R-93-01-28-13A - 1/28/1993'HOT INSPECTION SERVICES, INC.
Welding Consultants & Inspection Specialists
p I Welding & Fabrication
Inspection & Testing
January 20, 1993
Steven D. Miller, P.E.
Dept. Of Public Works
City Of Round Rock
2008 Enterprise
Round Rock, Texas 78664
RE: McNeil Road Water Tank Inspection
Dear Steve:
Please find attached the proposal for the referenced inspection project. As you
requested the changes have been made to clarify the proposal and identify the hourly
rates which will be charged during the project.
As a local tank inspection firm our goal is to furnish the City Of Round Rock with the
most accurate inspection available. We feel that our 8 years of existence here in
Round Rock has proven to be a successful one and are committed to offering many
more years of professional services at the most reasonable cost available.
ate
your
ve any questions or need to discuss the contents of the proposal, please feel
free to contact me anytime.
Respectfully Submitt ,
n H. K en
President
JHK/pr
Attachment
MAILING: P.O. Box 1208
Round Rock, TX 78680
SHIPPING: 1411 Sam Bass Rd.
Round Rock, TX 78681
(512) 244.2523
FAX: 244.0607
HOT INSPECTION SERVICES, INC.
Welding Consultants & Inspection Specialists
Welding & Fabrication
Inspection & Testing
SCOPE:
MAILING: P.O. Box 1208
Round Rock, TX 78680
SHIPPING: 1411 Sam Bass Rd.
Round Rock, TX 78681
(512) 244-2523 FAX: 244 -0607
MCNEIL ROAD WATER TANK INSPECTION PROPOSAL
HOT Inspection Services, Inc. (HOT) hereby offers to perform the following work on the
McNeil Road Water Tank project at the price, terms and conditions listed:
HOT proposes to provide tank inspection and integrity assessment services to the City
Of Round Rock, Texas on the McNeil Road storage tank. The objective of this project
is to provide an accurate condition survey of the tank and document in a technical
report in order to assist the Public Works Department in the rehabilitation process. The
services to be rendered will include the following:
- Conduct a visual inspection of the shell, roof, floor, accesses, appurtenances and
weldments in accordance with the AWWA D100 visual criteria. All areas of the tank
will be accessed as required for visually evaluating the status of welds, coating, and
base material.
- Perform ultrasonic thickness measurements of the tarn shell, roof and floor for base
material evaluation and thickness verification. Reading to be taken at random select-
ed areas and where worse cases of corrosion are visually detected.
- Magnetic Particle examine any areas of the tank showing signs of stress for the
detection of cracks per the City's approval.
- Perform a leak test of the complete tank bottom and shell to bottom weldments using
vacuum box leak detection device.
-Take still photographs of the exterior and interior areas of the tank and any exces-
sively damaged portion of tank for documentation in report.
- Produce a detailed as built drawing or sketch with dimensions of any areas of the tarn
requiring repairs or containing questionable defects; provided, the still photographs
are not sufficient for showing in detail the existing condition of the tank.
HOT INSPECTION SERVICES, INC.
Welding Consultants & Inspection Specialists
Welding & Fabrication
Inspection & Testing
- Compile the inspection and testing results, tabulated data, drawings and pictures in
sufficient detail to report the condition and provide information for bidding the rehabili-
tation work of the tank. Recommendations for repairs will be provided in the report. A
total of seven (7) inspection reports will be supplied to the City Of Round Rock.
WORK EXCLUDED;
The water and sediment after tank draw down shall be removed by the City Of Round
Rock unless the request is made otherwise. Any evaluations or recommendations
pertaining to the lead or chromium contained in the coating will not be provided in this
report. Inspection visits during the reconstruction work of the tank is not included in
this proposal.
PRICE:
An estimated budget cost for the above mentioned services is $5,800.00
`All work will be conducted and billed at an hourly rate as shown below. The budget
cost for conducting the tank inspection and report will not exceed the cost above
without the written approval of the City. Once the cost approaches the budget cost, the
City will be notified and informed of the remaining work required to complete the
project.
ADDITIONAL SERVICES:
MAILING: P.C. Box 1208
Round Rock, TX 78680
SHIPPING: 1411 Sam sass Rd.
Round Rock, TX 78681
(512) 244-2523 FAX: 244 -0607
Any work not specifically listed herin or by reference will be negotiated prior to
performance at the appropriate hourly rate as stated below.
1. Tank integrity Inspection Team (2 men)
2. Additional Inspector/Technician
3. Standby Safety Support
4. Ultrasonic Testing
5. Magnetic Particle Testing
6. Radiographic Testing
7. Welding & Cutting
8. Technical Report Preparation
9. See price schedule for additional services
TERMS:
$100.00/hr
$ 40.00/hr
$ 35.00/hr
$ 50.00 /hr
$ 45.00 /hr
$ Cost + 20%
$ 40.00 /hr
$ 50.00 /hr
This proposal is offered subject to acceptance within 30 days. Payments to be made
within 30 days of invoice date.
' HOT INSPECTION SERVICES, INC.
Welding Consultants & Inspection Specialists
Welding & Fabrication
Inspection & Testing
CONDITIONS:
This proposal assumes that the tank will be accessible for inspection and that any
restrictions requiring special work will affect the cost of this proposal.
INSURANCE:
HOT to provide insurance certificate verifying liability and statutory coverage limits.
TIME OF PERFORMANCE:
Work to begin upon notification that tank is ready for the appropriate inspection. Five
working days notice is requested for scheduling. The inspection will be completed
within 3 working days after initial tank entry. The condition survey report will be
completed within 5 working days of completed inspection.
ACCEPTANCE:
Should you find this proposal acceptable at the prices, terms and conditions offered ,
please indicate your acceptance by signing in the space provided.
Executed at Round Rock, Texas on this the o D day of
Attest:
Attest:
MAILING: P.O. Box 1208
Round Rock, TX 78680
SHIPPING: 1411 Sam Bass Rd.
Round Rock, TX 78681
(512) 244-2523 FAX: 244-0607
City Of Round Rock
1993.
Mice Robinson, Mayor
HOT Inspection Services
WHEREAS, the City of Round Rock desires to have inspection
services for the McNeil Road Tank, and
WHEREAS, Heart of Texas, Inc. has submitted an agreement to
provide said inspection services, and
WHEREAS, the City Council desires to enter into said agreement
with Heart of Texas, Inc., Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,
TEXAS,
RESOLUTION NO. R-93-01-.28 /3f1
That the Mayor is hereby authorized and directed to execute on
behalf of the City an agreement with Heart of Texas, Inc. for
inspection services for the McNeil Road Tank, a copy of said agreement
being attached hereto and incorporated herein for all purposes.
RESOLVED this 28th day of January, 1993.
ATTEST:
JOi E LAND, City Secretary
RS01283A
MIKE ROBINSON, Mayor
City of Round Rock, Texas
01/26/93 16:57 ROUND ROCK PUBLIC WORKS -. 512 255 6676
HOT INSPECTION SERVICES, INC.
Welding Consultants & Inspection Specialists
Welding & Fabrication
Inspection & Testing
SCOPE:
MAILING: P.O. Box 1208
Round Rock, TX 78880
SHIPPING: 1411 Sam Bass Rd,
Round Rock, TX 78681
(512) 244.2523 FAX: 244-0607
MCNEIL ROAD WATER TANK INSPECTION PROPOSAL
HOT Inspection Services, Inc. (HOT) hereby offers to perform the following work on the
McNeil Road Water Tank project at the price, terms and conditions listed:
HOT proposes to provide tank Inspection and integrity assessment services to the City
Of Round Rook, Texas on the McNeil Road storage tank. The objective of this project
is to provide an accurate condition survey of the tank and document in a technical
report in order to assist the Public Works Department in the rehabilitation process. The
services to be rendered will include the following:
- Conduct a visual Inspection of the shell, roof, floor, accesses, appurtenances and
weldments in accordance with the AWWA D100 visual criteria. All areas of the tank
will be aooessed as required for visually evaluating the status of welds, coating, and
base material.
- Perform ultrasonic thickness measurements of the tank shell, roof and floor for base
material evaluation and thickness verification. Reading to be taken at random select-
ed areas and where worse cases of corrosion are visually detected.
- Magnetic Partlole examine any areas of the tank showing signs of stress for the
detection of cracks per the City's approval.
- Perform a leak test of the complete tank bottom and shell to bottom weldments using
vacuum box leak detection device.
- Take still photographs of the exterior and interior areas of the tank and any exoes-
sively damaged portion of tarn for documentation in report.
- Produce a detailed as built drawing or sketch with dimensions of any areas of the tank
requiring repairs or containing questionable defects; provided, the still photographs
are not sufficient for showing in detail the existing condition of the tank.
NO. 052 P27
01/26/93 16:58 ROUND ROCK PUELIC WORKS -+ 512 255 6676
HOT INSPECTION SERVICES, INC.
Welding Consultants 8 Inspection Specialists
Welding & Fabrication
Inspection & Testing
MAILING: P O Box 1208
Round Rock. TX 78680
SHIPPING: 1411 Sem Bass Rd.
Round Rock, TX 78681
(512) 244 -2523 FAX: 244.0607
-Compile the inspection and testing results, tabulated data, drawings and pictures in
sufficient detail to report the condition and provide information for bidding the rehabili-
tation work of the tank. Recommendations for repairs will be provided in the report. A
total of seven (7) inspection reports will be supplied to the City Of Round Rock.
WORK EXCLUDED:
The water and sediment after tank draw down shall be removed by the City Of Round
Rook unless the request is made otherwise. Any evaluations or recommendations
pertaining to the lead or ohromium contained in the coating will not be provided in this
report. Inspection visite during the reconstruction work of the tank is not included in
this proposal,
PRICE;
An estimated budget cost for the above mentioned services is $5,800.00
'All work will be conducted and billed at an hourly rate as shown below. The budget
cost for conducting the tank inspection and report will not exceed the cost above
without the written approval of the City. Once the cost approaches the budget cost, the
City will be notified and informed of the remaining work required to complete the
project.
ADDITIONAL SERVICES:
Any work not specifically listed herin or by reference will be negotiated prior to
performance at the appropriate hourly rate as stated below.
1. Tank integrity Inspection Team (2 men)
2. Additional InspeotorlTeohnloian
3. Standby Safety Support
4. Ultrasonic Testing
5. Magnetic Particle Testing
6. Radlographlo Testing
7. Welding & Cutting
8. Technical Report Preparation
9. See price schedule for additional services
Si 00.00 /hr
$ 40.00 /hr
$ 35.00 /hr
$ 50.00/hr
$ 45.00/hr
$ Cost + 20%
$ 40.00 /hr
$ 50.00/hr
TERMS:
This proposal is offered subject to acceptance within 30 days. Payments to be made
within 30 days of invoice date.
N0. 052 P28
01/26/93 16:50 ROUND ROCK PUELIC WORKS - 512 255 6676 ND.052 P29
HOT INSPECTION SERVICES, INC.
Welding Consultants & Inspection Specie■sts
Welding & Fabrication
Inspection & Testing
CONDITIONS:
Executed at Round Rook, Texas on this the oi6 — day of
Attest:
Attest:
a
1
n
Corporate Secretary
MAILING: P.O. Box 1208
Round Rock, TX 78680
SHIPPING: 1411 Sam Bass Rd,
Round Rock, TX 78681
(512) 244.2523 FAX 244-0607
This proposal assumes that the tank will be accessible for inspection and that any
restrictions requiring special work will affect the cost of this proposal.
INSURANCE:
HOT to provide insurance certificate verifying liability and statutory coverage limits.
TIME OF PERFORMAN E:
Work to begin upon notification that tank is ready for the appropriate inspection. Five
working days notice is requested for scheduling. The inspection will be completed
within 3 working days after initial tank entry. The condition survey report will be
completed within 5 working days of completed inspection.
ACCEPTANCE:
Should you find this proposal acceptable at the prices, terms and conditions offered ,
please indioate your aooeptanoe by signing in the space provided.
City Of Round Rook
Mike Robinson, Mayor
1993.
HOT Inspection Services
01/26/93 16:59 ROUND ROCK PUBLIC WORKS -. 512 255 6676 NO.052 P30
HOT INSPECTION SERVICES, INC.
Welding Consultants 8 Inspection Spactahsts
P I Welding & Fabrication
Inspection & Testing
January 20, 1993
Steven D. Miller, P.E.
Dept. Of Public Works
City Of Round Rock
2008 Enterprise
Round Rook, Texas 78664
RE: McNeil Road Water Tank Inspection
Dear Steve:
MAILING: P.O, Sox 1208
Round Rock, TX 78880
SHIPPING: 1411 Sam Bass Rd.
Round Rock. TX 78681
(512) 244 -2523 FAX: 244 -0807
Please find attached the proposal for the referenced Inspection project. As you
requested the changes have been made to clarify the proposal and Identify the hourly
rates which will be charged during the project.
As a local tank inspection firm our goal is to furnish the City Of Round Rook with the
most accurate inspection available. We feel that our 8 years of existence here in
Round Rock has proven to be a successful one and are committed to offering many
more years of professional services at the most reasonable cost available.
your sve any questions or need to discuss the contents of the proposal, please feel
free to contact me anytime.
Respectfully Submltt-
n H. K! en
President
JHK/pr
Attachment
01/26/93 16 :57 ROUND ROCK PUBLIC WORKS -∎ 512 255 6676 NO.052 D26
DATE: January 26, 1993
SUBJECT: City Council Meeting, January 28, 1993
ITEM: 13A. Consider a resolution authorizing the Mayor to enter into
an agreement for the Heart of Texas, Inc. for inspection
services on the McNeil Road Tank.
STAFF RESOURCE PERSON: Steve Miller
STAFF RECOMMENDATION: In order to paint the McNeil Tank, an inspection
for structural integrity is required. HOT inspection Service is recommended to
perform this service. Staff recommends award of this project to Hot Services for
$5,800.
Mayor
Mike Robinson
Mayor Pro-tern
Charles Culpepper
Council Member.
Robert Stluka
Rod Morgan
Rick Stewart
Earl Palmer
JimmyJoseph
City Manager
Robert L. Bennett, Jr.
City Attorney
Stephan L. Sheets
February 3, 1993
Mr. John Konzen
HOT Inspection Services, Inc.
P.O. Box 1208
Round Rock, Texas 78680
Dear Mr. Konzen:
Resolution No. R- 93- 01- 28 -13A was approved by the Round
Rock City Council on January 28, 1993.
Enclosed is a copy of the resolution and the agreement
for your files. If you have any questions, please do not
hesitate to call.
Sincerely,
I
THE CITY OF ROUND ROCK
221 East Main Street
Round Rock, Texas 78664
512- 255 -3612
Joanne Land,
Assistant City Manager/
City Secretary
JL:km
Enclosures