R-85-783 - 11/14/1985RESOLUTION NO.
WHEREAS, engineering services are necessary in order to obtain land
surveys in connection with the A.J. Palm Estate; and
WHEREAS, the engineering firm of Haynie & Kallman, Inc., has submitted
a proposal to provide the needed engineering services; and
WHEREAS, the City Council wishes to accept said proposal, Now Therefore,
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS
That the Mayor is hereby authorized and directed to execute on behalf
of the City, a letter agreement submitted by Haynie & Kallman, Inc., to
submit the necessary land survey, a copy of said letter agreement being
attached hereto and incorporated herein for all purposes.
RESOLVED this 14th day November, 1985.
ATTEST:
J NNE LAND, City Secretary
MIKE ROBINSON, Mayor
City of Round Rock, Texas
Haynie & Kallman, Inc.
CONSULTING ENGINEERS
1106 South Mays • Round Rock, Texas 78664 • (512) 255. 7861/12212 Technology Blvd., Suite H • Austin, Texas 78727 (512) 250-8611
October 24 1985
Mr. Don Wolfe, City Attorney
City of Round Rock
214 E. Main Street
Round Rock, Texas 78664
RE: Palm Estate Survey
Dear Mr. Wolfe:
We are pleased to acknowledge your verbal authorization to survey and
prepare a survey plat for the A.J. Palm Estate.
Our Job No. 103 -1022 has been assigned to this project and our charges
will be on an hourly reimbursable basis according to the attached Hourly Rate
Schedule. We anticipate that the assignment will be completed by November 30,
1985, and the estimated charges will be $10,800.00.
If this expenditure meets with your approval, please sign both copies
of this letter in the spaces provided below, and return one copy to our office
along with a copy of your purchase order. Please retain one copy for your
file. Work will commence upon receipt of the signed authorization letter.
JDB /jg
Enclosure
APPROVED BY:
We appreciate the opportunity to be of service to you.
Very truly yours,
HAYNIE & EALLMAN, INC.
Name
tle
Becker,
Survey Manager
Date
CIVIL ENGINEERING • CONSULTANTS • MUNICIPAL ENGINEERING • LAND PLANNING • SURVEYING
HAYNIE & RALLMAN. INC.
HOURLY RATE SCHEDULE
CLASSIFICATION HOURLY RATE
1. Corporate Officer $100
2. Registered Professional Engineer $ 75
3. Registered Public Surveyor $ 60
4. Project Manager /Hydrologist $ 55
5. Engineer —in— Training (E.I.T.) $ 45
6. Land Planner $ 50
7. Survey Crew Coordinator $ 40
8. Project Representative (includes Vehicle and Equipment) $ 40
9. Design Technician $ 35
10. Drafter $ 30
11. Survey Calculation Technician $ 40
12. Technical Support Personnel $ 30
13. Secretarial Personnel $ 25
14. Four Man Survey Crew (includes Vehicle and Equipment) $ 80
15. Three Man Survey Crew (includes Vehicle and Equipment) $ 75
16. Two Man Survey Crew (includes Vehicle and Equipment) $ 65
17. Reimbursement for Direct Non —Labor Expense and Sub —
Contract Expense — Cost Plus 20%
Revised 8-1 -85