R-93-09-23-10H - 9/23/1993RESOLUTION NO. R Q3- 0943-1,01-1
WHEREAS, the City of Round Rock desires the construction of lighting,
sidewalks, landscaping pavers, and curb and gutter improvements for the Round
Rock Avenue /Mays Street Project, and
WHEREAS, the State of Texas, by and through its Department of
Transportation will provide such construction in exchange for a contribution from
the City of $268,366.86, and
WHEREAS, the City has made a deposit to the Department �of Transportation
in the amount of $193,218.14 in accordance with Resolution R93- 0-08 -9E,
WHEREAS, additional escrow funds are needed as a result of higher bids
being received at contract letting, Now Therefore
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ROUND ROCK,
TEXAS,
That the Mayor is hereby authorized and directed to deposit additional escrow
funds in the amount of $75,148.72 with the Texas Department of Transportation for
the construction of lighting, sidewalk, landscaping pavers, and curb and gutter
improvements as described above, said invoice being attached hereto and
incorporated herein as Exhibit "A ".
RESOLVED this 023- day of
1993.
L/
CHARLES CULP • � P FT Mayor
City of Round Rock, Texas
EXHIBIT "�A" � RECEIVED AUG 1 71333
A ir Texas Department of Transportation
Williamson County
Control 0683 -01 -041
Project: CD 683 -1-41
RM 620: From Hi 35 to Loop 384
Hon. Charles Culpepper
Mayor, City of Round Rock
221 East Main Street
Round Rock, Texas 78664
Dear Sir:
P.O. DRAWER 15426 • AUSTIN, TEXAS 78761 -5426 • (512) 832 -7000
August 11, 1993
Returned herewith for your permanent files is one fully executed counterpart to
one of two separate escrow agreements on the above referenced project. This
agreement covers sidewalks, curb and gutter, illumination, and landscape pavers,
whereas the other covers water and wastewater adjustments and is being
transmitted under separate cover to avoid confusion.
In a related matter, as a result of higher bids being received at contract letting
some additional escrow funds are needed. Using the same cost components as in
our preliminary estimate calculations, the amount due is as follows:
Total bid items $233,696.55
7% Construction Engineering
and Contingencies 16,358.76
Sub -Total $250,055.31
7.323% Indirect Cost 18,311.55
Sub -Total $268,366.86
Less Previous Deposit (193,218.14)
Balance Due $75,148.72
While these funds are due on receipt of this letter, TxDOT agrees in this one
instance to allow deferment on this deposit until after October 1, 1993. Please
forward a check or warrant as soon as possible after that date.
An Equal Opportunity Employer
if you have any questions in this matter, please let us know.
Sincerely,
TEW:GLL:ljb
Attachment
cc Danny Stabeno w/o attach
Bill Glenn, P.E., w/o attach
Thomas E. Word, Jr., P.E.
Director of Transportation
Planning and Development
��JIL T E.
STATE OF TEXAS
COUNTY OF TRAVIS
THIS AGREEMENT is made thisc/l day of
City of Round Rock, Texas, hereinafter called the "City ", Party of the First Part, acting
by and through its City Council and the State of Texas, hereinafter called the "State ",
Party of the Second Part, acting by and through its Texas Department of
Transportation Commission.
WHEREAS, the City desires participation in illumination, curb and gutter, sidewalks
and landscape pavers and incidental items within the limits from Interstate Highway
No. 35 to Loop 384 on Ranch to Market Road No. 620, which is solely the City's
responsibility and the City has requested the State to construct or have constructed
this work. The State will construct or have constructed this work for and on behalf of
the City and at the City's sole expense, excluding preliminary engineering. The
estimated construction cost of this work is One Hundred Ninety Three Thousand Two
Hundred Eighteen and 14/100 Dollars ($193,218.141, including contingencies and
construction engineering, and including indirect costs at the rates in effect for the
fiscal years during which the work is accomplished. The indirect cost rate will be
based on the Texas Department of Transportation's Indirect Cost Plan.
NOW THEREFORE, it is understood that this proposed work will constructed by
the State and the City will transmit to the State with the return of this agreement,
executed by the City, a warrant or check made payable to the Texas Department of
CD 683 -1 -41
0683 -01 -041
Williamson County
, 1993, by and between the
-2-
CD 683 -1 -41
0683 -01 -041
Williamson County
Transportation in the amount of One Hundred Ninety Three Thousand Two Hundred
Eighteen and 14/100 Dollars ($193,218.14), to be used in paying for the proposed
work required by the City in the City of Round Rock. It is further understood that the
State will construct only those items for the City as requested and required by the City
and the entire cost of such items, excluding preliminary engineering, will be borne by
the City. If the State elects to receive bids and if upon receipt of bids by the State
and /or the actual construction and /or approved changes in the contemplated
improvements it is found that this amount is insufficient to pay the City's portion, then
the City upon request of the State will forthwith supplement this amount by an
amount equal to the City's full estimated or actual share of the cost of this work less
the amount previously paid to the Texas Department of Transportation. In the event
the amount as paid is more than the actual cost, then the excess amount will be
returned to the City. It is further understood that the work to be done on behalf of the
City, as herein provided, will include the cost of contingencies and construction
engineering and indirect cost.
IN TESTIMONY WHEREOF, the parties hereto have caused these presents to be
executed in dup!icate on the day above stated.
By:
By:
By:
CITY OF ROUND ROCK
Party of the First Part
By:
City Manager/
Y
Member of City Council
By:
Member of City Council
Member of City Council
Member of City Council
ATTEST:
/1,
y Clerk/City Secretary
APPROVED AS TO FORM:
Certified as being executed for the
purpose and effect of activating and /or
carrying out the orders, established
policies, or work programs heretofore
approved and authorized by the Texas
Department of Transportation
Commission under the authority of
Minute Order 100002.
By:
-3-
CD 683 -1 -41
0683 -01 -041
Williamson County
TEXAS DEPARTMENT OF
TRANSPORTATION
Party of the Second Part
i ir _+.sact • : ministration
DATE: September 21, 1993
SUBJECT: City Council Meeting, September 23,1993
ITEM: 10.H Consider a resolution authorizing additional funds to be paid to
the Texas Department of Transportation for lighting, sidewalk,
and curb and gutter improvements for the Round Rock
Avenue /Mays Street project.
STAFF RESOURCE
PERSON: Joe Vining
STAFF
RECOMMENDATION: Approval
As a result of higher bids being received at contract letting, additional escrow funds
are needed. Using the same cost components as in the preliminary estimate
calculations, the amount due is as follows:
Total bid items $233,696.55
7% Construction Engineering
and Contingencies 16,358.76
Sub -Total $250,055.31
7.323% Indirect Cost 18,311.55
Sub -Total $268,366.86
Less Previous Deposit (193,218.14)
Balance Due $75,148.72
Economic Impact: $75,148.72 being paid from interest income from street bond
projects.