R-89-1323 - 8/24/1989WHEREAS, the City of Round Rock ( "City ") entered into a contract with W. L. Wood Excavation ( "Wood ") for certain improvements to East Main Street and Circle Drive, and WHEREAS, Wood provided performance and payment bonds from National Surety Corporation ( "Surety ") for the project, and WHEREAS, Wood failed to complete the contract and the City directed Surety to complete the contract, and WHEREAS, Surety arranged for J. C. Evans Construction Company to complete the contract work, and upon completion there exists a contract balance of $54,829.67, and WHEREAS, an Agreement has been proposed whereby the City retains $15,000.00 as liquidated damages and the balance of $39,829.67 is paid to Surety, and WHEREAS, the Council wishes to approve said Agreement, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized to execute on behalf of the City an Aareement with National Surety Corporation, a copy of said Agreement being attached hereto and incorporated herein for all purposes. RESOLVED this 24th day of August, 1989. ATTEST: ANNE LAND, City Secretary C- RS08249H RESOLUTION NO. /33 R. MIKE ROBINSON, Mayor City of Round Rock, Texas A G R E E M E N T This agreement has entered into this day of August 1989, between the National Surety Corporation and (Surety) and The City of Round Rock Texas (City). R E C I T A L S 1. Surety executed and delivered to The City its performance and payment bonds no. 524 3502 dated September 2, 1987 in the penal amount sum of $391,975.25, covering certain agreements between W.L. Wood Excavation (Wood) and The City, dated September 10, 1987, identified as project 103 - 1517 -38, Main Street - Circle Drive. 2. W.L. Wood Excavation failed to complete the contract and The City terminated its right to proceed under the contract effective June 5, 1988. At that time The City directed the Surety to complete the work of the contract. 3. In fulfillment of his obligations under said bond, Surety arranged for a completion proposal by J.C. Evans (Evans) Construction Company to complete the contract work of Wood. A contract to complete the work was entered into on June 13, 1988, between The City and Evans for an amount of $112,445.10, and included the obligations of the Surety under a maintenance bond dated September 2, 1987. At that time sufficient funds remained in the contract balance to complete the work under the Evans contract. 4. Evans satisfactorily completed the contract work and there remained upon completion a contract balance of $54,829.67. A dispute arose between The City and the Surety over the question of liquidated damages. The Surety questioned the right of The City to impose liquidated damages, and The City feels it has the right to impose such damages. Now therefore, the parties wish and intend to resolve all outstanding claims, obligations, and liabilities and agree as follows: 1. The City acknowledges the completion and acceptance of contract no. 103 - 1517 -38 and that there remains in contract balance, the sum of $54,829.67. 2. Each party retains its position on the disputed question of liquidated damages, but to resolve its differences, each agrees to compromise on its original demands. 3. The Surety will pay and The City will accept in satisfaction of its claim for liquidated damages, the sum of $15,000.00 and further agrees to pay, within 15 days of execution of this agreement, to the Surety, the remaining contract balance of $39,829.67. 4. This agreement resolves between parties, all causes of action, damages, claims and demands whatsoever, in law and in equity, which each party ever had, now has, or which it may aquire against the other, and that all rights and obligations of either party arising out of, through, or under the bonds or contract are herein extinguished. 5. The City herein assigns and sets over to the Surety, its successors and assigns, for its and their own use and benefit forever, all claims, demands and causes of actions whatsoever, at law or in equity, which The City now has against Wood. Dated in Round Rock, Texas this a 4 day of August 1989 City of Roun�ck� By: Title R.ownd. lei:)/Ck) i-t4aOJ City Counsel Resolution Attached Dated in Rolling Meadows, Illinois this j.- day of August 1989, National Surety Corporation by WJS /45- 48 /scl Title DATE: August 21, 1989 SUBJECT: Council Agenda, August 24, 1989 ITEM: 12H. Consider a resolution authorizing the Mayor to enter into an agreement with Fireman's Fund Insurance regarding final disbursement on the East Main Street Project. STAFF RESOURCE PERSON: Jim Nuse STAFF RECOMMENDATION: This Agreement will finalize the East Main Street Project. There is $54,829.67 left in the project account. The Agreement provides that the City will retain $15,000.00 as liquidated damages. The balance of $39,829.67 will be released to the bond company. Staff recommends approval. ECONOMIC IMPACT: City retains $15,000.00 as liquidated damages. DATE: August 21, 1989 SUBJECT: Council Agenda, August 24, 1989 ITEM: 12H. Consider a resolution authorizing the Mayor to enter into an agreement with Fireman's Fund Insurance regarding final disbursement on the East Main Street Project. STAFF RESOURCE PERSON: Jim Nuse STAFF RECOMMENDATION: This Agreement will finalize the East Main Street Project. There is $54,829.67 left in the project account. The Agreement provides that the City will retain $15,000.00 as liquidated damages. The balance of $39,829.67 will be released to the bond company. Staff recommends approval. ECONOMIC IMPACT: City retains $15,000.00 as liquidated damages. (J 0 J need, e dJ e 46,0 /76etyi /(229-n 2 . 45)9P WHEREAS, the City of Round Rock ( "City ") entered into a contract with W. L. Wood Excavation ( "Wood ") for certain improvements to East Main Street and Circle Drive, and WHEREAS, Wood provided performance and payment bonds from National Surety Corporation ( "Surety ") for the project, and WHEREAS, Wood failed to complete the contract and the City directed Surety to complete the contract, and WHEREAS, Surety arranged for J. C. Evans Construction Company to complete the contract work, and upon completion there exists a contract balance of $54,829.67, and WHEREAS, an Agreement has been proposed whereby the City retains $15,000.00 as liquidated damages and the balance of $39,829.67 is paid to Surety, and WHEREAS, the Council wishes to approve said Agreement, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized to execute on behalf of the City an Agreement with National Surety Corporation, a copy of said Agreement being attached hereto and incorporated herein for all purposes. RESOLVED this 24th day of August, 1989. ATTEST: JOANNE LAND, City Secretary C- RS08249H RESOLUTION NO. MIKE ROBINSON, Mayor City of Round Rock, Texas AGREEMENT This agreement has entered into this day of August 1989, between the National Surety Corporation and (Surety) and The City of Round Rock Texas (City). RECITALS 1. Surety executed and delivered to The City its performance and payment bonds no. 524 3502 dated September 2, 1987 in the penal amount sum of $391,975.25, covering certain agreements between W.L. Wood Excavation (Wood) and The City, dated September 10, 1987, identified as project 103 - 1517 -38, Main Street - Circle Drive. 2. W.L. Wood Excavation failed to complete the contract and The City terminated its right to proceed under the contract effective June 5, 1988. At that time The City directed the Surety to complete the work of the contract. 3. In fulfillment of his obligations under said bond, Surety arranged for a completion proposal by J.C. Evans (Evans) Construction Company to complete the contract work of Wood. A contract to complete the work was entered into on June 13, 1988, between The City and Evans for an amount of $112,445.10, and included the obligations of the Surety under a maintenance bond dated September 2, 1987. At that time sufficient funds remained in the contract balance to complete the work under the Evans contract. 4. Evans satisfactorily completed the contract work and there remained upon completion a contract balance of $54,829.67. A dispute arose between The City and the Surety over the question of liquidated damages. The Surety questioned the right of The City to impose liquidated damages, and The City feels it has the right to impose such damages. Now therefore, the parties wish and intend to resolve all outstanding claims, obligations, and liabilities and agree as follows: 1. The City acknowledges the completion and acceptance of contract no. 103- 1517 -38 and that there remains in contract balance, the sum of $54,829.67. 2. Each party retains its position on the disputed question of liquidated damages, but to resolve its differences, each agrees to compromise on its original demands. 3. The Surety will pay and The City will accept in satisfaction of its claim for liquidated damages, the sum of $15,000.00 and further agrees to pay, within 15 days of execution of this agreement, to the Surety, the remaining contract balance of $39,829.67. 4. This agreement resolves between parties, all causes of action, damages, claims and demands whatsoever, in law and in equity, which each party ever had, now has, or which it may aquire against the other, and that all rights and obligations of either party arising out of, through, or under the bonds or contract are herein extinguished. 5. The City herein assigns and sets over to the Surety, its successors and assigns, for its and their own use and benefit forever, all claims, demands and causes of actions whatsoever, at law or in equity, which The City now has against Wood. Dated in Round Rock, Texas this day of August 1989 City of Round Rock, Texas By: Title City Counsel Resolution Attached Dated in Rolling Meadows, Illinois this pe■ day of August 1989, National Surety Corporation by WJS /45- 48 /scl