Loading...
R-93-11-23-9G - 11/23/1993•. C �2.'3Bi94 DATE: SUBJECT: ITEM: 11:55 ROUND ROCK PUELIC WORKS 4 512 255 6676 February 8, 1994 STAFF RESOURCE PERSON: STAFF RECOMMENDATION: City Council Meeting, February 10, 1994 12A. Consider Change Order No. 1 to Haegelin Construction Company, Inc. for the Southeast Round Rock Water /Wastewater Improvements. Jim Nuse NO.433 DR5 931143 -9G In order to complete some of the required improvements for the Dell project, a change order is required to complete a tie -in. 1) - n r 11 11 r .l 11 n r r 02/20/94 15:13 ROUND ROCK PUBLIC WOR� KS -4 512 255 6676 FEB- 8 -94 TUE 14:50 HAEGELIN CONST. CO. INC. FAX NO 5123889911 FE8 -1994 14 FROM BURY P. PITTMAN. INC. TO debruary 4, 1994 Haegelin Construction Co., Inc. City of Round Rock . c/o bury 6 pittman, InC. 3345 Bee Cave Road Austin, Texas 78746 Put OIDoe Lot ooae • Auaan. TeRas 7789 • (61'i) 388.8900 NO.435 P05 P. 07 3889911 P.86 attn: Mr. Greg strmieka ROI Water and Wastewater Improvements for Doll Center Blvd. Dear sir, We are pleased to offer the following proposal for addition of 16" water line improvements associated with the above project more specifically enumerated on.the attached scope of work. We propose to perform the above work in a substantial workmanlike manner for tha sum Thirty Thousand Wight Hundred Ten end 00/100 Dollars, ($80,810.00). We appreciate the opportunity to quota this project. Please contact our offi0a if We can he of further service. sincerely, - In, 141 i • Michael W. Carson Baegelin Conetruction Co., Inc. 021W/94 15:13 ROUND ROCK PUELIC WORKS -. 512 255 6676 NO.435 DO6 FEB- 8 -94 TUE 14;50 HAEGEL1N CONST, CO. 1NC. FAX NO. 5123889911 P.08 FEB-OS-1994 14.30 FROM BURY 8 PITTt . IMO. TO 388991! P.87 rn / ri r 'TI '1 11 r DELL CENTER 16" WL 8C0PE Of WORK DESCRIPTION 16` DI CL 52 SORE W/24" CASING L2X12 WET CONNECTION 12° GATE VALVE 6" GATE VALVE HYDRANT RESPECTFULL SUBMITTED, 7'. w. CARSON HAEGELIN CONST. CO., INC. FEB 4, 1994 DELLISBI UNITS AMOUNT EXTENSION 304.0 *40.00 *12,160.00 76.0 *170,00 *12,780.00 1.0 $2,600.00 *2,600.00 2.0 *1,000.00 *2,000.00 1.0 *400.00 *400.00 1.0 $1,000.00 *1,000.00 TOTAL WATER *30,810.00 TOTAL P.0? PROJECT: Water and Wastewater Improvements for Dell Center Boulevard PROJECT NO: 525-03.61 OWNER: City of Round Rock, Texas CONTRACT DATE: 12 /6/93 sunIECr OF CHANGE ORDER: As described below. I DESCRIPTION (list Attachments, If Any) Change No. Description Change in Contract Price 1 See Attachment "A" $30,810 REASON FOR CHANGE: See Attachment "A" ORIGINAL CONTRACT: $123.591.50 ADDITIONS TO DATE: $ 0 THIS ADD: DEDUCTIONS TO DATE: $Q THIS DEDUCT: • CONTRACT TO DATE: $ 123,591.50 $ 30.810 TOTAL ADD: $ 30 810 $Q TOTAL DEDUCT:$Q NEW CONTRACT AMOUNT:$ 154.401.50 ORIGINAL CASH ALLOWANCE: $ -- EXPENDITURES TO DATE: $ -- THIS EXPENDITURE: $ -- REMAINING CASH ALLOWANCE: $ -- NEW CASH ALLOWANCE BALANCE: $ -- CHANGE ORDER NO. 1 • 1 of 2 DATE: 2/7/94 ORIGINAL CONTRACT PERIOD: 60 THIS EXTENSION: CALENDAR DAYS CALENDAR DAYS EXTENSIONS TO DATE: 0 NEW CONTRACT PERIOD: CALENDAR DAYS CALENDAR DAYS CONTRACT PERIOD TO DATE: 60 AMENDED COMPLETION DATE: CALENDAR DAYS RECOMMENDED BY: ACCEPTED BY: APPROVED BY: Bury & Pittman, Inc. IN q REPRESENT Ha e 0 . - _ - Con _ c ' 5 n • m . an Inc. DATE REPRESENT A 51 r {, n 5L /as DATE a lc- 9' OWNER ��,.� `% REPRESENTATIVE DATE : 11U11ULJ-US. 2 of 2 CHANGE #1 Description of Change: ATTACHMENT "A" CHANGE ORDER #1 Water and Wastewater Improvements for Dell Center Boulevard Construct waterline Improvements per approved plans from Sta. 17 + 15.32 to Sta. 20 + 23.84. Delete one section of 20' pipe and one 16" butterfly valve. (Construct per attached scope of work from Haeglin Construction) WHEREAS, the City of Round Rock'has duly advertised for bids for the Water and Wastewater System Improvements for Dell Center Blvd., and WHEREAS, Haegelin Construction Company, Inc., has submitted the lowest and best bid, and WHEREAS, the City Council wishes to accept the bid of Haegelin Construction Company, Inc., Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized and directed to execute on behalf of the City an agreement with Haegelin Construction Company, Inc., for Dell Center Blvd., a copy of said agreement being attached hereto and incorporated herein for all purposes. RESOLVED this 23rd day of November, 1993. ATTEST: E LAND, City Secretary RS /RESOLUTION RS11233H RESOLUTION NO. gi 2 ) - J -o)S-9G- CHARLES CULP P , Mayor City of Round Rock, Texas 11/19/93 16:34 ROUND ROCK PUELIC WORKS -. 512 255 6676 Bury 1 Pittma ri November 19, 1993 Mr. Jim Nuse, Director Public Works Department City of Round Rock 221 East Main Street Round Rock, Texas 78664 Re: Award of Contract Water and Wastewater System Improvements For Dell Center Boulevard Dear Mr Nuse: By Tuesday, November 16, 1993 eight (8) bids were received from contractors to perform the work required to complete the water and wastewater system improvements for Dell Center Boulevard as designated in the construction bid set. Attached please find a bid tabulation showing the eight bids ranging from a low bid of $123,591.50 to a high bid of $185,661.79. The low bid of $123,591.50 for the improvements required was submitted by Haegelin Construction Company. Bury & Pittman, Inc. is recommending that the City Council of Round Rock award the contract for the water and wastewater system improvements for Dell Center Boulevard to Haegelin Construction Company. Should you have any questions or require additional information, please call. 1 y, T.... k 1 V �--� S •• . /% Paul J 1�c�'orin, P.E. $ PAUL J. VIKTORIN .i W. . 66879 65, 5 cc: Bay Maintenance Co., Co., ncn f l e , s o ..... Borah, Inc.J.C. Evans Construction Co., Inc. )I- j9- 53 Haegelin Construction Co., Inc. Keystone Construction, Inc. M & R Plumbing, Inc. Trident Underground Utilities Corp. Attachments f: \jnuse.ltr \pv \ltr \bh\525 -03.61 Rum a Pinioao. al .I,1nug . Ib, .. 11„ „�1 /,111. 201, h1 iI .1. 5i. 4,.111 112 yt1.,1t NO.166 P03 i � um.1> f % .I.7..o.w.luk r.OILG72k00smtve..lw e....w ,M arexwo , DAM ..A..�r e-r v. ... _ ... _.... rw,.crll.x. 02.1.1.�..r. YE ur.r c� Ail!. J. VIM - ORIN 'f 1 66R71 9 e � ....w.�..�a.mmr-..®es a. C.......w.1 '�r]1 \, Da re 1'^'� OF �C � Ma., A 1°1- i40;907vpT; EN .9r6Wrar6r a -m.l N.. x..w 6K ���.w.r 6.710 Ce- uv1rcR7 - W 9 m / VIM Mr. .00,1.1 war 7 1 1.re ..100711 nxe .10..0.7 i97 .169 171 ra re .6 00 rwee .1.100 Rae .000.0 1 c 9alawssc.9n96 RON ern 1310 LP 3110 052030 2000 20 90 5020 020 wm 500 2 4.11401C1•062 DOGMA otoh 213 LF 33.21 340870 093 2000 mm 500 9]20 5000 3 6-0500067eV..LE 4 EA 313330 36,22311 3920 2000 0(01 5+]20 9120 00 0 S 9.- 0020/00900 2 EA 371179 313031 9300 S10 2020 0A3 fOm ]900 1 14- ne3lrleex 6 EA 31.0361 91121.6 5900 3000 50.93 501.0 IOW mm 6 .- n.Q1001.,W1.5 1 en 1.517 71 32_680'.9 Sim 3320 9120 0 W - 50AJ 200 7 6- 00110umx POx 496 110 LP 1260 32,99910 3400 9365 3020 0020 mm mm 0 0.1VATER 2944.10 1 FA 0031 037.81 3200 SOW 50.00 020 360 020 9 49 19,10.10111.00 RIM 1 FA 3400 39030 9200 9100 Me W m 200 010 10 a• CAM SOW PVC YAM - WAWA me 017 LP 921.0 90200 9200 SSW 020 000 020 5020 11 4 00;rE1HtvI31 2 FA 20013 0900 5020 5000 500 500 9200 0030 1: 6 - F09070600/ tATPwATe■ R.01.T 1 EA 31121.13 3723432 SAW 50 W 0 20 2020 SOm 0 W 13 . 1907 P 1.0,0311632£7!.11x/1 DRpfO04019 1 FA 01710 3E47)67 3000 0000 OW 9100 0320 000 0 w072796102 use rum 1 EA 51133 001 AR 5010 10 00 0000 206. mm mm IS 6- 09f511.319r709A N 1 EA 117917 109.0 1000 000 500 5000 5003 9100 114 305249 353 LP 3318 5000 00.03 200 500 5000 5030 300 17 099000/0 00 LP 51233 30.0310 3093 200 0020 90.00 l= 5060 14 06070100e0091 2 EA 11170 303.06 1010 0000 000 00107 0040 0OW 19 Wen. SAFER.1.1chr3 32 LP 911 3332106 5020 500 2900 5050 0010 5010 20 9r2693a900911900000 exr0309 1 EA 123679 1056.79 020 200 0(00 000 2020 000 21 - - a Nv0R0nw1 m 51 000 939390 WW 930 5000 093 WW 010 w'.renare Harm. 2.3 TON 5196629 31E465 020 020 5004 500 930 000 23 •..064Prr1.eeww 77 SY 36395 31.70133 1000 5190 000 00 000 000 .`kon."r. A77 3739em'T° - . R , Tn- t:. - " Z :` 1 39 ir3i i'9$.. 5.1 x. 00 e. =M• )t°:! 0 19 2 FTi ;. so ; s .So 096OV: f -- :' " T -F'S :50 a z / y �?E OF 7•fi�;Lf CUM' 11l 1 .m„3.+ Ns...1.101 S: 0401360403100 r . l01¢, . 1.., e.,..,............,.... e.,..,............,.... . p J _ L WKT RIN 1 PROM, 4uFAaw:P +..Pam ....... n 1 \ % p GFS8 1 PRDR xrRa1a11an w.e<.....slr o-1 rJ.,.r p Q - k L.0) ' ln % . C lg P F : ': '( 7 3_` 1 -4,36 `9 '' �► d ,+.I.. e„E... m-01•1 BLOOM x •lere.vlm OMAO r. 300..8 r ®.a,. be Mr.�...c4he .., 133.0 t e w ®e4..e:.•,La. ul....c.....A.1.. 13341. 316- 333101+0'64-c 3x8013 cs an a Re ,,,,, eD es � M APIMUCIPM AONnRLeDOPD 95903407 8590 sum 01¢1rCE9 • • 0 • • • • 310 _ _ am V% M MC! .W 99M x141 100X4 M A .' 'RYE w51w M 34650059 WTI PUCE 3 110131, .0 TIC! 01134 00 IPM MLR ...007 1 P a- 0340466336 men 3403. me 1810 LF 0330 347,56000 51100 5500 33400 5542100) 5331 On 357,92000 13600 005.16003 34130 9 31600 365,16030 2 R- 30660 ssa DUCTILE IRON eve 275 LF 12710 SUDO 10 5940 3632519 9610 511530 SZAN 3663007 [10 00 5625000 r54M 39,31750 33000 58,15030 0,40110 01X010 3 0 -0001 OATEVA1.E 0 EA 1120250 5&52(0 51.400 (0 313.0003 145000 510000 12,6000 530100 070103 19007 03,1000 5110010 580000 347500 33,20)01 595000 310010 17000) 56 10001 11 1min 331531.40 0®710 31,20003 31.26000 590103 5N000 4 0_ 1Ha73ATEVAME 2 EA 3 0 - e107c1)lxr0wwn 6 EA 51360(0 56310059 37, 7059 3610010 3300 3300500 01000.W 3634010 5130000 31]00 03 66)10000 34/0059 1 1 2 10,0 920(10 6 a MCnaA16VAV4,e 5 EA 5401.00 9,011030 0540) 517330 00760 320030 97300 11,61510 560000 towns 3(8000 32.50159 3410. IMM O 7 •_01150 Duels Mrn eve NO LF 17010 V.1700 03 Sn40 0pnm mm WOODS SHOD L 90M noon, 52630 06010 53360 99040 0• WC/1 WAMILIR PLUG 1 EA 110070 110000 115000 510300 140501 570300 373.050 17507 00 00 520050 5100.04 00059 36000 310001 9 0 E1070A1e 1 FA 15003 55010 110000 010040 50110 38000 34070 MUD 515000 515000 9300 31101 110340 304000 10 P00Cxa04n HEwA51FRAn•A PUP 1537 LE 31M 93'700 03 00 0 0,03003 0510 530 5900 /00/9990 32E40 530.96200 5 7190 1 04430 13100 500 35230 11 ._fODr 0733/803 wss1V.'wrea •304,179 COMM 2 FA 3620007 12,40000 3110301 52200.00 .51.30,30 883060 1120030 32,00 40 320000 010059 11,00110 5360010 344007 0,1=40 1000000 P2 . 000r 0161¢13 RA3rE.417. Covu 4 EA 3170400 3400060 312(010 14/00., 313000) 13210140 31300(0 CUOMO 111000 55 0300 51/1010 320040 320000 t3 1 ;N0� 519wA're) 00001u101AS 1 FA 31.4330 5134000 3150300 31510/0 3691050 104040 5130001 11-54000 3.5.400 030140 7,070(0 1230201 0.0059 51,00.00 14 3033159471363043 1303 1 EA 15200 13000 13000 55000 310001 5110010 55001 11300 310070 310000 571110 0000 01010 30300 13 9- E4IL.A54EMw1PY CO1L4CC41ax 3 EA 35008 575020 51.0000 57,500.10 551100 350000 373003 35000 11.0010 0,00000 3 5101 560000 134010 16 043530 478 551 LF 350 sr 5150 14_40 5050 53250 3200 51,3003 3123 139173 5130 1121...41 5105 310000 17 - fill ROM 0W7 03 LF 11500 51 000 51200 590000 57310 11 33100 0500 312000) 11200 3(001 1760) 3120x0 Sri* 3200010 340¢1 PROM - 1108 2 EA 41500 1150003 331070 140000 530011 513000 25003 00000 111000 13000 00060 160..100 3100 00 30.00 19 1)101[1 M00701r30010 1722 LF 1100 9,'71100 3 00 3.75300 1100 17,721(t 359 537. 3160 30,7110 SIM 0,71200 5140 3 3.77230 20 s7A00Y000011300E714 640151102 1 EA 16000 163010 05900 340110 3501110 150000 1750 375000 00000 00100 3404100 500000 11,00390 1140110 21 009000MIa44) 505 sr 1140 571510 30-10 01927.1 5140 397340 00.72 570201 3140 097500 30.75 373121 1030 30150 22 146441.C100nnlos 23 TON 0;1000 31.73010 3.070591 57.9059 0J4n50 52.7040 000 100) 5250000 3603000 1030 DODO 0,00000 5134000 23 PAVen3O APtut 77 14 355M 367500 53000 011010 31310 340500 8910 551000 33.1404 0•02 5290 354001 0000 334040 •- ...+.'ase."0.3370iL•r1 ,- ' gr ma ca '5 - w•F eM 5 3113WI]U 3 '7'3 Z .7.4 'c':3t30a^Sy.W'Rwc ' 4' 11$04393'00$' - 331 3 515010 :0 :i3129 mq'30 7-' '5503140,$1 0 J'.•• OF r001.0••••...010_ 1.■•44.111619■4 11/19/93. , 16:34 ROUND ROCK PUBLIC WORKS + 512 255 6676 DATE: November 19, 1993 SUBJECT: City Council Meeting, November 23, 1993 ITEM: 9G. Consider a resolution authorizing the Mayor to enter into an agreement with Haegelin Construction Company, Inc. for the Southeast Water /Wastewater Improvements. STAFF RESOURCE PERSON: Jim Nuse STAFF RECOMMENDATION: Based on a review of the low bidder's qualifications, work experience, and previous history of projects with the City we recommend award of the contract to Haegelin Construction Company, Inc. NO.165 D02 I ) Bury +Pittman Consulting Engineers and Surveyors PROJECT MANUAL FOR WATER AND WASTEWATER SYSTEM IMPROVEMENTS FOR DELL CENTER BOULEVARD Prepared for: CITY OF ROUND ROCK, TEXAS Public Works Department October 1993 Project No. 525 -03.60 v -q ii-a---q- 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 PROJECT MANUAL FOR WATER AND WASTEWATER SYSTEM IMPROVEMENTS FOR DELL CENTER BOULEVARD Prepared for: CITY OF ROUND ROCK, TEXAS Public Works Department Prepared by: BURY & PITTMAN, INC. 3345 Bee Caves Road, Suite 200 Austin, Texas 78746 OCTOBER 1993 Project No. 525 -03.60 v5. Section 1.0 Notice to Bidders NB -1 2.0 Bid Documents BD -1 3.0 Post Bid Documents PBD -1 4.0 General Conditions GC -1 5.0 Special Conditions SC -1 6.0 Technical Specifications TS -1 table.mst/spec TABLE OF CONTENTS Description Enk Item 1 General Description Item 2 Control of Work Item 3 Examination and Review Item 4 Protection and Precaution Item 5 Materials Item 6 Grading, Restoration, Revegetation, and Erosion Control Measures (Series 600) Item 7 Construction and Traffic Control within Highway Right -of -Way Item 8 Mail Boxes Item 9 Seal Coat Item 506 Manholes Item 509 Trench Safety Systems Item 510 Pipe Item 511 Water Valves 1.0 NOTICE TO BIDDERS NOTICE TO BIDDERS Sealed bids addressed to the Purchasing Agent, City of Round Rock, 221 East Main Street, Round Rock, Texas 78664, for furnishing all labor, material and equipment and performing all work required for the project titled Water and Wastewater System Improvements for Dell Center Boulevard (project includes approximately 1810 feet of 12 -inch ductile iron waterline, 275 feet of 8 -inch ductile iron waterline, and approximately 1537 feet of 8 -inch wastewater line including all ancillary items) will be received until 2:00 p.m. November 16, 1993 then publicly opened and read aloud at the City Hall Council Chambers at the same address. Bid envelopes should state date and time of bid and "Water and Wastewater System Improvements for Dell Center Boulevard ". No bids may be withdrawn after the scheduled opening time. Any bids received after scheduled bid opening time will be returned unopened. Bids must be submitted on City of Round Rock bid forms and must be accompanied by an acceptable bid security as outlined in the Instructions to Bidders, payable to the City of Round Rock, Texas equal to five percent (5 %) of the total bid amount. Plans, Bid Forms, Specifications, and Instructions to Bidders may be obtained from the Bury & Pittman, Inc., 3345 Bee Caves Road, Suite 200, Austin, Texas 78746 beginning Wednesday. November 3. 1993 at 1:00 p.m. for a non - refundable charge of $25.00 per set. In case of ambiguity, duplication, or obscurity in the bids, the City of Round Rock reserves the right to construe the meaning thereof. The City of Round Rock further reserves the right to reject any or all bids and waive any informalities and irregularities in the bids received. The successful bidder will be expected to execute the standard contract prepared by the City of Round Rock, and to furnish performance and payment bonds as described in the bid documents. Publish Dates: Austin American Statesman: Round Rock Leader: October 31, 1993 November 1, 1993 November 7, 1993 November 8, 1993 eeticebd/.Pec.m. r NB -1 2.0 BID DOCUMENTS INSTRUCTIONS TO BIDDERS 1. Prior to submitting any proposal, bidders are required to read the plans, specifications, proposal, contract and bond forms carefully; to inform themselves by their independent research, test and investigation of the difficulties to be encountered and judge for themselves of the accessibility of the work and all attending circumstances affecting the cost of doing the work and the time required for its completion and obtain all information required to make an intelligent proposal. 2. Should the bidder find discrepancies in, or omissions from the plans, specifications, or other documents, or should he be in doubt as to their meaning, he should notify at once the Engineer and obtain clarification or addendum prior to submitting any bid. 3. It shall be the responsibility of the bidder to see that his bid is received at the place and time named in the Notice to Bidders. Bids received after closing time will be returned unopened. 4. Bids shall be submitted in sealed envelopes plainly marked "Sealed Bid" and showing the name of the project, the job number if applicable, and the opening date and time. 5. Bids shall be submitted on proposal forms furnished by the City of Round Rock. 6. All proposals shall be accompanied by a certified cashier's check upon a National or State bank in an amount not less than five percent (5%) of the total maximum bid price, payable without recourse to the City of Round Rock, or a bid bond in the same amount from a reliable surety company, as a guarantee that the bidder will enter into a contract and execute performance and payment bonds, as stipulated by item 11 below, within ten (10) days after notice of award of contract to him. Proposal guarantees must be submitted in the same sealed envelope with the proposal. Proposals submitted without check or bid bonds will not be considered. 7. All bid securities will be returned to the respective bidders within twenty-five (25) days after bids are opened, except those which the owner elects to hold until the successful bidder has executed the contract. Thereafter, all remaining securities, including security of the successful bidder, will be returned within sixty (60) days. biddoc.mst/spec BD -1 8. Until the award of the contract, the City of Round Rock reserves the right to reject any and all proposals and to waive technicalities; to advertise for new proposals; or to do the work otherwise when the best interest of the City of Round Rock will be thereby promoted. 9. In case of ambiguity or lack of clarity in the statement of prices in the bids, the City of Round Rock reserves the right to consider the most favorable analysis thereof, or to reject the bid. Unreasonable (or unbalanced) prices submitted in a bid may result in rejection of such bid or other bids. 10. Award of the contract, if awarded, will be made within sixty (60) days after opening of the proposals, and no bidder may withdraw his proposal within said sixty (60) day period of time unless a prior award is made. 11. Within ten (10) days after written notification of award of the contract, the successful bidder must furnish a performance bond and a payment bond in the amount of one - hundred percent (100 %) of the total contract price. Provided however, if the contract price is less than $50,000.00, the bidder shall have the option of providing a letter of credit in lieu of a performance bond, said letter of credit in a form acceptable to the City of Round Rock. Said performance bond, or letter of credit, if applicable, and payment bond shall be from an approved surety company holding a permit from the State of Texas to act as surety (and acceptable according to the latest list of companies holding certificates of authority from the Security of the Treasury of the United States) or other surety or sureties acceptable to the Owner, with approval prior to bid opening. 12. If the total contract price is less than $25,000.00 the performance and payment bond requirement will be waived by the City of Round Rock. Payment will be made following completion of the work. 13. Failure to execute the construction contract within ten (10) days of written notification of award or failure to furnish the performance bond, or letter of credit if applicable, and payment bond as required by item 11 above, shall be just cause for the annulment of the award. In case of the annulment of the award, the proposal guarantee shall become the property of the City of Round Rock, not as a penalty, but as a liquidated damage. 14. No contract shall be binding upon the City of Round Rock until it has been signed by its Mayor after having been duly authorized to do so by the City Council. biddoc.mstispec BD -2 15. The Contractor shall not commence work under this contract until he has furnished certification of all insurance required and such has been approved by the City of Round Rock, nor shall the contractor allow any subcontractor to commence work on his subcontract until proof of all similar insurance that is required of the subcontractor has been furnished and approved. 16. Any quantities given in any portion of the contract documents, including the plans, are estimates only, and the actual amount of work required may differ somewhat from the estimates. The basis for the payment shall be the actual amount of work done and /or material furnished. 17. No Texas sales tax shall be included in the prices bid for work under this contract. This contract is issued by an organization which is qualified for exemption pursuant to the provisions of Article 10.04 (h) of the Texas Limited Sales, Excise and Use Tax Act. The contractor performing this contract may purchase, rent or lease all materials, supplies, equipment used or consumed in the performance of this contract by issuing to his supplier an exemption certificate complying with State Comptroller's ruling #95 -0.07. Any such exemption certificate issued by the contractor in lieu of the tax shall be subject to the provisions of the State Comptroller's ruling #95 -0.09 as amended to be effective July 1, 1979. 18. No conditional bids will be accepted. biddoc.mst/spec BD -3 1 PLANET INSURANCE CON,r.PAN5r HEAD OFFICE, SUN PRAIRIE, WISCONSIN 1 BID BOND 1 KNOW ALL MEN BY THESE PRESENTS, that we HAEGELIN CONSTRUCTION CO., INC., P. 0. Box 9086, Austin, Texas 78766 as Principal, hereinafter called the Principal, and the PLANET INSURANCE COMPANY of Madison, Wisconsin, a corporation duly organized under the laws of the State of Wisconsin, as Surety, hereinafter called the Surety, are held and firmly bound unto CITY OF ROUND ROCK 1 as Obligee, hereinafter called the Obligee, in the sum of five percent (5Z) of greatest amount bid in - - - -- Dollars ($ ), for the ' payment of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. 1 WHEREAS, the Principal has submitted a bid for Water and Wastewater Improvements for Dell Center Blvd. 1 NOW, THEREFORE, if the contract be timely awarded to the Principal and the Principal shall within such time as specified in the bid, enter into a contract in writing and give bond with good and 1 sufficient surety, or, in the event of the failure of the Principal to enter into such Contract and give such bond or bonds; if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith contract with another party to perform the work covered by said bid, then this obligation 1 shall be null and void, otherwise to remain in full force and effect. PROVIDED, HOWEVER, neither Principal nor Surety shall be bound hereunder unless Obligee prior to ' execution of the final contract shall furnish evidence of financing in a manner and form acceptable to Principal and Surety that financing has been firmly committed to cover the entire cost of the project. Signed and sealed this 16th day of November 19 93 L4 fc.t. L aGt4i J HAEGELIN CONSTRUCTION CO., INC. (Witness) (Princiipal) (Seal) 1 By: / /, //er 4OL; 4 ; !4 (Title) 1 1 1 By: 1 BDP- 23232/90 PLANET INSURANCE COMPANY Peter Pincoffs, (Attorney -in -Fact) PLANET IN COMPAN HEAD OFFICE, MADISON. WISCONSIN • POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS, That the PLANET INSURANCE COMPANY, a corporation duly organized under the laws of the State of Wisconsin, does hereby make, constitute and appoint Robt. H. Bin, Thomas C. Wa111tack, Bess Ann Roberts, Peter Pincoffs, John S. Burns, Jr. and Joe George, individually, of Austin, Texas its true and lawful Attorney -in -Fact, to make, execute, seal and deliver for and on its behalf, and as its act and deed any and all bonds and undertakings of Suretyship, an • to bind the PLANET INSURANCE COMPANY thereby es fully and to the same extent as if such bonds and undertakings and other writings obligatory in the nature thereof were signed by an Executive Officer of the PLANET INSURANCE COMPANY and sealed and attested by one other of such officers, and hereby ratifies and confirms all that its said Attorney(s) -in -Fact ma•do in pursuance hereof. This Power of Attorney is granted under and by authority of Article VII of the 8y -Laws of PLANET INSURANCE COMPANY which became effective September 21, 1981, which provisions are now in full force and effect, reading as follows: ARTICLE VII — EXECUTION OF BONDS AND UNDERTAKINGS 1. The Board of Directors, the President, the Chairman of the Board, any Senior Vice President, any Vice President or Assistant Vice President or other officer designated by the Board of Directors shall have power and authority to (a) appoint Attorneys -in -Fact and to authorize them to execute on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof, and (b) to remove any such Attorney -in -Fact at any time and revoke the power and authority given to him. 2. Attorneys -in -Fact shall have power and authority, subject to the terms and limitations of the power of attorney issued to them, to execute and deliver on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof. The corporate seal is not necessary for the validity of any bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof. 3. Attorneys -in -Fact shall have power and authority to execute affidavits required to be attached to bonds, recognizances, contracts of indemnity or other conditional or obligatory undertakings and they shall also have power and authority to certify the financial statement of the Company and to copies of the By -Laws of the Company or any article or section thereof. This power of attorney is signed and sealed by facsimile under and by authority of the following Resolution adopted by the Board of Directors of PLANET INSURANCE COMPANY at a meeting held on the 29th day of March, 1982, at which a quorum was present, and said Resolution has not been amended or repealed: "Resolved, that the signatures of such directors and officers and the seal of the Company may be affixed to any such power of attorney or any certificate relating thereto by facsimile, and any such power of attorney or certificate bearing such facsimile signatures or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by facsimile signatures and facsimile seal • shall be valid and binding upon the Company in the future with respect to any bond or undertaking to which it is attached." IN WITNESS WHEREOF, the PLANET INSURANCE COMPANY has caused these presents to be signed by in Vice President, and in corporate seal to be hereto affixed, this 12th day of September 19 89 STATE OF COUNTY OF On this BDP -1431 1/82 Pennsylvania Philadelphia 12th day of September ,19 89 , personally appeared Raymond MacNeil to me known to be the Vice - President of the PLANET INSURANCE COMPANY, and acknowledged that he executed and attested the foregoing instrument and affixed the seal of said corporation thereto, and that Article VII, Section 1, 2, and 3 of the By -Laws of said Company, and the Resolution, set forth therein, are still in full force. 1 N �0. .. / My Commission Expires:y /r '4.11. n�� -� / A • Fels 1 ,19 9 e 1 J Notary Public in and for State of Pennsyl r uary ''' 0 ' "5 Residing at Philadelphia 1, Ray L. Lorah , Assistant Secretary of the PLANET INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy of a Power of • tt�o pay executed by said PLANET INSURANCE COMPANY, which is still in full force and effect. i • ' u' -. Z:+ .. f .t F1s s IN WITNESS WHEREOF, I have hereunto set my han nd a►f' ": - 'e s of said Company this 1 6th day of November 19 93 Assistant Secretary Ae BID BOND KNOW ALL MEN BY THESE PRESENTS THAT WE, as PRINCIPAL and as SURETY, are held and firmly bound unto the hereinafter referred to as the "OWNER ", in the penal sum of five percent (5%) of the total amount of the bid of the PRINCIPAL submitted to the OWNER, for the work described below; for the payment of which sum in lawful money of the United States of America, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. In no case shall the liability of the SURETY hereunder exceed the sum of The CONDITIONS OF THIS OBLIGATION ARE SUCH, THAT whereas, said PRINCIPAL has submitted the above mentioned bid to the OWNER, for construction for the work under the "SPECIFICATIONS FOR CONSTRUCTION OF for which bids are to be opened at the office of the OWNER on NOW THEREFORE, if the PRINCIPAL is awarded the contract, and within the time and manner required under the heading "Instructions to Bidders ", after the prescribed forms are presented to him for signature, enters into a written agreement, substantially in the form contained in the Specifications, in accordance with the bid and files the town bonds with the OWNER, one to guarantee faithful performance and the other to guarantee payment for labor and materials, then this obligation shall be null and void, otherwise, it shall be and remain in full force and effect. In the event suit is brought upon this bond by the OWNER and judgement is recovered, said SURETY shall pay all costs incurred by the OWNER in such suit, including a reasonable attorney's fee to be fixed by the Court. In WITNESS WHEREOF, we have hereunto set our hands and seals this day of Principal: Surety: By: By: (Seal) (Seal) biddoc.mst/spec BD-4 1 PROPOSAL BIDDING SHEET ' TOB NAME: Water and Wastewater System Improvements for Dell Center Boulevard ' JOB LOCATION: Round Rock, Williamson County, Texas OWNER: City of Round Rock, Texas 1 DATE: November 16, 1993 Gentlemen: Pursuant to the foregoing Notice to Bidders and Instructions to Bidders, the undersigned bidder ' hereby proposes to do all the work, to furnish all necessary superintendence, labor, machinery, equipment, tools, materials, insurance and miscellaneous items, to complete all the work on which he I bids as provided by the attached supplemental specifications, and as shown on the plans for the construction of Water and Wastewater System Improvements for Dell Center Boulevard and binds himself on acceptance of this proposal to execute a contract and bond for completing said project within ' the time stated, for the following prices, to wit: BASE BID ' Bid Item Description Unit I Item Quantity Unit and Written Unit Price Price Amount 1. 1810 LF 12 -inch class 52 ductile I iron pipe. complete and in place �with , compacted backfill for dollars 1 and - cents. $ 26— $47060 1 2. 275 LF 8 -inch class 52 ductile iron pipe. complete and in I place with compacted backfill for�G( �� -0-0 dollars and cents. $ 2-2-. — $ 6 0S6 3. 4 EA 12 -inch gate valve ' complete and in place 1 for it)ollars and /N o cents. $ /Zoo— $ 4800— ' 1 biddoc.mst/spec BD - Bid Item Description Unit Item Quantity Unit and Written Unit Price Price Amount 1 4. 2 EA 8 -inch gate valve complete and in place ' forAhlAtiollars and „n o cents. $ SOD — $ 160o — 1 5. 6_ EA 5 1/4 -inch fire hydrants complete and in place ' for Oru.- ( dollars I and /n.0 cents. $ /000 — $ 6e700 - 6. 5 EA 6 -inch gate valve ' complete and in place for zw dollars 1 and in,o cents. $ /aO0 — $ 300o — ' 7. 100 LF 6 -inch ductile iron pipe complete and in place with. compacted backfill for dollars and �, cents. $ 2 — $ Zooa — 8. 1 EA 12 -inch water line plug complete and in place ' form/dollars and i71.0 cents. $ /o'— $ /0,0 -- ' 9 1 EA 8 -inch water line plug complete and in place 1 for dollars and cents. $ — $ -. 0 1 biddoc.mst/spec BD -6 Bid Item Description Unit Item Quantity Unit and Written Unit Price Price Amount 1 10. 1537 LF 8 -inch SDR35 PVC 1 wastewater pipe. all depths complete and in place with ' compacted backfill dollars and cents. $ 2-/ — $ 3 2277— 11. 2 EA 1 12. 4 EA 1 1 13. 1 EA 1 15. 1 1 1 ' biddoc.mst/spec EA 4-foot diameter wastewater manhole complete and in place foi]`c. J.u,a- dollars and cents. $ /20a' -- $ 2 400 -- 4-foot diameter wastewater manhole without bolted cover complete and in place for e f4.0-1A.., Qdollars and cents. 4-foot diameter wastewater drop manhole complete and in place for ' an6' �r, cents. $ /S $ /SOD -- EA Wastewater line plug complete and in place $ /000 $ 40 for f c dollars ent cents. and cs. $ S o — $ ,co 8 -inch wastewater connection to the existing 24 -inch interceptor fo s�llars and ' / - nts. $ 7S'0 — $ 7So - BD -7 Bid Item Description Unit Item Ouantitv Unit and Written Unit Price Price Amount 1 16. 555 LF Silt fence complete and in place for ,' dollars 1 and cents. $ 677 $ Z . ' 17. 80 LF Rock berm complete and in place t for dollars ' and C d cents. $ $ /ZOO — 18. 2 EA Inlet protection complete and in place for,au,u Vic, dollars and ....--no cents. $ 7S' $ /4'0 19. 3722 LF Trench safety systems - ' complete and in place for r y yµ , dollars and --7-1.o cents. $ / $ 37 20. 1 EA Stabilized construction entrance complete and in I place for . ollars and ,--34.,o cents. $ 4S $ GS' -- 21. ES SY Hydromulch complete and " in place for ( , dollars and �yi ,, cents. $ /.` $ 9 1 biddoc.mst/spec BD -8 r 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 F 1� 1 1 Bid Item Quantity 22. 2.5 23. 27 TOTAL BASE BID (Items 1 thru 23): Respectfully Submitted, Title for I4AEGELIN CONSTRUCTION CO., INC. Name of Firm Item Description Unit and Written Unit Price TONS Waterline fittings complete and in place for o ars an „ , cents. $ /.S 90 — $ 3 7sb — Pavement repair complete and in place for and STATEMENT OF SEPARATE CHARGES: Materials: All Other Charges: Total: If this proposal is accepted, the undersigned agrees to execute the contract and provide necessary bonds and insurance certification as per the Instructions to Bidders and commence work within ten (10) days after written Notice to Proceed. The undersigned further agrees to complete the work in full within sixty (60) calendar days after the date of the written Notice -to- Proceed. The undersigned certifies that the bid prices contained in the proposal have been carefully checked and are submitted as correct and final The Owner reserves the right to reject any or all bids and may waive any informalities. Telephone Unit Price Amount dollars cents. $ $ 7s /Z3s5 /. &LO UST/Af, X . 7 8766 Address <c /Z -358 —,- /6 /93 Date Secretary, if Contractor is a Corporation biddoc.mst/spec BD -9 $ S3o i (, 7os7s, se $ /Z3S91. s� 3.0 POST BID DOCUMENTS THE STATE OF TEXAS COUNTY OF WIT.T.IAMSON AGREEMENT THIS AGREEMENT, made and entered into this 6/z day of Oe-c- A.D. 19 93 , by and between the CITY OF ROUND ROCK, TEXAS acting through it's Mayor, Party of the First Part, hereinafter termed the OWNER, and %epe%, si,da., "of the City of , 6-,' , County of Tu.,; , State of , Party of the Second Part, hereinafter termed Contractor. WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned, to be made and performed by said First Party (Owner), the said Second Party (Contractor), hereby agrees with the first Party to commence and complete the construction of certain improvements at the prices set forth in the Contractor's Proposal dated l /- —93 for certain improvements described as follows: Project includes approximately 1,810 feet of 12" Ductile iron waterline, approximately 275 feet of 8" Ductile iron waterline and approximately 1,537 feet of 8" wastewater line including all ancillary items. The Contractor shall perform all work shown on the Plans and described in the Contract and shall meet all requirements of this Agreement, the General and Special Conditions of the Contract; and such Orders and Agreements for Extra Work as may subsequently be entered by the above named parties to this Agreement. The Contractor hereby agrees to commence work under this contract within 10 consecutive calendar days after that date of the Notice to Proceed and shall cause work to progress in a manner satisfactory to the Owner. Such work shall be completed in full within 60 calendar days after the date of the written Notice to Proceed. Time is of the essence to this contract. The Owner agrees to pay the Contractor in current funds, and to make payments on account, for the performance of the work in accordance with the Contract, at the prices set forth in the Contractor's Proposal, subject to additions and deductions, all as provided in the General Conditions of the Agreement. posthid.m.Uepec Water and Wastewater ystem Improvements for Dell Center Blvd. PBD -1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 M AGREEMENT - continued The following documents together with this Agreement, comprise the Contract, and they are fully a part thereof as if herein repeated in full: The Notice to Bidders The Instruction to Bidders The Proposal and Bidding Sheets The Performance & Payment Bonds The General Conditions of Agreement The Special Conditions of Agreement The Technical Specifications Addenda Change Orders The Certificate of Insurance The Plans IN WITNESS WHEREOF the Parties to these presents have executed this Agreement in multiple originals in the year and day first above written. ATTEST: posthid.m Jlpec By: V — ,,,r�i/� Party of the First ' . Owner) Mayor - City of Round Rock By : 4/ By: 62 Secretary, if Contractor is a Corporation or otherwise registered with the Secretary of the State PBD -2 Party of the Second Part (Contractor) THE STATE OF TEXAS COUNTY OF WILLIAMSON PERFORMANCE BOND #P2502864 KNOW ALL MEN BY THESE PRESENTS: That Haegelin Construction Co., Inc. of the City of Austin , County of Travis , and State of Texas , as Principal, and Planet Insurance Canpany authorized under the law of the State of Texas to act as surety on bonds for principals, are held and firmly bound unto [HE CITYOFROUND ROCK, TEXAS, (Owner), in the penal sum oft hundred twenty three thousand, five hundred ninety one & 50 /100 dollars ($ 123,591.50AAAAAA ) for the payment whereof, well and truly to be made the said Principal and Surety bind themselves, and their heirs, administrators, executors, successors and assigns, jointly and severally, by these presents: WHEREAS, the Principal has entered into a certain written contract with the Owner dated the 6th day of December , 19 9 to which the contract is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein consisting of: Water and Wastewater System Improvements for Dell Center Blvd. NOW, THEREFORE, THE CONDITIONS OF THIS OBLIGATION IS SUCH, that if the said Principal shall faithfully perform said Contract and shall, in all respects, duly and faithfully observe and perform all and singular the covenants, conditions and agreements in and by said Contract, agreed and covenanted by the Principal to be observed and performed, including but not limited to, the repair of any and all defects in said work occasioned by and resulting from defects in materials furnished by or workmanship of, the Principal in performing the work covered by said Contract and occurring within a period of twelve (12) months from the date of the contract Completion Certificate and all other covenants and conditions, according to the true intent and meaning of said Contract and the Plans and Specifications hereto annexed, then this obligation shall be void; otherwise to remain in full force and effect; PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statues of Texas as amended and all liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein. postbid.mWspec PBD -3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ccz: 1 1 PERFORMANCE BOND (continued) Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the term of the contract, or to the work performed thereunder, or the plans, specifications, or drawings accompanying the same, shall in anywise affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract, or to the work to be performed thereunder. IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this 6th day of December instrument this 19 93 . HAEGELIN CONSTRUCTION CO., INC. PLANET INSURANCE COMPANY Address Title P. 0. Box 9086 Austin, Texas 78766 (512) 388 -9900 popbid.mR/gxc PBD-4 Surety By Ar-o Bess Ann Roberts Attorney -in -Fact Title c/o CIA Insurance Agency, Inc. dba Consolidated Insurance Agency Address 101 West 6th Street, #350 Austin, Texas 78701 -2995 (512) 478 -5631 The name and address of the Resident Agent of Surety is : CIA Insurance Agency, Inc. dba Consolidated Insurance Agency 101 West 6th Street, 11350, Austin, Texas 78701 -2995 posibid.mittspec PAYMENT BOND #P2502864 THE STATE OF TEXAS COUNTY OF WILLIAMSON KNOW ALL MEN BY THESE PRESENTS: That Haegelin Construction Co., Inc. , of the City of Austin , County of Travis , and State of Texas as Principal, and Planet Ins. Co. authorized under the laws of the State of Texas to act as Surety on Bonds for Principals, are held and firmly bound unto THE CITY OF ROUND ROCK, (OWNER), and all subcontractors, workers, laborers, mechanics and suppliers as their interest may appear, all of whom shall have the right to sue upon this bond, in the penal sum of One hundred twenty three thousand, five hundred ninety one & 50/100 Dollars ($ 123,591. ) for the payment whereof, well and truly be made the said Principal and Surety bind themselves and their heirs, administrators, executors, successors, and assigns, jointly and severally, by these presents: WHEREAS, the Principal has entered into a certain written contract with the Owner, dated the 6th day of December , 19 93 , to which Contract is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein consisting of: Water and Wastewater System Improvements for Dell Center Blvd. NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall well and truly pay all subcontractors, workers, laborers, mechanics, and suppliers, all monies to them owing by said Principals for subcontracts, work, labor, equipment, supplies and materials done and furnished for the construction of the improvements of said Contract, then this obligation shall be and become null and void; otherwise to remain in full force and effect. PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas as amended and all liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein. PBD -5 PAYMENT BOND (continued) Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract, or to the work performed thereunder, or the plans, specifications or drawings accompanying the same shall in anywise affect it's obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract, or to the work to be performed thereunder. IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this Instrument this 6th day of member , 19 9 HAECELIN CONSTRUCTION CO., INC. PLANET INSURANCE COMPANY Title P. 0. Box 9086 Address Austin, Texas 78766 (512) 488 -9900 (512) 478 -5631 The name and address of the Resident Agent of Surety is : 101 West 6th Street, #350, Austin, Texas 78701 -2995 pn.Wld.m.Vgac PBD -6 Surety /f By: /'1�4.a, �rr w /ter Bess Ann Roberts - Attorney -in -Fact Title c/o CIA Insurance Agency, Inc. dba Consolidated Insurance Agency Address 101 West 6th Street, #350 Austin, Texas 78701 -2995 CIA Insurance Agency, Inc. dba Consolidated Insurance Agency • PLANET INSURANCE COMPANY HEAD OFFICE, MADISON, WISCONSIN 1 ` , POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS, That the PLANET INSURANCE COMPANY, a corporation duly organized under the laws of the State of Wisconsin, does hereby make, constitute and appoint Robt. H. Bowman, Thomas C. Womack, Bess Ann Roberts, Peter Pincoffs, John S. Burns, Jr. and Joe George, individually, of Austin, Texas its true and lawful Attorney -in -Fact, to make, execute, seal and deliver for and on its behalf, and as its act and deed and undertakings of Suretyship, any and all bonds a to bind the PLANET INSURANCE COMPANY thereby as fully and to the same extent as if such bonds and undertakings and other writings obligatory in the nature thereof were signed by an Executive Officer of the PLANET INSURANCE COMPANY and sealed and attested by one other of such officers, and hereby ratifies and confirms all that its said Attorney(s)-in -Fact may do in pursuance hereof. This Power of Attorney is granted under and by authority of Article VII of the By -Laws of PLANET INSURANCE COMPANY which became effective September 21, 1981, which provisions are now in full force and effect, reading as follows: ARTICLE VII — EXECUTION OF BONDS AND UNDERTAKINGS 1. The Board of Directors, the President, the Chairman of the Board, any Senior Vice President, any Vice President or Assistant Vice President or other officer designated by the Board of Directors shall have power and authority to (a) appoint Attorneys- in-Fact and to authorize them to execute on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof, and (b) to remove any such Attorney -in -Fact at any time and revoke the power and authority given to him. 2. Attorneys -in -Fact shall have power and authority, subject to the terms and limitations of the power of attorney issued to them, to execute and deliver on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof. The corporate seal is not necessary for the validity of any bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof. 3. Attorneys -in -Fact shall have power and authority to execute affidavits required to be attached to bonds, recognizances, contracts of indemnity or other conditional or obligatory undertakings and they shall also have power and authority to certify the financial statement of the Company and to copies of the By -Laws of the Company or any article or section thereof. This power of attorney is signed and sealed by facsimile under and by authority of the following Resolution adopted by the Board of Directors of PLANET INSURANCE COMPANY at a meeting held on the 29th day of March, 1982, at which a quorum was present, and said Resolution has not been amended or repealed: "Resolved, that the signatures of such directors and officers and the seal of the Company may be affixed to any such power of attorney or any certificate relating thereto by facsimile, and any such power of attorney or certificate bearing such facsimile signatures or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by facsimile signatures and facsimile seal shall be valid and binding upon the Company in the future with respect to any bond or undertaking to which it is attached." IN WITNESS WHEREOF, the PLANET INSURANCE COMPANY has caused these presents to be signed by its Vice President, and its corporate seal to be hereto affixed. this 12th day of September 19 89 STATE OF COUNTY OF On this My Commission Expires: February 1 IN WITNESS WHEREOF, 1 have hereunto set my han BOP-1431 1/82 Pennsylvania Philadelphia 12th day of September "ate Assistant Secretary ,19 89 , personally appeared Raymond MacNeil ' to me known to be the Vice - President of the PLANET INSURANCE COMPANY, and acknowledged that he executed and attested the foregoing instrument and affixed the seal of said corporation thereto, and that Article VII, Section 1, 2, and 3 of the By -Laws of said Company, and the Resolution, set forth therein, are still in full force. .19 93 `, " . f Notary Public in and for State of Penn.Sylvan Residing at Philadelphia L Ray L. Lorah , Assistant Secretary of PLANET INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy of a Powor of/tt@* - ss y executed by said PLANET INSURANCE COMPANY, which is still in full force and effect. 2 � of said Company this 6 th day of December P 19 93 IMPORTANT NOTICE To obtain information or make a complaint: You may contact the Texas Department of Insurance to obtain information on companies, coverages, rights or complaints at: 1- 800 - 252 -3439 You may write the Texas Department of Insurance: P. 0. Box 149104 Austin, TX 78714 -9104 FAX #(512) 475 -1771 PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or about a claim, you should contact the agent of the company first. If the dispute is not resolved, you may contact the Texas Department of Insurance. ATTACH THIS NOTICE TO YOUR POLICY: This notice is for information only and does not become a part or condition of the attached document. AIDIII:11 CERTIMATE OF PRODUCER INSURED Haegelin Construction Company P.O. Box 9086 Austin, Texas 78766 Consolidated Insurance Agency CIA Insurance Agency, Inc. 101 West 6th Street, Suite 350 Austin, TX 78701 (512)478 -5631 NSU l A tJCE ISSUE DATE (MAWDA'Y) x € 5/10/1994 THIS CERTIFICATE IS ISSUED AS A Po MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POUCIES BELOW. COWMIY LETIM COMPANY LEIER COLWANY LETTER COMPANY D LETTER COMPANY LE TER COMPANIES AFFORDING COVERAGE A Valley Forge Insurance Company B Continental Casualty Company C Transportation Ins. Company Continental Casualty Transcontinental Ins. Company COVERAGES s - - THIS IS TO CERTIFY THAT THE POUCIES OF INSURANCE USTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POUCIES DESCRIBED HEREIN IS SUBJECT TO AU. THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POUCIES. UMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. CO LTR A GENERAL LIABILITY X COMMERCIN. GENERN. LIABLITY A90027237T CLAIMS MADE X OCCUR OWNERS & CONRIACTCRS PROT. AUTOMOBB.E LUIBLJTY B X IX X EXCESS LIABILITY D X : UMBRELLA FORM • OTHER THAN UMBRELLA FORM OTHER ANY AUTO ALL OWNED AUTOS SCHEDULED AUTOS HIRED AUTOS NON -OWNED AUTOS GARAGE UABLTY WORKER'S COMPENSATION 0000 - EJMPLOYERS' DABLTTY CERTIFIC hQL1S1:R - m..._.. City of Round Rock Attn: Kathy Stagman 309 East Main Round Rock TX 78664 ACORO 254 (7/90) TYPE OF INSURANCE POLICY NUL®ER • 8UA400272382 Al22211083 WC113339042 POLICY EFEECTLYE POLICY EXPPUTTON IAQIB DATE (MLLBDAY) DATE(MMAD/YI') GENERAL ADDFE:DATE s , 2 , 00 mmuclS VPAGG. $1,000,000 s 1,000,000 s 1,000,000 . FINE DAMAGE (Any one We) s 50,000 MIOD. E)S'ENSE W one pe.R) $ 5,000 05/16/94 05/16/94 05/16/94 05/16/94 05/16/95 rE° L ADY' DA" EACH OCCURRENCE . LIMIT CONFINED SINGLE 0 1,000,000 05/ 16/ 95!BGDLYWUJRY . s . (Per Penn) . GODLY AWRY .S (Per accident PROPERTY DAMAGE EACH OCCURENCE s 3,000,000 05/ 16/ 95 AGGREGATE s 3 000 000 . STAMCRY LIMITS 05 /16 /95EAHlCC DISEASE _ POLL:Y LJMIT DISEASE . EACH EMPLOYEE • DESCRIPTION OF OPETATIONLM1OCATIONSNEMCLES /SPECIAL HEMS As respects Commercial General Liability and Business Automobile policies City of Round Rock is shown as an additional insured. Dell Center Blvd. - Dell Computer Job s 1,090,000 1,000,000 s 1,000,000 £ c SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE MF „ EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO MAIL 3 0 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABIUTY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES. �,. T,..._._.. I £AUTHOR® c : AYONSOLIDATEpwA AGENCY %... ..............,.. Bye.., : - - �. r (4A I p �eA�l ..,.., . • . • ••••• - 9 OR ANON •. AOO C 1998 ai oi:i�® CERTIFICATE - OF CO LTR A AUTOIADBLE LIABILITY B $ ANY ALTO X AIL OWNED AUTOS .SOiEDULED AUTOS $ • HEED AUTOS X . NON-0KNED AUTOS ' GARAGE LUBLIN EX W CESS BLITY D. g: UMBIELLA FORMA • OTHER THAN U1,9RELUL FORM WORKERS COMPENSATION AND EMPLOYERS' UABLITY OMER E Builder's Risk 004215 CERTIFICATE HOLDER City of Round Rock Attn: Kathy Stagman 309 East Main Round Rock TX 78664 Consolidated Insurance Agency CIA Insurance Agency, Inc. 101 West 6th Street, Suite 350 Austin, T$ 78701 (512)478 -5631 NSURED Haegelin Construction Company P.O. Boa 9086 Austin, Texas 78766 TYPE OF INSURANCE POLICY RUBBER GENERAL LIABILITY $ COMMERCIAL GENERAL uABLm A900272371 CANS MME ;:$:: OCCUR OWNERS & CONTRACTORS PROT. BUA400272382 Al22211083 WC113339042 INSURANCE THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. COMPANY LETTER COMPANY LETTER CCLIPANY LEDER CCLIPANY .......... . LEVER CCMPANY IJERER A Valley Forge Insurance Company B Continental Casualty Company C Transportation Ins. Company D Continental Casualty E Transcontinental Ins. Company COVERAGESS _ • _ __ • THIS IS TO CERTIFY THAT THE POUCIES OF INSURANCE USTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY 80 ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POUCIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDMONS OF SUCH POLICIES. OMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAMS. • ..... POLICY EFFECTIVE POLICY EXPIRATION lillq DATE (MMrDOIYY) : DA7E(MMAD/YY) :s 1,000,06'6 05/16/93 :OS /16 /94 '' °M0NPL8PD" • s �"' R ! ' EACH OCCURRENCE ;s 1,000, • • FRE DAMAGE (Any one Km) is 50,000 • • MED. E7WENSE (Any cne pereon S 5,000 COMBINED SINGLE Limn- :S 1,000,000 05/16/93 05/16/93 05/16/93 12/15/93 05 / 16 / 9 4 AoOREMTE • IBSUE•,RTF (M1 UDA'Y) 12/15/1993 COMPANIES AFFORDING COVERAGE GENEALADDAEGATE s 2,000,000 PRODUCTS-COMP/OP AGO. E S 1. 0 0 0. 0 0 0 05/ 16/ 94 BODLY INJURY ' (Per perecn) BODLY INJURY (Per eaiden) PROPERTY DMIAGE EACH OCCURRENCE STATUTORY LIMITS DESCR0'TK/N OP OPERATIONS/LOCATIONSITEHICLEWSPEcIAL TEILS As respects Commercial General Liability and Business Automobile policies City of Round Rock is shown as an additional insured. Dell Center Blvd. - Dell Computer Job s 2,000,000 s 2,000,000 05/16/94 EACH ACCIDENT 1,000,000'1 DISEASE- POUCYLYAIT s 1,000,000' DISEASE- EA.CHEMPLOYEE s 1,000,000 03/15/94 @ job site $123,592. deductible ' $500.00 CANCELLATION - - : SHOULD ANY OF THE ABOVE DESCRIBED POUCIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL BNCIEOLLCRI$( • MAIL 30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE • LEFFaidikaMBL/tikkZaktigaggAliht-PBEVAT,R f T IL kFiVE1ANkti LeMRF 4LxT> 4cRGNa���1f?F BBL R5CX i1CAVOf i= tegAiAbWLKYA EU,* ▪ ?DBA C SOLMATEMJRADI AGENCY CORPORATION 1900- To: City of Round Rock 221 East Main Street Round Rock, Texas 78664 TYPE OF POLICY EFFECTIVE INS. NO. DATE Workmen's Compensation Comprehensive General Liability Includes Contractual Liability Covers Independent Contractors Owner's Protective Contractors popbid.m i/epx CERTIFICATE OF INSURANCE THIS IS TO CERTIFY THAT Haegelin Construction Co., Inc.is, at the date of this certificate, insured by this company with respect to the business operations hereinafter described, for the types of insurance and in accordance with the provisions of the standard policies used by this company, and further hereinafter described. Exceptions to standard policies are noted on the reverse side hereof. EXPIRATION DATE WC113339042 05/16/93 05/16/94 TPP90027237 -1 05/16/93 PBD -7 Date: December 6, 1993 Water and Wastewater System Description of Work Improvements for Dell Center Boulevard LIMITS OF LIABILITY Statutory, State of Texas, $ 500, 000. Employer's Liability Bodily Injury 05/16/94 $ /person $ /person $2,000,000 General Aggregate $1,000,000 Each Occurrence $1,000,000 Products Completed Operations Agg Property Damage $ /accident $ aggregate Bodily Injury $ /person $ /accident Property Damage $ /accident $ aggregate .74 Certificate of Insurance (continued) Comprehensive Automobile Liability Owned Vehicles Hired Vehicles Non -owned Vehicles Includes Contractual Liability Contractual Liability BUA400272382 05/16/93 05/16/94 Bodily Injury $ /person $ /accident Property Damage $ /accident $1,000,000 Combined Single Limit - Bodily Injury and Property Damage The above policies either in the body thereof or by appropriate endorsement provide that they may not be changed or canceled by the insurer in less than thirty (30) days after the insured has received written notice of such change or cancellation. The Certificate of Insurance neither affirmatively or negatively amends extends, or alters the coverage afforded by policy or policies indicated by this certificate. portbid.m t/.px Transcontinental Insurance Company Name of Insurer By: O . 7� E. Peter Pincoffs Title: A�nY Address: 101 West 6th Street, #350 PBD -8 Austin, Texas 78701 (512) 478 -5631 MAINTENANCE BOND BOND NUMBER KNOW ALL MEN BY THESE PRESENTS, That we, AMOUNT (hereinafter called the "Principal ") as Principal, and the a Corporation duly organized under the laws of the State of and duly licensed to transact business in the State of (hereinafter called the "Surety"), as Surety, are held and firmly bound unto THE CITY OF ROUND ROCK, TEXAS (hereinafter called the "Obligee "), in the sum of dollars ($ ) for the payment of which sum well and truly to be made, we, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly, by these presents. Sealed with our seals and dated this day of , A.D. nineteen hundred and WHEREAS, the said Principal has heretofore entered into a contract with Dated ,19 , for construction of WHEREAS, the said Principal is required to guarantee the construction of all improvements installed under said contract, against defects in materials or workmanship, which may develop during the period of year(s) from the date of acceptance of the project above described, by Owner: The City of Round Rock, Texas NOW, THEREFORE, THE CONDITIONS OF THE OBLIGATIONS IS SUCH, that if said Principal shall faithfully carry out and perform the said guarantee, and shall, on due notice, repair and make good at its own expense any and all defects in materials or workmanship in the said work which may develop during the period of year(s) from the date of acceptance of the project above described, by Owner: The City of Round Rock, Texas po.tbid.mu/.{roc PBD -9 MAINTENANCE BOND (continued) OR shall pay over, make good and reimburse to the said Obligee all loss and damage which said Obligee may sustain by reason of failure or default of said Principal so to do, then this obligation shall be null and void; otherwise shall remain in full force and effect. Principal Surety By By poubid.mNgKc PBD -10 4.0 GENERAL CONDITIONS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Contents 1. Definition of Terms 1.01 - Owner, Contractor and Engineer 1.02 - Contract Documents 1.03 - Subcontractor 1.04 - Sub - Subcontractor 1.05 - Written Notice 1.06 - Work 1.07 - Extra Work 1.08 - Working Day 1.09 - Calendar Day 1.10 - Substantially Completed General Conditions of Agreement 2. Responsibilities of the Engineer and the Contractor 2.01 - Owner - Engineer Relationship 2.02 - Professional Inspection by Engineer 2.03 - Payments for Work 2.04 - Initial Determinations 2.05 - Objections 2.06 - Lines and Grades 2.07 - Contractor's Duty and Superintendence 2.08 - Contractor's Understanding 2.09 - Character of Workers 2.10 - Contractor's Buildings 2.11 - Sanitation 2.12 - Shop Drawings 2.13 - Preliminary Approval 2.14 - Defects and Their Remedies 2.15 - Changes and Alterations 2.16 - Inspectors yrncood.ovdspec GC -1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3. General Obligations and Responsibilities 3.01 - Keeping of Plans and Specifications Accessible 3.02 - Ownership of Drawings 3.03 - Adequacy of Design 3.04 - Right of Entry 3.05 - Collateral Contracts 3.06 - Discrepancies and Omissions 3.07 - Equipment, Materials and Construction Plant 3.08 - Damages 3.09 - Protection Against Accident to Employees and the Public 3.10 - Performance and Payment Bonds 3.11 - Losses from Natural Causes 3.12 - Protection of Adjoining Property 3.13 - Protection Against Claims of Subcontractors, etc. 3.14 - Protection Against Royalties or Patented Invention 3.15 - Laws and Ordinances 3.16 - Assignment and Subletting 3.17 - Indemnification 3.18 - Insurance 3.19 - Final Clean-Up 3.20 - Guarantee Against Defective Work 3.21 - Testing of Materials 3.22 - Wage Rates 4. Prosecution and Progress 4.01 - Time and Order of Completion 4.02 - Extension of Time 4.03 - Hindrances and Delays 5. Measurement and Payment 5.01 - Quantities and Measurements 5.02 - Estimated Quantities 5.03 - Price of Work 5.04 - Partial Payments 5.05 - Use of Completed Portions 5.06 - Final Completion and Acceptance 5.07 - Final Payment 5.08 - Payments Withheld 5.09 - Delayed Payments gc o d mwp GC -2 6. Extra Work and Claims 6.01 Change Orders 6.02 Minor Changes 6.03 Extra Work 6.04 Time of Filing Claims 6.05 Continuing Performance 6.06 Arbitration 7. Abandonment of Contract 7.01 Abandonment by Contractor 7.02 Abandonment by Owner 8. Subcontractors 8.01 Award of Subcontracts for Portions of Work 8.02 Subcontractual Relations 8.03 Payments to Subcontractors 9. Separate Contracts 9.01 Owner's Right to Award Separate Contracts 9.02 Mutual Responsibility of Contractors 9.03 Cutting and Patching Under Separate contracts 10. Protection of Persons and Property 10.01 Safety Precautions and Programs 10.02 Safety of Persons and Property 10.03 Location and Protection of Utilities geaccod.mWryee GC -3 1 1 General Conditions of Agreement 1 1. Definition of Terms 1 1.01 Owner, Contractor and Engineer I The Owner, the Contractor and the Engineer and those persons or organization identified as such in the Agreement and are referred to throughout the contract Documents as if singular in number and masculine in gender. The term Engineer means the Engineer or I his duly authorized representative. The Engineer shall be understood to be the Engineer of the Owner, and nothing contained in the Contract Documents shall create any contractual or agency relationship between the Engineer and the Contractor. 1 1.02 Contract Documents I The Contract Documents shall consist of the Notice to Contractors, Instructions to Bidders, Proposal, Signed Agreement, Performance and Payment Bonds (when required), Special Bonds (when required), General Conditions of the Agreement, Construction I Specifications, Plans and all modifications thereof incorporated in any of documents before the execution of the agreement. I The Contract Documents are complementary, and what is called for by any one shall be as binding as if called for by all. In case of conflict between any of Contract documents, priority of interpretation shall be in the following order: Signed Agreement, Performance 1 and Payment Bonds, Special Bonds (if any), Proposal, Special Conditions of Agreement, Notice to Contractors, Technical Specifications, Plans, and General Conditions of I Agreement. 1.03 Subcontractor 1 The term Subcontractor, as employed herein, includes only those having a direct contract with the Contractor and it includes one who furnishes material worked to special design I according to the plans or specifications of this work, but does not include one who merely furnishes material not so worked. 1 1.04 Sub- subcontractor The term Sub - Subcontractor means one who has a direct or indirect contract with a sub- ' contractor to perform any of the work at the site and includes one who furnishes material worked to a special design according to the plans or specifications of this work, but does not include one who merely furnishes material not so worked. 1 1 geseced.ma. GC-4 1 1 1.05 Written Notice ' Written notice shall be deemed to have been duly served if delivered in person to the individual or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered mail to the last business address known to him who gives the notice. 1 1.06 Work ' The Contractor shall provide and pay for all materials, machinery, equipment, tools, superintendence, labor, services, insurance, and all water, light, power, fuel, transportation and other facilities necessary for the execution and completion of the work covered by the contract documents. Unless otherwise specified, all materials shall be new and both workmanship and materials shall be of a good quality. The Contractor shall, if required, furnish satisfactory evidence as to the kind and quality of materials. 1 Materials or work described in words which so applied have a well known technical or trade meaning shall be held to refer to such recognized standards. ' 1.07 Extra Work The term "Extra Work" as used in this contract shall be understood to mean and include all work that may be required by the Engineer or Owner to be done by the Contractor to accomplish any change, alteration or addition to the work shown upon the plans, or reasonably implied by the specifications, and not covered by the Contractor's Proposal, except as provided under "Changes and Alteration," herein. 1.08 Working Day A "Working Day" is defined as any day not including Saturdays, Sundays or any legal holidays, in which weather or other conditions, not under the control of the Contractor, will permit construction of the principal units of the work for a period of not less than seven (7) hours between 7:00 a.m. and 6:00 p.m. 1 1.09 Calendar Day 1 "Calendar Day" is any day of the week or month, no days being excepted. 1.10 Substantially Completed ' By the term "substantially completed" is meant that the structure has been made suitable for use or occupancy or the facility is in condition to serve its intended purpose, but still may require minor miscellaneous work and adjustment. 1 g aim. GC -5 1 1 2. Responsibilities of the Engineer and the Contractor 2.01 Owner- Engineer Relationship The Engineer will be the Owner's representative during construction. The duties, 1 responsibilities and limitations of authority of the Engineer as the Owner's representative during construction are as set forth in the Contract Documents and shall not be extended or limited without written consent of the Owner and Engineer. The Engineer will advise and consult with the Owner, and all of Owner's instructions to the Contractor shall be issued through the Engineer. 1 2.02 Professional Inspection by Engineer ' The Engineer shall make periodic visits to the site to familiarize himself generally with the progress of the executed work and to determine if such work generally meets the essential performance and design features and the technical and functional engineering ' requirements of the Contract Documents; provided and except, however, that the Engineer shall not be responsible for making any detailed, exhaustive, comprehensive or continuous on -site inspection of the quality or quantity of the work or be in any way ' responsible, directly or indirectly, for the construction means, methods, techniques, sequences, quality, procedures, programs, safety precautions or lack of same incident thereto or in connection therewith. Notwithstanding any other provision of this ' agreement or any other Contract Document, the Engineer shall not be in any way responsible or liable for any acts, errors, omissions or negligence of the Contractor, any Subcontractor or any of the Contractor's or Subcontractor's agents, servants or ' employees or any other person, firm or corporation performing or attempting to perform any of the work. ' 2.03 Payments for Work The Engineer shall review Contractor's applications for payment and supporting data, ' determine the amount owed to the Contractor and recommend, in writing, payment to Contractor in such amounts; such recommendation of payment to Contractor constitutes a representation to the Owner of Engineer's professional judgement that the work has progressed to the point indicated to the best of his knowledge, information and belief, but such recommendation of an application for payment to Contractor shall not be 1 deemed as a representation by Engineer that Engineer has made any examination to determine how or for what purpose Contractor has used the moneys paid on account of the Contract price. zeocand.m,u. GC -6 2.04 Initial Determinations The Engineer initially shall determine all claims, disputes and other matters in question between the Contractor and the Owner relating to the execution or progress of the work or the interpretation of the Contract Documents and the Engineer's decision shall be rendered in writing within a reasonable time, which shall not be construed to be less than ten (10) days. Appeal to arbitration upon mutual agreement may be taken as if his decision had been rendered against the party appealing. 2.05 Objections gencoad romc In the event the Engineer renders any decision which, in the opinion of either party hereto, is not in accordance with the meaning and intent of this contract, either party may file with the Engineer within thirty (30) days his written objection to the decision, and by such action may reserve the right to submit the question so raised to arbitration as hereinafter provided. 2.06 Lines and Grades Unless otherwise specified, all lines and grades shall be furnished by the Engineer or his representative. Whenever necessary, construction work shall be suspended to permit performance of this work, but such suspension will be as brief as practicable and the Contractor shall be allowed no extra compensation therefor. The contractor shall give the Engineer ample notice of the time and place where lines and grades will be needed. All stakes, marks, etc., shall be carefully preserved by the Contractor, and in case of careless destruction or removal by him or his employees, such stakes, marks, etc., shall be replaced at the Contractor's expense. 2.07 Contractor's Duty and Superintendence The Contractor shall give adequate attention to the faithful prosecution and completion of this contract and shall keep on the work, during its progress, a competent English - speaking superintendent and any necessary assistants to supervise and direct the work. The superintendent shall represent the Contractor in his absence and all directions given to him shall be as binding as if given to the Contractor. The Contractor is and at all times shall remain an independent contractor, solely responsible for the manner and method of completing his work under this contract, with full power and authority to select the means, method and manner of performing such work, so long as such methods do not adversely affect the completed improvements, the Owner and Engineer being interested only in the result obtained and conformity of such completed improvements to the plans, specifications and contract. Likewise, the Contractor shall be solely responsible for the safety of himself, his GC -7 employees and other persons, as well as for the protection and safety of the improvements being erected and the property of himself or any other person, as a result of his operations hereunder. Engineering construction drawings and specifications as well as any additional information concerning the work to be performed passing from or through the Engineer shall not be interpreted as requiring or allowing Contractor to deviate from the plans and specifications, the intent of such drawings, specifications and any other such information being to define with specificity the agreement of the parties as to the work the Contractor is to perform. Contractor shall be fully and completely liable, at his own expense, for design, construction, installation and use, or non -use of all items and methods incident to performance of the contract, and for all loss, damage or injury incident thereto, either to person or property, including, without limitation, the adequacy of all temporary supports, shoring, bracing, scaffolding, machinery or equipment, safety precautions or devices, and similar items or devices used by him during construction. Any review of work in process, or any visit or observation during construction, or any clarification of plans and specifications, by the Engineer or Owner, or any agent, employee, or representative of either of them, whether through personal observation on the project site or by means of approval of shop drawings for temporary construction or construction processes, or by other means or method, is agreed by the Contractor to be for the purpose of observing the extent and nature of work completed or being performed, as measured against the drawings and specifications constituting the contract, or for the purpose of enabling Contractor to more fully understand the plans and specifications so that the completed construction work will conform thereto, and shall in no way relieve the Contractor from full and complete responsibility for the proper performance of his work on the project, including but not limited to the propriety of means and methods of the Contractor in performing said contract, and the adequacy of any designs, plans or other facilities for accomplishing such performance. Deviation by the Contractor from plans and specifications that may have been in evidence during any such visitation or observation by the Engineer, or any of his representatives, whether called to the contractor's attention or not shall in no way relieve Contractor from his responsibility to complete all work in accordance with said plans and specifications. 2.08 Contractor's Understanding geeemd.mitlryee It is understood and agreed that the Contractor has, by careful examination, satisfied himself as to the nature and location of the work, the conformation of the ground, the character, quality and quantity of the materials to be encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the work, the general and local conditions, and all other matters which can in any way effect the work under this contract. The Contractor agrees that he will make no claim against the Owner or the Engineer if, in the prosecution of the work, he finds that the actual site or subsurface conditions encountered do not conform to those indicated by excavation, test excavation, test procedures, borings, explorations or other subsurface excavations. No GC -8 verbal agreement or conversation with any officer, agent or employee of the Owner or Engineer either before or after the execution of this contract, shall affect or modify any of the terms or obligations herein contained. 2.09 Character of Workers The Contractor agrees to employ only orderly and competent workers, skillful in the performance of the type of work required under this contract, to do the work; and agrees that whenever the Engineer shall inform him in writing that any workers on the work are, in his opinion, incompetent, unfaithful or disorderly, or refuse instructions from the Engineer in the absence of the Superintendent, such worker shall be discharged from the work and shall not again be employed on the work without the Engineer's written consent. No illegal alien may be employed by any Contractor for work on this project, and a penalty of $500.00 per day will be assessed for each day and for each illegal alien who works for the Contractor at this project. 2.10 Contractor's Buildings ewecod.mat/wee The building of structures for housing workers, or the erection of tents or other forms of protection, will be permitted only at such places as the Engineer shall direct, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a manner satisfactory to the Engineer. 2.11 Sanitation Necessary sanitary conveniences for the use of laborers on the work, properly secluded from public observation, shall be constructed and maintained by the Contractor in such manner and at such points as shall be approved by the Engineer, and their use shall be strictly enforced. 2.12 Shop Drawings The Contractor shall submit to the Engineer, with such promptness as to cause no delay in his own work or in that of any other Contractor, four (4) checked copies, unless otherwise specified, of all shop and/or setting drawings and schedules required for the work of the various trades, and the Engineer shall pass upon them with reasonable promptness, making desired corrections. The Contractor shall make any corrections required by the Engineer, file with him two (2) corrected copies and furnish such other copies as may be needed. The Engineer's review of such drawings or schedules shall not relieve the Contractor from responsibility for deviations from drawings or specifications, unless he has in writing called the Engineer's attention to such deviations at the time of submission, nor shall it relieve him from responsibility for errors of any sort in shop drawings or schedules. It shall be the Contractor's responsibility to fully and completely review all shop drawings to ascertain their effect on his ability to perform GC -9 gelaccad.cutivet the required contract work in accordance with the plans and specifications and within the contract time. Such review by the Engineer shall be for the sole purpose of determining the general conformity of said shop drawings or schedules to result in finished improvements in conformity with the plans and specifications, and shall not relieve the Contractor of his duty as an independent contractor as previously set forth, it being expressly understood and agreed that the Engineer does not assume any duty to pass upon the propriety or adequacy of such drawings or schedules, or any means or methods reflected thereby, in relation to the safety of either person or property during Contractor's performance hereunder. 2.13 Preliminary Approval The Engineer shall not have the power to waive the obligations of this contract for the furnishing by the Contractor of good material, and of his performing good work as herein described, and in full accordance with the plans and specifications. No failure or omission of the Engineer to discover, object to or condemn any defective work or material shall release the Contractor from the obligations to fully and properly perform the contract, including without limitations, the obligation to at once tear out, remove and properly replace the same at any time prior to final acceptance upon the discovery of said defective work or material; provided, however, that the Engineer shall, upon request of the Contractor, inspect and accept or reject any material furnished, and in event the material has been once accepted by the Engineer, such acceptance shall be binding on the Owner, unless it can be clearly shown that such material furnished does not meet the specifications for this work. Any questioned work may be ordered taken up or removed for re- examination, by the Engineer, prior to final acceptance, and if found not in accordance with the plans and /or specifications for said work, all expense of removing, re- examination and replacement shall be borne by the Contractor, otherwise the expense thus incurred shall be allowed as Extra Work, and shall be paid for by the Owner; provided that, where inspection or approval is specifically required by the specifications prior to performance of certain work, should the Contractor proceed with such work without requesting prior inspection or approval he shall bear all expense of taking up, removing, and replacing this work if so directed by the Engineer. 2.14 Defects and Their Remedies It is further agreed that if the work or any part thereof, or any material brought on the site of the work for use in the work or selected for the same, shall be deemed by the Engineer as unsuitable or not in conformity with the plans, specifications, or the intent thereof, the Contractor shall after receipt of written notice thereof from the Engineer, GC -10 forthwith remove such material and rebuild or otherwise remedy such work so that it shall be in full accordance with this contract. 2.15 Changes and Alterations Ymemd.wuWa The Contractor further agrees that the Owner may make such changes and alterations as the Owner may see fit, in the line, grade, form, dimensions, plans or materials for the work herein contemplated, or any part thereof, either before or after the beginning of the construction, without affecting the validity of this contract and the accompanying Performance and Payment Bonds. If such changes or alterations diminish the quantity of the work to be done, they shall not constitute the basis for a claim for damages, or anticipated profits on the work that may be dispensed with, except as provided for unit price items under Section 5 "Measurement and Payment ". If the amount of work is increased, and the work can fairly be classified under the specifications, such increase shall be paid for according to the quantity actually done and at the unit price, if any, established for such work under this contract, except as provided for unit price items under Section 5 "Measurement and Payment "; otherwise, such additional work shall be paid for as provided under Extra Work. In case the Owner shall make such changes or alterations as shall make useless any work already done or material already furnished or used in said work, then the Owner shall recompense the Contractor for any material or labor so used, and for any actual loss occasioned by such change, due to actual expense incurred in preparation for the work as originally planned. 2.16 Inspectors The Engineer may provide one (or more) field inspectors at the work site for the limited purpose of observing the work in progress and reporting back to the Engineer on the extent, nature, manner and performance of the work so that the Engineer may more effectively perform his duties hereunder. Such inspectors may also communicate between Engineer and Contractor their respective reports, opinions, questions, answers and clarifications concerning the plans, specifications and work but shall not be deemed the agent of the Contractor for all purposes in communicating such matters. Such inspector may confer with the Contractor or Contractor's superintendent concerning the prosecution of the work and its conformity with the plans and specifications but shall never be, in whole or part, responsible for, charged with, nor shall he assume, any authority or responsibility for the means, methods or manner of completing the work or of the superintendence of the work or of the Contractor's employees. It is expressly understood and agreed that any such inspector is not authorized by the Engineer or Owner to independently act for either or answer on behalf of either, any inquiries of the Contractor concerning the plans, specifications or work. No inspector's opinion; advice; interpretation of the plans or specifications of this contract; apparent or express approval of the means, methods or manner of Contractor's performance of work in progress or GC -11 completed; or discovery or failure to discover or object to defective work of materials shall release Contractor from his duty to complete all work in strict accordance with the plans and specifications or stop the Owner or Engineer from requiring that all work be fully and properly performed including, if necessary, removal of defective or otherwise unacceptable work and the re -doing of such work. 3. General Obligations and Responsibilities 3.01 Keeping of Plans and Specifications Accessible The Engineer shall furnish the Contractor with an adequate and reasonable number of copies of all plans and specifications without expense to him and the Contractor shall keep one (1) copy of the same constantly accessible on the work, with the latest revisions noted thereon. 3.02 Ownership of Drawings All drawings, specifications and copies thereof furnished by the Engineer shall not be reused on other work, and, with the exception of the signed contract sets, are to be returned to him on request, at the completion of the work. All models are the property of the Owner. 3.03 Adequacy of Design It is understood that the Owner believes it has employed competent engineers and designers. It is therefore agreed that the Owner shall be responsible for the adequacy of the design, sufficiency of the Contract Documents, the safety of the structure and the practicability of the operations of the completed project; provided the Contractor has complied with the requirements of the said Contract Documents, all approved modifications thereof, and additions and alterations thereto approved in writing by the Owner. The burden of proof of such compliance shall be upon the Contractor to show that he has complied with the said requirements of the Contract Documents, approved modification thereof and all approved additions and alterations thereto. 3.04 Right of Entry The Owner reserves the right to enter the property or location of which the works herein contracted for are to be constructed or installed, by such agent or agents as he may elect, for the purpose of inspecting the work, or for the purpose of constructing or installing such collateral work as said Owner may desire. GC -12 1 3.05 Collateral Contracts The Owner agrees to provide by separate contract or otherwise, all labor and material essential to the completion of the work specifically excluded from this contract, in such manner as not to delay the progress of the work, or damage said Contractor, except where such delays are specifically mentioned elsewhere in the Contract Documents. The Owner will attempt to coordinate the collateral work of utility companies regulated by City franchises, but the City shall not be responsible for delays or other damages to the Contractor which may result from their acts or omissions. 3.06 Discrepancies and Omissions The Contractor shall provide written notice to the Engineer of any omissions or 1 discrepancies found in the contract. It is further agreed that it is the intent of this contract that all work must be done and all material must be furnished in accordance with the generally accepted practice for construction, and in the event of any discrepancies ' between the separate contract documents, the priority of interpretation defined under "Contract Documents" shall govern. In the event that there is still any doubt as to the meaning and intent of any portion of the contract, specifications or drawings, the ' Engineer shall define which is intended to apply to the work. 3.07 Equipment, Materials and Construction Plant The Contractor shall be responsible for the care, preservation, conservation, and protection of all materials, supplies, machinery, equipment, tools, apparatus, accessories, facilities, all means of construction, and any and all parts of the work, whether the Contractor has been paid, partially paid, or not paid for such work, until the entire work is completed and accepted. 1 3.08 Damages ' In the event the Contractor is damaged in the course of completion of the work by the act, neglect, omission, mistake or default of the Owner or Engineer, thereby causing loss to the Contractor, the Owner agrees that he will reimburse the Contractor for such loss. ' In the event the Owner is damaged in the course of the work by the act, negligence, omission, mistake or default of the Contractor, or should the Contractor unreasonably delay the progress of the work being done by others on the job so as to cause loss for which the Owner becomes liable, then the Contractor shall reimburse the Owner for such loss. 3.09 Protection Against Accident to Employees and the Public 1 The Contractor shall at all times exercise reasonable precautions for the safety of employees and others on or near the work and shall comply with all applicable provisions g cood.m.u,p« GC -13 geoeood.mal/pa of Federal, State, and Municipal safety laws and building and construction codes. All machinery and equipment and other physical hazards shall be guarded in accordance with the "Manual of Accident Prevention in Construction" of the Associated General Contractors of America except where incompatible with Federal, State, or Municipal laws or regulations. The Contractor shall provide such machinery guards, safe walkways, ladders, bridges, gangplanks, and other safety devices. The safety precautions actually taken and their adequacy shall be the sole responsibility of the Contractor, acting at his discretion as an independent contractor. In the event there is an accident involving injury to any individual on or near the work, the Contractor shall immediately notify the Owner and Engineer of the event and shall be responsible for recording the location of the event and the circumstances surrounding the event through photographs, interviewing witnesses, obtaining of medical reports and other documentation that defines the event. Copies of such documentation shall be provided to the Owner and the Engineer for their records. 3.10 Performance and Payment Bonds Unless otherwise specified, it is further agreed by the Parties to the Contract that the Contractor will execute separate performance and payment bonds, each in the sum of one hundred (100 %) percent of the total contract price, in standard forms for this purpose, guaranteeing faithful performance of the work and the fulfillment of any guarantee required, and further guaranteeing payment to all persons supplying labor and materials or furnishing him any equipment in the execution of the Contract. If the contract price is less that $50,000.00, a letter of credit may be furnished in lieu of a performance bond. It is agreed that the Contract shall not be in effect until such performance bond or letter of credit, and payment bond are furnished and approved by the owner. Unless otherwise specified, the cost of the premium for the performance bond or letter of credit, and payment bond shall be included in the price bid by the Contractor for the work under this Contract, and no extra payment for such bond or letter of credit will be made by the Owner. Unless otherwise approved in writing by the Owner, the surety company underwriting the bonds or letter of credit shall be acceptable according to the latest list of companies holding certificates of authority from the Secretary of the Treasury of the United States and shall be licensed to write such bonds or letters of credit in the State of Texas. 3.11 Losses from Natural Causes Unless otherwise specified, all loss or damage to the Contractor arising out of the nature of the work to be done, or from the action of the elements, or from any unforeseen circumstance in the prosecution of the same, or from unusual obstructions or difficulties which may be encountered in the prosecution of the work, shall be sustained and borne GC -14 Qeumd.matlpee by the Contractor at his own cost and expense. 3.12 Protection of Adjoining Property The said Contractor shall take proper means to protect the adjacent or adjoining property or properties in any way encountered, which might be injured or seriously affected by any process of construction to be undertaken under this Agreement, from any damage or injury by reason of said process of construction; and he shall be liable for any and all claims for such damage on account of his failure to fully protect all adjoining property. The Contractor agrees to indemnify, save and hold harmless the Owner and Engineer against any claim or claims for damages due to any injury to any adjacent or adjoining property, arising or growing out of the performance of the contract regardless of whether or not it is caused in part by a party indemnified hereunder, but any such indemnity shall not apply to any claim of any kind arising solely out of the existence or character of the work. 3.13 Protection Against Claims of Subcontractors, Laborers, Materialmen and Furnishers of Machinery, Equipment and Supplies The Contractor agrees that he will indemnify and save the Owner and Engineer harmless from all claims growing out the lawful demands of Subcontractors, laborers, workers, mechanics, materialmen and furnishers of machinery and parts thereof, equipment, power tools, and all supplies, including commissary, incurred in the furtherance of the performance of this contract. When so desired by the Owner, Contractor shall furnish satisfactory evidence that all obligations of the nature hereinabove designated have been paid, discharged or waived. If the Contractor fails to do so, then the Owner may at the option of the Contractor either pay directly any unpaid bills, of which the Owner has written notice, or withhold from the Contractor's unpaid compensation a sum of money deemed reasonably sufficient to liquidate any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been fully discharged, whereupon payments to the Contractor shall be resumed in full, in accordance with the terms of this contract, but in no event shall the provisions of this sentence be construed to impose any obligation upon the Owner by either the Contractor or his Surety. 3.14 Protection Against Royalties or Patented Invention The Contractor shall pay all royalties and license fees, and shall provide for the use of any design, device, material or process covered by letter patent or copyright by suitable legal agreement with the patentee or owner. The contractor shall defend all suits or claims for infringement of any patent or copyright rights and shall indemnify and save the Owner and Engineer harmless from any loss on account thereof, except that the Owner shall defend all such suits and claims and shall be responsible for all such loss when a particular design, device, material or process or the product of a particular manufacturer or manufacturers is specified or required by the Owner; provided, however, GC -15 if choice of alternate design, device, material or process is allowed to the Contractor, then Contractor shall indemnify and save Owner harmless form any loss on account thereof. If the material or process specified or required by the Owner is known by the Contractor to be an infringement, the Contractor shall be responsible for such loss unless he promptly gives such information to the Owner. 3.15 Laws and Ordinances The Contractor shall at all times observe and comply with all Federal, State and local laws, ordinance and regulations, which in any manner affect the contract or the work, and shall indemnify and save harmless the Owner and Engineer against any claim arising from the violation of any such laws, ordinances, and regulations whether by the Contractor or his employees, except where such violations are called for by the provisions of the Contract Documents. If the Contractor observes that the plans and specifications are at variance therewith, he shall promptly notify the Engineer in writing, and any necessary changes shall be prepared as provided in the contract for changes in the work. If the Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, he shall bear all costs arising therefrom. In case the Owner is a body politic and corporate, the law from which it derives its powers, insofar as the same regulates the objects for which, or the manner in which, or the conditions under which the Owner may enter into contract, shall be controlling, and shall be considered as part of this contract, to the same effect as though embodied herein. 3.16 Assignment and Subletting The Contractor further agrees that he will retain personal control and will give his personal attention to the fulfillment of this contract and that he will not assign by Power of Attorney, or otherwise, or sublet said contract without the written consent of the Engineer, and that no part or feature of the work will be sublet to anyone objectionable to the Engineer or the Owner. The Contractor further agrees that the subletting of any portion or feature of the work, or materials required in the performance of this contract, shall not relieve the Contractor from his full obligations to the Owner, as provided by this Agreement. 3.17 Indemnification The Contractor shall defend, indemnify and hold harmless the Owner and the Engineer and their respective officers, agents and employees, from and against all damages, claims, losses, demands, suits, judgements and costs, including reasonable attorneys' fees and expenses, arising out of or resulting from the performance of the work, provided that any such damages, claim, loss, demand, suit, judgment, cost or expense: GC -16 ;eoeand.matirycc 1. Is attributable to bodily injury, sickness, disease or death to any person including Contractor's employees and any Subcontractor's employees and any Sub - Subcontractor's employees or to injury to or destruction of tangible property including Contractor's property (other than the work itself) and the property of any Subcontractor of Sub - Subcontractor including the loss of use resulting therefrom; and, 2. Is caused in whole or in part by any intentional or negligent act or omission of the Contractor, any Subcontractor, any Sub - subcontractor or anyone directly or indirectly employed by any one of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder. The obligation of the Contractor under this Paragraph shall not extend to the liability of the Engineer, his agents or employees arising out of the preparation of maps, plans, reports, surveys, Change Orders, designs or specifications, or the approval of maps, plans, reports, surveys, Change Orders, designs or specifications or the issuance of or the failure to give directions or instructions by the Engineer, his agents or employees, provided such is the sole cause of the injury or damage. In any and all claims against the Owner or the Engineer or any of their agents or employees by any employee of the Contractor, any Subcontractor, any Sub - Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligation under Paragraph 3.17 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any Subcontractor or Sub - Subcontractor under workmen's compensation acts, disability benefit acts or other employee benefit acts. 3.18 Insurance The Contractor shall vary insurance as follows for the duration of this contract. A. Statutory Workmen's Compensation. B. Comprehensive General Liability Insurance with minimum Bodily Injury limits of $300,000 for each occurrence including like coverage for acts and omissions of Subcontractors and contractual liability coverage. C. Property Damage Insurance with minimum limits of $50,000 for each occurrence including like coverage for acts and omissions of Subcontractors and contractual liability coverage. GC -17 amccad.mu/yKe D. Automobile Liability Insurance for all owned, non - owned, and hired vehicles with minimum limits for Bodily Injury of $100,000 for each person and $300,000 for each occurrence and Property Damage minimum limits of $50,000 for each occurrence. Contractor shall require subcontractors to provide Automobile Liability Insurance with same minimum limits. The Contractor shall not commence work at the site under this contract until he has obtained all required insurance and until such insurance has been approved by the Owner and Engineer. The Contractor shall not allow any Subcontractors to commence work until all insurance required has been obtained and approved. Approval of the insurance by the Owner and Engineer shall not relieve or decrease the liability of the contractor hereunder. The required insurance must be written by a company licensed to do business in Texas at the time the policy is issued. In addition, the company must be acceptable to the Owner and all insurance (other than Workmen's compensation) shall be endorsed to include the Owner as an additional insured thereunder. The Contractor shall not cause any insurance to be cancelled nor permit any insurance to lapse. All insurance certificates shall include a clause to the effect that the policy shall not be cancelled or reduced, restricted or limited until ten (10) days after the Owner has received written notice as evidenced by return receipt of registered or certified letter. Certificates of Insurance shall contain transcripts from the proper office of the insurer, evidencing in particular those insured, the extent of the insurance, the location and the operations to which the insurance applies, the expiration date, and the above mentioned notice of cancellation clause. 3.19 Final Clean -up Upon the completion of the work and before acceptance and final payment will be made, the Contractor shall clean and remove from the site of the work, surplus and discarded materials, temporary structures and debris of every kind. He shall leave the site of the work in a neat and orderly condition at least equal to that which originally existed. Surplus and waste materials removed from the site of the work shall be disposed of at locations satisfactory to the Engineer. In the event Contractor fails or refuses to clean and remove surplus materials and debris as above provided, the Owner or Engineer may do so, or cause same to be done, at the Contractor's expense and the reasonable cost thereof shall be deducted from the final payment. 3.20 Guarantee Against Defective Work The contractor warrants the materials and workmanship and that the work is in GC -18 3.21 Testing of Materials gcncccd.m,uryu conformance with the plans and specifications included in this contract for a period of one year from the date of acceptance of the project. Said warranty binds the contractor to correct any work that does not conform with such plans and specifications or any defects in workmanship or materials furnished under this con tract which may be discovered within the said one year period. The Contractor shall at his own expense correct such defect within thirty days after receiving written notice of such defect from the Owner or Engineer by repairing same to the condition called for in the contract documents and plans and specifications. Should the Contractor fail or refuse to repair such defect within the said thirty day period or to provide acceptable assurances that such repair work will be completed within a reasonable time thereafter, the Owner may repair or cause to be repaired any such defect at the Contractor's expense. Unless otherwise specified, testing of all materials to be incorporated into the project will be as directed by the Engineer at the expense of the Owner. All retesting for work rejected on the basis of test results will be at the expense of the Contractor and the extent of the retesting shall be determined by the Engineer. The Engineer may require additional testing for failing tests and may require two passing retests before acceptance will be made by the Owner. The testing laboratory will be designated by the Owner. All materials to be incorporated into the project must meet the requirements of these specifications. For manufactured materials such as reinforcing steel, expansion joint materials, concrete pipe, cement, miscellaneous steel, cast iron materials, etc. , the Contractor will be required to furnish a manufacturer's certificate stating that the material meets the requirements specified for this project. 3.22 Wage Rates Contractors are required to pay the prevailing wage rates to laborers, workmen and mechanics employed on behalf of the city engaged in the construction of public works. The wage rate for these jobs shall be the general prevailing wage rates for work of a similar character. This applies to contractors and subcontractors. The contractor and subcontractors shall keep and make available records of workers and their wages. Prevailing wage rates are published by the U. S. Department of Labor, Bureau of Labor Statistics, Southwestern Division and the Texas Employment Commission for the Austin Job Bank Area. The wage rate shall not be less than the minimum wage rates set by the U. S. Department of Labor, Employment Standards Administration, Wage and Hour Division. There is penalty of $10.00 per worker per day or portion of a day that the prevailing wage rate is not paid by the contractor or any subcontractor. GC -19 1 1 4. Prosecution and Progress 4.01 Time and Order of Completion It is the meaning and intent of this contract, unless otherwise herein specifically 1 provided, that the Contractor shall be allowed to prosecute his work at such times and seasons, in such order of precedence, and in such manner as shall be most conducive to economy of construction; provided, however, that the order and the time of prosecution shall be such that the work shall be substantially completed as a whole and in part, in accordance with this contract, the plans and specifications, and within the time of completion designated in the Proposal: provided, also, that when the Owner is having other work done, either by contract or by his own force, the Engineer may direct the time and manner of constructing the work done under this contract, so that conflict will be avoided and the construction of the various works being done for the Owner shall be harmonized. ' The Contractor shall submit, at such times as may reasonably be requested by the Engineer, schedules which shall show the order in which the Contractor proposes to carry on the Work, with dates at which the Contractor will start the several parts of the ' work, and estimated dates of completion of the several parts. 4.02 Extension of Time ' Should the Contractor be delayed in the completion of the work by any act or neglect of the Owner or Engineer, or of any employee of either, or by other contractors employed ' by the Owner, or by changes ordered in the work, or by strikes, lockouts, fires, and unusual delays by common carriers, or unavoidable cause or causes beyond the Contractor's control, or by any cause which the Engineer shall decide justifies the delay, then an extension of time shall be allowed for completing the work, sufficient to compensate for the delay, the amount of the extension to be determined by the Engineer, provided, however, that the Contractor shall give the Engineer prompt notice in writing of the cause of such delay. Adverse weather conditions will not be justification for extension of time on "Calendar Days" contracts. 4.03 Hindrances and Delays No claims shall be made by the Contractor for damages resulting from hindrances or 1 delays from any cause (except where the work is stopped by order of and for the convenience of the Owner) during the progress of any portion of the work embraced in ' this contract. In case said work shall be stopped by the act of the Owner, then such expense as in the judgment of the Engineer is caused by such stoppage of said work shall be paid by the Owner to the Contractor. 1 ecm.m.u.Q« GC -20 5. Measurement and Payment 5.01 Quantities and Measurements 5.02 Estimated Quantities gacad.mstl.pcc No extra or customary measurements of any kind will be allowed, but the actual measured and/or computed length, area, solid contents, number and weight only shall be considered, unless otherwise specifically provided. This agreement, including the specifications, plans and estimate, is intended to show clearly all work to be done and material to be furnished hereunder. Where the estimated quantities are shown for the various claccFs of work to be done and material to be furnished under this contract, they are approximate and are to be used only as a basis for estimating the probable cost of the work and for comparing the proposals offered for the work. It is understood and agreed that the actual amount of work to be done and material to be furnished under this contract may differ somewhat from these estimates, and that where the basis for payment under this contract is the unit price method, payment shall be for the actual amount of such work done and material furnished. Where payment is based on the unit price method, the Contractor agrees that he will make no claim for damages, anticipated profits or otherwise on account of any differences which may be found between the quantities of work actually done, the material actually furnished under this contract and the estimated quantities contemplated and contained in the proposal; provided, however, that in case the actual quantity of any major item should become as much as 20% more than, or 20% less than the estimated or contemplated quantity for such items, then either party to this Agreement, upon demand, shall be entitled to revised consideration upon the portion of the work above or below 20% of the estimated quantity. A "Major Item" shall be construed to be any individual bid item incurred in the proposal that has a total cost equal to or greater that five (5) percent of the total contract cost, computed on the basis of the proposal quantities and the contract unit prices. Any revised consideration is to be determined by agreement between the parties, otherwise by the terms of this Agreement, as provided under "Extra Work ". 5.03 Price of Work In consideration of the furnishing of all the necessary labor, equipment and material, and the completion of all work by the Contractor, and on the completion of all work and on the delivery of all material embraced in this Contract in full conformity with the specifications and stipulations herein contained, the Owner agrees to pay the Contractor the prices set forth in the Proposal hereto attached, which has been made a part of this GC -21 contract. The Contractor hereby agrees to receive such prices in full for furnishing all material and all labor required for the aforesaid work, also for all expense incurred by him, and for well and truly performing the same and the whole thereof in the manner and according to this Agreement. 5.04 Partial Payments ameu"d.m.Upx On or before the 1st day of each month, the Contractor shall submit to the Engineer a statement showing the total value of the work performed up to and including the 25th day of the preceding month. The statement shall also include the value of all sound materials delivered on the job site and to be included in the work and all partially completed work whether bid as a lump sum or a unit item which in the opinion of the Engineer is acceptable. The Engineer shall examine and approve or modify and approve such statement. The Owner shall then pay the Contractor on or before the 20th day of the current month the total amount of the approved statement, less 10 percent of the amount thereof, which 10 percent shall be retained until final payment, and further less all previous payments and all further sums that may by retained by the Owner under the terms of this Agreement. It is understood, however, that in case the whole work be near to completion and some unexpected and unusual delay occurs due to no fault or neglect on the part of the Contractor, and Owner may - upon written recommendation of the Engineer - pay a reasonable and equitable portion of the retained percentage to the Contractor; or the Contractor at the Owner's option, may be relieved of the obligation to fully complete the work and, thereupon, the Contractor shall receive payment of the balance due him under the contract subject only to the conditions stated under "Final Payment ". 5.05 Use of Completed Portions The Owner shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portions may not have expired but such taking possession and use shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents. If such prior use increases the cost of or delays the work, the Contractor shall be entitled to such extra compensation, or extension of time, or both, as the Engineer may determine. The Contractor shall notify the Engineer when, in the Contractor's opinion, the contract is "substantially completed" and when so notifying the Engineer, the Contractor shall furnish to the Engineer in writing a detailed list of unfinished work. The Engineer will review the Contractor's list of unfinished work and will add thereto such items as the Contractor has failed to include. The "substantial completion" of the structure or facility shall not excuse the Contractor from performing all of the work undertaken, whether of GC -22 a minor or major nature, and thereby completing the structure or facility in accordance with the Contract Documents. 5.06 Final Completion and Acceptance Within ten (10) days after the Contractor has given the Engineer written notice that the work has been completed, or substantially completed, the Engineer and the Owner shall inspect the work and within said time, if the work be found to be completed in accordance with the Contact Documents, the Engineer shall issue to the Owner and the Contractor his Certificate of Completion, and thereupon it shall be the duty of the Owner to issue a Certificate of Acceptance of the work to the Contractor or to advise the Contractor in writing of the reason for non - acceptance. 5.07 Final Payment Upon the issuance of the Certificate of Completion, the Engineer shall proceed to make final measurements and prepare final statement for the value of all work performed and materials furnished under the terms of the Agreement and shall certify same to the Owner, who shall pay to the Contractor on or before the 30th day, and before the 35th day, after the date of the Certificate of Completion, the balance due the Contractor under the terms of this contract; and said payment shall become due in any event upon said performance by the Contractor. Neither the Certificate of Acceptance nor the final payment, nor any provision in the Contract Documents, shall relieve the Contractor of the obligation for fulfillment of any warranty which may be required. 5.08 Payments Withheld geocood.mst/spcc The Owner may, on account of subsequently discovered evidence, withhold or nullify the whole or part of any certificate to such extent as may be necessary to protect himself from loss on account of: a) Defective work not remedied or other obligations hereunder not done. b) Claims filed or reasonable evidence indicating probable filing of claims. c) Failure of the Contractor to make payments properly to subcontractors or for material or labor. d) Damage to the Owner or another contractor's work, material or equipment. e) Reasonable doubt that the work can be completed for the unpaid balance of the contract amount. GC -23 f) Reasonable indication that the work will not completed within the contract time. g) Other causes affecting the performance of the contract. When the above grounds are removed or the Contractor provides a Surety Bond satisfactory to the Owner, which will protect the Owner in the amount withheld, payment shall be made for amounts withheld because of them. 5.09 Delayed Payments Should the Owner fail to make payment to the Contractor of the sum named in any partial or final statement, when payment is due, then the Owner shall pay to the Contractor, in addition to the sum shown as due by such statement, interest thereon at the rate of 6% per annum, unless otherwise specified, from date due as provided under 'partial payments' and final 'payments,' until fully paid, which shall fully liquidate any injury to the Contractor growing out of such delay in payment. It is expressly agreed that delay by the Owner in making payment to the Contractor of the sum named in any partial or final statement shall not constitute a breach of this contract on the part of the Owner nor an abandonment thereof nor shall it to any extent or for any time relieve the Contractor of his obligations to fully and completely perform hereunder. 6. Extra Work and Claims 6.01 Change Orders Without invalidating this Agreement, the Owner may, at any time or from time to time, order additions, deletions or revisions to the work; such changes will be authorized by Change Order to be prepared by the Engineer for execution by the Owner and the Contractor. The Change Order shall set forth the basis for any change in contract price, as hereinafter set forth for Extra Work, and any change in contract time which may result from the change. In the event the Contractor shall refuse to execute a Change Order which has been prepared by the Engineer and executed by the Owner, The Engineer may in writing instruct the Contractor to proceed with the work as set forth in the Change Order and the Contractor may make claim against the Owner for Extra Work involved therein, as hereinafter provided. 6.02 Minor Changes amcwd.mw,p« The Engineer may authorize minor changes in the work not inconsistent with the overall intent of the Contract Documents and not involving an increase in Contract Price. If the GC -24 Contractor believes that any minor change or alteration authorized by the Engineer involves Extra Work and entitles him to an increase in the Contract Price, the Contractor shall make written request to the Engineer for a written Field Order. In such case, the Contractor by copy of his communication to the Engineer or otherwise in writing shall advise the Owner of his request to the Engineer for a written Field Order and that work involved may result in an increase in the Contract Price. Any request by the Contractor for a change in Contract Price shall be made prior to beginning the work covered by the proposed change. 6.03 Extra Work sencand.aul/yea It is agreed that the basis of compensation to the Contractor for work either added or deleted by a Change Order or for which a claim for Extra Work is made shall be determined by the unit prices upon which this contract was bid to the extent such work can be fairly classified within the various work item descriptions and for work items that cannot be so classified by one or more of the following methods: Method (A) By agreed unit prices; or Method (B) By agreed lump sum; or Method (C) If neither Method (A) nor Method (B) be agreed upon before the Extra Work is commenced, then the Contractor shall be paid the "actual field cost" of the work, plus fifteen (15) percent. In the event said Extra Work be performed and paid for under Method (C), then the provisions of this paragraph shall apply and the "actual field cost" is hereby defined to include the cost to the Contractor of all workmen, such as foreman, timekeepers, mechanics and laborers, and materials, supplies, trucks, rentals on machinery and equipment, for the time actually employed or used on such Extra Work, plus actual equipment, for the time actually employed or used on such Extra Work, plus actual transportation charges necessarily incurred, together with all power, fuel, lubricants, water and similar operating expenses, also all necessary incidental expenses incurred directly on account of such Extra Work, including Social Security, Old Age Benefits and other payroll taxes, and, a rateable proportion of premiums on Performance and Payment Bonds and Maintenance Bonds, Public Liability and Property Damage and Workmen's GC -25 Compensation, and all other insurance as may be required by any law or ordinance, or directed by the Owner, or by them agreed to. The Engineer may direct the form in which accounts of the "actual field cost" shall be kept and the records of these accounts shall be made available to the Engineer. The Engineer or Owner may also specify in writing, before the work commences, the method of doing the work and the type and kind of machinery and equipment to be used; otherwise these matters shall be determined by the Contractor. Unless otherwise agreed upon, the prices for the use of machinery and equipment shall be determined by using 100 per cent, unless otherwise specified, of the latest schedule of Equipment Ownership Expense adopted by the Associated General Contractors of America. Where practicable the terms and prices for the use of machinery and equipment shall be incorporated in the Written Extra Work Order. The fifteen (15 %) percent of the "actual field cost" to be paid the Contractor shall cover and compensate him for his profit, overhead, general superintendence and field office expense, and all other elements of cost and expense not embraced within the "actual field cost" as herein defined, save that where the Contractor's Camp or Field Office must be maintained primarily on account of such Extra Work; then the cost to maintain and operate the same shall be included in the "actual field cost." No claim for Extra Work of any kind will be allowed unless ordered in writing by the Engineer. In case any orders or instructions, either oral or written, appear to the Contractor to involve Extra Work for which he should receive compensation or an adjustment in the construction time, he shall make written request to the Engineer for written order authorizing such Extra Work. Should a difference of opinion arise as to what does or does not constitute Extra Work, or as to the payment therefor, and the Engineer insists upon its performance, the Contractor shall proceed with the work after making written request for written order and shall keep an accurate account of the "actual field cost" thereof, as provided under Method (C). The Contractor will thereby preserve the right to submit the matter of payment to arbitration, as hereinbelow provided. 6.04 Time of Filing Claims geecmd.mWpee It is further agreed by both parties hereto that all questions of dispute or adjustment presented by the Contractor shall be in writing and filed with the Engineer within thirty (30) days after the Engineer has given any directions, order or instruction to which the Contractor desires to take exception. The Engineer shall reply within thirty (30) days to such written exceptions by the Contractor and render his final decision in writing. In case the Contractor should appeal from the Engineer's decision, any demand for arbitration shall be filed with the Engineer and the Owner in writing within ten (10) days after the date of delivery to Contractor of the Engineer's final decision. It is further agreed that final acceptance of the work by the Owner and the acceptance by the Contractor of the final payment shall be a bar to any claims by either party, except claims by Owner for defective work or enforcement of warranties and except as noted otherwise in the contract documents. GC -26 1 6.05 Continuing Performance The Contractor shall continue performance of the contract during all disputes or disagreements with the Owner. The production or delivery of goods, the furnishing of services and the construction of projects or facilities shall not be delayed, prejudiced or postponed pending resolution of any disputes or disagreements, except as the Owner may otherwise agree in writing. 6.06 Arbitration All questions of dispute under this Agreement shall be submitted to arbitration at the ' request of either party to the dispute. The parties may agree upon one arbiter, otherwise, there shall be three, one named in writing by each party, and the third chosen by the two arbiters so selected; or if the arbiters fail to select a third within ten (10) days, he shall be chosen by a District Judge serving the County in which the major portion of the project is located, unless otherwise specified. Should the party demanding arbitration fail to name an arbiter within ten (10) days of the demand, his right to arbitrate shall lapse, ' and the decision of the Engineer shall be final and binding on him. Should the other party fail to choose an arbiter within ten (10) days, the Engineer shall appoint such arbiter. Should either party refuse or neglect to supply the arbiters with any papers or ' information demanded in writing, the arbiters are empowered by both parties to take ex parte proceedings. The arbiters shall act with promptness. The decision of any two shall be binding on both parties to the contract. The decision of the arbiters upon any questions submitted to arbitration under this contract shall be a condition precedent to any right of legal action. The decision of the arbiter or arbiters may be filed in court to carry it into effect. The arbiters, if they deem the case demands it, are authorized to award the party whose contention is sustained, such sums as they deem proper for the time, expense and trouble incident to the appeal, and if the appeal was taken without reasonable cause, they may ' award damages for any delay occasioned thereby. The arbiters shall fix their own compensation unless otherwise provided by agreement, and shall assess the cost and charges of the arbitration upon either or both parties. The award of the arbiters must be made in writing. 1 7. Abandonment of Contract 7.01 Abandonment by Contractor In case the Contractor should abandon and fail or refuse to resume work within ten (10) days after written notification from the Owner, or the Engineer, or if the Contractor fails ' eeac m.u. GC -27 acxood.m t/ px to comply with the orders of the Engineer, when such orders are consistent with the Contract Documents, then, and in that case, where performance and payment bonds exist, the Sureties on these bonds shall be notified in writing and directed to complete the work, and a copy of said notice shall be delivered to the Contractor. After receiving said notice of abandonment the Contractor shall not remove from the work any machinery, equipment, tools, materials or supplies then on the job, but the same, together with any materials and equipment under contract for the work, may be held for use on the work by the Owner or the Surety on the performance bond, or another contractor in completion of the work; and the Contractor shall not receive any rental or credit therefor (except when used in connection with Extra Work, where credit shall be allowed as provided for under Section 6, Extra Work and Claims), it being understood that the use of such equipment and materials will ultimately reduce the cost to complete the work and be reflected in the final settlement. Where there is no performance bond provided or in case the Surety should fail to commence compliance with the notice for completion hereinbefore provided for, within ten (10) days after service of such notice, then the Owner may provide for completion of the work in either of the following elective manners: (1) The Owner may thereupon employ such force of men and use such machinery, equipment, tools, materials and supplies as said Owner may deem necessary to complete the work and charge the expense of such labor, machinery, equipment, tools, materials and supplies to said Contractor, and expense so charged shall be deducted and paid by the Owner out of such moneys as may be due, or that may thereafter at any time become due to the Contractor under and by virtue of this Agreement. In case such expense is less than the sum which would have been payable under this contract, if the same had been completed by the Contractor, then said Contractor shall receive the difference. In case such expense is greater than the sum which would have been payable under this contract, if the same had been completed by said Contractor, then the Contractor and/or his Surety shall pay the amount of such excess to the Owner, or (2) The Owner under competitive bids, taken after notice published as required by law, may let the contract for the completion of the work under substantially the same terms and conditions which are provided in this contract. In case there is any increase in cost to the Owner under the new contract as compared to what would have been the cost under this contract, such increase shall be charged to the Contractor and the Surety shall be and remain bound therefor. However, should the cost to complete any such contract prove to be less than would have been the cost to complete under this contract, the Contractor and /or his Surety shall be credited therewith. GC -28 When the work shall have been substantially completed the Contractor and his Surety shall be so notified and Certificates of Completion and Acceptance, as provided in Paragraph 5.06 hereinabove, shall be issued. A complete itemized statement of the contract accounts, certified to by the Engineer as being correct, shall then be prepared and delivered to the Contractor and his Surety, whereupon the Contractor and/or his Surety, or the Owner as the case may be, shall pay the balance due as reflected by said statement, within fifteen (15) days after the date of such Certificate of Completion. In the event the statement of accounts shows that the cost to complete the work is less than that which would have been the cost to the Owner had the work been completed by the Contractor under the terms of this contract; or when the Contractor and /or his Surety shall pay the balance shown to be due by them to the owner, then all machinery, equipment, tools, materials or supplies left on the site of the work shall be turned over to the Contractor and/or his Surety. Should the cost to complete the work exceed the contract price, and the Contractor and/or his Surety fail to pay the amount due the Owner within the time designated hereinabove, and there remains any machinery, equipment, tools, materials or supplies on the site of the work, notice thereof, together with an itemized list of such equipment and materials, shall be mailed to the Contractor and his Surety at the respective addresses designated in this contract, provided, however, that actual written notice given in any manner will satisfy this condition. After mailing, or other giving of such notice, such property shall be held at the risk of the Contractor and his Surety subject only to the duty of the Owner to exercise ordinary care to protect such property. After fifteen (15) days from the date of said notice the Owner may sell such machinery, equipment, tools, materials or supplies and apply the net sum derived from such sale to the credit of the Contractor and his Surety. Such sale may be made at either public or private sale, with or without notice, as the Owner may elect. The Owner shall release any machinery, equipment, tools, materials, or supplies, which remain on the work, and belong to persons other than the Contractor or his Surety, to their proper owners. The books on all operations provided herein shall be opened to the Contractor and his Surety. 7.02 Abandonment by Owner gmccod.msthca In case the Owner shall fail to comply with the terms of this contract, and should fail to comply with said terms within ten (10) days after written notification by the Contractor, then the Contractor may suspend or wholly abandon the work, and may remove therefrom all machinery, tools and equipment, and all materials on the site of work that have not been included in payments to the Contractor and have not been wrought into the work. And thereupon the Engineer shall make an estimate of the total amount earned by the Contractor, which estimate shall include the value of all work actually completed by said Contractor (at the prices stated in the attached proposal where unit prices are used), the value of all partially completed work at a fair and equitable price, and the amount of all Extra Work performed at the prices agreed upon, or provided for by the terms of this contract, and a reasonable sum to cover the cost of any provisions made by GC -29 the Contractor to carry the whole work to completion and which cannot be utilized. The Engineer shall then make a final statement of the balance due the Contractor by deducting from the above estimate all previous payments by the Owner and all other sums that may be retained by the Owner under the terms of this Agreement and shall certify same to the Owner who shall pay to the Contractor on or before thirty (30) days after the date of the notification by the Contractor the balance shown by said final statement as due the Contractor, under the terms of this Agreement. 8. Subcontractors 8.01 Award of Subcontracts for Portions of the Work pevcood.ouUrycc Unless otherwise specified in the Contract Documents or in the Instructions to Bidders, the Contractor, as soon as practicable after the award of the Contract, shall furnish to the Engineer in writing for acceptance by the Owner and the Engineer a list of the names of the Subcontractors proposed for the principal portions of the work. The Engineer shall promptly notify the Contractor in writing if either the Owner or the Engineer, after due investigation, has reasonable objection to any Subcontractor on such list and does not accept him. Failure of the Owner or Engineer to make objection promptly to any Subcontractor on the list shall constitute acceptance of such Subcontractor. The Contractor shall not contract with any Subcontractor or any person or organization (including those who are to furnish materials or equipment fabricated to a special design) proposed for portions of the work designated in the Contract Documents or in the Instructions to Bidders or, if none is so designated, with any Subcontractor proposed for the principal portions of the work who has been rejected by the Owner and the Engineer. The Contractor will not be required to contract with any Subcontractor or person or organization against whom he has a reasonable objection. If the Owner or Engineer refuses to accept any Subcontractor or person or organization on a list submitted by the Contractor in response to the requirements of the Contract Documents or the Instructions to Bidders, the Contractor shall submit an acceptable substitute and the Contract amount shall be increased or decreased by the difference in cost occasioned by such substitution and an appropriate change order shall be issued; however, no increase in the Contract amount shall be allowed for any such substitution unless the Contractor has acted promptly and responsively in submitting for acceptance any list or lists of names as required by the Contract Documents or the Instructions to Bidders. If the Owner or the Engineer requires a change of any proposed Subcontractor or person or organization previously accepted by them, the Contract amount shall be increased or decreased by the difference in cost occasioned by such change and an appropriate Change Order shall be issued. GC -30 The Contractor shall not make any substitution for any Subcontractor or person or organization who has been accepted by the Owner and the Engineer, unless the substitution is acceptable to the Owner and the Engineer. 8.02 Subcontractual Relations All work performed for the Contractor by a Subcontractor shall be pursuant to an appropriate written agreement between the Contractor and the Subcontractor (and where appropriate between Subcontractors and Sub - subcontractors) which shall contain provisions that: (1) preserve and protect the rights of the Owner and Engineer under the Contract with respect to the work to be performed under the subcontract so that the subcontracting thereof will not prejudice such rights; (2) require that such work be performed in accordance with the requirements of the Contract Documents; (3) require submission to the Contractor of the applications for payment under each subcontract to which the Contractor is a party, in reasonable time to enable the Contractor to apply for payment in accordance with this contract; (4) require that all claims for additional costs, extensions of time, damages for delays or otherwise with respect to subcontracted portions of the work shall be submitted to the Contractor (via any Subcontractor or Sub - subcontractor where appropriate) in sufficient time so that the Contractor may comply in the manner provided in the Contract Documents for like claims by the Contractor upon the Owner; (5) obligate each subcontractor specifically to consent to the provisions of this section. A copy of all such Subcontract Agreements shall be filed by the Contractor with the Engineer before the Subcontractor shall be allowed to commence work. 8.03 Payments to Subcontractors The Contractor shall pay each Subcontractor, upon receipt of payment from the Owner, an amount directly based upon the value of the work performed and allowed to the Contractor on account of such Subcontractor's work, less the percentage retained from payments to the Contractor. The Contractor shall also require each Subcontractor to make similar payments to his subcontractors. If the Engineer fails to approve a payment for any cause which is the fault of the Contractor and not the fault of a particular Subcontractor, the Contractor shall pay the Subcontractor on demand, made at any time after the Certificate for Payment should otherwise have been issued, for his work to the extent completed, less the retained GC -31 percentage. The Engineer may, on request and at his discretion, furnish to any Subcontractor, if practicable, information regarding percentages of completion certified to the Contractor on account of work done by such Subcontractors. Neither the Owner nor the Engineer shall have any obligation to pay or to see to the payment of any moneys to such Subcontractor except as may otherwise be required. 9. Separate Contracts 9.01 Owner's Right to Award Separate Contracts The Owner reserves the right to award other contracts in connection with other portions of the project under these or similar conditions of the Contract. When separate contracts are awarded for different portions of the Project, "The Contractor" in the contract documents in each case shall be the contractor who signs each separate contract. 9.02 Mutual Responsibility of Contractors Qencmd.mst/yx The Contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and equipment and the execution of their work, and shall properly connect and coordinate his work with theirs. If any part of the Contractor's work depends for proper execution or results upon the work of any other separate contractor, the Contractor shall inspect and promptly report to the Engineer any apparent discrepancies or defects in such work that render it unsuitable for such proper execution and results. Failure of the Contractor to so inspect and report shall constitute an acceptance of the other contractor's work as fit and proper to receive his Work, except as to defects which may develop in the other separate contractor's work after the execution of the Contractor's Work. Should the Contractor cause damage to the work or property of any separate contractor on the project, the Contractor shall, upon due notice, settle with such other contractor by agreement or arbitration, if he will so settle. If such separate contractor sues the Owner or initiates an arbitration proceeding on account of any damage alleged to have been so sustained, the Owner shall notify the Contractor who shall defend such proceedings at the Contractor's expense, and if any judgment or award against the Owner arises therefrom the Contractor shall pay or satisfy it and shall reimburse the Owner for all attorney's fees and court or arbitration costs which the Owner has incurred. GC -32 9.03 Cutting and Patching under Separate Contracts The Contractor shall be responsible for any cutting, fitting and patching that may be required to complete his work except as otherwise specifically provided in the Contract Documents. The Contractor shall not endanger any work of any other contractors by cutting, excavating or otherwise altering any work and shall not cut or alter the work of any other contractor except with the written consent of the Engineer. Any costs caused by defective or ill-timed work shall be borne by the party responsible therefor. 10. Protection of Persons and Property 10.01 Safety Precautions and Programs The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the work. 10.02 Safety of Persons and Property The Contractor shall take all reasonable precautions for the safety of, and shall provide all reasonable protection to prevent damage, injury, or loss to: erncood.msvgec (1) all employees on the work and all other persons who may be affected thereby: (2) all the work and all materials and equipment to be incorporated therein, whether in storage or off the site, under the care, custody or control of the Contractor or any of his Subcontractors or Sub - Subcontractors; and (3) other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, fences, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. The Contractor shall comply with all applicable laws, ordinances, rules, regulations and lawful orders of any public authority having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss. He shall erect and maintain, as required by existing conditions and progress of the work, all reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent utilities. When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of the work, the Contractor shall exercise the utmost care and shall carry on such activities under the supervision of properly qualified personnel. GC -33 `eacoad.mNgx All Blasting, including methods of storing and handling explosives and highly inflammable materials, shall conform to Federal, State, Local Laws and Ordinances. All City Ordinances shall be complied with even though some or all of the blasting is done outside the City Limits unless the applicable Ordinance is in conflict with the law of the jurisdiction where the action is being taken. The following is a list of requirements in addition to Federal, State, and Local Laws and Ordinances. 1. The Contractor shall furnish the City of Round Rock with a Certificate of Blasting Insurance in the amount of $300,000.00 for each contract, at least twenty-four hours prior to using explosives. A blasting permit must be obtained from the City at least five (5) days prior to use of explosives. If Blasting is covered under the Contractors General Insurance Certificate for each contract, a separate blasting certificate will not be required. 2. The following public utility companies and City Department will be notified by the Contractor, on every occasion, at least twenty-four (24) hours prior to the use of explosives: Water and Wastewater, Electric, Gas, Telephone and the City Engineering Department. 3. Explosive materials to be used shall be limited to blasting agents and dynamite, unless prior approval of other materials is obtained in writing from the Engineering Department. 4. During blasting, all reasonable precautions shall be taken to protect pedestrians, passing vehicles, and public or private property. Blasting mats or protective cover shall be used when required by the City Inspector, the permit, or by safe blasting practices. 5. All explosives shall be stored in accordance with Chapter 5, Section 5.200, of the City Code. 6. The Director of Engineering or his representative shall have the right to limit the use of explosives and/or blasting methods which in his opinion are dangerous to the public or nearby property of any kind. 7. The Contractor, at his expense, shall promptly repair or replace all items known to be damaged as a result of blasting. All claims of damage shall be investigated by the City or by Consulting Firms approved by the City. 8. The Contractor shall maintain accurate records throughout the Blasting operations showing the type explosive used, number of holes, pounds per hole, depth of hole, total pounds per shot, delays used, date and time of GC -34 P.ond mstiMa blast and initials of the Inspector. The Contractor is fully responsible for all claims resulting from his blasting operation. All damage or loss to any property referred to in this article caused in whole or in part by the Contractor, any Subcontractor, any Sub - subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable, shall be remedied by the Contractor, except damage or loss attributable solely to faulty Drawings or Specifications or solely to the acts or omissions of the Owner or Engineer or anyone employed by either of them, and not attributable in any degree to the fault or negligence of the Contractor. The contractor shall designate a responsible member of his organization at the site whose duty shall be the prevention of accidents. This person shall be the Contractor's superintendent unless otherwise designated in writing by the Contractor to the Owner and the Engineer. 10.03 Location and Protection of Utilities Notwithstanding any other provision of this contract, the Contractor shall be solely responsible for the location and protection of any and all public utility lines and utility customer service lines in the work area. The Contractor shall exercise due care to locate and to mark, uncover or otherwise protect all such lines in the construction zone and any of the Contractor's work or storage areas. Upon request, the Owner shall provide such information as it has about the location and grade of water, sewer, gas, and telephone and electric lines and other utilities in the work area but such information shall not relieve or be deemed to be in satisfaction of the Contractor's obligation hereunder, which shall be primary and nondelegable. Any such lines damaged by the Contractor's operations shall be immediately repaired by the Contractor or he shall cause such damage to be repaired at his expense. GC -35 5.0 SPECIAL CONDITIONS SECTION 01- INFORMATION 01 - 01 ENGINEER The word "Engineer" in these Specifications shall be understood as referring to Bury & Pittman, Inc., 3345 Bee Caves Road, Suite 200, Austin, Texas 78746, Engineer of the Owner, or the Engineer's authorized representative to act in any particular position for the Owner. 01 -02 COPIES OF PLANS AND SPECIFICATIONS FURNISHED 01 -05 LOCATION The Agreement will be prepared in not less than five (5) counterpart (original signed) sets. Owner will furnish Contractor two (2) sets of conforming Contract Documents and Specifications and four (4) sets of Plans free of charge, and additional sets will be obtained from the Engineer at commercial reproduction rates plus 20% for handling. 01 - 03 GOVERNING CODES All construction as provided for under these Plans and Specifications shall be governed by any existing Resolutions, Codes and Ordinances, and any subsequent amendments or revisions thereto as set forth by the Owner. 01-04 LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE ON TIME The Contractor agrees that time is of the essence for this Contract and that the definite value of damages which would result from delay would be incapable of ascertainment and uncertain, so that for each day of delay beyond the number days of herein agreed upon for the completion of the work herein specified and contracted for, after due allowance for such extension of time as is provided for under the provisions of Section 4.02 of the General Conditions, the Owner may withhold permanently from the Contractor's total compensation, not as penalty but as liquidated damages, the sum of $100.00 per calendar day. The location of work shall be as mentioned in the Notice to Bidders and as indicated on Plans. specond.mst/spec SC -1 1 01-06 USAGE OF WATER All water used during construction shall be provided by the City. The City shall specify the location from which the Contractor is to procure water. The Contractor shall be responsible for providing all apparatus necessary 1 for procuring, storing, transporting and using water during construction. The Contractor shall strive to use that amount of water which is reasonable to perform the work associated with this contract and shall endeavor to avoid excessive waste. The Contractor will be required to pay for all water used if it is found that unnecessary or excessive waste is occurring during construction. 01-07 PAY ESTIMATES 1 If pay estimates from the Contractor are not received by the Engineer on or before the time specified in Section 5.04 of the General Conditions, then 1 the pay estimate will not be processed and will be returned to Contractor. 1 SECTION 02- SPECIAL CONSIDERATIONS 1 02 -01 CROSSING UTILITIES 1 Prior to commencing the work associated with this contract, it shall be the Contractor's responsibility to make arrangements with the Owners of such utility companies to uncover their particular utility lines or otherwise ' confirm their location. Certain utility companies perform such services at their own expense, however, where such is not the case, the Contractor will cause such work to be done at his own expense. 02 -02 UTILITY SERVICES FOR CONSTRUCTION The Contractor will be responsible for providing his own utility services while performing the work associated with this contract. No additional 1 payment will be made for this item. 02 -03 GUARANTEES The Contractor warrants the materials and workmanship and that the work 1 is in conformance with the plans and specifications included in this contract specond.mst/spec SC -2 1 for the period that the Maintenance Bond, as outlined in Section 04 of the Special Conditions, is in effect. Upon notice from Owner, the Contractor shall repair defects in all construction or materials which develop during specified period and at no cost to Owner. Neither final acceptance, Certificate of Completion, final payment nor any provision in Contract Documents relieves Contractor of above guarantee. Notice of observed defects will be given with reasonable promptness. Failure to repair or replace defect upon notice entitles Owner to repair or replace same and recover reasonable cost thereof from Contractor. 02 MINIMUM WAGE SCALE Minimum wage scale as specified in section 3.22 of the General Conditions and in accordance with State of Texas and Federal Government regulations. 02 - 05 LIMIT OF FINANCIAL RESOURCES The Owner has a limited amount of financial resources committed to this Project; therefore, it shall be understood by all bidders that the Owner may be required to change and /or delete any items which he may feel is necessary to accomplish all or part of the scope of work within its limit of financial resources. Contractor shall be entitled to no claim for damages anticipated profits on any portion of work that may be omitted. At any time during the duration of this contract, the Owner reserves the right to omit any work from this contract. Unit prices for all items previously approved in this contract shall be used to delete or add work per change order. 02 CONSTRUCTION REVIEW The Owner shall provide a project representative to review the quality of materials and workmanship. 02 - 07 LIMITS OF WORK AND PAYMENT It shall be the obligation of the Contractor to complete all work included in this Contract, so authorized by the Owner, as described in the contract documents and technical specifications. All items of work not specifically paid for in the bid proposal shall be included in the unit price bids. Any question arising as to the limits of work shall be left up to the interpretation specond.mst/spec SC - of the Engineer. 02-08 PAYMENT FOR MATERIALS ON HAND Owner will not pay for materials on hand. Payment will be made for work completed in accordance with monthly estimate procedure stipulated in the General Conditions of the Agreement. 02-09 "AS- BUILT" DRAWINGS The Contractor shall mark all changes and revisions on all of his copies of the working drawings during the course of the Project as they occur. Upon completion of the Project and prior to final acceptance and payment, the Contractor shall submit to the Engineer one set of his working drawings, dated and signed by himself and his project superintendent and labeled as "As- Built ", that shows all changes and revisions outlined above and that shows field locations of all above ground appurtenances including but not limited to valves, fire hydrants and manholes. These as -built drawings shall become the property of the Owner. Each appurtenance shall be located by at least two (2) horizontal distances measured from existing, easily identifiable, immovable appurtenances such as fire hydrants or valves. Property pins can be used for as- builts tie -ins provided no existing utilities as previously described are available. Costs for delivering as -built drawings shall be subsidiary to other bid items. 02 - 10 LAND FOR WORK Owner provides, as indicated on Drawings, land upon which work is to done, right -of -way for access to same and such other lands which are designated for use of Contractor. Contractor provides, at his expense and without liability of Owner, any additional land and access thereto that may be required for his construction operations, temporary construction facilities, or for storage of materials. 02 -11 DEVIATIONS OCCASIONED BY UTILITY STRUCTURES specond.mst/spec Whenever existing utilities, not indicated on Plans, present obstructions to grade and alignment of proposed improvements immediately notify engineer, who without delay, will determine if existing utilities are to be relocated, or grade and alignment of proposed improvements changed. Where necessary to move existing services,poles, guy wires, pipelines, etc., SC-4 as determined by the Engineer, the Contractor will make arrangements with the owner of the utility to be moved and have it moved. The costs of any utility relocations will be at the Contractor's sole expense. Owner will not be liable for relocations costs or damages on account of delays due to changes made by owners of privately owned utilities which hinder progress of the work. 02 -12 CONSTRUCTION STAKING All construction staking required to complete the work associated with this contract shall be provided by the Contractor. The Contractor shall be responsible for determining the layout and extent of staking necessary to construct the improvements to the lines and grades shown in the Plans. This item shall not be paid for separately and shall be considered subsidiary to other bid items. SECTION 03- TRAFFIC CONTROL Access shall be.provided for residents and emergency vehicles at all times. When it becomes necessary to restrict access, the Contractor shall notify all applicable agencies (ie. Fire Department, E.M.S., Public Works, etc.). At the end of each day two lanes of traffic shall be opened to the public. The Contractor shall be responsible for all maintenance, signing and safety precautions necessary for traffic control. This item shall be considered subsidiary to other bid items and no additional compensation shall be given for complying with this Special Condition. SECTION 04-MAINTENANCE BOND Per City of Round Rock Ordinances, a two (2) year Maintenance Bond naming the City of Round Rock as obligee will be required for public streets constructed without lime stabilization of subgrade material when the Plasticity Index of the subgrade is above 24. Maintenance Bond shall remain in effect for two (2) years from date of City of Round Rock acceptance of improvements. A one (1) year Maintenance Bond in the amount of one hundred (100%) specoad.msuspec SC -5 SECTION 5 INSURANCE specond.mst/spec percent of the contract price will be required for all other improvements and shall be submitted prior to final payment. Such bonds shall be from an approved surety company holding a permit from the State of Texas to act as surety (and acceptable according to the latest list of companies holding certificates of authority from the Security of the Treasury of the United States) or other surety or sureties acceptable to the Owner prior to final payment. Section 3.18 of the General Conditions of the Agreement is hereby amended to include the following: 3.18 Insurance Contractor shall carry insurance in the following types and amounts for the duration of this Contract, which shall include items owned by Owner in care, custody and control of Contractor prior and during construction and warranty period, and furnish Certificates of Insurance along with copies of policy declaration pages and all policy endorsements as evidence thereof: a. Statutory Worker's Compensation and minimum $100,000 Employers Liability Insurance. b. Commercial General Liability Insurance with minimum limits of $500,000 per occurrence and $1,000,000 Aggregate or $500,000 for this designated project and $100,000 Fire Damage. c. Automobile Liability Insurance for all owned, nonowned and hired vehicles with minimum limits for Bodily Injury of $250,000 for each person and $500,000 for each occurrence and Property Damage limits of $100,000 or Combined Single Limit of $600,000. d. On all new or remodeling building projects: All Risk Builders Risk Insurance for insurable building projects shall be insured in the amount of the contract price for such improvements. Owner and Contractor waive all rights against each other for damages caused by fire or other perils to the extent covered by Builders Risk Insurance required under this section, except as to such rights as they may SC -6 specond.mst/spec have in the proceeds of such insurance. Contractor shall require similar waivers by Subcontractors and Sub - subcontractors. e. Owner and Contractor's Protective Policy. The Contractor shall provide and maintain during the life of this contract and until all work under said contract has been completed and accepted by the Owner, an Owner's and Contractor's Protective Policy which co- insures the Owner and the Owner's agents and employees with the same Commercial General Liability coverage as described above, entitled "Commercial General Liability Insurance." When offsite storage is permitted, policy will be endorsed for transit and off site storage in amounts sufficient to protect property being transported or stored. This insurance shall include, as insured, City of Round Rock, Contractor, Subcontractors and Sub - subcontractors in the work, as their respective interest may appear. If insurance policies are not written for amount specified in b. and c. above, Contractor is required to carry an Excess Liability Insurance Policy for any difference in amounts specified. Contractor shall be responsible for deductibles and self insured retentions, if any, stated in policies. Any self insured retention shall not exceed ten percent of minimum required limits. All deductibles or self insured retentions shall be disclosed on Certificate of Insurance required above. Contractor shall not commence work at site under this Contract until he has obtained required insurance and until such insurance has been reviewed by Owner's Contract Administration Office. Contractor shall not allow any Subcontractors to commence work until insurance required has been obtained and approved. Approval of insurance by Owner shall not relieve or decrease liability of Contractor hereunder. Insurance to be written by a company licensed to do business in the State of Texas at the time policy is issued and acceptable to owner. SC -7 specond.msUspec Contractor shall produce an endorsement to each effected policy: 1. Naming City of Round Rock, 221 East Main Street, Round Rock, Texas 78664 as additional insured (except Workers' Compensation and Builders Risk). 2. That obligates the insurance company to notify Joanne Land, City Secretary, City of Round Rock, 221 East Main Street, Round Rock, Texas 78664 of any and all changes to policy 30 days prior to change. 3. That the "other" insurance clause shall not apply to Owner where City of Round Rock is an additional insured shown on policy. It is intended that policies required in this agreement, covering both Owner and Contractor, shall be considered primary coverage as applicable. Contractor shall not cause any insurance to be canceled nor permit any insurance to lapse during term of this Contract or as required in the Contract. If Contractor is underwritten on a claim -made basis, the retroactive date shall be prior to, or coincident with, the date of this Contract and the Certificate of Insurance shall state that coverage is claims made and also the retroactive date. Contractor shall maintain coverage for duration of this Contract and for two years following completion of this Contract. Contractor shall provide the City annually a Certificate of Insurance as evidence of such insurance. It is further agreed that Contractor shall provide Owner a 30 day notice of aggregate erosion, an advance of the retroactive date, cancellation and /or renewal. It is also agreed that Contractor will invoke the tail option at request of Owner and the Extended Reporting Period (ERP) premium shall be paid by Contractor. Owner reserves the right to review insurance requirements of this section during effective period of the Contract and to make reasonable adjustments to insurance coverages and their limits when deemed necessary and prudent SC -8 by Owner based upon changes in statutory law, court decisions or the claims history of the industry as well as Contractor. Owner shall be entitled, upon request, and without expense, to receive copies of policies and all endorsements thereto and may make any reasonable requests for deletion or revision or modification of particular policy terms, conditions, limitations or exclusions, except where policy provisions are established by law or regulation binding upon either of the parties hereto or the underwriter on any of such policies. Actual losses not covered by insurance as required by the section shall be paid by Contractor. (continue with Special Conditions as necessary) specond.mst/spec SC - 6.0 TECHNICAL SPECIFICATIONS 1 ITEM 1 GENERAL DESCRIPTION 1.01 SCOPE OF WORK The work covered by these Specifications consists of furnishing all labor, equipment, appliances, materials and performing all operations in connection with the installation of water and wastewater system improvements complete in accordance with the Plans, and subject to the terms and conditions of the Contract Documents. 1.02 GOVERNING TECHNICAL SPECIFICATIONS NOTE: The item number designation shown in parentheses adjacent to captions herein is a reference to City of Austin Standard Specifications. STREET. WATER, SEWER AND DRAINAGE IMPROVEMENTS The current City of Austin Standard Specifications as adopted and amended ' by the City of Round Rock and the current City of Austin Erosion and Sedimentation Control Manual are hereby referred to and included in this contract as fully and to the same extent as if copied at length herein and 1 they shall be applied to this project except as modified in these Specifications and on the Plans. Note that copies of the Austin Specifications governing the major items of work are attached at the end of 1 this section for ease of reference. Wherever the term "City of Austin" is used in the Austin Specifications, it shall be construed to mean the City of Round Rock. Wherever the term "Engineer" is used in the Austin Specifications, it shall be construed to mean Bury & Pittman, Inc, 3345 Bee Caves Road, Suite ' 200, Austin, Texas 78746. IE I1 2 CONTROL OF WORK 2.01 CLEAN -UP ' 2.01.1 CONSTRUCTION SITE During construction the Contractor shall coordinate all activities with Russell Garner of White Construction Company currently providing construction activities on the site area. techspec.scp /dh TS -1 2.01.2 BACKWORK 2.02 GRADING The contractor shall keep the site free and clean from his own rubbish and debris originating from construction activity and shall clean-up the site promptly when notified to do so by the Engineer. The Contractor shall, at his own expense, maintain the streets and roads free from dust, mud, excess earth or debris originating from construction activities which constitutes a nuisance or danger to the public using the thoroughfare, or the occupants of adjacent properties. Care shall be taken to prevent spillage on streets and roads over which hauling is done, and any such spillage or debris deposited on streets, due to the Contractor's operations, shall be immediately removed. The Contractor shall coordinate his operations in such a manner as to prevent the amount of clean -up and completion of back works from becoming excessive. Should such a condition exist, the Engineer may order all or portions of the work to cease and refuse to allow any work to commence until the back work is done to the Engineer's satisfaction. The Contractor shall do such grading in and adjacent to the construction area associated with this contract as may be necessary to leave such areas in a neat and satisfactory condition approved by the Engineer. ITEM 3 EXAMINATION AND REVIEW 3.01 EXAMINATION OF WORK The work covered under this Contract shall be examined and reviewed by the Engineer, representatives of all governmental entities which have jurisdiction, and the Owner's authorized representative. The quality of material and the quality of installation of the improvements shall be to the satisfaction of the Engineer. It shall be the Contractor's responsibility for the construction methods and safety precautions in the undertaking of this Contract. techspec.scp /dh TS - 1 3.02 NOTIFICATION The Engineer and Owner must be notified a minimum of 24- hours in advance of beginning construction, testing, or requiring presence of the Engineer, project representative, or Owner's representative. 3.03 CONSTRUCTION STAKING The Engineer shall furnish the Contractor reference points and benchmarks for construction as necessary. ' 3.04 PROTECTION OF STAKES. MARKS. ETC. ' All engineering and surveyor's stakes, marks, property corners, etc., shall be carefully preserved by the Contractor, and in case of destruction or removal during the course of this project, such stakes, marks, property ' corners, etc., shall be replaced by the Contractor at the Contractor's sole expense. 1 ITEM 4 PROTECTION AND PRECAUTION 4.01 WORK IN FREEZING WEATHER Portions of the work may continue as directed by the Engineer. 1 4.02 PROTECTION OF TREES. PLANTS AND SHRUBS 1 The Contractor shall take necessary precautions to preserve all existing trees, plants and shrubs but where it is justifiable and necessary the ' Contractor may remove trees and plants for construction right -of -way but only with approval of the Engineer. 1 1 1 1 techspec.scp/dh TS - 4.03 TRAFFIC CONTROL MEASURES AND BARRICADES Traffic control measures and barricades shall be installed in accordance with the Texas Manual of Uniform Traffic Control Devices and in other locations deemed necessary by the Engineer, for the protection life and property. Under no circumstances will any existing road be permitted to remain closed over a weekend. No separate pay will be made for this item. Costs for this item shall be subsidiary to other items of work. 4.04 PROPERTY LINES AND MONUMENTS The Contractor shall be responsible for the protection, reference and resetting of property corner monuments if disturbed. 4.05 DISPOSAL OF SURPLUS MATERIAL The Contractor shall at his own expense, make arrangement for the disposal of surplus material, such as rock, trees, brush and other unwanted backfill materials. 4.06 CONTRACTOR'S USE OF PREMISES The Contractor shall, at his own expense, provide additional space as necessary for his operations and storage of materials. The contractor shall coordinate use of the premises with White Construction Company. The contractor shall not interfere with construction activities being undertaken by White Construction Company or any of their subcontractors. ITEM 5 MATERIALS 5.01 TRADE NAMES Except as specified otherwise, wherever in the specifications an article or class of material is designated by a trade name or by the name or catalog number of any maker, patentee, manufacturer, or dealer, such designations shall be taken as intending to mean and specify the articles described or another equal thereto in quality, finish, and serviceability for the purpose intended, as may be determined and judged by the Engineer in his sole discretion. techspec.scp /dh TS-4 5.02 MATERIALS AND WORKMANSHIP No material which has been used by the Contractor for any temporary purpose whatever is to be incorporated in the permanent structure without the written consent of the Engineer. Where materials or equipment are specified by a trade or brand name, it is not the intention of the owner to discriminate against an equal product of another manufacturer, but rather to set a definite standard of quality for performance, and to establish an equal basis for the evaluation of bids. Where the words "equivalent ", "proper" or "equal to" are used, they shall be understood to mean that the item referred to shall be "proper ", the "equivalent" of, or "equal to" some other item, in the opinion or judgement of the Engineer. Unless otherwise specified, all materials shall be the best of their respective kinds and shall be in all cases fully equal to approved samples. Notwithstanding that the words "or equal to" or other such expressions may be used in the specifications in connection with a material, manufactured article or process, the material, article or process specifically designated shall be used, unless a substitute is approved in writing by the Engineer, and the Engineer will have the right to require the use of such specifically designated material, article or process. ITEM 6 GRADING. RESTORATION. REVEGETATION. AND EROSION CONTROL MEASURES (series 600) This item shall govern the furnishing, placing, maintaining and removal of all erosion control measures, site work, restoration work, grading, shaping, seeding and sodding for all disturbed areas and in accordance with the plans. EROSION CONTROL Temporary erosion control measures shall include but not be limited to: Silt Fences, Rock Berms, Land Grading and Storm Inlet Sediment Traps. The Contractor is alerted to the fact that his construction operations may cause undue sedimentation at various locations and erosion of the land in and around the construction area. Such areas of erosion and sedimentation are difficult to predict and are best determined in the field as construction progresses. The Contractor should be aware that such areas of erosion and techspec.scp /dh TS - sedimentation generally include but are not limited to: drainage outlets, steep slopes and in areas where vegetation has been removed. The Contractor should be prepared to take remedial measures and to install erosion and sedimentation control devices as necessary to correct all adverse erosion and sedimentation. The extent and location of erosion control measures shall be as determined in the field by the Engineer or his designated representative. The Contractor shall be responsible for providing all materials, labor and equipment necessary for the construction of erosion control measures. The Contractor shall maintain all erosion control measures until final acceptance and shall remove them after final acceptance of the project. This item will not be measured and paid for separately. Costs for this item shall be subsidiary to other items of work. RESTORATION AND REVEGETATION Unless otherwise directed by the Engineer: All unpaved areas disturbed during construction shall be graded and shaped to conform to the topography existing prior to construction. Said areas shall then be restored by providing topsoil and vegetation or by providing surface material that existed prior to construction (ie. peagravel, flexible base, etc.). The type of vegetation or surface material provided shall equal or exceed the type of vegetation or surface material which existed prior to construction unless otherwise requested by the property owner. This item shall be measured and paid for as one lump sum. EXISTING SHRUBS AND TREES It is the intent of the Owner to preserve as many existing trees and shrubs within the construction area as possible. The Contractor shall not remove, trim or otherwise disturb existing trees and shrubs unless otherwise directed by the Engineer. The Contractor, at his sole expense and without compensation from the Owner, shall be responsible for replacing all trees and shrubs damaged where in the opinion of the Engineer, such damage was avoidable. techspec.scp /dh TS - When directed by the Engineer, the Contractor shall carefully excavate existing shrubs that conflict with proposed construction and properly re- plant said shrubs within the right -of -way in a location determined by the Engineer after he has conferred with the respective property owner. The Contractor will not be responsible for guaranteeing the success of the re- planted shrubs provided he has exercised proper care and followed appropriate re- planting procedures. No separate pay will be made for this item. Costs for this item shall be subsidiary to other items of work. All shrubs unduly damaged during excavation or re- planting shall be replaced at the Contractor's sole expense without compensation from the Owner. ITEM 7 CONSTRUCTION AND TRAFFIC CONTROL WITHIN HIGHWAY RIGHT -OF -WAY All construction performed, all traffic controls and all warning signs within any right -of -way of the State of Texas shall be in accordance with any rules, regulations and policies of the State Department of Highways and Public Transportation. techspec.scp /dh TS - X6.1 Description This item shall govern constriction of manholes complete in place and the materials used therein, including excavation, installation, backfilling and surface restoration. It shall also include furnishing and installing rings, covers, appurtenances and any pumpiRg, and drainage necessary to complete the wont. Wastewater manholes shall be acceptance tested by the Contractor. Rater and Wastewater Standard Products Lists form a part of the Specifications. Should the Contractor elect to use any materials from these lists, they should be completely and clearly identified when submitted. 506.2 Materials and Caponents (1) Concrete and Cement Stabilized Sand: All concrete shall conform to nom N0. 403 CiNCREIE FOR SERLCTURE4. Cast in place concrete shall be Class A, and precast concrete shall be Class I All interior surfaces of wastewater manholes shall have an approved mating or be otherwise acceptably protected from the acidic effects of municipal wastewater. Concrete for backfill of averexcavated arms shall. be Class A or Class J as indicated. Cement stabilized sand for bedding or backfilling, where indicated or required, shall contain 2 be of Portland Cement per cubic yard; sand shall be as defined for "Fine Aggregate" in Uf21 403 CONCRETE FOR S1i L ITEES. (2) Mortar: Mortar shall be composed of one part Portland Cement, one part masonry cement (or 1/4 part hydrated lime), and sand equal to 2 -1/2 to 3 times the sun of the volumes of the cements and lime used. The sand shall meet the requirements for "Fine Aggregate" as given in ITEM 403 CRETE FOR STR=ZTURES. (3) (4) Brick.: Brick for ring adjustment courses and for stormwater manholes shall be of first quality, sand, hard burned, perfectly shaped brick conforming to the requirements of ASTM C 62 Grade SW or concrete brick meeting the requirements of ASTM C 55, Grade N-1. (5) 506 08/17/92 (6) R.01d:eanis: Bulkheads shall meet the requirements of ITEM N0. 507 BULKHEADS. Item 506 Manholes Peinfor it: Reinforcing steel shall conform to the requirements of ITEM NO. 406 REINFOKING STEEL. Secodary, nal- structural steel may be replaced by approved collated fibrillated polypropylene fibers in cast -in -place stormwater manholes. Ringss and Comore, 24-In di Inside Diameter. Rings and covers shall conform to the requirements of ITEM NO. 503 FRAMES, GRATES, RIGS AND COVERS. (7) Precast Base Sections, Riser Sections, and Canes: Precast concrete base sections, riser sections, and cones shall conform to the requi.renents of ASTM C 478. Joints for wastewater base sections, riser sections, and cones shall conform to the requirements of ASTM C 443. Additionally, joint dimensions for 48 -inch inside diameter wastewater manhole sections and cones shall comply with STANDARD W. 506-12 0-RIND JOINT LETAIL or N0. 506-13 WEDGE SEAL JOINT DETAIL. Precast bases for 48 inch inside diameter manholes shall have preformed inverts. Approved inserts shall be embedded in the concrete all of the manhole sections to facilitate handling; through holes for lifting will not be permitted. (8) Precast Junction Booms: Precast junction boxes shall be allowed only where indicated an the plans or approved by the Engineer. Joints for wastewater junction boxes shall conform to the requirements of ASH 43. Page 1 Manholes (9) Pipe -to -Mari e/Junctim Box Assemblies- Precast basses and precast junction booms shall have flexible, resilient and non-corrosive approved boot connectors or ring waterstops conforming to the requirements of ASIM C 923 on all wastewater pipe connections. (10) Precast Flat-Slab Transition/Junction Box Lids: Precast slab transitions and lids shall be designed to safely resist pressures resulting fran leads which might result from any combination of forces imposed by an HS-20 Loading as defined by the American Association of State Highway and Transportation Officials (AASHTO). The joints of precast slab transitions and of lids for wastewater applications shall conform to the requirements of ASIM 0443. (11) Precast - Prefabricated Tea Manholes: Tee manholes shall be allowed only where indicated on the plans or approved by the Engineer. The Hain pipe section shall_ conform to the requirements of TIFS1 NO. 510 PIPE. The vertical manhole portion (tee) above the main pipe shall conform to the requires nts of the precast coapanents• The manhole tee shall have a minimm inside diameter of 48 inches and shall rise vertically centered or tangent to the Hain pipe, as indicated or approved. An access hole less than 48- inches in diameter shall be cut into the main pipe to all a ledge for support of access ladders. Unless otherwise specified, the main pipe portion of the tee manhole shall be paid subsidiary to the emit tee manhole price. (12) Precast Grade Rings, 24-1/2 Inch Inside Illieter: Rings shall be reinforced !'lace A or I concrete 6 inches wide with a thidaness of 3 to 6 inches. (13) Waterproofing Joint Materials: 0 -rings and wedge seals for the joints of all wastewater manholes, and for stormrater manholes when indicated, shall conform to the requirements of ASIM C443. Cold applied pteforned plastic gaskets for stomnwater manholes shall be as specified in ITEM U. 510 PIPE. Connections between reinforcer) concrete wastewater manhole structures and pipes shall meet the requirements of ASIM C923. 506.3 Construction All manholes shall have a mint= inside diameter of 48 inches. Manhole base dimensions shall be appropriately increased to accommodate all converging pipe. A miniamn horizontal clearance of 12 inches shall be maintained between pipe walls at the sprirglines of adjacent pipes. Pipe ends within the manhole base walls shall not be relied upon to support overlying manhole dead and live load weights. All wastewater branch connections to new or existing mains shall be made at manholes with the influent pipe crown installed at the effluent pipe crown elevation. Where the springline of an influent pipe is 24 inches or more above the springline of the effluent pipe, a drop manhole shall be used. Construction of extensions to existing systems shall require p1acerent of bulkheads at locations indicated or directed by the Engineer. Unless otherwise indicated, stoomwater manholes shall have eccentric cones; wastewater manholes shall have concentric cores, except on manholes over large rains where an eccentric cone shall be situated to provide access to an invert ledge. Eccentric cones may be used where conflicts with other utilities dictate. Flat -slab tops may be used where clearance problems exist; see 506.2(10) above. Manholes shall be founded at the established elevations on uniformly stable subgrade. Unstable subgrade shall be over-excavated a minimm of 12 inches and replaced with an 506 08/17/92 Page 2 Manholes approved material. Precast base units shall be founded and leveled on a 6 inch coarse aggregate bedding. A pipe section with a prefabricated tee manhole and half the length of the adjoining pipe sections on each side shall be founded on a minimum of 6 inch unueinforced Class A concrete. The cast -in -place concrete cradle shall be poured against undisturbed trench walls up to the pipe's springline. Cast -in -place foundations shall have a minimum depth of 12 inches at the invert flowline. The lowermost riser section may be set in the concrete while still green, after which the foundation shall be cured a minimum of 24 hours prior to proceeding with construction of the manhole up to 12 feet in depth. The foundation shall be cured an additional 24 hours prior to continuing construction above the 12 foot level. Manhole depth shall be measured from the invert flowline to the finish surface elevation. Wastewater pipes, except polyvinyl chloride ( PVC), may be laid through the manholes and the top half of the pipes removed to facilitate invert construction. The manhole bottom shall rise from the springl.ine elevation of the pipe, approximately one inch for each 12 inches of rum (8X). Wastewater manholes with lines larger than 18 inches shall require precast bases; manholes constructed over in- service maims however, may be built on cast -in -place foundations if the flow cannot be interrupted. Precast and cast -in -place wastewater ju=nction boxes shall be allowed only where indicated on the plans or approved by the Engineer. The floors of stonawater manholes also, shall rise outwardly from the springline on a slope of 1:12 (8X). Wastewater lines, except reinforced concrete pipe, set in cast -in -place foundations, shall require an approved waterstop seal or gasket around the outside perimeter of the pipe. It shall be approximately centered under the manhole section wall. Cast -in -place storseater manholes, junction boxes and flat -slab transitions shall be reinforced, r1a¢s A concrete. All structural concrete work shall conform to 11FM N0. 410 =REM STRUCTURES. Formes will be required for all cast -in -place walls above the foundation. Where the surrounding material can be trimmed to a smooth vertical face, outside forms may be omitted. All manholes with precast grade rings or brick adjustment courses may have a muds= vertical rise of 24 inches (the maximum includes the depth of the ring casting). All manholes not located in paved areas shall have bolted covers. Backfilling for manholes shall conform to the density requirements of ITEM 510 PIPE. Manhole construction in roadways may be staged to facilitate base construction. Manholes constructed to interim elevations shall be covered with steel plates of sufficient thickness to support vehicular traffic. Steel plates on wastewater manholes shall be set in mortar to minimize inflow. Manholes shall be completed to finish elevation prior to placement of the roadway's finish surface. The excavation for completion of manhole construction shall be berkfilled with cement stabilized sand (2 sacks per cubic yard) up to the bottom of Portland Cement pavement slabs or to within two (2) inches of finish elevation of asphaltic concrete pavements. The cement stabilized sand shall be a minims of 12 inches thick. 506.4 Acceptancelesth4rof Wastewater Manholes: Manholes shall be tested separately and independently of the wastewater lines. (1) Test by the &fzlriatica Method All backfilling and compaction are to be colleted prior to the commencement of testing. 506 08/17/92 Page 3 Manholes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 506 (a) Procedures: 1. Manhole section interiors shall be carefully inspected; units found to have through -mall lift holes, or and penetration of the interior surface by inserts provided to facilitate handling, mill not be accepted. 2. After cleannirg the interior surface of the manhole, the Contractor shall place and inflate pneumatic plugs in all of the connecting pipes to isolate the manhole; sealing pressure within the plugs shall be as recommended by the plug naraufacturer. 3. Concrete manholes shall be filled with eater or otherwise thoroughly wetted for a period of 24 hairs prior to testing. 4. At the start of the test, the manhole shall be filled to the top with water. The test time shall be 1 hour (60 minutes). The Construction Inspector must be present for observation during the entire time of the test. Permissible loss of water in the 1 hour test time is 0.025 gallons per diameter foot, per foot of manhole depth. For a 4 foot diameter manhole, this quantity converts to a madjun permissible drop in the water level (from the top of a 24" diameter manhole cone) of 0.05 inches per foot of manhole depth (0.5 inches for a 10 foot deep manhole). (2) That by the Vaasa Method: At the discretion of the Engineer, the Contractor may substitute the Vacuum Method of testing for the Exfiltration test described in 506.4(1) above. The vacuum method may be used by the contractor prior to beckfilling, but only for his convenience so that defects may be located and repaired. Final acceptance testing shall be done after all 6eckfilling, and compaction are complete. (a) Equipment: 1. Manhole vacua tester shall be by P.A. Glazier, Inc., Quern Industries, or other approved manufacturer. 2. Pipe sealing plugs shall have a load resisting capacity equal to or greater than that required for the size of the connected pipe to be sealed (b) Procedures — applicable to new 4' -0" diameter manholes. 1. Manhole section interiors shall be carefully inspected; units found to have through -wall lift holes, or any penetration of the interior surface by inserts provided to facilitate handling, will not be accepted. 2. After cleaning the interior surfaces of the manhole, the Contractor shall place and inflate pneumatic plugs in all of the connecting pipes to isolate the manhole; sealing pressure within the plugs shall be as recommended by the plug manufacturer. Plugs -and the ends of pipes connected by flemdble boots —shall be blocked to prevent their movement during the vacuum test. 3. The vacuum test head shall be placed at the inside of the top of the manhole cone section, and the compression seal band inflated to the pressure recamended by its manufacturer. The vacuum pump shall be connected to the outlet port with the valve open. Zen a vacuum of 10 inches of mercury ( -5 psig) has be attained, the valve shall be closed and the time noted. 08/17/92 Page 4 Manholes 4. The manhole shall have passed the test if the vacum does not drop below 9 inches of nnercury (-4.5 psig) within three (3) minutes of the time the valve as closed. The actual vacuun shall be recorded at the end of the three (3) minutes during which the valve was closed. (3)-- Failure to Pass -the Test — Meanie: of Teets If the manhole fails to pass the test by either the exfiltration or the vacuum method as described in (1) and (2) above, or if visible groundwater leakage into the manhole is observed, the Contractor shall locate the leek, make repairs acceptable to the E and retest. Records of all manhole tasting shall be made available to the Engineer at the close of each working day, or as otherwise directed. (4) Inspection: The Engineer shall make a visual inspection of each manhole after it has passed the testing requirements and is considered to be in its final condition. The inspection shall determine the completeness of the manhole; any defects shall be corrected to the EYngineer'a satisfaction. 506.5 Measurement: All junction boxes and manholes of the type indicated shall be measured as units complete in place. New msnilnles constructed to interim elevations to facilitate stage construction shall be measured as one unit re ardless of the number of interim elevations constructed. All labor, materials and other expanses necessary for the stage construction shall be considered subsidiary to the completed unit. 506.6 Payment: Paymennt for completed junction boxes and manholes of the type indicated shall be made at the unit price bid for each including all labor,equipnait, materials, time and incidentals necessary to complete the work. The intended use of cosh item shall be designated by a two code (Wastewater = WW; Stormwater = SW) in the spaces provided after the pay item number: 1. Pay Item No. 506 M_: Manhole, Dia. Per Each 2. Pay Item No. 506 S • Special Manhole, Dia. Per Each 3. Pay Item No. 506 DWW: Drop Mannhole, Dia. Per Each 4. Pay Item No. 506 C : Centered Tee Manhole, -- Dia. x _ Dia. Per Each 5. Pay Item No. 506 T : Tangent Tee Manhole, Dia. x Dia. Per Each 6. Pay Item No. 506 J : Junction Box, _ Ft x _ Ft Per Each END Applicable Pefe na se: , Standard Specifications Manual: Item Nos. 403, 406, 410, 503, 507, 510 Standards Manual: Standard Detail Nos. 100 -1, 503-2, 503-3, 506-1, 506-3, 506-5, 506-7, 506-8, 506-9, 506 -10, 506 -11, 506 -12, 506-13 Utilities Manual: Section 2, Water and Wastewater Design Criteria 506 06/17/92 Page 5 Manholes 509.1 Description This item consists of designing, furnishing. installing, dewatenng, maintaining and removing safety systems for trench excavations as determined by Contractor's Trench Safety Engineer and/or Contractor's Competent Person(s). This includes special clearing. excavation and backfiiling for safely systems. At a minimum. this work shall conform to United States Department of Labor Rules 29 CFR, Part 1926 (OSHA). 509.2 Trench Safety System Plan Submittal Prior to, or at the Pre - Construction Conference, the Contractor shall submit to Owner a Trench Safety System Plan sealed by a Professional Engineer registered in the State of Texas Notice To Proceed with construction will not be issued by Owner until Contractor has submitted a Trench Safety System Plan to Owner. The Trench Safety System Plan at a minimum, shall conform to OSHA standards for sloping of sides, utilization of trench boxes. and/or utilization of shoring. sheeting and bracing methods. Contractor shall be responsible for obtaining the necessary geotechnical information to design the Trench Safety System Plan; however, if geotechnical information was obtained by Owner for the design of the improvements (normally taken at 500 foot intervals along the proposed centerline to a depth not exceeding five feet below proposed fowline), it shall be provided to Contractor for information purposes subject to the provisions of Section 00220 Soil Investigation Data. The Trench Safety System Plan submittal shall include: (1) A plait or other designation of areas in which each type of system is to be used, including length of trench to be opened. length of time trench to remain opened, means of egress, storage of materials, allowable loads on trench walls. methods for filling /compacting beddingrbackfill within the safety of the system. removal of system and equipment restrictions. (2) Drawings or manufacturer's data describing various elements of Trench Safety System with sufficient detail for workers to properly install Trench Safety System, as applicable. (3) Recommendations and limitations for using systems. (4) Sealed engineering calculations and /or equipment manufacturer's certifications. as applicable. showing that systems designed to withstand anticipated loadings and can be fully installed in designated space within the street right of way or easement provided by Owner. (5) Certificate of Insurance of Trench Safety Engineer's Professional Liability Insurance coverage written by a company acceptable to Owner and authonzed to do business in State of Texas at time policy is issued. Contractor's Trench Safety Engineer shall carry and maintain coverage with mi nimum limits of 5500,000. 509.3 Trench Safety System Plan Review Item No. 509 Trench Safety Systems Review of the Trench Safety System Plan by Owner is only for general conformance to OSHA standards and regulations. Owner's failure to note exception(s) to the submittal does not relieve Contractor of any or all responsibility or liability for the Trench Safety System Plan. Contractor remains solely and completely responsible for all trench safety systems and for the means, methods, procedures, and materials therefor. 509.4 Construction Methods Contractor's Competent Person(s) shall maintain a copy of and implement OSHA trenching safety regulations at the worksite. Trenching shall be completed to lines and grades indicated or as specified in various technical specification items requinng excavation and trenching and/or backfilling. Contractor shall perform all trenching in a safe manner and maintain safety systems to prevent death or injury to personnel or damage to structures, utilities or property in or near excavation. If evidence of possible cave -ins or slides is apparent or an installed trench safety system is damaged, work in trench shall immediately cease and personnel evacuated from hazardous area and Owner notified. Personnel shall not re -enter excavation until necessary repairs or replacements are completed, inspected and approved by 5119 112/19/93 1 Trench Safety Systems 'Contractor's Competent Person(s). Repair and replacement of damaged safety system shall be at Contractor's sole expense. 1 509.5 Changed Conditions When changed conditions require modifications to the Trench Safety System, Contractor shall provide a new "d esign or an alternate Trench Safety System designed by Contractor's Trench Safety Engineer adequate for 'conditions encountered. Copies thereof shall be provided to Owner in accordance with 509.2 'Trench Safety Plan Submittal A copy of the most current Trench Safety System shall be maintained on site and made ( variable to inspection and enforcement officials at all times hanges to the Trench Safety System Plan initiated by Contractor for operational efficiency or by changed conditions that could be reasonably anticipated will not be cause for contract time extension or cost adjustment 't hereof When changes to the Trench Safety System Plan are the result of severe and uncharacteristic natural conditions or other conditions totally out of the control of Contractor. Contractor may make a wntten request to Owner for a Change Order to address said work. Contractor shall notify Owner in wnting Immediately, but no later than 24 hours, whenever changed conditions are encountered that Contractor may claim for additional ompensallon. Only that work that Contractor deems Immediately necessary to protect the safety of workers and public, equipment or materials may be accomplished until Contractor makes the written request for a Change Order and Owner has a reasonable opportunity to investigate and respond in wnting to the request. 1 509.6 Measurement Trench Safely Systems shall be measured by linear foot through manholes and other appurtenances along the 'centerline of trench conforming to Contractor's plans and specifications. 509.7 Payment 'Payment for Trench Safety Systems, measured as prescribed above. will be made at unit price bid per centerline linear foot of trench per Contractor's plan and specifications which price shall include designing, furnishing, i nstalling. dewatering, maintaining. replacing and removing the Trench Safety Systems, sloping, special clearing, nd excavation necessary to safely implement the Trench Safety System Plan. Payment will be made under the following ' Pay Item No. 509 - 1: Trench Safety Systems (all depths) Per Linear Foot. I ND ef: 104, 110. 111, 120, 130, 401, 414, 501, 502, 504, 506, 508, 510, 511, 551, 558, 559, 591, 593, 594 1)2/19/93 2 Trench Safety Systems 509.6 Measurement Trench Safety Systems shall be measured by linear foot through manholes and other appurtenances along the centerline of trench conforming to Contractor's plans and specifications. 509.7 Payment Payment for Trench Safety Systems, measured as prescribed above, will be made at unit price bid per centerline linear foot of trench per Contractor's plan and specifications which price shall include designing, furnishing, installing, dewatering, maintaining, replacing and removing the Trench Safety Systems, sloping, special clearing, and excavation necessary to safely implement the Trench Safety System Plan. Payment will be made under the following: END Pay Item No. 509 -1: Trench Safety Systems (all depths) Per Linear Foot. Ref: 104, 110, 111, 120, 130, 401, 414, 501, 502, 504, 506, 508, 510, 511, 551, 558, 559, 591, 593, 594 509 08/28/89 Page 3 Trench Safety Systems $0.1 Description Item No. 510 Pipe This item shall consist of furnishing all pipe and /or materials for constructing pipe mains, severs, laterals, stubs, inlet leads, service connections and culverts, including all applicable work such as excavating, bedding, jointing, backfilling materials, tests, concrete trench cap, concrete cap and encasement, etc., prescribed under this item in accordance with the provisions of the Edwards Aquifer Protection Ordinance, when applicable and Specification "Cuts in Public Right of Way" for existing streets. The pipe shall be of the sizes, types, class and dimensions indicated or as designated by the Engineer and shall include all joints or connections to new or existing mains, pipes, severs, manholes, inlets, structures, etc., as may be required to complete the work in accordance with specifications and published standard practices of the trade associations for the material specified and to the lines and grades indicated. This item shall consist of any pumping, bailing, drainage and Item No. 509, "Trench Safety Systems" for trench walls, when indicated. Mess otherwise provided, this item.shall consist of the removal and disposition of trees, stumps and other obstructions, old structures or portions thereof such as house foundations, old sewers, masonry or concrete lolls, the plugging of the ends of abandoned piped utilities cut and left in place and the restoration of existing utilities damaged in the process of excavation, cutting and restoration of pavement and base courses, the furnishing and placing of select bedding, backfilling and cement or lime stabilized backfill, the hauling and disposition of surplus materials, bridging of trenches and other provisions for maintenance of traffic or access as indicated. 510.2 Materials bee Contractor shall submit descriptive information and evidence that the arerials and equipment the Contractor proposes for incorporation into the murk is of the kind and quality that satisfies the specified functions and Qsality. Water and Wastewater Standard Products Lists form a part of the Specifications. Should the Contractor elect to use any materials from tiese lists, they should be completely and clearly identified when submitted. (1) Concrete Concrete shall conform to Item No. 403, "Concrete for Structures ". (2) Coarse Aggregate Coarse aggregate shall conform to Item No. 403, "Concrete for Structures" or one of the following: 510 06/09/88 Page 1 Pipe (a) Pipe Bedding Stone Pipe bedding stone shall be clean gravel, crushed gravel or crushed limestone, free of mud, clay, vegetation or other debris, conforming to AST)! C 33 for stone quality. Size gradation shall conform to ASTH C -33 No. 57 or No. 67 or the following Table: (b) Foundation Rock SIEVE SIZE PERCENT RETAINED BY VEIGBT 1 1/2" 0 1" 0 -10 1/2" 40 -85 *4 90 -100 *8 95 -100 Foundation rock shall be well graded coarse aggregate ranging in size from 2 to 8 inches. (c) Flexible Base Flexible base shall conform to Item No. 210, "Flexible Base ". (3) Fine Aggregate (a) Concrete and Mortar Sand Fine aggregate shall be Grade 1 and shall conform to Item No. 403, "Concrete for Structures ". (b) Bedding Sand Sand for use as pipe bedding shall be clean, granular and homogeneous material composed mainly of mineral matter, free of mud, silt, clay lumps or clods, vegetation or debris. The material removed by decantation SDHPT Test Method Tex - 406 -A, plus the weight of any clay lumps, shall not exceed 4.5 percent by weight. The average electrical resistance when eater- saturated shall be at least 1,800 ohm /cm by the single probe method, with no single test reading lower than 1,500 ohm /cm. Size gradation of sand for bedding shall be as follows: 510 06/09/88 Page 2 Pipe (4) Soil Cement GRADATION TABLE SIEVE SIZE PERCENT RETAINED BY 'WEIGHT 1/4" 0 #60 75 - 100 #100 95 -100 Soil cement bedding shall consist of a mixture of approved soil, cement, eater and approved admixtures. The soil cement mixture shall have a minimum 14 day compressive strength of 120 psi and a maximum shrinkage of 5 percent. The mix design and the results of mix testing, both done by an independent testing laboratory acceptable to the Owner, shall be submitted to the Engineer for approval prior to construction. The water content shall not exceed that required to provide a mix that will flow, can be pumped and vill maintain the soil in suspension while being placed. The soil cement bedding shall be placed such that all voids are filled. Soil for the soil cement bedding shall meet the following requirements: a. A minimum of 80 percent by dry weight shall pass a *4 sieve. 510 06/09/88 b. Between 5 percent and 30 percent shall pass a #200 sieve. c. The soil material shall have a plasticity index of 3 or less. d. The maximum size of any clay balls in the soil shall be 1/2 inch. Class C or Class F fly ash may be used as an admixture. The fly ash shall meet the requirements of ASTM C 595, C 618 and the supplier's certificate as to the analysis and composition shall be furnished. Batching equipment shall be provided to obtain the proper weights of soil, cement, eater and admixture. All measuring devices shall be sensitive to a 2 percent variation above or below the actual weights required. The mixers used for mixing the soil cement bedding shall be designed and operated so that the soil cement discharged from the mixer is uniform in compaction and consistency throughout each batch. Page 3 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (5) Pea Gravel SIEVE SIZE PERCENT RETAINED BY WEIGHT 3/4" 0 1/2" 0 -25 1/4" 90 -100 (6) Select Backfill or Borrow This material shall consist of borrov or suitable material excavated from the trench which has a plasticity index of less than 20, a moisture content vhich does not exceed 2 percent from optimum as determined in accordance with SDHPT Test Method Tex -114 -E and free of stones or rocks over 8 inches. All suitable materials from excavation operations not required for backfilling the trench shall be placed in embankments, if applicable. All unsuitable materials should be dried or modified to make them suitable for use, as required. (7) Cement Stabilized Backfill When indicated or directed by the Engineer, all backfill shall be with cement - stabilized backfill rather than the usual materials. Unless otherwise indicated, cement stabilized backfill material shall consist of a mixture of the dry constituents described for Class J Concrete. The cement and aggregates shall be thoroughly dry mixed vith no eater added to the mixture except as may be directed by the Engineer. (8) Pipe Pea gravel bedding shall be clean washed material, hard and insoluble in vater, free of mud, clay, silt, vegetation or other debris. Stone quality shall meet ASTM C 33. Size gradation shall be as follovs: General Fire line leads and fire hydrant leads shall be ductile iron. Domestic water services shall not be supplied from fire service leads, unless the domestic and fire connections are on separately valved branches with an approved backflov prevention device in the fire service branch. All wastewater force mains shall be constructed of ductile iron pipe of the class indicated, Thickness Class 50 minimum. Water pipe in or near structures and in vehicular traffic areas within utility easements on private property shall be Ductile Iron Pipe, Thickness Class 52 wrapped as indicated, except for sizes over 24 inches, Concrete Pressure Pipe, steel cylinder type, conforming to the requirements of AVVA C -301 will be acceptable. 510 06/09/88 Page 4 Pipe There may be no service connections to Concrete Pressure Pipe installed in these areas. All service tubing (3/4 inch thru 2 inches) installed in any such private property shall be 150 psi annealed seamless Type K copper tubing with no sweat or soldered joints. The quality of materials, the process of manufacture and the finished pipe shall be subject to inspection and approval by the Engineer at the pipe manufacturing plant and at the project site prior to and during installation. (a) Reserved (b) Iron Pipe Iron pipe shall be ductile iron pipe conforming to the specifications below: AVVA C -151 For push -on ar mechanical joint piple. AVVA C - 115 For flanged pipe, flanges must be ductile iron (gray iron is not acceptable) Class 125 ANSI B16.1 and must be fabricated and attached to the pipe barrels by the original pipe manufacturer. AVVA C -104 All pipe interiors shall be cement - mortar lined and seal coated accordingly; pipe exteriors shall be coated as required by the applicable pipe specification. Except as described above for easements, and where not otherwise indicated, ductile iron pipe shall meet the following minimum physical requirements: Thickness Class 50 Tensile Strength 60,000 psi Yield Strength 42,000 psi 1. Ductile Iron and Gray Iron Fittings Fittings shall be push -on, flanged or mechanical joint as indicated or approved and shall conform to the following specifications: Sizes 4 inch through 12 inch: AVVA C - 110 or AVVA C - 153 Sizes larger than 12 inch: AVVA C -110 510 06/09/88 Page 5 Pipe 1 1 1 J 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 AVVA C -104: 2. Joint Materials The interior of all fittings shall be cement - mortar lined and coated as per C -104; exterior coating shall be as required by the applicable fitting specification. Gaskets for mechanical joints shall conform to ANSI /IOVA A21.11 /C -111. Joining of slipjoint iron pipe shall, without exception, be accomplished with the natural or synthetic rubber gaskets of the manufacturer of that particular pipe being used. A joint lubricant shall be used and applicable recommendations of the manufacturer shall be followed. Gaskets for flanged joints shall be bonded continuous full face gaskets, of 1/8 inch minimum thickness of natural or synthetic rubber, cloth- reinforced rubber, neoprene or asbestos composition material, preferably of deformed cross section design and shall meet all applicable requirements of ANSI /AVVA A21.11 /C -111 for gaskets. They shall be manufactured by, or satisfy all recommendations of, the manufacturer of the pipe /fittings being used and be fabricated for use with Class 125 ANSI B16.1 flanges. Tee -head bolts, nuts and washers for mechanical joints shall be high strength, low alloy, corrosion resistant steel stock equal to "COR -TEN A" or alloyed ductile iron conforming to ASTM A 536, fabricated in accordance with the ANSI /AWVA A21.11 /C - 111. Hex head bolts and nuts shall satisfy the chemical and mechanical requirements of ASTM A 307 Grade B and shall be fabricated in accordance with ASTH B 18.2 with UNC Class 2 rolled threads. Hex bolts, nuts and washers shall be stainless steel or hot -dip zinc or hot -dip aluminum coated. Either hex or tee head bolts, nuts and washers with bonded fluoropolymer corrosion resistant coating may be used where specifically approved. All threadea fasteners shall be marked with a readily visible symbol cast, forged or stamped on each nut and bolt, which will identify the fastener grade /material and the producer and the supplier shall provide adequate literature to facilitate such identification. Painted markings are not acceptable. 510 06/09/88 Page 6 Pipe 3. Polyethylene Film Wrap All iron pipe, fittings and accessories shall be wrapped with 8 mil (minimum) polyethylene film conforming to AWVA C - 105, with all edges overlapped and taped securely with duct tape to provide a continuous wrap to prevent contact between the piping and the surrounding backfill. Repair all punctures of the polyethylene vith duct tape to restore the continuous protective wrap before backfilling. 4. Marking (c) Concrete Each pipe joint shall be marked with the pipe class, manufacturer's identification, year manufactured and "Ductile" or "DI ". 1. General Pipe shall conform to AST( C 76 for Circular Pipe. Concrete pipe smaller than 12 inches in diameter shall conform to AST( C 14, Extra Strength. All pipe shall be machine made or cast by a process which will provide uniform placement of the concrete in the form and compaction by mechanical devices which will assure a dense concrete. Concrete shall be mixed in a central batch plant or other approved batching facility from which the quality and uniformity of the concrete can be assured. Transit mixed concrete will not be acceptable for use in precast pipe. The pipe shall be Class III or the class indicated. Storm sewer pipe shall be of the tongue and groove or 0 -ring joint design. Wastewater pipe shall be of the 0 -ring joint design. 2. Marking Each joint of pipe shall be marked with the pipe class, the date of manufacture, the manufacturer's name or trade mark, diameter of pipe and orientation, if required. Pipe marking shall be waterproof and conform to ASTM C 76. Harking of Life Design shall be included on wastewater pipe. 3. Minimum Age for Shipment Pipe shall be considered ready for shipment when it conforms to the tests specified in ASTM C 76. 510 06/09/88 Page 7 Pipe 1 1 1 1 1 1 1 t 1 1 1 1 1 1 I 1 1 1 4. Joint Materials When constructing storm sewers, the Contractor shall have the option of making joints with either of the following materials: a. Hortar Mortar for joints shall meet the requirements set forth below in "Mortar". b. Cold Applied Preformed Plastic Gaskets Cold Applied Plastic Gaskets shall be suitable for sealing joints of tongue and groove concrete pipe. The gasket sealing the joint shall be produced from blends of refined hydrocarbon resins and plasticizing compounds reinforced with inert mineral filler and shall contain no solvents, irritating fumes or obnoxious odors. The gasket joint sealer shall not depend on oxidizing, evaporating or chemical action for its adhesive or cohesive strength and shall be supplied in extruded rope form of suitable cross section. The size of the plastic gasket joint sealer shall be in accordance with the manufacturer's recommendations and sufficient to obtain squeeze -out around the joint. The gasket joint sealer shall be protected by a suitable removable wrapper that may be removed longitudinally without disturbing the joint sealer to facilitate application. The chemical composition of the gasket joint sealing compound as shipped shall meet the following requirements: Composition Test Method Typical Analysis Bitumen (petroleum ASTM D 4 50 -70 plastic content) (Y by weight) Ash -inert Mineral Water Tex -526 -C 30 -50 (Z by weight) Volatile Matter (at 325 F) Tex -506 -C 2.0 Maximum (Z by weight) The gasket joint sealing compound when immersed for 30 days at ambient room temperature separately in 5 percent solution of caustic potash, a mixture of 5 percent hydrochloric acid, a 5 percent solution of 510 06/09/88 Page 8 Pipe 5. Beds 510 08/24/93 sulfuric acid and a saturated F2S solution shall show no visible deterioration. The physical properties of the gasket joint sealing compound as shipped shall meet the following requirements: ProPertY Specific Gravity at 77 F Ductility at 77F (cm) Minim= Softening point Penetration: 32 F (300 g) 60 sec 77 F (150 g) 5 sec 115 F (150 g) 5 sec Flashpoint C.O.C. F Fire Point C.O.C. F Test Typical Analysis Method Minimise Maxim ASDI D 71 Tex -503 -C Tex -505 -C Tex -502-C Tex -502 -C Tex -502 -C Tex-504 -C Tex-504-C 1.20 1.35 5.0 275 F 75 50 120 150 600 F 625 F When constructing wastewater lines, the contractor shall use rubber gasket joints conforming to ASIM C 443. Just before :raking a joint, the ends of the pipe shall be clean, dry, free of blisters or foreign matter and shall be wire brushed. For 0 -ring joints, the gasket and the inside surface of the bell shall be lubricated with a light film of soft vegetable soap compound to facilitate assembly of the joint. The rubber O-ring gasket shall be stretched uniformly in the joint. Wedge seal type ( "Forsheda" pre- lubricated) gaskets may be used if joint details submitted are approved; installation of such gaskets shall be in strict accordance with the manufacturer's rer miadatic s, and shall be the sole element depended upon to make the joint flexible and watertight. In wastewater lines no horizontal or vertical angles in the alignment of pipes shall be permitted unless indicated. The spigot shall be centered in the bell, the pipe pushed uniformly home and brought into true alignment. Bedding material shall be placed and tamped against pipe to secure the joint. When horizontal or vertical angles in the alignment of storm sewers are indicated, the bed or angle shall be constructed by cutting on a bias one or both pipes as may be required for the aligr=mt indicated. The pipe cut shall be sufficiently long to allow exposing the reinforcement, which shall be bent, welded and incorporated into the pipe bed and reinforced concrete collar to maintain the structural integrity. The collar shall be 6 inches minimum, reinforced with #4 bars anal foot center both directions. Builder's hardware cloth may be used on the outside of the joint to aid in holding cementing materials in place. Plywood, fiberboard or other materials placed an the inside of the pipe as formwork shall be re oved as soon as the joint materials have obtained initial set, after which the inside surface of the pipe joint shall be finished smooth and true to the line and grade Page 9 Pipe 510 established. The Contractor may use prefabricated bends meeting the specification requirements in lieu of field fabricated bends. All bends shall be watertight, have a smooth floe line and be equal or greater in strength to the adjacent pipe. Horizontal or vertical bends in wastewater lines shall be accomplished by use of manholes. Vith the Engineer's approval, bends may be constructed using beveled radius pipe joints or deflected straight pipe meeting the manufacturer's recommended minimum radius of curvature. 6. Sulfide and Corrosion Control All concrete pipe used for wastewater installations shall be protected from sulfide and corrosion damage by using limestone aggregate or wall thickness pipe which meets the 100 year life design. (d) Concrete Steel Cylinder (CSC) Pipe 1. General Requirements The Contractor shall submit to the Engineer for approval along with other required data a tabulated layout schedule with reference to the stationing and grade lines to be used. The manufacturer shall furnish all fittings and special pieces required for closures, bends, branches, manholes, air valves, blovoffs and connections to main line valves and other fittings as indicated. Each pipe length, fitting and special joint shall have plainly marked on the bell end of the pipe, the head condition for which it is designed. In addition, marking will be required to indicate the location of each pipe length or special joint in the line and such markings will be referenced to the layout schedules and drawings and submitted for approval. Hydrostatic testing of concrete steel cylinder fittings during fabrication will not be required. 2. Design and Inspection Vhere not otherwise indicated, concrete steel cylinder pipe shall be Class 150, designed to withstand a vacuum of not less than 28 feet of water in addition to other loads. Valve reducers, tees and outlets from a pipe run shall be designed and fabricated so that all stresses are carried by the steel forming the fitting or outlet. 06/09/88 Page 10 Pipe Concrete steel cylinder pipe shall meet one of the following specifications: AVWA C -301 - Any Size AWA C -303 - 24 inch maximum size All pipe flanges shall conform to AWVA C -207, requirements for standard steel flanges of pressure classes corresponding to the pipe class. Pipe to be installed in a tunnel or encasement shall be manufactured with 1 inch thick by 24 inch wide skid bands of mechanically impacted mortar in addition to the normal coating. All concrete steel cylinder fittings shall be constructed of steel plate of adequate strength to 'withstand both internal pressure and external loading. Rod reinforcing shall not be used to figure the required steel area. The fittings shall have a concrete lining and 1 inch minimum coating of cement mortar, except that centrifugally spun lining need not be reinforced. Minimum lining thickness shall be 1/2 inch for 16 inch pipe and 3/4 inch for sizes larger than 16 inch pipe. Vhere it is impractical to place such concrete protection on interior surfaces of small outlets, 2 coats of "Situmastic Tank Solution" shall be applied. No fitting shall be made by cutting of standard pipe, except that outlets of less than 75 percent of the pipe diameter may be placed in a standard pipe. Beveled spigots may be placed on standard pipe. 3. Joint Materials Joints shall be of the rubber gasket type conforming to the applicable standards. The inside and outside recesses between the bell and spigot shall be completely filled with Cement Grout in accordance vith the pipe manufacturer's recommendations. Grout materials for jointing such pipe, unless otherwise indicated, shall be as described herein. (e) In Place Pipe Rehabilitation 1. In Place Sliplining With or Vithout Pipe Destruction /Replacement This item shall consist of installing a high density polyethylene pipe by use of a pipe insertion machine, such as Expand -A -Line or approved equal, into an existing line. 510 06/09/88 Page 11 Pipe a. Material Requirements The polyethylene pipe shall meet the following specifications: ASTM F 714 Plastic Pipe Institute PE3408 Unless otherwise specified, the Contractor shall furnish the polyethylene pipe in accordance with the following table: Depth of Cover Expressed in Feet SDR of Pipe 0 - 16 16.1 - b. Functional Requirements 17 11 The polyethylene pipe shall be assembled and joined at the site using the thermal butt fusion method. All equipment and procedures shall be in strict compliance with the manufacturer's recommendations. Fusing shall be accomplished by personnel certified as fusion technicians by a manufacturer of polyethylene pipe and /or fusing equipment. The complete joint shall be in true alignment and have a uniform double roll back bead resulting from the use of proper temperature and pressure. The joint shall be allowed adequate cooling time before removal of pressure. Joints shall be smooth on the inside vith a maximum projection of the veld bead of approximately 3/16 inch. The fused joint shall be watertight and shall have a tensile strength equal to that of the pipe. All joints shall be subject to acceptance by the Engineer or his /her representative prior to placement. All defective joints shall be cut out and replaced. Any section of the pipe with a gash, abrasion, nick or scar greater in depth than 10 percent of the wall thickness, or containing concentrated ridges, discolorization, excessive spot roughness, pitting, variable wall thickness, or any other defect of manufacturing or handling as determined by the Engineer or his /her representative, shall be discarded and removed from the site. Terminal sections of pipe that are joined within the insertion pit shall be connected with a full circle pipe repair clamp with a minimum length of 510 06/09/88 Page 12 Pipe one and one half times the nominal inside pipe diameter, in accordance with Water and Wastewater OPL No. 271. The butt gap between pipe ends shall not exceed 1 /10 of the nominal inside diameter of the pipe. c. Installation Procedure The Contractor shall carry out his operations in strict accordance with all OSHA and manufacturer's safety requirements. Particular attention is drawn to those safety requirements involving entering confined spaces and trench safety. The Contractor, when required, shall provide for the flow of water around the section or sections of pipe designated for rehabilitation including active services in the rehabilitation section. The bypass shall be made by plugging the line at an existing upstream manhole or adjacent system. The pump and bypass lines shall be of adequate capacity and size to handle the flow. The Contractor shall take all necessary steps to prevent flooding of any private property and shall be liable for damages incurred by the flooding. Nev polyethylene pipe shall be inserted immediately behind the boring equipment in accordance with the manufacturer's procedures. The boring machine shall be specifically designed and manufactured by Expand -A -Line or approved equal. The boring machine shall be equipped with all controls necessary to place the pipe on proper line and grade according to the plans. The Contractor shall install all pulleys, rollers, bumpers, alignment control devices and other equipment required to protect existing manholes and to protect the pipe from damage during installation. Lubrication may be used as recommended by the pipe manufacturer. Under no circumstances shall the pipe be stressed beyond its elastic limit. All active service connections shall be identified by video inspection or other means and connected to the new main in accordance with the plan details. Upon commencement, insertion, from manhole to manhole, shall be continuous without interruption except as approved by the Engineer. 510 06/09/88 Page 13 Pipe The installed pipe shall be allowed the manufacturer's recommended amount of time, but not less than 12 hours, to provide for complete ' shrinkage or relaxation of the pipe prior to any connection of service lines, sealing of the annular space where the pipe enters the manhole, or ' backfilling of the insertion pit. Sufficient excess length of pipe shall be allowed to provide for this shrinkage. ' The pipe bedding in the insertion pit shall be either pea gravel or pipe bedding stone. Bedding and backfill shall conform to the specifications contained herein. All street repairs and pavement replacement shall conform to Item No. 500, "Cuts in Public Right of Way ". ' The relaxed pipe shall be cut so that it projects 4 inches inside of the manhole and any annular space shall be sealed. Sealing shall be with material ' approved by the Engineer. The sealant shall completely fill the void between the pipe and the manhole .a11 and shall extend 3 inches beyond the ' annulus on the inside wall of the manhole. The sealant shall form a smooth transition from the pipe onto the manhole. The complete joint shall be uniform and watertight. A concrete invert shall be ' poured in place and shaped to form a smooth flow channel through the manhole. 2. Cured Resin Pipe Lining This item shall consist of installing a resin impregnated flexible felt tube by an inversion reconstruction method, such as Insicuform or equal, into an existing pipe. Curing shall be accomplished by circulating hot vater or other approved method to cure ' the resin into a hard impermeable pipe lining. Insituform is a patented process installed by licensed installers. a. Material Requirements The fiber felt tube shall be fabricated to a size that when installed will neatly fit the internal circumference of the conduit specified by the Engineer. ' The minimum length shall be that deemed necessary by the Contractor to effectively span the distance from the inlet to the outlet of the respective manholes unless otherwise specified. The Contractor shall verify the lengths in the field before impregnation. Individual inversion runs can ' l 510 06/09/88 Page 14 Pipe P be made over one or more manhole sections as determined in the field by the Contractor, subject to approval by the Engineer. Unless otherwise specified, the Contractor shall furnish a general purpose unsaturated polyester resin and catalyst system that meets the finished cured physical strengths listed below: Flexural Stress (ASTM D 790) 4,500 psi_ Tensile Stress (ASTM D 368) 2,500 psi Modulus of Elasticity (ASTM D 790) 250,000 psi If so directed,.the Contractor shall furnish, prior to use of the materials, satisfactory written certification of his compliance with the above standards. b. Installation Procedure The Contractor shall carry out his operations in strict accordance with all OSHA and manufacturer's safety requirements. Particular attention is drawn to those safety requirements involving working with scaffolding and entering confined spaces. When required, cleaning and repair of the pipe line shall be performed by City of Austin Water and Wastewater Utility. Inspection of pipe line by the Contractor shall be performed by experienced personnel trained in locating breaks, obstacles and service connections by closed circuit television. The interior of the pipe shall be carefully inspected to determine the location of any conditions which may prevent proper installation into the pipe and these conditions shall be corrected. A video tape and log shall be made by the Contractor and kept for later reference by the Owner. The Contractor, when required, shall provide for the flow of water around the section or sections of pipe designated for rehabilitation including active services in the rehabilitation section. The bypass shall be made by plugging the line at an existing upstream manhole and pumping the flow into a downstream manhole or adjacent system. The pump and bypass lines shall be of adequate capacity and size to handle the flow. The Contractor shall take all necessary steps to prevent flooding of any private property and shall be liable for any damages incurred by the flooding. 510 06/09/88 Page 15 Pipe 510 It shall be the responsibility of che City of Austin to clear the lines of obstructions such as solids, dropped joints, protruding service connections or collapsed pipe that will prevent the insertion of Insituform. The Contractor shall designate a location where the uncured resin in the original containers and the unimpregnated fiber -felt tube shall be vacuum impregnated prior to installation. The Contractor shall alloy the Engineer to inspect the materials and "vet out" procedure. The quantities of the liquid thermosetting materials shall be per manufacturer's standards to provide the wall thickness specified. Water for the work shall be furnished by the City. Contractor shall use a double -check valve assembly to prevent backflow in the event of pressure failure. The wet out fiber -felt tube shall be inserted through an existing manhole or other approved access by means of an inversion process and the application of a hydrostatic bead sufficient to fully extend it to the next designated manhole. The impregnated tube material shall be inserted into the vertical inversion standpipe with the impermeable plastic membrane side out. At the lover end of the inversion standpipe, the felt tube shall be turned inside out and attached to the standpipe so that a leakproof seal is created. The inversion head will be adjusted to be of sufficient height to cause the impregnated tube to invert from manhole to manhole and hold the tube tight to the pipe wall, produce dimples at side connections and flared ends at manholes. The use of a lubricant is recommended and, if used, such lubricant shall be as approved by manufacturer's standards. The manufacturer's standards shall be closely followed during the elevated curing temperature so as not to over stress the felt -fiber and cause damage or failure prior to cure. (If prior approval is obtained from the owner, the Contractor may elect to use a Top Inversion. In this method the fiber -felt tube is preinverted to a distance that corresponds to che minimum inversion head and instead of attaching to 'am elbow at the base of the vertical inversion standpipe, it is attached to a top ring and the standpipe is formed from the felt tube itself.) After inversion is completed the Contractor shall supply a suitable heat source and water 06/09/88 Page 16 Pipe recirculation equipment. The equipment shall be capable of delivering hot eater throughout the section by means of a prestrung hose, which has been perforated per manufacturer's recommendations, to uniformly raise the eater temperature above the temperature required to effect a cure of the resin. This temperature shall be determined by the resin /catalyst system employed. The heat source shall be fitted with suitable monitors to gauge the temperature of the incoming and outgoing water supply. Another such gauge shall be placed between the impregnated felt tube and the pipe invert at the remote manhole to determine the temperature during cure. Water temperature in the line during the cure period shall not be less than 150 F or more than 200 F as measured at the heat source return line. Initial cure shall be deemed to be completed when inspection of the exposed portions of pipe liner appear to be hard and sound and the remote temperature sensor indicated that an exotherm had occurred. The cure period shall be of a duration recommended by the resin manufacturer, as modified for the manufacturer's process during which time the recirculation of the water and cycling of the head exchanger to maintain the temperature continues. The Contractor shall cool the hardened pipe liner to a temperature below 100 F before relieving the static head in the inversion standpipe. Cool -down may be accomplished by the introduction of cool eater into the inversion standpipe to replace water being drained from a small hole made in the downstream end. Care shall be taken in the release of the static head so that a vacuum will not be developed that could damage the newly installed pipe liner. The fir`shed pipe liner shall be continuous over the ent_re length of an inversion run between two manholes and be free from visual defects such as foreign inclusions, dry spots or voids. Any defect which will affect, in the foreseeable future, or warranty period, the integrity or strength of the pipe liner shall be repaired at the Contractor's expense, in a manner specified by the Engineer. 510 06/09/88 Page 17 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 After the pipe liner has been cured in place, the Contractor shall connect new services or reconnect existing service connections as designated and identified by the proposal. This shall generally be done without excavation, from the interior of the pipeline by means of a television camera and a cutting tool. The eater- tightness of the pipe liner shall be-gauged while curing and under a positive head. To ascertain that there is no leakage, the eater pressure inside the pipe should hold at 6 pounds per square inch for a duration of at least 4 hours testing time. After the work is completed the Contractor will provide the Engineer with a video tape showing both the before and after conditions including the restored connections. (f) Polyethylene Tubing 1. General If, due to broken or misaligned pipe at a manhole wall, the pipe liner failed to make a tight seal, the Contractor shall apply a seal at that point. The seal shall be of a resin mixture compatible with pipe liner. All polyethylene (PE) plastic tubing shall be high density, high molecular weight plastic tubing, pressure rated at 200 psi working pressure and must bear the National Sanitation Foundation seal of approval for potable eater service. When tested for Environmental Stress Cracking, the PE tubing shall not shoe any loss of pressure in the 6 specimens tested for 3 hours in accordance with the requirements of ASTM 0 2737 using the test pressure of 400 psi at 73.4 F. The minimum burst pressure shall be 630 psi at 73.4 F determined in accordance with ASTM D 1599, latest revision. The time of testing of each specimen shall be between 60 and 70 seconds. The tubing shall not fail, balloon, burst or veep as defined in ASTM D 1598, latest revision, when tested in accordance with the Sustained Pressure Test Method of ASTH D 2737 but under the following test conditions: Temperature Time Pressure 73.4 F 1,000 hours 400 psi 100 F 1,000 hours 330 osi 510 06/09/88 Page 18 Pipe 2. Markings Permanent marking an the tubing shall include the following at intervals of not more than 5 feet: 3. Tube Size Nominal tubing size. The type of plastic material, i.e., PE 3408. The Standard Dimension Ratio (SDR) and the pressure rating in psi for water at 73.4 F (e.g., SDR -9, 200 psi). ASTM D 2737 designation. The manufacturer's name or trademark, code and seal of approval (NSF mark) of the National Sanitation Foundation. PE tubing shall be standard copper tube size outside diameter, with Standard Dimension Ratio (SDR) of 9. Standard sizes, dimensions and tolerances shall be as follows: Nominal Outside Diameter Wall Thickness Tube Size Average Tolerance Minimum Tolerance (inches) (inches) (inches) (inches) (inches) 3/4 0.875 +0.004 0.097 +0.010 1 1.125 +0.005 0.125 0.012 1 1/4 1.375 +0.005 0.153 + 0.015 1 1/2 1.625 +0.006 0.181 +0.018 2 2.125 +0.006 0.236 +0.024 (g) Copper Tubing All copper service tubing shall be annealed seamless Type K water tube rated at 150 psi vorking pressure. The tubing shall be homogenous throughout and free from cracks, holes, crimping, foreign inclusions or other defects. It shall be uniform in density and other physical properties. Nominal Tube Size Outside Diameter Wall Thickness (inches) (inches) (inches) 1/2 0.625 +0.0025 0.049 +0.004 3/4 0.875 ±0.003 0.065 ± 0.0045 1 1.125 *0.0035 0.065 +0.0045 1 1/4 1.375 +0.004 0.065 +0.0045 1 1/2 1.625 +0.0045 0.072 ±0.005 2 2.125 ±0.005 0.083 ±0.007 510 06/09/88 Page 19 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 (h) Service Connection Fittings All fittings used in cus mains, connecting meters the Vater and Wastewater in the Standard Installa Connection Guide section (i) Brass Goods tomer service connection - tapping , etc. - must be currently listed on Standard Products List or called for tion Details in the Service of the City of Austin Standards. All brass stops, couplings, bends, connections, nipples and miscellaneous brass pipe fittings and accessories used in meter connections, copper service lines, air release piping assemblies and wherever needed in the eater distribution system, shall conform to the Standards, Vater and Wastewater Standards product list and AWVA C -800, except as herein modified or supplemented. Unless otherwise noted, the goods described herein shall be fabricated of standard.Red Brass (Waterworks Brass) consisting of 85 percent copper and 5 percent each of tin, lead and zinc. Exposed threads shall be covered with plastic caps or sheeting to protect the threads. Brass goods of each type and class shall be compatible with other fittings in common usage for similar purposes. Where not otherwise indicated, all such materials shall meet the following requirements: Corporation stop thread (where used) shall conform to Table 1, Figure 1, AWA C -800, commonly called the Hueller,Thread. Corporation stops with iron pipe threads are also permitted. Iron pipe threads shall conform to ANSI B2, 1 - 1969 and Table 9, Figure 9 of AWVA C -800. Copper fittings threads shall conform to Table 2 and 3, Figure 2 and 3 of AWA C -800 and ANSI 81.1960 with approximate tolerance of Class 2. Flanges shall conform to ANSI 816.1, Class 125 (or Class 250 where so noted), as to dimensions, drillings, etc. Brass pipe shall conform to the weight and dimensions of Table 2 in the Appendix for AWA C -800. All fittings shall be suitable for use at hydrostatic working pressures up CO 150 psi. 06/09/88 Page 20 Pipe (j) PVC - Plumbing Pipe 1. General Polyvinyl chloride pipe and fittings shall be Type I, Grade 1, schedule 40, 200 psi conforming to the City of Austin plumbing code, CS 270 and PS 21. 2. Physical Requirements Pipe shall be extruded from 100 percent virgin unplasticized Type 1, Normal Impact Polyvinyl Chloride (PVC) to conform to the following minimum physical properties: Specific Gravity 1.36 -1.40 Tensile Strength at 78 F (PSI) 7,500 Compression Strength (PSI) 9,400 Modulus of Elasticity 410,000 Coefficient of Linear Expansion 6.70K/Cx10 -5 Izod Impact at 78 F (ft. lbs. /in. notch) 0.7 -1.5 Burning Rate Self Extinguishing Heat Distortion at 264 PSI 4. Dimensions and Tolerance 160 F 3. Visual Inspection Pipe shall be homogenous throughout and free from visible cracks, holes or foreign materials. Pipe shall be free from blisters, wrinkles and dents. This inspection shall be made on each length of pipe. Dimensional measurements of plastic pipe will be made on the outside diameter, wall thickness and out -of- roundness. Pipe not meeting these requirements shall be rejected. Dimensions and tolerances shall be in accordance with Commercial Standard CS 256 - 63. 5. Marking and Identification All PVC pipe shall be continuously and permanently marked with the following information: manufacturer's name, pipe size, class or schedule, type of pipe and material. When used for potable eater line, the pipe shall bear the seal of the National Sanitation Foundation for potable water pipe. 510 06/09/88 Page 21 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6. PVC Pipe Fittings All fittings shall be of schedule 40 or heavier plasticized polyvinyl chloride. 7. Inspection and Testing of Materials Test certificates from a testing laboratory and /or guarantee by the manufacturer satisfactory to the Engineer shall be furnished for the pipe and fittings to be incorporated in the work. As required by the Engineer, certificates shall be submitted for other materials to be incorporated in the work. These certificates, stating that the materials meet the requirements of the specifications, will be required before permission is given to incorporate such materials in the work. The cost of this inspection and testing will be paid for by the Contractor and shall be included in his price bid for such materials complete in place. Any material brought on the ground for use in the work and deemed by the Engineer as unsuitable or not in conformity with the specifications shall be removed from the site of the work by the Contractor upon receipt of written notice from the Engineer to that effect. 8. Handling of PVC Pipe and Fittings The Contractor is cautioned to exercise care in handling, loading, unloading and storing PVC pipe and fittings. All PVC pipe and fittings will be stored under cover before using and will be transported in a vehicle with a bed long enough to allow the length of pipe to lay flat so as not to be subject to undue bending or concentrated external load at any point. Any section of pipe that has been dented or damaged will be discarded until said section of pipe is cut out and rejoined with a coupling. 9. Threaded Connections On PVC to metal connections, the Contractor shall work the metal connections first. A nonhardening pipe dope such as Permatex #2 or equal shall be used on all threaded PVC to metal joints and light wrench pressure is all that should be used. Vhere threaded PVC connections are required, use threaded PVC adapters into which the pipe may be welded 510 06/09/88 Page 22 ri e P (k) Polyvinyl Chloride Water Pipe 1. General All polyvinyl chloride (PVC) vater pipe shall be of the rigid (UNPLASTICIZED) type and must bear the National Sanitation Foundation seal of approval for potable vater pipe. Each joint of pipe shall consist of single continuous extrusion; bells or other components attached by solvent welding are not acceptable. Pipe shall be pressure rated at 200 psi (SDR -14) or 150 psi (SDR -18) as indicated. Pipe shall have push -on, rubber gasket joints of the bell and spigot type vith thickened integral bells or of the double spigot type vith thickened coupling sleeves vith rubber gasket joints. The vall thickness of each pipe bell and joint coupling must be greater than the standard pipe barrel thickness. Clearance must be provided in every gasket joint for both lateral pipe deflection and for linear expansion and contraction. Concrete thrust blocking shall be placed behind bends and tees. Unless the granular bedding envelope material is pipe bedding stone, concrete support blocking shall also be placed between the bottom of the fitting and the undisturbed trench bottom. 2. Applicable Specifications Except as modified or supplemented herein, PVC pipe shall meet the following standards: AVVA C -900, SDR 18 or SDR 14 for PVC Pressure Pipe, in 4, 6, 8 and 12 inch nominal sizes, having Cast Iron Pipe size outside diameters. Fittings used vith PVC Pressure pipe shall be AVVA C -110 or AVVA C -153 cast iron fittings. Standard sizes, dimensions and tolerances shall be as follows: SDR -18 SDR -14 Nominal Outside Diameter Wall Thickness Wall Thickness Size Avg. Tolerance Min. Tolerance Min. Tolerance (inches) (inches) (inches) (inches) (inches) (inches) (inches) 4 4.800 , 0.009 0.267 .0.032 0.343 .0.041 6 6.900 .0.011 0.383 0.046 0.493 .0.059 8 9.050 .0.015 0.503 .0.060 0.646 .0.078 12 13.200 .0.015 0.733 0.088 0.943 .0.113 510 06/09/88 Page 23 Pipe (1) All pipe 4 inches and larger must be approved Underwriter's Laboratories for use in buried eater supply and fire protection systems. 3. Material Requirements All pipe and fittings shall be made from clean, virgin, NSF approved, Class 12454B PVC. Clean reworked materials generated from the manufacturer's own production may be used within the current limits of the referenced AVVA C - 900. 4. Marking Permanent marking on each joint of pipe shall include the following at intervals of not more than 5 feet: 2. Joint Material 3. Pipe Markings Nominal pipe size and OD base (e.g., 4 CIPS). The type of plastic material (e.g., PVC 12454 -B). The standard Dimension Ratio and the pressure rating in psi f " r water at 73 F (e.g., SDR 18, 150 psi). The AWWA or ASTM designation with which the pipe complies (e.g., AWVA C 900). The manufacturer's name or code and the National Sanitation Foundation (NSF) mark. Polyvinyl Chloride (PVC) Pipe (Nonpressure) and Fittings 1. General Where PVC sewer or wastewater pipe is indicated, it shall conform to the requirements of ASTM D 3034, SDR 35 or ASTM F 679, having T -1 wall thickness. Minimum cell classification shall be 12354 -B as defined by ASTM D1784. PVC pipe and fitting shall have elastomeric gasket joints conforming to ASTM D 3212; gaskets to ASTM F 477. Permanent marking on the pipe shall include the following at intervals of not more than 5 feet: Manufacturer's name and /or trademark. 510 02/20/92 Page 24 Pipe Nominal pipe size. PVC cell classification per ASTM D 1784 (Min. 12354_3) ASTM designation and legend: -For pipe 6 inch to 15 inch size; ASTM D3034, type PSM, SDR -35 PVC sever pipe -For pipe 18 inch and larger: ASTM F 679, T -I vall PVC sever pipe. 4. Fitting Markings Fittings shall be clearly marked as follows: Manufacturer's name or trademark, Nominal size, The material designation "PVC ", PSM, and This designation, "Specification D3034 ". (m) Steel Pipe 1. Standard Weight ASTM A 53, Schedule 40. 2. Extra Heavy Weight Seamless ASTM A 53, Schedule 80. 3. Encasement Pipe Welded or Seamless pipepiles ASTM A -252, Grade 2 4. Fittings Nipples and fillings extra strong Federal Specification WW -N 351 or WW -P 521. 5. Coatings Black or galvanized as indicated. (n) Welded Steel Pipe and Fittings for Water -Pipe 1. General Reference Standards Specification. a. Specifications of the American Water Works Association (AWWA) listed below shall apply to this Section. 510 02/20/92 Page 25 Pipe 510 3. Job Conditions C -200 Steel Water Pipe 6 inches and larger. C -205 Cement- Mortar Protective Lining and Coating for Steel Vater Pipe, 4 inches and larger, Shop Applied. C -206 Field Welding of Steel Water Pipe. C -207 Steel Pipe Flanges for Vatervorks Services, Sizes 4 inches through 144 inches. C -208 Dimensions for Steel Vater Pipe Fittings. C -602 Cement - Mortar Lining of Water Pipelines, 4 inches and larger in Place. 2. Submittals a. Furnish shop dravings, product data, design calculations and test reports as described below: (1) Certified copies of mill tests confirming the type of materials used in steel plates, mill pipe flanges and bolts and nuts to shoe compliance vith the requirements of the applicable standards. (2) Complete and dimensional working dravings of all pipe layouts. Shop drawings shall include the grade of material, size, vall thickness of the pipe and fittings, type and location of fittings and the type and limits of the lining and coating systems of the pipe and fittings. (31 Product data to shov compliance of all couplings, supports, fittings, coatings and related items. a. The internal design pressure of all steel pipe and fittings shall be as indicated. b. The interior of all steel pipe for potable eater, 4 inches and larger, shall be cement- mortar lined. 4. Manufacturing a. Description Pipe shall comply with AVVA C -200. 06/09/88 Page 26 Pipe 510 Nominal pipe diameter shall be the inside diameter of lining or pipe barrel, unless otherwise designated in Job Conditions. b. Wall Thickness 5. Fittings a. Welded (1) Circumferential deflection of all pipe in -place shall not exceed 2.0 percent of pipe diameter. (2) Diameter (1) Steel pipe.vall thickness shall be designed for the internal and external loads specified in this section. The cylinder thickness needed to resist internal pressure shall be based on an allowable stress in the steel equal to 1/2 the minimum yield stress of the material used. Fabricated steel fittings shall be of the same material as pipe and shall comely with AWA C -208. 6. Flanges a. Flanges shall comply with the requirements of AWA C - 207, Class D or Class E. The class shall be based on operating conditions and mating flanges of valves and equipment. b. Gaskets shall be cloth- inserted rubber, 1/8 inch thick. c. Flanges shall be flat faced with a serrated finish. 7. Pipe Joints a. Lap Joints for Field Welding (1) Lap joints for field welding shall conform to AWA C -206. This item applies only to pipes 72 inches in diameter and larger. (2) The bell ends shall be formed by pressing on a hydraulic expander or a plug die. After forming, the minimum radius of curvature of the bell end at any point shall not be less than 15 times the thickness of the steel shell. Bell ends shall be formed in a manner to avoid impairment of the physical properties 06/09/88 Page 27 Pipe P 510 06/09/88 of the steel shell. Joints shall permit a lai at least 1 1/2 inches when assembled. The longitudinal or spiral weld on the inside of the bell end and the outside of the spigot end on each section of pipe shall be ground flush with the plate surface. The inside edge of the bell and the outside edge of the spigot shall be scarfed or lightly ground to remove the sharp edges or burrs. b. Bell and Spigot Joints with 0 -Ring Gasket (1) Bell and.spigot joints with rubber gasket shall conform to AVVA C - 200. (2) The bell and spigot ends shall be so designed that when the joint is assembled, it will be self- centered and the gasket will be confined to an annuler space in such manner that movement of the pipe or hydrostatic pressure cannot displace it. Compression of the gasket when the joint is completed shall not be dependent upon water pressure in the pipe and shall be adequate to ensure a watertight seal when subjected to the specified conditions of service. Bell and spigot ends shall be welded on preformed shapes. The bell and spigot ends shall conform to the reviewed shop drawings. 8. Interior and Exterior Protective Surface Coatings a. Exterior Surface to be mortar coated shall conform to AVVA C -205 for shop application and AVVA C -602 for field application. Pipe materials shall be the product of an organization which has had not less than 5 years successful experience manufacturing pipe materials and the design and manufacture of the pipe, including all materials, shall be the product of one company. b. All surfaces except as noted in c and d below shall receive shop application of mortar lining and coating. c. Field Welded Joints. After installation, clean, line and coat unlined or uncoated ends adjacent to welded field joints, including the veld proper, as specified for pipe adjacent to the veld. d. Machined Surfaces. Shop coat machined surfaces with a rust preventative compound. After jointing surfaces, remaining exposed surfaces shall be coated per a and b above. Page 28 Pipe (o) Corrugated Metal Pipe 1. General Pipe shall be corrugated continuous lock or welded seam helically corrugated pipe. Corrugated metal pipe may be galvanized steel, aluminized steel or aluminum conforming to the following: Galvanized Steel AASHTO M 218 Aluminized Steel AASHTO M 274 Aluminum AASHTO M 197 where reference is made herein to gage of metal, the reference is to U.S. Standard Gage for uncoated sheets. Tables in AASHTO M 218 and AASHTO M 274 list thicknesses for coated sheets in inches. The Tables in AASHTO H 197 list thicknesses in inches for clad aluminum sheets. Sampling and testing of metal sheets and coils used for corrugated metal pipe shall be in accordance with SDHPT Test Method Tex - 708 -I. Damaged spelter coating shall be repaired by thoroughly vire brushing the damaged area and removing all loose, cracked or veld burned spelter coating. The cleaned area shall be painted 'with a zinc dust -zinc oxide paint conforming to Federal Specifications TT -P 641b. Damaged pipe shall be rejected and removed from the project. Damaged aluminized coating shall be repaired in accordance with the manufacturer's recommendations. The following information shall be clearly marked on each section of pipe: Thickness and corrugations Trade Hark of the manufacturer Specification compliance 2. Fabrication a. Steel Pipe Galvanized or aluminized steel pipe shall be full circle or arch pipe conforming to AASHTO M 36, Type I or Type II as indicated. It may be fabricated with circumferential corrugations, lap joint construction with riveted or spot welded seams or it may be fabricated with helical corrugations with continuous helical lock 510 06/09/88 Page 29 Pipe P seam or ultra high frequency resistance butt - velded seams. b. Aluminum Pipe Pipe shall conform to AASHTO M 196, Type I, circular pipe or Type II, pipe arch as indicated. It may be fabricated with circumferential corrugations, lap joint construction with riveted or spot welded seams or it may be fabricated with helical corrugations with a continuous helical lock seam. Portions of aluminum pipe that are to be in contact with high chloride concrete or metal other than aluminum, shall be insulated from these materials by a coating of bituminous material. The coating applied to the pipe or pipe arch to provide an insulation between the aluminum and other material shall extend a minimum distance of 1 foot beyond the area of contact. 3. Selection of Gages The pipe diameter, permissible corrugations and required gauges shall be as indicated. 510 06/09/118 Page 30 Pipe 510 TABLE I Corrugated Steel 2 2/3 inches by 1/2 inch Corrugations Pull Circle Pipe Minimum Cover, Thickness Top of Pipe to Pipe Top of 0.064 In. 0.079 In. 0.109 In. 0.138 In. 0.168 In. Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage Inches Maximum Fill 8eight Above Top of Pipe in Feet * 12 12 112 122 157 164 171 15 12 90 97 125 131 137 18 12 75 81 104 109 114 21 12 64 70 82 94 98 24 12 56 60 69 78 86 27 12 50 54 60 67 73 30 12 49 51 55 59 65 33 12 41 44 52 55 59 36 12 37 41 49 52 55 42 12 41 45(57) 46(90) 49(94) 50(98) 48 12 43(50) 44(78) 46(82) 47(86) 54 12 - 43 43(70) 44(73) 45(76) -60 12 - 43(63) 43(66) 44(69) 66 12 - - - 43(60) 43(62) 72 12 - - 43(55) 43(57) 78 12 - - 42(53) 84 12 - - - - 42(49) Fill heights in ( ) apply when pipe is 5 percent vertically longated prior to installation. Note: Thickness in inches, as shown above, refers to the coated metal after galvanizing. 06/09/88 Page 31 Pipe The line in the gage columns is drawn below the maximum diameter allowed for that gage. Table II Corrugated Steel 3 inches x 1 inch or 5 inches x 1 inch Full Circle Pipe Minimum Cover, Thickness Top of Pipe to Pipe Top of 0.064 In. 0.879 In. 0.109 In. 0.138 In. 0.168 In. Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage Inches Maximum Pill Height Above Top of Pipe in Feet * 48 12 48 52(60) 56(89) 61(107) 60(118) 54 12 43 48(53) 52(79) 55(95) 58(105) 60 12 38 46(48) 49(71) 51(85) 53(95) 66 12 35 43 47(65) 48(78) 50(86) 72 12 32 40 45(59) 47(71) 48(79) 78 12 29 36 44(54) 45(66) 46(73) 84 12 34 43(51) 44(61) 45(68) 90 12 - 32 43 44(57) 44(63) 96 12 - 30 43 43(53) 44(59) 102 24 - 28 42 43(50) 43(56) 108 24 - - 39 42 43(53) 114 24 - - 37 42 42(50) 120 24 - - 35 42 42 * Fill heights in ( ) apply when pipe is 5 percent vertically elongated prior to installation. Note: Thickness in inches, as shown above, refers to the coated metal after galvanizing. The line in the gage columns is drawn below the maximum diameter allowed for that gage. 510 06/09/88 Page 32 Pipe 510 Table III Corrugated Aluminum 2 2/3 inches x 1/2 inch Corrugations Full Circle Pipe Minimum Cover, Thickness Top of Pipe to Pipe Top of 0.060 In. 0.075 In. 0.105 In. 0.135 In. 0.164 In. Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage Inches Maximum Fill Height, Above Top of Pipe in Feet * 12 12 45 45 77 - - 15 12 36 37 56 - 18 12 28 30 36 43 49 24 12 22 23 25 28 31 27 12 20 21 23 25 27 30 12 18 18 21 23 24 33 12 16 17 20 21 22 36 12 - 15 19 20 21 42 12 - 19 19 20 48 15 - - 18 18 19 54 16 - - 17 18 18 60 16 - - - 16 18 66 18 - - 12 15 72 20 - - 18 11 78 20 - - - 9 84 20 - - 7 * Fill heights in ( ) apply when pipe is 5 percent vertically elongated prior to installation. Note: Thickness in inches, as shown above, refers to the clad sheet. The line in the gage columns is drawn below the maximum diameter alloyed for that gage. 06/09/88 Page 33 Pipe 510 Table IV Corrugated Aluminum 3 inches x 1 inch or 6 inches x 1 inch Corrugations Pull Circle Pipe Minimum Cover, Thickness Top of Pipe to Pipe Top of 0.060 In. 0.075 In. 0.105 In. 0.135 In. 0.164 In. Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage Inches Maximum Pill Height Above Top of Pipe in Peet * 30 12 27 30 35 41 46 36 12 23 24 28 30 34 42 14 21 22 24 26 28 48 16 20 20 22 23 24 54 18 19 19 20 21 22 60 20 18 19 20 20 21 66 22 - 18 19 19 20 72 24 - 17 19 19 19 78 26 - - 18 18 19 84 26 - 15 18 18 90 24 - _ 16 18 96 24 14 16 102 30 — - 14 108 30 _ 12 114 30 10 120 30 _ 06/09/88 Page 34 8 * Fill heights in ( ) apply when pipe is 5 percent vertically elongated prior to installation. Note: Thickness in inches, as shown above, refers to the clad sheet. The line in the gage columns is drawn below the maximum diameter allowed for that gage. Pipe 510 For pipe arch, rtie design size and permissible corrugations only will be indicated, since the shape and minimum gage for pipe arch 'shall be as designated in Tables A, 8, C or D for the specified design size and corrugation for metal pipe. Table A Steel Pipe Arch 2 2/3 Inch by 1/2 Inch Corrugations H - Loading Equivalent Min. Min. Coated Diameter Design *Span *Rise Cover Gage Thickness Full Cir. Size Inches Inches Inches Required Inches Pipe Inches 1 17 13 12 16 0.064 15 2 21 15 12 16 0.064 18 3 28 20 12 16 0.064 24 4 35 24 12 16 - 0.064 30 5 42 29 12 14 0.079 36 6 49 33 12 14 0.079 42 7 57 38 12 12 0.109 48 8 64 43 12 12 0.109 54 9 71 47 12 10 0.138 60 * The fill heights for all sizes of pipe arch are limited to a maximum of 7 feet. A tolerance of plus or minus 1 inch or 2 percent of equivalent circular diameter, whichever is greater, will be permissible in span and rise, with all dimensions measured from the inside crests of the corrugations. Table B Steel Pipe Arch 3 Inch by 1 Inch Corrugations H -20 Loading Min. Min. Coated Diameter nt Design *Span *Rise Cover Gage Thickness Pull Cir. Size Inches Inches Inches Required Inches Pipe Inches 7 53 41 12 12 0.109 48 8 60 46 12 12 0.109 54 9 66 51 12 12 0.109 60 10 73 55 12 12 0.109 66 11 81 59 12 12 0.109 72 12 87 63 12 12 0.109 78 13 95 67 12 12 0.109 84 14 103 71 18 12 0.109 90 15 112 75 18 12 0.109 96 16 117 79 18 12 0.109 102 17 128 83 24 12 0.109 108 18 137 87 24 10 0.138 114 19 142 91 24 10 0.138 210 06/09/88 Page 35 Pipe 510 * The fill heights for all sizes of pipe arch are limited to a maximum of 10 feet. A tolerance of plus or minus 1 inch or 2 percent of equivalent circular diameter, whichever is greater, will be permissible in span and rise, with all dimensions measured from the inside crests of the corrugations. Table C Steel Pipe Arch 5 Inch by 1 Inch Corrugations H -20 Loading Equivalent Min. Min. Coated Diameter Design Size Inches *Rise Cover Gage Inches Required Thickness Pipe Inches 11 81 59 12 12 0.109 72 12 87 63 12 12 0.109 78 13 95 67 12 12 0.109 84 14 103 71 18 12 0.109 90 15 112 75 18 12 0.109 96 16 117 79 18 12 0.109 102 1 7 128 83 24 10 0.138 108 18 137 87 24 10 0.138 114 19 142 91 24 10 0.138 120 * The fill heights for all sizes of pipe arch are limited to a maximum of 10 feet. A tolerance of plus or minus 1 inch or 2 percent of equivalent circular diameter, whichever is greater, will be permissible in span and rise, with all dimensions measured from the inside crests of the corrugations. Table D Aluminum Pipe Arch. 2 2/3 Inch by 1/2 Inch Corrugations 8 Loading Equivalent Min. Min. Coated Diameter Design *Span *Rise Cover Gage Thickness Full Cir. Size Inches Inches Inches Required Inches Pipe Inches 1 17 13 12 16 0.060 15 2 21 15 12 16 0.060 18 3 28 20 12 14 0.075 24 4 35 24 12 14 0.075 30 5 42 2 9 18 12 0.105 36 6 49 33 18 12 0.105 42 7 57 38 18 10 0.135 48 8 64 4 3 18 10 0.135 54 9 71 47 18 8 0.164 60 06/09/88 Page 36. Pipe P * A11 dimensions are measured from the inside crests of the corrugations. A tolerance of plus or minus 1 inch or 2 percent of the equivalent circular diameter, whichever is greater will be permissible in span and rise. The fill heights for all sizes of pipe arch are limited to a maximum of 7 feet. 4. Joint Material Except as otherwise indicated, coupling bands and other hardware for galvanized or aluminized steel pipe shall conform to AAS8T0 H 36 for steel pipe and AAS8TO M 196 for aluminum pipe. Field joints for each type of corrugated metal pipe shall maintain pipe alignment during construction and prevent infiltration of soil material during the life of the installation. Coupling bands shall be not more than 3 nominal sheet thicknesses lighter than the thickness of the pipe to be connected and in no case lighter than 0.052 inch for steel or 0.048 inch for aluminum. Coupling bands shall be made of the same base metal and coating (metallic or otherwise) as the pipe. Coupling bands shall lap equally on each of the pipes being connected to form a tightly closed joint after installation. Pipes furnished with circumferential corrugations shall be field jointed with corrugated locking bands. This includes pipe vith helical corrugations which has reformed circumferential corrugations on the ends. The locking bands shall securely fit into at least one full circumferential corrugation on each of the pipe ends being coupled. The minimum width of the corrugated locking bands shall be as shown below for the corrugation which corresponds to the end circumferential corrugations on the pipes being joined: 10 1/2 inches vide for 2 2/3 inches x 1/2 inch corrugations. 12 inches vide for 3 inches x 1 inch or 5 inches x 1 inch corrugations. Helical pipe without circumferential end corrugations will be permitted only when it is necessary to join a new pipe to an existing pipe which vas installed with no circumferential end corrugations. In this event pipe furnished with helical corrugations at the ends shall be field jointed with either helically corrugated bands or 510 06/09/88 Page 37 Pipe 510 with bands with projections or dimples. The minimum width of helically corrugated bands shall conform to the following: 12 inches wide for pipe diameters up to and including 72 inches. 14 inches wide for 1 inch deep helical end corrugations. Bands with projections shall have circumferential rows of projections with one projection for each corrugation. The width of bands with projections shall be not less than the following: 12 inches wide for pipe diameters up to and including 72 inches. The bands shall have 2 circumferential rows of projections. 16 1/4 inches wide for pipe diameters of 78 inches and greater. The bands shall have 4 circumferential rows of projections. Unless otherwise indicated, all bolts for coupling bands shall be 1/2 inch diameter. Bands 12 inches wide or less will have a minimum of 2 bolts and bands greater than 12 inches vide shall have a minimum of 3 bolts. Galvanized bolts may be hot dip galvanized conforming to AASHTO M 232, mechanically galvanized to provide the same requirements as AASHTO M 232 or electrogalvanized per ASTM A 164 Type RS. 5. Additional Coatings or Linings a. Bituminous Coated Bituminous Coated pipe or pipe arch shall be as indicated both as to base metal and fabrication and in addition shall be coated inside and out with a bituminous coating which shall meet the performance requirements set forth herein. The bituminous coating shall be 99.5 percent soluble in carbon bisulphide. The pipe shall be uniformly coated inside and out to a minimum thickness of 0.05 inch, measured on the crests of the corrugations. The bituminous coating shall adhere to the metal tenaciously, shall not chip off in handling and shall protect the pipe from deterioration as evidenced by samples prepared from the coating 06/09/88 Page 38 Pipe P 510 material successfully meeting the Shock Test and Flow Test in accordance with Test Method Tex - 522 -C. b. Paved Invert tihere a Paved Invert is indicated, the pipe or pipe arch, in addition to the fully coated treatment described above, shall receive additional bituminous material of the same specification as above, applied to the bottom quarter of the circumference to for a smooth pavement with a minimum thickness of 1/8 inch above the crests of the corrugations. c. Cement Lined (1) General Except as modified herein, pipe shall conform to AASHTO M 36 for lock seam or welded helically corrugated steel pipe. Pipe shall be of full circle and shall be fabricated with two annular corrugations for purposes of joining pipes together with band couplers. Lock seams shall develop the seam strength as required in Table 3 of AASHTO M 36. Concrete lining shall conform to the following: Composition Concrete for the lining shall be composed of cement, fine aggregate and water that are well mixed and of such consistency as to produce a dense, homogenous, nonsegregated lining. Cement Portland Cement shall conform to AASHTO M 85. Aggregates shall conform to AASHTO M 6 except that the requirements for gradation and uniformity of gradation shall not apply. Mixture The aggregates shall be sized, graded, proportioned and thoroughly mixed with such proportions of cement and eater as will produce a homogenous concrete mixture of such quality that the pipe will conform to the design requirements 06/09/88 Page 39 Pipe P 510 indicated. In no case, however, shall the proportions of Portland Cement, blended cement or Portland Cement plus pozzolanic admixture be less than 470 lb /cu. yd of concrete. Thickness The lining shall have a minimum thickness of 1/8 inch above the crest of the corrugations. Lining Procedures The lining shall be plant applied by a machine traveling through a stationary pipe. The rate of travel of the machine and the rate of concrete placement shall be mechanically regulated so as to produce a homogenous nonsegregated lining throughout. Surface Finish The lining machine shall also mechanically trovel the concrete lining as the unit moves through the pipe. Certification Furnish manufacturer's standard certification of compliance upon request of the purchaser. Joints Pipe shall be joined together vith coupling bands made from steel sheets to an in :icated thickness of 0.064 inch (12 ga.). Coupling bands shall be formed with two corrugations that are spaced to provide seating in the third corrugation of each pipe end vithout creating more than 1/2 inch ± annular space between pipe ends vhen joined together. Bands shall be drawn together by two 1/2 inch galvanized bolts through the use of a bar and strap suitably welded to the band. When 0 -ring gaskets are indicated they shall be placed in the first corrugation of each pipe and shall be compressed by 06/09/88 Page 40 Pipe 1 . 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 (2) d. Fiber Bonded tighrpning the coupling hand. Rubber O -ring gaskets shall conform to Section 5.9, ASTM C 361. Causes for Rejection Pipe shall be subject to rejection on account of failure to conform to any of the indications. Individual sections of pipe may be rejected because of any of the following: Damaged ends, where such damage would prevent making satisfactory joint. Defects that indicate poor workmanship and could not be easily repaired in the field. Severe dents or bends in he metal itself. If concrete lining is broken out, pipe may be rejected or at the discretion of the Engineer, repaired in the field in accordance with the manufacturer's recommendation. Hairline cracks or contraction cracks in the concrete lining is to be expected and does not constitute cause for rejection. Vhere fiber bonded pipe is indicated, the pipe or pipe arch shall be formed from sheets vhose base metal shall be as indicated. In addition, the sheets shall have been coated with a layer of fibers, applied in sheet form by pressing them into a molten metallic bonding. If a paved invert is indicated it shall be in accordance with the procedure outlined above. The test for spelter coating above is waived for fiber bonded pipe. 6. Slotted Drain Storm Severs The pipes for the slotted drain and slotted drain outfall shall be helically corrugated, lock seam or welded seam pipe. Materials and fabrication shall be in accordance with the above. The metal thickness shall be a minimum 16 gage. The chimney assemblies shall be constructed of 3/16 inch welded plate or machine formed 14 gage galvanized steel sheets. The height of the chimney required will be as indicated. Metal for the welded plate slot shall meet 06/09/88 Page 41 Pipe P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 06/09/88 Veld areas and the heat affected zones where the slot is welded to the corrugated pipe shall be thoroughly cleaned and painted vith a good quality asphalt base aluminum paint. 7. Mortar the requirements of ASTM A 36 and the completed plate slot shall be galvanized after fabrication in accordance vith ASTM A 123. Mortar shall be composed of 1 part Type I Portland Cement and 2 parts clean, sharp mortar sand suitably graded for the purpose and conforming in other respects to the provisions for fine aggregate of Item No. 403, "Concrete maybeeaddedrtotthet mix, butHinrnoecasemshallliteexceed 10 percent by weight of the total dry mix. (p) Vitrified Clay Pipe Vitrified Clay Pipe shall conform to ASTM C 700, extra strength clay pipe. The joint material for vitrified clay pipe shall conform to ASTM C 425 compression joints for vitrified clay bell and spigot pipe. 510.3 Construction Methods (1) General Prior to commencing this work, all erosion control and tree protection measures required shall be in place and all utilities located and protected as sec forth in "General Conditions of Agreement ". Clearing the site shall conform to Item No. 102, "Clearing and Grubbing ". Maintenance of environmental quality protection shall comply with all requirements of "General Conditions of Agreement" and Item No. 601, "Salvaging and Placing Topsoil ". The-Contractor shall conduct his work such that a reasonable minimum of disturbance to existing utilities will result. Particular care shall be exercised to avoid the cutting or breakage of all existing utilities. If at any time the Contractor damages the utilities in place through his operations, the Contractor shall immediately notify the owner of the utility to make the necessary repairs. When active wastewater sewer lines are cut in the trenching operations, temporary flumes shall be provided across the trench while open and the lines shall be restored when the backfilling has progressed to the original bedding lines of the sever so cut. The Contractor shall inform utility owners sufficiently in advance of the Contractor's operations to enable such utility owners to reroute, provide temporary detours or to make other adjustments to utility lines in order that the Contractor may proceed with his Page 42 Pipe work with a minimum of delay and expense. The Contractor shall cooperate with all utility owners concerned in effecting any utility adjustments necessary and shall not hold the City liable for any expense due to delay or additional work because of conflicts arising from existing utilities. The Contractor shall do all trenching in accordance with the provisions and the directions of the Engineer as to the amount of trench left unfilled at any time. All excavation and backfilling shall be accomplished as indicated and in compliance with State Statutes. Where excavation for a pipe line is required in an existing City street, a street cut permit is required and control of traffic shall be as indicated in accordance with the Texas Manual on Uniform Traffic Control Devices. Wherever existing utility branch connections, sewers, drains, conduits, ducts, pipes or structures present obstructions to the grade and alignment of the pipe, they shall be permanently supported, removed, relocated or reconstructed by the Contractor through cooperation with the owner of the utility, structure or obstruction involved. In those instances where their relocation or reconstruction is impractical, a deviation from line and grade will be ordered by the Engineer and the change shall be made in the manner directed. — Adequate temporary support, protection and maintenance of all underground and surface utility structures, drains, sewers and other obstructions encountered in the progress of the work shall be furnished by the Contractor, at his expense and as approved by the Engineer. Where traffic must cross open trenches, the Contractor shall provide suitable bridges. For trenches less than 2 feet in width, sheet steel plates having a minimum thickness of 1/2 inch shall be used. For trenches up to 4 feet in width, sheet steel plates having a minimum thickness of 3/4 inches shall be used. In all cases, the plates shall overlay the top of the trench a minimum of 18 inches on both sides and secured by asphalt. Adequate provisions shall be made for the flow of sewers, drains and watercourses encountered during construction and any structures which may have been disturbed shall be satisfactorily restored upon completion of work. When rainfall or runoff is occurring or is forecast by the U.S. Weather Service, the Contractor shall not perform or attempt any excavation or other earth moving work in or near the flood plain of any stream or watercourse or on slopes subject to erosion or runoff, unless given specific approval by the Engineer. When such conditions delay the work, an extension of time for working day contracts will be allowed in accordance with "General Conditions of Agreement ". 510 06/09/88 Page 43 Pipe 1 t 1 1 1 1 1 1 1 1 i 1 1 1 1 (2) Water Line /New Wastewater Line Separation Installation of new water or wastewater lines shall conform to the following: Where feasible, water and wastewater lines shall be no closer to each other than 9 feet between outside diameters in all directions and shall be in separate trenches. If the 9 foot separation cannot be achieved, any portion of a new gravity wastewater line within 9 feet in any direction (between OD's) of a potable water line, shall be in a separate trench and constructed of ductile iron (thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWWA C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12 inches. If the lines are parallel, they shall not be closer than 4 feet horizontally or 2 feet vertically between OD's with the wastewater lower than the water line. If the lines cross, they may be no closer than 6 inches vertically between OD's with the sewer below the water line and one standard 20 foot length of ductile iron (thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWVA C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12 inches. Unless wastewater manholes and the connection to the sewer can be made completely watertight and tested for no leakage, they must be installed so as to provide a minimum of 9 feet of horizontal clearance from an existing or proposed water line. All force mains shall be ductile iron pipe, of the class indicated, Thickness Class 50 minimum. (3) Utility and Storm Sewer Crossings When the Contractor installs a pipe that crosses under a utility structure or storm sewer and the top of the pipe is within 18 inches of the bottom of the utility structure, the pipe shall be encased as specified in Item No. 505, "Concrete Encasement and Encasement Pipe ", for a distance of at least 1 foot on either side of the ditch line of the utility structure or the storm sewer. Unless otherwise specified by the Engineer, concrete encasement will not be required for ductile iron (thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWWA C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12 inches. When the Contractor installs a pipe that crosses over a utility structure or storm sewer and the top of the utility structure or storm sewer is within 18 inches of the bottom of the pipe, the pipe shall be either ductile iron (thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWWA C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12 inches, unless otherwise specified by the Engineer. Where trenches wider than 12 inches cross under existing wastewater lines, the sewer lines shall be replaced with one 20 foot joint of ductile iron (thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWWA C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12 inches, centered over the trench. 510 05/24/91 Page 44 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 (4) Trench Excavation Underground piped utilities to be constructed in an open cut in accordance with Federal regulations, applicable State Statutes conforming to Item Yo. 509, "Trench Safety Systems" and with a trench width and depth described below. When pipe is to be constructed in fill above the natural ground, Contractor to construct embankment to an elevation not less than one foot above tope of pipe, after which trench is excavated. Required vertical sides shall be sheeted and braced as indicated to maintain the sides of the required vertical excavation throughout the construction period. Adequacy of the design of sheeting and bracing shall be the responsibility of design professional. Contractor shall be responsible for installation as indicated. After the pipe has been laid and the backfill placed and compacted to 12 inches above the top of the pipe, any sheeting, shoring and bracing required may be removed with special care to insure that the pipe is not disturbed. As each piece of sheeting is removed, the space left by its removal must be thoroughly filled and compacted with suitable material and provisions made to prevent the sides of the trench from caving until the backfill has been completed. Any sheeting left in place will not be paid for and shall be considered subsidiary to the pipe item bid. (5) Trench Width Trenches for water and wastewater lines shall have a minimum vidth of 6 inches and a maximum width of 1 foot on each side beyond the outside surfaces of the pipe bell or coupling. Trenches for Storm Sewers up co 42 inches shall have a width of 1 foot on each side beyond the outside surfaces of the pipe. Pipes more than 42 inches shall have a trench width not to exceed 18 inches on each side beyond the outside surfaces of the pipe. If trench width within the pipe zone exceeds this maximum, the entire pipe zone shall be refilled with approved backfill material, thoroughly compacted to a minimum of 95 percent of maximum density as determined by SDHPT Test Method Tex -114_E and then re- excavated to the proper grade and dimensions. Excavation along curves and bends shall be so oriented that the trench and pipe are approximately centered on the centerline of the curve, using short lengths of pipe and /or bend fittings if necessary. For all utilities co be constructed in fill above natural ground, the embankment shall first be constructed to an elevation• not less than 1 foot above the top of the utility, after which excavation for the utility shall be made. (6) Trench Depth and Depth of Cover All pipe and in -line appurtenances shall be laid to the grades indicated. The depth of cover shall be measured from the established finish grade, natural ground surface, subgrade for 06/09/88 Page 45 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 staged construction, street or other permanent surface to the top or uppermost projection of the pipe. (a) Where not otherwise indicated, all water piping shall be laid to the following minimum depths: 1. Water piping installed in undisturbed ground in easements of undeveloped areas which are not within existing or planned streets, roads or other traffic areas shall be laid with at least 36 inches of cover. 2. Water piping installed in existing streets, roads or other traffic areas shall be laid with at least 48 inches of cover below finish grade. 3. Unless approved by the Engineer, installation of water piping in proposed new streets will not be permitted until paving and drainage plans have been approved and the roadway traffic areas excavated to the specified or standard paving subgrade, with all parkways and sidewalk areas graded according to any applicable provisions of the drainage plans or sloped uniformly from the curb line to the right of way line. Piping and appurtenances installed in such proposed streets shall be laid with at least 36 inches of cover below the actual subgrade. (b) Where not otherwise indicated, all wastewater piping shall be laid to the following minimum depths: 1. Wastewater piping installed in natural ground in easements or other undeveloped areas which are not within existing or planned streets, roads or other traffic areas shall be laid with at least 42 inches of cover. 2. Wastewater piping installed in existing streets, roads or other traffic areas shall be laid with at least 66 inches of cover. 3. Wastewater piping installed in such proposed streets shall be laid with at least 48 inches of cover below the actual subgrade. (7) Classification of Excavation Excavation will not be considered or paid for as a separate item of work, so excavated material vill not be classified as to type or measured as to quantity. Full payment for all excavation required for the construction shall be included in the various unit or lump sum contract prices for the various items of work installed, complete in place. No extra compensation, special treatment or other consideration will be allowed due to rock, pavement, caving, sheeting and bracing, falling or rising water, 06/09/88 Page 46 Pipe 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 (9) working under and in the proximity of trees or any other handicaps to excavation. (8) Devatering Excavation Underground piped utilities shall not be constructed or the pipe laid in the presence of water. All water shall be removed from the excavation prior to the pipe placing operation to insure a dry firm granular bed on which to place the underground piped utilities and shall be maintained in such unwatered condition until all concrete and mortar is set. Removal of water may be accomplished by bailing, pumping or by a well -point installation as conditions - :arrant. In the event that the excavation cannot be dewatered to the point where the pipe bedding is free of mud, a seal shall be used in the bottom of the excavation. Such seal shall consist of Class B concrete, conforming to Item No. 403, "Concrete for Structures ", with a minimum depth of 3 inches. Trench Conditions Before attempting to lay pipe, all water, slush, debris, loose material, etc., encountered in the trench must be pumped or bailed out and the trench must be kept clean and dry while the pipe is laid and backfilled. Where needed, sump pits shall be dug adjoining the trench and pumped as necessary to keep the excavation devatered. Backfilling shall closely follow pipe laying so that no pipe is left exposed and unattended after initial assembly. All open ends, outlets or other openings in the pipe shall be protected from damage and shall be properly plugged and blocked watertight to prevent the entrance of trench water, dirt, etc. The interior of the pipeline shall at all times be kept clean, dry and unobstructed. Where the soil encountered at established footing grade is a quicksand, saturated or unstable material, the following procedure shall be used unless other methods are indicated: All unstable soils shay_ be removed to a depth of a minimum 2 feet below bottom of piped utility or as required to stabilize the trench foundation. Such excavation shall be carried out for the entire trench width. All unstable soil so removed shall be replaced with a concrete seal, foundation rock or coarse aggregate materials placed across the entire trench width in uniform layers not to exceed 6 inches, loose .measure and compacted by mechanical tamping or other means which will provide a stable foundation for the utility. r)5/09/ 8p, Page 47 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 Forms, sheathing and bracing, pumping, additional excavation and backfill required in unstable trench conditions shall be subsidiary to pipe bid. (10) Blasting All blasting shall conform to the provisions of "General Conditions of Agreement ". (11) Removing Old Structures When out of service masonry structures or foundations are encountered in the excavation, such obstructions shall be removed for the full width of the trench and to a depth of 1 foot belov the bottom of the trench. When abandoned inlets or manholes are encountered and no plan provision is made for adjustment or connection to the new sewers, such manholes and inlets within the construction limits shall be removed completely to a depth 1 foot below the bottom of the trench. In each instance, the bottom of the trench shall be restored to grade by backfilling and compacting by the methods provided above. Where the trench cuts through storm or vastevater severs which are known to be abandoned, these sewers shall be cut flush with the sides of the trench and blocked with a concrete plug in a manner satisfactory to the Engineer. When old structures are encountered, vhich are not visible from the existing surface and are still in service, they shall be protected and adjusted as required to the finished grade. (12) Lines and Grades Grades, lines and levels shall conform to Section No. 00341, "Grades, Lines and Levels ". Any damage to the above by the Contractor shall be re- established at the Contractor's expense. The location of the lines and grades indicated may be changed only by direction of the Engineer and it is understood that the Contractor vill be paid on the basis of his unit contract prices bid for such work actually performed and will make no claim for damages or loss of anticipated profits due to the change of location or grade. The Contractor shall furnish, at his expense, all necessary batter boards or electronic devices for controlling the work. Batter boards shall be of adequate size material and shall be supported substantially. The boards and all location stakes must be protected from possible damage or change of location. The Contractor shall furnish good, sound twilled lines for use in achieving lines and grades and the necessary plummets and graduated poles. The Contractor shall submit to the Engineer at least 6 copies of any layout plans from the pipe manufacturer for review and approval. The Contractor shall submit the layout plans at least 06/09/88 Page 48 Pipe USE/PIPE MATERIAL CEMENT STAB B[CEIIL SAID PEA GRAVEL PIPE BEDDING SICKE Uncrushed Gravel Crushed Gravel Crushed Stone WATERNELDED STEEL x X VATER/PILMIllt X X WA'IIR/ALL OIffiRS UP 1O 15 INCH ID x x x x x VA'IIR/ALL OTHERS LARGER THAN 15BXHID x x x x WASTEWATER/ ALL UP TO 15IIJ_1ID X X X X X WASIEWATER/ALL LARGER THAN 15DU ID X X X X 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 1 30 days in advance of any actual construction of the project. The E ngineer will forward all comments of the review to the Contractor for revision. Revisions shall be made and forwarded to the Engineer for his acceptance. Prior to commencement of the Project, reviewed layout plans will be sent to the Contractor marked for construction. Should the Contractor's procedures not produce a finished pipe placed to grade and alignment, the pipe shall be removed and relayed and the Contractors procedures modified to the satisfaction of the Engineer. NO additional compensation shall be paid for the removal and relaying of pipe required above. (13) Sirplis Excavated materials: Excess material or material which cannot be node suitable for use in enbanknaits will be declared surplus by the Engineer and shall became the property of the Contractor to dispose of off site at a permitted fill site, without injury to the City or any individual. Such surplus material shall be removed from the cork site promptly following the completion of the portion of the utility involved. (14) Pipe Bedding Envelope: Pipe shall be installed in a continuous bedding envelope. The envelope shall extend for the full trench width to a depth of 6 inches below the pipe. The envelope shall rise to springline of stormwater pipe and to 12 inches above water and wastewater pipe. The following requirements and limitations shall govern bedding material selection. The compatibility of the bedding envelope with the excavated and backfill materials shall be ensured to minimize particle migration into pea gravel and pipe bedding stone envelopes. Measures taken to minimize migration shall be subsidiary to the pipe, unless specifically provided by the bid items, for pipe with sand as an approved bedding material. Specific measures for other pipes shall be as agreed upon by change order unless otherwise provided by the contract. (a) Standard Bedding Materials SI7ATER/O0tErE STCRMWATER/METAL 05/0L90 Page 49 X X X j X X X X Pipe X 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (b) Requirements & Limitations (1) Lnpervious cut -off walls of compacted clay or other approved methods shall be used to isolate sand beddings from pea gravel or stone beddings (2) Pea gravel or pipe bedding stone shall be used in blasted trenches. (3) Crushed gravel or crushed stone shall not be used with polyethylene tubing or polyethylene film wrap. 510 05/01/90 (4) Uncrushed gravel may be used with polyethylene film wrap in trenches up to 6 feet in depth and in deeper trenches where ample trench width, a trenie, or other conditions will allow controlled placement of the gravel without damaging the polyethylene wrap. (5) Sand, alone, shall not be used in watercourses, in trenches where groundwater is present, or in trenches with grades greater than 5 percent. (6) Pea gravel and pipe bedding stone, alone, shall not be used in trenches with soils prone to vibratory or hydraulic particle migration. Pea gravel or pipe beddirr stone mixed with sand, stabilized backfill, filter fabric envelopment of the bedding materials, or other approved materials or means shall be used wherever non- cemaitatious, silty, or sandy soils as determined by the Engineer are encountered with plasticity indices less than 20. (7) Pea gravel and pipe bedding stone, alone, shall not be used in street right - of-way within 5 feet of subgrade elevation in trenches 3 feet or wider. (8) When pea gravel or pipe bedding stone is premixed with sand, a sufficient volume of sand shall be used to fill all voids within the bedding envelope. The mixture shall be mechanically compacted in place. (9) Sand bedding envelopes shall be compacted to a minimum of ninety percent (909.') of the density as determined in accordance with test method ASIM D 698. (15) laying Pipe: No pipe shall be installed in the trench until excavation has been completed, the bottom of the trench graded and the trench completed as indicated. Laying of corrugated metal pipes on the prepared foundation shall be started at the outlet ad with the separate sections firmly joined together, with outside laps of circumferential joints pointing upstream and with longitudinal l ps on the sides Any metal in joints which is not protected by galvanizing shall be coated with a suitable asphaltum paint. Proper facilities shall be provided for hoisting and lowering the sections of pipe into the trench without damaging the pipe or disturbing the prepared Page 50 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 foundation and the sides of the trench. Any pipe which is not in alignment or which shows any undue settlement after laying or is damaged, shall be taken up and relaid without extra compensation. Multiple installations of corrugated pipe or arches shall be laid with the centerlines of individual barrels parallel. When not otherwise indicated, clear distances of 2 feet between outer surfaces of adjacent pipes shall be maintained. No debris =hall remain in the drainvays or drainage structures. All backfill in streets and under structures will be tested by the City and must satisfy the specified density requirements conforming to Section 00344, "Testing Laboratory Services" before final acceptance )f or payment for the work. All recommendations of the manufacturer shall be carefully observed during handling and installation of each material. Unless otherwise indicated, all materials shall be delivered to the project by the manufacturer or" agent and unloaded as directed by the Contractor. Each piece shall be placed facing the proper direction near :o where it :ill be installed. The interior of all pipe, fittings and other accessories shall be kept free from dirt and foreign matter at all times and stored in a manner that will protect them from damage. Stockpiled materials shall be stacked so as to minimize entrance of foreign matter. The interior of all pipeline components shall be clean, dry and unobstructed -hen installed. Piping materials shall not be skidded or rolled against other pipe, etc. and under no circumstances shall pipe, fittings or other accessories be dropped or jolted. During handling and placement, materials shall be carefully observed and inspected and any damaged, defective or unsound materials shall be marked, rejected and removed from the job site. Minor damage shall be marked and repaired in a manner satisfactory tc the Engineer. Joints which have been placed but not joined, backfilled, etc., shall be protected in a manner satisfactory to the Engineer. (16) Assembling of Pipe Angular spacing of all joints shall meet the manufacturer's recommendations for the pipe and accessories being used. Side outlets shall be rotated so that the operating stems of valves will be vertical when the valves are installed. Pressure pipe shall be laid with bell ends Facing the direction of pipe installation. Pipe end bells shall be placed upgrade for all wastewater lines. 06/09/88 Page 51 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Orientation marks, when applicable, shall be in their proper position before pipe is seated. Before joining any pipe, all foreign matter, lumps, blisters, excess coal tar coating, oil or grease shall be removed from the ends of each pipe and the pipe ends shall then be wire brushed and wiped clean and dry. Pipe ends shall be kept clean until joints are made. Every precaution shall be taken to prevent foreign material from entering the pipe during installation. No debris, tools, clothing or other materials shall be placed in the pipe. (17) Joints (a) Mortar Pipe ends shall be clean, free of asphalt or other contaminants which will inhibit the bond of the mortar to the pipe. The pipe ends shall be moistened immediately prior to placing the mortar in the joint. (b) Cold Applied Preformed Plastic Gaskets The pipe ends shall be clean and the joint material applied to the dry pipe. In cold weather, the joint material shall be heated to facilitate the seal of the joint. (c) 0 - Ring Just before making a joint the ends of the pipe shall be clean, dry, free of any foreign matter, lump blisters, excessive coal tar coating and grease or oil and shall be wire brushed. The gasket and the inside surface of the bell shall be lubricated with a light film of soft vegetable soap compound to facilitate assembly of the joint. The rubber gasket shall be stretched uniformly as it is placed in the spigot groove to insure a uniform volume of rubber around the circumference of the groove. The spigot shall be centered in the bell, the pipe pushed home uniformly and brought into true alignment. Bedding material shall be placed and tamped against pipe to secure the joint. (d) Push -on Joints Just before making a joint, the bell and spigot rings shall be clean and dry. The gasket and the inside surface of the bell shall be lubricated with a light film of soft vegetable soap compound (Flax Soap) to facilitate telescoping the joints. The rubber gasket if not factory installed shall be stretched uniformly as it is placed in the spigot groove to insure a uniform volume of rubber around the circumference of the groove. The spigot shall be centered in the bell, the pipe pushed home and brought into true alignment. It shall be 510 06/09/88 Page 52 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 secured • - ere :. n oecdinq material vhicn is carefully under and m on each side o: e tamped hoe. Care should oe taken to prevent d`.:t or foreign • - entering tae _Dirt space. (e) 3olted Joints All flarced. , .,e__a:.-_: or other Doi :ad joints shall be joir.ec - n h high nuts , :: • 'oh cf hig strength, low alloy, Y, - re::: an: _c.._nless steel or be coated as a =c.e ii Iron :.pea (f) Sc .•e --- - For olumSir.a - :pe. (18) Press':_.. PiLa -aging (a) 't:` --, ..:,hare:. -- Cy Pipe (CSC) and Welded Steel Aggregate cement, _ 57.11_ -_ a_ indicated in "Mortar" herein __ . _ -doss between the bell and c: the , c' and contained by a joint w t - cJer =ce :ea::-meaaan by the pipe manufacturer. The wrapper s`.eii have a minimum width cf 7 inches for 30 inch and s maller and 9 inches for larger pipe, secured to the pipe by "3and Iron' steel straps. The grout shall be poured in one continuous cperaticn in such manner that after shrinkage and curing the joint recess .i11 be completely filled. Mortar for :ne inside recess s' be of consistent of pia ^ter. The inside races; between the bell and spigot shall be filled 'wit: mortar after the pipe joint on either side of the recess has been backfilied and well tamped with no less than one pipe joint installed ahead of the pipe forming the re -less. The mortar shall completely fi :1 the recess and shall be trowelled and packed into place and finished off s-ooch *with the irsid- ,f :he p The Contra =to- ;!ail - - - tint aft the r ae mortar has sec and make repairs of any pocl'ets, crac r c. other defects caused by shrinkage to the satisfaction of the Engineer. The inside surface shall ;.e c_ea :ed of any mortar droppings, cement, eater, slurry, etc., before they have become set and shall be cleared of any o :her tcreign ratter. The inside surface of the pipe shall be left clean and smooth. Pipe shall be handled at all times with ride nonabrassive slings, belts or other equipment designed to prevent damage to the coating and all zu ^h ee.ipr.ent shall be kept in such repair that Its •_J•• use is not injurious to the Coating. The use of ton q ^, bare pinch-oars, chain slings, rope slings vt:hou; ranvaf .0 'e ;s. _anvis or composition belt 510 06/09/38 ". Pipe .p e 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 . 1 1 1 1 010 slings with protruding rivets, pipe hooks without proper padding or any other handling equipment which the Engineer deems to be injurious to the coating shall not be permitted. The spacing of pipe supports required to handle pipe shall be adequate to prevent cracking or damage to the he cement mortar lining. (19) Placing Pipe in Tunnels Piping installed as a carrier pipe in a tunnel, encasement pipe, etc., shall have uniform alignment, grade, bearing and conform to the reviewed shop drawings. All necessary skid blocks, rails, bedding material, grout cradle or paving, bracing, blocking, etc., as stipulated by the Contract or as may be required to provide and maintain the required pipe alignment and grade, shall be provided by the Contractor at no cost except as provided by the Bid Items. This shall include at least 1 scree -type hold down jack per joint of pipe to prevent flotation of the pipe, unless otherwise indicated. Such carrier piping shall have flexible bolted or gasketed push -on joints or Concrete Steel Cylinder pipe installed as follows: (a) 21 Inch Pipe and Smaller Prior to placing the pipe in the tunnel, the inside joint recess at the bell shall be buttered with cement mortar. After the joint is engaged, the excess mortar shall be smoothed by pulling a tight fitting swab through the joint. The pipe joints shall then be welded rigid by placing 3 segments of veld, having a minimum length of 9 inches each and equally spaced around the joint. Cement mortar protection shall then be placed in the normal manner to the exterior of the joint and allowed to harden sufficiently to avoid dislodgement during installation. If time is of the essence, a quick setting compound may be used. (b) 24 Inch Pipe and Larger Each length of pipe shall be pushed into the tunnel as single units. A flexible mastic sealer shall be applied to the exterior of the joint prior to joint engagement. The surfaces receiving the mastic sealer shall be cleaned and primed in accordance with the manufacturer's recommendation. Sufficient quantities of the mastic sealer shall be applied to assure complete protection of all steel in the joint area. The interior of the joint shall be filled with cement mortar in the normal manner after the pipe is in its final position within the tunnel. 06/09/88 Page 54 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 (20) Temporary Pipe Plugs, Caps, Bulkheads and Trench Caps Temporary plugs, caps or plywood bulkheads shall be installed to close all openings of the pipe and fittings when pipeline construction is not in progress. Standard plugs shall be inserted into the bells of all dead ends of pipes, tees or crosses and spigot ends shall be capped. All end plugs or caps shall be secured to the pipe as provided under Item No. 507, "Bulkheads ". Trench caps shall be reinforced Class D concrete as indicated. (21) Corrosion Control (a) Protective Covering Unless otherwise indicated, all flanges, nuts, bolts, threaded outlets and all other iron or steel components buried and in contact with earth or backfill shall be wrapped with 8 -mil (minimum) polyethylene film meeting ANSI /AVVA C -105 to provide a continuous wrap. (b) Corrosion ;'onitoring System 1. ' If indicated the corrosion monitoring system shall be furnished and installed to meet the following requirements: a. Bonds shall be provided between steel cylinders of adjacent pipe sections and all noninsulating joints as necessary to assure electrical continuity except where electrical isolation is required. The joint bonds shall be designed: (1) with sufficient slack to allow for a total joint displacement of 1/2 inch. (2) Using insulated copper cable metallurgically bonded to adjacent cylinders. All bare copper and steel at the connection shall be insulated by an approved means. b. Intermediate bonds for the prestress vire of embedded cylinder prestressed concrete pipe shall also be provided as required to minimize attenuation. The intermediate bonds shall be in the form of steel straps, embedded in the outer surface of the concrete core directly upon which the prestress wire is tightly wound. The size and number of straps shall be designed to provide uniform current distribution to all embedded metallic surfaces of the pipe. 06/09/88 Page 55 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 c. Electrical isolarinn in the form of either flexible or rigid insulating fittings as specified herein shall be provided as required to obtain electrical discontinuity. d. Flexible insulating fittings required shall be style 39 insulating couplings as manufactured by Dresser Industries, 41 Fisher Avenue, Bradford, PA 16701 or equal. e. Rigid insulating fittings required shall be insulated vith fullface gaskets and combination bolt sleeves and washers for flanges as manufactured by Central Plastics Co., P.O. Box 762, Shawnee, OK 74801 or equal. f. Corrosion test stations shall be installed on the pipeline at: (1) All buried line crossings. (2) The beginning and end of the portions of the • pipeline to be monitored. a. Both sides of insulating fittings. b. Intermediate locations along the line, such that the test stations are no more than 1,000 feet apart. c. For the embedded cylinder prestressed concrete pipe alternative, test stations, with wires originating at the prestress wire at the midpoint of the pipelaying length at the above locations, shall also be provided. g. Test stations shall be of the two -vire type with one of the vire being sized (No. 6 AVG or larger) such that it can be used for bonding. The other vire, for determining pipe -to -soil potentials, shall be No. 12 AVG or larger. Both leads shall be continuous (without splices) and laid with sufficient slack to prevent stress. The leads shall be insulated with 600 -volt rated insulation suitable for direct burial. Prior to backfilling, the insulation shall be inspected for defects. All defects shall be repaired by approved methods. h. Test stations shall be of the flush type (terminal below grade) or the above surface type, protected as required for permanency. The flush type shall be installed in developed, urban areas (streets, alleys, sideways, etc.) and the above- surface type 06/09/88 Page 56 Pipe P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (mounted on a post) shall be installed in cross - country areas (rangeland, farmland, etc.). 'Mere practicable, test stations shall be located at or closely adjacent to clearly identifiable topographical features (fence line, road intersection, section line, etc.) of the pipeline right of way. i. The Contractor shall perform tests as required to determine the following and correct the corrosion - monitoring system to comply with these specifications: 3• 1. Pipeline electrical continuity. 2. Effectiveness of insulating joints. 3. Test station integrity. 4. Static pipe -to -soil potentials at each test station. 5. Soil resistivity at each test station. All design, installation and testing shall be consistent with sound corrosion engineering practice. (22) Pipe Anchorage, Support and Protection Pressure pipeline tees, plugs, caps and bends exceeding 22 1/2 degrees; other bends as directed shall be securely anchored by suitable concrete thrust blocking or by approved metal harness. Unless otherwise indicated, on 24 inch or larger piping, all bends greater than 11 1/4 degrees shall be anchored as described herein. Storm severs on steep grades shall be lugged as indicated. (a) Concrete Thrust Blocking Concrete for use as reaction or thrust blocking shall be Class B conforming to Item No. 403, "Concrete for Structures ". Concrete blocking shall be placed between solid ground and the fitting to be anchored. The area of bearing on the pipe and on the ground shall be as indicated or directed by the Engineer. The blocking shall, unless otherwise indicated, be so placed that the pipe, fittings and joints will be accessible for repair. The trench shall be excavated at least 6 inches outside the outermost projections of the pipe or appurtenance and the trench walls shaped or undercut according to the detail 510 06/09/88 Page 57 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 drawings or as required to provide adequate space and bearing area for the concrete. The pipe and fittings shall be adequately weighted and laterally braced to prevent floating, shifting or straining of the pipeline while the concrete is being placed and taking initial set. The Contractor shall be solely responsible for the sufficiency of such restraints. (b) Hetal Thrust Restraint Fabricated thrust restraint systems such as those described below may be approved for use instead of concrete blocking. To obtain approval, the project plans must include sufficient drawings, notes, schedules, etc., to assure that the proposed restraints as installed will be adequate to prevent undesirable movement of the piping components. Such restraint systems may only be used where and as specifically detailed and scheduled on approved project plans. 1. Thrust Harness A metal thrust harness of tie rods, pipe clamps or lugs, turnbuckles, etc., may be approved. All carbon steel components of such systems, including nuts and washers, shall be hot -dip galvanized; all other members shall be cast ductile iron. After installation, the entire assembly shall be wrapped with 8 mil polyethylene film, overlapped and taped in place vith duct tape to form a continuous protective wrap. The number, size and arrangement of rods, lugs, etc., shall be specifically detailed on the approved plans. 2. Restrained Joints Piping or fitting systems utilizing integral mechanically restrained joints may be approved. All components of such systems shall be standard manufactured products fabricated from cast ductile iron, hot -dip galvanized steel, brass or other corrosion resistant materials and the entire assembiy'shall be protected with a continuous film wrap as described for 1. above. Location, configuration and description of such products shall be specifically detailed on the plans. (Add -on attachments such as retainer glands, all- thread rods, etc., are not acceptable.) (c) Concrete Encasement, Cradles, Caps and Seals • When trench foundation is excessively wet or unstable or installation of eater or wastewater pipe will result in less 06/09/88 Page 58 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 than 30 inches of cover, Contractor shall notify Engineer. Engineer may require Contractor to install a concrete seal, cradle, cap, encasement or other appropriate action. All concrete cap, etc., shall be continuous and begin and end within 6 inches of pipe joints. Concrete cap, cradle and encasement shall conform to City of Austin Standards No. 510 -1, 510 -9 and 510 -7 respectively. The pipe shall be well secured to prevent shifting or flotation while the concrete is being placed. (d) Anchorage Bulkheads Concrete bulkheads keyed into the undisturbed earth shall be placed as indicated to support and anchor the pipe and /or backfill, against end thrust, slippage on slopes, etc. Concrete material and placement shall be Class A, Item No. 403, "Concrete for Structures ". (e) Trench Caps, Concrete Rip -Rap and Shaped Retards Vhere called for by the Contract or as directed by the Engineer, concrete trench caps, concrete rip -rap and /or shaped retards shall be placed as detailed by the standard drawings as protection against erosion. Concrete material and placement shall be Class B, Item No. 403, "Concrete for Structures ". (23) Wastewater Connections (a) Connections to Mains 12 Inches and Smaller All branch connections of nev main lines shall be made by use of manholes. • Service stubs shall be installed as indicated. Minimum grade shall be 1 percent and minimum over shall be 4 1/2 feet at the curb. Standard plugs shall be installed in the dead end before backfilling. Vhere a service connection to a main 12 inches or smaller is indicated, a vye, tee or double vye shall be installed. Where a service connection to a main 15 inches or larger is indicated, a field tap may be made vith the pipes installed crovn to crovn. The tap should be made conforming to the pipe manufacturer's recommendations vith the Engineer's approval. Vhere not otherwise indicated, service connections to mains shall be installed at an angle approximately 45 degrees above the horizontal. 510 06/09/88 Page 59 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (b) Connections to the Existing Systea Unless otherwise specified by the Engineer, all connections made to existing mains shall be made at manholes with the crown of the inlet pipe installed at the same elevation as the crown of the existing pipe. Service stubs installed on the existing system shall be installed by use of tapping saddles unless otherwise approved by the Engineer. Extreme care shall be exercised to prevent material from depositing in the existing pipe as the taps are being made. When connections to existing mains are made, a temporary plug approved by the Engineer must be installed dovnstream in the manhole to prevent water and debris from entering the existing system before final acceptance. These plugs shall be removed after the castings are adjusted to finish grade or when final acceptance is given. (24) Water System Connections The Contractor shall, at his expense, make all necessary connections of new piping or accessories to the existing water system. To minimize any inconvenience from outages, the Contractor shall schedule all such connections in advance and such schedule must be approved by the Engineer before beginning any work. (a) Shutoffs The City will make all shutoffs on existing water mains. The Contractor will be required to notify the Engineer's field representative on the job at least 72 hours prior to the desired time for any shutoff. The Engineer's field representative shall notify any affected utility customers at least 24 hours prior to the shutoff. The Water Utility will make the shutoff after ensuring that all appropriate measures have been taken to protect the water system, customers and employees. The City will operate all valves to fill existing mains. Where a newly constructed main has not been placed in service and has only one connection to the public water supply, the contractor may operate one valve to fill the main after approval has been obtained from the Water Utility. The operation of the valve is to be conducted under the immediate supervision of the Engineer's field representative. (b) Wet Connections to Existing Water System The Contractor shall make all wet connections called for by the Contract or required to complete the work. A wet connection shall include draining and cutting into existing piping and connecting a new pipeline or other extension into the existing pressure piping, forming an addition to the water transmission and distribution network. 510 11/22/91 Page 60 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 The contract price for vet connections shall be full payment for all necessary shutoffs, excavation, removing plugs and fittings, pumping eater to drain the lines, cutting in new fittings, blocking and anchoring piping, bedding and backfilling, placing the lines and service and all site cleanup. No water containing detectable amounts of chlorine may be drained, released or discharged until specific planning and appropriate preparations to handle, dilute and dispose of such chlorinated eater are approved in advance by the City and the disposal operations shall be witnessed by an authorized representative from the City. (c) Pressure Taps to Existing Vetter System The Contractor shall make all pressure taps called for by the Contract Documents or required to complete the work. A pressure tap shall consist of connecting new piping to the existing water system by drilling into the existing pipe while it is carrying water under normal pressure without taking the existing piping out of service. Unless otherwise provided by the Contract, the Contractor shall, at his expense, perform all necessary excavation, furnish and install the tapping sleeve, valve and accessories, provide the tapping machine, drill the tap (unless otherwise indicated) and shall block, anchor and backfill the piping, valve and all accessories, place the new piping in service and perform all site cleanup. Where that the City will make the tap, City forces are not obligated or expected to perform any work except to provide tapping machine and drill the actual hole. If City crews are to make the tap, fiscal arrangements must be made in advance at the Taps Office, Avante Plaza, 625 East 10th Street. If a private contractor makes the tap, a W -WW inspector must be present. "Size on size" taps will not be permitted, unless made by use of an approved full circle gasket tapping sleeve. Concrete blocking shall be placed behind and under all tap sleeves 24 hours prior to making the wet tap. (d) Service Connections Tapping of PVC or AC pipe for service connections may be made using either a service clamp or saddle or a tapping sleeve recommended by the manufacturer and approved as satisfactory by the Engineer. Direct tapping will not be permitted. All service connections shall be installed so that the outlet is at an angle of approximately 45 degrees above horizontal at the main line. Precautions should be taken to ensure that the tapping saddle or sleeve is placed on the pipe straight to prevent any binding or deformation of the PVC pipe. The mounting chain or U -bolt strap must be tight. 510 11/22/91 Page 61 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Tapping shall be performed with a sharp shell type cutter so designed that it will smoothly penetrate heavy walled PVC DR14 and 200 psi AC and will retain and extract the coupon from the pipe. (25) Backfilling (a) General Special emphasis is placed upon the need to obtain uniform density throughout the backfill material. The maximum lift of backfill shall be determined by the compaction equipment selected and in no case shall it exceed 18 inches, loose measurement. No heavy equipment, which might damage pipe, will be allowed over the pipe until sufficient cover has been placed and compacted. All internal pipe bracing installed or recommended by the manufacturer shall be kept in place until the pipe bedding and trench backfill have been completed over the braced pipe section. Testing of the completed backfill in streets and under and around structures shall meet the specified density requirements. Initial testing shall not be at Contractor's expense and shall conform to Section 00344, "Testing Laboratory Services." (b) General Corrugated Metal Pipe After the corrugated metal pipe structure has been completely assembled on the proper line and grade and headwalls constructed where indicated; selected material free from rocks over 8 inches in size from excavation or borrow, as approved by the Engineer, shall be placed along both sides of the completed structures equally, in uniform layers not exceeding 6 inches in depth (loose measurement), sprinkled if required and thoroughly compacted between adjacent structures and between the structures and the sides of the trench or for a distance each side of the structures equal to the diameter of the pipe if pipe is laid above the existing ground. Backfill material shall be compacted to the same density requirements as indicated for the adjoining sections of embankment in accordance with the governing specifications thereof. Above the 3/4 point of the structure, the fill shall be placed uniformly on each side of the pipe in layers not to exceed 12 inches, loose measure. Prior to adding each new layer of loose backfill material, until a minimum of 12 inches of cover is obtained over the crown of the pipe, an inspection will be made of the inside periphery of the corrugated metal structure to determine if 510 11/22/91 Page 62 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 any floating, local or unequal deformation has occurred as a result of improper construction methods. (c) Backfill Materials The Engineer may approve any of the following well graded materials: 1. Select trench material 2. Sand 3. Crushed rock cuttings 4. Rock cuttings 5. Foundation Rock 6. Blasted material with fines and rock 7. Cement stabilized material 8. Borrow Within the 100 year flood plain, sand will not be permitted for backfilling. The Engineer shall approve the topsoil for areas to be seeded or sodded. (d) Backfill in Street Right of Way Placement of backfill under pavement structures and within 2 feet of any structures shall be compacted to the required density using any method, type and size of equipment which will give the required compaction without damaging the pipe or bedding. Placement of backfill greater than 2 feet beyond structures in Right of Way shall be conform to (g) belov. The depth of layers, prior to compaction, shall depend upon the type of sprinkling and compacting equipment used and the test results thereby obtained. Prior to and in conjunction vith the compaction operation, each layer shall be brought to the moisture content necessary to obtain the required density and shall be kept level to insure uniform compaction over the entire layer. Testing for density will be in accordance vith Test Method Tex -114 -E and Test Method Tex - 115 -E. Each layer of backfill must provide the density as required herein. Swelling soils (soils with plasticity index of 20 or more) shall be sprinkled as required to provide not less than optimum moisture nor more than 2 percent over optimum moisture content and compacted to the extent necessary to provide not less than 95 percent nor more than 102 percent of the density as determined in accordance with Test Method Tex - 114 - E. Nonsvelling soils (soils with plasticity index less than 20) shall be sprinkled as required and compacted to 510 06/09 Page 63 Pipe 510 the extent necessary to provide not less rhan 95 percent of the density as determined in accordance with Test Method Tex- 114 -E. After each layer of backfill is complete, tests may be made by the Engineer. If the material fails to meet the density indicated, the course shall be reworked as necessary to obtain the indicated compaction and the compaction method shall be altered on subsequent work to obtain indicated density and conform to Section 00344, "Testing Laboratory Services ". At any time, the Engineer may order proof rolling to test the uniformity of compaction of the backfill layers. All irregularities, depressions, weak or soft spots which develop shall be corrected immediately by the Contractor. Should the backfill, due to any reason, lose the required stability, density or finish before the pavement structure is placed, it shall be recompacted and refinished at the sole expense of the Contractor. Excessive loss of moisture in the subgrade shall be prevented by sprinkling, sealing or covering with a subsequent backfill layer or granular material. Excessive loss of moisture shall be construed to exist when the subgrade soil moisture content is more than 4 percent below the optimum of compaction ratio density. Backfill shall be placed from the top of the bedding material to the existing grade, base course, subgrade or as indicated. The remainder of the street backfill shall be Flexible Base, Concrete or Hot Mix Asphalt Concrete as indicated or to replace in kind the surface removed to construct the pipe. (e) Backfill in County Street or State Highway Right of Way All work within the right of way must meet the requirements of (d) above, as a minimum and shall meet the requirements of the permit issued by the County when their requirements are more stringent. Prior to the start of construction, the Contractor will be responsible for contacting the appropriate SDHPT office or County Commissioner's Precinct Office and for coordinating his activities with the operating procedures in effect for utility cut permits and pavement repair under their jurisdiction. Approval for all completed work in the State or County right of way must be obtained from the appropriate Official prior to final payment by the Owner. (f) Backfill in Railroad Right of Way All work within the railroad right of way must meet the requirements of (d) above, as a minimum and shall meet the requirements of the permit issued by the Railroad Owner when their requirements are more stringent. Approval for all completed work in the railroad right of way must be obtained from the Railroad prior to final acceptance. 06/09/88 Page 64 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (g) Backfill in Easements Where not otherwise indicated, Contractor may select whatever methods and procedures may be necessary to restore entire work area to a safe, useful and geologically stable condition with a minimum density of 85 percent or a density superior to that prior to constructs In and near flood plain of all streams and watercourses, under or adjacent to utilities, structures, etc., all backfill shall be compacted to a density of not less than 95 percent conforming to SDRPT Test Method Tex - 114 -E, unless otherwise directed by Engineer. All soil areas disturbed by construction shall be covered with top soil and seeded conforming to Item No. 604, "Seeding for Erosion Control ". All turf, drainvays and drainage structures shall be constructed or replaced to their original condition or better. No debris shall remain in the drainvays or drainage structures. (26) Quality Testing for Installed Pipe (a) Wastewater Pipe Acceptance Testing After construction is complete, Engineer shall determine whether the pipeline is to be tested for infiltration, exfiltration or by the low pressure air test method. Wastewater pipe installed in the City of Austin and its ETJ areas shall be tested for exfiltration or infiltration as described belov in "Exfiltration Test" and "Infiltration Test" or by acceptable low pressure air test, as described below. At the conclusion of either test series, the work shall be further tested for pipeline settlement as described below. The Contractor shall be solely responsible for making proper repairs to those elements which do not pass these test - requirements. (b) Exfiltration Test The pipeline shall be completely filled with water for its complete length or by sections as determined by the Engineer. If tested for its complete length, the maximum head at any point shall not exceed 25 feet unless otherwise indicated. If tested in sections, the manholes in the test section shall be completely filled with water. After the pipeline has been filled and allowed to stand for 24 hours, the amount of exfiltration shall be calculated. Any amount in excess of 200 gallons per inch of inside pipe diameter per mile per day shall be cause for rejection. 510 06/09/AR Page 65 Pipe (c) Infiltration Test When the pipe placed in easements is completed, the upper portion of the ditch backfill shall be removed to a depth of not less than 18 inches below the finished surface and width equal to the original trench width. The trench shall then be flooded with eater until it is completely saturated and eater stands in the ditch a minimum of 12 inches deep. In cases of steep terrain, earthen dikes shall be used to assure that water will stand over the trench. After it is apparent that the trench is completely saturated, the main shall then be inspected with closed- circuit television for infiltration. Any section of the main or any service stub that indicates excessive infiltration shall be cause for rejection. This procedure shall not be used for pipes installed in areas where the P.Z. of the surrounding material is 20 or higher or where the backfill material has a P.I. of 20 or more. (d) Pipeline Settlement Test During the infiltration test or after the exfiltration test, the pipe will be TV inspected for possible settlement. When air testing has been used, water shall be flowed into the pipe to permit meaningful observations. Any pipe settlement which causes excessive ponding of water in the pipe shall be cause for rejection. (e) Low Pressure Air Test of Gravity Flow Wastewater Lines (1) General Wastewater lines in sizes for which the City has testing equipment may, at the discretion of the Engineer, be air tested between manholes. Backfilling to grade shall be completed before the test and all laterals and stubs shall be capped or plugged by the Contractor so as not to alloy air losses which could cause an erroneous test result. Manholes are to be plugged so they are isolated from the pipe and cannot be included in the test. All plugs used to close the sewer for the air test must be capable of resisting the internal pressures and must be securely braced. Place all air testing equipment above ground and alloy no one to enter a manhole or trench where a plugged sever is under pressure. Release all pressure before the plugs are removed. The testing equipment used must include a pressure relief device designed to relieve pressure in the sewer under test at 10 psi or less and must alloy continuous monitoring of the test pressures in order to avoid excessive pressure. Use care to avoid the flooding of the air inlet by infiltrated ground eater. (Inject the air at the upper plug if possible.) Use only qualified personnel to conduct the test. 510 06/09/88 Page 66 Pipe 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 510 (2) Ground water Since the presence of ground water will affect the test results, test holes shall be dug to the pipe zone at intervals of not more than 100 feet and the average height of ground eater above the pipe (if any) shall be determined before starting the test. (3) Test Procedure The Engineer may, at any time, require a calibration check of the instrumentation used. Use a pressure gauge having minimum divisions of 0.10 psi and an accuracy of 0.0625 psi. (One ounce per square inch.) All air used shall pass through a single control panel. Clean the sever to be tested and remove all debris where indicated. Jet the sewer prior to testing. The average back pressure of any groundwater shall be determined (0.433 psi) for each foot of average water depth (if any) above the sever. Add air slowly to the section of sewer being tested until the internal air pressure is raised to 4.0 psig greater than the average back pressure of any ground water that may submerge the pipe. After the internal test pressure is reached, alloy at least 2 minutes for the air temperature to stabilize, adding only the amount of air required to maintain pressure. After the temperature stabilization period, disconnect the air supply. Determine and record the time in seconds that is required for the internal air pressure to drop from 3.5 psig to 2.5 psig greater than the average back pressure of any ground eater that may submerge the pipe. Compare the time recorded with the time required as follows: Pipe Size (Inches)6 8 10 12 15 18 21 24 Time (Minutes) 3 4 5 6 7.5 9 10.5 12 Any drop in pressure, from 3.5 psig to 2.5 psig, in a time less than that required by the above table shall be cause for rejection. Vhen the line tested includes more than one size pipe, the minimum time shall be that given for the largest size pipe included. When lines are air tested, manholes are to be tested separately by exfiltration or infiltration. 06/09/88 Page 67 Pipe 510 (27) Pressure Pipe Hydrostatic Testing After the pipe has been installed and backfilled and all service laterals, fire hydrants and other appurtenances installed and connected, a pressure test, followed by a leakage test, will be conducted by the City. The City will furnish the pump and gauges for the tests. The Contractor will be present and shall furnish all necessary assistance for conducting the tests. The specified test pressures will be based on the elevation of the lowest point of the line or section under test. Before applying the specified test pressure, all air shall be expelled from the pipe. If permanent air vents are not located at all high points, the Contractor shall install corporation cocks at such points. All service laterals and fire hydrant leads, with the hydrant valves closed and nozzle caps open, shall be included in the tests. (a) Pressure Test The entire project or each valved section shall be tested, at a pressure of 200 psi for a sufficient period (approximately 10 minutes) to discover all leaking or defective materials. Repairs shall be made by the Contractor to correct any leaking or defective materials. (b) Pressure Pipe Leakage Test A leakage test will follow the pressure test and be conducted on the entire project or each valved section. The leakage test shall be at 150 psi for at least 1 hour. (1) Allowable Leakage Leakage shall be defined as the quantity of eater that must be supplied into any test section of pipe to maintain the specified leakage test pressure (see above, "Pressure Pipe Leakage Test ") after the air in the pipeline has been expelled and the pipe has been filled with water. No pipe installation will be accepted if the leakage exceeds 25 gallons /24 hours /mile of pipe /inch nominal pipe diameter. ( 25 gpd ) (in. - mi.) (28) Service Charges for Testing No charge will be made to the Contractor for the City's test equipment, inspection, etc., when the test results shov that leakage is within the indicated allowable limits. 06/09/88 Page 68 Pipe 1 _ 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 For each test, either for leakage or for pressure, which fails to meet the indicated requirements, the City's flat charge of S50.00 for such tests will be charged to the Contractor and will be deducted from any funds due the Contractor. (29) Sterilization of Potable Water Lines The Contractor shall protect all piping materials from contamination during storage, handling and installation. Prior to disinfection, the pipeline interior shall be clean, dry and unobstructed. All dirt, debris, gasket lubricant, etc., shall be washed from the line by swabbing with hypochlorite solution and /or flushing with clean vater. The City, at its expense, will supply the test gauges and the concentrated disinfecting material and City personnel will supervise and direct the overall sterilization procedure. The Contractor, at his expense, shall provide all other equipment, supplies and the necessary labor to perform the sterilization under general supervision of the City. (a) Procedure and Dosage All valves shall be arranged to prevent the strong disinfecting dosage from floving back into the existing water supply piping. The new pipeline shall then be completely filled with disinfecting solution by feeding the concentrated chlorine and approved water from the existing system uniformly into the new piping in such proportions that every part of the line has minimum concentration of 50 parts per million (50 ppm or 50 mg /liter) available chlorine. Unless otherwise indicated,, all quantities called for herein refer to measurements by the testing procedures in the current edition of "Standard Methods ". The chlorine concentration of each step in the sterilization procedure shall be verified by chlorine residual determinations. This disinfecting solution shall be retained in the piping for at least 24 hours and all valves, hydrants, etc., shall be operated to disinfect all their parts. After this retention period, the water shall contain no less than 25 parts per million chlorine throughout the treated section of the pipeline. This heavily chlorinated water shall then be carefully flushed from the line until the chlorine concentration is no higher than the residual generally prevailing in the existing distribution system or approximately one part per million. Proper planning and appropriate preparations to handle, dilute and dispose of this strong chlorine solution without causing injury or damage to the public, the water system or the environment must be approved by the City before flushing of the line may begin and the flushing shall be witnessed by an authorized representative of the City. 510 06/09/88 Page 69 Pipe (b) Bacteriological Testing After final flushing of the strong disinfecting solution, eater samples from the line shall be tested for bacteriological quality by the City and must be found free of coliform organisms before the pipeline may be placed in service. One test sample shall be drawn from the end of the main and additional samples collected at intervals of not more than 1000 feet along the pipeline. The Contractor, at his expense, shall install sufficient sampling taps at proper locations along the pipeline. Each sampling tap shall consist of a standard corporation cock installed in the line and extended with a copper tubing gooseneck assembly. After samples have been collected, the gooseneck assembly may be removed and retained for future use. Samples for bacteriological analysis shall be collected only from suitable sampling.taps in sterile bottles treated with sodium thiosulfate. Samples shall not be drawn from hoses, fire hydrants, etc. The City, at its expense, vill furnish the sterile sample bottles and may, at its discretion, collect the test samples with City personnel. _= the initial disinfection fails to produce acceptable sample tests, the disinfection procedure shall be repeated (without extra compensation) until satisfactory test results have been obtained before the piping may be placed in service. (30) Cleanup and Restoration It shall be the Contractor's responsibility to keep the construction site neat, clean and orderly at all times. Cleanup shall be vigorous and continuous to minimize traffic hazards or obstructions along the streets and to driveways. Trenching, backfill and cleanup shall be coordinated as directed by the City. The Engineer shall regulate the amount of open ditch and may halt additional trenching if cleanup is not adequate to alloy for orderly traffic floe and access. Materials at the site shall be stored in a neat and orderly manner so as not to obstruct pedestrian or vehicular traffic. All damaged material shall be removed from the construction site immediately and disposed of in a proper manner. All surplus excavated materials become the property of the Contractor for disposal at his expense. After trenching, the Contractor shall immediately remove all excavated materials unsuitable for or in excess of, backfill requirements. Immediately following the pipe laying work as it progresses, the Contractor shall backfill, grade and compact all excavations as provided elsewhere and shall immediately clean 510 06 /09 /88 Page 70 Pipe 510.4 lfeastuement 510.5 Payment up and remove all taused soil, waste and debris and restore all surfaces and iniprovenents to a condition equal or superior to that before construction began and to an appearance which cariplenetts the surroundings. The Contractor shall grade and dress the top 6 inches of earth surfaces with soil or other material similar and equal to the surrounding, fill and smooth any visible tracks or ruts, replace and reestablish all damaged or disturbed turf or other vegetation and otherwise make every effort to Encourage the return of the entire surface and all impruvenents to a pleasant appearance and useful condition appropriate and complementary to the surrotadings and equal or similar to that before construction began. Pipe will be measured by the linear foot for the various types, sizes and classes Parallel lines will be measured individually. Where a line ties into an existing system, the length of the new line shall be measured fran the visible end of the existing system at the canpleted joint. Unless otherwise indicated, the length of water and wastewater Lines shall be measured along pipe horizontal centerline stationing through fittings, valves, manholes, and other appurtenances. Unless otherwise provided, fitting sizes less than 16 -inch shall be measured by the ton; 16 -inch and larger sizes shall be subsidiary to the pipe. Stornaater pipe shall be measured along the slope of the pipe. Where drainage pipe ties into inlets, headwalls, catch basins, manholes, junction boxes or other structures, that length of pipe tying into the structure wall will be included for measurement but no other portion of the structure length or width will be so included. Pipe depth shall be measur from the existing ground surface in easenetts and fran existing ground surface or proposed street subgrade in the right -of -way, whichever is less, over the centerline of the pipe to the flowline elevation. When pay items are provided for the other canixnents of the system, measurement will be made as addressed hereunder. Payment for pipe, measured as prescribed above, will be made at the unit price bid per linear foot for the various sizes of pipe, of the materials and macs indicated, unless unstable material is encountered or trench excavation and backfill is bid as a separate item. The concrete seal, foundation rock or coarse aggregate shall be paid for at the unit price bid per cubic yard, which shall be full payment for all excavation and removal of unsuitable material and furnishing, placing and compacting the foundation rock, coarse aggregate or other approved material all canplete in place. Excavation and beckfill, when included as a separate pay item, will be measured by Pay Iten No. 510-E or F. Excavation and backfill, when included as pipe installation will not be measured as such but shall be included in the unit price bid for constructing pipe and measured as pipe complete in place including 510 05/01/90 Page 71 Pipe (3) excavation and bnckfill. As established in the bid, pipe including excavation and backfill may be either (1) payment for any and all depths or (2) payment in 2 foot incremental depth. Paymment for pipe excavation will be included in the Bid to be measured methods of measurement uremt and payment methods indicated above aor and paid as s "Structural of the may be measured Excavation and Rackfill" as indicated. Payment shall be full compensation, in accordance with the pay it set in the bid. For excavation, furnishing, hauling and placing pipe including lugs and all incidental and subsidiary materials and work; preparing, shaping, dewatering and shoring of trenches; hauling, planing and preparing bedding; for cconnecting to new or existing systems or structures; for hauling, moving, placing and compacting backfill materials and for all other mincidentais necessary to complete the pipe installation as indicated. (1) Pipe Payment for pipe, measured as prescribed above, will be made at the unit price bid per lineal foot complete- in -pta,o as designed and represented in the plans and other contract documents. The bid price per lineal foot of pipe shall include all clearing, embankment, excavation, bedding materials, particle migration measures, fittings, field constructed joints, collars. temporary plugs, pumping, caps or bulkheads, all necessary lugs, rods or braces, pipe coatings and protection, connections to existing systems, concrete blocking and thrust blocks, disposal of surplus excavated material, laying of pipe, beckfilling, temporary pavement repairs and maintenance, cleanup and all other incidental ccmpon nts necessary to complete the work. Payment will also represent compensation for removal and replacement of pavement, curb, drainage structures, driveways, sidewalks and any other improvements damaged or removed during construction. Pipe shall be paid at the contract unit price for any and all depths or at two foot incremental depths in accordance with the selected method of Pay Item No. 510-A. Items listed above as subsidiary to the pipe will be paid individually only when provided by the bid. No separate payment will be made for welded or harnessed joints required for thrust restraint which are scheduled, indicated, generally required for the pipe material used, or otherwise accepted as an industry standard. Steel cylinder concrete pipe and welded steel pipe fittings shall be subsidiary to the pipe pay item. (2) Concrete Cradles and Seals When called for in the Bid, concrete seals or cradles shall be paid for at the unit contract price bid per linear foot for the size of pipe specified, complete in place. Cmc ete Retards When called for in the Bid, Concrete retards shall be paid under Item No. 593, "Concrete Retards." 510 05/01/90 Page 72 Pipe 1 -- 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (4) Boring, Jacking and Tunneling When called for in the Bid, boring, jacking and tunneling shall be paid under Item No. 501, "Jacking or Boring" or Item No. 502, "Tunneling ". (5) Vet connections to Water Mains Wet connections shall be paid for at the unit price bid per each, complete in place, according to the size of the main that is in service and shall be full compensation for all work required to make the connection and place the pipe in service. Cast iron fittings shall be paid for as a separate item. (6) Fittings Cast iron and ductile iron fittings of the class indicated, furnished in accordance with these specifications will be paid for at the unit price bid per ton, complete in place, according to scheduled weights for mechanical joint fittings furnished, including giands,•bolts and gaskets, as published in the following standards: AVVA C -153 for all fittings in 4 inch through 12 inch sizes, regardless of whether AWVA C -110 or AVVA C -153 fittings are furnished or the type of end connections supplied. AWVA C - 110 for all fittings larger than 12 inch size. Steel cylinder concrete pipe fittings and welded steel pipe fittings will not be paid for separately. The Contractor shall include these in his bid for pipe. (7) Concrete Trench Cap and Encasement Where the distance between the top of the concrete encasement and the top of the trench cap is less than 36 inches, the concrete cap and encasement will be poured as one unit and paid for under this bid item at the contract price bid per linear foot. When the distance above is greater than 36 inches or when the trench cap is placed separately, the trench cap shall be paid for as a separate item, per linear foot, complete in place. (8) Cement Stabilized Backfill Cement - stabilized backfill shall be paid for at the unit price bid per linear foot and shall be full payment to the Contractor for furnishing and installing the required material, mixed, placed and cured complete in place. (9) Concrete Encasement When called for in the Bid, Concrete Pipe Encasement shall be paid under Item No. 505, "Concrete Encasement and Encasement Pipe ". 510 06/09/88 Page 73 Pipe (10) Pressure Taps Pressure taps will be paid for at the unit price bid, complete in place, according to the size tap made and the size main tapped and shall be full payment for furnishing all necessary materials, making the tap, testing and placing the connection in service. (11) Trench Safety Systems vhen called for in Bid, Trench Safety Systems will conform to Item No. 509, "Trench Safety Systems ". (12) In -Place Sliplining vith or without In -Place Pipe Destruction /Replacement As called for in the corresponding bid items, pipe sliplining with or without in -place pipe destruction /replacement shall be paid for at the contract price per linear foot for the specified liner and pipe size and type pipe, at all depths, complete in place. Installation of new services, or reconnection of existing services, to the liner will be paid for at the contract price per each for the specified size and type of service, at all depths, complete in place. (13) Cured Resin Pipe Lining 'Men called for in the bid, cured resin pipe lining will be paid for per linear foot, for the size and type of pipe lined, at all depths, complete in place including all equipment set - ups, video inspection and cleaning of existing pipe. Installation of new services or reconnection of existing services to the relined pipe will be paid for per each, for the specified size and type of service, at all depths, complete in place. Payment, when included as a contract pay item, will be made under one of the following: Pay Item 510 -A: Pay Item No. 510 -A: Pay Item No. 510 -B: Pipe, Dia. (all depths), including Excavation and Backfill - per Linear Foot. Pipe, Dia. ( to depths), including Excavation and Backfill - per Linear Foot. In -Place Sliplining without In -Place Pipe Destruction /Replacement ( Dia. Pipe Lining in Dia. Existing Pipe) - per Linear Foot. Pay Item No. 510 -C: In -Place Sliplining with Pipe Destructiion /Replacement ( Dia. Replacement Pipe in Dia. Existing Pipe) - per Linear Foot. 510 06/09/88 Page 74 Pipe End Pay No. 510 -D: _Installing or Reconnecting Lateral Service to Relined or Replaced Pipe ( Dia. Service) in Dia. Pipe - per Each. Pay Item No. 510 -E: Pipe Excavation, Ft. Width - Per Linear Foot. Pay Item No. 510 -F: Pipe Trench 3ackfill, Ft. width - per Liner Foot. Pay Item No. 510 -G: Concrete Seal or Cradle, Dia. Pipe - Per Linear Foot. Pay Item No. 510 -E: Concrete Trench Cap, Ft. Width - Per Linear Foot. Pay Item No. 510 -I: Concrete Cap and Encasement, Dia. Pipe - Per Linear Foot. Pay Item No. 510 -K: Cement Stabilized Backfi'_1, Dia. Pipe - per Linear Foot. Pay Item No. 510 -M: Foundation Rock - Per Cubic Yard. Pay Item No. 510 -N: Cured Resin Pipe Lining (for Dia. Pipe) - per Linear Foot. Pay Item No. 510 -0: Coarse Aggregate - Per Cubic Yard. Pay Item No. 510 -P: Installing or Reconnecting Lateral Service to Cured Resin Lined Pipe, Dia. Service (for Dia. Main) - per Each. Pay Item No. 510 -T: Pressure Taps, _ Dia. X _ Dia. - Per Each. Pay Item No. 510 -V: wet Connections, _ Dia. x Dia. - Per Each. Pay Item No. 510 -1: Cast Iron or Ductile Iron Fittings - Per Ton. A "W" after the pay item indicates the use for water. A "WV" after the pay item indicates the use for wastewater. Ref: 102, 210, 403, 501, 502, 505, 507, 593, 601, 604 510 Page 75 Pipe 511.1 Description This item to consist of valves furnished and installed as indicated. Unless otherwise indicated, all valves 4 inches and larger shall be AWWA -type valves of suitable design and fully equipped for service buned in the earth, without need for further modification and shall be wrapped with 8 -mil polyethylene film with all edges and laps securely taped to provide a continuous wrap. Where not indicated, the Contractor may use valves with any type end -joint allowed for fittings of the pipe class being used. Unless otherwise indicated, all valve stems shall be adjusted to situate the operating nut not less than 30 inches nor more than 36 Inches below the proposed ground or paving surface of the finished project. 511.2 Materials Contractor to submit descriptive information and evidence that materials and equipment Contractor proposes for incorporation into work is of the kind and quality that satisfies the specified functions and quality. Because City of Austin water has a relatively high pH, bronze parts of valves shall not contain over 16% zinc. Through previous investigation, testing and usage. certain types, brands and models of materials have established a record of prior approval and satisfactory service. Water and Wastewater Standard Products Lists form a part of these Specifications. Should Contractor elect to use any materials from these lists, they should be completely and clearly identified when submitted. (1) Samples, Inspection and Testing Requirements: All tests and inspections called for by the applicable standards shall be performed by the manufacturer. Upon request, results of these tests shall be made available to the purchaser. (2) Other Requirements: .511.3 Valves Item No. 511 Water Valves Each bid shall be accompanied by Complete data covering the operator, including type and size, model number, etc., the manufactuier's name and address of his nearest service facility, the number of turns to fully open or close the valve. detailed instructions for calibrating the limit stops for open and closed positions and any other information which may be necessary to operate and maintain the operator. Complete dirnensional data and installation instructions for the valve assembly as it is to be installed. including the operator. Complete replacement parts lists and drawings, identifying every part for both the valve and operator (1) Iron - Body Gate Valves Unless otherwise indicated, Iron Body Gate Valves, 4" to 12 " -- including Tapping Valves —shall conform to AWWA C509, "Resilient Seated Gate Valves for Water and Sewerage Systems ". Iron Body Gate Valves larger than 12" — including Tapping Valves —shall be double disc, parallel seat valves meeting the requirements of AWWA C500. (a) Stem Seals: All valves shall have approved O -nng type stem seals. At least two O -rings shall be in contact with the valve stem where it penetrates the valve body. (b) Operation: All valves shall have non -nsing stems with a 2" square operating nut, or with a spoke type handwheel when so ordered, tuming clockwise to close. 511 02/19/93 1 Water Vahcs (c) Gearing. Double disc gate valves in 16" and larger sizes shall oe geared and. when necessary for proper bury depth and cover, shall be the honzontal bevel- geared type enclosed in a lubncated gear case. (d) Bypass Unless otherwise indicated, 16 inch and larger gate valves shall be equipped with a bypass of the nonrrsing stem type which meets the same AWWA standard required for the main valve. (e) Valve Ends. Valve ends shall be push -on. flanged or mechanical joint, as indicated or approved. Tapping valves shall have inlet flanges conforming to MSS SP -60, with boll holes drilled per ANSI B16.1 Class 125. Seat nngs and body casting shall be over -sized as required to accommodate full size cutters; the outlet end shall be constructed and dolled to allow the dnlling machine adapter to be attached directly to the valve. (f) Gear Case. All geared valves shall have enclosed gear cases of the extended type, attached to the valve bonnet in a manner that makes it possible to replace the stem seal without disassembly and without disturbing the gears, bearing or gear lubricant. Gear cases shall be designed and fabricated with an opening to atmosphere so that valve leakage past the stem seal does not enter the gear case. (g) Valve Body: Double disc gate valves in 16" and larger sizes installed in the horizontal position shall have bronze rollers. tracks, scrapers, etc. (2) Butterfly Valves: Unless otherwise indicated, all valves shall conform to the current "AWWA" Standard C - 504, "Rubber Seated Butterfly Valves ", Class 1506, except as modified or supplemented herein. (a) Functional Requirements 1. Valves shall be the snort body design and shall have flanged connections on both ends unless otherwise called for. 2. Valves shall be of such design that the valve discs will not vibrate or flutter when operated in a throttled position. Valve discs shall be secured to the shafts by means of keys or pins so arranged that the valve discs can be readily removed without damage thereto. All keys and pins used in securing valve discs to shafts shall be stainless steel or monel. Valve discs shall be stainless steel or ductile iron. ASTM A 536. Grade 65 45 - 12, seating edge shall be stainless steel or other corrosion resistant material. 3. Valve shafts shall be constructed of wrought stainless steel or monel. The ends of the shaft shall be permanently marked to indicate the position of the disc on the shaft 4. All buried valves shall have approved manufacturer's 0-ring type or split V type "Chevron" shaft seals When 0-ring seals are used, there shall be at least two 0-rings in contact with the valve shaft where it penetrates the valve body. On 24 inch and larger valves. the seat shall be completely replaceable and /or adjustable with common hand tools without disassembling the valve from the pipeline. Rubber seats located on the valve disc shall be mechanically secured with stainless steel retainer rings and fasteners. 5. Unless otherwise indicated, valves shall be provided with manual operators with vertical stems and 2 inches square operating nut tuming clockwise to close and equipped with a valve disc position indicator. All keys or pins shall be stainless steel or monel. Buried valves shall have the valve stems extended or adjusted to locate the top of the operating nut approximately 30 inches to 36 inches below finish grade. 6. Unless otherwise indicated, motorized butterfly valves shall be equipped with 230/460 volt, 3 -phase reversing motor operators, extended as required to locate the center line of the operator shaft approximately 4 feet to 4 feet, 6 inches above finish grade. Operators shall be equipped with cast iron or malleable iron manual override hand wheel with a valve position indicator, local push button controls, lighted status /position indicator, torque and travel limit switches and all switches, relays 511 112 /19/93 2 Water Vahcs and controls (except extemal power and signal wrong) necessary for both local and remote operation (b) Performance Requirements 1. Unless otherwise indicated. valve operators shall be sized to seat. unseat. open and close the valve with 150 psi shutoff pressure differential across the disk and allow a flow velocity of 16 feet per second valve second past the disc in either direction. 2. Motorized valve motors shall be capable of producing at least 140 percent of the torque required to operate the valves under conditions of maximum nonshock shutoff pressure without exceeding a permissible temperature rise of 55 degrees Celsius over 40 degrees Celsius ambient; they shall have a duty rating of not less than 15 minutes and shall be capable of operating the valve through 4 1/2 cycles against full unbalanced pressure without exceeding the permissible temperature nse. Motors shall be suitable for operating thee valve under maximum differential pressure when voltage to motor terminals is 80 percent of nominal voltage. Motor bearings shall be permanently lubricated and sealed. (3) Brass (Bronze) Valves: Unless otherwise indicated, brass gate valves shall be those makes and models included in the Standard Product List (SPL WW -174). Brass globe valves by the same manufacturers will be acceptable when required. (4) Air- Vacuum Release Valves (a) Valves shall be combination air- release. air- vacuum units having small and large onfice units contained and operating within a single body or assembled unit. The small onfice system shall automatically release small volumes of air while the pipe is operating under normal conditions. The large air- vacuum onfice system shall automatically exhaust large volumes of air while the pipe is being filled and shall permit immediate re -entry of air while being drained. Valves shall be rated for at least 150 psi maximum normal service pressure. (b) Material Requirements: Valve exterior bodies and covers shall be cast iron. Internal bushings, hinge pins, float guide and retaining screws. pins, etc, shall be stainless steel or bronze. Orifice seats shall be Buna -N rubber. Floats shall be stainless steel, rated at 1000 psi. Unless otherwise indicated, these valves shall be as included in the Standard Products List (SPL WW -367 for water. WW -462 for wastewater force mains). (5) Fire Hydrants: All fire hydrants shall be Dry Barrel, Traffic Model (break- away), Post Type having Compression Type Main Valves (5 1/4" opening). closing with line pressure. Approved models are listed on QPL WW -3 of the Water and Wastewater Utility Standard Products List. (6) Pressure /Flow Control Valves: All control valves to regulate pressure, flow, etc., in City lines shall be models listed in Water and Wastewater Standard Products List. (7) Drain Valves: Drain valve materials and installation shall conform to City of Austin Standard Detail No. 511 -9 or 511 -17. 511 112 /19/93 3 Water Valscs 1 1 11.4 Construction Methods 11) Setting Valves, Drains and Air Releases: Unless otherwise indicated, main line valves, drain valves and piping, air and vacuum release assemblies and other miscellaneous accessones shall be set and jointed in the manner described for cleaning, laying. and jointing pipe. Unless otherwise indicated. valves shall be set in line with the radius point and the corresponding point of curvature or point of tangency of adjacent curbs or nght of way lines. Valves shall be installed so that the tops of operating stems will be at the proper elevation required for the piping at the location indicated above. Valve boxes and valve stem casings shall be firmly supported and maintained, centered and aligned plumb over the valve or operating stem. with the top of the box or casing installed flush with the finished ground or pavement in existing streets. and installed with the top of the box or casing approximately 6 inches below the standard street subgrade in streets which are excavated for paving construction or where such excavation is scheduled or elsewhere as directed by the Engineer. Drainage branches or air blowoffs shall not be connected to any sanitary sewer or submerged in any stream or be installed in any other manner that will permit back siphonage into the distribution system (see "Standard Detail Drawings"). Every drain line and every air release line shall have a full sized independent gate valve flanged directly to the main. Flap - valves, shear gates. etc.. will not be accepted. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 (2) Setting Fire Hydrants: Fire hydrants shall be located in a manner to provide accessibility and in such a manner that the possibility of damage from vehicles or injury to pedestrians will be minimized Unless otherwise directed, the setting of any hydrant snail conform to the following. Hydrants between curb and sidewalk on public streets, shall be installed as shown on Standard 511 -17, with outermost point of large nozzle cap 6" to 18" behind back of curb. Where walk abuts curb, and in other public areas or in commercial areas. dimension from gutter face of curb to outermost part of any nozzle cap shall be not less than 3 feet. nor more than 6 feet. except that no part of a hydrant or its nozzle caps shall be within 6 inches of any sidewalk. Any fire hydrant placed near a street corner shall be no less than 20 feet from the curb line intersection. All hydrants shall stand plumb. those near curbs shall have the 4" nozzle (the large one) facing the curb and perpendicular to it. The hydrant bury mark shall be located at ground or other finish grade. nozzles of all new hydrants shall be approximately 18 inches above grade. Lower barrel length shall not exceed 5 feet. Barrel extensions are not permitted unless approved by the Engineer. Each hydrant shall be connected to the main by 6" ductile iron pipe, a 6 inch gate valve shall be installed in the line for Individual shutoff of each new hydrant Below each hydrant, a drainage pit 2 feet in diameter and 2 feet deep shall be excavated and filled compactly with coarse gravel or broken stone mixed with coarse sand under and around the blow of the hydrant. except where thrust blocking is situated and to a level 6 inches above the hydrant drain opening. No hydrant drainage pit shall be connected to a sanitary sewer. Cover drain gravel with filter fabric to prevent blockage of voids in the gravel by migration of backfill material. The bowl of each hydrant shall be well braced against unexcavated earth at the end of the trench with concrete thrust blocking (taking care not to obstruct the hydrant drain holes) or it shall be tied to the pipe with approved metal harness rods and clamps. Hydrants shall be thoroughly cleaned of dirt or foreign matter before setting. Fire hydrants on mains under construction shall be securely wrapped with a poly wrap bag or envelope taped into place and removed when the mains are accepted and placed in service. (3) Pressure Taps: Refer to Item No. 510.3(24), "Pipe ". (4) Plugging Dead Ends: Standard plugs shall be inserted into the bells of all dead ends of pipes, tees or crosses and spigot ends shall be capped. All end plugs or caps shall be secured to the pipe conforming to Item No. 510.3 (22), "Pipe ". 511 02/19/93 4 Water Vakin 1 1 1 1 1 1 1 1 1 1 1 1 1 (5) Protective Covering: Unless otherwise indicated, all flanges, nuts, bolts, threaded outlets and all other steel component shall be coal tar coated and shall be wrapped with 8 -mil (minimum) polyethylene film meeting ANSI /AWWA Specification C- 105 - current. with all edges and laps taped securely to provide a continuous and watertight wrap. (6) Valve Box, Casing and Cover. Stems of all buried valves shall be protected by valve box assemblies as shown on City of Austin Standard No. 511 -10. Valve box castings shall conform to ASTM A 48. Class 308. Testing shall be verified by the manufacturer at the time of shipment. Each casting shall have cast upon it a distinct mark identifying the manufacturer and the country of origin. (7) Drain Valve Installations: Refer to City of Austin Standards. (8) Air Release Assemblies: Refer to City of Austin Standards. (9) Pressure /Flow Control Valves: Assemblies shall be installed as indicated. (10) Connections to Existing System: Refer to Item No 510, 'Pipe" for connections to the existing system. (11) Shutoffs: Refer to Item No. 510, 'Pipe" for shutoffs. 511.5 Measurement All types of valves will be measured per each. Fire hydrants and drain valves will be measured per each. Fire Hydrant and Drain Valve barrel extensions will be measured per vertical foot. Pressure /Flow control valve assemblies and both manual and automatic air release assemblies will be measured per each. 511.6 Payment Payment shall be full compensation in accordance with the pay item set in the bid, for excavation, furnishing. hauling and placing valves and barrel extensions including anchorage and all Incidental and subsidiary materals and work; preparing, shaping, dewatering, shoring of trenches, bedding, placing and compacting backfill materials and for all other incidentals necessary to complete the installation, as indicated, complete in place. Payment for iron fittings and for wet connections are covered in Item No. 510.6. 'Pipe ". (1) Valves: Valves will be paid for at the unit price bid for the size and type valve Installed, including valve stem casing and cover, excavation and backfill, setting, adjusting to grade, anchoring In place, and other appurtenances necessary for proper operation. (2) Fire Hydrants: Fire Hydrants Installation shall be paid for at the unit pnce bid, including fittings. between the main line and the fire hydrant, setting, adjusting to grade, anchoring in place, and other appurtenances necessary for proper operation; but shall not include pipe and valve between the main line and fire hydrant. (3) Fire Hydrant and Drain Valve Barrel Extensions: Barrel extensions will be paid for at the pnce bid measured by the vertical foot for bury depths greater than 5 feet, including stem extensions, bolts and all other required accessories. (4) Pressure /Flow Control Assemblies: Pressure control and flow control valve assemblies will be paid for at the unit price bid, including box or vault, setting, adjusting to grade, anchonng in place, adjusting the control device to the required conditions, providing other appurtenances necessary for proper operation, and placing in operation. (5) Drain Valve Assemblies: Drain valve installation shall be paid for at the unit price bid, including fittings between the main line and the drain valve, setting, adjusting to grade, anchoring in place, and other appurtenances necessary for proper operation; but shall not include pipe and valve between the main line and drain hydrant. 511 112/17/93 5 Water Va■es 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 END Ref: 510 (6) Manual Air Release: Manual air release installations will be paid for at the unit puce bid and shall include valves, fittings, pipe, tapping the main, box and cover, and other appurtenances necessary for proper operation. (7) Automatic Air- Vacuum Valves: Automatic air - vacuum release assemblies will be paid for at the unit price bid and will include the main line tap or outlet, all pipe, valves, fittings, box or vault and cover, and other appurtenances necessary for proper operation. Payment, when included as a contract pay item, will be made under one of the following: Pay Item No. 511-A: Valves, Type, Dia. - Per Each. Pay Item No. 511-8: Fire Hydrants - Per Each. Pay Item No. 511-C: Fire Hydrant Bartel Extensions - Per Vertical Foot. Pay Item No. 511 -0: Pressure or Flow Control Valve Assemblies - Per Each. Pay Item No. 511-E: Drain Valve Assemblies - Per Each. Pay Item No. 511-F: Manual Air Release Assemblies Dia. - Per Each. Pay Item No. 511-G: Automatic Combination Air and Vacuum Release Valve Assemblies. Dia. - Per Each. 511 112/17/73 6 Water Vxhcs