 1971 By, and Reprinted with, Permission of TS -ASCE. PB -3 ESPY, HUSTON l ASSOCIATES. INC. Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract, or to the work performed thereunder, or the plans, specifications or drawings accompanying the same, shall in anywise affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract, or to the work to be performed thereunder. IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this , 19 • il‘V 19.46P() Surety e By Attorney - in. Fact instrument this day of Principal ,i V - 7 1 AYAIraL6 PAizudeird Title '500 Addr , , 55 6Az y in, The name and address of the Resident Agent of Surety b: Contractors Pend & Insurance,Agency, Inc.' t l '_c a- S i.tc 200 Houston, Texas 77098 523 -3610 PB -4 Title 3131 West Alabama, Suite 200 Houston, Texas 77098 Address CO T TYPE OF INSURANCE P POLICY NUMBER P POLICY EFECTNE P PCUCY EXPIRATION L LIABILITY LIMITS IN THOUSANDS y =AH GCCURRENCE A AGGEGATE ^ G GENERAL L LIABILITY B 540 6544449 6 6 -10 -85 6 6 -10 -86 I BODILY $ $ $ PROPERTY $ $ $ -r BI a PD � . . .�3 A •::•Yqui�� ; b f1 �.� .�i' •� Y a ; k � _. y � ��t I � � ✓l CER TIFICATE, OF`' INSURA -, Rt �a �L...., �.,i pA n� ..'i..e rra,•a;.!.,�. ..,.). .. d "?. t,., .i ^.$... v cONEIMGES f a PRODUCER Essary, Hart & MacWilliam, Inc. 3131 W. Alabama, Suite 200 Houston, Texas 77098 INSURED Sabine Consolidated, Inc. P. 0. Box 3676 Port Arthur, Texas 77640 DESCRIPTION OF OPERATIONS /LOCATIONSNEHICLES /SPECIAL ITEMS Utility Construction Re: Brushy Creek 54 -Inch Wastewater Interceptor City of Round Rock, Texas THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND 0R ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. COMPANIES AFFORDING COVERAGE COMPANY LETTER A United States Fire Insurance Company COMPANY S Houston General Insurance Company COMPANY LETTER COMPANY I] LETTER THIS IS TO CERTIFY THAT POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUEDTO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONOTTION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS, AND CONDI- TIONS OF SUCH POLICIES. SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EX. PIRATION DATE THEREOF, THE ISSUING COMPANY ',TILL ENDEAVOR TO MAIL -311 _DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY OF A KINO UPON THE CO PANT, ITS AGENT /•R REPRESENTATIVES. Espey, Huston & Associates, Inc. P. 0. Box 1269 Round Rock, Texas 78680 AORKSAAAL �4 [SKY, HUSTON. ASSOCIATES, INC. STANDARD GENERAL CONDEMNS OF TOE CONSTRDCPION CONTRACT HARTFORD CASUALTY INSURANCE COMPANY Executive Oma: Hertford, Connecticut POWER OF ATTORNEY - Know ell men by these Presents, That the HARTFORD CASUALTY INSURANCE COMPANY, a corporation duly orgaMzed under to laws of the State of New Jersey, and having its Executive Office in the City of Hartford. County of Hanford, State of Connecticut, does hereby make, constitute and appoint MARVIN M. DURRENEERGEH, DON R. HART, JAMES D. MacWILLIAM, JR., ROY S. TUSKINGTON, NANCY COILS and LELAND L. RAUCH of HOUSTON, TEXAS Its true and lawful Attamey(s )-n -Fact, with full power and authority to each of Said Attome s }in -Fact, n their separate aty capad morethan oneisnemed above, to sign, execute and acknowledge any and all bondsand undertakings andother writings obligatory M the nature thereof on behalf of the corn on Its buennees.of guaranteeing the *dotty of persons holding places of pudic or pnvaee trust: guaranteeing the pertormance of contracts other than neura policies; guaranteeing guaranteeing an bos arid u � akl cdn eta g�ata or permitted in all actions 01 proceedings or by law allowed, and to bind the HARTFORD CASUALTY INSURANCE COMPANY thereby as fully and to the same extend as t such bonds and • nORD undertakings U and other obligatory in the nature thereof signed by an Executive Officer of the NC nnggsa E COMPANY and sealed and attested by one other of such Officers, and hereby ratifies and confirms ell that its said Attomey(s}in -Fact may Agin pursuance hereof. This power of attorney is granted under and by authority of the following Resolutions adopted by the Board of Directors of the HARTFORD) CASUALTY INSURANCE COMPANY at a meeting duly called and held on the 15th day of September, 1976. 14E80080 act.tMPnddentoraanyVIc PrsakHM, 009. any or Afaatant Secretary, Well havaposer aadaut lwltyto went. for Resident �8au edhrw and A and waaf el any lime any Such Resident Ree t W ares a M, Raul se Samelon or Aawnst1HFea, and revoke the power and authority given to line Adomswe•FwteneenavePOrwrrd 81e r0.eublectb8MrraandsnOt n of the P owna8ued tonne. toexecu end de1Ner 00.b h a nd an oM fo eecyyanysuuch An pen yalere te to anyeM ba ling up ,utderaklnpg arala a nIf seined paatmyinae and ted n ▪ aiad I ate executed b other W Such Onleerss,d. AaMneydn4F8100000 bee bXWlnp rpariar COrrpenyallalpned aye fit ieeulNSOakereM RESOLVED, tint. Rawl N. H Seer, MWMnt VkWraltlsnt and Thane F Deeney..Aabem Vice-Pre de t, she ate teva, as long as he rade audl office, the eame pavan as any cube - Prudent naval to the preceding Meoeadn RESOLVE D.. thlt. whereas to President or any VlcsPrafdem alien M ow�lr , en tide any or Assistant Secretary, I p and authority to m a mre p RelltleMV ai Aaalent of a Annaya and eandu ,a OtlerwntllgeoaIlgabrynlMnalure thereof, Now, therefore, the a gMhra watch Guars and me9WaMe Company may beamaedmry such eowra attorney orm cert9eremang t ereto br td0b, end any such power aaapmey r certificate bearing such Wenn signatures a reanNe manna a awned binding upon the Comma end any such poem a ezeoed and ccaddied by tacaee n apnea. end Mama naiad be valid and binding upon t a o Company fie nmae wan seaport seaport ap b e nd r a ybo undertaking to which k e attached. RESOLVED, Ina, Robert N. H. Saner, MaWnt Vice-Padden end Tames F. Dana Masbm IRa0PresMSnn may sok as long as he holds such once. anx hie signature by fac pursuant too and with the same effect as that grated to Vlca•Pradants under the encoding Rasoludal. In Witness Whereof, the HARTFORD CASUALTY INSURANCE COMPANY has caused these presents to be signed by Its Assistant Ylce- President. and Its corporate seal to be hereto affixed, duly attested by Its Secretary, this 1st day of Apnl, 1983. Attest Gay Sdra, Secreey STATE OF CONNECTICUT, } COUNTY OF HARTFORD, On this 1st day of April, A.D. 1983, before me personally came Robert N. H. Seiler, to me known, who being by me duly sworn, dbd depose ands that he reeldes in the County of Hartford, State of Connecticut; that he Is the Ailment Vice - Presidsmof thsHARTFORD CASUALTY INSURANCE COMPANY, the corporation described In and which executed the above Insttruwesq that seal fsocarorat00Wsat the seal affneed to the saki instrument Is such corporate corporation and that he signed his MIMS thereto by like order. Fern 845074 pt,) Ponta m LISA as HARTFORD CASUALTY INSURANCE COMPANY Robert N. H. Sena Assistant Vannreddal ..es+eev+sv0i STATE OF CONNECTICUT, St tsea )} aorta Menem Nary Pack COUNTY OF HARTFORD. ) ss CERTIFICATE My CrnmeaortEaplres Minch I. the undersigned Assistant Secretary of the HARTFORD CASUALTY INSURANCE COMPANY, a New Jersey Corporation, DO HEREBY CERTIFY that the foregoing and attached POWER OF ATTORNEY remains n full force and has not been revoked: and furthermore, that the Resolutions of the Board of Directors, set fate in the Power of Attorney, are now In force Signed and sealed at the City of Hartford Dated the day of 19 611535 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 [SPEY, HUSTON L *SSOCMTES. WC. STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT e h ESPEY. HUSTDH 1 ASSOCIATES. INC. TABLE OF CONTENTS OF GENERAL CONDITIONS Article Number Title Page 1 DEFINITIONS GC-1 2 PRELIMINARY MATTERS GC-4 3 CONTRACT DOCUMENTS: GC-6 INTENT AND REUSE 4 AVAILABILITY OF LANDS; PHYSICAL CONDITIONS; GC-8 REFERENCE POINTS 5 ' BONDS AND INSURANCE GC-1I 6 CONTRACTOR'S RESPONSIBII TI1ES GC-16 7 OTHER WORK GC-25 8 OWNER'S RESPONSIBILITIES GC-26 9 ENGINEER'S STATUS DURING CONSTRUCTION GC-27 10 CHANGES IN THE WORK GC-30 11 CHANGE OF CONTRACT PRICE GC-32 12 CHANGE OF CONTRACT TIME GC-38 13 WARRANTY AND GUARANTEE; TESTS AND GC-38 INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 14 PAYMENTS TO CONTRACTOR AND COMPLETION GC-42 15 - SUSPENSION OF WORK AND TERMINATION GC-4 16 ARBITRATION GC-5I e F f 17 MISCELLANEOUS ` GC-52 -- M GC -i 1 1 1 1 1 1 1 1 1 1 .1 1 1 1 1 1 1 1 [SPEY. HUSTON a ASSOCUIT[S, INC. Before Starting Construction Bid - definition of Bonds and Insurance—b general Bonds— definition of Bonds, Delivery of Bonds, Performance and Other INDEX TO GENERAL CONDITIONS Acceptance of Insurance Access to the Work Addenda - definition of (see definition of Spec ficatiois} Agreement — definition of All Risk Insurance Application for Payment — definition of Application for Payment, Final Application for Progress Payment Application for Progress Payment - review of Arbitration Availability of Lands Award Notice of— defined Cash Allowances 11.10 Change Order— Definition of 1 Changes in the Work 10 Claims, Waiver ofronFinal Payment 14.16 Clarifications and Interpretations 9.3 Cleaning Completion on 6.17 Completion, Substantial 14.8, 14.9 Conference —Pre - Construction 2.8 Construction Machinery, Equipment, etc. 6.4 Continuing Work 629 Contract Documents—definition of 1 Contract Documents— intent and reuse 3 Contract Documents - -reuse of t 3.5 Contract Price, Change of ' . , ' 11 Contract Price—definition 1 Contract Time, Change of - - 12 Contract Time — Commencement of • r 2.3 Contract Time — definition of ' 1 GC -ii Article or Paragraph Number 5.13 132 1 1 5.6 l 14.12 14.2 14.4 thru 14.7 16 4.1 2.5 thru 2.7 1 5 1 2.1, 5.1 5.1, 52 e EMIT, HUSTON i ASSOCIATES. INC. Contractor — definition of I Contractor May Stop Work or Terminate 15.5 Contractor's Continuing Obligation 14.15 Contractor's Duty to Report Discrepancy in Documents 2.5 3.2 Contractor's Fee —Cats Plus 11.6 Contractor's Liability Insurance 5.3 Contractor's Responsibilities --in general 6 Contractor's Warranty of Title 14.3 Contractual Liability Insurance 5.4 Copies of Documents 2.2 Correction or Removal of Defective Work 13.11 Correction Period, One Year 13.12 Correction, Removal or Acceptance of Defective 13.11 thru 13.14 Work —in general Cost of Work 11 .4, 11.5 Cats, Supplemental 11.4.5 Day — definition of 1 Defective Work, Acceptance of 13.13 Defective Work, Correction or Removal of 13.11 Defective— definition of 1 Defective Work —in general 13 Defective Work, Rejecting 9.4 Definitions 1 Delivery of Bonds 2.1 Disagreements, Decisions by Engineer • 9.9, 9.10 Documents, Copies of 2.2 Documents, Record 6.19 Documents, Reuse 3.5 Drawings - definition of 1 Effective date of Agreement— definition of Emergencies Engineer - definition of Engineer's— Notice Work is Acceptable Engineer's Responsibilities, Limitations on Engineer's Status During Construction - ix general Engineer's— Recommendation of Payment Equipment, Labor, Materials and Equivalent Materials and Equipment _ INDEX (Continued) GC -iii Article or Paragrapb Number 1 6.22 l 14.3 ' 9.11 tbru 9.14 9 14.4, 14.13 6.3 thru 6.6 6.7 1 e WIT, HUSTON a ASSOCIATES, INC. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 INDEX (Continued) Labor, Materials and Equipment Laws and Regulations Liability Insurance Contractor's Liability Insurance - Owner's Limitations on Engineer's Responsibilities Materials and Equipment- furnished by Contractor Materials or Equipment-Equivalent Miscellaneous Provisions Modification - definition of GC - iv Article or Paragraph Number Fee, Contractor's -Costs Plus 11.6 Field Order- definition of 1 Field Order - issued by Engineer 10.2 Final Application for Payment 14.12 Final Inspection 14,11 Final Payment, Recommendation of 14.13, 14.14 Final Payment and Acceptance 14.13 General Requirements- definition of 3 General Provisions 17.3, 17.4 Giving Notice 17.1 Guarantee of Work -by Contractor 13.1 Indemnification 6.30 tbru 6.32 Inspection, Final 14.11 Inspection, Tests and 13.3 tbru 13.7 Insurance, Bonds and general 5 Insurance- Certificates of 2.7 a 5 Insurance, Contractor's Liability 5.3 Insurance, Contractual Liability 5.4 Insurance, Owner's Liability 5.5 Insurance, Property 5.6 tbru 5.12 Intent of Contract Documents 3.1 tbru 3.4, 9.12 Interpretations and Clarifications 9.3 Investigations of Physical Conditions 4.2 6.3 ticu 6.6 6.14 5.3 5.5 9.11 6 .3 6.7 17 1 Notice, Giving of - ` . 17.1 Notice of Award - definition of 1 Notice of Acceptability of Project 14.13 4 r • e Es►[r. HUSTON & ASSOCIATES, tNC. INDEX (Continued) Notice to Proceed - definition of ' Notice to Proceed - giving of "Pi-Equal' items Other Contractors ' Overtime Work - prohibition of Owner--definition of Owner May Correct Defective Work ' Owner May Stop Work Owner May Suspend Work, Terminate Owner's Duty to Execute Change Orders Owner's Liability Insurance ' Owner's Representative - Engineer to nerve as Owner's Responsibilities -fn general Owner's Separate Representative at Site 1 Partial Utilization Partial Utilization - Property Insurance ' Patent Fees and Royalties Payments to Contractor - in general Payments, Recommendation of Pre- construction Conference 1 Performance, and other Bonds Permits Physical Conditions-Investigations and Reports ' Physical Conditions, Unforeseen Preconstruction Conference Preliminary Matters Premises, Use of ' Price- Change of Contract Price- Contract- definition of Progress Payment, Applications for ' Progress Schedule Project- definition of Project Representative, Resident - definition of Project Representation -Provision for 1 Project, Starting Property Insurance Propertylnsurance Receipt and Application of Proceeds'' I Propertylnsurance -Partial Utilization ° Protection, Safety and 1 1 GC-v Article or Paragraph Number l 2.3 6.7 7 6.3 1 13.14 13.10 15.1 thru 15.4 11.8 5.5 9.1 8 9.8 14.10 5.14 6.12 14 14.4 thru 14.7.5 2.8 5.1 thru 5.2 6.13 4.2 4.3 2.8 2 6.16, 6.17, 6.18 11 1 14.2 2.6, 14.1 1 1 9.8 2.4 5.6 thru 5.12 5.11, 5.12 5.14 6.20 thru 6.21 % LSPtY. NUSTON a ASSOCIAT[s, tNC. t INDEX (Continued) Recommendation of Payment 14.4, 14.13 Record Documents 6.19 Reference Points 4,4 Regulations, Laws and 6.14 Rejecting Defective Work 9.4 Remedies Not Exclusive 17.5 Removal or Correction of Defective Work 13.11 Resident Project Representative — definition of 1 Resident Project Representative—provision for 9.8 Responsibilities, Contractor's 6 Responsibilities, Owner's 8 Reuse of Documents • 3.5 Royalties, Patent Fees and 6.13 Safety and Protection Samples Schedule of Shop Drawing Submissions Schedule of Values Shop Drawings and Samples Shop Drawings— definition of Site, Visits to by Engineer Specifications - definition of Starting Construction, Before Starting the Project Stopping Work by Contractor Stopping Work —by Owner Subcontractor - definition of Subcontractors -in general Substantial Completion— certification of Substantial Completion— definition of Subsurface Conditions Supplemental Costs Surety — consent to payment Surety- notice of changes Surety — qualification of Suspending Work, by Owner Suspension of Work and Termination —in general Superintendent—Contractor's Supervision and Superintendence GC-vi Article or Paragraph Number 620 thru 6.21 623 2.6, 14.1 2.6, 14.1 623 tbru 6.29 1 9.2 1 2.5 tbsu 2.9 2.4 15.5 13.10 1 6.8 thru 6.11 14.8 1 4.2, 4.3 11.4.5 14.12, 14.14 10.5 5.1, 5.2 15.1 15 6.2 6.1, 6.2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 , 1 1 e EMT, HUSTON a ASSOCIATES, INC. Article or Paragraph Number Taxes Payment by Contractor 6.15 Termination —by Contractor 15.5 Termination by Owner 152 thru 15.4 Termination, Suspension of Work and --in general 15 Tests and Inspections 13.3 thru 13.7 Time, Change of Contract 12 Time, Computation of 17.2 Time, Contract — definition of 1 Uncovering Work Unit Prices Unit Prices — Adjustment of Use of Premises Values, Schedule of Visits to Site —by Engineer INDEX (Concluded) Waiver of Claims —on Final Payment 14.16 Waiver of Rights by Insured Parties 5.10 Warranty and Guarantee —by Contractor 13.1 Warranty of Title, Contractor's 14.3 Work, Access to 13.2 Work by Others—in general 7 Work, Cost of 11.4, 11.5 Work Continuing During Disputes 6.29 Work — definition of 1 Work, Neglected by Contractor 13.14 Work, Stopping by Contractor 15.5 Work, Stopping by Owner 15.1 thru 15.4 GC-vii 13.8, 13.9 11.3.1 11.9 6.16, 6.17, 6.18 14.1 9.2 e h WET. HUSTON 4 ASSOCIATES, INC. 1 1 . 1 1 1 1 GENERAL CONDIIiONS ARTICLE 1--DEFINITIONS Wherever used in these General Conditions or in the other Contract Documents, the following terms have the meanings indicated which are applicable to both tbe singular and plural thereof: Addenda — Written or graphic instruments issued prior to the opening of Bids which clarify, correct or change tbe bidding documents or the Contract Documents. Agreement The written agreement between OWNER and CONTRACTOR covering the Work to be performed; other Contract Documents are attached to the Agreement and made a part thereof as provided therein. Application for Payment The form accepted by ENGINEER which is to be used by CONTRACTOR in requesting progress or final payments and which is to include such supporting documentation as is required by the Contract Documents. Bid —The offer or proposal of the bidder submitted on the prescribed form setting forth the prices for the Work to be performed. Bonds --Bid, performance and payment bonds and other instruments of security. Change Order —A document recommended by ENGINEER, whieb is Signed by CONTRACTOR and OWNER and authorises an addition, deletion or revision in the Work, or an adjustment in tbe Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. Contract Docmnents —The Agreement, Addenda (which pertain to the Contract Documents), CONTRACTOR'S Bid fincluding documentation accompanying the Bid and any post -Bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Agreement, the Bonds, these General Conditions, the Supplementary Conditions, the Specifications and the Drawings as the same are more specifically identified in the Agreement, together with all amendments, modifications and supplements issued pursuant to paragraphs 3.4 and 3.5 on or after the Effective Date of the Agreement. Contract Piece --The moneys payable by OWNER to CONTRACTOR =der the Contract Documents as stated in the Agreement (subject to the provisions of paragraph 11.9.1 in the case of Unit Price Work). Contract Time —The number of days (computed as provided in paragraph 17.2) or the date stated in the Agreement for the completion of the Work. GC -1 e EMT. HUSTON & ASSOCIATES, INC. CONTRACTORTbe person, firm or corporation with whom OWNER has entered into the Agreement. defective - -An adjective which when modifying the word Work refers to Work that h unsatisfactory, faulty or deficient, or does not conform to the Contract Documents, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents, or has been damaged prior to ENGINEER's recommendation of final payment (unless responsibility for the pro- tection thereof has been assumed by OWNER at Substantial Completion in accord- ance with paragraph 14.6 or 14.10). Drawings--The drawings which show the eheracter and scope of the Work to be performed and which have been prepared or approved by ENGINEER and are referred to in the Contract Documents. Effective Date of the Agreement The date indicated in the Agreement on which it becomes effective, but if no such date is indicated it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver. ENGINEER The person, firm or corporation named as such in the Agreement. Field Order --A written order issued by ENGINEER which orders minor changes in the Work in accordance with paragraph 9.5 but which does not involve a change in the Contract Price or the Contract Time. GeneralRequirementa— Sections of Division 1 of the Specifications. Laws and Regulations; Laws or Regulation— laws, rules, regulations, ordinances, codes and/or orders. Notice of Award- -The written notice by OWNER to the apparent successful bidder stating that upon compliance by the apparent successful bidder with the conditions precedent enumerated therein, within the time specified, OWNER will sign and deliver the Agreement. Notice to Proceed —A written notice given by OWNER to CONTRACTOR (with a copy to ENGINEER) firing the date on which the Contract Time will commence to run and on which CONTRACTOR shall start to perform CONTRACTOR': obligations under the Contract Docum ents. OWNER The public body or authority, corporation, association, firm or person with whom CONTRACTOR has entered into the Agreement and for whom the Work is to be provided. GC -2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h ES►FT. HUSTON 1 ASSOCIATES, INC. Partial Utilisation —Placing • portion of the Work in service for the purpose for which it is intended (or • related purpose) before reaching Substantial Completion for all the Work. Project The total construction of which the Work to be provided tide the Contract Documents may be the whole, ce a part as indicated elsewhere is the Contract Documents. Resident Project Representative --The authorised representative of ENGINEER who is assigned to the site or any pat thereof. Shop Drawings —All drawings, diagrams, illustrations, schedules and other data which are specifically prepared by or for CONTRACTOR to illustrate some portion of the Work and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams and other information prepared by • Supplier and submitted by CONTRACTOR to illustrate material or equipment for some portion of the Work. Specifications Those portions of the Contract Documents consisting of written technical descriptions of materials, equipment, construction systems, standards and workmanship as applied to the Work and certain administrative details applicable thereto. Subcontractor —An individual, firm ce corporation having a direct contract with CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the site. Substantial Completion- -The Work (or a specified part thereof) hos progressed to the point where, in the opinion of ENGINEER, as evidenced by ENGINEER'S definitive certificate of Substantial Completion, it is sufficiently complete, in accordance with the Contract Documents, so that the Work (or specified part) can be utilised for the purposes for which it is intended; or if there be no such certificate issued, when Snail payment is due is accordance with paragraph 14.13. The terms 'substantially complete' and 'substantially completed' as applied to any Work refer to Substantial Completion thereof. Supplement/ay Conditioos The part of the Contract Documents which amends or supplements the General Conditions. Supplie —A manufacturer, fabricator, supplier, distributor, materialman or vendor. Uadergronad Fatuities AD pipelines, conduits, ducts, cables, wire, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water. GC -3 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h ERPEY. HUSION & ASSOCIATES, INC. Unit Price Work —Work to be paid for on the basis of unit prices. Work —The entire completed construction or the various separately identifiable parts thereof required to be furnished under the Contract Documents. Work is the result of performing services, furnishing labor and furnishing and incorporating materials and equipment into the construction, all as required by the Contract Documents. Work Directive Change - -A written directive to CONTRACTOR, issued on or after the Effective Date of the Agreement and signed by OWNER and recommended by ENGINEER, ordering an addition, deletion or revision hi the Work, or responding to differing or unforeseen physical conditions under which the Work k to be performed as provided in paragraph 4.2 or 4.3 or to emergencies wader paragraph 6.22. A Work Directive Change may not change the Contract Price or the Contract Time, but is evidence that the parties expect that the change directed or documented by • Work Directive Change will be incorporated in a subsequently issued Change Order following negotiations by tbe parties as to its effect, if any, on the Contract Price or Contract Time as provided in paragraph 10.2. Written Amendment —A written amendment of the Contract Documents, signed by OWNER and CONTRACTOR an or after the Effective Date of the Agreement and normally dealing with the nonengineering or nontechnical rather than strictly Work - related aspects of the Contract Documents. Delivery of Bonds: ARTICLE 2--PIRELIMLNARY MATTERS 2.1 When CONTRACTOR delivers the executed Agreements to OWNER, CONTRACTOR shall also deliver to OWNER such Bonds as CONTRACTOR may be required to furnish in accordance with paragraph 5.1. Copies of Documents 2.2 OWNER shall furnish to CONTRACTOR up to ten copies (unless other- wise specified in tbe Supplementary Conditions) of the Contract Documents as are reasonably necessary for tbe execution of the Work. Additional copies will be furnished, upon request, at the cost of reproduction. Commence of Contract Time•, Notice to Proceed: 2.3 The Contract Time will commence to run on the thirtieth day after the Effective Date of tbe Agreement, or, if a Notice to Proceed is given, on tbe day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within thirty days after the Effective Date of the Agreement. In no event will the Contract Time commence to rum later than the seventy -fifth day after the day of GC-4 e Starting tbe Project: [SPEY. HUSTON & ASSOCIATES. INC. GC -5 Bid opening or the thirtiety day after the Effective Date of the Agreement, whichever date is earlier. 2.4 CONTRACTOR shall start to perform the Work on the date when the Contract Time commences to run, but no Work shall be done at the site prior to the date on which the Contract Time commences to run. Before Starting Construction: 2.5 Before tardertaking each part of the Work, CONTRACTOR shall care- fully study and compare tbe Contract Documents and check and verify pertinent figures shown thereon and all applicable field measurements. CONTRACTOR shall promptly report in writing to ENGINEER any conflict, error or discrepancy which CONTRACTOR may discover and shall obtain a written interpretation or clarifies - tion from ENGINEER before proceeding with any Work affected thereby; however, CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any conflict, error or discrepancy in the Contract Documents, unless CONTRAC- TOR had actual knowledge thereof or should reasonably have known thereof. 2.6 Within ten days after the Effective Date of the Agreement (unless otherwise specified in the General Requirements), CONTRACTOR shall submit to ENGINEER for review: 2.6.1 an estimated progress schedule indicating the starting and completion dates of the various stages of the Work; 2.6.2 a preliminary schedule of Shop Drawing submissions; and 2.6.3 a preliminary schedule of values for all of the Work which will include quantities and prices of items aggregating the Contract Price and will subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during construction. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work which will be confirmed in writing by CONTRACTOR at :tbe time of submission. 2.7 Before any Work at the site is started, CONTRACTOR shall deliver to OWNER, with a copy to ENGINEER, certificates (and other evidence of insurance requested by OWNER) which CONTRACTOR is required to purchase and maintain in accordance with paragraphs 5.3 and 5.4, and OWNER shall deliver to CONTRACTOR certificates (and other evidence of insurance requested by CONTRACTOR) which OWNER is required to purchase and maintain in accordance with paragraphs 5.6 and 5.7. 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h CSITY. HUSTON a AS INC. Preconstruction Conference: 2.8 Within twenty days after the Effective Date of the Agreement, but before CONTRACTOR starts the Work at the site, a conference attended by CONTRACTOR, ENGINEER and others as appropriate will be held to discuss the schedules referred to in paragraph 2.6, to discuss procedures for handling Shop Drawings and other submittals and for processing Applications for Payment, and to establish a working understanding among the parties as to tbe Work. Finalising Schedules: 2.9 At least ten days before submission of the first Application for Payment a conference attended by CONTRACTOR, ENGINEER and others as appropriate will be held to finalise tbe schedules submitted in accordance with paragraph 2.6. The finalized progress schedule will be acceptable to ENGINER as providing an orderly progression of the Work to completion within the Contract Time, but such acceptance will neither impose on ENGINEER responsibility for the progress or scheduling of the Work nor relieve CONTRACTOR from full responsibility therefor. The finalized schedule of Shop Drawing submissions will be acceptable to ENGI- NEER as providing a workable arrangement for processing tbe submissions. The finalized schedule of values will be acceptable to ENGINEER as to form and substance. Intent: ARTICLE 3-- CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE 3.1 The Contract Documents comprise the entire agreement between OWNER and CONTRACTOR concerning the Work. The Contract Documents are complementary, what is called for by one is as binding as if called for by a11. The Contract Documents will be construed in accordance with the law of the place of the Project. 3.2 It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents. Any Work, materials or equipment that may reasonably be inferred from the Contract Documents as being required to produce the intended result will be supplied whether or not specifically called for. When words which have a well -known technical cc trade meaning are used to describe Work, materials or equipment, such words shall be interpreted in accordance with that meaning. Reference to standard specifications, manuals or codes of any technical society, organization or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the Latest standard specification, manual, code or Laws or Regulations in effect at the GC-6 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 [SKY, HUSTON i ASSOCIATES, INC. time of opening of Bids (or, on the Effective Dateof the Agreement if there were no Bids), except as may be otherwise specifically stated. However, no provioon of any referenced standard specification, manual or code (whether or bot specifically incorporated by reference in the Contract Documents) sbaD be effective to change the duties and responsibilities of OWNER, CONTRACTOR or ENGINEER, or any of their consultants, agents or employees from those set forth in the Contract Documents, nor shall it be effective to assign to ENGINEER, or any of ENGINEER'S consultants, agents or employees, any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.15 or 9.16. Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in paragraph 9.4. 3.3 H, during the performance of the Work, CONTRACTOR finds a conflict, error or discrepancy in the Contract Documents, CONTRACTOR shall so report to ENGINEER in writing at once and before proceeding with the Work affected thereby shall obtain a written interpretation or clarification from ENGINEER; however, CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any conflict, error or discrepancy in the Contract Documents unless CONTRACTOR bad actual knowledge thereof or should reasonably have known thereof. Amending and Supplementing Contract Documents: 3.4 The Contract Documents may be amended to provide for additions, deletions and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways: 3.4.1 a formal Written Amendment, 3.4.2 a Change Order (pursuant to paragraph 10.4), or 3.4.3 a Work Directive Change (pursuant to paragraph 10.1). As indicated in paragraphs 11.2 and 12.1, Contract Price and Contract Time may only be changed by a Change Order or a Written Amendment. 3.5 In addition, the requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorised, in one or more of the following ways: 3.5.1 afield Order (pursuant to paragraph 9.5), 3.5.2 ENGINEER'S approval of a Shop Drawing or sample (pursuant to para- graphs 6.26 and 627), or GC-7 • e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h IVEY, HUSTON a ASSOCIATES. INC. 8 S 3.5.3 ENGINEER'S written_interpretstion or clarification (pursuant to para- graph 9.4). Reuse of Documents: 3.6 Neither CONTRACTOR nor any Subcontractor or Supplier or other person or organization performing or furnishing any of the Work under a direct or indirect contract with OWNER shall have or acquire any title to or ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER; and they shall not reuse any of them on extensions of the Project or any other project withoug written consent of OWNER and ENGINEER and specific written verification or adaptation by ENGD EER. Physical Conditions: ARTICLE 4— AVAII.ASIISrY OF LANDS: PHYSICAL CONDrIIONS; REFERENCE POINTS Availability of Lands: 4.1 OWNER shall furnish, as indicated in the Contract Documents, the lands upon which the Work is to be performed, rights - of-way and easements for access thereto, and such other lands which are designated for the use of CONTRACTOR. Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by OWNER, tmless otherwise provided in the Contract Documents. If CONTRACTOR believes that any delay in OWNER'S furnishing these lands, rights - of-way or easements entitles CONTRACTOR to an extension of the Contract Time, CONTRACTOR may make a claim therefore as provided in Article 12. CONTRACTOR shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment. 4.2.1 Explorations and Reports. Reference is made to the Supplementary Conditions for identification of those reports of explorations and tests of subsurface conditions at the site that have been utilized by ENGINEER in preparation of the Contract Documents. CONTRACTOR may rely upon the accuracy of the technical data contained in such reports, but not upon nontechnical data, interpretations ce opinions contained therein or for the completeness thereof for CONTRACTOR'S purposes. Except as indicated in the immediately preceding sentence and in para- graph 4.2.6, CONTRACTOR shall have full responsibility with respect to subsurface conditions at the site. GC -8 e [SKr. HUSTON a ASSOCIATES. INC. 4 > 4.2.2 Existing Structures. Reference is made to the Supplementary Condition Ice identification of those drawings of physical conditions in or relating to existing surface and subsurface structures (except Underground Facil- ities referred to in paragraph 4.3) which are at or contiguous to the site that been utilised by ENGINEER in preparation of the Contract Documents. CONTRACTOR may rely upon the accuracy of the tech- nical data contained in such drawings, but not for the completeness thereof for CONTRACTOR'S purposes. Except as indicated in the immediately preceding sentence and in paragraph 4.2.6, CONTRACTOR shall have full responsibility with respect to physical conditions in or relating to such structures. 4.2.3 Report of Differing Conditions. If CONTRACTOR believes that: 4.2.3.1 any technical data on which CONTRACTOR is entitled to rely as provided in paragraphs 42.1 and 42.2 is inaccurate, or 4.2.3.2 any physical condition uncovered or revealed at the site differs materially from that indicated, reflected or referred to in the Contract Document s, CONTRACTOR shall, promptly after becoming aware thereof and before performing any Work in connection therewith (except in an emergency as permitted by paragraph 6.22), notify OWNER and ENGINEER in writing about the inaccuracy or difference. 4.2.4 ENGINEER'S Review. ENGINEER will promptly review the pertinent conditions, determine the necessity of obtaining additional explorations or tests with respect thereto and advise OWNER in writing (with a dopy to CONTRACTOR) of ENGINEER'S findings and conclusions. 4.2.5 Possible Document Change. If ENGINEER concludes that there is a material error in the Contract Documents or that because of newly discovered conditions a change in the Contract Documents is required, a Work Directive Change or a Change Order win be issued as provided is Article 10 to reflect and document the consequences of the inaccuracy or difference. 4.2.6 Possible Price and Time Adjustments. In each such case, an ineease or decrease is the Contract Price or an extension or shortening of the Contract Time, or any combination thereof, will be allowable to the extent that they are attributable to any such inaccuracy or difference. If OWNER and CONTRACTOR are unable to agree as to the amount or length thereof, a claim may be made therefor as provided in Articles 11 and 12. GC-9 1 eh t , I WET. HUSTON i ASSOCIATES, INC. 1 Pbysicsl Conditions--Undergrotmd Facilities: ' . 4.3.1 Shown or Indicated. The information and data shown or indicated in tbe 1 Contract Documents with respect to existing Underground Facilities at or contiguous to the site is based on information and data furnished to OWNER or ENGINEER by the owners of such Underground Facilities or by others. Unless it is otherwise expressly provided in the Supplemen- t terry Conditions: 4.3.1.1 OWNER and ENGINEER shall not be responsible for the accuracy 1 or completeness of any such information or data; and, 4.3.1.2 CONTRACTOR shall have full responsibility for reviewing and checking all such information and data, for locating all Under- , ground Facilities shown or indicated in tbe Contract Documents, for coordination of the Work with the owners for such Underground Facilities during construction, for the safety and protection 1 thereof as provided in paragraph 6.20) and repairing any damage thereto resulting from the Work, the cost of all of which will be considered as having been included in the Contract Price. ' 4.3.2 Not Shown or Indicated. If an Underground Facility h w covered or revealed at or contiguous to the site which was not shown or indicated in the Contract Documents and which CONTRACTOR could not reasonably have been 1 expected to be aware of, CONTRACTOR shall, promptly after becoming aware thereof and before performing any Work affected thereby (except in an emergency as permitted by paragraph 6.22), identify the owner of such Underground Facility 1 and give written notice thereof to that owner and to OWNER and ENGINEER. ENGINEER will promptly review tbe Underground Facility to determine the extent to which the Contract Documents should be modified to reflect and document the consequences of the existence of the Underground Facility, and the Contract I Documents will be amended or supplemented to the extent necessary. During such time, CONTRACTOR shall be responsible for the safety and protection of such Underground Facility as provided in paragraph 6.20. CONTRACTOR shall be 1 allowed an increase in the Contract Price or an extension of the Contract Time, or both, to the extent that they are attributable to the existence of any Underground Facility that was not shown or indicated in the Contract Documents and which CONTRACTOR could not reasonably have been expected to be aware of. If the ' parties are unable to agree at to the amount or length thereof, CONTRACTOR may make a claim therefor as provided in Articles 11 and 12. 1 Reference Pants 4.4 OWNER shall provide engineering surveys to establish reference points 1 for construction which in ENGINEER'S judgment are necessary to enable CON- TRACTOR to proceed with the Work. CONTRACTOR shall be responsible for laying 1 1 GC -10 • e 1 1 1 . 1 1 1 1 1 1 1 1 1 h ISM, HUSTON a ASSOCIATES, INC. . out the Work (unless otherwise specified in the General Requirements), shall protect and preserve the established reference points and shall make to changes or relocations without the prior written approval of OWNER. CONTRACTOR shall report to ENGINEER whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points by professionally qualified personnel. Performance and Other bonds: ARTICLE 5--BONDS AND INSURANCE 5.1 CONTRACTOR shall furnish performance and payment Bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all CONTRACTOR; obligations under the Contract Documents. These Bonds shall remain in effect at least until one year after the date when final payment becomes due, except as otherwise provided by Law or Regulation or by the Contract Documents. CONTRACTOR shall also furnish such other Bonds as are required by the Supplementary Conditions. All Bonds shall be in the forms prescribed by Law or Regulation or by the Contract Documents and be executed by such streties as are named in the current list of 'Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies' as published in Circular 570 (amended) by the Audit Staff Bureau of Accounts, U.S. Treasury Department. All Bonds signed by an agent must be accompanied by a certified copy of the authority to act. 5.2 If the surety on any Bond furnished by CONTRACTOR is declared a bankrupt or becomes insolvent or its right to do business is terminated in any state where any part of the Project is located or it ceases to meet the requirements of paragraph 5.1, CONTRACTOR shall within five days thereafter substitute another Bond and Surety, both of which must be acceptable to OWNER. Contractor's Liability Insurance 5.3 CONTRACTOR shall purchase and maintain such comprehensive general liability and other insurance as is appropriate for the Work being performed and furnished and as will provide protection from claims set forth below which may arise out of or result from CONTRACTOR'; performance and furnishing of the Work and CONTRACTOR's other obligations carder the Contract Docmnent;, whether it is to be performed or furnished by CONTRACTOR, by any Subcontractor, by anyone directly or indirectly employed by any of them to perform or furnish the Work, or by anyone for whose acts any of them may be liable: 5.3.1 Claims under workers' or workmen's compensation, disability benefits and other similar employee benefit acts; GC -11 e E1PE1', HUSTON & ASSOCIATES, INC. - 5.3.2 Claims for damages because of bodily injury, sielmess � disease, or death of CONTRACTOR'' employees; 5.3.3 Claims for damages because of bodily injury, sickness or disease, or death of any person other than CONTRACTOR's employees; 5.3.4 Claims for damages insured by personal injury liability coverage which are sustained (a) by any person as a result of an offense directly or indirectly related to the employment of such person by CONTRACTOR, or (h) by any other person for any other reason; 5.3.5 Claims for damages, other than to the Work itself, because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom; 5.3.6 Claims arising out of operation of Laws or Regulations for damages because of bodily injury or death of any person or for damage to property and 5.3.7 Claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle. The insurance required by this paragraph 5.3 shall include the specific coverages and be written for not less than the limits of liability and coverages provided in the Supplementary Conditions, or required by law, whichever is greater. The comprehensive general liability insurance shall include completed operations insurance. All of the policies of insurance so required to be purchased and maintained (or the certificates or other evidence thereof) shall contain a provision or endorsement that the coverage afforded will not be cancelled, materially changed or renewal refused until at least thirty days prior written notice has been given to OWNER and ENGINEER by certified mail. All such insurance shall remain in effect until final payment and at all times thereafter when CONTRACTOR may be correcting, removing or replacing defective Work in accordance with para- graph 13.12. la addition, CONTRACTOR shall maintain such completed operations insurance for at least two years after final payment and furnish OWNER with evidence of continuation of such insurance at final payment and one year thereafter. Contractual Liability Insurance: 5.4 The comprehensive general liability insurance required by paragraph 5.3 will include contractual liability insurance applicable to CONTRACTOR'S obliga- tions wader paragraphs 6.30 and 6.31. GC -12 1 1 1 1 1 1 1 1 1 1 1 1 e ESPtY. HUSTON 1 ASSOCian , tNC. Owners Liability Insurance: 5.5 OWNER shall be responsible for purchasing and maintaining OWNER's own liability insurance and, at OWNER's option, may purchase and maintain such insurance as will protect OWNER against claims which may arise from operations under the Contract Documents. Property lastrance: 5.6 Unless otherwise provided in the Supplementary Conditions, OWNER shall purchase and maintain property insurance upon the Work at the site to the full insurable value thereof (subject to such deductible amounts as may be provided in the Supplementary Conditions or required by Laws and Regulations). This insurance shall include the interests of OWNER, CONTRACTOR, Subcontractors, ENQNEER and ENGINEER'S consultants in the Work, all of whom shall be listed as insureds or additional insured parties, shall insure against the perils of fire and extended coverage and shall include "all risk" insurance for physical loss and damage inducting theft, vandalism and malicious mischief, collapse and water damage, and such other peris as may be provided in the Supplementary Conditions, and shall included. damages, loss and expenses arising out of or resulting from any insured loss or incurred in the repair m replacement of any insured property Gncluding but not limited to fees and charges of engineers, architects, attorneys and other profes- sionals). If not covered under the "all risk' insurance or otherwise provided in the Supplementary Conditions, CONTRACTOR shall purchase and maintain similar property insurance cm portions of the Work stored on and off the site or in transit when such portions of the Work are to be included is an Application for Payment. 5.7 OWNER shall purchase and maintain such boiler and machinery insurance or additional property insurance as may be required by the Supplementary Condi- tions or Laws and Regulations which will include the interests of OWNER, CONTRACTOR, Subcontractors, ENGINEER and ENGINEER'S consultants hi the Work, all of whom shall be listed as insured or additional insured parties. 5.8 All the policies of insurance or the certificates or other evidence thereof) required to be purchased and maintained by OWNER in accordance with paragraphs 5.6 and 5.7 will contain • provision or endorsement that the coverage afforded will not be cancelled or materially changed or renewal refused until at least thirty days' prior written notice has been given to CONTRACTOR by certified mail and will contain waiver provisions in accordance with paragraph 5.11.2. 5.9 OWNER shall not be responsible for purchasing and maintaining any property insurance to protect the interests of CONTRACTOR, Subcontractors or others in the Work to the extent of any deductible amounts that are provided in the Supplementary Conditions. The risk of loss within the deductible amount will be borne by CONTRACTOR, Subcontractor or others suffering any such loss and if any GC-13 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h MET. HUSTON a ASSOCIATES, INC. of them wishes property insurance coverage within tbe limits of such amounts, each may purchase and Maintain it at the purchaser's own expense. 5.10 If CONTRACTOR requests in 'Writing that other special insurance be included in the property insurance policy, OWNER shall, if possible, include such insurance, and tbe cost thereof uri11 be charged to CONTRACTOR by appropriate Change Order or Written Amendment. Prior to commencement of the Work at the site, OWNER shall in writing advise CONTRACTOR whether or not such other insurance has been procured by OWNER. Waiver of Rights: 5.11.1 OWNER and CONTRACTOR waive all rights against each other for all losses and damages caused by any of the perils covered by the polices of insurance provided in response to paragraphs 5.6 and 5.7 and any other property insurance applicable to the Work, and also waive all such rights against tbe Subcontractors, ENGINEER, ENGINEER'S consultants and all other parties named as insureds in such policies for losses and damages so caused. As required by paragraph 6.11, each subcontract between CONTRACTOR and a Subcontractor will contain similar waiver pro- visions by the Subcontractor in favor of OWNER, CONTRACTOR, ENGINEER, ENGNEER's consultants and all other parties named as insureds. None of the above waivers shall extend to the rights that any of the insured parties may have to the proceeds of insurance bled by OWNER as trustee or otherwise payable under any policy so issued. 5.112 OWNER and CONTRACTOR intend that any polices provided in re- sponse to paragraphs 5.6 ands 5.7 shall protect all of the parties insured and provide primary coverage for all losses and damages caused by the perils covered thereby. Accordingly, all such policies shall contain provisions to the effect that in the event of payment of any loss or damage the insurer will have no rights of recovery against any of the parties named as insureds or additional insureds, and if the insurers require separate waiver forms to be signed by ENGINEER or ENGI- NEER's consultant, OWNER will obtain the same, and if such waiver forms are required of any Subcontractor, CONTRACTOR will obtain the same. Receipt and Application of Proceeds: 5.12 Any insured lass under the policies of insurance required by para- graphs 5.6 and 5.7 will be adjusted with OWNER and made payable to OWNER as trustee for the insureds, as their interests may appear, subject to the requirements of any applicable mortgage clause and of paragraph 5.13. OWNER shall deposit in a separate account any money so received, and shall distribute it in accordance with such agreement as the parties in interest may reach. If no other special agreement GC -14 1 1 1 1 1 1 1 1 1 1 1 . .1 .1 1 1 1 1 e ESKY. HUSTON a ASSOCIATE& INC. is reached, the damaged Work shall be repaired or replaced, tbe moneys so received applied on account thereof and the Work and the cost thereof covered by an appropriate Change Order or Written Amendment. 5.13 OWNER as trustee shall have power to adjust and settle any loss witb the insurers unless one of the parties in interests shall object in writing within fifteen days after tbe occurrence of loss to OWNER's exercise of this power. If such objection be made, OWNER as trustee shall make settlement with the ituurers in accordance with such agreement as the parties in inderest may reach. If required in writing by any party in interest, OWNER as trustee shall, upon the occurrence of an insured loss, give bond for the proper performance of such duties. Acceptance of Insurance 5.14 If OWNER has any objection to the coverage afforded by or other provisions of the insurance required to be purchased and maintained by CON- TRACTOR in accordance with paragraphs 5.3 and 5.4 on the basis of its not complying with the Contract Documents, OWNER shall notify CONTRACTOR in writing thereof within ten days of the date of delivery of such certificates to OWNER in accordance with paragraph 2.7. If CONTRACTOR has any objection to the coverage afforded by or other provisions of the policies of insurance required to be purchased and maintained by OWNER in accordance with paragraphs 5.6 and 5.7 on the basis of their not complying with the Contract Documents, CONTRACTOR shall notify OWNER in writing thereof within ten days of the date of delivery of such certificates to CONTRACTOR in accordance with paragraph 2.7. OWNER and CONTRACTOR shall each provide to the other such additional information in respect of insurance provided by each as the other may reasonably request. Failure by OWNER or CONTRACTOR to give any such notice of objection within the time provided shall constitute acceptance of such insurance purchased by the other as complying with the Contract Documents. Partial Utilisation— propertylswanx: 5.15 If OWNER finds it necessary to occupy or use a portion or portions of the Work prior to Substantial Completion of all the Work, such use ce occupancy may be accomplished in accordance with paragraph 14.10; provided that no such use or occupancy shall commence before the insurers providing the property insurance have acknowledged notice thereof and in writing effected the changes in coverage necessitated thereby. The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be cancelled or lapse on account of any such partial use or occupancy. GC -15 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h ES ►fY. HUSION a ASSOCIATES. INC. ARTICLE 6— CONTRACTOR'S RESPONSIBI MES Supervision and Superintendence: 6.1 CONTRACTOR shall supervise and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. CONTRACTOR shall be solely responsible for the means, methods, techniques, sequences and procedures of construction, but CONTRACTOR shall not be respon- sible for the negligence of others in the design se selection of a specific meats, method, technique, sequence or procedure of construction which is indicated in and required by the Contract Documents. CONTRACTOR shall be responsible to see that the finished Work complies accurately with the Contract Documents. 62 CONTRACTOR shall keep on the Work at all times during its progress a competent resident superintendent, who shall not be replaced without written notice to OWNER and ENGINEER except under extraordinary circumstances. The super- intendent will be CONTRACTOR'S representative at the site and shall have autbority to act on behalf of CONTRACTOR. All communications given to the superintendent shall be as binding as U given to CONTRACTOR. Labor, Materials and Equipment: 6.3 CONTRACTOR shall provide competent, suitably qualified personnel to survey and lay out the Work and perform construction as required by the Contract Documents. CONTRACTOR shall at all times maintain good discipline and order at the site. Except in connection with the safety or protection of persons or the Work or property at the site or adjacent thereto, and except as otherwise indicated in the Contract Documents, all Work at the site shall be performed during regular working hours, and CONTRACTOR will not permit overtime work or the performance of Work on Saturday, Sunday or any legal holiday without OWNER's written consent given after prior written notice to ENGINEER. 6.4 Unless otherwise specified in the General Requirements, CONTRACTOR shall furnish and assume full responsibility for all materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, beat, telephone, water, sanitary facilities, temporary facilities and all other facilities and incidentals necessary for the furnishing, performance, testing, start -up and completion of the Work. 6.5 All materials and equipment shall be of good quality and new, except as otherwise provided in the Contract Documents. If required by ENGINEER, CON- TRACTOR shall furnish satisfactory evidence (including reports of required tests) as to the kind and quality of materials and equipment. All materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with the instructions of the applicable Supplier except as otherwise GC -16 . 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 . h EPtY.HUSTON a ASSOCIATES. INC. provided in the Contract Documents; but DO provision of any such instructions will be effective to assign to ENGINEER, or any of ENG1NEER's consultants, agents or employees, any duty or authority to supervise or direct the furnishing or perform- ance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.15 or 9.16. Adjusting Progress Schedule 6.6 CONTRACTOR shall submit to ENGINEER for acceptance (to the extent indicated in paragraph 1.9) adjustments in the' progress schedule to reflect the impact thereon of new developments, the will conform generally to the progress schedule then in effect and additionaby comply with any provisions of the General Requirements applicable thereto. Substitutes or 'Or— Equal Items: 6.7.1 Whenever materials or equipment se e specified or described in the Contract Documents by using the name of a proprietary item or the name of a• particular Supplier the naming of the item is intended to establish the type, function and quality required. Unless the name is followed by words indicating that no substitution is permitted, materials or equipment of other Suppliers may be accepted by ENGINEER if sufficient information is submitted by CONTRACTOR to allow ENGI- NEER to determine that the material or equipment proposed is equi- valent or equal to that named. The procedure for review by ENGINEER will include the following as supplemented in the General Requirements. Requests for review of substitute items of materials and equipment will not be accepted by ENGINEER from anyone other than CONTRACTOR. If CONTRACTOR wishes to furnish or use a substitute item of material or equipment, CONTRACTOR shall make written application to ENGI- NEER for acceptance thereof, certifying that the proposed substitute will perform adequately the functions and achieve the results called for by the general design, be similar and of equal substance to that specified and be suited to the same use as that specified. The application will state that the evaluation and acceptance of the proposed substitute will not prejudice CONTRACTOR's achievement of Substantial Completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) to adapt the design to the proposed substitute and whether or not incorporation or use of the substitute in connection with the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute from that specified will be identified in the appli- cation and available maintenance, repair and replacement service will be indicated. The application will also contain an itemized estimate of all costs that wiD result directly or indirectly from acceptance of such GC -17 h ESFEY. HUSTON L ASSOCIATES. INC. substitute, including costs of redesign and claims of other contractors affected by the resulting change, all of which shall be considered by ENGINEER in evaluating tbe proposed substitute. ENGINEER may require CONTRACTOR to furnish at CONTRACTOR'S expense additional data about the proposed substitute. 6.7.2 If a specific means, method, technique, sequence or procedure of construction is indicated in or required by tbe Contract Documents, CONTRACTOR may futaisb or utilise a substitute means, method, sequence, technique or procedure of construction acceptable to ENGI- NEER, if. CONTRACTOR submits sufficient information to allow ENGINEER to determine that the substitute proposed is equivalent to that indicated or required by the Contract Documents. The procedure for review by ENGINEER will be similar to that provided in Para- graph 6.7.1 as applied by ENGINEER and as may be supplemented in the General Requirements. 6.7.3 ENGINEER will be allowed • reasonable time within which to evaluate eacb proposed substitute. ENGINEER will be the sole judge of accept- ability, and no substitute will be ordered, installed or utilized without ENGINEER's prior written acceptance which will be evidenced by either a Change Order or an approved Shop Drawing. OWNER may require CONTRACTOR to furaisb at CONTRACTOR'S expense a special per- formance guarantee or other surety with respect to any substitute. ENGINEER will record time required by ENGINEER and ENGINEER'S consultants in evaluating substitutions proposed by CONTRACTOR and in maivng changes in the Contract Documents occasioned thereby. Whether or not ENGINEER accepts a proposed substitute, CONTRAC- TOR shall reimburse OWNER for the charges of ENGINEER and ENGINEER'S consultants for evaluating each proposed substitute. Concerning Subcontractors, Suppliers and Others: 6.8.1 CONTRACTOR shall not employ any Subcontractor, Supplier or other person or organization ('including those acceptable to OWNER and ENGINEER as indicated in paragraph 6.8.2), whether initially or as a substitute, against whom OWNER or ENGINEER may have reasonable objection. CONTRACTOR shall not be required to employ any Subcon- tractor, Supplier or other person or organization to furnish or perform any of the Work against whom CONTRACTOR has reasonable objection. 6.8.2 If the Supplementary Conditions require the identity of certain Subcon- tractors, Suppliers or other persons or organization (including those who are to furnish the principal items of materials and equipment) to be submitted to OWNER in advance of the specified date prior to the Effective Date of the Agreement for acceptance by OWNER and GC -18 1 � .r e h ELPEY. HUSTON & ASSOCIATES, INC. ENGINEER, and if CONTRACTOR has submitted a list thereof in accordance with the Supplementary Conditions, OWNER's or ENGI- NEER', acceptance (either in writing or by tailing to make written objection thereto by the date indicated f or acceptance or objection in the bidding documents or the Contract Documents) of any sucb Subcon- tractor, Supplier or other person or organisation as identified may be revoked on the basis of reasonable objection after due investigation, in which case CONTRACTOR shall submit an acceptable substitute, the Contract Price will be increased by the difference in tbe cost occasioned by such substitution and an appropriate Change Order will be issued or Written Amendment signed. No acceptance by OWNER or ENGINEER of any such Subcontractor, Supplier or other person or organisation shall constitute a waiver of any right of OWNER or ENGINEER to reject defective Work. 6.9 CONTRACTOR shall be fully responsible to OWNER and ENGINEER for all acts and omissions of the Subcontractors, Suppliers and other persons and organizations performing or furnishing any of the Work under • direct or indirect contract with CONTRACTOR just as CONTRACTOR is responsible for CON - TRACTOR's own acts and omissions. Nothing in tbe Contract Documents shall create any contractual relationship between OWNER or ENGINEER and any such Subcontractor, Supplier or other person or organisation, nor shall it create any obligation on the part of OWNER or ENGINEER to pay or to see to the payment of any moneys due any such Subcontractor, Supplier or other person or organisation except as may otherwise be required by Laws and Regulations. 6.10 The divisions and sections of the Specifications and the identifications of any Drawings shaD not control CONTRACTOR in dividing the Work among Subcon- tractors or Suppliers or delineating the Work to be performed by any specific trade. 6.11 All Work performed for CONTRACTOR by a Subcontractor will be pursuant to an appropriate agreement between CONTRACTOR and the Subcon- tractor which specifically binds the Subcontractor to the applicable terms and conditions of the Contract Documents for the benefit of OWNER and ENGINEER and contains waiver provisions as required by paragraph 5.11. CONTRACTOR shall pay each Subcontractor a just share of any insurance moneys received by CON- TRACTOR on account of losses under policies issued pursuant to paragraphs 5.6 and 5.7. Patent Fees and Royalties: 6.12 CONTRACTOR shall pay all license fees and royalties and assume all costs incident to the we in the performance of the Work or the incorporation in the Work of any invention, design, process, product or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product or device is specified in the Contract Documents for use in the performance • GC -19 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h UPEI% HUSTON & ASSOCIATES. INC. of the Work and if to the actual knowledge of OWNER or ENGINEER its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by OWNER in the Contract Documents. CONTRACTOR shall indemnify and bold harmless OWNER and ENGINEER and anyone directly or indirectly employed by either of them from and against all claims, damages, losses and expenses (including attorney's fees and court and arbitration costs) arising out of any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product or device not specified in the Contract Documents, and shall defend all sueb claims in connection with any alleged infringement of such rights. Permits: 6.13 Unless otherwise provided in. the Supplementary Conditions, CON- TRACTOR sball obtain and pay for all construction permits and licenses. OWNER shall assist CONTRACTOR, when necessary, in obtaining such permits and licenses. CONTRACTOR shall pay all governmental charges and inspection fees necessary for the prosecution of the Work, which are applicable at the timeof opening of Bids, or if there are no Bids on the Effective Date of the Agreement. CONTRACTOR shall pay all charges of utility owners for connections to the Work, and OWNER shall pay all charges of such utility owners for capital costs related thereto such as plant investment fees. Laws and Regulations: 6.14.1 CONTRACTOR shall give 511 notices and comply with all Laws and Regulations applicable to furnishing and performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither OWNER nor ENGINEER shall be responsible for monitoring CONTRACTOR'S compliance with any Laws or Regulations. 6.14.2 If CONTRACTOR observes that the Specifications or Drawings are at variance with any Laws or Regulations, CONTRACTOR shall give ENGINEER prompt written notice tberof, and any necessary changes will be authorized by one of the methods indicated in paragraph 3.4. If CONTRACTOR performs any Work knowing or having reason to know that it is contrary to such Laws or Regulations, and without such notice to ENGINEER, CONTRACTOR shall bear all costs arising therefrom; however, it shall not be CONTRACTOR'S primary responsibility to make certain that the Specifications and Drawings are in accordance with such Laws and Regulations. GC -20 e 1 1 _ 1 1 1 1 .1 1 1 1 1 1 h ESPZY. HUSTON a ASSOCIATES. INC. Taxes: 6.15 CONTRACTOR shall pay all sales, consumer, use and other similar taxes required to be paid by CONTRACTOR in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance of the W ork. Use of premises: 6.16 CONTRACTOR shall confine construction equipment, the storage of materials and equipment and the operations of workers to the Project site and land and areas identified in and permitted by the Contract Documents and other land and areas permitted by Laws and Regulations, rights -of -way, permits and easements, and shall not unreasonably encumber the premises with construction equipment or other materials or equipment. CONTRACTOR shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof or of any land or areas contiguous thereto, resulting from the performance of the Work. Should any claim be made against OWNER or ENGINEER by any such owner or occupant because of the performance of the Work, CONTRACTOR shall promptly attempt to settle with such other party by agreement or otherwise resolve the claim by arbitration ar at law. CONTRACTOR shall, to the fullest extent permitted by Laws and Regulations, indemnify and lipid OWNER and ENGINEER harmless from and against all claims, damages, losses and expenses (including, but not Limited to, fees of engineers, architects, attorneys and other professionals and court and arbitration costs) arising directly, indirectly or consequentially out of any action, legal or equitable, brought by any such other party against OWNER or ENGINEER to the extent based on a claim arising out of CONTRACTOR'' performance of the Work. 6.17 During the progress of the Work, CONTRACTOR shall keep the premises free from accumulations of waste materials, rubbish and other debris resulting from the Work. At the completion of the Work, CONTRACTOR shall remove all waste materials, rubbish and debris from and about the permises as well as all tools, appliances, construction equipment and machinery, and surplus materials, and shall leave the site clean and ready for occupancy by OWNER. CONTRACTOR shall restore to original condition all property not designated for alteration by the Contract Documents. 6.18 CONTRACTOR shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses or pressures that will endanger it. GC -21 1 1 1 1 �1 1 1 1 1 1 1 1 1 1 1 e ISM. HUSTON a ASSOCIATES, INC. Record Documents: 6.19 CONTRACTOR shall maintain in a safe place at the site one record copy of an Drawings, Specifications, Addenda, Written Amendments, Change Orders, Work Directive Changes, Field Orders and written interpretations and clarifications (issued pursuant to paragraph 9.4) in good order and annotated to show all changes made during construction. These record documents together with all approved samples and a counterpart of all approved Shop Drawings will be available to ENGINEER for reference. Upon completion of the Work, these record documents, samples and Shop Drawings will be delivered to ENGINEER for OWNER. Safety and Protections 6.20 CONTRACTOR shall be responsible for' initiating, maintaining and supervising all safety precautions and programs in connection with the Work. CONTRACTOR shall take all necessary precautions for• :tbe safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 6.20.1 all employees on the Work and other persons and organisations who may be affected thereby; 6.20.2 all the Work and materials and equipment to be incorporated therein, whether in storage on or off the site; and 6.20.3 other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and Underground Facilities not designated for removal, relocation or replacement in the course of construction. CONTRACTOR shall comply with all applicable Laws and Regulations of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss and shall erect and maintain all necessary safeguards for such safety and protection. CONTRACTOR shall notify owners of adjacent property and of Underground Facilities and utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation and replacement of their property. All damage, injury or loss to any property referred to in paragraph 620.2 or 6.20.3 caused, directly or indirectly, in whole or in part, by CONTRACTOR, any Subcontractor, Supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, shall be remedied by CONTRACTOR (except damage or loss attributable to the fault of Drawings or Specifications or to the acts or omissions of OWNER or ENGINEER or anyone employed by either of them or anyone for whose acts either of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of CONTRACTOR). CONTRACTOR' duties and responsibilities for the safety and protection of the Work shall continue until such time as all the Work is GC -Z2 e ISM, HUSTON & ASSOCIATES, INC. competed and ENGINEER has issued a notice to OWNER and CONTRACTOR in accordance with paragraph 14.13 that the Work is acceptade (except as otherwise expressly provided in connection with Substantial Comptetim). 621 CONTRACTOR shall designate a responsible representative at the site whose duty shall be the prevention of accidents. This person shall be CONTRAC- TOR'S superintendent unless otherwise designated in writing by CONTRACTOR to OWNER. Emagenda: 6.22 In emergencies affecting the safety or protection of persons or the Work or property at the site or adjacent thereto, CONTRACTOR, without special instruction or authorization from ENGINEER or OWNER, is obligated to act to prevent threatened damage, injury or loss. CONTRACTOR shall give ENGINEER prompt written notice if CONTRACTOR believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby. If ENGINEER determines that a change in the Contract-Documents is required because of the action taken in response to an emergency, a Work Directive Change or Change Order will be issued to document the ooasequences of the changes or variations. Shop Drawings and Samples: 623 After checking and verifying all field measurements and after complying with applicable procedures specified in the General Requirements, CONTRACTOR shall submit to ENGINEER for review and approval in accordance with the accepted schedule of Shop Drawing submissions (see paragraph 2.9), or for other appropriate action if so indicated in the Supplementary Conditions, five copies (tmless otherwise specified in the General Requirements) of all Shop Drawings, which will bear a stamp or specific written indication that CONTRACTOR has satisfied CONTRAC- TOR's responsibilities under the Contract Documents with respect to the review of the submission. All submissions will be identified as ENGINEER may require. The data shown on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and design criteria, materials and similar data to enable ENGINEER to review the information as required. 6.24 CONTRACTOR shall also submit to ENGINEER for review and approval with such promptness as to cause no delay in Work, all samples required by the Contract Documents. All samples will have been checked by and accompanied by a specific written indication that CONTRACTOR has satisfied CONTRACTOR'S responsibilities under the Contract Documents with respect to the review of the submission and will be identified clearly as to material, Supplier, pertinent data such as catalog numbers and the use for which intended. GC -23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 I ES►(r. HUSTON S. ASSOCIATES, INC. 6.25.1 Before submission of each Shop Drawing or sample CONTRACTOR shall have determined and verified all quantities, dimensions, specified per- formance criteria, installation requirements, materials, catalog numbers and similar data with respect thereto and reviewed or coordinated each Shop Drawing or sample with other Shop Drawings and samples and with the requirements of the Work and the Contract Documents. 6.25.2 At the time of each submission, CONTRACTOR shall give ENGINEER specific written notice of each variation that the Shop Drawings or samples may have from the requirements of the Contract Documents, and, in addition, shall cause a specific notation to be made on each Shop Drawing submitted to ENGINEER for review and approval of each such variation. 6.26 ENGINEER will review and approve with reasonable promptness Shop Drawings and samples, but ENGINEER'S review and approval will be only for conformance with the design concept of the Project and for compliance with the information given in the Contract Documents and shall not extend to means, methods, techniques, sequences or' procedures of construction (except where a specific means, method, technique, sequence or procedure of construction is indicated in or required by the Contract Documents) or to safety precautions � programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. CONTRACTOR shall make corrections required by ENGINEER, and shall return the required number of corrected copies of Shop Drawings and submit as required new samples for review and approval. CONTRACTOR shall direct specific attention in writing to revisions other than the corrections called for by ENGINEER on previous submittals. 6.27 ENGINEER'S review and approval of Shop Drawings or samples shall not relieve CONTRACTOR from responsibility for any variation from the requirements of the Contract Documents unless CONTRACTOR has in writing called ENGINEER'S attention to each such variation at the time of submission as required by para- graph 6.25.2 and ENGINEER has given written approval of each such variation by a specific written notation thereof incorporated in or accompanying the Shop Drawing or sample approval; nor will any approval by ENGINEER relieve CONTRACTOR from responsibility for errors or omissions in the Shop Drawings or from responsi- bility for having complied with the provisions of paragraph 6.25.1. 6.28 Where a Shop Drawing or sample is required by the Specifications, any related Work performed prior to ENGD EER's review and approval of the pertinent submission will be the sole expense and responsibility of CONTRACTOR. Continuing the Work: 6.29 CONTRACTOR shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with OWNER. No Work shall be GC-24 1 1 1 1 1 1 1 1 1 . • 1 1 e h EMT. HUSTON & ASSOCIATES. INC. delayed or postponed pending resolution of any disputes or d except as permitted by paragraph 15.5 or as CONTRACTOR and OWNER may otherwise agree in writing. Indemnification: 6.30 To the fullest extent permitted by Laws and Regulations, CONTRAC- TOR shall indemnify and bold harmless OWNER and ENGINEER and their consult- ants, agents and employees from and against all claims, damages, losses and expenses, direct, indirect or consequential (including but not limited to fees and charges of engineers, architects, attorneys and other professionals and court and arbitration costs) arising out of or resulting from the perfeemance of the Work, provided that any such claim, damage, loss or expense (a) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom and (b) is caused in whole or in part by any negligent act or omission of CONTRACTOR, any Subcontractor, any person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder or arises by or is imposed by Laws and Regulations regardless of the negligence of such party. 6.31 In any and all claims against OWNER or ENGINEER or any of their consultants, agents or employees by any employee of CONTRACTOR, any Subcon- tractor, any person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, the indemnification obligation under paragraph 6.30 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for CONTRACTOR or any such Subcontractor or other person or organization under workers' or workmen' compensation acts, disability benefit acts or other employee benefit acts. 6.32 The obligations of CONTRACTOR Under paragraph 6.30 shall not extend to the liability of ENGINEER, ENGWEER's consultants, agents or employees arising out of the preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders, designs of specifications. Related Work at Site ARTICLE 7 - OTHER WORK 7.1 OWNER may perform other work related to the Project at the site by OWNER's own forces, have other work performed by utility owners or let other direct contracts therefor which shall contain General Conditions similar to these. If the fact that such other work is to be performed was not noted in the Contract GC -25 e EUPEr. NUS1ON 1. ASSOCIATES, INC. Documents, written notice thereof will be given to CONTRACTOR prior to starting any such other work; and, if CONTRACTOR believes that such performance will involve additional expense to CONTRACTOR or requires additional time and the parties are unable to agree ss to the extent thereof, CONTRACTOR may make a claim therefor as provided in Articles 11 and 12. 7.2 CONTRACTOR shall afford each utility owner and other contractor who is a party to such a direct contract (or OWNER, if OWNER is perfuming the additional work with OWNER's employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such work, and shall properly connect and coordinate the Work with theirs. CONTRACTOR shall do all cutting, fitting and patebdng of the Work that may be required to make its several parts come together properly and integrate with such other work. CONTRACTOR shall not endanger any work of others by cutting, excavating or otherwise altering their work and will only cut or alter their work with the written consent of ENGINEER and the others whose work will be affected. The duties and responsibiliies of CONTRACTOR tender this paragraph are for the benefit of such utility owners and other contractors to the extent that there are comparable provisions for the benefit of CONTRACTOR in said direct contracts between OWNER and such utility owners and other consultants. 7.3 If any part of CONTRACTOR'S Work depends for proper execution or results upon the work of any such other contractor or utility owner (or OWNER), CONTRACTOR shall inspect and promptly report to ENGINEER in writing any delays, defects or deficiencies in such work that render it unavailable or unsuitable for such proper execution and results. CONTRACTOR'S failure so to report will constitute an acceptance of the other work as fit and proper for integration with CONTRACTOR'S Work except for latent or non - apparent defects and deficiencies in the other work. Coordination: 7.4 If OWNER contracts with others for the performance of other work en the Project at the rite, the person or organisation who will have authority and responsibility for coordination of the activities among the various prime contractors will be identified in the Supplementary Conditions, and the specific matters to be covered by such authority and responsibility will be itemized, and the extent of such authority and responsibilities will be provided, in the Supplementary Conditions. Unless otherwise provided in the Supplementary Conditions, neither OWNER nor ENGINEER shall have any authority or responsibility in respect of such coordination. ARTICLE $- OWNERS RESPONSmII1TIES 8.1 OWNER shall issue all commimications to CONTRACTOR through ENGINEER. GC -26 e [SPEY. HUSTON a ASSOCIATES. INC. 8.2 In case of termination of the employment of ENGINEER, OWNER shall appoint an engineer against whom CONTRACTOR makes no reasonable objection, whose status under the Contract Documents shall be that of the former ENGINEER. Any dispute in connection with such appointment shall be subject to arbitration. 8.3 OWNER shall furnish the data required of OWNER tinder the Contract Documents promptly and shall make payments to CONTRACTOR promptly after they are due as provided in paragraphs 14.4 and 14.13. 8.4 OWNER's duties in respect of providing lands and easements and providing engineering surveys to establish reference points are set forth in para- graphs 4.1 and 4.4. Paragraph 4.2 refers to OWNER's identifying and making available to CONTRACTOR copies of reports of explorations and tests of subsurface conditions at the site and in existing structures which have been utilized by ENGINEER in preparing the Drawings and Specifications. 8.5 OWNER's responsibilities in respect of purchasing and maintaining liability and property insurance are set forth to paragraphs 5.5 througb 5.8. 8.6 OWNER is obligated to execute Change Orders as indicated in para- grapb 10.4. 8.7 OWNER's responsibility in respect of certain inspections, tests and approvals is set forth in paragraph 13.4. 8.8 In connection with OWNER's right to stop Work or suspend Work, see paragraphs 13.10 and 15.1. Paragraph 15.2 deals with OWNER's right to terminate services of CONTRACTOR wader certain circumstances. ARTICLE 9--ENGINEER'S STATUS DURING CONSTRUCTION Owner's Representative: 9.1 ENGINEER will be OWNER's representative during the construction period. The duties and responsibilities and the limitations of authority of ENGINEER as OWNER's representative during construction are set forth in the Contract Documents and shall not be extended without written consent of OWNER and ENGINEER. Visits to Site: 9.2 ENGINEER will make visits to the site•at intervals appropriate to the various stages of construction to observe the progress and quality of the executed Work and to determine, in general, if the Work is proceeding in accordance with the Contract Documents. ENGINEER will not be required to make exhaustive or GC -27 e 1 , [SKY. HUSTON i ASSOCIATES. INC. continuous on -site inspections to check the quality or quantity of the Work. ENGINEER'S efforts will be directed toward providing for OWNER a greater degree of confidence that the completed Work will conform to the Contract Documents. On the basis of such visits and on -site observations as an experienced and qualified design professional, ENGINEER will keep OWNER informed of the progress of the Work and will endeavor to guard OWNER against defects and deficiencies in the Work. Project Representation: 9.3 If OWNER and ENGINEER agree, ENGINEER will furnish a Resident Project Representative to assist ENGINEER in observing the performance of the Work. The duties, responsibilities and limitations of authority of any such Resident Project Representative and assistants will be provided in the Supplementary Conditions. If OWNER designates another agent to represent OWNER at the site who is not ENGINEER'S agent or employee the duties, responsibilities and limita- tions of authority of such other person will be as provided in the Supplementary Conditions. Clarifications and Interpretations: 9.4 ENGINEER will issue with reasonable promptness such written clarifi- cations or interpretations of the requirements of the Contract Documents On the form of Drawings or otherwise( as ENGINEER may determine necessary, which shall be consistent with or reasonably inferable from the overall intent of the Contract Documents. If CONTRACTOR believes that a written clarification or interpreta- tion justifies an increase in the Contract Price or an extension of the Contract Time and the parties are unable to agree to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in Article 11 or Article 12. Authorized Variations fa Wank: 9.5 ENGINEER may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are consistent with the overall intent of the Contract Documents. These may be accomplished by a Field Order and will be binding on OWNER, and also on CONTRACTOR who shall perform the Work involved promptly. If CONTRACTOR believes that a Field Order justifies an increase in the Contract Price or an extension of the Contract Time and the parties are unable to agree as to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in Article 11 or It Rejecting Defective Wade 9.6 ENGINEER will have authority to disapprove or reject Work which ENGINEER believes to be defective, and will also have authority to require special GC -28 /SPEY. HUSTON t ASSOCIATES, INC. inspection or testing of the Work as provided in paragraph 13.9, whether or not the Work is fabricated, installed or completed. Shop Drawings, Change Orders and Payments: 9.1 In connection with ENGINEER's responsibility for Shop Drawings and samples, see paragraphs 623 through 629, inclusive. 9.8 In connection with ENGINEER'S responsibilities as to Change Orders, see Articles 10, 11 and 12. 9.9 In connection with ENGINEER's responsibilities in respect of Applica- tions for Payment, etc., see Article 14. Determinations for Unit Prices: 9.10 ENGINEER will determine the actual quantities and classifications of Unit Price Work performed by CONTRACTOR. ENGINEER will review with CONTRACTOR ENG1NEER's preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application for Payment or otherwise). ENGINEER's written decisions thereon will be final and binding upon OWNER and CONTRACTOR, unless, within ten days after the date of any such decision, either OWNER or CONTRACTOR delivers to the other party to the Agreement and to ENGINEER written notice of intention to appeal from such a decision. Decisions on Disputes: 9.11 ENGINEER will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other matters relating to the acceptability of the Work or the interpretation of the requirements of the Contract Documents pertaining to the performance and furnishing of the Work and claims wider Articles 11 and 12 in respect of changes in the Contract Price or Contract Time will be referred initially to ENGINEER in writing with a request for a formal decision in accordance with this paragraph, which ENGINEER wit render in writing within a reasonable time. Written notice of each such claim, dispute and other matter will be delivered by the claimant to ENGINEER and the other party to the Agreement promptly (but in no event later than thirty days) after the occurrence of the event giving rise thereto, and written supporting data will be submitted to ENGINEER and the other party within sixty days after such occurrence unless ENGINEER allows an additional period of time to ascertain more accurate data in support of the claim. • 9.12 When functioning as interpreter and judge under paragraphs 9.10 and 9.11, ENGINEER will not show partiality to OWNER or CONTRACTOR and will not be liable in connection with any interpretation or decision rendered in good faith in GC -29 1 1 1 1 1 1 1 1 1 1 1 .1 1 1 h ESKY. HUSTON i ASSOCIATES, INC. such capacity. The rendering of a decision by ENGINEER pursuant to para- graphs 9.10 and 9.11 with respect to any such claim, dispute or other matter (except any which have been waived by the making or acceptance of final payment as provided in paragraph 14.16) will be a condition precedent to any exercise by OWNER or' CONTRACTOR of such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect of any such claim, dispute or other matter. Limitations on ENCENEER's Rtspoasitiilities: 9.13 Neither ENGINEER'S authority to act under this Article 9 or elsewhere in the Contract Documents nor any derision made by ENGINEER in good faith either to exercise or not exercise such authority shall give rise to any duty or responsibility of ENGINEER to CONTRACTOR, any Subcontractor, any Supplier, or any other person or organization performing any of the Work, or to any surety for any of them. 9.14 Whenever in the Contract Documents the terms as ordered ", "as directed ", as required ", as allowed', as approved" or terms of like effect or import are used, or the adjectives 'reasonable , "suitable", 'acceptable", "proper' or "satisfactory" or adjectives of like effect or import are used to describe a requirement, direction, review or judgment of ENGINEER as to the Work, it is intended that such requirement, direction, review or judgment will be solely to evaluate the Work for compliance with the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to ENGINEER any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.15 or 9.16. 9.15 ENGINEER will not be responsible for CONTRACTOR'S means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, and ENGINEER will not be responsible for CONTRAC- TOR's failure to perform or furnish the Work in accordance with the Contract Documents. 9.16 ENGINEER will not be responsible for the acts or omissions of CON- TRACTOR or of any Subcontractor, any Supplier, or of any other person or organization performing or furnishing any of the Work. ARTICLE 10— CHANGES III TEE WORK 10.1 Without invalidating the Agreement and without notice to any surety, OWNER may, at any time or from time to time, order additions, deletions or revisions in the Work; these will be authorized by a Written Amendment, a Change Order, or a Work Directive Change. Upon receipt of any such document, CONTRACTOR shall promptly proceed with the Work involved which will be GC 30 e EUPEY. HUSTON & ASSOCIATES. INC. performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). 10.2 if ;OWNER and CONTRACTOR are unable to agree as to the extent, if any, of an increase or decrease in the Contract Price or an extension or shortening of the Contract Time that should be allowed as • result of a Work Directive Change, a claim may be made therefor as provided in Article 11 or Article 12. 10.3 CONTRACTOR shall not be entitled to an increase in the Contract Price or an extension of the Contract Time with respect to any Work performed that is not required by the Contract Documents as amended, modified and supplemented as provided in paragraphs 3.4 and 3.5, except in the case of an emergency as provided in paragraph 6.22 and except in the case of uncovering Work as provided in paragraph 13.9. 10.4 OWNER and CONTRACTOR shall execute appropriate Change Orders (or Written Amendments) covering: 10.4.1 changes in the Work which are ordered by OWNER pursuant to para- graph 10.1 are required because of acceptance of defective Work under paragraph 13.13 or correcting defective Work under paragraph 13.14, or are agreed to by the parties; 10.4.2 changes in the Contract Price or Contract Time which are agreed to by the parties; and 10.4.3 changes in the Contract Price or Contract Time which embody the substance of any written decision rendered by ENGINEER pursuant to paragraph 9.11; provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance with the provisions of the Contract Documents and applicable Laws and Regulations, but during any such appeal, CONTRACTOR shall carry on the Work and adhere to the progress schedule as provided in paragraph 6.29. 10.5 If notice of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time) is required by the provisions of any Bond to be given to a surety, the giving of any such notice will be CONTRACTOR's responsibility, and the amount of each applicable Bond will be adjusted accordingly. GC-31 1 e ESPET. HUSTON & ASSOCIATES, INC. 1 1 1 ,1 ARTICLE 11— CHANGE OF CONTRACT PRICE 31.3 The Contract Price constitutes the total compensation (subject to authorized adjustments) payable to CONTRACTOR for performing the Work. All ' duties, responsibilities and obligations assigned to or undertaken by CONTRACTOR shall be at his expense without change in the Contract Price. ' 112 The Contract Price may only be changed by a Change Order or by a Written Amendment. Any Maim for an increase or decrease in the Contract Price shall be based on written notice delivered by the party maldng the claim to the other party and to ENGINEER promptly (but in no event later than thirty days) after ' the occurrence of the event giving rise to the claim and stating the general nature of the claim. Notice of the amount of the claim with supporting data shall be delivered within sixty days after such occurrence (unless ENGINEER allows an ' additional period of time to ascertain more accurate data in support of the claim) and shall be accompanied by claimant's written statement that the amount claimed covers all known amounts (direct, indirect and consequential) to which the claimant is entitled as • result of the occurrence of said event. All claims for adjustment in ' the Contract Price shall be determined by ENGINEER in accordance with para- graph 9.11 if OWNER and CONTRACTOR cannot otherwise agree on the amount involved. No claim for an adjustment in the Contract Price will be valid if not submitted in accordance with this paragraph 11.2. 11.3 The value of any Work covered by a Change Order or of any claim for an increase or decrease in the Contract Price shall be determined in one of the 1 following ways: 11.3.1 Where the Work involved is covered by trait prices contained in the Contract Documents, by application of unit prices to the quantities of the items involved (subject to the provisions of paragraphs 11.9.1 through 11.9.3, inc)usive). 1 1 1 1 11.3.2 By mutual acceptance of a lump stun (which may include an allowance for overhead and profit not necessarily in accordance with para- graph 11.6.2.1). 11.3.3 On the basis of the Cost of the Work (determined as provided in paragraphs 11.4 and 11.5) plus a CONTRACTOR'' Fee for overhead and profit (determined as provided in paragraphs 11.6 and 11.7). Cost of the Work IIA The term Cost of the Work means the sum of -all costs necessarily incurred and paid by CONTRACTOR in the proper performance of the Work. Except GC 32 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h [SPEY. HUSTON a ASSOCIATES. INC. as otherwise may be agreed to in writing by OWNER, such costs shall be in amounts no higher than those prevailing in the locality of the Project, shall include only the following items and shall not include any of the costs itemized in paragraph 11.5. 11.4.1 Payroll costs for employees in the direct employ of CONTRACTOR in the performance of the Work under schedules of job classifications agreed upon by OWNER and CONTRACTOR. Payroll costs for employ- ees not employed full time on the Work shall be apportioned on the basis of their time spend on the Work. Payroll costs shall include, but not be limited to, salaries and wages plus the cost of fringe benefits which shall include social security contributions, unemployment, excise and payroll taxes, workers' or workmen's compensation, health and retirement bene- fits, bonuses, sick leave, vacation and holiday pay applicable thereto. Such employees shall include superintendents and foremen at the site. The expenses of performing Work after regular working boors, on Saturday, Sunday or legal holidays, shall be included in the above to the extent authorised by OWNER. 11.4.2 Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Sup- pliers' field services required in connection therewith. All cash discounts shall accrue to CONTRACTOR unless OWNER deposits funds with CONTRACTOR with which to make payments, in which case the cash discounts shall accrue to OWNER. All trade discounts, rebates and refunds and al1 returns from sale of surplus materials and equipment shall accrue to OWNER, and CONTRACTOR sbaf make provisions so that they may be obtained. 11.4.3 Payments made by CONTRACTOR to the Subcontractors for Work performed by Subcontractors. If required by OWNER, CONTRACTOR shall obtain competitive lads from Subcontractors acceptable to CON- TRACTOR and shall deliver such bids to OWNER who will then deter- mine, with the advice of Engineer, which bids wi11 be accepted. If a subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work Plus a Fee, the Subcontractor's Cost of the Work shall be determined in the same manner as CONTRACTOR'S Cost of the Work. All subcontracts shall be subject to the other provisions of the Contract Documents insofar as applicable. 11.4.4 Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys and accountants) employed for services specifically related to the Work. GC -33 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h ESPEY. HUSTON i ASSOCIATES. INC. 11.4.5 Supplemental costs including the following: 11.4.5.1 The proportion of necessary transportation, travel and subsistence expenses of CONTRACTOR'S employees incurred in discharge of duties connected with the Work. 11.4.52 Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office and temporary facilities at the site and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost less market value of such items used but not consumed which remain the property of CONTRACTOR. 11 .4.5.3 Rentals of all construction equipment and machinery and the parts thereof whether rented from CONTRACTOP or others in accord- ance with rental agreements approved by OWNER with the advice of ENGINEER, and the costs of transportation, loading, unloading, installation, dismantling and removal thereof - -all in accordance with terms of said rental agreements. The rental of any such equipment, machinery or parts shall cease when the use thereof is no longer necessary for the Work. 11.4.5.4 Sales, consumer, use or similar taxes related to the Work, and for which CONTRACTOR is liable, imposed by Laws and Regulations. 11.4.5.5 Deposits lost for causes other than negligence of CONTRACTOR, any Subcontractor or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses. 11 .4.5.6 Losses and damages (and related expenses), not compensated by insurance or otherwise, to the Work or otherwise sustained by CONTRACTOR in connection with the performance and furnishing of the Work (except losses and damages within the deductible amounts of property insurance established by OWNER in accord- ance with paragraph 5.9), provided they have resulted from causes other than the negligence of CONTRACTOR, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of OWNER. No such losses, damages and expenses shall be included in the Cost of the Work for the purpose of determining CONTRAC- TOR's Fee. If, however, any such loss or damage requires reconstruction and CONTRACTOR is placed in charge thereof, CONTRACTOR shall be paid for services a fee proportionate to that stated in paragraph 11.62. GC -34 1 1 . 1 1 1 1 1 1 1 1 1 1 h ESPIY. HUSTON a ASSOCIATES, INC. 11.4.5.7 The cost of utilities, fuel and sanitary facilities at the site. 11.4.5.8 Minor expenses such as telegrams, long distance . telephone calls, telephone service at the ate, expressage and similar petty cash Hems in connection with the Work. 11.4.5.9 Cost of premiums for additional Bonds and *Intranet required because of changes in the Work and premiums for property insurance coverage within the limits of the deductible amounts established by OWNER in accordance with paragraph 5.9. 11.5 The term Cost of the Work shall not include any of the following: 11.5.1 Payroll costs and other compensation of CONTRACTOR'; officers, executives, principals (of partnership and sole proprietorships), general managers, engineers, architects, estimators, attorneys, auditors, ac- countants, purchasing and contracting agents, expediters, timekeepers, clerks and other personnel employed by CONTRACTOR whether at the site or in CONTRACTOR'& principal or a branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in paragraph 11.4.1 or specifically covered by paragraph 11 .4.4 - -all of which are to be con- sidered administrative costs covered by the CONTRACTOR'' Fee. 11.5.1 Expenses of CONTRACTOR'; principal and branch offices: other than CONTRACTOR'; office at the site. 11.5.3 Any part of CONTRACTOR'S capital expenses, including interest on r*ONTRACTOR's capital employed for the Work and charges against CONT ACTOR for delinquent payments. 11.5.4 Cost of premiums for all Bonds and for all insurance whether or not CONTRACTOR is required by the Contract Documents to purchase and maintain the same (except for the cost of premiums covered by subparagraph 11.4.5.9 above). 11.5.5 Costs due to the negligence of CONTRACTOR, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to the correction of defective Work, disposal of materials or equipment wrongly supplied and m good any damage to property. 11.5.6 Other overhead or general expense costs of any kind and the costs of any item not specifically and expressly included in paragraph 11.4. • GC -35 -1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 UPCY. HUSTON a ASSOCIATES. INC. CONTRACTOR's Fee: 11.6 The CONTRACTOR'' Fee allowed to CONTRACTOR for overhead and profit 'ball be determined as follows: 11.6.1 a mutually acceptable fixed fee; or if none can be agreed upon, 11.62 a fee based on the following percentages of the various portions of the Cost of the Work: 11.6.2.1 for costs incurred under paragraphs 11.4.1 and 11.4.2, the CON- TRACTOR'S Fee shall be fifteen percent; 11.622 for costs incurred under paragraph 11 .4.3, the CONTRACTOR'S Fee shall be five percent; and if a subcontract is on the basis of Cost of the Work Plus • Fee, the maximum allowable to CON- TRACTOR on account of overhead and profit of all Subcontractors shall be fifteen percent; 11.62.3 no fee shall be payable on the basis of costs itemised under paragraphs 11.4.4, 11.4.5 and 11.5; 11.6.2.4 the amount of credit to be allowed by CONTRACTOR to OWNER for any such change which results in a net decrease in cost will be the amount of the actual net decrease plus a deduction in CON - TRACTOR's Fee by an amount equal to ten percent of the net decrease; and 11.6.2.5 when both additions and credits ere involved in any one change, the adjustment in CONTRACTOR'S Fee shall be computed on the basis of the net change in accordance with paragraphs 11.6.2.1 through 11.6.2.4, inclusive. 11.7 Whenever the cost of any Work is to be determined pursuant to paragraph 11.4 or 11.5, CONTRACTOR will submit in form acceptable to ENGI- NEER an itemised cost breakdown together with supporting data. Cash Allowances: 11.8 It is understood that CONTRACTOR has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be done by such Subcontractors or Suppliers and for such as within the limit of the allowances as may be acceptable to ENGINEER. CONTRACTOR agrees that: GC -36 1 1 1 1 1 1 1 1 1 1 1 1 1 e ES►EY. HUSTON a ASSOCIATES, INC. 11.8.1 The allowances include the cost to CONTRACTOR (less any applicable trade discounts) or materials and equipment required by the allowances to be delivered at the site, and all applicable taxes; and 11.82 CONTRACTOR'' costs for tmloading and handling on the site, labor, installation costs, overhead, profit and other expenses contemplated for the allowances have been included in the Contract Price and not in the allowances. No demand for additional payment on account of any thereof will be valid. Prior to final payment, an appropriate Change Order will be issued as recommended by ENGINEER to reflect actual amounts due CONTRACTOR on account of Work covered by allowances, and the Contract Price shall be corre- spondingly adjusted. Unit Price Work: 11.9.1 Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to • the sum of the established unit prices for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by CON- TRACTOR will be made by ENGINEER in accordance with pars_ graph 9.10. 11.9.2 Each unit price will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR'. overhead and profit for each separately identified item. 11.9.3 Where the quantity of any item of Unit Price Work performed by CONTRACTOR differs materially and significantly from the estimated quantity of such item indicated in the Agreement and there is no corresponding adjustment with respect to any other item of Work and if CONTRACTOR believes that CONTRACTOR has incurred additional expense as a result thereof, CONTRACTOR may make a claim for an increase in the contract Price in accordance with Article II if the parties are unable to agree as to the amount of any such increase. GC 37 1 e 1 1 1 1 1 1 1 1 1 1 1 : 1 1 1 1 1 1 h ISM. HUSTON & ASSOCIATES, INC. ARTICLE 12-- CRANGE OF CONTRACT TIME 12.1 The Contract Time may only be changed by a Change Order or a Written Amendment. Any claim for an extension or shortening of the Contract Time shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty days) after the occurrence of the event giving rise to the claim and stating the general nature of the claim. Notice of the extent of the claim with supporting data shall be delivered within sixty days after such occurrence (unless ENGINEER allows an additional period of time to ascertain more accurate data in support of the claim) and shall be accompanied by the claimant's written statement that the adjustment claimed is the entire adjustment to which the claimant has reason to believe it is entitled as a result of the occurrence of said event. All claims for adjustment in the Contract Time shall be determined by ENGINEER in accordance with paragraph 9.11 if OWNER and CONTRACTOR cannot otherwise agree. No claim for an adjustment in the Contract Time will be valid if not submitted in accordance with the require- ments of this paragraph 12.1. 12.2 The Contract Time will be extended in an amount equal to time lost due to delays beyond the control of CONTRACTOR if a claim is made therefor as provided in paragraph 12.1. Such delays shall include, but not be limited to, acts or neglect by OWNER or others performing additional work as contemplated by Article 7, or to fires, floods, labor disputes, epidemics, abnormal weather conditions or acts of God. 12.3 All time limits stated in the Contract Documents are of the essence of the Agreement. The provisions of this Article 12 shall not exclude recovery for damages (including but not limited to fees and charges of engineers, architects, attorneys and other professionals and court and arbitration costs) for delay by either party. ARTICLE 13-- WARRANTY AND GUARANTEE; TESTS AND 1TNSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK Warranty and Guarantee: 13.1 CONTRACTOR warrants and guarantees to OWNER and ENGINEER that all Work will be in accordance with the Contract Documents and wit not be defective. Prompt notice of all defects shall be given to CONTRACTOR. All defective Work, whether or not in place, may be rejected or accepted as provided in this Article 13. GC -38 1 e 1 1 1 1 1 1 1 1 1 1 . 1 1 1 h ES►CY. HUSTON & ASSOCIATES. INC. Access to Work: IIncovering Work 13.2 ENGINEER and ENGINEER'' representatives, other representatives of OWNER, testing agencies and governmental agencies with jurisdictional interests will have access to the Work at reasonable times for their observation, inspecting and testing. CONTRACTOR shall provide proper and safe conditions for such access. Tests and Inspections: 13.3 CONTRACTOR shall give ENGINEER timely notice of readiness of the Work for all required inspections, tests or approvals. 13.4 If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) to specifically be inspected, tested or approved, CONTRAC- TOR shall assume full responsibility therefor, pay all costs in connection therewith and furnish ENGINEER the required certificates of inspection, testing or approval. CONTRACTOR shall also be responsible for and shall pay all costs in connection with any inspection or testing required in connection with OWNER or ENGDlEER's acceptance of a Supplier of materials or equipment proposed to be incorporated in the Work, or of materials or equipment submitted for approval prior to CON- TRACTOR'S purchase thereof for the incorporation in the Work. The cost of all inspections, tests and approvals in addition to the above which are required by the Contract Documents shall be paid by OWNER (unless otherwise specified). 13.5 All inspections, tests or approvals other than those required by Laws or Regulations of any public body having jurisdiction shall be performed by organisa- tions acceptable to OWNER and CONTRACTOR (or by ENGINEER if an specified). 13.6 If any Work (including the work of others) that is to be inspected, tested or approved is covered without written concurrence of ENGINEER, it must, if requested by ENGINEER, be uncovered for observation. Such tmcovering shall be at CONTRACTOR's expense unless CONTRACTOR has given ENGINEER timely notice of CONTRACTOR'' intention to cover the same and ENGINEER has not acted with reasonable promptness in response to such notice. 13.7 Neither observations by ENGINEER nor inspections, tests or approvals by others shall relieve CONTRACTOR from CONTRACTOR'' obligations to perform the Work in accordance with the Contract Documents. 13.6 • If any Work is covered contrary to the written request of ENGINEER, it must, if requested by ENGINEER, be uncovered for ENGINEER'S observation and replaced at CONTRACTOR's expense. GC -39 e a -, 1 I (SPEY. HUSTON i ASSOC ATEI. INC. 13.9 If ENGINEER considers it necessary or advisable that covered Work be observed by ENGINEER or inspected or tested by others, CONTRACTOR, at ENGINEER'' request, shall uncover, expose or otherwise make available for obser- vation, inspection or testing as ENGINEER may require, that portion of the Work in question, furnishing all necessary labor, material and equipment. If it is found that such Work is defective, CONTRACTOR shall bear all direct, indirect and conse- quential costs of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction (including but not limited to fees and charges of engineers, architects, attorneys and other professionals), and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, may make a claim therefor as prodded in Article 11. 1f, however, such Work is not found to be defective, CONTRACTOR shall be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction; and, if the parties are unable to agree as to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in Articles 11 and 12. Owner May Stop the Work: 13.10 If the Work is defective, or CONTRACTOR fails to supply sufficient skilled workers or suitable materials or equipment, or falls to furnish or perform the Work in such a way that the completed Work will conform to the Contract Documents, OWNER may order CONTRACTOR to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of OWNER to stop the Work shall not give rise to any duty on the part of OWNER to exercise this right for the benefit of CONTRACTOR or any other party. Correction or Removal of Defective work: 13.11 If required by ENGINEER, CONTRACTOR shall promptly, as directed, either correct all defective Work, whether or not fabricated, installed or completed, or, if the Work has been rejected by ENGINEER, remove it from the site and replace it with nondefective Work. CONTRACTOR shall bear all direct, indirect and consequential costs of such correction or removal (including but not limited to fees and charges of engineers architects, attorneys and other professionals) made necessary thereby. One Year Correction Period: 13.12 If within one year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, any Work is found to be defective, CONTRACTOR shall promptly, without cost to OWNER and in accordance with OWNER's written instructions, either correct such defective Work, or, if it has been GC-40 1 e 1 1 1 1 1 1 1 1 1 1 1 1 t 1 1 1 h ESKY. HUSTON a ASSOCIATES. INC. rejected by OWNER, remove it from the site and replace it with bondef ective Work. If CONTRACTOR does not promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss ce damage, OWNER may have the defective Work corrected or the rejected Work removed and replaced, and all direct, indirect and consequential costs of such removal and replacement (including but not limited to fees and charges of engineers, architects, attorneys and other professions) will be paid by CONTRACTOR. In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of at the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications or by Written Amendment. Acceptance of Defective Wort: 13.13 1f, instead of requiring correction or removal and replacement of defective Work, OWNER (and, prior to ENGINEER'S recommendation of final payment, also ENGINEER) prefers to accept it, OWNER may do so. CONTRACTOR shall bear all direct, indirect and consequential costs attributable to OWNER'S evaluation of and determination to accept such defective Work (such costs to be approved by ENGINEER as to reasonableness and to include but not be limited to fees and charges of engineers, architects, attorneys and other professionals). If any such acceptance occurs prier to ENGINEER': recommendation of final payment, a Change Order will be issued incorporating the necessary reviaion< in the Contract Documents with respect to the Work; and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree es to the amount thereof, OWNER may make a claim therefor as provided in Article 11. If the acceptance occurs after such recommendation, an appropriate amount will be paid by CONTRACTOR to OWNER. OWNER May Correct Defective Work: 13.14 If CONTRACTOR fails within a reasonable time after written notice of ENGINEER to proceed to correct and to correct defective Work or to remove and replace rejected Work as required by ENGINEER in accordance with para- graph 13.11, or if CONTRACTOR fails to perform the Work in accordance with the Contract Documents, or if CONTRACTOR fails to comply with any other provision of the Contract Documents, OWNER may, after seven days' written notice to CONTRACTOR, correct and remedy any such deficiency. In exercising the rights and remedies under this paragraph, OWNER shall proceed expeditiously. To the extent necessary to complete corrective and remedial action, OWNER may exclude CONTRACTOR from all or part of the ate, take possession of all oe part of the Work, and suspend CONTRACTOR'S services related thereto, take possession of CONTRACTOR': tools, appliances, construction equipment and machinery at the site and incorporate in the Work all materials and equipment stored at the site or For which OWNER has paid CONTRACTOR but which are stored elsewhere. CONTRACTOR shall allow OWNER, OWNER's representatives, agents and employ- ees such access to the site as may be necessary to enable OWNER to exercise the GC-41 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 h ESPEY. HUSTON L ASSOCIATES. INC. rights and remedies under this paragraph. All direct, indirect and consequential costs of OWNER in exercising such rights and remedies will be charged against CONTRACTOR in an amount approved as to reasonableness by ENGINEER, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and OWNER shaU be entitled to an appropriate decrease in the Contract Price, and if the parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article 11. Such direct, indirect and consequential costs will include but not be limited to fees and charges of engineers, architects, attorneys and other professionals, all court and arbitration costs and all costs of repair and replacement of work of others destroyed or damaged by correction, removal ce replacement of CONTRACTOR'. defective Work. CONTRACTOR shall not be allowed an extension of the Contract Time because of any delay in performance of the Work attributable to the exercise by OWNER of OWNER'S rights and remedies hereunder. Schedule of Values: ARTICLE 14 —PAYMENTS TO CONTRACTOR AND COMPLETION 14.1 The schedule of values established as provided in paragraph 2.9 will serve as the basis for progress payments and will be incorporated into • form of Application for Payment acceptable to ENGINEER. Progress payments oo account of Unit Price Work will be based on the number of tmits completed. Application for Progress Payment: 14.2 At least twenty days before each progress payment is scheduled (but not more often than once a'month), CONTRACTOR shall submit to ENGINEER for review an Application for Payment filled and signed by CONTRACTOR covering the Work completed as of the date of the Application and accompanied by suck supporting documentation as is required by the Contract Documents. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that OWNER has received the materials and equipment free and clear of all liens, charges, security interests and =cumbrances (which are hereinafter in these General Conditions referred to as 'Liens') and evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect OWNER'S interest therein, all of which will be satisfactory to OWNER. The amount of retainage with respect to progress payments will be as stipulated in the Agreement. GC-42 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h WET. HUSTON a ASSOCIATES. INC. CONTRACTOR'' Warranty of Title: 14.3 CONTRACTOR warrants and guarantees that title to all Work, materials and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to OWNER no later than the time of payment free and clear of all Liens. Review of Applications for Progress Payment: 14.4 ENGINEER will, within ten days after receipt of each Application for Payment, either indicate in writing a recommendation of payment and present the Application to OWNER, or return the Application to CONTRACTOR indicating in writing ENGINEER's reasons for refusing to recommend payment. In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application. Ten days after presentation of the Application for Payment with ENGINEER's recommendation, the amotmt recommended will (subject to the pro- visions of the last sentence of paragraph 14.7) become due and when due will be paid by OWNER to CONTRACTOR. 14.5 ENGINEER's recommendation of any payment requested in an Applica- tion for Payment will constitute a representation by ENGINEER to OWNER, based on ENGINEER'S on -site observations of the Work in progress as an experienced and qualified design professional and on ENGINEER's review of the Application for Payment and the accompanying data and schedules that the Work has progressed to the point indicated; that, to the best of ENGINEER'S knowledge, information and belief, the quality of the Work is in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents, to a final determination of quantities and classifications for Unit Price Work under paragraph 9.10, and to any other qualifications stated in the recommendation); and that CONTRACTOR is entitled to payment of the amount recommended. However, by recommending any such payment, ENGINEER will not thereby be deemed to have represented that exhaustive or continuous on -site inspections have been made to check the quality or the quantity of the Work beyond the responsibilities specifically assigned to ENGINEER in the Contract Documents or that there may not be other matters or issues between the parties that might entitle CONTRACTOR to be paid additionally by OWNER or OWNER to withhold payment to CONTRACTOR. 14.6 ENGINEER'S recommendation of final payment will constitute an addi- tional representation by ENGINEER to OWNER that the conditions precedent to CONTRACTOR's being entitled to final payment as set forth in paragraph 14.13 have been fulfilled. 14.7 ENGINEER may refuse to recommend the whole or any part of any payment if, in ENGINEER'S opinion, it would be incorrect to make such GC-43' 1 1 1 1 1 1 1 1 1 1 e 1f1 . w 0 1 ISM, HUSTON i ASSOCIATES, INC. representations to OWNER. ENGINEER ma also refuse to recommend any such payment, or, because of subsequently discovered evidence of the results of subse- quent inspections or tests, nullify any such payment previously recommended, to such extent as may be necessary in ENGINEER'S opinion to protect OWNER from loss because: - 14.7.1 the Work is defective, or completed Work has been damaged requiring correction or replacement, 14.7.2 the Contract Price has been reduced by Written Amendment or Change Order, 14.7.3 OWNER has been required to correct defective Work or complete Work in accordance with paragraph 13.14, or 14.7.4 of ENGINEER'S actual knowledge of the occurrence of any of the events enumerated in paragraphs 152.1 through 15.2.9 inclusive. OWNER may refuse to make payment of the full amount recommended by ENGINEER because claims have been made against OWNER on account of CON - TRACTOR's performance or furnishing of the Work or Liens have been filed in connection with the Work or then are other items entitling OWNER to a set -off against the amount recommended, but OWNER must give CONTRACTOR immediate written notice (with a copy to ENGINEER) stating the reasons for such action. Substantial Completion 14.8 When CONTRACTOR considers the entire Work ready for its intended use, CONTRACTOR shall notify OWNER and ENGINEER in writing that the entire Work is substantially complete (except for items specifically listed by CONTRAC- TOR as incomplete) and request that ENGINEER issue a certificate of Substantial Completion. Within a reasonable time thereafter, OWNER, CONTRACTOR and ENGINEER shall make an inspection of the Work to determine the status of completion. If ENGINEER does not consider the Work substantially complete, ENGINEER will notify CONTRACTOR in writing giving the seasons therefor. If ENGINEER considers the Work substantially complete, ENGINEER will prepare and deliver to OWNER a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment. OWNER shall have seven days after receipt of the tentative certificate during which to make written objection to ENGINEER as to any provisions of the certificate or attached list. If, after considering such objections, ENGINEER concludes that the Work is not substantially complete, ENGINEER will within fourteen days after submission of the tentative certificate to OWNER notify CONTRACTOR in writing, stating the reasons therefor. If, after consideration of OWNER's objections, ENGINEER considers the Work substantially complete, ENGINEER will within said fourteen days GC-44 1 1 1 1 1 1 1 1 1 1 1 1 1 e ESPEY. HUSTON II ASSOCIATES. INC. + GC-45 execute and deliver to OWNER and .CONTRACTOR a definitive certificate of Substantial Completion (with'• revised tentative list of items to be completed or corrected) reflecting such changes from the tentative certificate as ENGINEER believes justified after consideration of any objections from OWNER. At the time of delivery of the tentative certificate of Substantial Completion, ENGINEER will deliver to OWNER and CONTRACTOR a written recommendation as to division of responsibilities pending final payment between OWNER and CONTRACTOR with respect to security, operation, safety, maintenance, beat, utilities, insurance and warranties. Unless OWNER and CONTRACTOR agree otherwise in writing and so inform ENGINEER prior to ENGINEER's issuing the definitive certificate of Substantial Completion, ENGINEER'. aforesaid recommendation will be binding on OWNER and CONTRACTOR until final payment. 14.9 OWNER shall have the right to exclude CONTRACTOR from the Work after the date of Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list. Partial Utilisation: 14.10 Use by OWNER of any finished part of the Work, which has specifically been identified in the Contract Documents, or which OWNER, ENGINEER and CONTRACTOR agree constitutes • separately functioning and usable part of the Work that can be used by OWNER without significant interference with CON- TRACTOR'' performance of the remainder of the Work, may be accomplished prior to Substantial Completion of all the Work subject to the following: 14.10.1 OWNER at any time may request CONTRACTOR in writing to permit OWNER to use any such part of the Work which OWNER believes to be ready for its intended use and substantially complete. If CONTRACTOR agrees, CONTRACTOR will certify to OWNER and ENGINEER that said part of the Work is substantially complete and request ENGINEER to issue • certificate of Substantial Completion for that part of the Work. CONTRACTOR at any time may notify OWNER and ENGINEER in writing that CONTRACTOR considers any such part of the Work ready for its intended use and substantially complete and request ENGINEER to issue a certificate of Substantial Completion for that part of the Work. Within a reasonable time after either such request, OWNER, CONTRACTOR and ENGINEER shall make an inspection of that part of the Work to determine its status of completion. If ENGINEER does not consider that part of the Work to be substantially complete, ENGINEER will notify OWNER and CONTRACTOR in writing, giving the reasons therefor. If ENGINEER considers that part of the Work to be substan- tially complete, the provisions of paragraphs 14.8 and 14.9 will apply with respect to certification of Substantial Completion of that part of the Work and the division of responsibility in respect thereof and access thereto. 1 e 1 1 ESPEY, HUSTON & ASSOCIATES, INC. 1 1 1 1 1 1 1 1 1 1 1 1 1 .1 1 14.10.2 OWNER may at any time request CONTRACTOR in writing to permit OWNER to take over operation of any such part of the Work although it is not substantially complete. A copy of such request will.be sent to ENGINEER and within a reasonable time thereafter OWNER, CON- TRACTOR and ENGINEER shall make an inspection of that part of the Work to determine its status of completion and will prepare a list of the items remaining to be completed or corrected thereon before final payment. 1f CONTRACTOR does not object in writing to OWNER and ENGINEER that such part of the Work is not ready for separate operation by OWNER, ENGINEER will finalise the list of items to be completed or corrected and will deliver such list to OWNER and CONTRACTOR together with a written recommendation as to the division of responsibilities pending final payment between OWNER and CONTRACTOR with respect to security, operation, safety, maintenance, utilities, insurance, warranties and guarantees for that part of the Work which will become binding upon OWNER and CONTRACTOR at the time when OWNER takes over such operation (unless they shall have otherwise agreed in writing and so informed ENGINEER). During such operation and prior to Substantial Completion of such part of the Work, OWNER shall allow CONTRACTOR reasonable access to complete or correct items on said list and to complete other related Work. 14.10.3 No occupancy or separate operation of part of the Work will be accomplished prior to compliance with the requirements of para- graph 5.15 in respect of property insurance. Final Inspection: 14.11 Upon written notice from CONTRACTOR that the entire Work or an agreed portion thereof is complete, ENGINEER will make a final inspection with OWNER and CONTRACTOR and will notify CONTRACTOR in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. CONTRACTOR shall immediately take such measures as are necessary to remedy such deficiencies. Final Application for Payment: 14.12 After CONTRACTOR has completed all such corrections to the satis- faction of ENGINEER and delivered all maintenance and operating instructions, schedules, guarantees, Bonds, certificates of inspection, marked -up record docu- ments (as provided in paragraph 6.19) and other documents - -all as required by the Contract Documents, and after ENGINEER has indicated that the Work is accept- able (subject to the provisions of paragraph 14.16), CONTRACTOR may make application for final payment following the procedure for progress payments. The final Application for Payment shall be accompanied by all documentation called for in the Contract Documents, together with complete and legally effective releases or GC-46 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h ESPtY. HUSTON & ASSOCIATES, INC. waivers (satisfactory to OWNER) of all Liens arising out of or filed in connection with the Work. In lieu thereof and as approved by OWNER, CONTRACTOR may furnish receipts or releues in full; an affidavit of CONTRACTOR that the releases and receipts include all labor, services, materials and equipment for which a Lien could be filed, and that all payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or OWNER's property might in any way be responsible, have been paid or otherwise satisfied; and consent of the surety, if any, to final payment. If any Subcontractor or Supplier fails to furnish a release or receipt in full, CONTRACTOR may furnish a Bond or other collateral satisfactory to OWNER to indemnify OWNER against any Lien. Final Payment and Acceptance: 14.13 If, on the basis of ENGINEER'S observation of the Work during construc- tion and final inspection, and ENGINEER's review of the final Application for Payment and accompanying documentation - -alt as required by the Contract Docu- ments, ENGINEER is satisfied that the Work has been completed and CONTRAC- TOR's other obligations under the Contract Documents have been fulfilled, ENGI- NEER will, within ten days after receipt of the final Application for Payment, indicate in writing ENGINEER'S recommendation of payment and present the Application to OWNER for payment. Thereupon, ENGINEER will give written notice to OWNER and CONTRACTOR that the Work is acceptable subject to the provisions of paragraph 14.16. Otherwise, ENGINEER will return the Application to CONTRACTOR, indicating in writing the reasons for refusing to recommend final payment, in which case CONTRACTOR shall make the necessary corrections and resubmit the Application. Thirty days after presentation to OWNER of the Application and accompanying documentation, in appropriate form and substance, and with ENGINEER'S recommendation and notice of acceptability, the amount recommended by ENGINEER will become due and will be paid by OWNER to CONTRACTOR. 14.14 If, through no fault of CONTRACTOR, final completion of the Work is significantly delayed and if ENGINEER so confirms, OWNER shall, upon receipt of CONTRACTOR'S final Application for Payment and recommendation of ENGINEER, and without terminating the Agreement, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by OWNER for Work not fully completed or corrected is less than the retaining stipulated in the Agreement, and if Bonds have been furnished as required in paragraph 5.1, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by CONTRACTOR to ENGINEER with the Application for such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. GC-47 I e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 i 1 h ESPEY, HUSTON 1 ASSOCIATES. INC. Contractor's Continuing Obligation GC-48 14.15 CONTRACTOR'S obligation to perform and complete the work in ac- cordance with the Contract Documents shall be absolute. Neither recommendation of any progress or final payment by ENGINEER, no the issuance of a certificate of Substantial Completion, nor' any payment by OWNER to CONTRACTOR under the Contract Documents, nor any use or occupancy of the Work or any part thereof by OWNER, nor any act of acceptance by OWNER no any failure to do so, nor any review and approval of a Shop Drawing or sample submission, nor the issuance of a notice of acceptability by ENGINEER pursuant to paragraph 14.13, nor any correc- tion of defective Work by OWNER will constitute an acceptance of Work not in accordance with the Contract Documents or a release of CONTRACTOR'S obliga- tion to perform the Work in accordance with the Contract Documents (except as provided in paragraph 14.16). • Waiver of Claim: 14.16 The making and acceptance of final payment will constitute: 14.16.1 a waiver of all claims by OWNER against CONTRACTOR, except claims arising from unsettled Liens, from defective Work appearing after final inspection pursuant to paragraph 14.11 or from failure to comply with the Contract Documents or the terms of any special guarantees specified therein; however, it will not constitute a waiver by OWNER of any rights in respect of CONTRACTOR'S continuing obligations under the Contract Documents; and 14.16.2 a waiver of all claims by CONTRACTOR against OWNER other than those previously made in writing and still unsettled. ARTICLE 1S SUSPENSION OF WORE AND TERIONATION Owner May Suspend Work: 15.1 OWNER may, at any time and without cause, suspend the Work or any portion thereof for a period of not more than ninety days by notice in writing to CONTRACTOR and ENGINEER which will fix the date on which Work will be resumed. CONTRACTOR shall resume the Work on the date so fixed. CONTRAC- TOR shall be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to any suspension if CONTRACTOR makes an approved claim therefore as provided in Articles 11 and 12. 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 h ESPEY. HUSTON L ASSOCIATES. INC. Owner May Terminate: 15.2 Upon the occurrence of any one of more of the - following events: 15.2.1 if CONTRACTOR commences a voluntary case tinder any chapter of the Bankruptcy Code (Title 11, United States Code), as now � hereafter in effect, or if CONTRACTOR takes any equivalent' or similar action by filing a petition or otherwise under any other federal or state law in effect at such time relating to the bankruptcy or insolvency; 15.2.2 if a petition is filed against CONTRACTOR tinder any chapter of the Bankruptcy Code as now cc hereafter in effect at the time of filing, or if a petition is filed seeking any such equivalent or similar relief against CONTRACTOR under any other federal or state law in effect at the time relating to bankruptcy or insolvency; 152.3 if CONTRACTOR makes a general assignment for the benefit of creditors; 15.2.4 if a trustee, receiver, custodian or agent of CONTRACTOR is appointed under applicable law or under contract, whose appointment or authority to take charge of property of CONTRACTOR is for the purpose of enforcing a Lien against such property or for the purpose of general administration of such property for the benefit of CONTRACTOR'S creditors; 15.2.5 if CONTRACTOR admits in writing an inability to pay its debts as they become due; 152.6 if CONTRACTOR persistently fails to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers ar suitable materials or equipment or failure to adhere to the progress schedule established under para- graph 2.9 as revised from time to time); 152.7 if CONTRACTOR disregards Laws or Regulations of any public body having jurisdiction; 152.8 if CONTRACTOR disregards the authority of ENGINEER; or 15.2.9 if CONTRACTOR otherwise violates in any substantial way any provi- sions of the Contract Documents; OWNER may, after giving CONTRACTOR (and the surety, if there be one) seven days' written notice and to the extent permitted by Laws and Regulations, terminate the services of CONTRACTOR, exclude CONTRACTOR from the cite and take GC-49 1 e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ESPEY, HUSTON 4 ASSOCIATEi, INC. possession of the Work and all of CONTRACTOR', tools, appliances, construction equipment and machinery at the site and use the same to the full extent they could be used by CONTRACTOR (without liability to CONTRACTOR for trespass or conversion), incorporate in the Work all materials and :equipment stored at the site or for which OWNER has paid CONTRACTOR but which are stored elsewhere, and finish the Work as OWNER may deem expedient. In such case, CONTRACTOR shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds the direct, indirect and consequential costs of completing the Work (including but not limited to fees and charges of engineers, architects, attorneys and other professional's and court and arbitration costs) such excess will be paid to CONTRACTOR. If such costs exceed such unpaid balance, CONTRACTOR shall pay the difference to OWNER.. Such costs incurred by OWNER will be approved as to reasonableness by ENGINEER and incorporated in a Change Order, but when exercising any rights or remedies under this paragraph, OWNER shall not be required to obtain the lowest price for the Work performed. 15.3 Where CONTRACTOR'S services have been so terminated by OWNER, the termination will not affect any rights or remedies of OWNER against CON- TRACTOR then existing of which may thereafter accrue. Any retention or payment of monies due CONTRACTOR by OWNER will not release CONTRACTOR from liability. 15.4 Upon seven days' written notice to CONTRACTOR and ENGINEER, OWNER may, without cause and without prejudice to any other right or remedy, elect to abandon the Work and terminate the Agreement. In such case, CON- TRACTOR shall be paid for an Work executed and any expense sustained pl reasonable termination expenses, which will include, but not be limited to, direct, indirect and consequential costs (including, but not limited to, fees and charges of engineers, architects, attorneys and other professionals and court and arbitration costs). Contractor May Stop Weak or Terminate: 15.5 If, through no act or fault of CONTRACTOR, the Work is suspended for a period of more than ninety days by OWNER m under an order of court or other public authority, or ENGINEER fails to act m any Application for Payment within thirty days after it is submitted, or OWNER fails for thirty days to pay CON- TRACTOR any sum finally determined to be due, the CONTRACTOR may, upon seven days' written notice to OWNER and ENGINEER, terminate the Agreement and recover from OWNER payment for all Work executed and any expense sustained plus reasonable termination expenses. In addition and in lieu of terminating the Agreement, if ENGINEER has failed to at on an Application for Payment or OWNER has failed to make any payment as aforesaid, CONTRACTOR may upon seven days' written notice to OWNER and ENGINEER stop the Work until payment of all amounts then due. The provisions of this paragraph shall not relieve CONTRACTOR of the obligations under paragraph 6.29 to carry on the Work in GC -50 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ESPCY, HUSTON & ASSOCIATES, INC. accordance with the progress schedule and without delay during disputes and disagreements with OWNER. ARTICLE 16- -ARETTRAT1ON 16.1 All claims, disputes and other matterfin'questlon between OWNER and CONTRACTOR arising out of, or relating to the Contract Documents or the breach thereof (except for claims which have been waived by 4be making or acceptance of final payment u provided by paragraph 14.16)'riid toe 'decided by artibration in accordance with the Construction Industry 'Arbitration Rules of the American Arbitration Association then obtaining subject to thelimititions of this Article 16. This agreement so to arbitrate and any other agreement or consent to arbitrate entered into in accordance herewith as provided in this Article 16 will be specific- ally enforceable under the prevailing law of any court laving jurisdiction. 162 No demand for arbitration of any claim, dispute or other matter that is required to be referred to ENGINEER initially for decision in accordance with paragraph 9.71 will be made until the earlier of {a) the date on which ENGINEER has rendered a decision or (b) the tenth day after Aire parties have presented their evidence to ENGINEER if a written decision bae not:been rendered by ENGINEER before that date. No demand fm arbitration 'of any 'such claim, dispute or other matter will be made later than thirty days after the date:on whicb ENGINEER has rendered a written decision in respect thereof in accordance with paragraph 9.11; and the failure to demand arbitration within said thirty days' period shall result in ENGINEER'S decision being final and binding upon OWNER- and CONTRACTOR. If ENGINEER renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but wiI:not supersede the arbitration proceedings, except where the decision is acceptable to tGe parties concerned. No demand for arbitration of any written decision of ENGINEER rendered in accord- ance with paragrapb 9.10 will be made later 4han - teri days after the party making such demand has delivered written notice 61 intention to appeal as provided in paragraph 9.10. 16.3 Notice of the demand for arbitration will be -filed in writing with the other party to the Agreement and with the American Arbitration Association, and a copy will be sent to ENGINEER for information. The demand for arbitration will be made within the thirty -day or ten -day period specified in paragraph 16.2, as applicable, and in all such cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no tweet shall any such demand be made after the date when institution of legal or etitiitable proceedings based on such claim, dispute or other matter in question would tee•barred the applicable statute of limitations. • 16.4 No arbitration arising out of or relating'tothe- Contract Documents shall include by consolidation, joinder or in any?otber: "manrirr any person or entity GC -51 1 e 1 1 1 1 1 1 1 1 .1 1 .1 1 1 1 1 ESPIY, HUSTON L ASSOCIATES, INC. (including ENGINEER, ENGINEER'' agents, employees or consultants) wbo is not • party to this contract unless: 16.4.1 the inclusion of such other person or entity is necessary if complete relief is to be afforded among those who are already parties to the arbitration, 2 , f• as 16.4.2 such other person or entity is substantially involved in a question of law or fact which is common to those who are already parties to the arbitration and which will arise in such proceedings, and s t - 4 , 16.4.3 the %written consent of the other person or entity sought to be included and of OWNER and CONTRACTOR has been obtained for such inclusion, which consent shall make specific reference to this paragraph; but no such consent shall constitute consent to arbitration of any dispute not specifically described in such consent or to arbitration with any party not specifically identified in such consent. 16.5 The award rendered by the arbitrators will be final, judgment may be entered upon it in any court having jurisdiction thereof, and will not be subject to modification or appeal except to the extent permitted by Sections 10 and 11 of the Federal Arbitration Act (9 D.S.C. i 110, 11). ARTICLE 17— MISCELLANEOUS Giving Notice 17.1 Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given 0 delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. Computation of Time: 172.1 When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation. 172.2 A calendar day of twenty -four hours measured from midnight to the next midnight shall constitute a day. GC -52 e ELPCY, MUSTON a ASSOCIATES, INC. General: 17.3 Should OWNER or CONTRACTOR suffer injury or damage to person or property because of any error, omission or act of the other party or of any of the other party's employees or agents or other for whose acts the other party is legally liable, claim will be made in writing to the other party within a reasonable time of the first observance of such injury or damage. The provisions of this paragraph 17.3 shall not be construed as a substitute for or a waiver of the provisions of any applicable statute of limitations or repose. 17.4 The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto, and, in particular but without limitation, the warranties, guarantees and obligations imposed upon CON- TRACTOR by paragraphs 6.30, 13.1, 13.12, 13.14, 14.3 and 15.2 and all of the rights and remedies available to OWNER and ENGINEER tberetmder, are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee or by other provisions of the Contract Documents, and the provisions of this paragraph will be effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right and remedy to which they apply. All representations, warranties and guaranteees made inthe Contract Documents will survive final payment and termination or completion of the Agreement. GC-53 SECTION 00800 - SUPPLEMENTARY CONDITIONS GENERAL: The provisions of this section of the specifications shall govern in the event of any conflict between them and the "General Conditions of Agreement." ARTICLE 2 -- PRELIMINARY MATTERS COPIES OF DOCUMENT: 2.2 Section 22, Copies of Documents, of the General Conditions is hereby modified as follows. Four (4) sets of Contract Documents shall be furnished to the CONTRACTOR, at no charge, for construction purposes. Additional copies may be obtained at cost of reproduction upon request. Cut sheets and one copy of field notes will be furnished to the proper inspection division of the City of Round Rock if required. ARTICLE 4 -- AVAILABILITY OF LANDS: PHYSICAL CONDITIONS: REFERENCE POINTS AVAILABILITY OF LANDS: 4.1 Section 4.1, Availability of Lands, of the General Conditions, is hereby modified to include the following. The OWNER will provide rights-of -way for the purpose of construction without cost to the CONTRACTOR. The Owner is in the process of finalizing easements, permits and site acquisition for lands upon which work is to be done. It is possible that delays on acquisition of some of the property owner's lands for easements may occur. In such cases, the Contractor shall schedule his work on easements and right-of -ways that already have been acquired while such easement acquisition procedures are in progress. No extra cost to Contractor shall be due by Owner for any delays caused by easement acquisition, but Owner may extend the calendar days of the contract, if delays occur. It shall be the responsibility of the CONTRACTOR, prior to the initiation of construction on easements through private property, to inform the property owner of his intent to begin construction. Before beginning construction in areas of public dedication, the CONTRACTOR shall inform the agency having jurisdiction in the area forty -eight (48) hours prior to initiation of the work. 00800 -1 PHYSICAL CONDITIONS: 4.2.1 Paragraph 4.2.1, Explorations and Reports, of the General Conditions is hereby modified to include the following: Explorations and Reports utilized by ENGINEER in preparation of Contract Documents are not to be construed as being a part of the Contract Documents. Such reports are presented as Information Available To Bidders and it is the Bidder's responsibility to inquire of ENGINEER if additional information is available, to make arrangements to review same prior to bidding and make his own determinations as to all physical conditions. Additional Information Available to Bidders: Geological Investigation for Proposed Brushy Creek Wastewater Line. Copies of this report are attached to the Bidding Documents or may be examined at the ofice of the Engineer during regular business hours. This report is not a part of the Contract Documents. EXISTING STRUCTURES: 4.2.2 Paragraph 4.22, Existing Structures, of the General Conditions is hereby modified as follows. The plans show the locations of all known surface and subsurface structures. However, the OWNER assumes no responsibility for failure to show any or all of these structures on the plans, or to show them in their exact location. It is mutually agreed that such failure shall not be considered sufficient basis for claims for additional compensation for extra work or for increasing the pay quantities in any manner whatsoever, unless the obstruction encountered is such as to necessitate changes in the lines or grades, or requires the building of special work, provisions for which are not made in the Contract Documents, in which case the provisions in these specifications for extra work shall apply. REFERENCE POINTS: 4.4 CONTRACTOR shall report to ENGINEER whenever any reference point established by the ENGINEER is lost or destroyed or requires relocation for any reason. ENGINEER shall re -establish such points and the OWNER shall deduct from monies due to the CONTRACTOR the expense of re- establishing the reference points. ENGINEER shall have the authority to stop all work and withhold approval of payment to the CONTRACTOR at any time reference points have been destroyed or adequate control is not in existence on the site. The decision of the ENGINEER is final. MATERIAL STORAGE: ARTICLE 6 — CONTRACTOR'S RESPONSIBILITIES 6.3 Section 6.3, Labor, Materials and Equipment, of the General Conditions is hereby modified to include the following. Materials and equipment delivered to the site of the work in advance of their use shall be stored so as to cause the least inconvenience and in a manner satisfactory to the ENGINEER. Materials and equipment stored for extended periods shall be protected from weather conditions in a manner satisfactory to the ENGINEER. 00800 -2 USED MATERIALS: 6.5 Section 6.5, Labor Materials and Equipment, of the General Conditions is hereby modified to include the following. No material which has been used by the CONTRACTOR for any temporary purpose whatever is to be incorporated in any permanent structure without written consent of the ENGINEER. The CONTRAC- TOR shall thoroughly clean all equipment and materials installed by him' and shall deliver over such materials and equipment in a bright, clean, polished, and new- appearing condition. USE OF PREMISES:, 6.16 Section 6.16, Use of Premises; of the General Conditions, is hereby modified to include the following. The CONTRACTOR's attention is directed to the limits of work space as obtained by the OWNER and as shown on the plans. The CONTRACTOR shall restrict his operations within the limits of the work space. He shall be responsible for all damages to trees, crops, grasses, etc. which as a result of his operations occur outside such limits. Should the CONTRACTOR require additional work space for access, he shall make arrangements with the owners of such property for such work space at no cost to the OWNER. DISPOSAL OF WASTE MATERIALS: 6.17 Section 6.17, Use of Premises of the General Conditions is hereby modified as follows. During the progress of the Work, CONTRACTOR shall keep the premises free from accumulations of excavated earth in excess of that required for backfilling, waste materials, rubbish and other debris resulting from the Work, in conformance with the Contract Documents. All such excess or waste materials, rubbish and other debris shall, unless otherwise specified in the Contract Documents, become the property of CONTRAC- TOR to be removed from the premises at CONTRACTOR's expense in conformance with all applicable governmental regulations, Contract Documents and to the satisfaction of ENGINEER. CONTRACTOR shall indemnify OWNER and ENGINEER against any and all claims arising as a result of the CONTRACTOR's disposition of any excess or waste materials, rubbish or other debris resulting from the Work. PUBLIC UTILITIES AND OTHER PROPERTY TO BE CHANGED: 6.20 Section 6.20, Safety and Protection, of the General Conditions, is hereby modified to include the following. In case it is necessary to change or move the property of any owner or of a public utility, such property shall not be moved or 00800-3 interfered with until ordered to do so by the ENGINEER. The right is reserved to the owner of public utilities to enter upon the limits of the project for the purpose of making such changes or repairs of their property that may be made necessary by performance of this contract. The CONTRACTOR shall be responsible for the protection of all existing utilities or improvements crossed by or adjacent to his construction operations. Where existing utilities or service lines are cut, broken or damaged, the CONTRAC- TOR shall replace or repair immediately the utilities, service lines or improvements with the same type of original material and construction, or better, at his own cost and expense. USE OF EXPLOSIVES: 6.20 Section 6.20, Safety and Protection, of the General Conditions is hereby modified to include the following. Use of explosives shall conform to all regulations of local government in force at the time of blasting. • .. Should the contractor elect to use explosives in the prosecution of the work, the utmost care shall be exercised so as not to endanger life or property. The OWNER and ENGINEER shall not be held liable for damages done by the CON- TRACTOR in the use of explosives. In addition, the Contractor will be compelled under the contract to provide, through a reputable soils engineering firm professing expertise in this engineering discipline, a monitoring of all blasting as it pertains to all surrounding existing structures, wells, or utilities; and show evidence of same prior to the execution of this Contract. The CONTRACTOR shall notify the proper representatives of any public service corporation, any company, or any individual not less than eight (8) hours in advance of the use of explosives which might endanger or damage their or his property along or adjacent to the work. Whenever explosives are stored or kept, they shall be stored in a safe and secure manner and all storage places be lain marked "DANGEROUS EXPLOSIVES,' and shall be under the care of a compe watchman at all times. TREE PROTECTION: 6.20.3 Section 6.20.3, Safety and Protection, of the General Conditions is hereby modified to include the following. The CONTRACTOR shall protect trees as required by the Contract Documents. The working space noted on the Plans is not intended to indicate all trees can be removed. Unauthorized tree removal or damage will be compensated as specified in the Contract Documents. SHOP DRAWINGS AND SAMPLES: 6.23 & 6.24Sections 6.23 and 6.24, Shop Drawings and Samples, of the General Conditions is hereby modified to include the following. The CONTRACTOR shall make all submittals in conformance with the General Requirements for Shop Drawings, Product Data and Samples. _ 00800 -4 COORDINATION: SCHEDULE OF VALUES: ARTICLE 7 — OTHER WORK 7.4 Section 7.4, Coordination, of the General Conditions is hereby modified as follows. If OWNER contracts with others for the performance of other work on the Project at the site, the person or organization who will have authority and responsibility for coordination of the activities among the various prime contractors shall be the OWNER's Representative. The extent of the authority and responsibi- lity of the OWNER'S Representative will be as specified in the Contract Documents. ARTICLE 13 — WARRANTY AND GUARANTEE; TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK INSPECTION: 13.4 Section 13.4,- Testing and Inspections, of the General Conditions is hereby modified as follows. The City of Round Rock Inspectors will inspect this project. The OWNER will pay inspection and testing fees required by the City of Round Rock. ARTICLE 14 -- PAYMENTS TO CONTRACTOR AND COMPLETMO 14.1 Section 14.1, Schedule of Values, of the General Conditions is hereby modified as follows. Unit Prices, as defined in the Bid Schedule, will serve as the basis for progress payments. APPLICATION FOR PROGRESS PAYMENT: 14.2 Section 14.2, Application for Progress Payment, of the General Condi- tions is hereby modified as follows. CONTRACTOR shall submit for payment on or before the last day of each month. ARBITRATION 16.1 Paragraph 16.1 of the General Conditions shall be modified t the following: PROVISIONS OF THIS AGREEMENT ARE SUBJECT TO ARBITRATION UNDER THE TEXAS GENERAL ARBITRATION ACT V.A.C.S., ART. 224 TO 238-6 00800 -5 include REVIEW OF APPLICATION FOR PROGRESS PAYMENT: 14.4 Section 14.4, Review of Application for Progress Payment, of the General Conditions is hereby modified as follows. The amount recommended by the ENGINEER will become due (subject to the provisions of the last sentence of paragraph 14.7, General Conditions) by the twentieth day of the month following the month in which the Application for Progress Payment was submitted by the CONTRACTOR to the ENGINEER. 00800 -6 1 e h ESPLY, HUSTON & ASSOCIATES, INC. DIVISION 1 GENERAL REQUIREMENTS 4 01000 - SECTION 01010 - SUMMARY OF WORK PART 1 - GENERAL 1.01 DESCRIPTION A. The CONTRACTOR shall construct in conformance with these Contract Documents certain gravity wastewater interceptor titled as BRUSHY CREEK 54 INCH WASTEWATER INTERCEPTOR. B. The CONTRACTOR shall furnish all superintendence, labor, and materials necessary to complete the installation of the work as shown on the Plans and described in the Specifications. Except where 'otherwise specified, the CONTRACTOR shall file all necessary applications or notices, pay all fees, deposits or other charges, and procure all , construc- tion permits, licenses, inspections, etc., which are customary or required for normal and lawful prosecution of the work. The CONTRACTOR shall remove pavement as may be necessary; excavate any necessary trenches and pits to the required dimensions; excavate the bell holes; construct and maintain all bridges required for traffic control; sheet, brace and support the adjoining ground or structures where necessary; handle all drainage or ground water; guard the site; unload, haul, and distribute, lay and test all materials, fittings, and accessories; rearrange sewers, conduits, ducts, or pipes where necessary; replace all damaged drains, sewers, or other structures; backfill trenches and pits; restore the surface and all improvements unless otherwise stipulated; remove surplus excavated material; clean the site of work; and maintain the existing creek grades or other surface over the trench. C. The finished project in all cases shall conform with the lines, grades, cross- sections, dimensions, finish and other requirements shown on the Plans or otherwise described in the Contract Documents. Such devi- ations from the approved Contract Documents as may be required during construction will in all cases be determined by the ENGINEER, and authorized in writing. 1.02 CONTRACT METHOD A. Construct the Work under a single unit price contract. B. Relations and responsibilities between CONTRACTOR and subcontrac- tors shall be as defined in Conditions of the Contract. Subcontractors shall, in addition: 1. Furnish to CONTRACTOR bonds covering faithful performance of subcontracted work and payment of all obligations thereunder when CONTRACTOR is required to furnish such bonds to OWNER. END OF SECTION 01010 -1 SECTION 01014 - WORK SEQUENCE PART 1 - GENERAL 1.01 GENERAL WORK SEQUENCE A. The CONTRACTOR shall at all times confine the construction operation to a work site of no greater than 2,600 feet as measured along the centerline of the pipe being installed and including those specified access roads as are required to conduct construction operations within the work site. For the purposes of determining the sequence of work within the work site the CONTRACTOR shall consider the work site as consisting of four parts, herein called Phases. The specific procedures and detailed work sequence determined by the CONTRACTOR shall conform to the following General Work Sequence: 1. Phase One (not to exceed 300 feet measured along the centerline of pipe and including specified access roads) - ahead of all material or equipment storage and all trenching operations the CONTRAC- TOR shall install all construction barriers, work site fences, tree protection devices, temporary erosion control devices including silt fences, brush berms, and all other items specified to protect the environment during the construction process. The CONTRACTOR shall locate all existing utilities and structures, underground and overhead, checking to assure that no conflicts with the proposed work will occur. Should any conflict with the proposed work be found, the CONTRACTOR shall promptly notify the ENGINEER who will arrange for remedial action. The CONTRACTOR shall endeavor to undertake all activity within Phase One with a minimum of clearing or grubbing in order to minimize environ- mental disturbance occurring prior to placement of erosion control and environmental protection devices. Z. Phase Two (not to exceed 300 feet measured along the centerline of pipe) - clearing, grubbing, trenching and pipe laying may pro- ceed where all Phase One activities have been concluded and the CONTRACTOR has assured himself that all utility locations have been determined and adequate measures have been taken to protect the existing utilities in conformance with the Contract Documents. 3. Phase Three (not to exceed 1,000 feet measured along the centerline of pipe) - backfilling, compaction, installation of additional or relocated erosion controls, testing of pipelines, and clean -up shall be performed promptly after pipe laying is completed and in conformance with the Contract Documents. 01014 -1 4. Phase Four (not to exceed 1,000 feet measured along the centerline of pipe) - where all backfill, compaction, and testing have been satisfactorily completed and approved the CONTRACTOR shall repair or restore and revegetate as specified all damages resulting from the construction operations to a pleasing and useful condition equal to or superior to the condition before construction began. The work site shall be thoroughly cleaned -up, revegetated and restored before a new area may be entered to begin Phase One activities. lI B. The CONTRACTOR may not construe the General Work Sequence as dictating any procedure which may endanger the safety of any person or property. The expense of all procedures which the CONTRACTOR may determine are necessary to safely, acceptably, and properly execute the work in conformance with the General Work Sequence shall be con- sidered as having been included in the applicable unit prices or lump sum prices bid for the work. 1.02 DETAILED WORK SEQUENCE The CONTRACTOR is required to determine his own method of con- struction and detailed work sequence conforming to the General Work Sequence specified herein, as well as all other terms of the Contract Documents. END OF SECTION 01014 -2 SECTION 01015 - CONTRACTOR USE OF PREMISES PART 1 - GENERAL 1.01 WORK SPACE A. The CONTRACTOR shall be responsible for accurately locating in the field the limits of the access roads, yards, workspaces, limited access areas, tree protection areas and similar spaces in conformance with the Drawings and Specifications. B. The CONTRACTOR shall fence, mark, or erect other boundaries around all spaces in conformance with the Contract Documents. C. The CONTRACTOR shall limit all work and materials handling to the area designated for such use in the Contract Documents. The CON- TRACTOR shall prevent any work or materials handling from encroach- ing on any tree protection areas or similar space in conformance with the Contract Documents. D. The CONTRACTOR shall at all times conduct his operations and use of construction machinery so as to avoid unnecessary injury, damage or destruction to any trees or shrubs, utilities, structures or other improve- ments except where and as noted' or stipulated by the Plans or other Contract Documents, or specifically approved or directed by the ENGINEER. E. The CONTRACTOR shall notify the owners or proper agents of the property adjacent to the construction operations at least forty -eight (48) hours before commencing any work which might damage or interfere with the operation of their property. If any public or private property, utility, or improvement is injured or damaged as a result of the conduct or neglect of the CONTRACTOR's operations, he shall at his own expense immediately repair, rebuild, replace or otherwise restore the property to a pleasing and useful condition equal or superior to that before damaged, in conformance with the Contract Documents and to the satisfaction of the ENGINEER. Within thirty (30) calendar days after the occurrence of any such damages, the CONTRACTOR shall file with the ENGINEER a written statement giving full particulars of the incident and describing the disposition of the claim. In case of failure by the CONTRACTOR to restore such property or make good the damages, upon seventy -two (72) hours written notice under ordinary circumstances -- and without notice when a hazardous condition results - the OWNER may arrange to repair, rebuild, or 01015 -1 otherwise restore such property as may be deemed appropriate and the entire cost will be deducted from funds due the CONTRACTOR under this or any other contract with the OWNER. F. The CONTRACTOR shall prohibit hunting, fishing, the building of ground fires or stoves for cooking or heating, keeping of animals, littering, or any other activity within the jobsite which is not directly required to pursue the work specified by these Contract Documents. G. The CONTRACTOR shall prohibit any overnight or after working hours occupancy of the jobsite except as specifically approved by the ENGINEER for purposes of providing security in conformance with the Contract Documents. H. The CONTRACTOR shall obtain the written permission of the ENGI- NEER prior to locating any temporary storage shed, office shed or trailer, watchman's quarters or office, or any other structure for the protection or housing of material, equipment or persons. 1.02 PRIVATE PROPERTY A. Where the work must pass into or across private property, the OWNER will provide the necessary permanent easements and such temporary working space easements as may be judged by the ENGINEER to be necessary and sufficient for construction of the project. Such permanent and temporary easements are as indicated on the Plans. Any additional ground desired by the CONTRACTOR for his use shall be obtained by him at his own expense. The CONTRACTOR shall furnish the ENGINEER with two copies of the agreement between the property owner and the CONTRACTOR permitting use of space in addition to that indicated on the plans prior to any occupancy of such space. Each temporary and permanent easement is obtained with the agreement and understanding that no serious damage will be done to the property during the construction. B. At his own expense and in conformance with the Contract Documents the CONTRACTOR shall perform all clearing, grubbing, grading, etc., required for construction of the project, but shall exercise every precaution to preserve the property from unnecessary damage. Except as noted or specified by the Contract Document or as specifically approved by the ENGINEER, all structures, fences, and other improve- ments shall be protected and maintained in condition for normal usage. 01015 -2 C. Any fencing, bracing, shoring, sheeting or other support, temporary or permanent repairs, and any other special care or precautions necessary to preserve the property and improvements shall be provided by the CONTRACTOR at his own expense. Immediately following the comple- tion of construction work as it progresses, the CONTRACTOR at his own expense shall restore or make good any damage, perform all cleanup, and return the property to a pleasing, useful condition appropriate to the surroundings, and equal to superior to the conditions before construction began in conformance with the Contract Documents. D. The prices bid for the various items of work shall be full payment to the CONTRACTOR for performing the work in strict compliance with all requirements of the easement. 1.03 CITY AND COUNTY RIGHTS -OF -WAY A. For the performance of contract, the CONTRACTOR will be allowed to occupy and use such portions of the public streets, alleys, rights -of -way, and other public places as may be permitted by the City of Round Rock's or Williamson County's Codes and Ordinances and deemed by the ENGINEER to be needed for effective prosecution of the work. The CONTRACTOR will be responsible for obtaining any required permits from the Public Works Department and paying all appropriate fees prior to cutting any street, sidewalk or driveway. In the case of the County right-of -way, the CONTRACTOR will be responsible for contacting the appropriate County Commissioner's Precinct Office and for coordinating his activities with the operating program in effect for utility cuts in that precinct. B. City of Round Rock or Williamson County work forces, or other contractors performing work for the City or County, may enter upon the premises or job site used by the CONTRACTOR and shall be provided all reasonable facilities and accommodations for carrying on their work. 1.04 RAILROAD RIGHTS -OF -WAY A. Where the project is scheduled to pass into or through any railroad right - of-way, the OWNER will unless otherwise specified secure the permit for construction operations. The CONTRACTOR shall comply with all the requirements of the permit, giving any notices called for, coordinating the work with train schedules, arranging for inspection of the work by railway personnel, and any other particular conditions to the satisfaction of the railroad's Roadmaster. B. Should the permit and contract documents for any given project fail to describe such conditions in specific detail, all work on railroad property shall meet the following minimum requirements: 01015 -3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 No open -cut trenching will be permitted within fifteen (15) feet of the track centerline under any circumstances; actual distance shall be based on roadbed and embankment conditions, according to railroad recom- mendations. Within such distance from the. tracks, gravity -flow piping shall be cast iron or ductile iron placed by boring, jacking or tunnelling and pressure grouted into place. Within that same distance, pipelines under pressure shall be placed in an approved encasement pipe which is bored, jacked or tunnelled and then pressure grouted into place. No vehicles, equipment, supplies, dirt or debris will be permitted within fifteen (15) feet of the track centerline at any time. 1.05 STATE RIGHTS -OF -WAY A. Where the project is scheduled to pass within the right -of -way of any State or U.S. Highway, the OWNER will unless otherwise specified secure the permit for construction operations. B. The CONTRACTOR shall comply with all provisions and requirements of the permit, giving any notices called for, coordinating and scheduling the work to minimize hazards, inconvenience and delays to the traffic. Should any such permit fail to stipulate more stringent conditions; however, all work on highway property shall meet the following minimum requirements: Unless specifically authorized in writing, no open -cut trenching will be permitted within ten (10) feet of highway paving. All work must be accomplished with minimum inconvenience to traffic. No excavated spoil, dirt, debris or supplies will be permitted within ten (10) feet of the highway pavement at any time. No vehicles or equipment will be permitted on the highway pavement at any time. All hazards to traffic, such as work on the road shoulder, must be clearly marked and protected by lights, warning signs and barricades at all times, and flagmen if equipment is within ten (10) feet of highway pavement. END OF SECTION 01015 -4 SECTION 01018 - OWNER FURNISHED ITEMS PART 1 - GENERAL 1.01 MATERIALS FURNISHED BY THE OWNER A. The OWNER reserves the right to furnish materials to the CONTRAC- TOR to be installed by the CONTRACTOR, whenever designated on the plans or other Contract Documents. These materials will be furnished to the CONTRACTOR at the project, unless otherwise noted, and it will be the CONTRACTOR'S duty to accept, load, haul and unload these materials at the job site. b. The CONTRACTOR's responsibility for material furnished by the OWNER shall begin at the point of delivery by the manufacturer, or OWNER, and upon acceptance of the material by the CONTRACTOR. The CONTRACTOR shall examine all material furnished by the OWNER at the time and place of delivery, and shall reject all defective material. Any defective material furnished by the OWNER and not rejected by the CONTRACTOR, and discovered prior to final acceptance of the work, will be recplaced with sound material by the OWNER, and the OWNER will furnish such additional material and supplies as may be necessary to install such replaced material; the CONTRACTOR, however, shall remove the defective material and install the replaced material at his own expense, furnishing all the labor and facilities necessary to complete the work to the satisfaction of the ENGINEER. C. Any material furnished by the OWNER that becomes damaged after acceptance by the CONTRACTOR, shall be replaced by the CONTRAC- TOR at his own expense. END OF SECTION 01018 -1 SECTION 01030 - SPECIAL PROJECT PROCEDURES PART 1 - GENERAL 1.01 CONTRACTOR'S RESPONSE PROCEDURE A. Before commencing work on the project, the CONTRACTOR shall submit to the ENGINEER in writing the name, residence address and telephone number of his project superintendent and at least one other foreman, supervisor, or responsible assistant, each having full authority to act as the Contractor's agent for the work. AT ALL TIMES one (1) or more such agents shall be immediately available by telephone and prepared to respond to emergencies. • B. Authorized agents of the CONTRACTOR shall respond immediately to call -out at any time of any day or night when the ENGINEER determines that circumstances warrant the presence on the project site of an agent of the CONTRACTOR to protect the work or adjacent property from damage, restriction or limitation, or to take such action or measures pertaining to the work as the ENGINEER may consider necessary to provide for the safety of the public. ' C. Should the CONTRACTOR and his agents fail to respond and take action to alleviate such an emergency situation, the ENGINEER may direct other forces to take action as necessary to remedy the emergency condition. In such a case, the OWNER will deduct the cost of such remedial action from funds to the CONTRACTOR. _ 1.02 ACCEPTABILITY OF PROCEDURES A. All work shall be accomplished by procedures which are acceptable to the ENGINEER. The ENGINEER will not attempt to dictate specific working methods, but it shall be the CONTRACTOR's responsibility to ascertain beforehand that the methods which he desires to use will be acceptable to the ENGINEER, taking into consideration the actual job conditions expected. B. All work must be done with the approval of the OWNER and his authorized representatives, in accordance with the Contract Documents. The ENGINEER will decide all questions as to acceptability of materials, manner of performance, rate of progress, beginning points of the work, interpretations of the Plans and Specifications, and the acceptable fulfillment of the Contract on the part of the CONTRACTOR. 01030 -1 1.03 PROCEDURES RELATING TO EXISTING UTILITIES A. The CONTRACTOR shall at all times take precautions to keep all utilities within the area of construction, either underground or overhead, operational. The CONTRACTOR shall notify the Owner of existing utilities at least forty -eight (48) hours before crossing underground piping, cables, conduits, etc. The Owner of any poles shall be notified and arrangements made for temporarily supporting, relocating, or moving any poles near the trenchline. The CONTRACTOR shall bear all expenses for temporary or permanent alterations or support, for repair of damage, or for precautions against damage to such other existing utilities. The locations of utilities shown on the Plans are approximate only and do not necessarily indicate all the utilities that may be encountered during construction. The failure of a utility to be shown on the Plans does not relieve the CONTRACTOR of the responsibility of any injuries he may inflict on the utility, and in case of injury, it shall be repaired at the expense of the CONTRACTOR. B. Underground utilities crossed shall be supported as shown on the Plans or as directed by the Owner of the utility and accepted by the ENGINEER. Trenching or tunnelling under existing utilities, culverts, etc., and providing temporary support shall be done at no additional expense to the OWNER. Whenever other utilities are encountered whose present grade would conflict with the construction, the CONTRACTOR shall notify the ENGINEER who shall arrange revisions without unreasonable delay. C. If the work requires shut -off of any part of the existing- City of Round Rock water system, these shut -offs will be made by the Water Dis- tribution Division upon reasonable notice by the CONTRACTOR requesting same, unless otherwise directed by the ENGINEER. D. Free access shall at all times be maintained to all emergency and utility control facilities such as fire hydrants, fire alarm boxes, police call boxes, and utility valves, vaults, manholes, junction boxes, etc. In the event that it is necessary to make one of these facilities temporarily inaccessible, the CONTRACTOR shall obtain approval of such action and the schedule of work from the ENGINEER. He shall also give at least twenty -four (24) hours prior notice to the Fire Department, Police Department, or the department governing the affected utility. The same department(s) shall be promptly notified by the CONTRACTOR when such facilities are placed back in unobstructed service. 1.04 PROCEDURES RELATING TO EMERGENCY RECTIFICATION WORK A. After a request from the ENGINEER to rectify omissions or dis- crepancies in the work, should the CONTRATOR fail to respond within a reasonable time with the corrective action necessary for the work to conform to the requirements of the Contract Documents, the ENGINEER 01030 -2 may give the CONTRACTOR written notice pointing out the specific omissions or discrepancies, requesting him to correct them and directing him that an emergency will exist if remedial action is not taken. B. If the CONTRACTOR does not respond to this .written notice with positive attempts to correct the situation within seventy -two (72) hours, or show good cause for not taking such action, the ENGINEER may direct other forces to carry out the necessary corrective action as an emergency measure. In such a case, the OWNER will deduct the cost of such remedial action from funds due the CONTRACTOR. 1.05 PROCEDURES RELATING TO BLASTING A. When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of the work, the CONTRAC- TOR shall exercise the utmost care and shall carry on such activities under the supervision of properly qualified personnel. B. All Blasting, including methods of storing and handling explosives and highly inflammable materials, shall conform to all Federal, State, and Local Laws and Ordinances. All City of Round Rock Ordinances shall be complied with even though some or all of the blasting is done outside the City Limits unless the applicable Ordinance is in conflict with the law of the jurisdiction where the action is being taken. • � vt C. The following is a list of requirements in addition to Federal, State, and Local Laws and Ordinances: _ 1. The CONTRACTOR shall furnish the owner with a Certificate of Blasting Insurance in the amount of $300,000.00 for each contract, at least twenty -four (24) hours prior to using explosives. If Blasting is covered under the Contractor's General Insurance Certificate for each contract, a separate blasting certificate will not be required. 2. The following public utility companies and City of Round Rock Departments will be notified by the CONTRACTOR, on every occasion, at least twenty -four (24) hours prior to the use of explosives: Water and Wastewater, Electric, Gas, Telephone and the City Engineering Department. 3. Explosive materials to be used shall be limited to blasting agents and dynamite, unless prior approval of other materials is obtained in writing from the Engineering Department of the City of Round Rock. 4. During blasting, all reasonable precautions shall be taken to protect pedestrians, passing vehicles, and public or private property. Blasting mats or protective cover shall be used when _ required by the permit or by safe blasting practices. 01030 -3 D. The OWNER or his representative shall have the right to limit the use of explosives and /or blasting methods which in his opinion are dangerous to the public or nearby property of any kind. E. The CONTRACTOR, at his expense, shall promptly repair or replace all items known, to be damaged as a result of blasting. F. The CONTRACTOR shall maintain accurate records throughout the Blasting operations showing the type explosive used, number of holes, pounds per hole, depth of hole, total pounds per shot, delays used, date and time of blast and initials of the Inspector. The CONTRACTOR is fully responsible for all claims resulting from his blasting operation. G. All damage or loss to any property referred to in this article caused in whole or in part by the CONTRACTOR, any Subcontractor, any Sub - subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable, shall be remedied by the CONTRACTOR, except damage or loss attributable solely to faulty Drawings or Specifications or solely to the acts or omissions of the OWNER or ENGINEER or anyone employed by either of them, and not attributable in any degree to the fault or negligence of the CONTRACTOR. & END OF SECTION 01030 -4 SECTION 01060 - REGULATORY REQUIREMENTS PART 1 - GENERAL 1.01 CITY OF ROUND ROCK It is the intention of these Contract Documents to describe and provide for work and materials which conform to all applicable parts of The Code of the City of Round Rock and which shall be acceptable for connection to and inclusion in the utility system of the City of Round Rock. 1.02 OTHER REGULATIONS The CONTRACTOR shall at all times observe and comply with all Federal, State and Local Laws, ordinances and regulations, which in any manner affect the contract or the work, and shall indemnify and save harmless the OWNER against any claim arising from the violation of any such laws and ordinances, whether by the r CONTRACTOR or his employees. In case the OWNER is a body politic and corporate, the law from which it derives its powers, insofar as the same regulates the objects for which or the manner in which, or the conditions under which, the OWNER may enter into contract, shall `be controlling, and shall be considered as part of this contract, to the same effect as though embodied herein. 1.03 CONFLICTING REQUIREMENTS A. The CONTRACTOR shall be familiar with all regulations applicable to the work and materials specified in the Contract Documents. The CONTRACTOR shall at all times be responsible for conducting the work in conformance with all applicable regulations. B. In case of conflicting requirements the CONTRACTOR shall immedi- ately notify the ENGINEER which will take prompt action in conform- ance with the Contract Documents. 1.04 PERMITS, LICENSES, AND FEES Except where otherwise noted or specified, the CONTRATOR shall file all applications or notices, pay all fees, deposits or other charges, and procure all inspections, meters, permits, licenses, etc., which are required or customary for normal and lawful prosecution of the work. END OF SECTION 01060 -1 SECTION 01090 - REFERENCE STANDARDS PART 1 - GENERAL 1.01 QUALITY ASSURANCE A. For products or workmanship specified by association, trade, or Federal Standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes. B. The date of the standard is that in effect as of the Bid date, or date of Owner- Contractor Agreement when there are no bids, except when a specific date is specified. C. When required by individual Specifications section, obtain copy of standard. Maintain copy at jobsite during submittals, planning, and progress of the specific work, until Substantial Completion. 1.02 SCHEDULE OF REFERENCES . f AASHTO American Association of State Highway . .i and Transportation Officials r 444 North Capitol Street, N.W.' Washington, DC 20001 ACI American Concrete Institute Box 19150 Reford Station Detroit, MI 48219 AGC Associated General Contractors of America 1957 E Street, N.W. Washington, DC 20006 AI Asphalt Institute Asphalt Institute Building College Park, MD 20740 AISC American Institute of Steel Construction 400 North Michigan Avenue Eighth Floor Chicago, IL 60611 AISI American Iron and Steel Institute 1000 16th Street, N.W. Washington, DC 20036 01090 -1 ANSI American National Standards Institute 1430 Broadway New York, NY 10018 ASTM American Society for Testing and Materials 1916 Race Street Phildelphia, PA 19103 AWWA American Water Works Association 6666 West Quincy Avenue Denver, CO 80235 AWS American Welding Society 550 LeJeune Road Miami, FL 33135 CRSI "Concrete Reinforcing Steel Institute 933 Plum Grove Road ' Schaumburg, IL 60195 ' ,* EJCDC Engineers' Joint Contract Documents Committee • - American Consulting Engineers Council. s 1050 15th Street, N.W. Washington, DC 20005 FS Federal Specification General Services Administration Specifications and Consumer Information Distribution Section (WFSIS) Washington Navy Yard, Bldg. 197 Washington, DC 20407 NEMA National Electrical Manufacturers' Association 2101 L Street, N.W. Washington, DC 20037 NFPA National Fire Protection Association Battery March Park Quincy, MA 02269 PCI Prestressed Concrete Institute 201 North Wacker Drive Chicago, IL 60606 RR City of Round Rock Standard Specifications for Public Works 214 E Main Round Rock, Texas 01090 -2 RR Standard Construction Specifications for Water and Wastewater Department Z14 E Main Round Rock, Texas 78701 THD Texas State Department of Highways and Public Transportation TWC Texas Water Commission P. O. Box 13087, Capitol Station Austin, Tx. 78711 UL Texas Standard Specifications Dewitt C. Greer State Highway Bldg. 11th and Brazos Austin, TX 78701 Underwriters' Laboratories, Inc. 333 Pfingston Road Northbrook,IL 60062 END OF SECTION 01090 -3 SECTION 01150 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01 BID QUANTITIES A. The bid quantities of the various classes of work to be done and material to be furnished under the contract are approximate and are to be used only as a basis for estimating the probable cost of the work and for comparing the Proposals offered for the work. It is understood and agreed that the CONTRACTOR will actually perform the quantities of work found to be necessary to produce a complete and workable project suitable for its intended purpose, and will be paid on the basis of his unit and lump sum contract prices for such work, and will make no claim for damages or loss of anticipated profits due to any such variation in quantities of work other, than as set out in the Contract Documents. B. Final payment will be made only for work performed and accepted. The CONTRACTOR shall verify quantities before ordering materials. Unless stated otherwise in the Contract Documents, it is understood that all payments are for finished work and include all labor, tools, materials, constructing and completing the item for which payment is made. 1.02 LETTER OF ACCEPTANCE A. The CONTRACTOR shall submit a letter of acceptance from the City of Round Rock before requesting final payment. PART 2 - PRODUCTS 2.01 WASTEWATER PIPE A. Wastewater pipe will be paid for at the unit contract price per linear foot, for the size, type and depths specified. Measurements for wastewater pipe line shall be the horizontal distance along the centerline of the pipe not including distance through the manholes. The contract price per linear foot shall also include all site preparation, excavation, bedding material, fittings, plugs, pipe coatings, connections to existing system, backfilling, disposal of surplus materials, work space fence, testing, and clean up. Payment will also represent compensation for replacement of pavement, curb, drainage structures, driveway, fencing and any other improvements damaged during construction. Concrete blocking for supporting and reinforcing bends, and thrust blocks shall be included in the cost for pipe. Measurement for depth shall be from proposed subgrade over centerline of the pipe to the flow line of the 01150 -1 pipe, except in areas where pipe is installed outside of subgrade limits; then depth shall be measured from existing ground elevation over centerline of the pipe to flow line of the pipe. B. When called for on the Plans pipe shall be installed by boring. Pipe shall be paid for at the unit price bid per linear foot for the length indicated on the Plans and will include the wastewater pipe and all grout, encase- ment, required testing and other appurtenances required to complete the approved installation. The unit price shall be full compensation for excavation pit, pilot hole, casing pipe and pressure grouting and all incidentals necessary to complete the item in place. The CONTRAC- TOR may request approval for boring, longer than required, however, any extra length requested solely for the CONTRACTOR's own convenience shall be paid as if installation were by open trench construction at the depth encountered. ° 3 C. As noted above, pipe complete in place includes testing. The CON- TRACTOR may request payment for 80 %, less retainage, of the unit price for pipe otherwise in place and not tested. 2.02 MANHOLES A. Manholes shall be paid for at the unit price bid per manhole structure with all appurtenances including precast base or "T" with "Eyes ", stubs and plugs as specified, as called for on the plans, rings, cones, lids, bolted covers, bedding and backfilling complete in place. B. Vertical riser pipe shall be paid for at the Unit Contract Price per vertical foot. Vertical footage shall be from ground surface to flowline of pipe less eight feet. C. As noted above, manholes complete in place include testing. The CONTRACTOR may request payment for 80 %, less retainage, of the unit price for manholes and risers complete in place and not tested to a total maximum of all manholes included within up to 1,000 linear feet of pipe. 2.03 CONCRETE ENCASEMENT A. Concrete Encasement will be paid for at the unit contract price per linear foot for the size of pipe specified. Measurement for Concrete Encasement shall be the horizontal distance along the centerline of the pipe as measured by the ENGINEER. The price shall be full compensa- tion for labor, equipment, materials, and all incidentals necessary to complete the item in place. 01150 -2 2.04 MISCELLANEOUS CONCRETE AND ROCK STRUCTURES: A. Miscellaneous concrete structures and appurtenances, such as, inlets, headwalls, drop structures, dissipators, etc., will be paid for at the unit contract price per each, which shall be considered full compensation for furnishing and placing all materials and incidentals necessary to complete the work. B. Rock Gabions, when called for in the contract documents, shall be paid for at the unit contract price per linear foot and shall be full compensation for furnishing all labor, equipment, materials and all incidentals necessary to complete the work. 2.05 TEMPORARY AND PERMANENT EROSION CONTROL r Tempor and Permanent Erosion Control items shall be paid for at the bid price per the unit of measure stated in the proposal including all required materials and - labor, complete in place. Items bid on a per linear foot or per each basis shall be paid for as installed. The lump sum for items so bid shall be full compensation for those items, monthly progress payments being made for work performed during the job. 2.06 TREE PROTECTION COLLARS A. Tree protection collars shall be paid for at the unit contract price per each and shall include full compensation for furnishing all labor, tools, equipment, materials and incidentals necessary to complete the work. 2.07 SANDBAG DIKE A. Sandbag dikes shall be paid for at the unit contract price per linear foot and shall include full compensation for furnishing all labor, tools, equipment, materials and i ncidentals necessary to complete the work. 2.08 SILT FENCE A. Silt Fence shall be paid for at the unit contract price per linear foot and shall include full compensation for furnishing all labor, tools, equipment, materials and incidentals necessary to complete the work. END OF SECTION 01150 -3 SECTION 01200 - PROJECT MEETINGS PART 1 - GENERAL 1.01 PRECONSTRUCTION CONFERENCES A. Schedule: ENGINEER will establish place, date, time, distribute agenda, notify CONTRACTOR in writing, and administer preconstruction con- ference. B. Anticipated Attendees: 1. OWNER. 2. ENGINEER. 3. CONTRACTO - '.. # 4. 4. ` Major Subcontractors. 5. Resident Project Representative. 6. Utility Companies. •' 7. Williamson County Engineers Office. 8. Water and Wastewater Department, City of Round Rock. 9. Brushy Creek WCID. C. Agenda: 1. Responsibilities. 2. General Contract Terms. 3. Resident Project Representation. 4. Schedules. 5. Submittals, Approvals, and Testing. 6. Payments and Estimates. 7. Construction Sequence. 8. Environmental Controls. 9. Use of Temporary Easements. D. Minutes: 1. Distribution: ENGINEER will prepare and distribute copies to participants within 14 days of meeting. 2. Review: Report corrections and comments within 10 days of receipt. 1.02 PROGRESS MEETINGS A. Schedule: ENGINEER will establish place, date, time, distribute agenda, notify CONTRACTOR in writing, and administer all progress meetings. 01200 -1 Meetings will be held on an as needed basis as determined by the ENGINEER. At a minimum, monthly meetings are anticipated. B. Attendance: 1. OWNER 2. ENGINEER. 3. CONTRACTOR. 4. Subcontractors as pertinent to agenda. 5. Resident Project Representative. 6. Governmental agencies as pertinent to agenda. C. Agenda: s 1. .' Review and approve minutes of previous meetings. 2. Review work progress and construction schedule: a. Note field observations, problems and decisions. b. Identify problems impeding planned progress. ,° c. Review constructoin equipment and labor force. d. Review off -site fabrication problems. e. Develop corrective measures and procedures to regain planned schedule. f. Revise construction schedule. g. Plan next work period progress. h. Coordinate projected progress with other contractors and subcontractors. 3. Review submittal schedules and expedite as required. 4. Review work performance since last meeting: a. Review bulletins and change orders: (1) Status. (Z) Effect on construction schedule. (3) Effect on completion date. 5. Safety report. 6. Discuss current work problems. 7. Review new business. 8. Establish date for next meeting. D. Minutes: ENGINEER will prepare and distribute for approval at the following meeting, or within 14 days of previous meeting. END OF SECTION 01200 -2 SECTION 01340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.01 MODIFICATIONS OF GENERAL CONDITIONS In accord with the Supplementary Conditions, the requirements of this Section of the Specifications supercedes the requirements of the General Conditions. 1.02 DESCRIPTION OF REQUIREMENTS ° . I A. Type of Submittals. This Section of the Specifications describes the procedures for submittal requirements applicable to work related sub- mittals, such as shop drawings, product data, samples and miscellaneous work - related submittals. It does not include the ,requirements for administrative submittals which are described in other Division 1 sec- tions and other contract documents. B. Individual Section Requirements. The individual submittal requirements are specified in other Sections of the Specifications for each unit of work. C. Definitions. The work -related submittals of this Section, in addition to the definitions of the General Conditions and elsewhere in the Contract Documents, are further categorized for convenience as follows: 1. Shop drawings include specially prepared technical data of all forms including drawings, diagrams, performance curves, data sheets, schedules, templates, patterns, reports, calculations, in- structions, measurements and similar information not in standard printed form for application to more than one project. 2. Product data includes standard printed information on materials, products and systems, not specially prepared for this project, other than the designation of selections from among available choices printed therein. 3. Samples include both fabricated and =fabricated physical examples of materials, products and units of work, both as com- plete units and as smaller portions of units of work, either for limited visual inspection or, where indicated, for more detailed testing and analysis. 01340 -1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 \ 4. Miscellaneous submittals related directly to the work (nonadmini- strative) include warranties, maintenance agreements, workman- ship bonds, project photographs, survey data and reports, physical work records, statements of applicability, quality testing and certifying reports, copies of industry standards, record drawings, field measurement data, operating and maintenance materials, overrun stock, security /protection/safety keys and similar informa- tion, devices and materials applicable to the Work and not processed as shop drawings, product data or samples. 1.03 GENERAL SUBMITTAL REQUIREMENTS A. Scheduling. Where appropriate, in various required administrative sub- mittals (listings of products, manufacturers, suppliers and subcontrac- tors, and in job progress schedule), show principal work - related submittal requirements and time schedules for coordination and integration of submittal activity with related work in each instance. -' B. Coordination of Submittal Times. Prepare and transmit each submittal to the ENGINEER sufficiently in advance of performing related work or other applicable activities, so the installation will not be delayed or improperly sequenced by processing times, including nonapproval and resubmittal (if required). Coordinate with other submittals, testing, purchasing, delivery and similar sequenced activities. No extension of time will be authorized because of CONTRACTOR', failure to transmit submittals to the ENGINEER sufficiently in advance of the work. C. Sequencing Requirements. As applicable in each instance, do not proceed with a unit of work until submittal procedures have been sequenced with related units of work in a mariner which will ensure that the action will not need to be later modified, or, rescinded by reason of a subsequent submittal which should have been processed earlier or con- currently for coordination. D. Preparation of Submittals. Provide permanent marking em each submit- tal to identify project, date, CONTRACTOR, subcontractor, submittal name and similar information to distinguish it from other submittals. Show CONTRACTOR', executed review and approval marking and pro- vide space for the ENGINEER's 'Action' marking. Package each submittal appropriately for transmittal and handling. Submittals which are received from sources other than through the CONTRACTOR', office will be returned 'without action.' E. Transmittal Form. The transmittal form used to transmit submittals may be obtained from the ENGINEER upon request. 01340 -2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1.04 F. Transmittal Identification. 1. Number transmittals in sequence for each Division of the Specifi- cations. The number after the dash indicates the Section of the Specifications, and the number before the dash is the sequence number of the transmittal (1 -15140 would be the first transmittal applicable to Section 15140 of the Specifications. 2 -15140 would be the second transmittal for Section 15140, etc.). 2. Identify resubmittals with a letter of the alphabet following the original number, using A for the first resubmittal, B for the second resubmittal, etc.. A resubmittal affecting transmittal 1 -15140 would then be numbered 1A-15140.,, The number 1 -15140 would then -be entered in the space 'Previous Transmittal Number; which is left blank except on resubmittals. SPECIFIC CATEGORY REQUIRE MENTS A. General. Except as otherwise indicated in the individual work sections, comply with general requirements specified herein for each indicated category of submittal. 1. Submittals shall contain: a. The date of submission and the dates of any previous submis- sions. b. The Project title and number. c. Contract identification: d. The names of the: 1) CONTRACTOR. 2) Supplier. 3) Manufacturer. e. Identification of the product with the Specification Section number. f. Field dimensions, clearly identified as such. g. Relation to adjacent or critical features of the work or materials. b. Applicable standards, such as ASTM or Federal Specification numbers. 01340 -3 i. Notification to the ENGINEER in writing, at time of submis- sion, of any deviations in the submittals from requirements of the Contract Documents. j• I. • Identification of revisions on resubmittals. k. An 8 -inch by 3-inch blank space for CONTRACTOR and ENGINEER stamps. CONTRACTOR'S stamp, initialed or signed, certifying review of submittal, verification of products, field measurements and field ^construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents. Submittal sheets or drawings showing more than the particu- lar item under consideration shall have all but the pertinent description of the item for which review is requested crossed out. B. Shop Drawings. Provide newly - prepared information, on reproducible sheets, with graphic information at accurate scale (except as otherwise indicated), with name of preparer (firm name) indicated. The Contract Drawings shall not be traced or reproduced by any method for use as or in lieu of detail shop drawings. Show dimensions and note which are based on field measurement. Identify materials and products in the work shown. Indicate compliance with standards and special coordination requirements Do not allow abop drawing copies without appropriate final Action markings by the ENGINEER to be used in connection with the Work. 1. Submittal. Eight prints. Four will be retained. Four will be marked -up and returned. The CONTRACTOR shall maintain one copy as the 'Record Document' The CONTRACTOR will be responsible for providing and marking additional copies as may be required. C. Product Data. Collect required data into one submittal for each unit of work or system, and mark each copy to show which choices and options are applicable to project. Include manufacturer's standard printed recommendations for application and use, compliance with standards, application of labels and seals, notation of field measurements which have been checked, and special coordination requirements. Maintain one set of product data (for each submittal) at project site, available for reference by the ENGINEER or others. 01340 -4 1. Submittals. Do not submit product data, or allow its use on the project, until compliance with requirements of Contract Docu- ments has been confirmed by the CONTRACTOR. Submittal is for information and record, unless otherwise indicated. Submittal is final unless returned promptly by the ENGINEER, marked with an 'Action' which indicates an observed noncompliance. Submit four copies, four of which will be returned. The CONTRACTOR will be responsible for providing and marking additional copies as may be • required. ` 2. Installer's Copy. Do not proceed with installation of materials, products or systems with copy of applicable product data k in possession of installer. D. Samples. Provide units identical with final condition of proposed materials or products for the work. Include 'range' samples (not less than three units) where unavoidable variations must be . expected, and describe or identify variations between units of each set. Provide full set of optional samples where the ENGINEER'' selection is required. Prepare samples to match the ENGINEER'' sample where so indicated. Include information with each sample to show generic description, source or product name and manufacturer, limitations, and compliance with standards. Samples are submitted for review and confirmation of color, pattern, texture, and 'kind' by the ENGINEER. ENGINEER will not 'test" samples (except as otherwise indicated) for other requirements, which are the exclusive responsibility of the CONTRACTOR. 1. Submittal. At CONTRACTOR'' option, provide preliminary sub- mittal of a single set of samples for the ENGINEER'' review and 'Action.' Otherwise, initial submittal is final submittal unless returned with 'Action' which requires resubmittal. Submit 2 sets of samples in final submittal; 1 set will be returned. 2. Quality Control Set. Maintain returned final set of samples at project site, in suitable condition and available for quality control comparisons by ENGINEER and by others. 1.05 DISTRIBUTION A. General Distribution. tribution. Shop drawings, product data and samples subject to Action by the ENGINEER shall be submitted as specified above. Additional copies required for distribution to subcontractors, suppliers, fabricators, installers, and others, as necessary, for proper performance of the work, shall be marked -up by the CONTRACTOR with the ENGINEER'' comments and distributed by the CONTRACTOR. 01340 -5 B. Review Time. Allow a minimum of 10 days for the ENGINEER'S initial processing of each submittal requiring review and response, except allow longer periods where processing must be delayed for coordination with subsequent submittals. The ENGINEER will advise the CONTRACTOR promptly when it is determined that a submittal being processed must be delayed for coordination. Allow 10 days for reprocessing each submittal. Advise the ENGINEER on each submittal as to whether processing time is critical to progress of the work, and therefore the work would be expedited if processing time could be foreshortened. - • + �r C. ENGINEER's Action.' , ,. • 1. Approved. Work may proceed, provided it complies with contract documents. Z. Approved as Corrected. Work may proceed, provided it complies with notations and corrections on submittal and with contract documents. 3. Not Approved or Revise and Resubmit. Do not proceed with work. Revise submittal in accordance with notations thereon, and resubmit without delay to obtain a different "Action" marking. Do not allow submittals with this marking to be used in connection with performance of the work. END OF SECTION 01340 -6 SECTION 01510 - TEMPORARY CONSTRUCTION FACILITIES AND UTILITIES PART 1 - GENERAL 1.01 TEMPORARY UTILITIES Unless otherwise provided bi the Contract Documents the CONTRAC- TOR shall at his own "expense arrange' and provide for all utilities necessary to conduct the work including testing in conformance with the Contract Documents. 1.02 TEMPORARY SANITATION FACILITIES The CONTRACTOR shall establish and enforce among his employees such regulations in regard to cleanliness and disposal of garbage and waste as will tend to prevent the inception and spread of infectious or contagious diseases and to effectively prevent the creation of a nuisance about the work on any property either public or private, and such regulations as are required by the ENGINEER shall be put into imme- diate force and effect by the CONTRACTOR. The necessary sanitary conveniences for use of laborers on the work, properly secluded from public observation, shall be constructed and maintained by the CON- TRACTOR in such a manner and at such point as will be acceptable to the ENGINEER, and their use shall be strictly enforced by the CON- TRACTOR. All such facilities shall be kept in a clean and sanitary condition, free from objectionable odors so as not to cause a nuisance. All sanitary laws and regulations of the State of Texas and the City of Round Rock shall be strictly complied with. END OF SECTION 01510 -1 SECTION 01531 - WORK SPACE FENCE PART 1 GENERAL 1.01 DESCRIPTION 2.02 Unless otherwise provided :in -in these TRACTOR shall at his own expense roads, yards and workspaces utilised mance with the Contract Documents. B. The CONTRACTOR shall prohibit any construction activity including but not limited to clearing, excavation, spoiling, stockpiling or vehicular movement outside of the limits of the area designated for such work or bounded by workspace fence in conformance with the Contract Docu- ments. A. C. Workspace fence shall be installed in accord with the General Work Sequence during Phase 1 of the work in any area. D. Workspace fence is not required where the limits of access roads, yards or workspaces are defined by silt fence, tree protection fence or other specified or existing barrier acceptable to the ENGINEER. E. Minimum width openings in the workspace fence shall be required in the following situations, as acceptable to the ENGINEER: 1. Where installation of the workspace fence will interfere with necessary access to public or private property. 2. Within the channel of streams, ditches or waterways. PART 2 - PRODUCTS 2.01 FENCE POSTS Fence posts utilized for work under this Section shall be steel or wood painted with fluorescent orange paint. Post length shall be sufficient to allow firm embedment in the ground and standing at least four (4) feet tall above the ground. WIRE AND ROPE Fencing may be either 10 gage or heavier strand wire, t4 inch or larger twisted or braided rope, or wire mesh at least 36 inches high and formed of 8 gage or heavier wire. 01531 -1 Contract Documents the CON- install 'a fence around all access by the CONTRACTOR in confor- 1 1 1 1 1 1 1 1 1 1 1 1 .1 1 1 1 3.03 FLAGGING Flagging shall be red or orange material at least one inch wide. PART 3 - EXECUTION 3.01 INSTALLATION OF WORKSPACE FENCE ai ~ A. Fence shall be located in conformance with the Contract Documents and installed in accord with the Genera] Work Sequence. 3. Fencing shall not be attached in any fashion to;,any tree or existing structure. C. Posts shall be firmly embedded in the ground and project at least 4 feet above fround. Posts shall be installed no greater than 20 feet apart and as required at corners or bends to cause the fencing to conform to the limits of the area being fenced is accord with the Contract Documents. D. Wire mesh, wire strands or rope shall be securely fastened to the posts and to no other support, tree or structure. When utilized, a minimum of two strands of wire or rope shall be installed. Red or orange flagging shall be draped along the fence to increase visibility. END OF SECTION 01531 -2 h ESPEY, HUSTON a ASSOCIATES, INC. 1 I SECTION 01532 - TREE PROTECTION COLLARS PART 1 - GENERAL ' 1.01 DESCRIPTION r A. The work under thi Section of the Specifications bncludes all labor I materials, equipment and installation of tree protection and similarly specified collars in accord with the Contract Documents. I B. Tree protection collars shall be installed in Conformance with the General Work Sequence during Phase 1 of the work in any area. I C. The CONTRACTOR shall prohibit any construction activity including but not limited to clearing, excavation, spoiling, stockpiling or vehicular movement within any area protected in conformance with the General Documents. D. On those trees designated for protection which are within 10 ft of pipe centerline on the plans, a protective collar shall be installed around the trunk prior to initiation of construction activities near each tree to prevent trunk scarring. ' PART 2 - PRODUCTS 2.01 LUMBER ' 2" x 6" lumber of sufficient length to extend from the ground to the juncture of the lower limbs of each tree (6 ft minimum). 1 2.02 FLAGGING Flagging shall be red or orange material at least one inch wide. PART 3 - EXECUTION 3.01 INSTALLATION OF TREE PROTECTION COLLARS A. 2" x 6" lumber shall be secured to lengths of steel cable of sufficient length to encircle the tree trunk. Lumber shall be placed with maximum 2 inch spacing between boards. A minimum of two strands of steel cable shall be used. . 1 B. The assembled collar shall then be tightly wrapped around the trunk of each tree and the ends of the cables secured with cable clamps. Care 1 1 01532 -1 e WET, HUSTON a ASSOCIATES, INC. C. should be taken not to gouge or debark the tree trunk during installation of the collar. Collars aball not be nailed to the trees. Collars shall be removed when construction has passed each tree. • END OF SECTION ; • ' 01532 -Z SECTION 01540 - PROTECTION OF WORK, PROPERTY AND PERSONS PART 1 - GENERAL ' s < 1.01 DESCRIPTIONS A. The CONTRACTOR shall exercise every precaution necessary to protect the work, and at'his own expense shall immediately repair, rebuild, or otherwise restore any injury or damage to the work, whether arising from the execution or non- execution of the CONTRACTOR'. •duties, or from action by the natural elements, or from any cause whatsoever. The CONTRACTOR% responsibility for protection and maintenance of the work shall not cease until the project has been accepted by the City of Austin. B. Where the work is carried on in or adjacent to any street, alley, or public place, the CONTRACTOR shall at his own expense furnish, erect, and maintain such barricades, fences, lights, and danger signals, shall provide such watchmen, and shall take all such other precautionary measures for the protection of persons or property and of the work as are necessary to keep pedestrians away from, and vehicles from being driven an or into, any work under construction or being maintained. The CONTRACTOR shall furnish watchmen and keep them at their respective assignments to sufficient numbers to protect the work and prevent accident or damage. C. The CONTRACTOR will be held responsible for all injury or damage to the work or the public due to failure of barricades, signs, fences, lights, or watchmen to protect them. Whenever evidence is found of such damage to the work, the ENGINEER may order the damaged portion immediately removed and replaced by the CONTRACTOR at the CON- TRACTOR% own expense. The CONTRACTOR'S responsibility for the maintenance of barricades, signs, fences, and lights, and for providing watchmen shall not cease until the project has been completed and accepted in accord with the Contract Documents. D. The CONTRACTOR shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the work. The CONTRACTOR shall designate a responsible member of his organi- zation at the site whose duty shall be the prevention of accidents. This person shall be the CONTRACTOR's superintendent unless otherwise designated in writing by the CONTRACTOR to the OWNER and the ENGINEER. 01540 -1 1 1 1 1 1 ' 1 1 . 1 i 1 1 1 .1 1 1 1 E. The CONTRACTOR shall take all reasonable precautions for the safety of, and shall provide all reasonable protection to prevent damage, injury, or loss to: 1. all employees on the work and all other persons who may be affected thereby; 2. all the work and all materials and equipment to be incorporated therein, whether in storage or off the site, under the care, custody or control of the CONTRACTOR or any of his Subcontractors or Sub - Subcontractors; and 3. other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, fences, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. F. The CONTRACTOR shall comply with all applicable laws, ordinances, rules, regulations and lawful orders of any public authority having jurisdiction for the safety of persons or property or to protect them from damage. END OF SECTION 01540 -2 SECTION 01550 - WORKSPACE, ACCESS ROADS, YARDS AND PROTECTED AREAS PART 1 - GENERAL 1.01 DESCRIPTION A. Unless otherwise provided for in accord with these Contract Documents the CONTRACTOR aball at all times confine all work at the job site to the physical limits of the various workspaces, access roads and construc- tion yards designated by the Contract Documents. All work shall be conducted in conformance with the General Work Sequence and condi- tions of CONTRACTOR'. Use of Premises. 1.02 PROTECTED AREAS A. The CONTRACTOR shall at all times exclude all work, materials, personnel, and debris from all areas specified to be bounded by tree protection fencing, tree protection areas, environmentally sensitive areas and other similar areas designated by the Contract Documents or the ENGINEER. B. The CONTRACTOR shall install workspace fence, tree protection fence, silt fence or other barriers acceptable to the ENGINEER along the limits of all workspaces, access roads, construction yards and protected areas in conformance with the Contract Documents. C. Unless otherwise provided in these Contract Documents the CON- TRACTOR shall at his own expense provide all qualified labor, equip- ment and materials necessary to accurately and acceptably locate on the ground the position of all workspaces, access roads, construction yards and protected areas described in the Contract Documents. 1.03 ACCESS ROADS PART 2 - PRODUCTS Not Used). Access roads shall be utilized only for the transportation of equipment, materials and personnel required to perform the work at hand. Other transportation storage of material or equipment and the location of offices, sheds, sanitary facilities or any other use of access roads is prohibited. 01550 -1 PART 3 - EXECUTION The CONTRACTOR shall at his own expense determine acceptable methods and procedures, furnish all labor, equipment and materials necessary to conduct all work in conformance with this Section of the Specifications as well as all other terms of the Contract Documents. END OF SECTION 01550 -2 I eh 1 ESPEY, HUSTON & ASSOCIATES, INC. 1 SECTION 01560 - TEMPORARY EROSION CONTROLS AND ENVIRONMENTAL PROTECTION PART 1 - GENERAL 1.01 DESCRIPTION ' A. It is the intention of these Contract Documents to describe and provide for work and materials which will effectively protect the environment by way of minimizing the adverse effects of erosion, sedimentation, pollu- tion, and disturbances to vegetation. B. The ENGINEER will not attempt to dictate specific working methods, ' but it will be the CONTRACTOR's responsibility to ascertain beforehand that the methods be desires to use will be consistent with the intention of these Contract Documents and acceptable to the ENGINEER. PART 2 - PRODUCTS 2.01 SPECIFIED DEVICES 1 When properly applied and implemented by the CONTRACTOR in accord with these Contract Documents, the following temporary environmental I protection devices shall be acceptable to the ENGINEER. A. General Work Sequence I B. Sandbag Berms C. Silt Fences D. Stabilized Construction Entrance E. Tree Protection Collar 1 F. Workspace Fence 2.02 OTHER DEVICES 1 A. Other products, installations or requirements may be directed by the OWNER or ENGINEER in accord wtih the Contract Documents. 1 B. The CONTRACTOR may seek acceptance of other products or installa- tions in accord with the Contract Documents. 1 1 1 1 01560 -1 PART 3 - EXECUTION 3.01 PREVENTION OF ENVIRONMENTAL DAMAGE A. The CONTRACTOR shall continually monitor the effectiveness of all temporary erosion controls and environmental protection measures, taking immediate action in accord with the Contract Documents to stop any harmful occurrence, maintain or repair or replace any substandard installation, and repair, restore and mitigate the effects of the occurrence. B. The CONTRACTOR is responsible for discerning when the intention of this Section of the Specifications b not being upheld, in which case the CONTRACTOR shall immediately notify the ENGINEER who will promptly determine the appropriate remedial action in accord with the Contract Documents. C. Conditions which are hazardous to the environment may warrant emer- gency rectification work in accord wtih the Contract Documents. D. • Failure by the CONTRACTOR to prevent environmental damage may result b withholding of payment, imposition of requirements for indem- nification, and other action by the OWNER or ENGINEER, in accord with the Contract Documents. END OF SECTION 01560 -2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 SECTION 01561 - SANDBAG BERMS PART 1 - GENERAL 1.01 DESCRIPTION A. The work under this Section of the Specifications includes all labor, equipment and materials necessary to install sandbag berms in accord with the Contract Documents. B. Sandbag berms shall be installed at specified locations as indicated on the plans at the start of construction in those given areas. Sandbag berms are intended as perimeter control measures along the downslope or downstream side of the construction zone in areas where higher water velocities may be experienced, such as creek banks and bottoms or steep slopes. PART 2 - PRODUCTS 2.01 SANDBAGS Sandbags shall be of good quality burlap material or equivalent filled • with clean sand. PART 3 - EXECUT)ON 3.01 INSTALLATION AND MAINTENANCE A. Berms shall be constructed of sandbags stacked in at least a double row with bags tightly abutting each other and placed in a staggered arrange- ment to close spaces between bags. Berms shall be a minimum of 18 inches in width and height. B. The berms shall be inspected regularly, after every large storm event, and repaired when they become damaged or dislodged. Damage shall constitute torn bags, significant gaps between individual bags or between the bags and the ground, and /or lost sand fill. C. Accumulated silt and debris shall be periodically removed when it reaches a depth of 6 inches. D. Sandbag berms shall remain in place and in good condition until removal is specified by the ENGINEER. At that time, sandbag berms shall be completely removed, including sandbags, sand, and accumulated silt and debris. END OF SECTION 01561 -1 SECTION 01562 - SILT FENCES PART 1- GENERAL 1.01 DESCRIPTION A. The work under this Section of the Specifications includes all labor, equipment and materials necessary to install silt fence in accord wtib the Contract Documents. B. Silt fences shall be installed at specified locations, as indicated on the plans, in advance of construction in those given areas. Silt fences will also be installed along the top of bank at all creek crossings immediately following construction at those locations. Silt fences are intended as perimeter control measures on the downslope side of the construction zone. PART 2 - PRODUCTS 2.01 SILT FENCES Silt fences may be constructed on-site with raw materials, or pre- fabricated silt fences such as Mirafi Environfence, or equivalent, may be used. Silt fences constructed on -site shall be burlap, polypropylene fabric or nylon reinforced with polyester netting having a Mullen burst strength of at least 150 psi. The edges shall be treated to prevent unraveling. Steel or 2" x 2" wood fenceposts spaced a mazlmum of 8 feet apart and woven wire fencing with a maximum mesh opening of 4 inches shall be used for support of the fabric. PART 3 - EXECUTION 3.01 INSTALLATION AND MAINTENANCE A. Posts which support the silt fence should be installed on a alight angle toward the upslope and driven a minumum of 18 inches into the soil. B. The toe of the silt fence shall be trenched in with a spade or mechanical trencher, so that the downslope face of the trench is flat and perpen- dicular to the surface of the ground. C. The trench should be a minimum of 6 inches deep and 6 inches wide to allow for the silt fence toe to be laid in the ground and backfilled. Trench backfill material should be tightly compacted to prevent displacement. 01562 -1 1 1 1 1 1 1 1 1 1 1 1 .1 1 •1 D. For on-site fabricated silt fences, the fabric should be securely fastened to the woven wire, which it in turn securely fastened to the fence post. E. Silt fences shall be frequently inspected and repaired 0 they become damaged or dislodged. Damage shall constitute tears or openings in the fabric, separation of fabric from woven wire or woven wire from fence posts, uprooting of trenched -in toe, loosened or broken posts, and/or a downslope angle of repose which allows water to flow over the top of the fence rather than being retained behind it. All repairs should be made promptly to ensure proper functioning of the silt fences. F. Accumulated silt and debris shall be removed when ft reaches a depth of 6 inches and disposed of in an approved permanent disposal site. G. Silt fences shall remain in place and in good condition until adequate restorative vegetation establishment or other permanent stabilization of the construction sone has been achieved. After that period, silt fences shall be completely removed, including fabric, woven wire, posts and accumulated silt and debris. Toe trenches shall be filled or leveled to original contours.: END OF SECTION 01562 -2 • e ESPEY, HUSTON & ASSOCIATES, INC. 1 SECTION 01564 - STAIU 1ZED CONSTRUCTION ENTRANCE PART 1 - GENERAL 1.01 DESCRIPTION A. The work under this Section of the Specifications includes all labor, ' equipment, and materials necessary to install a stabilized construction entrance in accord wtih the Contract Documents. ' B. Stabilized construction entrances shall be installed at specific locations as indicated on the plans or as directed by Engineer in advance of construction in those given areas. Stabilized construction entrances and ' requirements for their use is intended to reduce or eliminate the tracking or flowing of sediment onto public rights -of -may or similarly maintained private drives. C. Stabilized construction entrances shall remain in place until the con- struction site is no longer accessed via the road in question, generally at the end of the project time. ' PART 2 - PRODUCTS 2.01 AGGREGATE Aggregate shall be coarse aggregates consisting of clean durable gravel ' or crushed hard stone of the following size gradation or equal: Sieve Size Percent Passing ' 100 1-1/2" 60 -90 3/4" 0 -20 1/2" 0 -5 ' PART 3 - EXECUTION 3.01 DIMENSIONS The stabilized construction entrance is a coarse aggregate mat laid at least eight inches thick and of the full width of the construction access drive. The aggregate mat shall be as long as necessary to be effective but no less than 50 feet long, terminating at the right -of -way or drive from which access is gained. 1 1 01564 -1 1 1 1 , 1 1 1 1 1 1 1 1 1 1 1 h &SPEY. HUSTON & ASSOCIATES, INC. 3.02 USE AND MAINTENANCE A. The entrance shall be maintained in a condition which will prevent tracking or flowing of sediment onto public rights -of -way. This may require periodic top dressing with additional stone as conditions demand and repair and /or cleanout of any measures used to trap sediment. All sediment spilled, dropped, washed or tracked onto public rights - of-way must be removed immediately by CONTRACTOR. B. When necessary, wheels must be cleaned to remove sediment prior to entrance onto public right-of -ray. When washing is required, it shall be done on an area stabilized with crushed stone which drains into an approved sediment trap or sediment basin. All sediment shall be prevented from entering any storm drain, ditch, or watercourse through use of sand bags, silt fences or other approved methods. END OF SECTION 01564 -2 SECTION 01570 - TRAFFIC REGULATION PART 1- GENERAL 1.01 DESCRIPTION A. The CONTRACTOR shall make adequate provisions to allow reasonable vehicular and pedestrian traffic, including the use of driveways, to proceed safely with minimum inconvenience except during actual con- struction operations such as trenching or pipe laying. Such provisions may include temporary fill and /or bridging, temporary surfacing with gravel, stone or paving, or such other means as the ENGINEER may approve. - B. Sidewalks must not be obstructed except by special permission of the ENGINEER. Access to private dwellings and to commercial establiab- ments must be provided at all times. C. If diversion of traffic is approved by the ENGINEER at any location, the CONTRACTOR shall make arrangements satisfactory to the ENGINEER for the diversion and the schedule of operations, and shall at his own expense provide and maintain all roadways, bridges or other facilities necessary for such diversion of traffic. At least three working days prior to the beginning of such traffic diversion, the CONTRACTOR shall notify the Police Department, Fire Department, Texas State Department of Highways and Public Transportation, and the owners or agents of all property likely to be affected by the diversion. The same parties shall be notified when normal traffic flow is restored. D. All traffic regulation shall be conducted in accord with these Contract Documents and the laws and ordinances of any agency having jurisdiction. END OF SECTION 01570 -1 SECTION 01600 - MATERIAL AND EQUIPMENT PART 1 - GENERAL 1.01 MATERIALS FURNISHED BY CONTRACTOR Except where otherwise specifically provided, the CONTRACTOR shall furnish and install all materials and incidental accessories and shall complete the installation and place it in normal service. All such materials furnished by the CONTRACTOR shall conform to the stan- dards set forth in these Contract Documents. The CONTRACTOR shall be responsible for all material furnished by biro and be shall replace at Ms own expense ill such material that is found to be defective in manufacture or that has become damaged in handling after delivery by the manufacturer. 1.0Z CARE AND HANDLING OF MATERIALS AND EQUIPMENT A. Except where otherwise directed, all materials shall be unloaded at the point of delivery, hauled to and distributed at the site of the project by the CONTRACTOR; they shall at all times be handled with care to avoid damage. In loading and unloading, they shall be lifted by proper equipment in such a manner as to avoid shock. Under no circumstances shall they be dropped. Pipe handled on akidways must not be rolled against pipe already on the ground. The CONTRACTOR shall be responsible for the safe storage of material furnished by or to him, and accepted by him, and intended for the work, until it has been incorporated in the completed project. B. All materials and equipment shall be so placed and used and the work operations so conducted that at no time do they obstruct, endanger or inconvenience the public or injure or damage any public or private property. Materials and equipment shall be stored in a neat, orderly manner, and at no time shall there be more tools, equipment, or materials on the job site than is necessary to avoid delay of the construction operations. Excess materials shall be stored elsewhere at the CONTRACTOR expense. Such excess materials shall not be stored in easements, right -of -way, or other public facilities. C. The entire job site shall be kept clear of trash, refuse, damaged or excess materials, excavated spoil, etc., and the site shall be kept neat, clean and orderly at all times. 01600 -1 D. The CONTRACTOR shall at all times handle all material and equipment in accord wtib the specifications of Workspace, General Work Sequence and other terms of the Contract Documents. 1.03 WASTE MATERIAL All waste material, including but not limited to debris, cleared brush and vegetation, excavated material unsuitable for use as backf[il and exca- vated material in excess of backfill requirements shall become the property of the CONTRACTOR and shall at his expense be promptly removed from the jobsite and disposed of in a legal manner. The CONTRACTOR shall indemnify the OWNER and ENGINEER against all claims arising from the disposal of waste material. 1.04 ERODEABLE MATERIALS ' All erodeable materials shall at all times be handled and situated so as to minimize the potential effects of erosion and sediment. The CONTRAC- TOR shall develop procedures which minimize the exposure of erodeable materials in flood -prone areas. The CONTRACTOR shall maintain acceptable erosion control devices around erodeable materials at all times to prevent siltation hazards. 1.05 HAZARDOUS FLUIDS A. The CONTRACTOR shall handle all hazardous fluids in conformance with all laws and regulations concerning their use. B. Temporary storage and handling of fuels, oils, hydraulic fluids and all other hazardous fluids shall be accomplished in a manner acceptable to the ENGINEER. The CONTRACTOR shall verify the acceptability of his procedures prior to implementation. Procedures shall include provisions designed to prevent contamination of soil or water and prevention of hazard to people, property and the environment. END OF SECTION 0160D -2 DIVISION 2 SITE WORK 02000 -1 e ESPET, HUSTON & ASSOCIATES. INC. 1 SECTION OUZS - TRENCHING, EMBEDMENT, BACK ILL, AND COMPACTION PART 1 - GENERAL 1.01 DESCRIPTION I A. The work under this Section of the Specifications consists of furnishing all labor, equipment and materials, and performing all operations in connection with the excavation, trenching, embed- 1 went, backfill and compaction required to install the pipelines shown on the Drawings, and as specified. I B. Unless otherwise specified the work under this Section of the Specifications shall be conducted only upon completion of all work required to be conducted during Phase One of the General Work Sequence. C. All work including movement of equipment, materials and person- nel shall be confined to the workspace allocated for such work by the Contract Documents. No work shall encroach upon any tree protection easement or similarly protected space. ' D. Excavation shall include the removal of any trees, stumps, brush, debris, or other obstacles that may obstruct the line of work as allowed by the Contract Documents, and the excavation and ' removal of all earth, rock or other materials to the extent necessary to install the pipe and appurtenances in conformance with the lines and grades shown on the Drawings, and as specified by the Contract Documents. 1 E. Backfill shall include the refilling and consolidation of the fill in the trenches and excavations up to the surrounding ground surface ' or grade indicated on the Drawings and as specified by the • Contract Documents. 1 F. Where construction enters the limits of State, County or City rights-of-way, the requirements of these agencies shall be met. 1.02 QUALITY ASSURANCE 1 A. Density. All references to "Maximum dry density shall mean the maximum dry density defined by the 'Maximum Density- Optimum I Moisture Test; ASTM D-698, unless otherwise specified. Deter- mination of the density of backfill in place shall be in accordance 1. 1 02225 -1 PART 2 - PRODUCTS with the requirements of ASTM -2922, "Density of Soil and Soil - Aggregate in Place by Nuclear Methods (Shallow Depth)." The OWNER will provide for initial density testing of in -place backfill; however, the CONTRACTOR shall pay for all additional density testing of backfills found not to be within the minimum require- ments of the Specifications. B. Sources and Evaluation Testing. Materials to be used for embed- ment and granular material to be used for select backfill shall be obtained in 'accordance with a sampling plan and ASTM D -75, Sampling Aggregates. Testing of materials to certify conformance with the specification requirements shall be performed by a testing laboratory approved - by the ` OWNER and paid by the CONTRACTOR. CONTRACTOR'S testing agency shall perform tests upon change of source and at sufficient intervals to certify conformance of all select material furnished for use on this project. C. Trench Dimensions. The sides of all trenches shall be cut as nearly vertical as possible. The french width at the bedding envelope (from six inches below to twelve inches above the outer projections of the pipe or accessories) shall be as indicated on the Drawings. Pipe lain in excessively wide trench or in trench formed or bordered by loose fill, rubble or boulders will not be accepted. Where these conditions occur the entire width between the m- disturbed walls of the excavation must be backfilled as pipe trench and compacted to 90% of maximum dry density to an elevation at least twelve inches above the proposed top of pipe. The trench may then be re- excavated to the proper grade and dimension. No extra compensation will be made to the CONTRACTOR for any additional material used to rectify unsound or excessively wide trench conditions. 2.01 MATERIALS FOR EMBEDMENT OF PIPE A. Unless otherwise specified, pipe of any size shall be installed in crushed stone bedding. Crushed stone for pipe bedding shall be clean, granular crushed limestone free of mud, clay, vegetation or other debris and shall meet ASTM 33 current standards for stone quality. Size gradations shall be as follows: 02225 -2 1. For pipe 24 inches in internal diameter and greater. Sieve Size Percent Passing 1-34" 100% 34" 90 - 100% #4 Mesh 0 10% #8 Mesh 0 -'S% 2.02 BACKFILL MATERIALS A. Backfill material within the bedding envelope shall be embedment material as specified. B. Unless otherwise specified the backfill from the top of the bedding envelope to within 6 inches of the top of the fully restored trench may ordinarily include the excavated soil materials meeting the following criteria: 1. All rock cuttings or boulders shall be no longer than 8 inches in their greatest dimension. 2. Coarse and fine materials shall be sufficiently mixed and balanced to be essentially free of voids after compaction. 3. No material, of a perishable, spongy or otherwise unsuitable nature shall be used. C. If excavated rock does not contain sufficient fines to satisfy the specification for backfill it may be crushed, mixed and graded to satisfy these conditions or material conforming to the specification shall be furnished and used as backfill instead of excavated material, at no additional expense to the OWNER. 02225 -3 D. Unless otherwise specified, the top 6 inches of the fully restored trench shall be backfilled with topsoil. PART 3 - EXECUTION 3.01 TRENCH EXCAVATION A. ' Unless otherwise specified, top soil and grass shall be stripped a minimum of 6 inches over the excavation site and stockpiled separately for replacement over the finished grading areas. B. Trenches shall be excavated to the lines, grades and dimensions as shown on the Drawings and as specified. The centerline of the trench shall be on the centerline of the pipe. C. Pipe shall not be lain in oversized trenches or trenches cut in unsound material. 1. Excessively wide trenches shall be backfilled, compacted and re- excavated as specified. 2. Should the bottom of the trench become an unstable founda- tion for the pipe through the failure of the CONTRACTOR to adequately perform, the CONTRACTOR shall remove the unstable material and fill the trench to the proper subgrade with approved embedment material. No extra compensation will be allowed for this material or work. 3. Should the undisturbed material encountered at the grade depth constitute, in the opinion of the OWNER, an unstable foundation for the pipe, the CONTRACTOR shall be required to remove such unstable material and fill the trench to the proper subgrade with approved embedment material. Pay- ment will be made to the CONTRACTOR at the unit price per cubic yard set forth in the Bid Schedule. 3.0Z SHEETING AND SHORING A. In caving ground or in wet, saturated or flowing or otherwise unstable materials, or where constrained by limited workspace or the requirements of a tree protection easement or similar area the sides of all trenches and excavations shall be adequately sheeted and braced, to maintain the excavation from slides or cave -ins and to provide safety for workmen. 02225 -4 ESPEY, HUSTON & ASSOCIATES, INC. B. In all cases, excavation shall conform to the requirements of the Occupational Safety and Health Act of 1970. C. Sheeting and shoring shall not be left in place. 3.03 TRENCH DEWATERING A. All dewatering activities shall conform to the Contract - Documents. . f 3.05 PIPE EMBEDMENT 02225 -5 B. There shall be available at all times, in good working order, sufficient pumping equipment and other material as may be required to mitigate pumping discharge effects, to remove any water that accumulates in the trench. C. In all cases, accumulated water in the trench shall be removed prior to placement of embedment, pipe or backfilL 3.04 EXCAVATED MATERIALS A. Top soil shall be stripped and stored for re-use in accord with the specifications. B. Excavated materials unsuitable for use as backfill or in excess of bckfill requirements shall be promptly removed from the work site in accord with the specifications. C. All handling, storage and movement of excavatd materials &hall be confined to the designated workspace and shall not encroach on any tree protection easement or similar area. A. The dimensions of the bedding envelope, the condition of the trench and the material available for bedding the pipe shall all be in conformance with the Contract Documents. B. The initial layer of embedment placed to receive the pipe shall be brought to grade and dimensions specified, and the pipe shall be placed thereon and brought to grade by tamping or by removal of the excess amount of embedment under the pipe. Adjustment to grade line shall be made by scraping away or filling with embed- ment material -- wedging or blocking up of pipe will not be permitted. Each pipe section shall have a uniform bearing on the embedment for the length of the pipe, except immediately at the joint. All embedment shall extend the full width of the trench. 1 1 ESPEY. HUSTON & ASSOCIATES, INC. C. After pipe bas been placed, joints made and inspected, and blocking or braces installed as specified or required, the bedding material *ball be placed simultaneously on both sides of the pipe and worked carefully into place without disturbing the pipe alignment. The 1 embedment shall be placed and tamped to fill the specified bedding envelope. 3.06 BACKFE.L ABOVE THE BEDDING ENVELOPE 1 A. Material used to backfill above the bedding envelope *ball conform to the specifications. 1 B. All backfill above the bedding envelope shall be consolidated to provide a density compaction of at least 90% of the medium dry density. C. The CONTRACTOR shall provide an acceptable method for con- solidation of material 12-lncbes or more above the pipe. The ' material may be placed mechanically or by other means to provide the compaction required. Such material shall be tested and approved by the ENGINEER before continuing. The initial test ' section shall be a minimum of 100 lineal feet. Material not meeting required specification *ball be removed and replaced at no additional cost to the OWNER. ' D. Backfifl of the top 6 inches of the excavation shall conform to the Contract Documents. ' END OF SECTION 1 1 1 - 1 02225 -6 . :1 1 1 1 1 1 1 1 . 1 1 1 1 1 1 1 1 SECTION 02401 - DEWATERING PART 1- GENERAL 1.01 DESCRIPTION A. The CONTRACTOR shall determine acceptable procedures for dewatering as specified, required or necessary to conduct the work for this project. B. The CONTRACTOR shall be responsible for the stability of all temporary and permanent slopes, grades, foundations, materials and structures during the course of the work. The CONTRACTOR shall repair and replace all slopes, grades, foundations, materials and structures damaged by water, both surface and subsurface, to conditions equal or better than those existing prior to the damage at no additional cost to the OWNER. C. All work under this section shall be confined to the allocated workspace for the project and shall not encroach on any tree protection easement or similar area D. Water shall be discharged from dewatering activities in such a manner that scouring or erosion will not occur. All discharges shall be to the upstream or upslope side of properly emplaced erosion control structures. PART Z - PRODUCTS E. No water shall be discharged directly into creeks, streams or other drainageways whether other water is present or not, without first being filtered of sediments. 2.01 EROSION CONTROL DEVICES A. All erosion control devices referenced in this section shall be utilized in conformance with the Contract Documents, and satisfy the requirements of the Drawings and Specifications. 2.02 QUALITY ASSURANCE A. The ENGINEER shall retain the authority to determine the accep- tability of dewatering procedures and procedures relating to the control of runoff from dewatering activities. Upon determination 02401 -1 PART 3 - EXECUTION 3.01 SILTATION CONTROL that the CONTRACTOR is not in compliance with the Contract Documents the ENGINEER may atop all work until the work is in compliance with the Contract Documents. This in no way relieves the CONTRACTOR of any of hi:: responsibilities under this Con- tract. A. Where water discharged from pumps or other dewatering opera- tions is not substantially clear, ft shall be filtered prior to entering any creek, stream or draiaageway or prior to flowing out of the designated work space. B. The CONTRACTOR shall devise acceptable procedures for filter- ing water as required. C. Where the CONTRACTOR or ENGINEER determines that temporary ponding of water is required to allow settlement of silt, the following minumum requirements shall be satisfied: 1. Ponds shall be formed by construction of Sand Bag Berms or Rock Dams in full compliance with the Specifications. Ponds formed by erodeable materials will not be acceptable. 2. The pond shall be periodically inspected and maintained in conformance with the specifications for those materials utilized to form the structure and as neces- sary to assure the proper filtering action. Silt removed from the pond shall be treated as waste material. 3. Discharge from ponds shall be refiltered if not clear. D. Where the CONTRACTOR or ENGINEER determines that filtration of sheet flow or other generally dispersed, low velocity water flow is required, the following minimum requirements shall be satisfied: 1. Filtration of sheet flow water shall be accomplished using single or multiple Silt Fences or Brush Dams installed and maintained in conformance with the speci- fications. 2. Filtering devices shall be configured such that all water shall be forced through the filtering media with no opportunity for undercutting or otherwise circumventing the filter. 02401 -2 3.01 EROSION CONTROL. A. Where discharges from pumps, ponds or other dewatering proce- dures are necessary in erodeable areas, the CONTRACTOR shall take steps to minimize the erosion potential from the discharge. B. The CONTRACTOR shall determine acceptable procedures for minimising erosion damage. C. When the CONTRACTOR determines that an energy dissipating apron is necessary, the apron shall be constructed of rip with minimum stone diameter of 6 inches. The apron shall be no less than 11 inches deep (thick). The apron shall be of a width sufficient to catch the flow from the discharge without allowing undercutting or scouring at the edges. The length of the apron shall be no less than six time the diameter of the discharge pipe. 3.03 CLEAN UP A. All filtration devices, ponds, dams, energy dissipations and aprons constructed in support of dewatering activities shall be dismantled as soon as their necessity is past. B. All silt and other debris collected aball be treated as waste material in accord with the specifications. C. All areas affected by dewatering activities shall be restored promptly upon completion of those activities in accord with the specifications. END OF SECTION 02401 -3 SECTION 02480 = REVEGETATION OF GRASSES PART 1 - GENERAL 1.01 DESCRIPTION A. The work under this Section of the Specifications consists of furnishing all supervision, labor, equipment, material and installa- tion of grasses for ground cover and permanent erosion control of the jobsite. 1.02 SUPERVISION PART 2 - PRODUCTS 2.01 SEED MIX B. Revegetation shall be a continual process during the construction and will immediately follow completion of construction and testing of each section of the line in conformance with the Section 01014 - Work Sequence. All work under this Section of the Specification shall be conducted during Phase Four (4) of the General Work Sequence except work described herein as Maintenance and watering, which shall be conducted as deemed necessary by the CONTRACTOR. A. The work under this Section of the Specifications shall be per- formed by or under the direct on -site supervision of an individual with proven expertise with the procedures and techniques required by these specifications. That person shall be acceptable to the ENGINEER. A. Revegetation shall be accomplished using the following mixtgure of grasses at the indicated rates of application: Little bluestem 3 lbs /ac or 0.1 lbs /1000 sq ft Sideoats grama 5 lbs /ac or 0.2 lbs /1000 sq ft Green sprangletop Z lbs /ac or 0.1 lbs /1000 sq ft Buffalograss 5 lbs/ac or 0.2 lbs /1000 sq ft Bermudagrass 5 lbs/ac or 0.2 lbs /1000 sq ft Total Seeding Rate 20 lbs /ac or 0.8 lbs /1000 sq ft PART 3 - EXECUTION 3.01 GROUND PREPARATION Immediately following completion of construction, excess spoil and debris shall be removed and the construction area shall be graded to the original 02480 -1 1 1 1 1 1 1 1 1 1 1 1 : 1 1 1 e 1 ESPEY, HUSTON & ASSOCIATES, INC. with Section 01014 - Work Sequence, excess spoil and debris shall be removed and the construction area shall be graded to the original contours existing prior to construction. The surface of the ground should be smooth with no large rocks, stumps, or other debris. Topsoil of sandy loam, loam or clay loam and free of tree roots, rocks greater than 2 inches in diameter and other debris shall then be uniformly spread over all disturbed areas to a minimum depth of 4 inches. The topsoil should be compacted by tracking a bulldozer with cleated treads vertically on the slopes to create horizontal erosion checks in the surface. 3.02 SEEDING AND MULCHING OR MATTING A. Reseeding shall immediately follow topsoiling with the specified mixture of grasses and rates of application. Seed shall be broadcast evenly over the topsoiled areas by hand or mechanical broadcaster. Mulching shall immediately follow seed application. B. Mulching may be accomplished by a number of methods and with various materials. Hay or straw material may be spread uniformly over the ground either by hand or with a mulching or shredding machine. Small brush or tree limbs which are removed during construction may also be passed through a shredder and spread evenly over the ground. Mulches shall cover the ground completely to a minimum depth of Z inches. Large concentrated accumulations should be avoided. C. The CONTRACTOR shall omit mulching and place excelsior matting in conformance with Section 02270 - Critical Slope Protection - Excelsior Mat, over all areas revegetated in accordance with this Section of the Specifications and having a slope exceeding 10 %. 3.03 MAINTENANCE AND WATERING A. The CONTRACTOR shall maintain and water the seeded area as necessary to establish acceptable ground coverage. B. Revegetation shall be acceptable when the grass has grown at least 1" high with 85% coverage and no bare spots larger than 10 square feet exist. END OF SECTION 02480 -2 e s ESPEY, HUSTON & ASSOCIATES, INC. SECTION 02491 - TREES PART 1 - GENERAL 1.01 DESCRIPTION Trees which are to be protected during construction include those indicated on the plan sheets within tree protection areas or outside of access or temporary work easements. The Contractor shall be respon- sible for the prevention of any and all damage to such trees. Unauthorized removal of or damage to such trees will be compensated at $10,000 per tree. Compensable damage as determined by the ENGINEER shall be defined as major damage which may result in death or loss of vigor and may include toppling; broken or fractured main stem (trunk); wounds to the main stem which are deeper than 25% of the diameter or cover a surface area greater than one square foot; breakage of more than 25 %n of the crown; encroachment of equipment, spoil, construction materials, or toxic'chemicals (fuel, oil, solvents, herbicides, etc.) within the designated tree protection area around each tree; or exposure and damage to more than 25% of the root zone as measured by diameter of tree crown. Pruning, as necessary for equipment movement, will be permissable with at least 24 hours prior notice to the ENGINEER. Pruning practices shall follow those outlined in the following section or by specific direction of the ENGINEER. If any tree to be protected presents severe restriction to working conditions, the Contractor shall confer with the ENGINEER. PART 2 - PRODUCTS (Not Used). PART 3 - EXECUTION 3.01 PRUNING Pruning shall be implemented only as necessary to allow equipment movement under or around trees. Such pruning shall be performed under the following guidelines: A. All limbs or branches to be pruned shall be cut or severed cleanly with saw or shears to avoid any breakage. Cuts should be made as flush as possible to the branch that is to remain. B. Large limbs or branches should be removed in smaller sections in order to avoid falling damage to surrounding vegetation. 02491 -1 1 e ESPEY, HUSTON & ASSOCIATES. INC. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 C. All cut surfaces on pruned trees shall be immediately treated with an approved tree wound dressing. Pruning of trees specifically indicated within tree protection areas shall be implemented only after prior notice to the ENGINEER. Pruning procedures shall follow those given above or as otherwise specified by the ENGINEER for each particular instance. Unauthorized pruning of such trees shall be subject to compensation as specified in the Contract Documents. 3.02 TREATMENT OF MINOR WOUNDS OR BREAKAGES Small wounds or minor breakages (i.e., less than those damages specified as "Compensable Damages" to any tree designated within a tree protec- tion area or any other tree outside of the construction zone as may result from equipment moving or any other construction activity shall be treated according to the following procedures: A. Scrapes, gouges, debarking or any other minor wounds or abrasions to the main stem or major limbs shall be cleaned of loosened tissues as necessary with saw, shears or wood chisel to result in clean, even edges and shall be immediately treated with an approved tree wound dressing. B. For minor breakages or fractures to tree limbs or branches, the affected part shall be cleanly sawn or sheared several inches below the damaged area in order to result in a clean sever which shall be immediately treated with an approved tree wound dressing. C. Exposed, broken or scraped root structures shall be cleaned as above and immediately treated with approved tree wound dressing. Exposed roots should be recovered with sandy loam soil or equiva- lent to original depth as soon as construction proceeds past the affected area. D. Breakages or fractures to the main stem (trunk), major wounds or limb breakages, or toppling of any trees to be protected or preserved during construction shall require immediate consultation with the ENGINEER to determine correct treatment procedures. END OF SECTION 02491 -2 SECTION 2601 - SEWER MANHOLES PART 1 - GENERAL 1.01 SCOPE OF WORK Work wider this section of the specifications includes all labor, materials, and equipment necessary to fabricate, assemble, install and test precast sewer manholes with base, stubs, risers, reducers, covers, fittings and all other appurtenances complete in place. 1.02 REFERENCES The specifications of the American Society for Testing and Materials (ASTM) referred to in this section shall be the latest edition and include: ASTM A48 ASTM C33 Specifications for Concrete Aggregates ASTM C76 Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe ASTM C150 Specifications for Portland Cement Concrete ASTM C361 Reinforced Concrete Low -Head Pressure Pipe ASTM C443 Joints for Circular Concrete Sewer and Culvert Pipe Using Rubber Gaskets ASTM C478 Precast Reinforced Concrete Manhole•Sections ASTM C923 Resilient Connections Between Reinforced Concrete Manhole Structures and Pipes ASTM C425 Compression Joints for Vitrified Clay Pipe and Fittings 1.03 SUBMITTALS A. All submittals shall comply with the requirements of Section 01340 - Submittals, and include all data required by this section of the Specifications. B. CONTRACTOR shall submit drawings and schedules showing full details including dimensions, layouts, thickness, material details, steel area, joint details, manufacturing and installation tolerances and other data pertinent to the manufacture, fabrication and installation of the manhole, stubs, fittings, specials and appurtenances. The CONTRACTOR shall furnish an affidavit of compliance with all specifications referenced herein. C. The CONTRACTOR shall submit the results of manhole testing within 5 days of test completion and shall include station of manhole tested, and the computed exfiltration or infiltration rate, as applicable. 02601 -1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 PAEBT a- PRODUCTS 2.O1 PRECAST TYPE "T" MANHOLE A. Where indicated as Type "T" manhole on the Drawings, the manhole shall be precast reinforced concrete fabricated as a vertical tee with the riser stub being 48 inches internal diameter. The tee section shall comply with specification Section 02612 - Reinforced Concrete Wastewater Pipe. B. Precast Type "T" manholes shall be of the strength classification indicated on the plans for the pipe at that location. C. Type "T" manholes shall be precast with eyes and adaptors for stubs as shown on the Drawing and specified in this section and in conformance with detailed drawings and schedules of the manholes, eyes and adaptors submitted by the CONTRACTOR and approved by the ENGINEER. D. Type "T" manholes shall be bedded in concrete encasement completely filing the bedding envelope around the "T ", taking care to keep all concrete away from all resilient pipe joints at the ends of the "T" and stubs. Encasement concrete shall contain 4 sacks of cement per cubic yard (minimum) and shall have a 28-day compressive strength of 2,000 psi (minimum). 2.48 STANDARD PRECAST MANHOLE BASE A. Unless otherwise noted on the Drawings, manholes shall be of the precast base type conforming to ASTM C-478. The base shall be precast with eyes and adaptors for stubs as shown on the Drawings and specified in this Section and in conformance with detailed drawings and schedules of the manholes, eyes and adaptors submitted by the CONTRACTOR and approved by the ENGINEER. B. The manhole base shall have precast or field grouted channel(s) sloping smoothly from influent to effluent eyes and designed to prevent reverse flow. C. The manhole base shall be 48 inches internal diameter (minimum). Where the internal diameter of the manhole exceeds 48 inches, a flat lid eccentric reducer in conformance with ASTM C-478 shall be provided with the 48 -inch riser opening situated directly above the effluent line eye. The distance from the bottom of the flat lid reducer to the flow line at the center of the manhole shall be equal to or greater than the internal diameter of the manhole. 02601 -2 D. All base and riser joints shall be of the confined 0-ring type in conformance with ASTM C-443. 2.03 EYES, ADAPTORS, CONNECTORS AND STUBS A. Manholes shall have eyes precast for influent and effluent lines of the size and material indicated on the Drawings. Manholes shall have eyes or integral stubs precast at the orientation indicated on the Drawings. Unless otherwise'aoted stub eyes shall be elevated to provide a crown -to -crown match with the effluent line. B. Eyes for lines or stubs 6 inches through 12 inches internal diameter shall provide a watertight compression joint between manhole base and the line conforming to ASTM C-425. , . C. Eyes for lines or stubs 15 inches through 24 inches internal diameter shall provide a watertight flexible "boot type" connector between manhole base and the line conforming to ASTM C -923 D. Eyes for lines or stubs larger than 24 inches internal diameter shall provide a watertight resilient gasket connector between manhole base and the line conforming to ASTM C -923. E. Joints between manhole base and lines or stubs shall permit 634 degrees of deflection in any axis while complying with all test requirements. However, no deflection within this joint shall be required to achieve the orientations and deflections indicated on the drawings. F. Stubs shall project one full standard pipe joint length beyond the face of the manhole or 10 feet, which ever is less. In no case shall any stub project outside of the permanent easement provided. Unless otherwise noted, stubs shall have 1% grade into the manhole. Stub ends shall be plugged using a temporary watertight plug designed for the pipe material utilized. Plugs shall be thrust blocked against undisturbed earth, taking care that concrete does not interfere with any resilient joint. 2.04 RISERS AND REDUCERS A. Risers and rducers shall be precast concrete in conformance with ASTM C-478 and having confined 0-ring joints conforming to ASTM C-443 B. Risers shall be 48 inches internal diameter. 02601 -3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 t 1 1 3.02 TESTING C. Risers atop type 'T" manholes and precast base manholes of 48 inches internal diameter shall be topped with a concentric reducer of 48 inches x 24 inches. D. Risers atop precast base manholes of greater than 48 inches internal diameter shall be topped with an eccentric reducer of 48 inches x 24 inches and oriented to match the flat lid reducer on the manhole base. 2.05 RINGS AND COVERS A. Manhole covers located within the pavement of public rights -of- way shall be unbolted. All other manhole covers shall be bolted. B. Manhole covers shall be flush with finished ground or pavement. No more than four grade rings shall be used per manhole. C. Manhole rings and covers shall conform to the specifications for wastewater manhole rings and covers of the City of Round Rock Water and Wastewater Department. PART 3 - - EXECUTION 3.01 GENERAL A. Unless noted otherwise the manhole base shall be bedded on crushed stone at proper grade. Six inches of crushed stone shall be placed to provide a firm foundation for the manhole. The CONTRACTOR shall level and plumb the base prior to setting the precast manhole riser sections on the precast concrete base. B. Dust, dirt, and foreign matter shall be removed from the joint surfaces. Gasket and joint surfaces shall be lubricated with a lubricant recommended by the manufacturer for use with rubber O- ring concrete pipe joints. Lubricant shall be applied with a brush, cloth pad, sponge, or glove. A smooth round object shall be inserted under the gasket and run around the circumference two or three times to equalize stretch in the gasket. A. Frequency of Testing - At no time shall there be more than 1000 linear feet of pipeline installed and otherwise complete in place where manholes within this 1000 linear feet have not been successfully tested in accordance with this specification. All tests shall be successfully completed prior to the placement of any grout, mortar or any material other than the specified gasket or connector at the pipe and manhole joints 02601 -4 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 i • 1 1 02601 -5 END OF SECTION r B. Acceptable Test Methods - Manholes shall be tested in accordance with the infiltration or exfiltration test as described in this section of the specifications. C. Exfiltration Test - The manhole shall be completely filled (to within 2' of casting) with water provided by the CONTRACTOR for its complete length. The maximum head at any point shall not exceed twenty -five (25) feet unless otherwise specified. After the manhole has been filled and allowed to stand for twenty -four (24) hours the amount of exfiltration shall be calculated. Any amount above the maximum allowable exfiltration rate shall be cause for rejection. The maximum allowable exfiltration and infiltration shall be 0.1 gallons per hour per foot inside diameter per foot of head. 1 1 1 1 1 1 1 1 1 1 1 1. 1 1 1 �1 i 1 1.02 REFERENCES 1.03 SUBMITTALS 1.04 QUALITY ASSURANCE a f a 4.- SECTION 02612 - REINFORCED CONCRETE WASTEWATER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED +S • The work to be performed under this section of the specifications shall include the labor, materials, tools, equipment and related items required to furnish and install all reinforced concrete pipe for gravity flow wastewater lines. The specifications of the American Society for Testing and Materials (ASTM) referred to in this section are listed below with their serial designation: ASTM C- 33 -74a Specifications for Concrete Aggregates ASTM C76 -83 Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe ASTM C150 -76 Specification for Portland Cement Concrete ASTM C361 -83a Reinforced Concrete Low Head Pressure Pipe ASTM C443 -78 Joints for Circular Concrete Sewer and Culvert Pipe Using Rubber Gaskets A. Submittals shall comply with the requirements of the Contract Docu- ments. B. The CONTRACTOR shall submit drawings and schedules showing full details of fabrication of pipe, fittings, specials and appurtenances, dimensions, layouts, wall thickness, concrete strength, steel area, joint details, and other data pertinent to the manufacture and fabrication of the pipe, fittings, specials, and appurtenances. The ENGINEER's approval shall be secured prior to pipe installation. Submittals for Joints are described in this section, part 2.05, paragraph B. C. The CONTRACTOR shall submit a tabulated layout schedule, with refernece to the stationing and grade lines shown on the Drawings. The ENGINEER'S approval shall be secured prior to installation. A. The CONTRACTOR shall furnish an affidavit that the pipe, specials, fittings, and appurtenances furnished comply with all provisions of this and the ASTM Specifications as stipulated in this section (to be approved by the ENGINEER prior to installation of any pipe). 02612 -1 , 1 1 1 1 1 1 i PART Z - PRODUCTS 1 1 1 1 1 1 i Z.01 GENERAL 02612 -2 B. Pipe Marking. Each pipe segment or fitting shall be plainly and permanently marked in accordance with ASTM C76 -83 paragraph 17. In addition, bends shall have the angle turned by the bend marked on the bend as described in ASTM C76 -83, paragraph 17.3. C. The OWNER and the ENGINEER shall at all times have free access to the manufacturer's plant while production is in progress, and may at any time refuse to accept pipe made when the plant is failing to follow the stipulations of the specifications in regard to workmanship or failing in provisions to ensure a uniform product coming within the permissible variations of the specifications as to size, thickness, position of rein- forcing steel, or curing of the pipe. The OWNER or ENGINEER may reject pipe if adequate means and methods are not provided to ensure manufacture of a product of uniform high quality. A. All reinforced concrete pipelines, Type 'T" manholes and fittings shall be of the size and class indicated on the Drawings and shall comply the following requirements of ASTM C76 -83: paragraphs 1 -4, 5.1.2, 5.2, 6, 7.1, 8 -10, 11.1, 11.2, 11.4, 11.5, and 12 - 17. In addition, reinforced concrete pipe joints shall comply with the following requirements of ASTM 361 -83a: paragraphs 6.9 and 8. B. The pipe class as shown on the Drawings represents minimum allowable pipe class with a maximum trench width as shown on the Drawings. Should the CONTRACTOR choose to reduce the number of various pipe classes by substituting a higher class than specified in certain areas, he may do so provided the above minimum requirements are met or exceeded, and provided the substitution is at no added cost to the OWNER and provided the CONTRACTOR notifies the ENGINEER in writing of all such substitutions. The minimum acceptable pipe class is Class III. C. Minimum laying length of each joint shall be 6' -0" for sizes up to and including 15" and 7'6" for sizes larger than 15 ", except for special radius pipe, bends, wyes, and other special fittings. D. Lifting Holes are not permitted . 2.02 WALL THICKNESS A. The wall thickness shall be Wall C in accordance with ASTM C76 -83. e ISM. HUSTON & ASSOCIATES. INC. 1 Z.03 CONCRETE 1 A. The concrete, materials, mixing, gradation, and curing shall conform to the requirements of ASTM C76 -83 with the following additional re- quirements. • 1 1 1 1 1 1 1 1 1 1 1 1. Coarse aggregate shall be crushed limestone per ASTM C33. The concrete shall be a minimum of 65% calcium carbonate equivalent. Alkalinity shall be determined in accordance with paragraph 3.04 of this section. 2. Cement shall be ASTM C150 Type D containing not more than 5% tricalcium ahrminate. 3. Water shall be potable, non recycled. 1 2.04 STEEL REINFORCEMENT A. All steel reinforcement shall be in accordance with ASTM C76 -83 and shall be circular in shape. No elliptical reinforcement or part circle will be permitted. Z.05 JOINTS 1 A. General. Joints for all reinforced concrete pipe shall conform to the requirements of ASTM C361 -83, paragraph 8, except as follows: 1. Gaskets shall have a circular cross section and shall be confined in a groove in the pipe spigot. Pipe with collars in lieu of integral bells will not be acceptable. 2. Following successfull testing of the pipeline in accordance with the Contract Documents, the inside joint recess of concrete pipe shall be filled with stiff mortar mixed in proportions of one part portland cement to two parts masonry sand passing a 16 mesh sieve size. Joint surfaces shall be damp, but free from surface water when mortar is placed. Mortar shall be thoroughly compacted and finished smooth. All excess mortar shall be removed from the pipe. 3. Each concrete pipe joint shall be designed to withstand, without cracking, the gasket compression plus a differentia] load across the joint equal to 4000 pounds per foot of internal diameter. 4. Pipe joints shall depend only upon the specified gasket for maintaining the required level of performance for infiltration and exf ltration. All required testing shall be conducted prior to placing any grout, mortar or any material in the pipe joint other than the specified gasket. 02612 -3 1 1 1 1 1 : 1 1 1 1 1 1 1 1 1 1 1 L Joint Approval 1. The pipe manufacturer shall furnish detail drawings of the joint design for each size to be furnished under this contract. The maximum allowable inside joint space, including nominal 'home' position, maximum 'pull', and manufacturing tolerances, shall be provided by the pipe manufacturer and indicated on the furnished details submitted in compliance with paragraph 1.02, part D. 2. Performance tests of the joints may be required. If such tests are required, they shall be subject to the hydrostatic test set forth in ASTM C443, both for 'Pipes in " Straight Alignment, paragra- ph 9.1.1' and for 'Pipes in Maximum Deflected Position, para- graph 9.1.2' without leakage either in the pipe or in the joints. C. Joint Dimensions. The bell and spigot of the joint shall be of such design that it will withstand the forces caused by the compression of the gasket when properly jointed without cracking or fracturing. All surfaces of the joint upon or against which the gasket may bear shall be smooth, free of 'palls, cracks, or fractures or imperfections that would adversely affect the performance of the joint. 2.06 FITTINGS AND SPECIALS All fittings and specials to be installed in the pipelines, including all bends and tees shall be manufactured on machines in the same manner as straight joint pipe. Quality of concrete, workmanship, and joints will be subjected to the same requirements as for straight pipe. Fittings and specials shall be made to conform to the requirements indicated on the Drawings for such. 2.07 GASKETS Rubber gaskets shall comply with the requirements of ASTM 361. PART 3 - EXECUTION 3.01 GRADES The grade elevation shown in the Drawings is the invert elevation, or lowest point, of the inside barrel of the pipe. The pipe shall run on straight grades between the elevations shown. 3.02 PIPE LAYING HANDLING AND JOINTING A. Pipe shall be laid only upon subgrade and embedment which are in satisfactory conditions and approved by the ENGINEER. All pipe shall 02612 -4 1 1 1 1 1 1 1 1 1 1 1 , 1 1 1 1 1 1 be carefully lowered to the bottom of the trench and shall be laid with the bell upgrade, unless otherwise approved by the ENGINEER; in any event, the pipe shall be laid with the bell away from the last section placed. B. In handling laying, and jointing the pipe, extreme care shall be exercised to prevent damaging the rubber gaskets and the ends of the pipe joints. Just prior to jointing, an inspection shall be made to be certain that the pipe ends and gaskets are thoroughly clean with no foreign materials adhering to them. The pipe shall then be assembled'by pulling the spigot of the joint being laid into the bell of the preceding pipe using a mechanical pipe puller. Acceptable jointing procedures are described on pages 9 -33 and 9 -34 of "Concrete Pipe Handbook" published by the American Concrete Pipe Association, 1st Edition, 1980. • C. All joints shall be checked with a- feeler gauge. If any irregularity in the position of the gasket is detected at any point on the entire circumfer- ence of the pipe, the pipe shall be removed and the gasket examined for cuts. If the gasket is undamaged, it may be used again, but both it and the joint must be relubricated. Before the pipe sling is cast off, the rubber gasket of the joint shall be checked for proper position as outlined above. Jointing shall be performed in a manner to prevent damage to the pipe and joints. After the pipe section is joined, it shall be checked for line and grade. D. Tight fitting stoppers or bulkheads shall be securely placed in the ends of all pipelines when the work is stopped temporarily, and at the end of the day's work, to prevent trash or dirt entering the pipe. 3.03 PROHIBITED FIELD PATCHING OF PIPE The pipe shall not be patched or dressed in any manner after it has been accepted by the CONTRACTOR without the written approval of the ENGINEER. Such approval shall be granted for a given section of pipe following inspection of the pipe by the ENGINEER or his representative and submittal and approval of repair method. Field patching will not be permitted if it will, in the opinion of the ENGINEER, adversely affect the performance of joints, or impair the strength, durability or serviceability of the pipe. 3.04 REJECTION OF THE PIPE The pipe may be rejected for having defects or failure to meet requirements as follows: A. Variations in any dimension exceeding the permissible variations prescribed. 02612 -5 B. A piece broken out of the bell or spigot of such size that the water- tightness of the joint would be impaired. ' C. Any shattering or flaking of concrete or other conditions indicating an improper concrete mix. D. Lack of uniformity in placement of steel which might preclude all joints being typical of those tested. ' E. Cracks sufficient to impair the strength, durability, or serviceability of the pipe. " F. Failure to conform with any of the' specifications herein set forth or referenced. G. Failure of pipe to go completely home.' : ! • H. Failure to pass any of the tests required by these specifications. ' I. Joint sections with spalls, cracks, fractures, or other imperfections that could adversely affect the performance of the joint. ' 3.05 ALKALINITY TESTING ' A. The alkalinity of the concrete shall be determined by an independent testing laboratory. B. Concrete test samples shall be obtained and tested in accordance with procedures described in "Concrete Pipe Handbook" published by the American Concrete Pipe Association, 1st Edition, 1980, pp. 7 -29 thru 7 -30. ' C. Samples shall be obtained and tested weekly for each pipe diameter produced during that week. D. Certified copies of the alkalinity tests results will be forwarded to the ENGINEER for review and acceptance within seven (7) days of sample collection. The average of the alkalinities measured from the two samples shall be used to determine compliance with this specification. E. Drill holes in the test pipes may be repaired and the test pipe used on the project. F. In the event that the average alkalinity for the two samples of the test ' pipe section is less than the specified value, two additional pipe sections shall be selected from the same production period, and alkalinity 1 ' 02612 -6 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ; 1 1 1 3.06 TESTING determinations made for these two sections. If either of the two retest pipe sections fail to meet the specified alkalinity, each pipe section in the failed production lot shall be tested prior to acceptance and only those pipes which meet the alkalinity requirement shall be accepted. If both retest sections meet the specified alkalinity value, the production lot will be accepted. Pipelines shall be subjected to other tests as required by the Contract Documents. END OF SECTION 02612 -7 1 1 1 1 1 1 1 1 1 1 1 1 1 e h ESPEY, HUSTON 1 ASSOCIATES, INC. SECTION 02650 - TESTING OF PIPELINE PART 1 - GENERAL 1.01 WORK INCLUDED 1.02 SUBMITTALS A. Submittal of proposed test methods and test results 'hall be in accord- ance with the Contract Documents. ' B. Submittal shall indicate test procedure used in accordance with'Part 3, stations between which the tests were conducted and other test results as applicable. PART 2 - PRODUCTS 2.01 GENERAL The work to be performed under this section of the specifications consists of acceptance testing of the installed pipeline. The pipeline shall be tested by low pressure air joint test. This Part defines the requirements for various tests which may be required to ascertain the pipeline's integrity. Part 3 defines which of these tests are required for each pipe material. At no time shall there by more than 1000 linear feet of pipeline installed and otherwise complete in place which has not been successfully tested in accordance with this specification. 2.02 LOW PRESSURE AIR JOINT TEST A. GENERAL After the pipe has been installed and backfilled, each joint shall be tested in such sections as are convenient for the CONTRACTOR and approved by the ENGINEER. The CONTRACTOR shall furnish all labor, material, tools and equipment required to successfully complete the test. B. EQUIPMENT REQUIRED FOR TEST The equipment used for testing will not be installed as a part of the project but shall be furnished and will remain the property of the CONTRACTOR. 02650 -1 1 1 1 . 1 1 1 1 1 1 1 1 1 e h 'SPEY. HUSTON & ASSOCIATES, INC. The minimum test equipment shall consist of heavy -gauge corrugated steel rings, with inflatable tubes encompassing the outside circum- ference. Connections for mounting air valves and hose shall be in the steel rings. The test equipment shall be similar to 'Joint Tester' as manufactured by Cherne Industries of Edina, Minnesota. Compressor Air Supply: Any source which will provide at least one hundred (100) cubic feet per minute at fifty (50) pounds per square inch. - s s Joint Tester, Valves, Pressure Gages; Air Hose, Connections and other equipment necessary to conduct the air test shall be furnished by the CONTRACTOR. The test equipment for air testing will consist of valves, joint testing, and pressure gages used to control the rate at which air flows to the joint being tested and to monitor the air pressure inside the joint testing ring. > , C. PREPARATION FOR TEST All joints to be tested shall be clean of sand, dirt or other materials. Visually inspect the interior of the pipe for cracks, boles or sealing. The surface of the pipe on each side of the joint to be tested shall be wiped clean. D. PROCEDURE 1. Place joint tester over joint to be tested. 2. Apply air pressure until the pressure inside the test cell reaches 4 p.s.i.g. 3. Allow the temperature and pressure inside the joint to stabilize at a minimum pressure of 2.5 p.s.i.g. for a period of two (2) minutes prior to the start of the testing operation; then either increase or decrease the pressure to 3.5 p.s.i.g. prior to the start of the testing. 4. At 3.5 p.s.i.g., the time and pressure will be observed. 5. This test procedure may be used as a presumptive test which enables the installer to determine the acceptability of the line prior to backfill and subsequent construction activities. If the time for the air pressure to decrease from 3.5 p.s.i.g. to 2.0 p.s.i.g. is greater than 20 seconds, the pipe joint shall be presumed to be free from defect. 02650 -2 1 1 1 1 1 1 1 1 .,1 1 1 1 1 1 1 1 e l l ESPEY, HUSTON a ASSOCIATES, INC. PART 3 - EXECUTION 3.01 GENERAL All labor and equipment required for testing the pipelines shall be furnished by the CONTRACTOR. Testing shall be scheduled by the CONTRACTOR, subject to observation and approval by the OWNER or his designated representative. 3.02 GRAVITY WASTEWATER LINES - A. Reinforced Concrete. Sewer Pipe (RCP) - 48 inch diameter or greater. RCP 48 inch diameter or greater shall be tested in accordance with Section 2.02. In addition, all leaks viable either during the testing or prior to final acceptance shall be plugged. - END OF SECTION 02650 -3