R-88-1123 - 6/3/1988RESOLUTION NO. PAY
WHEREAS, the City has duly advertised for bids for the
hauling of base material for Old Settlers Park at Palm Valley, and
WHEREAS, S.S.T. Transport, Inc. submitted the lowest and
and best bid, and
WHEREAS, the Council wishes to accept the bid of S.S.T.
Transport, Inc., and to authorize the execution of the necessary
documents, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,
TEXAS
That the bid of S.S.T. Transport, Inc., is hereby accepted
as the lowest and best bid, and the Mayor is authorized and
directed to enter into an agreement with S.S.T. Transport, Inc.,
for the hauling of base material for Old Settlers Park at Plam
Valley.
RESOLVED this 3rd day of June, 1988.
ATTEST:
NE LAND Ci
Secretary
tary
MIKE ROBINSON, Mayor
City of Round Rock, Texas
CITY OF ROUND ROCK
OLD SETTLER'S PARK AT PALM VALLEY
HAULING BASE, PHASE 1 ROAD
CITY OF ROUND ROCK
OLD SETTLER'S PARK AT PALM VALLEY
HAULING BASE, PHASE 1 ROAD
Section Table of Contents _Ent
1.0 Notice to Bidders NB -1
2.0 Bid Documents BD - 1
3.0 Post Bid Documents PBD -1
4.0 General Conditions GC -1
5.0 Special Conditions SC -1
1.0 NOTICE TO BIDDERS
NOTICE TO BIDDERS
RUN: 19 May 1988
23 May 1988
26 May 1988
30 May 1988
The City of Round Rock will be accepting sealed bids at City Hall, 221
East Main Street, Round Rock, Texas for the hauling of base material by
20 Yard Belly Dump Trucks from Texas Crushed Stone to job site at 3300
Palm Valley Boulevard. Bids will be received until 2:00 p.m., Thursday,
June 2, 1988 at which time they will be opened and publicly read. Bids
will be submitted in a sealed envelope marked: "BID FOR Phase I, Hauling
Base Material for Road, Old Settler's Park at Palm Valley."
Specifications are available at job site from Larry Madsen, Project Manager,
3300 Palm Valley Boulevard, Round Rock, Texas, phone number 244 -2463.
The City of Round Rock reserves the right to reject any or all bids.
NB -1
2.0 BID DUCUMENPS
OWNER: City of Round Rock, Texas
INSTRUCTIONS TO BIDDERS
JOB NAME: Old Settler's Park at Palm Valley, Phase 1 Road, Hauling Base
1. The Contractor is to haul base material from Texas Crushed Stone by
20 Yard Belly Dump Trucks and dump in excavated road that is to be
built.
2. The Contractor will be given 24 hour notice to haul.
3. A per ton price is required and quantities of work to be done are
unit prices and are approximate only and are intended to serve as
a guide in evaluating Bids.
4. It is further agreed that quantities of work to be done at unit prices
may be increased or diminished as may be considered necessary in the
opinion of the Project Manager to complete the work as planned and
all quantities of work are to be performed at unit prices.
5. The Contractor shall assure that only material from the City approved
stockpile at Texas Crushed Stone be received. A weigh ticket indicating
source and weight is the liability of the Contractor. The Owner's
representative will be given a weigh ticket at time of delivery.
6. Awarding of Contract will be made within 30 days after opening of
the proposals and within 5 days after written notification of Award
of the Contract the successful Bidder must furnish proof of Insurance,
and it must be approved by the City of Round Rock.
7. A notice of 24 hours will be given to haul. The price will be good
for six months from date of Contract.
8. Construction funds are being assisted by the Texas Parks & Wildlife
and Contractor must comply with regulation of the Civil Rights Act
of 1964.
9. Specifications are those of the City of Austin Standard Codes as adopted
by the City of Round Rock.
BD -1
3.0 POST BID DOCUMENTS
01 PROPOSAL BIDDING SHEET i AGREEMENT
Bid Item Quantity Unit Item Description Unit Price Amount
1 7,400 Tons Hauling Base Material 1.16/T $8584.00
By 20 Yard Dump Trk,
to excavated Road
M and dump, per ton
If proposal is accepted, the Undersigned agrees to execute the Contract
and provide necessary Insurance Certification and commence work with five
(5) days after written Notice to Proceed. The prices will be good for
a six month period.
SST TRANSPORT, INC.
N P.O. BOX 12517
Address
AUSTIN, TEXAS 78711
Telephone
lik) ‹s-7— i-
Na m of d
iiir
frj
1
1
BD -2
Respectfully Submitted
-7/1
Autho z Signature
T'8tle For:
THE STATE OF TEXAS 1
COUNTY OF WILLIAMSON
That this Agreement made and entered into this ,2 day of
A.D., 19, by and between the CITY OF ROUND ROCK, TEXAS,
B Mayor, First Party, hereinafter termed the Owner, and
, of the City of„
County of ". J , State of ■a-tJ , Second
Party, hereinafter termed the Contractor.
WITNESSETH: That for and in consideration of the payments and
agreements hereinafter mentioned to be made and performed by said First
Party (Owner), the said Second Party (Contractor) hereby agrees with the
First Party to commence and complete the construction of certain
im rovemen at the prices set forth in the Contractor's Proposal dated
L_n€. ki / 9 g g for certain improvements described as follows:
AGREEMENT
KNOW ALL MEN HY THESE PRESENTS
The Contractor shall perform all work shown on the Plans and described
in the Specifications and shall meet all requirements of this Agreement,
the General and Special Conditions of the Contract; and such Orders and
Agreements for Extra Work as may subsequently be entered by the above
named parties to this Agreement.
The Contractor hereby agrees to commence work under this contract
within 5 consecutive calendar days after Award of Contract and shall cause
work to progress in a manner satisfactory to the Owner. Such work shall
be completed in full within six months.
The Owner agrees to pay the Contractor in current funds, and to make
payments on account, for the performance of the work in accordance with
the Contract, at the prices set forth in the Contractor's Proposal, subject
to additions and deductions, all as provided in the General Conditions
of the Agreement.
The following documents together with this Agreement, comprise the
Contract, and they are as fully a part thereof as if herein repeated in
full:
The Invitation to Bidders
The Instructions to Bidders
The Proposal and Bidding Sheets
The General Conditions of Agreement
The Special Conditions of Agreement
PBD -1
AGREEMENT (CONTINUED)
IN WITNESS WHEREOF the Parties to these presents have executed this
Agreement in the year and day first above written.
ATTEST:
City Secretar
PBD -2
CITY OF ROUND ROCK, TEXAS, OWNER
By
Mayor
5 7_ 5 7 5 - 1
Contractor d
Of ®
.1.4-
-
CERTIFI ATE I SSUE DATE (MMJOD/YV)
OF INSURANCE
6/3/88 ncb
PRODUCER
Keith Surplus Lines Agency
P. 0. Box 609
Desoto, Texas 75115
(214) 224 -3503
IN -TEXAS ONLY: WATS 1-800-442-
3307
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS
NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND,
EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
COMPANIES AFFORDING COVERAGE
COMPANY A
LtIIER SOUTHERN COUNTY MUTUAL INSURANCE CO
COMPANY B
LETTER
INSURED
Steves South Texas Corporation
SST Transport, Inc.
P. O. BOX 12517
Austin, Texas 78711
COVERAGES
THIS IS TO CERTIFY THAT POLICIES OF INSURANCE LISTED BELOW HAVE
NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY
BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES
TIONS OF SUCH POLICIES.
COMPANY
LETTER C RECEIV ■
p
COMPANY D - ; ' 1988
LETTER
COMPANY E
LETTER
BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED.
CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY
DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS, AND CONDI-
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE
PATE (MAINONY)
PO T M/DEVTDN
GATE (8855515
LIABILITY LIMITS IN THOUSANDS
EA H
OCCURRENCE
AGGREGATE
GENERAL
■
•
-
■
■
■
III
■
•
LIABILITY
COMPREHENSIVE FORM
PREMISES/OPERATIONS
EEXPLLO IION COLLAPSE HAZARD
PROOUCTS/COMPLETED OPERATIONS
CONTRACTUAL
INDEPENDENT CONTRACTORS
BROAD FORM PROPERTY DAMAGE
PERSONAL INJURY
BODILY
INJURY
$
$
PROPERTY
DAMAGE
$
$
COMBINED
$
$
PERSONAL INJURY
A .
AUTOMOBILE
■
■
■
■
■
1
LIABILITY
ANY AUTO
ALL OWNED AUTOS (PRIV. PASS)
uL OWNED AUTOS ( R N)
HIRED AUTOS
NON-BWNED AUTOS
GARAGE LIABILITY
___ _ ..IE H -. _._' -._.
SCB 000054
- • • - • , - . .
11/01/87
L- ased t
11/01/88
m "NAMED
MET
INJURY
PB50Rl
$
C-
EODt
INJURY
m
$
PROPERTY
DAMAGE
$
Bt a PD
COMBINED
MI
'
EXCESS
■UMBRELLA
■
LIABILITY
FORM
OTHER THAN UMBRELLA FORM
INSURED"
BI a PD
COMBINED
m
$
$
WORKERS' COMPENSATION
AND
EMPLOYERS' LIABILITY
®..
$ (EACH ACCIDENT)
$ (DISEASE- POLICY LIMIT)
OTHER
- �
DESCRIPTION OF OPERATIONSILOCATIONSNEHICLESISPECIAL ITEMS
RECEIVED I g : :
CERTIFICATE HOLDER
CITY OF ROUND ROCK
Attn: Mr. Larry Matheson
Round Rock, Texas 78664
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EX-
PIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO
MAIL 10 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE
LEFT, BUT F URE TO MAIL SUCH NOTICE SHALL IMPOSE NO OR LIABILITY
OF ANY KIWI; PON THE COMPANY ITS AGENTS OR REPRESENTATIVES.
AUTHORIZED / •
,Tam- : �Rli� e
ACORD 25 (8/84)
•
4 IIR /ACORD CORPORATION 1984
TYPE OF
INSURANCE
POLICY
. NO. .
' EFFECTIVE
. ..DATE ..
EXPIRATION
.. DATE.... .
---
.LIMITS.OF.LIABILITY
Workmen's
Compensation
.
of
Texas, $
Employer..s is t tty
Comprehensive
General
Liability
Includes
Contractual
-•---Liability-
Covers
Independent
Contractors
Owner's r
Protective .
_
. • • -
. •
- --
.
•
.. .
.
Bodily Injury
$ . - •• each person
$ •• each person
• .
.
Property. Damage
$' " ': each acciden•
S' " aggregate
Bodily Injury
'$ •.. . -. each person
"$ each acciden'
Property Damage
•$ - - - - •each acciden'
aggregate
..
Comprehensive .
Automobile., _: ' - -
Liability.-•.- . -..
Owned ..
_ Vehicles
- Hired
Vehicles
Non -owned
Vehicles
Includes
Contractual
Liability
:.. ..
_ —
_
. . ..
_ . .
-
::r,••
-
Bodily Injury .
'$ • • -.. :. each per
$ each acciden'
..
Property Damage
$' • .. each acciden'
.
.
•
__
1
t
Ci
1
1
1
l
1
1
1
•
A l 70: City of Round Rock
214 East Main Street
Round Rock, Texas 78664
.%
CERTIFICATE OF INSURANCE
•
PBD -3
•
Date:
Description of Work: . •
THIS IS TO CERTIFY THAT is, at the date of
I this certificate, insured by this company with respect to the business opera-
tions hereinafter described, for the types of insurance and in accordance with '
the provisions of the standard policies used by this company, and further here-
/ inafter described. Exceptions to standard policies are noted on the reverse
side hereof.
' CERTIFICATE OF INSURANCE (CONTINUED)
• The above policies either in the body thereof or by appropriate endorsement provide
1 that they may not be changed or cancelled by the insurer in less than ten (10) days
11 the insured has received written notice of such change or cancellation.
1 This Certificate of Insurance neither affirmatively or negatively amends, extends,
or alters the coverage afforded by policy or policies indicated by this certificate.
1
1
i
1
1
1
1
1
1
1
1
PBD -4
(Name of Insurer)
By:
Title:
Address:
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.0 GENERAL CONDIT IONS
1
1
1
1
1
1
1
1
1
Contents
1. Definition of Terms
1.01 Owner, Contractor and Engineer
1.02 Contract Documents
1.03 Sub - Contractor
1.04 SubSubcontractor
1.05 Written Notice
1.06 Work
. 1.07 Extra Work
1.08 Working Day
1.09 Calendar Day
1.10 Substantially Completed
2. Responsibilities of the Engineer and the Contractor
2.01 Owner - Engineer Relationship
2.02 Professional Inspection by Engineer
2.03 Payments for Work
2.04 Initial Determinations
2.05 Objections
2.06 Lines and Grades
2.07 Contractor's Duty and Superintendence
2.08 Contractor's Understanding
2.09 Character of Workmen
2.10 Contractor's Buildings
2.11 Sanitation
2.12 Shop Drawings
2.13 Preliminary Approval
2.14 Defects and Their Remedies
2.15 Changes and Alterations
2.16 Inspectors
3. General Obligations and Responsibilities
3.01 Keeping of Plans and Specifications Accessible
3.02 Ownership of Drawings
3.03 Adequacy of Design
3.04 Right of Entry
3.05 Collateral Contracts
3.06 Discrepancies and Omissions
3.07 Equipment, Materials and Construction Plant
3.08 Damages
3.09 Protection Against Accident to Employees and the Public
z,3. 10 _Performance_and_Pa
3.11 Losses from Natural Causes
3.12 Protection of Adjoining. Property
General Conditions of Agreement
GC-1
$.18 Protection Against Claims of SubContracton, ate.
1.14 Protection Against Royalties or Patented Invention
▪ .16 Laws and Ordinances
$16 Assignment and Subletting
� 17 Indemnification
.18 Insurance
3.19 Final Clean -Up
(.20 Guarantee Against Defective Work
. Prosecution and Progress
1 01 Time and Order of Completion
.02 Extension of Time
4.03 Hindrances and Delays
I . Measurement and Payment
I .O1 Quantities and Measurements
.02 Estimated Quantities
.03 Price of Work t r 04 Partial Payments)
.05 Use of Completed Portions
. 06 Final Completion and Acceptance
6.07 Final Payment
1.08 Payments Withheld
▪ .09 Delayed Payments
Extra Work and Claims
.01 Change Orders
I .02 Minor Changes
.03 Extra Work
.04 Time of Filing Claims
6.05 Arbitration
I . Abandonment of Contract
I .01 Abandonment by Contractor
.02 Abandonment by Owner
I . Subcontractors
.01 Award of Subcontracts for Portions of the Work
8.02 Subcontractual Relations
1 .03 Payments to Subcontractors
9. Separate Contracts
I .01 Owner's Right to Award Separate Contracts
.02 Mutual Responsibility of Contracts
.03 Cutting and Patching Under Separate Contracts
i 0. Protection of Persons and Property
▪ 0.01 Safety Precautions and Programs
▪ 0.02 Safety of Persons and Property.
10.03 Location and Protection of Utilities
IC•2
•
• • -7
i
The Contract Documents shall consist of the Notice to Contractors, Instructions to Bidders, Proposal,
Signed Agreement, Performance and Payment Bonds (when required), Special Bonds (when required),
General Conditions of the Agreement, Construction Specifications, Plans, and all modifications thereof
incorporated in any of the documents before the execution of the agreement.
' The Contra.^.t Documents are complementary, and what is called for by any one shall be as binding as if
called for by all. In case of conflict between any of the Contract Documents, priority of interpretation
shall be in the following order: Signed Agreement, Performance and Payment Bonds, Special Bonds (if
z any), Proposal, Special Conditions of Agreement, Notice to Contractors, Technical Specifications, Plans,
and General Conditions of Agreement.
1
1
I
1
1
1.02 Contract Documents
General Conditions of Agreement
1. Definition of Terms
1.01 Owner, Contractor and Engineer
The Owner, the Contractor and the Engineer are those persons or organizations identified as such in the
Agreement and are referred to throughout the Contract Documents as if singular in number and mascu-
line in gender. The term Engineer means the Engineer or his duly authorized representative. The Engi-
neer shall be understood to be the Engineer of the Owner, and nothing contained in the Contract Docu-
ments shall create any contractual or agency relationship between the Engineer and the Contractor. •
1.03 Sub - contractor
The term Sub- Contractor, as employed herein, includes only those having a direct contract with the
Contractor and it includes one who furnishes material worked to a special design according to the plans
or specifications of this work, but does not include one who merely furnishes material not so worked.
1.04 Sub - subcontractor '
The term Sub-Subcontractor means one who has a direct or indirect contract with a sub-contractor to
perform any of the work at the site and includes one who furnishes material worked to a special design
according to the plans or specifications of this work, but does not include one who merely furnishes
material not so worked.
1.05 Written Notice
Written notice shall be deemed to have been duly served if delivered in person to the individual or to a
member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent
by registered mail to the last business address known to him who gives the notice.
1.06 Work
The Contractor shall provide and pay for all materials, supplies, machinery, equipment, tools, superin-
tendence, labor, services, insurance, and all water, light, power, fuel, transportation and other facilities
necessary for the execution and completion of the work covered by the contract documents. Unless
otherwise specified, all materials shall be new and both workmanship and materials shall be of a good
quality. The Contractor Shall if required, furnish satisfactory evidence as to the kind and quality of
GC-3
w
ii, •.
k
materials. Materials or work described In words which so applied have a well known technics/ or trade
meaning shall be held to refer to such recognized standards.
' 1.07 Extra Work . "
/The term "Extra Work" as used in this contract shall be understood to mean and include all work that
may be required by the Engineer or Owner to be done by the Contractor to accomplish any change.
alteration or addition to the work shown upon the plans, or reasonably implied by the specifications, and
'not covered by the Contractor's Proposal, except as provided under "Changes and Alterations," herein.
1.08 Working Day .
'A "Working Day" Is defined as any day not including Saturdays, Sundays or any legal holidays, in
which weather or other conditions, not under the control of the Contractor, will permit construction of
the principal units of the work for a period of not less than seven (7) hours between 7:00 a.m. and 6:00
'Pm.
1.09 Calendar Day
' "Calendar Day" is any day of the week or month, no days being excepted.
.1.10 Substantially Completed
By the term "substantially completed" is meant that the structure has been made suitable for use or oc-
cupancy or the facility is in condition to serve its intended purpose, but still may require minor miscel-
,laneous work and adjustment.
1 2. Responsibilities of the Engineer and the Contractor
2.01 Owner - Engineer Relationship
It! Engineer will be the Owner's representative during construction. The duties, responsibilities and
'tations of authority of the Engineer as the Owner's representative during construction are as set
forth in the Contract Documents and shall not be extended or limited without written consent of the
ner and Engineer. The Engineer will advise and consult with the Owner, and all of Owner's instruc-
'ons to the Contractor shall be issued through the Engineer.
1 .02 Professional Inspection by Engineer
The Engineer shall make periodic visits to the site to familiarize himself generally with the progress of
e executed work and to determine if such work generally meets the essential performance and design
e atures and the technical and functional engineering requirements of the Contract Documents; provided
d except, however, that the Engineer shall not be responsible for making any detailed, exhaustive,
comprehensive or continuous on.site inspection of the quality or quantity of the work or be in any way
t esponsible, directly or indirectly, for the construction means, methods, techniques, sequences, quality,
rocedures, programs, safety precautions or lack of same incident thereto or in connection therewith.
Notwithstanding any other provision of this agreement or any other Contract Document, the Engineer
hall not be in any way responsible or liable for any acts, errors, omissions or negligence of the Contrac.
�
or, any subcontractor or any of the Contractor's or subcontractor's agents, servants or employees or
any other person, firm or corporation performing or attempting to perform any of the work.
1 .03 Payments for Work
•
The Engineer shall review Contractor's applications for payment and supporting data, determine the
ount owed to the Contractor and approve, in writing, payment to Contractor in such amounts; such
pproval of payment to Contractor constitutes a representation to the Owner of Engineer's professional
IrC-4
g.
yJ
1
a
Judgment that the work has progressed to the point indicated to the best of his knowledge, information
and belief, but such approval of an application for payment to Contractor shall not be deemed as a repro.
sentation by Engineer that Engineer has made any 'examination to determine bow or for what purpose
Contractor has used the moneys paid on account of the Contract price.
2.04 Initial Determinations
The Engineer initially shall determine all claims disputes and other matters in question between the
Contractor and the Owner relating to the execution or progress of the work or the interpretation of the
Contract Documents and the Engineer's decision shall be rendered in writing within a reasonable time,
which shall not be construed to be less than ten days, appeal to arbitration may be taken as if his deci-
sion had been rendered against the party appealing.
2.05 Objections
In the event the Engineer renders any decision which, in the opinion of either party hereto, is not in ac-
cordance with the meaning and intent of this contract, either party may file with the Engineer within
thirty days his written objection to the decision, and by such action may reserve the right to submit the
question so raised to arbitration as hereinafter provided.
2.06 Lines and Grades
Unless otherwise specified, all lines and grades shall be furnished by the Engineer or his representative.
Whenever necessary, construction work shall be suspended to permit performance of this work, but such
suspension will be as brief as practicable and the Contractor shall be allowed no extra compensation
therefor. The Contractor shall give the Engineer ample notice of the time and place where lines and
grades will be needed. All stakes, marks, etc., shall be carefully preserved by the Contractor, and in case
of careless destruction or removal by him or his employees, such stakes, marks, etc., shall be replaced at
the Contractor's expense.
2.07 Contractor's Duty and Superintendence
The Contractor shall give adequate attention to the faithful prosecution and completion of this contract
and shall keep on the work, during its progress, a competent English-speaking superintendent and any
necessary assistants to supervise and direct the work. The superintendent shall represent the Contractor
in his absence and all directions given to him shall be as binding as if given to the Contractor.
The Contractor is and at all times shall remain an independent contractor, solely responsible for the
manner and method of completing his work under this contract, with full power and authority to select
the means, method and manner of performing such work, so long as such methods do not adversely
affect the completed improvements, the Owner and Engineer being interested only in the result obtained
and conformity of such completed improvements to the plans, specifications and contract.
Likewise, the Contractor shall be solely responsible for the safety of himself, his employees and other
persons, as well as for the protection of the safety of the improvements being erected and the property of
himself or any other person, as a result of his operations hereunder. Engineering construction drawings
and specifications as well as any additional information concerning the work to be performed passing
from or through the Engineer shall not be interpreted as requiring or allowing Contractor to deviate
from the plans and specifications, the intent of such drawings, specifications and any other such instruc-
tions being to define with specificity the agreement of the parties as to the work the Contractor is to
perform. Contractor shall ' be fully and completely liable, at his own expense, for design, construction,
installation and use, or non-use, of all items and methods incident to performance of the contract, and
for all loss, damage or injury incident thereto, either to person or property, including, without limitation,
the adequacy of all temporary supports, shoring, bracing, scaffolding, machinery or equipment, safety
precautions or devices, and similar items or devices used by him during construction.
Any review of work in process, or any visit or observation during construction, or any clarification of
plans and specifications, by the Engineer or Owner, or any agent, employee, or representative of either
of them, whether through personal observation on the project site or by means of approval of shop draw-
' GC5
logs for temporary construction or construction processes, or by other mans or method, is agreed by
the Contractor to be for the purpose of observing the extent and nature of work completed or being per-
formed. as measured against the drawings and specifications constituting the contract, or for the
purpose of enabling Contractor to more fully understand the plans and specifications so that the com•
pleted construction work will conform thereto. and shall in no way relieve the Contractor from full and
complete responsibility for the proper performance of his work on the project, including but not limited
to the propriety of means and methods of the Contractor in performing said contract, and the adequacy
of any designs, plans or other facilities for accomplishing ouch performance. Deviation by the Contractor
from plena and specifications that may have been in evidence during any such visitation or observation
by the Engineer, or any of his representatives, whether called to the Contractor's attention or not shall
in no way relieve Contractor from his responsibility to complete all work in accordance with said plans
and specifications.
2.08 Contractors Understanding
It is understood and agreed that the Contractor has, by careful examination, satisfied himself as to the
nature and location of the work, the conformation of the ground, the character, quality and quantity of
the materials to be encountered, the character of equipment and facilities needed preliminary to and
during the prosecution of the work, the general and local conditions, and all other matters which can in
any way affect the work under this contract. No verbal agreement or conversation with any officer,
agent or employee of the Owner or Engineer either before or after the execution of this contract, shall
affect or modify any of the terms or obligations herein contained.
2.09 Character of Workmen
The Contractor agrees to employ only orderly and competent men, skillful in the performance of the type
of work required under this contract, to do the work; and agrees that whenever the Engineer shall
inform him in writing that any man or men on the work are, in his opinion, incompetent, unfaithful or
disorderly, such man or men shall be discharged from the work and shall not again be employed on the
work without the Engineer's written consent. No illegal alien may be employed by any Contractor for
work on this project, and a penalty of S500.00 per day will be assessed for each day and for each illegal
alien who works for the Contractor at this project.
2.10 Contractors Buildings
The building of structures for housing men, or the erection of tents or other forms of protection, will be
permitted only at such places as the Engineer shall direct, and the sanitary conditions of the grounds in
or about such structures shall at all times be maintained in a manner satisfactory to the Engineer.
2.11 Sanitation
Necessary sanitary conveniences for the use of laborers on the work, properly secluded from public ob.
servation, shall be constructed and maintained by the Contractoria such manner and at such points as
shall be approved by the Engineer, and their use shall be strictly enforced.
2.12 Shop Drawings
The Contractor shall submit to the Engineer, with such promptness as to cause no delay in his own work
or in that of any other Contractor, four checked copies, unless otherwise specified, of all shop and /or set-
ting drawings and schedules required for the work of the various trades, and the Engineer shall pass
upon them with reasonable promptness, making desired corrections. The Contractor shall make any cor-
rections required by the Engineer, file with him two corrected copies and furnish such other copies as
may be needed. The Engineer's approval of such drawings or schedules shall not relieve the Contractor
from responsibility for deviations from drawings or specifications, unless he has in writing called the
Engineer's attention to such deviations at the time of submission, nor shall it relieve him from responsi-
bility for errors of any sort in shop drawings or schedules. It shall be the Contractor's responsibility to
fully and completely review all shop drawings to ascertain their effect on his ability to perform the
required contract work in accordance with the plans and specifications and within the contract time.
Such review by the Engineer shall be for the sole purpose of determining the sufficiency of said drawings
GC-6 -
M
• Y
1
1
1 .
1
1
1
or schedules to result in finished improvements In conformity with the plans and spedfications, and
shall not relieve the Contractor of hie duty as an independent contractor as previously set forth, E being
expresuly understood and agreed that the Engineer does not assume "any duty to pus upon the
propriety or adequacy of such drawings or schedules, or any means or methods reflected thereby, In rela-
tion to the safety of either person or property during Contractor's performance hereunder.
2.13 Preliminary Approval
The Engineer shall not have the power to waive the obligations of this contract for the furnishing by the
Contractor of good material, and of his performing good work as herein described, and in full accordance
with the plans and specifications. No failure or omission of the Engineer to discover, object to or
condemn any defective work or material shall release the Contractor from the obligations to fully and
properly perform the contract, including without limitations, the obligation to et once tear out, remove
and properly replace the same at any time prior to final acceptance upon the discovery of said defective
work or material; provided, however, that the Engineer shall, upon request of the Contractor, inspect
and accept or reject any material furnished, and in event the material has been once accepted by the
Engineer, such acceptance shall be binding on the Owner, unless it can be clearly shown that such
material furnished does not meet the specifications for this work.
Any questioned work may be ordered taken up or removed for reexamination, by the Engineer, prior to
fmal acceptance, and if found not in accordance with the plans and /or specifications for said work, all
expense of removing, reexamination and replacement shall be borne by the Contractor, otherwise the
expense thus incurred shall be allowed as Extra Work, and shall be paid for by the Owner: provided
that, where inspection or approval is specifically required by the specifications prior to performance of
certain work, should the Contractor proceed with such work without requesting prior inspection or
approval he shall bear all expense of taking up, removing, and replacing this work if so directed by the
Engineer.
2.14 Defects and Their Remedies
It is further agreed that if the work or any part thereof, or any material brought on the site of the work
for use in the work or selected for the same, shall be deemed by the Engineer as unsuitable oe not in
conformity with the plans, specifications, or the intent thereof, the Contractor shall, after receipt of
written notice thereof from the Engineer, forthwith remove such material and rebuild or otherwise
remedy such work so that it shall be in full accordance with this contract.
2.15 Changes and Alterations
The Contractor further agrees that the Owner may make such changes and alterations as the Owner
may see fit, in the line, grade, form, dimensions, plans or materials for the work herein contemplated, or
any part thereof, either before or after the beginning of the construction, without affecting the validity
of this contract and the accompanying Performance and Payment Bonds.
If such changes or alterations diminish the quantity of the work to be done, they shall not constitute the
basis for claim for damages, or anticipated profits on the work that may be dispensed with, except as
provided for unit price items under Section 5 "Measurement and Payment." If the amount of work is
increased, and the work can fairly be classified under the specifications, such increase shall be paid for
according to the quantity actually done and at the unit price, if any, established for such work under
this contract, except as provided for unit price items under Section 5 "Measurement and Payment ";
otherwise, such additional work shall be paid for as provided under Extra Work. In case the Owner shall
snake such changes or alterations as shall make useless any work already done or material already
furnished or used in said work, then the Owner shall recompense the Contractor for any material or labor
so used, and for any actual loss occasioned by such change, due to actual expenses incurred in prepare.
Lion for the work as originally planned.
2.16 Inspectors
The Engineer May provide one (or more) field inspectors at the work site for the limited purpose of
GC-7
: ,..
I
3.02 Ownership of Drawings
• observing the coo& to pmgras and reporting back to the Engineer on the extent, nature, manner and
▪ performance of the work so that the Engineer may more effectively perform his duties hereunder. Such
• Inspectors may also communicate between Engineer and Contester their respective reports, opinions,
questions, answers and clarifications concerning the plane, specifications and work but shall be deemed
▪ the agent of the Contractor for all purposes in communicating such matters.
▪ Such inspector may confer with the Contractor or Contractor's superintendent concerning the prosecu-
tion of the work and its conformity with the plans and specifications but shall never be, in whole or part,
' responsible for, charged with, nor shall he assume, any authority or responsibility for the means,
methods or manner of completing the work or of the superintendence of the work or of the Contractor's
employees. It is expressly understood and agreed that any such inspector is not authorized by the Engi-
I neer or Owner to independently act for either or answer on behalf of either, any inquiries of the Con-
tractor concerning the plane, specifications or work. No inspector's opinion; advice; interpretation of the
plans or specifications of this contract; apparent or express approval of the means, methods or manner
of Contractor's performance of work in progress or completed; or discovery or failure to discover or
' object to defective work of materials shall release Contractor from his duty to complete all work in strict
accordance with the plans and specifications or estop the Owner or Engineer from requiring that all
work be fully and properly performed including, if necessary, removal of defective or otherwise unaccep-
I table work and the re-doing of such work.
3. General Obligations and Responsibilities
3.01 Keeping of Plans and Specifications Accessible
I The Engineer shall furnish the Contractor with an adequate and reasonable number of copies of all plans
and specifications without expense to him, and the Contractor shall keep one copy of the same con-
stantly accessible on the work, with the latest revisions noted thereon.
' All drawings, specifications and copies thereof furnished by the Engineer shall not be reused on other
work, and, with the exception of the signed contract sets, are to be returned to him on request, at the
completion of the work. All models are the property of the Owner.
1 3.03 Adequacy of Design
it is understood that the Owner believes it has employed competent engineers and designers. It is there-
. fore agreed that the Owner shall be responsible for the adequacy of the design, sufficiency of the
• Contract Documents, the safety of the structure and the practicability of the operations of the
completed project; provided the Contractor has complied with the requirements of the said Contract
I Documents, all approved modifications thereof, and additions and alterations thereto approved in
writing by the Owner. The burden of proof of such compliance shall be upon the Contractor to show that
he has complied with the said requirements of the Contract Documents, approved modifications thereof
and all approved additions and alterations thereto.
1 3.04 Right of Entry
I The Owner reserves the right to enter the property or location on which the works herein contracted for
are to be constructed or installed, by such agent or agents as he may elect, for the purpose of inspecting
the work, or for the purpose of constructing or installing such collateral work as said Owner may desire.
1 3.05 Collateral Contracts
The Owner agrees to provide by separate contract or otherwise, all labor and material essential to the
I completion of the work specifically excluded from this contract, in such manner as not to delay the
progress of the work, or damage said Contractor, except where such delays are specifically mentioned
elsewhere in the Contract Documents. The Owner will attempt to coordinate the collateral work of utility
I GC-8
��1
• 1
1
1
1
1
1
1
1
1
1
1
i
1
1
companies regulated by City franchises, but the City shall not be responsible for delays or other
damages to the Contractor which may result from their acts or omissions.
3.06 Discrepancies and Omissions
It is further agreed that It Is the intent of this contract that all work must be done and all material must
be, furnished in accordance with the generally accepted practice, and in the event of any discrepancies
between the separate contract documents, the priority of Interpretation defined under "Contract Docu•
ments ",shall govern. In the event that there is still any doubt as to the meaning and Intent of any por-
tion of the contract, specifications or drawings, the Engineer shall define which Is intended to apply to
the work.
3.07 Equipment, Materials and Construction Plant
The Contractor shall be responsible for the care, preservation, conservation, and protection of all mate-
rials, supplies, machinery, equipment, tools, apparatus, accessories, facilities, all means of construction,
and any and all parts of the work, whether the Contractor has been paid, partially paid, or not paid for
such work, until the entire work is completed and accepted.
3.08 Damages
In the event the Contractor is damaged in the course of completion of the work by the act, neglect, orris•
sion, mistake or default of the Owner or Engineer, thereby causing loss to the Contractor, the Owner
agrees that he will reimburse the Contractor for such loss. In the event the Owner is damaged in the
course of the work by the act, negligence, omission, mistake or default of the Contractor, or should the
Contractor unreasonably delay the progress of the work being done by others on the job so as to cause
loss for which the Owner becomes liable, then the Contractor shall reimburse the Owner for such loss.
3.09 Protection against Accident to Employees and the Public
The Contractor shall at all times exercise reasonable precautions for the safety of employees and others
on or near the work and shall comply with all applicable provisions of Federal, State, and Municipal
safety laws and building and construction codes. All machinery and equipment and other physical
hazards shall be guarded in accordance with the "Manual of Accident Prevention in Construction" of
the Associated General Contractors of America except where incompatible with Federal, State, or
Municipal laws or regulations. The Contractor shall provide such machinery guards, safe walkways,
ladders, bridges, gangplanks, and other safety devices. The safety precautions actually taken and their
adequacy shall be the sole responsibility of the Contractor, acting at his discretion as an independent
contractor.
3.10 Performance and Payment Bonds
Unless otherwise specified, it is further agreed by the parties to this Contract that the Contractor will
execute separate performance and payment bonds, each in the sum of one hundred (1001 percent of the
total contract price, in standard forms for this purpose, guaranteeing faithful performance of the work
and the fulfillment of any guarantees required, and further guaranteeing payment to all persons supply-
ing labor and materials or furnishing him any equipment in the execution of the Contract, and it is
agreed that this Contract shall not be in effect until such performance and payment bonds are furnished
and approved by the Owner.
Unless otherwise approved in writing by the Owner, the surety company underwriting the bonds shall
be acceptable according to the latest list of companies holding certificates of authority from the
Secretary of the Treasury of the United States and shall be licensed to write such bonds in the State of
Texas.
Unless otherwise specified, the cost of the premium for the performance and payment bonds shall be
included in the Contractor's proposal.
GC•9
3.12 Losses from Natural Causes
')pleas otherwise specified, all b» or damage to the Con tractor arising out of the nature • of the work to
�e done, or from the action of the elements, or from any unforeseen circumstance in the prosecution of
same, or from unusual obstructions or difficulties which may be encountered in the prosecution of
he work, shall be sustained and borne by the Contractor at his own cost and expense.
9.11 Protection of Adjoining Property
L e said Contractor shell take proper means to protect the adjacent or adjoining property or properties
in any way encountered, which might be injured or seriously affected by any process of construction to
undertaken under this Agreement, from any damage or injury by reason of said process of construc-
'on; and he shall be liable for any and all claims for such damage on account of his failure to fully
protect all adjoining property. The Contractor agrees to indemnify, save and hold harmless the Owner
d Engineer against any claim or claims for damages due to any injury to any adjacent or adjoining
1 roperty, arising or growing out of the performance of the contract regardless of whether or not it is
used in part by a party indemnified hereunder, but any such indemnity shall not apply to any claim of
any kind arising solely out of the existence or character of the work.
1 .13 Protection against Claims of Sub - contractors, Laborers,
Materialmen and Furnishers of Machinery, Equipment and Supplies
he Contractor agrees that he will indemnify and save the Owner and Engineer harmless from all claims
wing out of the lawful demands of sub - contractors, laborers, workmen, mechanics, materialmen and
• furnishers of machinery and parts thereof, equipment, power tools, and all supplies, including commis.
L ary, incurred in the furtherance of the performance of this contract. When so desired by the Owner, the
ntractor shall furnish satisfactory evidence that all obligations of the nature hereinabove designated
have been paid, discharged or waived. If the Contractor fails to do so; then the Owner may at the option
B A the Contractor either pay directly any unpaid bills, of which the Owner has written notice, or withhold
oom the Contractor's unpaid compensation a sum of money deemed reasonably sufficient to liquidate
any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been fully
1 ischarged, whereupon payments to the Contractor shall be resumed in full, in accordance with the
i
rms of this contract, but in no event shall the provisions of this sentence be construed to impose any
bligation upon the Owner by either the Contractor or his Surety.
1 .14 Protection against Royalties or Patented Invention
The Contractor shall pay all royalties and license fees, and shall provide for the use of any design,
pa evice, material or process covered by letter patent or copyright by suitable legal agreement with the
tentee or owner. The Contractor shall defend all suits or claims for infringement of any patent or copy-
right rights and shall indemnify and save the Owner and Engineer harmless from any loss on account
L thereof, except that the Owner shall defend all such suits and claims and shall be responsible for all such
oss when • particular design, device, material or process or the product of a particular manufacturer or
�mm anufacturers is specified or required by the Onwer; provided, however, if choice of alternate design,
device, material or process is allowed to the Contractor, then Contractor shall indemnify and save Owner
armless from any loss on account thereof. If the material or process specified or required by the Owner
Rs an infringement, the Contractor shall be responsible for such loss unless he promptly gives such
information to the Owner.
.I.15 Laws and Ordinances
The Contractor shall at all times observe and comply with all Federal, State and local laws, ordinances
ari regulations, which in any manner affect the contract or the work, and shall indemnify and save
armless the Owner and Engineer against any claim arising from the violation of any such laws, ordi-
nances, and regulations whether by the Contractor or his employees, except where such violations are
r led for by the provisions of the Contract Documents. If the Contractor observes that the plans and
ecificstions are at variance therewith, he shell promptly notify the Engineer in writing, and any neces-
sary changes shall be adjusted as provided in the contract for changes in the work. If the Contractor
1C -10
t
1
I
1
3.17 Indemnification
3.18 Insurance
performs any wont knowing k tabs contrary to such hwa, adinancsa, rules and regulations, and with-
out such notice to the Engineer, be shall bear all cats arising therefrom. In case the Owner is a body
politic and corporate, the law from which it derives its powers, Insofar as the same regulates the objects
for which, or the manner in which, or the conditions under which the Owner may enter into contract,
shall be controlling, and shall be considered as part of this contract, to the same effect as though
embodied herein.
3.18 Assignment and Subletting
The Contractor further agrees that he will retain personal control and will give his personal attention to
the fulfillment of this contract and that he will not assign by Power of Attorney, or otherwise, or sublet
said contract without the written consent of the Engineer, and that no part or feature of the work will be
sublet to anyone objectionable to the Engineer or the Owner. The Contractor further agrees that the
subletting of any portion or feature of the work, or materials required in the performance of this con-
tract, shall not relieve the Contractor from his full obligations to the Owner, as provided by this Agree-
ment.
The Contractor shall defend, indemnify and hold harmless the Owner and the Engineer and their respec-
tive officers, agents and employees, from and against all damages, claims, losses, demands, suits, judg-
ments and costs, including reasonable attorneys' fees and expenses, arising out of or resulting from the
performance of the work, provided that any such damages, claim, loss, demand, suit, judgment, cost or
expense:
(1) Is attributable to bodily injury, sickness, disease or death to any person including Contractor's
employees and any Subcontractor's employees and any Sub-Subcontractor's employees or to
• injury to or destruction of tangible property including Contractor's property (other than the
work itself) and the property of any Subcontractor or Sub - Subcontractor including the loss of
use resulting therefrom; and,
(2) Is caused in whole or in part by any intentional or negligent act or omission of the Contractor,
any Sub-Subcontractor, anyone directly or indirectly employed by any one of them or anyone
for whose acts any of them may be liable, regardless of whether or not it is caused in part by a
party indemnified hereunder.
The obligation of the Contractor under this Paragraph shall not extend to the liability of the Engineer,
his agents or employees arising out of the preparation or approval of maps, drawings, reports, surveys.
Change Orders, designs or specifications, or approval of maps, drawings, reports, surveys,- Change
Orders, designs or specifications, or the giving of or the failure to give directions or instructions by the
Engineer, his agents or employees, provided such giving or failure to give is the sole cause of the injury
or damage.
In any and all claims against the Owner or the Engineer or any of their agents or employees by any
employee of the Contractor, any Subcontractor, any Sub-Subcontractor, anyone directly or indirectly
employed by any of them or anyone for whose acts any of them may be liable, the indemnification obli-
gation under Paragraph 3.17 shall not be limited in any way by any limitation on the amount or type of
damages, compensation or benefits payable by or for the Contractor or any Sub - Contractor or Sub -
Subcontractor under workmen's compensation acts, disability benefit acts or other employee benefit
acts.
The Contractor shall carry inurance as follows for the duration of this contract.
A. Statutory Workmen's Compensation
B. Comprehensive General Liability Insurance with minimum Bodily Injury limits of $300,000 for
each occurrence including like coverage for acts and omissions of Subcontractors and
contractual liability coverage.
` GC -11
C. Property Damage Insurance with minimum limits of Is0,000 for each occurrence including like
coverage for acts and omissions of Subcontractors and contractual liability coverage.
D. Automobile Liability Insurance for all owned, non-owned, and hired vehicles with minimum
limits for Bodily Injury of $100,000 for each person and $300,000 for each occurrence and
Property Damage minimum limits of $50,000 for each occurrence. Contractor shall require sub-
contractors to provide Automobile Liability Insurance with same minimum limits.
The Contractor shall not commence work at the site under this contract until be has obtained all re.
quired insurance and until such insurance has been approved by the Owner and Engineer. The Contrac-
tor shall not allow any Subcontractors to commence work until all insurance required has been obtained
and approved. Approval of the insurance by the Owner and Engineer shall not relieve or decrease the
liability of the Contractor hereunder.
The required insurance must be written by a company licensed to do business in Texas at the time the
policy is issued. In addition, the company must be acceptable to the Owner and all insurance (other than
workmen's compensation) shall be endorsed to include the Owner as an additional insured thereunder.
The Contractor shall not cause any insurance to be cancelled nor permit any insurance to lapse. All in-
surance certificates shall include a clause to the effect that the policy shall not be cancelled or reduced,
restricted or limited until ten (10) days after the Owner has received written notice as evidenced by
return receipt of registered or certified letter. Certificates of Insurance shall contain transcripts from the
proper office of the insurer, evidencing in particular those insured, the extent of the insurance, the loca-
tion and the operations to which the insurance applies, the expiration date, and the above mentioned
notice of cancellation clause.
3.19 Final Clean - up
Upon the completion of the work and before acceptance and final payment will be made, the Contractor
shall clean and remove from the site of the work, surplus and discarded materials, temporary structures
and debris of every kind. He shall leave the site of the work in a neat and orderly condition at least equal
to that which originally existed. Surplus and waste materials removed from the site of the work shall be •
disposed of at locations satisfactory to the Engineer.
In the event Contractor fails or refuses to clean and remove surplus materials and debris as above
provided, the Owner or Engineer may do so, or cause same to be done, at the Contractor's expense and
the reasonable cost thereof shall be deducted from the final payment.
3.20 Guarantee Against Defective Work
The contractor warrants the materials and workmanship and that the work is in conformance with the
plans and specifications included in this contract for a period of one year from the data of acceptance of the
project. Said warranty binds the contractor to correct any work that does not conform with such plans and
specifications or any defects in workmanship or materials furnished under this contract which may be dis-
covered within the said one year period. The Contractor shall at his own expense correct such defect within
thirty days after receiving written notice of such defect from the Owner or Engineer by repairing same to
the condition called for in the contract documents and plans and specifications. Should the Contractor fail
or refuse to repair such defect within the said thirty day period or to provide acceptable assurances that
such repair work will be completed within a reasonable time thereafter, the Owner may repair or cause to
be repaired any such defect at the Contractor's expense.
3.21 Testing of Materials
Unless otherwise specified, testing of all materials to be incorporated into the project will be as directed by
the Engineer at the expense of the Owner. All retesting for work rejected on the basis of test results will be
at the expense of the Contractor and the extent of the retesting shall be determined by the Engineer. The
Engineer may require additional testing for failing tests and may require two passing retests before ac-
ceptance will be made by the Owner. The testing laboratory will be designated by the Owner.
All materials to be incorporated into the project must meet the requirements of these specifications. For
manufactured materials such as reinforcing steel, expansion joint materials, concrete pipe, cement, mis-
cellaneous steel, cast iron materials, etc., the Contractor will be required to furnish a manufacturer's cer-
tificate stating that the material meets the requirements specified for this project.
GC-12
11..7
1
r,✓
1
1
1
1
1
1
1
1
4. Prosecution and Progress
4.01 Time end Order of Completion
•
It is the meaning and intent of this contract, unless otherwise herein specifically provided, that the Con.
tractor shall be allowed to prosecute his work at such times and seasons, in such order of precedence.
and in such manner as shall be most conducive to economy of construction; provided, however, that the
order and the time of prosecution shall be such that the work shall be substantially completed as a whole
and in part, in accordance with this contract, the plans and specifications, and within the time of com-
pletion designated in the Proposal; provided, also, that when the Owner is having other work done,
either by contract or by his own force, the Engineer may direct the time and manner of constructing the
work done under this contract, so that conflict will be avoided and the construction of the various works
being done for the Owner shall be harmonized.
The Contractor shall submit, at such times as may reasonably be requested by the Engineer, schedules
which shall show the order in which the Contractor proposes to carry on the work, with dates at which
the Contractor will start the several parts of the work, and estimated dates of completion of the several
parts.
4.02 Extension of Time
Should the Contractor be delayed in the completion of the work by any act or neglect of the Owner or
Engineer, or of any employee of either, or by other contractors employed by the Owner, or by changes
ordered in the work, or by strikes, lockouts, fires, and unusual delays by common carriers, or unavoid-
able cause or causes beyond the Contractor's control, or by any cause which the Engineer shall decide
justifies the delay, then an extension of time shall be allowed for completing the work, sufficient to com-
pensate for the delay, the amount of the extension to be determined by the Engineer, provided, however,
that the Contractor shall give the Engineer prompt notice in writing of the cause of such delay.
4.03 Hindrances and Delays
No claims shall be made by the Contractor for damages resulting from hindrances or delays from any
cause (except where the work is stopped by order of and for the convenience of the Owner) during the
progress of any portion of the work embraced in this contract. In case said work shall be stopped by the
act of the Owner, then such expense as in the judgment of the Engineer is caused by such stoppage of
said work shall be paid by the Owner to the Contractor.
5. Measurement and Payment
5.01 Quantities and Measurements
No extra or customary measurements of any kind will be allowed, but the actual measured and /or com-
puted length, area, solid contents, number and weight only shall be considered, unless otherwise spe-
cifically provided.
5.02 Estimated Quantities
This agreement, including the specifications, plans and estimate, is intended to show clearly all work to
be done and material to be furnished hereunder. Where the estimated quantities are shown for the
various classes of work to be done and material to be furnished under this contract, they are approxi-
mate and are to be used only as a basis for estimating the probable cost of the work and for comparing
the proposals offered for the work. It is understood and agreed that the actual amount of work to be
done and material to be furnished under this contract may differ somewhat from these estimates, and
that where the basis for payment under this contract is the unit price method, payment shall be for the
actual amount of such work done and the material furnished.
GC-13
I
Where payment is based on the unit price method, the Contractor agrees that be will make no claim for
damages, anticipated profits or otherwise on account of any differences which may be found between the
quantities of work actually done, the material actually furnished under this contract and the estimated
quantities contemplated and contained in the proposal; provided, however, that in case the actual quart•
tity of any major item should become as much as 20% more than, or 20% less than the estimated or con.
templated quantity for such items, then either party to this Agreement, upon demand, shall be entitled
to a revised consideration upon the portion of the work above or below 20% of the estimated quantity.
A "Major Item" shall be construed to be any individual bid Item incurred in the proposal that has a
total cost equal to or greater than five (5) per cent of the total contract cost, computed on the basis of
the proposal quantities and the contract unit prices.
Any revised consideration is to be determined by agreement between the parties, otherwise by the terms
of this Agreement, as provided under "Extra Work."
5.03 Price of Work
In consideration of the furnishing of all the necessary labor, equipment and material, and the completion
of all work by the Contractor, and on the completion of all work and on the delivery of all material em-
braced in this Contract in full conformity with the specifications and stipulations herein contained, the
Owner agrees to pay the Contractor the prices set forth in the Proposal hereto attached, which has been
made a part of this contract. The Contractor hereby agrees to receive such prices in full for furnishing all
material and all labor required for the aforesaid work, also for all expense incurred by him, and for well
and truly performing the same and the whole thereof in the manner and according to this Agreement.
5.04 Partial Payments � of p ct 1 \ k��
On or before the 1st day of each month, tI4 Contractor shall submit to the Engineer a statement showing
the total value of the work performed up to and including the 25th day of the preceding month. The state-
ment shall also include the value of all sound materials delivered on the job site and to be included in the
work all partially completed work whether bid as a lump sum or a unit item which in the opinion of the
Engineer is acceptable. The Engineer shall examine and approve or modify anri approve such statement.
The Owner shall then pay the Contractor on or before the 10th day of the current month the total
amount of the approved statementfless cent of the amount_thereof; rohich 10 per cent shall be
retained until final payment, and further previous payments and all further sums that may be
retained by the Owner under the terms of this Agreement. It is understood, however, that in case the
whole work be near to completion and some unexpected and unusual delay occurs due to no fault or
neglect on the part of the Contractor, the Owner may —upon written recommendation of the Engineer —
pay a reasonable and equitable portion of the retained percentage to the Contractor: or the Contractor at
the Owner's option, may be relieved of the obligation to fully complete the work and, thereupon, the
Contractor shall receive payment of the balance due him under the contract subject only to the condi-
tions stated under "Final Payment."
5.05 Use of Completed Portions
The Owner shall have the right to take possession of and use any completed or partially completed por-
tions of the work, notwithstanding the time for completing the entire work or such portions may not
have expired but such taking possession and use shall not be deemed an acceptance of any work not
completed in accordance with the Contract Documents. If such prior use increases the cost of or delays
the work, the Contractor shall be entitled to such extra compensation, or extension of time, or both, as
the Engineer may determine.
The Contractor shall notify the Engineer when, in the Contractor's opinion, the contract is "substan-
tially completed" and when so notifying the Engineer, the Contractor shall furnish to the Engineer in
writing a detailed list of unfinished work. The Engineer will review the Contractor's list of unfinished
work and will add thereto such items as the Contractor has failed to include. The "substantial comple-
tion" of the structure or facility shall not excuse the Contractor from performing all of the work under-
taken, whether of a minor or major nature, and thereby completing the structure or facility in accor-
dance with the Contract Documents.
GC -14 P... r.,vs
ki
ti ,
1 ..
a
1
1
I
1
6. Extra Work and Claims
6.01 Change Orders
6.06 Final Compistlon and Acceptance
Within ten U0) days after the Contractor has given the Engineer written notice that the work Las been
completed, or substantially completed, the Engineer and the Owner shall inspect the work and within
said time, if the work be found to be completed in accordance with the Contract Documents, the Engi-
neer shall issue to the Owner and the Contractor his Certificate of Completion, and thereupon it shall be
the duty of the Owner within ten (10) days to issue a Certificate of Acceptance of the work to the Con.
tractor or to advise the Contractor in writing of the reason for non- acceptance.
6.07 Final Payment
Upon the issuance of the Certificate of Completion, the Engineer shall proceed to make final measure•
ments arid prepare final statement for the value of all work performed and materials furnished under the
terms of the Agreement and shall certify same to the Owner, who shall pay to the Contractor on or
before the 30th day, and before the 35th day, after the date of the Certificate of Completion, the balance
due the Contractor under the terms of this contract; and said payment shall become due in any event
upon said performance by the Contractor. Neither the Certificate of Acceptance nor the final payment,
nor any provision in the Contract Documents, shall relieve the Contractor of the obligation for fulfill-
ment of any warranty which may be required.
•
5.08 Payments Withheld
The Owner may, on account of subsequently discovered evidence, withhold or nullify the whole or part
of any certificate to such extent as may be necessary to protect himself from loss on account of:
(a) Defective work not remedied or other obligations hereunder not done.
(b) Claims filed or reasonable evidence indicating probable filing of claims.
(c) Failure of the Contractor to make payments properly to subcontractors or for material or labor.
(dl Damage to another contractor.
(e) Reasonable doubt that the work can be completed for the unpaid balance of the contract amount.
(f) Reasonable indication that the work will not be completed within the contract time.
When the above grounds are removed or the Contractor provides a Surety Bond satisfactory to the
Owner, which will protect the Owner in the amount withheld, payment shall be made for amounts
withheld because of them.
5.09 Delayed Payments
Should the Owner fail to make payment to the Contractor of the sum named in any partial or final state-
ment, when payment is due, then the Owner shall pay to the Contractor, in addition to the sum shown as
due by such statement, interest thereon at the rate of 6% per annum, unless otherwise specified, from date
due as provided under 'partial payments' and 'final payments,' until fully paid, which shall fully liquidate
any injury to the contractor growing out of such delay in payment. It is expressly agreed that delay by the
Owner in making payment to the Contractor of the sum named in any partial or final statement shall not
constitute a breach of this contract on the part of the Owner nor an abandonment thereof nor shall it to
any extent or for any time relieve the Contractor of his obligations to fully and completely perform here-
under.
Without invalidating this Agreement, the Owner may, at any time or from time to time, order additions,
deletions or revisions to the work; such changes will be authorized by Change Order to be prepared by
the Engineer for execution by the Owner and the Contractor. The Change Order shall set forth the basis
for any change in contract price, as hereinafter set forth for Extra Work, and any change in contract
time which may result from the change.
5...7.1.75
GC-15
In the event the Contractor shall refuse to execute a Change Order which bu been prepared by the
- Engineer and executed by the Owner, the Engineer may in writing instruct the Contractor to proceed
. with the work u set forth in the Change Order and the Contractor may make claim against'the Owner
for Extra Work Involved therein, as hereinafter provided,
6.02 Minor Changes
The Engineer may authorize minor changes in the work not inconsistent with the overall intent of the
Contract Documents and not involving an increase In Contract Price. If the Contractor believes that any
minor change or alteration authorized by the Engineer involves Extra Work and entitles him to an in-
crease in the Contract Price, the Contractor shall make written request to the Engineer for a written
Field Order.
In such case, the Contractor by copy of Ms communication to the Engineer or otherwise in writing shall
advise the Owner of his request to the Engineer for a written Field Order and that work involved may
result in an increase in the Contract Price.
Any request by the Contractor for a change in Contract Price shall be made prior to beginning the work
covered by the proposed change.
6.03 Extra Work
It is agreed that the basis of compensation to the Contractor for work either added or deleted by a
Change Order or for which a claim for Extra Work is made shall be determined by the unit prices upon
which this contract was bid to the extent such work can be fairly classified within the various work item
descriptions and for work items that cannot be so classified by one or more of the following meth„ds:
Method (A) •
By agreed unit prices; or
Method (8)
By agreed lump sum; or
Method (C)
If neither Method (A) nor Method (B) be agreed upon before the Extra Work is commenced,
then the Contractor shall be paid the "actual field cost" of the work, plus fifteen (15) percent.
In the event said Extra Work be performed and paid for under Method (C), then the provisions of this
paragraph shall apply and the "actual field cost" is hereby defined to include the cost to the Contractor
of all workmen, such as foreman, timekeepers, mechanics and laborers, and materials, supplies, trucks,
rentals on machinery and equipment, for the time actually employed or used on such Extra Work, plus
actual equipment, for the time actually employed or used on such Extra Work, plus actual transporta-
tion charges necessarily incurred, together with all power, fuel, lubricants, water and similar operating
expenses, also all necessary incidental expenses incurred directly on account of such Extra Work,
including Social Security, Old Age Benefits and other payroll taxes, and, a rateable proportion of
premiums on Performance and Payment Bonds and Maintenance Bonds, Public Liability and Property
Damage and Workmen's Compensation, and all other insurance as may be required by any law or
ordinance, or directed by the Owner, or by them agreed to. The Engineer may direct the form in which
accounts of the "actual field cost" shall be kept and the records of these accounts shall be made avail-
able to the Engineer. The Engineer or Owner may also specify in writing, before the work commences,
the method of doing the work and the type and kind of machinery and equipment to be used; otherwise
these matters shall be determined by the Contractor. Unless otherwise agreed upon, the prices for the
use of machinery and equipment shall be determined by using 100 per cent, unless otherwise specified, of
the latest schedule of Equipment Ownership Expense adopted by the Associated General Contractors of
America. Where practicable the terms and prices for the use of machinery and equipment shall be incor-
porated in the Written Extra Work Order. The fifteen (15 %) per cent of the "actual field cost" to be paid
the Contractor shall cover and compensate him for his profit, overhead, general superintendence and
field office expense, and all other elements of cost and expense not embraced within the "actual field
cost" as herein defined, save that where the Contractor's Camp or Field Office must be maintained pri-
GC -l6
e.
I
1
t
' X0 5
Arbitration
inertly on a000uat of such Extra Work: than the cost to maintain and operate the same shall be Included
!a tba "actual field cost." No claim for Extra Work of any kind will be allowed unless ordered In writing by the Engineer. In ease
any orders or instructions, either oral or written, appear to the Contractor to involve Extra Work for
which he should receive compensation or an adjustment in the construction time, he shall make written
request to the Engineer for written order authorizing such Extra Work. Should a difference of opinion
arise as to what does or does not constitute Extra Work, or as to the payment therefor, and the
Engineer insists upon its performance, the Contractor shall proceed with the work after making written
request for written order and shall keep an accurate account of the "actual field cost" thereof, as pro.
vided under Method (C). The Contractor will thereby preserve the right to submit the matter of
payment to arbitration, as hereinbelow provided.
6.04 Time of Filing Claims
It is further agreed by both parties hereto that all questions of dispute or adjustment presented by the
Contractor shall be in writing and filed with the Engineer within thirty (30) days after the Engineer has
given any directions, order or instruction to which the Contractor desires to take exception. The
Engineer shall reply within thirty (30) days to such written exceptions by the Contractor and render his
final decision in writing. In case the Contractor should appeal from the Engineer's decision, any demand
for arbitration shall be filed with the Engineer and the Owner in writing within ten (10) days after the
date of delivery to Contractor of the Engineer's final decision. It is further agreed that final acceptance
of the work by the Owner and the acceptance by the Contractor of the final payment shall be a bar to
any claims by either party, except claims by Owner for defective work or enforcement of warranties and
except as noted otherwise in the contract documents.
All questions of dispute under this Agreement shall be submitted to arbitration at the request of either
party to the dispute. The parties may agree upon one arbiter, otherwise, there shall be three, one named
in writing by each party, and the third chosen by the two arbiters so selected; or if the arbiters fail to
select a third within ten (10) days, he shall be chosen by a District Judge serving the County in which
the major portion of the project is located, unless otherwise specified. Should the party demanding
arbitration fail to name an arbiter within ten (10) days of the demand, his right to arbitrate shall lapse,
and the decision of the Engineer shall be final and binding on him. Should the other party fail to choose
an arbiter within ten (101 days, the Engineer shall appoint such arbiter. Should either party refuse or
neglect to supply the arbiters with any papers or information demanded in writing, the arbiters are
empowered by both parties to take ex parte proceedings.
The arbiters shall act with promptness. The decision of any two shall be binding on both parties to the
contract. The decision of the arbiters upon any questions submitted to arbitration under this contract
shall be a condition precedent to any right of legal action. The decision of the arbiter or arbiters may be
filed in court to carry it into effect.
The arbiters, if they deem the case demands it, are authorized to award the party whose contention is
sustained, such sums as they deem proper for the time, expense and trouble incident to the appeal, and
if the appeal was taken without reasonable cause, they may award damages for any delay occasioned
thereby. The arbiters shall fix their own compensation unless otherwise provided by agreement, and
shall assess the cost and charges of the arbitration upon either or both parties. The award of the arbiters
must be made in writing.
7. Abandonment of Contract
7.01 Abandonment by Contractor
In case the Contractor should abandon and fail or refuse to resume work within ten (10) days after writ-
ten notification from the Owner, or the Engineer, or if the Contractor fails to comply with the orders of
GC -17
:fl
the Engines, when such orders are consistent with the Contract Documents, then, and in that ease,
`
L_e__re �performance and payment bonds exist, the Sureties on these bonds shall be notified in writing and
[eeeted to complete the work, and a copy of said notice shall be delivered to the Contractor.
After receiving said notice of abandonment the Contractor shall not remove from the work any marlin.
&y, equipment, tools, materials or supplies then on the job, but the same, together with any materials
Mild equipment under contract for the work, may be held for use on the work by the Owner or the Surety
on the performance bond, or another contractor in completion of the work: and the Contractor shall not
lye any rental or credit therefor (except when used in connection with Extra Work, where credit shall
■` a allowed as provided for under Section 6, Extra Work and Claims), it being understood that the use of
such equipment and materials will ultimately reduce the cost to complete the work and be reflected in
Abe final settlement.
here there is no performance bond provided or in case the Surety should fail to commence compliance
with the notice for completion hereinbefore provided for, within ten (10) days after service of such notice,
T hen the Owner may provide for completion of the work in either of the following elective manners:
(1) The Owner may thereupon employ such force of men and use such machinery, equipment, tools,
materials and supplies as said Owner may deem necessary to complete the work and charge
' the expense of such labor, machinery, equipment, tools, materials and supplies to said Con-
tractor, and expense so charged shall be deducted and paid by the Owner out of such moneys
as may be due, or that may thereafter at any time become due to the Contractor under and
by virtue of this Agreement. In case such expense is less than the sum which would have
'
been payable under this contract, if the same had been completed by the Contractor, then
said Contractor shall receive the difference. In case such expense is greater than the sum
which would have been payable under this contract, if the same had been completed by said
I Contractor, then the Contractor and /or his Surety shall pay the amount of such excess to the
Owner, or
(2) The Owner under competitive bids, taken after notice published as required by law, may let the
I
contract for the completion of the work under substantially the same terms and conditions
which are provided in this contract. In case there is any increase in cost to the Owner under
the new contract as compared to what would have been the cost under this contract, such
increase shall be charged to the Contractor and the Surety shall be and remain bound there.
for. However, should the cost to complete any such contract prove to be less than would
have been the cost to complete under this contract, the Contractor and /or his Surety shall
be credited therewith.
L hen the work shall have been substantially completed the Contractor and his Surety shall be so noti-
fied and Certificates of Completion and Acceptance, as provided in Paragraph 5.06 hereinabove, shall be
�t sued. A complete itemized statement of the contract accounts, certified to by the Engineer as being
orrect, shall then be prepared and delivered to the Contractor and his Surety, whereupon the Con-
tractor and /or his Surety, or the Owner as the case may be, shall pay the balance due as reflected by
li aid statement, within fifteen (15) days after the date of such Certificate of Completion.
n the event the statement of accounts shows that the cost to complete the work is less than that which
would'have been the cost to the Owner had the work been completed by the Contractor under the terms
f this contract; or when the Contractor and /or his Surety shall pay the balance shown to be due by
hem to the owner, then all machinery, equipment, tools, materials or supplies left on the site of the
ork shall be turned over to the Contractor and /or his Surety. Should the cost to complete the work
exceed the contract price, and the Contractor and /or his Surety fail to pay the amount due the Owner
i thin the time designated hereinabove, and there remains any machinery, equipment, tools, materials
r supplies on the site of the work, notice thereof, together with an itemized list of such equipment and
materials, shall be mailed to the Contractor and his Surety at the respective addresses designated in this
'contract, provided, however, that actual written notice given in any manner will satisfy this condition.
After mailing, or other giving of such notice, such property shall be held at the risk of the Contractor
and his Surety subject only to the duty of the Owner to exercise ordinary care to protect such property.
After fifteen (151 days from the date of said notice the Owner may sell such machinery, equipment,
,tools, materials or supplies and apply the net sum derived from such sale to the credit of the Contractor
and his Surety. Such sale may be made at either public of private sale, with or without notice, as the
IC -18
Owner may elect. The Owner shall release any machinery, equipment, tools, materials, or supplies, which
remain on the work, and belong to persons other than the Contractor or his Surety, to their proper
owners. The books on all operations provided herein shall be opened to the Contractor and his Surety.
7.02 Abandonment by Owner
In case the Owner shall fail to comply with the terms of this contract, and should fail to comply with
said terms within ten (10) days after written notification by the Contractor, then the Contractor may
suspend or wholly abandon the work, and may remove therefrom all machinery, tools and equipment,
and all materials on the site of work that have not been included in payments to the Contractor and
have not been wrought into the work. And thereupon the Engineer shall make an estimate of the total
amount earned by the Contractor, which estimate shall include the value of all work actually completed
by said Contractor (at the prices stated in the attached proposal where unit prices are used), the value of
all partially completed work at • fair and equitable price, and the amount of all Extra Work performed
at the prices agreed upon, or provided for by the terms of this contract, and • reasonable sum to cover
the cost of any provisions made by the Contractor to carry the whole work to completion and which
cannot be utilized. The Engineer shall then make a final statement of the balance due the Contractor by
deducting from the above estimate all previous payments by the Owner and all other sums that may be
retained by the Owner under the terms of this Agreement and shall certify same to the Owner who shall
pay to the Contractor on or before thirty (30) days after the date of the notification by the Contractor
the balance shown by said final statement as due the Contractor, under the terms of this Agreement.
I -
8. Subcontractors -
•tfl:o1 Award of - Subs oritracts -of-tne -Work
Unless otherwise specified in the Contract Documents or in the Instructions to Bidders, the Contractor,
as soon as practicable after the award of the Contract, shall furnish to the Engineer in writing for accep-
::7:. tance e by the Owner and the Engineeria _list,.of_the_names_of_ the= Subcontrac tors - proposed= for.=the
, principal.po`ions of orrk . The Engineer shall promptly notify the Contractor in writing if either the
I Owner or the Engineer, after due investigation, has reasonable objection to any Subcontractor on such
list and does not accept him. Failure of the Owner or Engineer to make objection promptly to any Sub-
contractor on the list shall constitute acceptance of such Subcontractor. -
I The Contractor shall not contract with any Subcontractor or any person or organization (including those
who are to furnish materials or equipment fabricated to a special design) proposed for portions of the
work designated in the Contract Documents or in the Instructions to Bidders or, if none is so desig-
I mated, with any Subcontractor proposed for the principal portions of the work who has been rejected by
the Owner and the Engineer. The Contractor will not be required to contract with any Subcontractor or
person or organization against whom he has a reasonable objection.
I If the Owner or Engineer refuses to accept any Subcontractor or person or organization on a list sub-
mitted by the Contractor in response to the requirements of the Contract Documents or the Instructions
to Bidders, the Contractor shall submit an acceptable substitute and the Contract amount shall be
I increased or decreased by the difference in cost occasioned by such substitution and an appropriate
change order shall be issued; however, no increase in the Contract amount shall be allowed for any such
substitution unless the Contractor has acted promptly and responsively in submitting for acceptance
I any list or lists of names as required by the Contract Documents or the Instructions to Bidders.
If the Owner or the Engineer requires a change of any proposed Subcontractor or person or organization
previously accepted by them, the Contract amount shall be increased or decreased by the difference in
J cost occasioned by such change and an appropriate Change Order shall be issued.
The Contractor shall not make any substitution for any Subcontractor or person or organization who
i has been accepted by the Owner and the Engineer, unless the substitution is acceptable to the Owner
and the Engineer.
-GC -19
842 Subcontractual Relations
f1-20
tee work performed for the Contractor bye Subcontractor shall be pursuant to an appropriate' written
meat between the Contractor and the Subcontractor (and where appropriate between Subcontr•c•
j o ts and Sub-subcontractors) which shall contain provisions that:
(11 preserve and protect the rights of the Owner and Engineer under the Contract with respect to
the work to be performed under the subcontract so that the subcontracting thereof will not
prejudice such rights;
(2) require that such work be performed in accordance with the requirements of the Contract Docu•
ments;
(3) require submission to the Contractor of the applications for payment under each subcontract
to which the Contractor is • party, in reasonable time to enable the Contractor to apply for
payment in accordance with this contract;
(4) require that all claims for additional costs, extensions of time, damages for delays or otherwise
with respect to subcontracted portions of the work shall be submitted to the Contractor (via
any Subcontractor or Sub-subcontractor where appropriate) in sufficient time so that the
Contractor may comply in the manner provided in the Contract Documents for like claims
by the Contractor upon the Owner;
(5) obligate each subcontractor specifically to consent to the provisions of this section.
A copy of all such Subcontract Agreements shall be filed by the Contractor with the Engineer before the
ubcontractor shall be allowed to commence work.
.03 Payments to Subcontractors
he Contractor shall pay each Subcontractor, upon receipt of payment from the Owner, an amount
irectly based upon the value of the work performed and allowed to the Contractor on account of such
Subcontractor's work, less the percentage retained from payments to the Contractor. The Contractor
t all also require each Subcontractor to make similar payments to his subcontractors.
the Engineer fails to approve a payment for any cause which is the fault of the Contractor and not the
fault of a particular Subcontractor, the Contractor shall pay the Subcontractor on demand, made at any
� e after the Certificate for Payment should otherwise have been issued, for his work to the extent co-
leted, less the retained percentage.
he Engineer may, on request and at his discretion, furnish to any Subcontractor, if practicable,
ormation regarding percentages of completion certified to the Contractor on account of work done by
ch Subcontractors.
I eith the Owner nor the Engineer shall have any obligation to pay or to see to the payment of any
er
oneys to such Subcontractor except as may otherwise be required.
I . Separate Contracts
1 01 Owner's Right to Award Separate Contracts
The Owner reserves the right to award other contracts in connection with other portions of the project
der these or similar conditions of the Contract.
finder
separate contracts are awarded for different portions of the Project, "The Contractor" in the
contract documents in each case shall be the contractor who signs each separate contract.
1 02 Mutual Responsibility of Contractors
a ir materials and equipment and the execution of their work, and shall properly connect and coor.
ate his work with theirs.
s -
r
1
1
1
1
1
1
1
1
1
1
1
1
1
If any part of the Contractor's work depends for proper execution or results upon the worm of any other
separate contractor, the Contractor shall inspect and promptly report to the Engineer any apparent
discrepancies or defects in such work that render it unsuitable for such proper exaction and results.
Failure of the Contractor so to inspect and report shall constitute an acceptance of the other contractor's
work as fit and proper to receive his Work, except as to defects which may develop in the other separate
contractor's work after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property of any separate contractor on the project,
the Contractor shall, upon due notice, settle with such other contractor by agreement or arbitration, if
he will so settle. If such separate contractor sues the Owner or initiates an arbitration proceeding on
account of any damage alleged to have been so sustained, the Owner shall notify the Contractor who
shall defend such proceedings at the Contractor's expense, and If any judgment or award against the
Owner arises therefrom the Contractor shall pay or satisfy it and shall reimburse the Owner for all
attorney's fees and court or arbitration costs which the Owner has incurred.
9.03 Cutting and Patching under Separate Contracts
The Contractor shall be responsible for any cutting, fitting and patching that may be required to com-
plete his work except as otherwise specifically provided in the Contract Documents. The Contractor
shall not endanger any work of any other contractors by cutting, excavating or otherwise altering any
work and shall not cut or alter the work of any other contractor except with the written consent of the
Engineer.
Any costs caused by defective or ill-timed work shall be borne by the party responsible therefor.
10. Protection of Persons and Property
10.01 Safety Precautions and Programs
The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions
and programs in connection with the work.
10.02 Safety of Persons and Property
The Contractor shall take all reasonable precautions for the safety of, and shall provide all reasonable
protection to prevent damage, injury, or loss to:
(1) all employees on the work and all other persons who may be affected thereby;
(2) all the work and all materials and equipment to be incorporated therein, whether in storage or
or off the site, under the care, custody or control of the Contractor or any of his
Subcontractors or Sub-Subcontractors; and
(3) other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pave-
ments. fences, roadways, structures and utilities not designated for removal, relocation or
replacement in the course of construction.
The Contractor shall comply with all applicable laws, ordinances, rules, regulations and lawful orders of
any public authority having jurisdiction for the safety of persons or property or to protect them from
damage, injury or loss. He shall erect and maintain, as required by existing conditions and progress of
the work, all reasonable safeguards for safety and protection, including posting danger signs and other
warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent
utilities.
When the use or storage of explosives or other hazardous materials or equipment is necessary for the
execution of the work, the Contractor shall exercise the utmost care and shall carry on such activities
under the supervision of properly qualified personnel.
11... 7.145
GC-21
•
I
All Blasting, including methods of storing and handling explosives and highly inflammable materials,
shall conform to Federal, State, Local laws and Ordinances. All City Ordinances shall be complied with
even though some or all of the blasting is done outside the City Limits unless the applicable Ordinance is
in conflict with the law of the Jurisdiction where the action is being taken.
The following is a list of requirements in addition to Federal, State, and Local Laws and Ordinances.
1. The Contractor shall furnish the City of Austin with a Certificate of Blasting Insurance in the
amount of 1300,000.00 for each contract, at least twenty-four hours prior to using explosives.
A blasting permit must be obtained from the City at least five (5) days prior to use of explo-
sives. If Blasting is covered under the Contractor's General Insurance Certificate for each
• contract, • separate blasting certificate w01 not be required.
2. The following public utility companies and City Department well be notified by the Contractor, on
every occasion, at least twenty -four (24) hours prior to the use of explosives: Water and
Wastewater, Electric, Gas, Telephone and the City Engineering Department.
3. Explosive materials to be used shall be limited to blasting agents and dynamite, unless prior ap-
proval of other materials is obtained in writing from the Engineering Department.
4. During blasting, all reasonable precautions shall be taken to protect pedestrians, passing vehicles,
and public or private property. Blasting mats or protective cover shall be used when required
by the City Inspector, the permit, or by safe blasting practices.
5. All explosives shall be stored in accordance with Chapter 38, Article 11, Section 38-11201, of the
City Code.
6. The Director of Engineering or his representative shall have the right to limit the use of explosives
and /or blasting methods which in his opinion are dangerous to the public or nearby property
of any kind.
7. The Contractor, at his expense, shall promptly repair or replace all items known to be damaged as
a result of blasting. All claims of damage shall be investigated by the City or by Consulting
Firms approved by the City.
8. The Contractor shall maintain accurate records throughout the Blasting operations showing the
type explosive used, number of holes, pounds per hole, depth of hole, total pounds per shot,
delays used, date and time of blast and initials of the Inspector. The Contractor is fully re-
sponsible for all claims resulting from his blasting operation.
All damage or loss to any property referred to in this article caused in whole or in part by the Contrac-
tor, any Subcontractor, any Sub - subcontractor, or anyone directly or indirectly employed by any of
them, or by anyone for whose acts any of them may be liable, shall be remedied by the Contractor,
except damage or loss attributable solely to faulty Drawings or Specifications or solely to the acts or
omissions of the Owner or Engineer or anyone employed by either of them, and not attributable in any
degree to the fault or negligence of the Contractor.
10.03 Location and Protection of Utilities
Notwithstanding any other provision of this contract, the Contractor shall be solely responsible for the
location and protection of any and all public utility lines and utility customer service lines in the work
area The Contractor shall exercise due care to locate and to mark, uncover or otherwise protect all such
lines in the construction zone and any of the Contractor's work or storage areas. Upon request, the
Owner shall provide such information as it has about the location and grade of water, sewer, gas, and
telephone and electric lines and other utilities in the work area but such information shall not relieve or
be deemed to be in satisfaction of the Contractor's obligation hereunder, which shall be primary and
nondelegable. Any such lines damaged by the Contractor's operations shall be immediately repaired by
the Contractor or he shall cause such damage to be repaired at his expense.
GC -22
The contractor shall designate a responsible member of his organization at the site whose duty shall be
the prevention of accidents. This person shall be the Contractor's superintendent unless otherwise desig-
nated in writing by the Contractor to the Owner and the Engineer.
5.0 SPECIAL CONDITIONS
1
A CTION 01 - IN ION
01 - 01 ENGINEER
The word 'Engineer" in these Specifications shall be
understood as referring to The City of Round Rock, 214 East
Main Street, Round Rock, Texas 78664. Engineer of the Owner,
or the Engineer's authorized representative to act in any
particular position for the Owner.
01 - 02 COPIES OF PLANS AND SPECIFICATIONS FURNISHED
The Agreement will be prepared in not less than five (5)
counterpart (original signed) sets. Owner will furnish
Contractor two (2) sets of conforming Contract Documents,
Technical Specifications and Plans free of charge, and
additional sets will be obtained from Engineer at commercial
reproduction rates plus 20% for handling.
01 - GOVERNING CODES
All construction as provided for under these Plans and
Specifications shall be governed by any existing
Resolutions, Codes and Ordinances, and any subsequent
amendments or revisions thereto as set forth by the Owner.
01 -04 LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE ON TIME
The Contractor agrees that time is of the essence for this
Contract and that the definite value of damages which would
result from delay would be incapable of ascertainment
and uncertain, so that for each day of delay beyond the
number of days herein agreed upon for the completion of the
work herein specified and contracted for, after due
allowance for such extension of time as is provided for
under the provisions of Section 4.02 of the General
Conditions, the Owner may withold permanently from the
Contractor's total compensation, not as penalty but as
liquidated damages, the sum of $50.00 per calendar day.
01 -05 IACATICN
The location of work shall be as mentioned in the Notice to
Contractors and as indicated on Plans.
01 - USAGE OF WATER
Contractor shall pay all costs of water used. Water is to be
metered by Contractor and the cost is to be subsidiary to
other bid items. No additional pay will be made for water.
SC -1
1
SWIGS 02 - SPECIAL CONSIDERATIONS
02 -01 CROSSING UTILITIES
Prior to commencing construction, it shall be the
Contractor's responsibility to make arragements with the
Owners of such utility companies to uncover their particular
utility lines or otherwise confirm their location. Certain
utility companies perform such services at their own
expense, however, where such is not the case, the Contractor
will cause such work to be done at his own expense.
02 -02 "AS- BUILTS" DRAWINGS
The Contractor shall mark all changes and revisions on all
of his copies of the working drawings during the course of
the Project as they occur. Upon completion of the Project
and prior to final acceptance and payment, the contractor
shall show field locations of all above ground appurtenances
including but not limited to valves, fire hydrants and
manholes. Each appurtenance shall be located by at least two
(2) horizontal distances measured from existing, easily
identifiable, immovable appurtenances such as fire hydrants
or valves. Property pins can be used for as -built tie -ins
provided no existing utilities as previously described are
available. Costs for developing as -built drawings shall be
subsidiary to other bid items.
02 -03 LANDS FOR WORE
Owner provides, as indicated on Drawings, land upon which
work is to be done, rights - of-way for access to same and
such other lands which are designated for use Contractor.
Contractor provides, at his expense and without liability of
Owner, any additional land and access thereto that may be
required for his construction operations, temporary
construction facilities, or for storage of materials.
02 - UTILITY SERVICES FOR CONSTRUCTION
The Contractor will be responsible for providing his own
utility services during construction. No additional payment
will be made for this item.
1
If pay estimates from the Contractor are not received by the
Engineer on or before the time specified in Section 5.04 of
the General Conditions, then the pay estimate will not be
processed and will be returned to the Contractor.
SC -2
SC -3
02 CIUMANTRES
Guarantee work, including equipment installed, shall be free
from defects due to faulty workmanship or materials for a
period of one (1) year from the date of final acceptance by
the Owner. Upon notice from Owner, the Contractor shall
repair defects in all construction which develop during
specified period at no cost to Owner. Neither final
acceptance, Certificate of Completion, final payment nor any
provision in Contract Documents relieves Contractor of above
guarantee. Notice of observed defects will be given with
reasonable promptness. Failure to repair or replace defect
upon notice entitles Owner to repair or replace same and
recover reasonable cost thereof from Contractor.
02 - DEVIATIONS OCCASIONED BY uriurY STRUCTURES
Whenever existing utilities, not indicated on Plans, present
obstructions to grade and alignment of pipe, immediately
notify Engineer, who without delay, will determine if
existing improvements are to be relocated, or grade and
alignment of proposed inprovements changed. Where necessary
to move existing services, poles, guy wires, pipelines,
etc., as determined by the Engineer, the Contractor will
make arrangements with the owner of the utility to be moved
and have it moved. The cost of any utility relocation will
be at the Contractor's sole expense. Owner will not be
liable for relocation costs or damages on account of delays
due to changes made by owners of privately owned utilities
which hinder progress of the work.
02 -07 MINIMUM WAGE SCALE
Minimum wage scale as specified and regulated by the State
of Texas and the Federal Government.
02 -08 LIMFP OF FINANCIAL RESQJRCES
The Owner has a limited amount of financial resources
committed to this Project; therefore, it shall be understood
by all bidders that the Owner may be required to change -
and/or delete any items which he may feel is necessary to
accomplish all or part of the scope of work within its limit
of financial resources. Contractor shall be entitled to no
claim for damages for anticipated profits on any portion of
work that may be omitted. At any time during the duration of
this contract, the Owner reserves the right to omit any work
from this contract. Unit prices for all items previously
approved in this contract shall be used to delete or add
work per change order.
1
t
02 -11 PAYMENT T FOR MFc ERIAIS ON HAND
Owner shall pay for 90% of amount of materials on hand in
accordance with monthly estimate procedure stipulated in the
General Conditions of the Agreement.
02-12 CONSTRUCTION SPARING
The Contractor shall provide all necessary construction
' staking required to successfully carry out the work included
in this contract, as shown on the Plans and as described in
the contract documents and technical specifications. The
' Contractor shall consult with the Engineer prior to
construction staking in order that the Engineer may direct
the Contractor in staking the location, alignment and grades
' of the proposed improvements. Contractor shall notify the
Engineer not less than twenty -four (24) hours prior to the
time of anticipated construction staking. No additional pay
will be made for construction staking.
SLION 03 - INSURANCE
I 03 -01 insurance policies must be obtained by the Contractor or
separate endorsement obtained by his existing insurance
policies on projects that involve special hazards, such as
' blasting, excavation on public properties, etc.
The principal types of insurance which will be necessary
are:
1
I
1
1
02 CCNSTRDMION REVIEW
The Owner. shall provide a project representative to- review
the quality of materials and workmanship.
02-10
LIMITS DP W= AND PAYMENT
It shall be the obligation of the Contractor to crnplete all
work included in this contract, so authorized by the Owner,
as shown on the drawings or described in the contract
documents and technical specifications. All items of
construction not specifically paid for in the bid schedule
shall be included in the unit price bids. Any question
arising as the limits of - work shall be left up to the
interpretation of the Engineer.
SC -4
INDEMNITY
Contractor's Indemnity Provision. To protect the Owner from
the Contractor's failure to perform any of the foregoing duties
or any of the terms of this Contract, the Contractor shall
indemnify and save harmless the Owner and the Owner's agents
and employees from all losses, damages, judgments, decrees,
expenses or costs of any nature whatsoever arising out of or
in anyway connected with any claims or actions of law or in
equity brought against the Owner and the Owner's agents and
employees for the death or injury to persons or for damage
to property caused, or allegedly caused, by any willful acts,
negligence, nuisance, or breach or any term or condition of
this Contract by the Contractor, his agents, servants,
subcontractors, or employees. The Contractor shall furthermore
indemnify and save harmless the Owner and the Owner's agents
and employees from all demands of subcontractors, workers,
material, persons, or suppliers of machinery and parts thereof,
equipment, power tools, and supplies incurred in connection
with work to be performed under this Contract. Property of
any description, including property of the Onwer, which shall
be damaged in the performance of this Contract by the Contractor,
his agents, employees and subcontractors shall be restored
to its condition prior to damage by the Contractor at the
Contractor's expense.
03 -03 Workers' Compensation Insurance. The Contractor agrees to
comply with the Workers' Compensation Act of the State of Texas,
and to pay or cause to be paid all compensation, medical or
other benefits, which may become due or payable thereunder,
and to protect and indemnify the Owner and the Owner's agents
and employees from and against any and all liabilities by reason
of accidental injury, disease or death sustained by
subcontractor's employees. The Contractor shall furnish the
Owner with a certificate from the Industrial Accident Board
evidencing the Contractor's and subcontractor's compliance
with said statute.
03 -04 Comprehensive General Liability Insurance. The Contractor
shall provide and maintain during the life of this Contract
and until all work under said Contract has been completed and
accepted by the Owner, a Comprehensive General Liability
insurance policy, said policy and the issuing carrier approved
by the Owner, which specifically insures the contractual
liability of the Contractor assumed under Paragraph 03 -02 above
entitled "Contractor's Indemnity Provision ". The liability
coverage under this policy shall cover Independent Contractors.
SC -5
Liability limits for the Comprehensive General Liability
insurance coverage under this policy shall not be less than
the following:
Bodily Injury
Property Damage
03 -05 Owner's Protective Insurance. The Contractor shall provide
and maintain during the life of this Contract and until all
work under said Contract has been completed and accepted by
the Owner, an Owner's and Contractor's Protective Policy which
co- insures the Owner and the Owner's agents and employees with
the same Comprehensive General Liablity coverage as described
in 03 -04 above entitled "Comprehensive General Liability
Insurance ".
03 -06 Comprehensive Automobile Liability Insurance. The Contractor
shall provide and maintain during the life of this Contract
and until all work under said Contract has been completed and
accepted by the Owner, a Comprehensive Automobile Liability
insurance policy, said policy and issuing carrier approved
by the Owner, covering the operation on or off the site of
the work of all motor vehicles licensed for highway use, whether
they are owner, non- owned, or hired by the Contractor, in which
shall specifically insure contractual liability of the Contractor
assumed under the above Paragraph 03 -02 entitled "Contractor's
Indemnity Provision ". The liability limits for the Comprehensive
Automobile Liability insurance coverage shall not be less than
the following:
Bodily Injury
Property Damage $ 50,000 each accident-
03 -07 Insurance Certificate. In connection with the insurance coverage
set out in sections 03 -03, 03 -04, 03 -05 and 03 -06 above, the
Contractor shall furnish the Owner with a certificate verifying
said insurance. Said certificate shall state that the Owner
shall be given ten (10) days advance written notice before
any provisions of the policies are changed or in the event
said policies shall be canceled. This Certificate of Insurance
shall be provided to the Owner prior to starting any construction
work in connection with this Contract.
SC -6
$100,000 each person
$300,000 each accident
$ 25,000 each accident
$ 50,000 aggregate
$100,000 each person
$300,000 each accident
SECTION 04 CIVIL RIGHTS
The Contractor is required to comply with regulations issued
pursuant to the Civil Rights Act of 1964 with repsect to
nondiscrimination in assisted programs of the Department.
The following provision known as EQUAL OPPORTUNITY CLAUSE are
to be incorporated verbatim in each Contract.
"During the performance of this Contract, the Contractor agrees
as follows:
"(1) The Contractor will not discriminate agianst any employee
or applicant for employment because of race, religion, color,
sec, or national origin. The Contractor will take affirmative
action to insure that applicants are employed, and that employees
are treated during employment, without regard to their race,
creed, color, sex, or national origin. Such action shall
include, but not limited to, the following: employment,
upgrading, demotion or transfer; recruitment or recruitment
advertising; layoff or termination; rates or pay or other forms
of compensation; and selection of training, including
apprenticeship. The Contractor agrees to post in conspicuous
places, available to employees and applicants for employment,
notices to be provided by the contracting officer setting forth
the provisions of the nondiscrimination clause.
"(2) The Contractor will, in all solicitations or advertisements
for employees placed by or on behalf of the Contractor, state
that all qualified applicants will receive consideration for
employment without regard to race, religion, color, sex, or
national origin.
"(3) The Contractor will send to each labor union or
representative of workers with which he has a collective
bargaining agreement or other contract or understanding, a
notice, to be provided by the agency contracting officer,
advising the labor union or workers' representative of the
contractor's commitments under Section 202 of Executive Order
No. 11246, as amended (3CFR 169 (1974)), and shall post copies
of the notice in conspicuous places available to employees
and applicants for employment.
"(4) The Contractor will comply with all provisions of Executive
Order No. 11246, as amended, and of the rules, regulations,
and relevant orders of the Secretary of Labor.
SC -7
"(S) The Contractor will furnish all information and reports
required by Executive Order No. 11246, as amended, and by the
rules, regulations, and orders of the Secretary of Labor, or
pursuant thereto, and will permit access to his books, records,
and accounts by the contracting agency and the Secretary of
Labor for purposes of investigation to ascertain compliance
with such rules, regulations, and orders.
"(6) In the event of the Contractor's noncompliance with the
nondiscrimination clauses of this contract or with any of
such rules, regulations, or orders, this contract may be
canceled, terminated, or suspended in whole or in part and
the Contractor may be declared ineligible for futher Government
contracts in accordance with procedures authorized in Executive
Order No. 11246, as amended, and such other sanctions may be
improved and remedies invoked as provided in Executive Order
No. 11246, as amended, or by rule, regulation, or order of
the Secretary of Labor, or as otherwise provided by law.
SC-8
Section 05 APPLICATION FOR PROGRESS PAYMENT
05 -01 Section 5.04 Partial Payments of the General Conditions is
hereby modified as follows: Contractor shall submit for payment
to the Owner on or before the 25th of each month for quantities
installed prior to and including the 25th of each month.
SC -9