R-86-802 - 1/9/1986ATTEST:
/
JO
NE
LAND, City Secretary
RESOLUTION NO. (�D�(,k
WHEREAS, engineering services are necessary in order to design
water and sewer improvements to provide service to the Palm Valley
Church; and
WHEREAS, the engineering firm of Haynie & Kallman, Inc. has submitted
a proposal to provide the needed engineering services; and
WHEREAS, the City Council wishes to accept said proposal, Now
Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS
That the Mayor is hereby authorized and directed to execute on behalf
of the City, a letter agreement submitted by Haynie & Kallman, Inc. to
submit the necessary land survey, a copy of said letter agreement being
attached hereto and incorporated herein for all purposes.
RESOLVED this `7 day of
MIKE ROBINSON, Mayor
City of Round Rock, Texas
, 1986.
Haynie & Kaltman, Inc.
CONSULTING ENGINEERS
Mr. Jim Nuse
Director of Public Works
City of Round Rock
214 E. Main Street
Round Rock, Texas 78664
Dear Jim:
This letter will serve as a Letter of Authorization for
the design of water and sewer improvements to provide service
to the Palm Valley Church as we discussed yesterday. Compen-
sation will be on an hourly basis as per the attached Hourly
Rate Schedule.
WVL /cla
Enclosure
We will begin design upon authorization by the City.
Sincerely,
HAYNIE & KALLMAN, INC.
AUTHORIZED BY THE CITY OF ROUND ROCK
1106 South Mays • Round Rock, Texas 78664 • (512) 255.7861
December 18, 1985
Re: Water & Sewer Service to the
Palm Valley Church
Scott Linden, P.E.
Mike Robinson, Mayor Date
/ -9 -
CIVIL ENGINEERING • CONSULTANTS • MUNICIPAL ENGINEERING • LAND PLANNING • SURVEYING
HAYNIE, &. KALLMAN, INC.
HOURLY RATE SCHEDULE
CLASSIFICATION HOURLY RATE
1. Corporate Officer $100
2. Registered Professional Engineer $ 75
3. Registered Public Surveyor $ 60
4. Project Manager /Hydrologist $ 55
5. Engineer -in- Training (E.I.T.) $ 45
6. Land Planner $ 50
7. Survey Crew Coordinator $ 40
8. Project Representative (includes Vehicle and Equipment) $ 40
9. Design Technician $ 35
10. Drafter $ 30
11. Survey Calculation Technician $ 40
12. Technical Support Personnel $ 30
13. Secretarial Personnel $ 25
14. Four Man Survey Crew (includes Vehicle and Equipment) $ 80
15. Three Man Survey Crew (includes Vehicle and Equipment) $ 75
16. Two Man Survey Crew (includes Vehicle and Equipment) $ 65
17. Reimbursement for Direct Non -Labor Expense and Sub -
Contract Expense - Cost Plus 20%
Revised 8 -1 -85