R-93-11-23-9G - 11/23/1993•. C �2.'3Bi94
DATE:
SUBJECT:
ITEM:
11:55 ROUND ROCK PUELIC WORKS 4 512 255 6676
February 8, 1994
STAFF RESOURCE PERSON:
STAFF RECOMMENDATION:
City Council Meeting, February 10, 1994
12A. Consider Change Order No. 1 to Haegelin Construction
Company, Inc. for the Southeast Round Rock
Water /Wastewater Improvements.
Jim Nuse
NO.433 DR5
931143 -9G
In order to complete some of the required improvements for the Dell project, a change
order is required to complete a tie -in.
1)
- n
r
11
11
r
.l
11
n
r
r
02/20/94 15:13 ROUND ROCK PUBLIC WOR� KS -4 512 255 6676
FEB- 8 -94 TUE 14:50 HAEGELIN CONST. CO. INC. FAX NO 5123889911
FE8 -1994 14 FROM BURY P. PITTMAN. INC. TO
debruary 4, 1994
Haegelin Construction Co., Inc.
City of Round Rock .
c/o bury 6 pittman, InC.
3345 Bee Cave Road
Austin, Texas 78746
Put OIDoe Lot ooae • Auaan. TeRas 7789 • (61'i) 388.8900
NO.435 P05
P. 07
3889911 P.86
attn: Mr. Greg strmieka
ROI Water and Wastewater Improvements for Doll Center Blvd.
Dear sir,
We are pleased to offer the following proposal for addition of 16"
water line improvements associated with the above project more
specifically enumerated on.the attached scope of work.
We propose to perform the above work in a substantial workmanlike
manner for tha sum Thirty Thousand Wight Hundred Ten end 00/100
Dollars, ($80,810.00).
We appreciate the opportunity to quota this project. Please contact
our offi0a if We can he of further service.
sincerely,
- In, 141 i
• Michael W. Carson
Baegelin Conetruction Co., Inc.
021W/94 15:13 ROUND ROCK PUELIC WORKS -. 512 255 6676 NO.435 DO6
FEB- 8 -94 TUE 14;50 HAEGEL1N CONST, CO. 1NC. FAX NO. 5123889911 P.08
FEB-OS-1994 14.30 FROM BURY 8 PITTt . IMO. TO 388991! P.87
rn
/
ri
r
'TI
'1
11
r
DELL CENTER 16" WL
8C0PE Of WORK
DESCRIPTION
16` DI CL 52
SORE W/24" CASING
L2X12 WET CONNECTION
12° GATE VALVE
6" GATE VALVE
HYDRANT
RESPECTFULL SUBMITTED,
7'. w.
CARSON
HAEGELIN CONST. CO., INC.
FEB 4, 1994
DELLISBI
UNITS AMOUNT EXTENSION
304.0 *40.00 *12,160.00
76.0 *170,00 *12,780.00
1.0 $2,600.00 *2,600.00
2.0 *1,000.00 *2,000.00
1.0 *400.00 *400.00
1.0 $1,000.00 *1,000.00
TOTAL WATER *30,810.00
TOTAL P.0?
PROJECT: Water and Wastewater Improvements
for Dell Center Boulevard
PROJECT NO: 525-03.61
OWNER: City of Round Rock, Texas
CONTRACT DATE: 12 /6/93
sunIECr OF CHANGE ORDER: As described below.
I
DESCRIPTION (list Attachments, If Any)
Change No. Description Change in Contract Price
1 See Attachment "A" $30,810
REASON FOR CHANGE: See Attachment "A"
ORIGINAL CONTRACT: $123.591.50
ADDITIONS TO DATE: $ 0 THIS ADD:
DEDUCTIONS TO DATE: $Q THIS DEDUCT: •
CONTRACT TO DATE: $ 123,591.50
$ 30.810 TOTAL ADD: $ 30 810
$Q TOTAL DEDUCT:$Q
NEW CONTRACT AMOUNT:$ 154.401.50
ORIGINAL CASH ALLOWANCE: $ --
EXPENDITURES TO DATE: $ --
THIS EXPENDITURE: $ --
REMAINING CASH ALLOWANCE: $ --
NEW CASH ALLOWANCE BALANCE: $ --
CHANGE ORDER NO. 1 •
1 of 2
DATE: 2/7/94
ORIGINAL CONTRACT PERIOD:
60
THIS EXTENSION:
CALENDAR DAYS
CALENDAR DAYS
EXTENSIONS TO DATE:
0
NEW CONTRACT PERIOD:
CALENDAR DAYS
CALENDAR DAYS
CONTRACT PERIOD TO
DATE: 60
AMENDED COMPLETION DATE:
CALENDAR DAYS
RECOMMENDED BY:
ACCEPTED BY:
APPROVED BY:
Bury & Pittman, Inc.
IN q
REPRESENT
Ha e 0
. - _ - Con _ c ' 5 n • m . an Inc.
DATE
REPRESENT A
51 r {, n 5L /as
DATE
a lc- 9'
OWNER ��,.� `%
REPRESENTATIVE
DATE
: 11U11ULJ-US.
2 of 2
CHANGE #1
Description of Change:
ATTACHMENT "A"
CHANGE ORDER #1
Water and Wastewater Improvements
for
Dell Center Boulevard
Construct waterline Improvements per approved plans from Sta. 17 + 15.32 to Sta. 20
+ 23.84. Delete one section of 20' pipe and one 16" butterfly valve. (Construct per
attached scope of work from Haeglin Construction)
WHEREAS, the City of Round Rock'has duly advertised for bids for
the Water and Wastewater System Improvements for Dell Center Blvd.,
and
WHEREAS, Haegelin Construction Company, Inc., has submitted the
lowest and best bid, and
WHEREAS, the City Council wishes to accept the bid of Haegelin
Construction Company, Inc., Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,
TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City an agreement with Haegelin Construction Company,
Inc., for Dell Center Blvd., a copy of said agreement being attached
hereto and incorporated herein for all purposes.
RESOLVED this 23rd day of November, 1993.
ATTEST:
E LAND, City Secretary
RS /RESOLUTION
RS11233H
RESOLUTION NO. gi 2 ) - J -o)S-9G-
CHARLES CULP P , Mayor
City of Round Rock, Texas
11/19/93 16:34 ROUND ROCK PUELIC WORKS -. 512 255 6676
Bury 1 Pittma ri
November 19, 1993
Mr. Jim Nuse, Director
Public Works Department
City of Round Rock
221 East Main Street
Round Rock, Texas 78664
Re: Award of Contract
Water and Wastewater System Improvements
For Dell Center Boulevard
Dear Mr Nuse:
By Tuesday, November 16, 1993 eight (8) bids were received from contractors to
perform the work required to complete the water and wastewater system improvements
for Dell Center Boulevard as designated in the construction bid set. Attached please find
a bid tabulation showing the eight bids ranging from a low bid of $123,591.50 to a high
bid of $185,661.79. The low bid of $123,591.50 for the improvements required was
submitted by Haegelin Construction Company.
Bury & Pittman, Inc. is recommending that the City Council of Round Rock award the
contract for the water and wastewater system improvements for Dell Center Boulevard
to Haegelin Construction Company.
Should you have any questions or require additional information, please call.
1 y, T.... k
1 V �--� S •• . /%
Paul J 1�c�'orin, P.E. $ PAUL J. VIKTORIN .i
W. . 66879 65, 5
cc: Bay Maintenance Co., Co., ncn f l e , s o .....
Borah, Inc.J.C.
Evans Construction Co., Inc. )I- j9- 53
Haegelin Construction Co., Inc.
Keystone Construction, Inc.
M & R Plumbing, Inc.
Trident Underground Utilities Corp.
Attachments
f: \jnuse.ltr \pv \ltr \bh\525 -03.61
Rum a Pinioao.
al .I,1nug
. Ib, .. 11„ „�1 /,111. 201,
h1 iI .1. 5i. 4,.111
112 yt1.,1t
NO.166 P03
i �
um.1> f
%
.I.7..o.w.luk r.OILG72k00smtve..lw e....w ,M arexwo , DAM ..A..�r e-r v. ... _ ... _....
rw,.crll.x. 02.1.1.�..r. YE ur.r c� Ail!. J. VIM - ORIN
'f
1 66R71 9 e �
....w.�..�a.mmr-..®es
a. C.......w.1
'�r]1 \,
Da re 1'^'� OF �C �
Ma., A 1°1- i40;907vpT; EN
.9r6Wrar6r a -m.l
N.. x..w 6K
���.w.r
6.710 Ce- uv1rcR7 -
W
9
m /
VIM
Mr.
.00,1.1
war 7 1
1.re
..100711
nxe
.10..0.7
i97
.169 171
ra re
.6 00
rwee
.1.100
Rae
.000.0
1
c 9alawssc.9n96 RON ern
1310
LP
3110
052030
2000
20 90
5020
020
wm
500
2
4.11401C1•062 DOGMA otoh
213
LF
33.21
340870
093
2000
mm
500
9]20
5000
3
6-0500067eV..LE
4
EA
313330
36,22311
3920
2000
0(01
5+]20
9120
00 0
S
9.- 0020/00900
2
EA
371179
313031
9300
S10
2020
0A3
fOm
]900
1 14- ne3lrleex
6
EA
31.0361
91121.6
5900
3000
50.93
501.0
IOW
mm
6
.- n.Q1001.,W1.5
1
en
1.517 71
32_680'.9
Sim
3320
9120
0 W
-
50AJ
200
7
6- 00110umx POx 496
110
LP
1260
32,99910
3400
9365
3020
0020
mm
mm
0 0.1VATER 2944.10
1
FA
0031
037.81
3200
SOW
50.00
020
360
020
9
49 19,10.10111.00 RIM
1
FA
3400
39030
9200
9100
Me
W m
200
010
10
a• CAM SOW PVC YAM - WAWA me
017
LP
921.0
90200
9200
SSW
020
000
020
5020
11
4 00;rE1HtvI31
2
FA
20013
0900
5020
5000
500
500
9200
0030
1:
6 - F09070600/ tATPwATe■
R.01.T
1
EA
31121.13
3723432
SAW
50 W
0 20
2020
SOm
0 W
13
. 1907 P 1.0,0311632£7!.11x/1
DRpfO04019
1
FA
01710
3E47)67
3000
0000
OW
9100
0320
000
0
w072796102 use rum
1
EA
51133
001 AR
5010
10 00
0000
206.
mm
mm
IS
6- 09f511.319r709A N
1
EA
117917
109.0
1000
000
500
5000
5003
9100
114
305249
353
LP
3318
5000
00.03
200
500
5000
5030
300
17
099000/0
00
LP
51233
30.0310
3093
200
0020
90.00
l=
5060
14
06070100e0091
2
EA
11170
303.06
1010
0000
000
00107
0040
0OW
19
Wen. SAFER.1.1chr3
32
LP
911
3332106
5020
500
2900
5050
0010
5010
20
9r2693a900911900000 exr0309
1
EA
123679
1056.79
020
200
0(00
000
2020
000
21
- - a
Nv0R0nw1
m
51
000
939390
WW
930
5000
093
WW
010
w'.renare Harm.
2.3
TON
5196629
31E465
020
020
5004
500
930
000
23
•..064Prr1.eeww
77
SY
36395
31.70133
1000
5190
000
00
000
000
.`kon."r. A77 3739em'T° - . R , Tn- t:. - " Z :` 1 39
ir3i i'9$.. 5.1
x. 00
e. =M•
)t°:! 0 19 2 FTi
;.
so ;
s .So 096OV: f --
:'
"
T -F'S :50
a
z
/ y �?E OF 7•fi�;Lf
CUM' 11l 1 .m„3.+ Ns...1.101 S:
0401360403100 r .
l01¢,
. 1.., e.,..,............,.... e.,..,............,.... . p J _ L WKT RIN 1
PROM, 4uFAaw:P +..Pam ....... n 1
\ % p GFS8 1
PRDR xrRa1a11an
w.e<.....slr o-1 rJ.,.r
p Q - k L.0) ' ln % . C lg P F : ':
'(
7 3_` 1 -4,36 `9 ''
�►
d
,+.I.. e„E...
m-01•1
BLOOM
x •lere.vlm
OMAO r.
300..8 r ®.a,. be
Mr.�...c4he
..,
133.0 t e
w ®e4..e:.•,La.
ul....c.....A.1..
13341. 316- 333101+0'64-c 3x8013 cs an
a
Re
,,,,,
eD
es
�
M
APIMUCIPM AONnRLeDOPD 95903407 8590 sum 01¢1rCE9
•
•
0
•
•
•
•
310
_ _
am
V% M
MC!
.W 99M
x141
100X4
M
A .'
'RYE
w51w M
34650059
WTI
PUCE
3 110131,
.0
TIC!
01134 00
IPM
MLR
...007
1
P
a- 0340466336 men 3403. me
1810
LF
0330
347,56000
51100
5500
33400
5542100)
5331 On
357,92000
13600
005.16003
34130
9
31600
365,16030
2
R- 30660 ssa DUCTILE IRON eve
275
LF
12710
SUDO 10
5940
3632519
9610
511530
SZAN
3663007
[10 00
5625000
r54M
39,31750
33000
58,15030
0,40110
01X010
3
0 -0001 OATEVA1.E
0
EA
1120250
5&52(0
51.400 (0
313.0003
145000
510000
12,6000
530100
070103
19007
03,1000
5110010
580000
347500
33,20)01
595000
310010
17000)
56 10001
11 1min
331531.40
0®710
31,20003
31.26000
590103
5N000
4
0_ 1Ha73ATEVAME
2
EA
3
0 - e107c1)lxr0wwn
6
EA
51360(0
56310059
37, 7059
3610010
3300
3300500
01000.W
3634010
5130000
31]00 03
66)10000
34/0059
1 1 2 10,0
920(10
6
a MCnaA16VAV4,e
5
EA
5401.00
9,011030
0540)
517330
00760
320030
97300
11,61510
560000
towns
3(8000
32.50159
3410.
IMM O
7
•_01150 Duels Mrn eve
NO
LF
17010
V.1700 03
Sn40
0pnm
mm
WOODS
SHOD
L
90M
noon,
52630
06010
53360
99040
0• WC/1 WAMILIR PLUG
1
EA
110070
110000
115000
510300
140501
570300
373.050
17507
00 00
520050
5100.04
00059
36000
310001
9
0 E1070A1e
1
FA
15003
55010
110000
010040
50110
38000
34070
MUD
515000
515000
9300
31101
110340
304000
10
P00Cxa04n HEwA51FRAn•A PUP
1537
LE
31M
93'700
03 00
0 0,03003
0510
530
5900
/00/9990
32E40
530.96200
5 7190
1 04430
13100
500
35230
11
._fODr 0733/803 wss1V.'wrea
•304,179 COMM
2
FA
3620007
12,40000
3110301
52200.00
.51.30,30
883060
1120030
32,00 40
320000
010059
11,00110
5360010
344007
0,1=40
1000000
P2
. 000r 0161¢13 RA3rE.417.
Covu
4
EA
3170400
3400060
312(010
14/00.,
313000)
13210140
31300(0
CUOMO
111000
55 0300
51/1010
320040
320000
t3
1 ;N0�
519wA're)
00001u101AS
1
FA
31.4330
5134000
3150300
31510/0
3691050
104040
5130001
11-54000
3.5.400
030140
7,070(0
1230201
0.0059
51,00.00
14
3033159471363043 1303
1
EA
15200
13000
13000
55000
310001
5110010
55001
11300
310070
310000
571110
0000
01010
30300
13
9- E4IL.A54EMw1PY CO1L4CC41ax
3
EA
35008
575020
51.0000
57,500.10
551100
350000
373003
35000
11.0010
0,00000
3
5101
560000
134010
16
043530 478
551
LF
350
sr
5150
14_40
5050
53250
3200
51,3003
3123
139173
5130
1121...41
5105
310000
17
- fill
ROM 0W7
03
LF
11500
51 000
51200
590000
57310
11 33100
0500
312000)
11200
3(001
1760)
3120x0
Sri*
3200010
340¢1 PROM - 1108
2
EA
41500
1150003
331070
140000
530011
513000
25003
00000
111000
13000
00060
160..100
3100 00
30.00
19
1)101[1 M00701r30010
1722
LF
1100
9,'71100
3 00
3.75300
1100
17,721(t
359
537.
3160
30,7110
SIM
0,71200
5140
3 3.77230
20
s7A00Y000011300E714 640151102
1
EA
16000
163010
05900
340110
3501110
150000
1750
375000
00000
00100
3404100
500000
11,00390
1140110
21
009000MIa44)
505
sr
1140
571510
30-10
01927.1
5140
397340
00.72
570201
3140
097500
30.75
373121
1030
30150
22
146441.C100nnlos
23
TON
0;1000
31.73010
3.070591
57.9059
0J4n50
52.7040
000
100)
5250000
3603000
1030
DODO
0,00000
5134000
23
PAVen3O APtut
77
14
355M
367500
53000
011010
31310
340500
8910
551000
33.1404
0•02
5290
354001
0000
334040
•- ...+.'ase."0.3370iL•r1 ,- ' gr ma ca
'5 -
w•F eM
5 3113WI]U
3 '7'3 Z .7.4
'c':3t30a^Sy.W'Rwc ' 4'
11$04393'00$' -
331 3
515010 :0
:i3129 mq'30
7-'
'5503140,$1
0
J'.•• OF
r001.0••••...010_ 1.■•44.111619■4
11/19/93. , 16:34 ROUND ROCK PUBLIC WORKS + 512 255 6676
DATE: November 19, 1993
SUBJECT: City Council Meeting, November 23, 1993
ITEM: 9G. Consider a resolution authorizing the Mayor to enter into an
agreement with Haegelin Construction Company, Inc. for the
Southeast Water /Wastewater Improvements.
STAFF RESOURCE PERSON: Jim Nuse
STAFF RECOMMENDATION:
Based on a review of the low bidder's qualifications, work experience, and previous
history of projects with the City we recommend award of the contract to Haegelin Construction
Company, Inc.
NO.165 D02
I ) Bury +Pittman
Consulting Engineers and Surveyors
PROJECT MANUAL
FOR
WATER AND WASTEWATER
SYSTEM IMPROVEMENTS
FOR
DELL CENTER BOULEVARD
Prepared for:
CITY OF ROUND ROCK, TEXAS
Public Works Department
October 1993
Project No. 525 -03.60
v -q ii-a---q-
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
PROJECT MANUAL
FOR
WATER AND WASTEWATER
SYSTEM IMPROVEMENTS
FOR
DELL CENTER BOULEVARD
Prepared for:
CITY OF ROUND ROCK, TEXAS
Public Works Department
Prepared by:
BURY & PITTMAN, INC.
3345 Bee Caves Road, Suite 200
Austin, Texas 78746
OCTOBER 1993
Project No. 525 -03.60
v5.
Section
1.0 Notice to Bidders NB -1
2.0 Bid Documents BD -1
3.0 Post Bid Documents PBD -1
4.0 General Conditions GC -1
5.0 Special Conditions SC -1
6.0 Technical Specifications TS -1
table.mst/spec
TABLE OF CONTENTS
Description Enk
Item 1 General Description
Item 2 Control of Work
Item 3 Examination and Review
Item 4 Protection and Precaution
Item 5 Materials
Item 6 Grading, Restoration, Revegetation, and Erosion
Control Measures (Series 600)
Item 7 Construction and Traffic Control within
Highway Right -of -Way
Item 8 Mail Boxes
Item 9 Seal Coat
Item 506 Manholes
Item 509 Trench Safety Systems
Item 510 Pipe
Item 511 Water Valves
1.0 NOTICE TO BIDDERS
NOTICE TO BIDDERS
Sealed bids addressed to the Purchasing Agent, City of Round Rock, 221 East
Main Street, Round Rock, Texas 78664, for furnishing all labor, material and equipment
and performing all work required for the project titled Water and Wastewater System
Improvements for Dell Center Boulevard (project includes approximately 1810 feet of
12 -inch ductile iron waterline, 275 feet of 8 -inch ductile iron waterline, and
approximately 1537 feet of 8 -inch wastewater line including all ancillary items) will be
received until 2:00 p.m. November 16, 1993 then publicly opened and read aloud at the
City Hall Council Chambers at the same address. Bid envelopes should state date and
time of bid and "Water and Wastewater System Improvements for Dell Center
Boulevard ". No bids may be withdrawn after the scheduled opening time. Any bids
received after scheduled bid opening time will be returned unopened.
Bids must be submitted on City of Round Rock bid forms and must be
accompanied by an acceptable bid security as outlined in the Instructions to Bidders,
payable to the City of Round Rock, Texas equal to five percent (5 %) of the total bid
amount. Plans, Bid Forms, Specifications, and Instructions to Bidders may be obtained
from the Bury & Pittman, Inc., 3345 Bee Caves Road, Suite 200, Austin, Texas 78746
beginning Wednesday. November 3. 1993 at 1:00 p.m. for a non - refundable charge of
$25.00 per set.
In case of ambiguity, duplication, or obscurity in the bids, the City of Round Rock
reserves the right to construe the meaning thereof. The City of Round Rock further
reserves the right to reject any or all bids and waive any informalities and irregularities
in the bids received.
The successful bidder will be expected to execute the standard contract prepared
by the City of Round Rock, and to furnish performance and payment bonds as described
in the bid documents.
Publish Dates:
Austin American Statesman: Round Rock Leader:
October 31, 1993 November 1, 1993
November 7, 1993 November 8, 1993
eeticebd/.Pec.m. r
NB -1
2.0 BID DOCUMENTS
INSTRUCTIONS TO BIDDERS
1. Prior to submitting any proposal, bidders are required to read the plans,
specifications, proposal, contract and bond forms carefully; to inform themselves
by their independent research, test and investigation of the difficulties to be
encountered and judge for themselves of the accessibility of the work and all
attending circumstances affecting the cost of doing the work and the time required
for its completion and obtain all information required to make an intelligent
proposal.
2. Should the bidder find discrepancies in, or omissions from the plans,
specifications, or other documents, or should he be in doubt as to their meaning,
he should notify at once the Engineer and obtain clarification or addendum prior
to submitting any bid.
3. It shall be the responsibility of the bidder to see that his bid is received at the place
and time named in the Notice to Bidders. Bids received after closing time will be
returned unopened.
4. Bids shall be submitted in sealed envelopes plainly marked "Sealed Bid" and
showing the name of the project, the job number if applicable, and the opening
date and time.
5. Bids shall be submitted on proposal forms furnished by the City of Round Rock.
6. All proposals shall be accompanied by a certified cashier's check upon a National
or State bank in an amount not less than five percent (5%) of the total maximum
bid price, payable without recourse to the City of Round Rock, or a bid bond in
the same amount from a reliable surety company, as a guarantee that the bidder
will enter into a contract and execute performance and payment bonds, as
stipulated by item 11 below, within ten (10) days after notice of award of contract
to him. Proposal guarantees must be submitted in the same sealed envelope with
the proposal. Proposals submitted without check or bid bonds will not be
considered.
7. All bid securities will be returned to the respective bidders within twenty-five (25)
days after bids are opened, except those which the owner elects to hold until the
successful bidder has executed the contract. Thereafter, all remaining securities,
including security of the successful bidder, will be returned within sixty (60) days.
biddoc.mst/spec
BD -1
8. Until the award of the contract, the City of Round Rock reserves the right to reject
any and all proposals and to waive technicalities; to advertise for new proposals;
or to do the work otherwise when the best interest of the City of Round Rock will
be thereby promoted.
9. In case of ambiguity or lack of clarity in the statement of prices in the bids, the
City of Round Rock reserves the right to consider the most favorable analysis
thereof, or to reject the bid. Unreasonable (or unbalanced) prices submitted in a
bid may result in rejection of such bid or other bids.
10. Award of the contract, if awarded, will be made within sixty (60) days after
opening of the proposals, and no bidder may withdraw his proposal within said
sixty (60) day period of time unless a prior award is made.
11. Within ten (10) days after written notification of award of the contract, the
successful bidder must furnish a performance bond and a payment bond in the
amount of one - hundred percent (100 %) of the total contract price. Provided
however, if the contract price is less than $50,000.00, the bidder shall have the
option of providing a letter of credit in lieu of a performance bond, said letter of
credit in a form acceptable to the City of Round Rock. Said performance bond,
or letter of credit, if applicable, and payment bond shall be from an approved
surety company holding a permit from the State of Texas to act as surety (and
acceptable according to the latest list of companies holding certificates of authority
from the Security of the Treasury of the United States) or other surety or sureties
acceptable to the Owner, with approval prior to bid opening.
12. If the total contract price is less than $25,000.00 the performance and payment
bond requirement will be waived by the City of Round Rock. Payment will be
made following completion of the work.
13. Failure to execute the construction contract within ten (10) days of written
notification of award or failure to furnish the performance bond, or letter of credit
if applicable, and payment bond as required by item 11 above, shall be just cause
for the annulment of the award. In case of the annulment of the award, the
proposal guarantee shall become the property of the City of Round Rock, not as
a penalty, but as a liquidated damage.
14. No contract shall be binding upon the City of Round Rock until it has been signed
by its Mayor after having been duly authorized to do so by the City Council.
biddoc.mstispec BD -2
15. The Contractor shall not commence work under this contract until he has furnished
certification of all insurance required and such has been approved by the City of
Round Rock, nor shall the contractor allow any subcontractor to commence work
on his subcontract until proof of all similar insurance that is required of the
subcontractor has been furnished and approved.
16. Any quantities given in any portion of the contract documents, including the plans,
are estimates only, and the actual amount of work required may differ somewhat
from the estimates. The basis for the payment shall be the actual amount of work
done and /or material furnished.
17. No Texas sales tax shall be included in the prices bid for work under this contract.
This contract is issued by an organization which is qualified for exemption
pursuant to the provisions of Article 10.04 (h) of the Texas Limited Sales, Excise
and Use Tax Act. The contractor performing this contract may purchase, rent or
lease all materials, supplies, equipment used or consumed in the performance of
this contract by issuing to his supplier an exemption certificate complying with
State Comptroller's ruling #95 -0.07. Any such exemption certificate issued by the
contractor in lieu of the tax shall be subject to the provisions of the State
Comptroller's ruling #95 -0.09 as amended to be effective July 1, 1979.
18. No conditional bids will be accepted.
biddoc.mst/spec
BD -3
1 PLANET INSURANCE CON,r.PAN5r
HEAD OFFICE, SUN PRAIRIE, WISCONSIN
1 BID BOND
1
KNOW ALL MEN BY THESE PRESENTS, that we
HAEGELIN CONSTRUCTION CO., INC., P. 0. Box 9086, Austin, Texas 78766
as Principal, hereinafter called the Principal, and the PLANET INSURANCE COMPANY of Madison,
Wisconsin, a corporation duly organized under the laws of the State of Wisconsin, as Surety,
hereinafter called the Surety, are held and firmly bound unto
CITY OF ROUND ROCK
1 as Obligee, hereinafter called the Obligee, in the sum of five percent (5Z) of greatest amount
bid in - - - -- Dollars ($ ), for the
' payment of which sum well and truly to be made, the said Principal and the said Surety, bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by
these presents.
1 WHEREAS, the Principal has submitted a bid for Water and Wastewater Improvements for Dell
Center Blvd.
1 NOW, THEREFORE, if the contract be timely awarded to the Principal and the Principal shall within
such time as specified in the bid, enter into a contract in writing and give bond with good and
1 sufficient surety, or, in the event of the failure of the Principal to enter into such Contract and give
such bond or bonds; if the Principal shall pay to the Obligee the difference not to exceed the penalty
hereof between the amount specified in said bid and such larger amount for which the Obligee may
in good faith contract with another party to perform the work covered by said bid, then this obligation
1
shall be null and void, otherwise to remain in full force and effect.
PROVIDED, HOWEVER, neither Principal nor Surety shall be bound hereunder unless Obligee prior to
' execution of the final contract shall furnish evidence of financing in a manner and form acceptable to
Principal and Surety that financing has been firmly committed to cover the entire cost of the project.
Signed and sealed this 16th day of November 19 93
L4 fc.t. L aGt4i J HAEGELIN CONSTRUCTION CO., INC.
(Witness) (Princiipal) (Seal)
1 By: / /, //er 4OL; 4 ; !4
(Title)
1
1
1
By:
1 BDP- 23232/90
PLANET INSURANCE COMPANY
Peter Pincoffs, (Attorney -in -Fact)
PLANET IN COMPAN
HEAD OFFICE, MADISON. WISCONSIN
•
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS, That the PLANET INSURANCE COMPANY, a corporation duly organized under the laws of the State
of Wisconsin, does hereby make, constitute and appoint Robt. H. Bin, Thomas C. Wa111tack, Bess Ann Roberts,
Peter Pincoffs, John S. Burns, Jr. and Joe George, individually, of Austin, Texas
its true and lawful Attorney -in -Fact, to make, execute, seal and deliver for and on its behalf, and as its act and deed any and all bonds
and undertakings of Suretyship,
an • to bind the PLANET INSURANCE COMPANY thereby es fully and to the same extent as if such bonds and undertakings and other writings
obligatory in the nature thereof were signed by an Executive Officer of the PLANET INSURANCE COMPANY and sealed and attested by one other of
such officers, and hereby ratifies and confirms all that its said Attorney(s) -in -Fact ma•do in pursuance hereof.
This Power of Attorney is granted under and by authority of Article VII of the 8y -Laws of PLANET INSURANCE COMPANY which became
effective September 21, 1981, which provisions are now in full force and effect, reading as follows:
ARTICLE VII — EXECUTION OF BONDS AND UNDERTAKINGS
1. The Board of Directors, the President, the Chairman of the Board, any Senior Vice President, any Vice President or Assistant Vice President
or other officer designated by the Board of Directors shall have power and authority to (a) appoint Attorneys -in -Fact and to authorize them to execute
on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof, and
(b) to remove any such Attorney -in -Fact at any time and revoke the power and authority given to him.
2. Attorneys -in -Fact shall have power and authority, subject to the terms and limitations of the power of attorney issued to them, to execute and
deliver on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof.
The corporate seal is not necessary for the validity of any bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory
in the nature thereof.
3. Attorneys -in -Fact shall have power and authority to execute affidavits required to be attached to bonds, recognizances, contracts of indemnity
or other conditional or obligatory undertakings and they shall also have power and authority to certify the financial statement of the Company and to
copies of the By -Laws of the Company or any article or section thereof.
This power of attorney is signed and sealed by facsimile under and by authority of the following Resolution adopted by the Board of Directors of
PLANET INSURANCE COMPANY at a meeting held on the 29th day of March, 1982, at which a quorum was present, and said Resolution has not been
amended or repealed:
"Resolved, that the signatures of such directors and officers and the seal of the Company may be affixed to any such power of attorney
or any certificate relating thereto by facsimile, and any such power of attorney or certificate bearing such facsimile signatures or facsimile
seal shall be valid and binding upon the Company and any such power so executed and certified by facsimile signatures and facsimile seal
• shall be valid and binding upon the Company in the future with respect to any bond or undertaking to which it is attached."
IN WITNESS WHEREOF, the PLANET INSURANCE COMPANY has caused these presents to be signed by in Vice President, and in corporate seal to
be hereto affixed, this 12th day of September 19 89
STATE OF
COUNTY OF
On this
BDP -1431 1/82
Pennsylvania
Philadelphia
12th day of
September
,19 89 , personally appeared Raymond MacNeil
to me known to be the Vice - President of the PLANET INSURANCE COMPANY, and acknowledged that he executed and attested the foregoing
instrument and affixed the seal of said corporation thereto, and that Article VII, Section 1, 2, and 3 of the By -Laws of said Company, and the Resolution,
set forth therein, are still in full force. 1 N �0. .. /
My Commission Expires:y /r '4.11. n�� -� / A •
Fels 1 ,19 9 e 1 J Notary Public in and for State of Pennsyl
r uary ''' 0 ' "5 Residing at Philadelphia
1, Ray L. Lorah , Assistant Secretary of the PLANET INSURANCE COMPANY, do hereby certify that the
above and foregoing is a true and correct copy of a Power of • tt�o pay executed by said PLANET INSURANCE COMPANY, which is still in full force
and effect. i • ' u' -. Z:+
.. f .t F1s s
IN WITNESS WHEREOF, I have hereunto set my han nd a►f' ": - 'e s of said Company this 1 6th day of November 19 93
Assistant Secretary
Ae
BID BOND
KNOW ALL MEN BY THESE PRESENTS THAT WE,
as PRINCIPAL and as
SURETY, are held and firmly bound unto the
hereinafter referred to as the "OWNER ", in the penal sum of five percent (5%) of the
total amount of the bid of the PRINCIPAL submitted to the OWNER, for the work
described below; for the payment of which sum in lawful money of the United States of
America, well and truly to be made, we bind ourselves, our heirs, executors,
administrators, successors and assigns, jointly and severally, firmly by these presents.
In no case shall the liability of the SURETY hereunder exceed the sum of
The CONDITIONS OF THIS OBLIGATION ARE SUCH, THAT whereas, said
PRINCIPAL has submitted the above mentioned bid to the OWNER, for construction
for the work under the "SPECIFICATIONS FOR CONSTRUCTION OF
for which
bids are to be opened at the office of the OWNER on
NOW THEREFORE, if the PRINCIPAL is awarded the contract, and within the time and
manner required under the heading "Instructions to Bidders ", after the prescribed forms
are presented to him for signature, enters into a written agreement, substantially in the
form contained in the Specifications, in accordance with the bid and files the town bonds
with the OWNER, one to guarantee faithful performance and the other to guarantee
payment for labor and materials, then this obligation shall be null and void, otherwise,
it shall be and remain in full force and effect.
In the event suit is brought upon this bond by the OWNER and judgement is recovered,
said SURETY shall pay all costs incurred by the OWNER in such suit, including a
reasonable attorney's fee to be fixed by the Court.
In WITNESS WHEREOF, we have hereunto set our hands and seals this day of
Principal: Surety:
By: By:
(Seal) (Seal)
biddoc.mst/spec
BD-4
1 PROPOSAL BIDDING SHEET
' TOB NAME: Water and Wastewater System Improvements for Dell Center Boulevard
' JOB LOCATION: Round Rock, Williamson County, Texas
OWNER: City of Round Rock, Texas
1 DATE: November 16, 1993
Gentlemen:
Pursuant to the foregoing Notice to Bidders and Instructions to Bidders, the undersigned bidder
'
hereby proposes to do all the work, to furnish all necessary superintendence, labor, machinery,
equipment, tools, materials, insurance and miscellaneous items, to complete all the work on which he
I bids as provided by the attached supplemental specifications, and as shown on the plans for the
construction of Water and Wastewater System Improvements for Dell Center Boulevard and binds
himself on acceptance of this proposal to execute a contract and bond for completing said project within
' the time stated, for the following prices, to wit:
BASE BID
' Bid Item Description Unit
I Item Quantity Unit and Written Unit Price Price Amount
1. 1810 LF 12 -inch class 52 ductile
I iron pipe. complete and in
place �with , compacted backfill
for dollars
1 and - cents. $ 26— $47060
1 2. 275 LF 8 -inch class 52 ductile
iron pipe. complete and in
I place with compacted backfill
for�G( �� -0-0 dollars
and cents. $ 2-2-. — $ 6 0S6
3. 4 EA 12 -inch gate valve
'
complete and in place
1 for it)ollars
and /N o cents. $ /Zoo— $ 4800—
'
1 biddoc.mst/spec BD -
Bid Item Description Unit
Item Quantity Unit and Written Unit Price Price Amount
1
4. 2 EA 8 -inch gate valve
complete and in place
'
forAhlAtiollars
and „n o cents. $ SOD — $ 160o —
1 5. 6_ EA 5 1/4 -inch fire hydrants
complete and in place
' for Oru.- ( dollars
I and /n.0 cents. $ /000 — $ 6e700 -
6. 5 EA 6 -inch gate valve
' complete and in place
for zw dollars
1 and in,o cents. $ /aO0 — $ 300o —
' 7. 100 LF 6 -inch ductile iron pipe
complete and in place with.
compacted backfill
for dollars
and �, cents. $ 2 — $ Zooa —
8. 1 EA 12 -inch water line plug
complete and in place
' form/dollars
and i71.0 cents. $ /o'— $ /0,0 --
' 9 1 EA 8 -inch water line plug
complete and in place
1 for dollars
and cents. $ — $ -. 0
1 biddoc.mst/spec BD -6
Bid Item Description Unit
Item Quantity Unit and Written Unit Price Price Amount
1
10. 1537 LF 8 -inch SDR35 PVC
1 wastewater pipe. all depths
complete and in place with
' compacted backfill
dollars
and cents. $ 2-/ — $ 3 2277—
11. 2 EA
1
12. 4 EA
1
1
13. 1 EA
1
15. 1
1
1
' biddoc.mst/spec
EA
4-foot diameter wastewater
manhole complete and in
place
foi]`c. J.u,a- dollars
and cents. $ /20a' -- $ 2 400 --
4-foot diameter wastewater
manhole without bolted
cover complete and in place
for e f4.0-1A.., Qdollars
and cents.
4-foot diameter wastewater
drop manhole complete
and in place
for '
an6' �r, cents. $ /S $ /SOD --
EA Wastewater line plug
complete and in place
$ /000 $ 40
for f c dollars ent cents. and cs. $ S o — $ ,co
8 -inch wastewater
connection to the existing
24 -inch interceptor
fo s�llars
and ' / - nts. $ 7S'0 — $ 7So -
BD -7
Bid Item Description Unit
Item Ouantitv Unit and Written Unit Price Price Amount
1
16. 555 LF Silt fence complete and in
place
for ,' dollars
1 and cents. $ 677 $ Z .
' 17. 80 LF Rock berm complete and
in place
t
for dollars
' and C d cents. $ $ /ZOO —
18. 2 EA Inlet protection complete
and in place
for,au,u Vic, dollars
and ....--no cents. $ 7S' $ /4'0
19. 3722 LF Trench safety systems -
' complete and in place
for r y yµ , dollars
and --7-1.o cents. $ / $ 37
20. 1 EA Stabilized construction
entrance complete and in
I place
for . ollars
and ,--34.,o cents. $ 4S $ GS' --
21. ES SY Hydromulch complete and
" in place
for ( , dollars
and �yi ,, cents. $ /.` $ 9
1
biddoc.mst/spec BD -8
r
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
F
1�
1
1
Bid
Item Quantity
22. 2.5
23. 27
TOTAL BASE BID (Items 1 thru 23):
Respectfully Submitted,
Title for
I4AEGELIN CONSTRUCTION CO., INC.
Name of Firm
Item Description
Unit and Written Unit Price
TONS Waterline fittings complete
and in place
for o ars
an „ , cents. $ /.S 90 — $ 3 7sb —
Pavement repair complete
and in place
for
and
STATEMENT OF SEPARATE CHARGES:
Materials:
All Other Charges:
Total:
If this proposal is accepted, the undersigned agrees to execute the contract and provide necessary bonds
and insurance certification as per the Instructions to Bidders and commence work within ten (10) days
after written Notice to Proceed. The undersigned further agrees to complete the work in full within
sixty (60) calendar days after the date of the written Notice -to- Proceed.
The undersigned certifies that the bid prices contained in the proposal have been carefully checked and
are submitted as correct and final The Owner reserves the right to reject any or all bids and may
waive any informalities.
Telephone
Unit
Price Amount
dollars
cents. $ $ 7s
/Z3s5 /. &LO
UST/Af, X . 7 8766
Address
<c /Z -358
—,- /6 /93
Date Secretary, if Contractor is a
Corporation
biddoc.mst/spec BD -9
$ S3o i (,
7os7s, se
$ /Z3S91. s�
3.0 POST BID DOCUMENTS
THE STATE OF TEXAS
COUNTY OF WIT.T.IAMSON
AGREEMENT
THIS AGREEMENT, made and entered into this 6/z day of Oe-c- A.D. 19 93 , by
and between the CITY OF ROUND ROCK, TEXAS acting through it's Mayor, Party of
the First Part, hereinafter termed the OWNER, and %epe%, si,da., "of the
City of , 6-,' , County of Tu.,; , State of
, Party of the Second Part, hereinafter termed Contractor.
WITNESSETH: That for and in consideration of the payments and agreements
hereinafter mentioned, to be made and performed by said First Party (Owner), the said
Second Party (Contractor), hereby agrees with the first Party to commence and complete
the construction of certain improvements at the prices set forth in the Contractor's
Proposal dated l /- —93 for certain improvements
described as follows:
Project includes approximately 1,810 feet of 12" Ductile iron waterline,
approximately 275 feet of 8" Ductile iron waterline and approximately 1,537 feet of 8"
wastewater line including all ancillary items.
The Contractor shall perform all work shown on the Plans and described in the
Contract and shall meet all requirements of this Agreement, the General and Special
Conditions of the Contract; and such Orders and Agreements for Extra Work as may
subsequently be entered by the above named parties to this Agreement.
The Contractor hereby agrees to commence work under this contract within 10
consecutive calendar days after that date of the Notice to Proceed and shall cause work
to progress in a manner satisfactory to the Owner. Such work shall be completed in full
within 60 calendar days after the date of the written Notice to Proceed. Time
is of the essence to this contract.
The Owner agrees to pay the Contractor in current funds, and to make payments
on account, for the performance of the work in accordance with the Contract, at the
prices set forth in the Contractor's Proposal, subject to additions and deductions, all as
provided in the General Conditions of the Agreement.
posthid.m.Uepec
Water and Wastewater ystem Improvements for Dell Center Blvd.
PBD -1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
M
AGREEMENT - continued
The following documents together with this Agreement, comprise the Contract, and
they are fully a part thereof as if herein repeated in full:
The Notice to Bidders
The Instruction to Bidders
The Proposal and Bidding Sheets
The Performance & Payment Bonds
The General Conditions of Agreement
The Special Conditions of Agreement
The Technical Specifications
Addenda
Change Orders
The Certificate of Insurance
The Plans
IN WITNESS WHEREOF the Parties to these presents have executed this
Agreement in multiple originals in the year and day first above written.
ATTEST:
posthid.m Jlpec
By: V — ,,,r�i/�
Party of the First ' . Owner)
Mayor - City of Round Rock
By : 4/ By: 62
Secretary, if Contractor
is a Corporation or
otherwise registered with
the Secretary of the State
PBD -2
Party of the Second Part
(Contractor)
THE STATE OF TEXAS
COUNTY OF WILLIAMSON
PERFORMANCE BOND #P2502864
KNOW ALL MEN BY THESE PRESENTS: That Haegelin Construction Co., Inc. of the
City of Austin , County of Travis , and State of
Texas , as Principal, and Planet Insurance Canpany authorized under the law
of the State of Texas to act as surety on bonds for principals, are held and firmly bound
unto [HE CITYOFROUND ROCK, TEXAS, (Owner), in the penal sum oft hundred twenty
three thousand, five hundred ninety one & 50 /100 dollars ($ 123,591.50AAAAAA ) for the payment
whereof, well and truly to be made the said Principal and Surety bind themselves, and
their heirs, administrators, executors, successors and assigns, jointly and severally, by
these presents:
WHEREAS, the Principal has entered into a certain written contract with the Owner
dated the 6th day of December , 19 9 to which
the contract is hereby referred to and made a part hereof as fully and to the same extent
as if copied at length herein consisting of:
Water and Wastewater System Improvements for Dell Center Blvd.
NOW, THEREFORE, THE CONDITIONS OF THIS OBLIGATION IS SUCH, that if
the said Principal shall faithfully perform said Contract and shall, in all respects, duly and
faithfully observe and perform all and singular the covenants, conditions and agreements
in and by said Contract, agreed and covenanted by the Principal to be observed and
performed, including but not limited to, the repair of any and all defects in said work
occasioned by and resulting from defects in materials furnished by or workmanship of,
the Principal in performing the work covered by said Contract and occurring within a
period of twelve (12) months from the date of the contract Completion Certificate and all
other covenants and conditions, according to the true intent and meaning of said Contract
and the Plans and Specifications hereto annexed, then this obligation shall be void;
otherwise to remain in full force and effect;
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article
5160 of the Revised Civil Statues of Texas as amended and all liabilities on this bond
shall be determined in accordance with the provisions of said Article to the same extent
as if it were copied at length herein.
postbid.mWspec
PBD -3
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
ccz:
1
1
PERFORMANCE BOND (continued)
Surety, for value received, stipulates and agrees that no change, extension of time,
alteration or addition to the term of the contract, or to the work performed thereunder,
or the plans, specifications, or drawings accompanying the same, shall in anywise affect
its obligation on this bond, and it does hereby waive notice of any such change, extension
of time, alteration or addition to the terms of the contract, or to the work to be performed
thereunder.
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this
6th day of December
instrument this
19 93 .
HAEGELIN CONSTRUCTION CO., INC. PLANET INSURANCE COMPANY
Address
Title
P. 0. Box 9086
Austin, Texas 78766
(512) 388 -9900
popbid.mR/gxc
PBD-4
Surety
By Ar-o
Bess Ann Roberts
Attorney -in -Fact
Title
c/o CIA Insurance Agency, Inc.
dba Consolidated Insurance Agency
Address
101 West 6th Street, #350
Austin, Texas 78701 -2995
(512) 478 -5631
The name and address of the Resident Agent of Surety is :
CIA Insurance Agency, Inc. dba Consolidated Insurance Agency
101 West 6th Street, 11350, Austin, Texas 78701 -2995
posibid.mittspec
PAYMENT BOND #P2502864
THE STATE OF TEXAS
COUNTY OF WILLIAMSON
KNOW ALL MEN BY THESE PRESENTS: That Haegelin Construction Co., Inc. , of the
City of Austin , County of Travis , and State of
Texas as Principal, and Planet Ins. Co. authorized under the laws of the
State of Texas to act as Surety on Bonds for Principals, are held and firmly bound unto
THE CITY OF ROUND ROCK, (OWNER), and all subcontractors, workers, laborers,
mechanics and suppliers as their interest may appear, all of whom shall have the right to
sue upon this bond, in the penal sum of
One hundred twenty three thousand, five hundred ninety
one & 50/100 Dollars ($ 123,591. ) for the payment
whereof, well and truly be made the said Principal and Surety bind themselves and their
heirs, administrators, executors, successors, and assigns, jointly and severally, by these
presents:
WHEREAS, the Principal has entered into a certain written contract with the Owner,
dated the 6th day of December , 19 93 , to which
Contract is hereby referred to and made a part hereof as fully and to the same extent as
if copied at length herein consisting of:
Water and Wastewater System Improvements for Dell Center Blvd.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the
said Principal shall well and truly pay all subcontractors, workers, laborers, mechanics,
and suppliers, all monies to them owing by said Principals for subcontracts, work, labor,
equipment, supplies and materials done and furnished for the construction of the
improvements of said Contract, then this obligation shall be and become null and void;
otherwise to remain in full force and effect.
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article
5160 of the Revised Civil Statutes of Texas as amended and all liabilities on this bond
shall be determined in accordance with the provisions of said Article to the same extent
as if it were copied at length herein.
PBD -5
PAYMENT BOND (continued)
Surety, for value received, stipulates and agrees that no change, extension of time,
alteration or addition to the terms of the contract, or to the work performed thereunder,
or the plans, specifications or drawings accompanying the same shall in anywise affect
it's obligation on this bond, and it does hereby waive notice of any such change,
extension of time, alteration or addition to the terms of the contract, or to the work to be
performed thereunder.
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this
Instrument this 6th day of member , 19 9
HAECELIN CONSTRUCTION CO., INC. PLANET INSURANCE COMPANY
Title
P. 0. Box 9086
Address
Austin, Texas 78766
(512) 488 -9900
(512) 478 -5631
The name and address of the Resident Agent of Surety is :
101 West 6th Street, #350, Austin, Texas 78701 -2995
pn.Wld.m.Vgac
PBD -6
Surety /f
By: /'1�4.a, �rr w /ter
Bess Ann Roberts -
Attorney -in -Fact
Title
c/o CIA Insurance Agency, Inc.
dba Consolidated Insurance Agency
Address
101 West 6th Street, #350
Austin, Texas 78701 -2995
CIA Insurance Agency, Inc. dba Consolidated Insurance Agency
•
PLANET INSURANCE COMPANY
HEAD OFFICE, MADISON, WISCONSIN 1 ` ,
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS, That the PLANET INSURANCE COMPANY, a corporation duly organized under the laws of the State
of Wisconsin, does hereby make, constitute and appoint Robt. H. Bowman, Thomas C. Womack, Bess Ann Roberts,
Peter Pincoffs, John S. Burns, Jr. and Joe George, individually, of Austin, Texas
its true and lawful Attorney -in -Fact, to make, execute, seal and deliver for and on its behalf, and as its act and deed
and undertakings of Suretyship,
any and all bonds
a to bind the PLANET INSURANCE COMPANY thereby as fully and to the same extent as if such bonds and undertakings and other writings
obligatory in the nature thereof were signed by an Executive Officer of the PLANET INSURANCE COMPANY and sealed and attested by one other of
such officers, and hereby ratifies and confirms all that its said Attorney(s)-in -Fact may do in pursuance hereof.
This Power of Attorney is granted under and by authority of Article VII of the By -Laws of PLANET INSURANCE COMPANY which became
effective September 21, 1981, which provisions are now in full force and effect, reading as follows:
ARTICLE VII — EXECUTION OF BONDS AND UNDERTAKINGS
1. The Board of Directors, the President, the Chairman of the Board, any Senior Vice President, any Vice President or Assistant Vice President
or other officer designated by the Board of Directors shall have power and authority to (a) appoint Attorneys- in-Fact and to authorize them to execute
on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof, and
(b) to remove any such Attorney -in -Fact at any time and revoke the power and authority given to him.
2. Attorneys -in -Fact shall have power and authority, subject to the terms and limitations of the power of attorney issued to them, to execute and
deliver on behalf of the Company, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof.
The corporate seal is not necessary for the validity of any bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory
in the nature thereof.
3. Attorneys -in -Fact shall have power and authority to execute affidavits required to be attached to bonds, recognizances, contracts of indemnity
or other conditional or obligatory undertakings and they shall also have power and authority to certify the financial statement of the Company and to
copies of the By -Laws of the Company or any article or section thereof.
This power of attorney is signed and sealed by facsimile under and by authority of the following Resolution adopted by the Board of Directors of
PLANET INSURANCE COMPANY at a meeting held on the 29th day of March, 1982, at which a quorum was present, and said Resolution has not been
amended or repealed:
"Resolved, that the signatures of such directors and officers and the seal of the Company may be affixed to any such power of attorney
or any certificate relating thereto by facsimile, and any such power of attorney or certificate bearing such facsimile signatures or facsimile
seal shall be valid and binding upon the Company and any such power so executed and certified by facsimile signatures and facsimile seal
shall be valid and binding upon the Company in the future with respect to any bond or undertaking to which it is attached."
IN WITNESS WHEREOF, the PLANET INSURANCE COMPANY has caused these presents to be signed by its Vice President, and its corporate seal to
be hereto affixed. this 12th day of September 19 89
STATE OF
COUNTY OF
On this
My Commission Expires:
February 1
IN WITNESS WHEREOF, 1 have hereunto set my han
BOP-1431 1/82
Pennsylvania
Philadelphia
12th day of September
"ate Assistant Secretary
,19 89 , personally appeared Raymond MacNeil '
to me known to be the Vice - President of the PLANET INSURANCE COMPANY, and acknowledged that he executed and attested the foregoing
instrument and affixed the seal of said corporation thereto, and that Article VII, Section 1, 2, and 3 of the By -Laws of said Company, and the Resolution,
set forth therein, are still in full force.
.19 93 `, " . f Notary Public in and for State of Penn.Sylvan
Residing at Philadelphia
L Ray L. Lorah , Assistant Secretary of PLANET INSURANCE COMPANY, do hereby certify that the
above and foregoing is a true and correct copy of a Powor of/tt@* - ss y executed by said PLANET INSURANCE COMPANY, which is still in full force
and effect. 2 �
of said Company this 6 th day of December
P
19 93
IMPORTANT NOTICE
To obtain information or make a complaint:
You may contact the Texas Department of Insurance to obtain information on
companies, coverages, rights or complaints at:
1- 800 - 252 -3439
You may write the Texas Department of Insurance:
P. 0. Box 149104
Austin, TX 78714 -9104
FAX #(512) 475 -1771
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your premium or about a claim, you should
contact the agent of the company first. If the dispute is not resolved, you may
contact the Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR POLICY:
This notice is for information only and does not become a part or condition of the
attached document.
AIDIII:11 CERTIMATE OF
PRODUCER
INSURED
Haegelin Construction Company
P.O. Box 9086
Austin, Texas 78766
Consolidated Insurance Agency
CIA Insurance Agency, Inc.
101 West 6th Street, Suite 350
Austin, TX 78701 (512)478 -5631
NSU l A tJCE ISSUE DATE (MAWDA'Y)
x € 5/10/1994
THIS CERTIFICATE IS ISSUED AS A Po MATTER OF INFORMATION ONLY AND
CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE
DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE
POUCIES BELOW.
COWMIY
LETIM
COMPANY
LEIER
COLWANY
LETTER
COMPANY D
LETTER
COMPANY
LE TER
COMPANIES AFFORDING COVERAGE
A Valley Forge Insurance Company
B Continental Casualty Company
C Transportation Ins. Company
Continental Casualty
Transcontinental Ins. Company
COVERAGES s - -
THIS IS TO CERTIFY THAT THE POUCIES OF INSURANCE USTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POUCIES DESCRIBED HEREIN IS SUBJECT TO AU. THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POUCIES. UMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
CO
LTR
A
GENERAL LIABILITY
X COMMERCIN. GENERN. LIABLITY A90027237T
CLAIMS MADE X OCCUR
OWNERS & CONRIACTCRS PROT.
AUTOMOBB.E LUIBLJTY
B X
IX
X
EXCESS LIABILITY
D X : UMBRELLA FORM
• OTHER THAN UMBRELLA FORM
OTHER
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
HIRED AUTOS
NON -OWNED AUTOS
GARAGE UABLTY
WORKER'S COMPENSATION
0000 -
EJMPLOYERS' DABLTTY
CERTIFIC hQL1S1:R - m..._..
City of Round Rock
Attn: Kathy Stagman
309 East Main
Round Rock TX 78664
ACORO 254 (7/90)
TYPE OF INSURANCE POLICY NUL®ER
• 8UA400272382
Al22211083
WC113339042
POLICY EFEECTLYE POLICY EXPPUTTON IAQIB
DATE (MLLBDAY) DATE(MMAD/YI')
GENERAL ADDFE:DATE s , 2 , 00
mmuclS VPAGG. $1,000,000
s 1,000,000
s 1,000,000
. FINE DAMAGE (Any one We) s 50,000
MIOD. E)S'ENSE W one pe.R) $ 5,000
05/16/94
05/16/94
05/16/94
05/16/94
05/16/95 rE° L ADY' DA"
EACH OCCURRENCE .
LIMIT CONFINED SINGLE 0 1,000,000
05/ 16/ 95!BGDLYWUJRY . s .
(Per Penn) .
GODLY AWRY .S
(Per accident
PROPERTY DAMAGE
EACH OCCURENCE
s 3,000,000
05/ 16/ 95 AGGREGATE s 3 000 000
. STAMCRY LIMITS
05 /16 /95EAHlCC
DISEASE _ POLL:Y LJMIT
DISEASE . EACH EMPLOYEE
•
DESCRIPTION OF OPETATIONLM1OCATIONSNEMCLES /SPECIAL HEMS
As respects Commercial General Liability and Business Automobile
policies City of Round Rock is shown as an additional insured.
Dell Center Blvd. - Dell Computer Job
s 1,090,000
1,000,000
s 1,000,000
£ c SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE MF „
EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO
MAIL 3 0 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE
LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR
LIABIUTY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES.
�,. T,..._._..
I £AUTHOR®
c : AYONSOLIDATEpwA AGENCY
%... ..............,.. Bye.., : - - �. r (4A I p �eA�l ..,..,
. • . • ••••• - 9 OR ANON •. AOO C 1998
ai oi:i�® CERTIFICATE - OF
CO
LTR
A
AUTOIADBLE LIABILITY
B $ ANY ALTO
X AIL OWNED AUTOS
.SOiEDULED AUTOS
$ • HEED AUTOS
X . NON-0KNED AUTOS
' GARAGE LUBLIN
EX W
CESS BLITY
D. g: UMBIELLA FORMA
• OTHER THAN U1,9RELUL FORM
WORKERS COMPENSATION
AND
EMPLOYERS' UABLITY
OMER
E Builder's Risk 004215
CERTIFICATE HOLDER
City of Round Rock
Attn: Kathy Stagman
309 East Main
Round Rock TX 78664
Consolidated Insurance Agency
CIA Insurance Agency, Inc.
101 West 6th Street, Suite 350
Austin, T$ 78701 (512)478 -5631
NSURED
Haegelin Construction Company
P.O. Boa 9086
Austin, Texas 78766
TYPE OF INSURANCE POLICY RUBBER
GENERAL LIABILITY
$ COMMERCIAL GENERAL uABLm A900272371
CANS MME ;:$:: OCCUR
OWNERS & CONTRACTORS PROT.
BUA400272382
Al22211083
WC113339042
INSURANCE
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND
CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE
DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE
POLICIES BELOW.
COMPANY
LETTER
COMPANY
LETTER
CCLIPANY
LEDER
CCLIPANY
.......... .
LEVER
CCMPANY
IJERER
A Valley Forge Insurance Company
B Continental Casualty Company
C Transportation Ins. Company
D Continental Casualty
E Transcontinental Ins. Company
COVERAGESS _ • _ __ •
THIS IS TO CERTIFY THAT THE POUCIES OF INSURANCE USTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY 80 ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POUCIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDMONS OF SUCH POLICIES. OMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAMS.
•
..... POLICY EFFECTIVE POLICY EXPIRATION lillq
DATE (MMrDOIYY) : DA7E(MMAD/YY)
:s 1,000,06'6
05/16/93 :OS /16 /94 '' °M0NPL8PD" • s �"' R ! '
EACH OCCURRENCE ;s 1,000,
•
•
FRE DAMAGE (Any one Km) is 50,000
•
• MED. E7WENSE (Any cne pereon S 5,000
COMBINED SINGLE
Limn- :S 1,000,000
05/16/93
05/16/93
05/16/93
12/15/93
05 / 16 / 9 4 AoOREMTE
• IBSUE•,RTF (M1 UDA'Y)
12/15/1993
COMPANIES AFFORDING COVERAGE
GENEALADDAEGATE s 2,000,000
PRODUCTS-COMP/OP AGO. E S 1. 0 0 0. 0 0 0
05/ 16/ 94 BODLY INJURY
' (Per perecn)
BODLY INJURY
(Per eaiden)
PROPERTY DMIAGE
EACH OCCURRENCE
STATUTORY LIMITS
DESCR0'TK/N OP OPERATIONS/LOCATIONSITEHICLEWSPEcIAL TEILS
As respects Commercial General Liability and Business Automobile
policies City of Round Rock is shown as an additional insured.
Dell Center Blvd. - Dell Computer Job
s 2,000,000
s 2,000,000
05/16/94 EACH ACCIDENT 1,000,000'1
DISEASE- POUCYLYAIT s 1,000,000'
DISEASE- EA.CHEMPLOYEE s 1,000,000
03/15/94 @ job site $123,592.
deductible ' $500.00
CANCELLATION - -
: SHOULD ANY OF THE ABOVE DESCRIBED POUCIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL BNCIEOLLCRI$(
• MAIL 30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE
• LEFFaidikaMBL/tikkZaktigaggAliht-PBEVAT,R
f T IL kFiVE1ANkti LeMRF 4LxT> 4cRGNa���1f?F BBL R5CX
i1CAVOf i= tegAiAbWLKYA EU,*
▪ ?DBA C SOLMATEMJRADI AGENCY
CORPORATION 1900-
To: City of Round Rock
221 East Main Street
Round Rock, Texas 78664
TYPE OF POLICY EFFECTIVE
INS. NO. DATE
Workmen's
Compensation
Comprehensive
General
Liability
Includes
Contractual
Liability
Covers
Independent
Contractors
Owner's
Protective
Contractors
popbid.m i/epx
CERTIFICATE OF INSURANCE
THIS IS TO CERTIFY THAT Haegelin Construction Co., Inc.is, at the date of this certificate,
insured by this company with respect to the business operations hereinafter described, for the types of
insurance and in accordance with the provisions of the standard policies used by this company, and
further hereinafter described. Exceptions to standard policies are noted on the reverse side hereof.
EXPIRATION
DATE
WC113339042 05/16/93 05/16/94
TPP90027237 -1 05/16/93
PBD -7
Date: December 6, 1993
Water and Wastewater System
Description of Work Improvements for
Dell Center Boulevard
LIMITS OF
LIABILITY
Statutory, State of
Texas, $ 500, 000.
Employer's Liability
Bodily Injury
05/16/94 $ /person
$ /person
$2,000,000 General Aggregate
$1,000,000 Each Occurrence
$1,000,000 Products Completed
Operations Agg
Property Damage
$ /accident
$ aggregate
Bodily Injury
$ /person
$ /accident
Property Damage
$ /accident
$ aggregate
.74
Certificate of Insurance (continued)
Comprehensive
Automobile
Liability
Owned Vehicles
Hired Vehicles
Non -owned Vehicles
Includes Contractual Liability
Contractual
Liability
BUA400272382 05/16/93 05/16/94
Bodily Injury
$ /person
$ /accident
Property Damage
$ /accident
$1,000,000 Combined Single
Limit - Bodily Injury and
Property Damage
The above policies either in the body thereof or by appropriate endorsement provide that they may not
be changed or canceled by the insurer in less than thirty (30) days after the insured has received written
notice of such change or cancellation.
The Certificate of Insurance neither affirmatively or negatively amends extends, or alters the coverage
afforded by policy or policies indicated by this certificate.
portbid.m t/.px
Transcontinental Insurance Company
Name of Insurer
By: O
. 7�
E. Peter Pincoffs
Title: A�nY
Address: 101 West 6th Street, #350
PBD -8
Austin, Texas 78701
(512) 478 -5631
MAINTENANCE BOND
BOND NUMBER
KNOW ALL MEN BY THESE PRESENTS,
That we,
AMOUNT
(hereinafter called the "Principal ") as
Principal, and the a Corporation duly organized
under the laws of the State of and duly licensed to
transact business in the State of (hereinafter called the
"Surety"), as Surety, are held and firmly bound unto THE CITY OF ROUND ROCK,
TEXAS (hereinafter called the "Obligee "), in the sum of
dollars ($ ) for the
payment of which sum well and truly to be made, we, the said Principal and the said
Surety, bind ourselves, our heirs, executors, administrators, successors and assigns,
jointly and severally, firmly, by these presents.
Sealed with our seals and dated this day of , A.D. nineteen
hundred and
WHEREAS, the said Principal has heretofore entered into a contract with
Dated ,19 , for construction of
WHEREAS, the said Principal is required to guarantee the construction of all
improvements installed under said contract, against defects in materials or workmanship,
which may develop during the period of year(s) from the date of
acceptance of the project above described, by Owner:
The City of Round Rock, Texas
NOW, THEREFORE, THE CONDITIONS OF THE OBLIGATIONS IS SUCH, that if
said Principal shall faithfully carry out and perform the said guarantee, and shall, on due
notice, repair and make good at its own expense any and all defects in materials or
workmanship in the said work which may develop during the period of
year(s) from the date of acceptance of the project above described, by Owner:
The City of Round Rock, Texas
po.tbid.mu/.{roc
PBD -9
MAINTENANCE BOND (continued)
OR shall pay over, make good and reimburse to the said Obligee all loss and damage
which said Obligee may sustain by reason of failure or default of said Principal so to do,
then this obligation shall be null and void; otherwise shall remain in full force and effect.
Principal Surety
By By
poubid.mNgKc
PBD -10
4.0 GENERAL CONDITIONS
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Contents
1. Definition of Terms
1.01 - Owner, Contractor and Engineer
1.02 - Contract Documents
1.03 - Subcontractor
1.04 - Sub - Subcontractor
1.05 - Written Notice
1.06 - Work
1.07 - Extra Work
1.08 - Working Day
1.09 - Calendar Day
1.10 - Substantially Completed
General Conditions of Agreement
2. Responsibilities of the Engineer and the Contractor
2.01 - Owner - Engineer Relationship
2.02 - Professional Inspection by Engineer
2.03 - Payments for Work
2.04 - Initial Determinations
2.05 - Objections
2.06 - Lines and Grades
2.07 - Contractor's Duty and Superintendence
2.08 - Contractor's Understanding
2.09 - Character of Workers
2.10 - Contractor's Buildings
2.11 - Sanitation
2.12 - Shop Drawings
2.13 - Preliminary Approval
2.14 - Defects and Their Remedies
2.15 - Changes and Alterations
2.16 - Inspectors
yrncood.ovdspec
GC -1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3. General Obligations and Responsibilities
3.01 - Keeping of Plans and Specifications Accessible
3.02 - Ownership of Drawings
3.03 - Adequacy of Design
3.04 - Right of Entry
3.05 - Collateral Contracts
3.06 - Discrepancies and Omissions
3.07 - Equipment, Materials and Construction Plant
3.08 - Damages
3.09 - Protection Against Accident to Employees and the Public
3.10 - Performance and Payment Bonds
3.11 - Losses from Natural Causes
3.12 - Protection of Adjoining Property
3.13 - Protection Against Claims of Subcontractors, etc.
3.14 - Protection Against Royalties or Patented Invention
3.15 - Laws and Ordinances
3.16 - Assignment and Subletting
3.17 - Indemnification
3.18 - Insurance
3.19 - Final Clean-Up
3.20 - Guarantee Against Defective Work
3.21 - Testing of Materials
3.22 - Wage Rates
4. Prosecution and Progress
4.01 - Time and Order of Completion
4.02 - Extension of Time
4.03 - Hindrances and Delays
5. Measurement and Payment
5.01 - Quantities and Measurements
5.02 - Estimated Quantities
5.03 - Price of Work
5.04 - Partial Payments
5.05 - Use of Completed Portions
5.06 - Final Completion and Acceptance
5.07 - Final Payment
5.08 - Payments Withheld
5.09 - Delayed Payments
gc o d mwp
GC -2
6. Extra Work and Claims
6.01 Change Orders
6.02 Minor Changes
6.03 Extra Work
6.04 Time of Filing Claims
6.05 Continuing Performance
6.06 Arbitration
7. Abandonment of Contract
7.01 Abandonment by Contractor
7.02 Abandonment by Owner
8. Subcontractors
8.01 Award of Subcontracts for Portions of Work
8.02 Subcontractual Relations
8.03 Payments to Subcontractors
9. Separate Contracts
9.01 Owner's Right to Award Separate Contracts
9.02 Mutual Responsibility of Contractors
9.03 Cutting and Patching Under Separate contracts
10. Protection of Persons and Property
10.01 Safety Precautions and Programs
10.02 Safety of Persons and Property
10.03 Location and Protection of Utilities
geaccod.mWryee
GC -3
1
1 General Conditions of Agreement
1 1. Definition of Terms
1 1.01 Owner, Contractor and Engineer
I The Owner, the Contractor and the Engineer and those persons or organization identified
as such in the Agreement and are referred to throughout the contract Documents as if
singular in number and masculine in gender. The term Engineer means the Engineer or
I his duly authorized representative. The Engineer shall be understood to be the Engineer
of the Owner, and nothing contained in the Contract Documents shall create any
contractual or agency relationship between the Engineer and the Contractor.
1 1.02 Contract Documents
I The Contract Documents shall consist of the Notice to Contractors, Instructions to
Bidders, Proposal, Signed Agreement, Performance and Payment Bonds (when required),
Special Bonds (when required), General Conditions of the Agreement, Construction
I Specifications, Plans and all modifications thereof incorporated in any of documents
before the execution of the agreement.
I The Contract Documents are complementary, and what is called for by any one shall be
as binding as if called for by all. In case of conflict between any of Contract documents,
priority of interpretation shall be in the following order: Signed Agreement, Performance
1 and Payment Bonds, Special Bonds (if any), Proposal, Special Conditions of Agreement,
Notice to Contractors, Technical Specifications, Plans, and General Conditions of
I Agreement.
1.03 Subcontractor
1 The term Subcontractor, as employed herein, includes only those having a direct contract
with the Contractor and it includes one who furnishes material worked to special design
I according to the plans or specifications of this work, but does not include one who
merely furnishes material not so worked.
1 1.04 Sub- subcontractor
The term Sub - Subcontractor means one who has a direct or indirect contract with a sub-
' contractor to perform any of the work at the site and includes one who furnishes material
worked to a special design according to the plans or specifications of this work, but does
not include one who merely furnishes material not so worked.
1
1 geseced.ma. GC-4
1
1 1.05 Written Notice
' Written notice shall be deemed to have been duly served if delivered in person to the
individual or to an officer of the corporation for whom it is intended, or if delivered at
or sent by registered mail to the last business address known to him who gives the notice.
1 1.06 Work
' The Contractor shall provide and pay for all materials, machinery, equipment, tools,
superintendence, labor, services, insurance, and all water, light, power, fuel,
transportation and other facilities necessary for the execution and completion of the work
covered by the contract documents. Unless otherwise specified, all materials shall be
new and both workmanship and materials shall be of a good quality. The Contractor
shall, if required, furnish satisfactory evidence as to the kind and quality of materials.
1 Materials or work described in words which so applied have a well known technical or
trade meaning shall be held to refer to such recognized standards.
' 1.07 Extra Work
The term "Extra Work" as used in this contract shall be understood to mean and include
all work that may be required by the Engineer or Owner to be done by the Contractor
to accomplish any change, alteration or addition to the work shown upon the plans, or
reasonably implied by the specifications, and not covered by the Contractor's Proposal,
except as provided under "Changes and Alteration," herein.
1.08 Working Day
A "Working Day" is defined as any day not including Saturdays, Sundays or any legal
holidays, in which weather or other conditions, not under the control of the Contractor,
will permit construction of the principal units of the work for a period of not less than
seven (7) hours between 7:00 a.m. and 6:00 p.m.
1 1.09 Calendar Day
1 "Calendar Day" is any day of the week or month, no days being excepted.
1.10 Substantially Completed
' By the term "substantially completed" is meant that the structure has been made suitable
for use or occupancy or the facility is in condition to serve its intended purpose, but still
may require minor miscellaneous work and adjustment.
1
g aim. GC -5
1
1 2. Responsibilities of the Engineer and the Contractor
2.01 Owner- Engineer Relationship
The Engineer will be the Owner's representative during construction. The duties,
1 responsibilities and limitations of authority of the Engineer as the Owner's representative
during construction are as set forth in the Contract Documents and shall not be extended
or limited without written consent of the Owner and Engineer. The Engineer will advise
and consult with the Owner, and all of Owner's instructions to the Contractor shall be
issued through the Engineer.
1 2.02 Professional Inspection by Engineer
' The Engineer shall make periodic visits to the site to familiarize himself generally with
the progress of the executed work and to determine if such work generally meets the
essential performance and design features and the technical and functional engineering
' requirements of the Contract Documents; provided and except, however, that the
Engineer shall not be responsible for making any detailed, exhaustive, comprehensive or
continuous on -site inspection of the quality or quantity of the work or be in any way
' responsible, directly or indirectly, for the construction means, methods, techniques,
sequences, quality, procedures, programs, safety precautions or lack of same incident
thereto or in connection therewith. Notwithstanding any other provision of this
' agreement or any other Contract Document, the Engineer shall not be in any way
responsible or liable for any acts, errors, omissions or negligence of the Contractor, any
Subcontractor or any of the Contractor's or Subcontractor's agents, servants or
' employees or any other person, firm or corporation performing or attempting to perform
any of the work.
' 2.03 Payments for Work
The Engineer shall review Contractor's applications for payment and supporting data,
' determine the amount owed to the Contractor and recommend, in writing, payment to
Contractor in such amounts; such recommendation of payment to Contractor constitutes
a representation to the Owner of Engineer's professional judgement that the work has
progressed to the point indicated to the best of his knowledge, information and belief,
but such recommendation of an application for payment to Contractor shall not be
1 deemed as a representation by Engineer that Engineer has made any examination to
determine how or for what purpose Contractor has used the moneys paid on account of
the Contract price.
zeocand.m,u. GC -6
2.04 Initial Determinations
The Engineer initially shall determine all claims, disputes and other matters in question
between the Contractor and the Owner relating to the execution or progress of the work
or the interpretation of the Contract Documents and the Engineer's decision shall be
rendered in writing within a reasonable time, which shall not be construed to be less than
ten (10) days. Appeal to arbitration upon mutual agreement may be taken as if his
decision had been rendered against the party appealing.
2.05 Objections
gencoad romc
In the event the Engineer renders any decision which, in the opinion of either party
hereto, is not in accordance with the meaning and intent of this contract, either party may
file with the Engineer within thirty (30) days his written objection to the decision, and
by such action may reserve the right to submit the question so raised to arbitration as
hereinafter provided.
2.06 Lines and Grades
Unless otherwise specified, all lines and grades shall be furnished by the Engineer or his
representative. Whenever necessary, construction work shall be suspended to permit
performance of this work, but such suspension will be as brief as practicable and the
Contractor shall be allowed no extra compensation therefor. The contractor shall give
the Engineer ample notice of the time and place where lines and grades will be needed.
All stakes, marks, etc., shall be carefully preserved by the Contractor, and in case of
careless destruction or removal by him or his employees, such stakes, marks, etc., shall
be replaced at the Contractor's expense.
2.07 Contractor's Duty and Superintendence
The Contractor shall give adequate attention to the faithful prosecution and completion
of this contract and shall keep on the work, during its progress, a competent English -
speaking superintendent and any necessary assistants to supervise and direct the work.
The superintendent shall represent the Contractor in his absence and all directions given
to him shall be as binding as if given to the Contractor.
The Contractor is and at all times shall remain an independent contractor, solely
responsible for the manner and method of completing his work under this contract, with
full power and authority to select the means, method and manner of performing such
work, so long as such methods do not adversely affect the completed improvements, the
Owner and Engineer being interested only in the result obtained and conformity of such
completed improvements to the plans, specifications and contract.
Likewise, the Contractor shall be solely responsible for the safety of himself, his
GC -7
employees and other persons, as well as for the protection and safety of the
improvements being erected and the property of himself or any other person, as a result
of his operations hereunder. Engineering construction drawings and specifications as
well as any additional information concerning the work to be performed passing from or
through the Engineer shall not be interpreted as requiring or allowing Contractor to
deviate from the plans and specifications, the intent of such drawings, specifications and
any other such information being to define with specificity the agreement of the parties
as to the work the Contractor is to perform. Contractor shall be fully and completely
liable, at his own expense, for design, construction, installation and use, or non -use of
all items and methods incident to performance of the contract, and for all loss, damage
or injury incident thereto, either to person or property, including, without limitation, the
adequacy of all temporary supports, shoring, bracing, scaffolding, machinery or
equipment, safety precautions or devices, and similar items or devices used by him
during construction.
Any review of work in process, or any visit or observation during construction, or any
clarification of plans and specifications, by the Engineer or Owner, or any agent,
employee, or representative of either of them, whether through personal observation on
the project site or by means of approval of shop drawings for temporary construction or
construction processes, or by other means or method, is agreed by the Contractor to be
for the purpose of observing the extent and nature of work completed or being
performed, as measured against the drawings and specifications constituting the contract,
or for the purpose of enabling Contractor to more fully understand the plans and
specifications so that the completed construction work will conform thereto, and shall in
no way relieve the Contractor from full and complete responsibility for the proper
performance of his work on the project, including but not limited to the propriety of
means and methods of the Contractor in performing said contract, and the adequacy of
any designs, plans or other facilities for accomplishing such performance. Deviation by
the Contractor from plans and specifications that may have been in evidence during any
such visitation or observation by the Engineer, or any of his representatives, whether
called to the contractor's attention or not shall in no way relieve Contractor from his
responsibility to complete all work in accordance with said plans and specifications.
2.08 Contractor's Understanding
geeemd.mitlryee
It is understood and agreed that the Contractor has, by careful examination, satisfied
himself as to the nature and location of the work, the conformation of the ground, the
character, quality and quantity of the materials to be encountered, the character of
equipment and facilities needed preliminary to and during the prosecution of the work,
the general and local conditions, and all other matters which can in any way effect the
work under this contract. The Contractor agrees that he will make no claim against the
Owner or the Engineer if, in the prosecution of the work, he finds that the actual site or
subsurface conditions encountered do not conform to those indicated by excavation, test
excavation, test procedures, borings, explorations or other subsurface excavations. No
GC -8
verbal agreement or conversation with any officer, agent or employee of the Owner or
Engineer either before or after the execution of this contract, shall affect or modify any
of the terms or obligations herein contained.
2.09 Character of Workers
The Contractor agrees to employ only orderly and competent workers, skillful in the
performance of the type of work required under this contract, to do the work; and agrees
that whenever the Engineer shall inform him in writing that any workers on the work
are, in his opinion, incompetent, unfaithful or disorderly, or refuse instructions from the
Engineer in the absence of the Superintendent, such worker shall be discharged from the
work and shall not again be employed on the work without the Engineer's written
consent. No illegal alien may be employed by any Contractor for work on this project,
and a penalty of $500.00 per day will be assessed for each day and for each illegal alien
who works for the Contractor at this project.
2.10 Contractor's Buildings
ewecod.mat/wee
The building of structures for housing workers, or the erection of tents or other forms
of protection, will be permitted only at such places as the Engineer shall direct, and the
sanitary conditions of the grounds in or about such structures shall at all times be
maintained in a manner satisfactory to the Engineer.
2.11 Sanitation
Necessary sanitary conveniences for the use of laborers on the work, properly secluded
from public observation, shall be constructed and maintained by the Contractor in such
manner and at such points as shall be approved by the Engineer, and their use shall be
strictly enforced.
2.12 Shop Drawings
The Contractor shall submit to the Engineer, with such promptness as to cause no delay
in his own work or in that of any other Contractor, four (4) checked copies, unless
otherwise specified, of all shop and/or setting drawings and schedules required for the
work of the various trades, and the Engineer shall pass upon them with reasonable
promptness, making desired corrections. The Contractor shall make any corrections
required by the Engineer, file with him two (2) corrected copies and furnish such other
copies as may be needed. The Engineer's review of such drawings or schedules shall
not relieve the Contractor from responsibility for deviations from drawings or
specifications, unless he has in writing called the Engineer's attention to such deviations
at the time of submission, nor shall it relieve him from responsibility for errors of any
sort in shop drawings or schedules. It shall be the Contractor's responsibility to fully
and completely review all shop drawings to ascertain their effect on his ability to perform
GC -9
gelaccad.cutivet
the required contract work in accordance with the plans and specifications and within the
contract time.
Such review by the Engineer shall be for the sole purpose of determining the general
conformity of said shop drawings or schedules to result in finished improvements in
conformity with the plans and specifications, and shall not relieve the Contractor of his
duty as an independent contractor as previously set forth, it being expressly understood
and agreed that the Engineer does not assume any duty to pass upon the propriety or
adequacy of such drawings or schedules, or any means or methods reflected thereby, in
relation to the safety of either person or property during Contractor's performance
hereunder.
2.13 Preliminary Approval
The Engineer shall not have the power to waive the obligations of this contract for the
furnishing by the Contractor of good material, and of his performing good work as
herein described, and in full accordance with the plans and specifications. No failure or
omission of the Engineer to discover, object to or condemn any defective work or
material shall release the Contractor from the obligations to fully and properly perform
the contract, including without limitations, the obligation to at once tear out, remove and
properly replace the same at any time prior to final acceptance upon the discovery of said
defective work or material; provided, however, that the Engineer shall, upon request of
the Contractor, inspect and accept or reject any material furnished, and in event the
material has been once accepted by the Engineer, such acceptance shall be binding on the
Owner, unless it can be clearly shown that such material furnished does not meet the
specifications for this work.
Any questioned work may be ordered taken up or removed for re- examination, by the
Engineer, prior to final acceptance, and if found not in accordance with the plans and /or
specifications for said work, all expense of removing, re- examination and replacement
shall be borne by the Contractor, otherwise the expense thus incurred shall be allowed
as Extra Work, and shall be paid for by the Owner; provided that, where inspection or
approval is specifically required by the specifications prior to performance of certain
work, should the Contractor proceed with such work without requesting prior inspection
or approval he shall bear all expense of taking up, removing, and replacing this work if
so directed by the Engineer.
2.14 Defects and Their Remedies
It is further agreed that if the work or any part thereof, or any material brought on the
site of the work for use in the work or selected for the same, shall be deemed by the
Engineer as unsuitable or not in conformity with the plans, specifications, or the intent
thereof, the Contractor shall after receipt of written notice thereof from the Engineer,
GC -10
forthwith remove such material and rebuild or otherwise remedy such work so that it
shall be in full accordance with this contract.
2.15 Changes and Alterations
Ymemd.wuWa
The Contractor further agrees that the Owner may make such changes and alterations as
the Owner may see fit, in the line, grade, form, dimensions, plans or materials for the
work herein contemplated, or any part thereof, either before or after the beginning of the
construction, without affecting the validity of this contract and the accompanying
Performance and Payment Bonds.
If such changes or alterations diminish the quantity of the work to be done, they shall not
constitute the basis for a claim for damages, or anticipated profits on the work that may
be dispensed with, except as provided for unit price items under Section 5 "Measurement
and Payment ". If the amount of work is increased, and the work can fairly be classified
under the specifications, such increase shall be paid for according to the quantity actually
done and at the unit price, if any, established for such work under this contract, except
as provided for unit price items under Section 5 "Measurement and Payment "; otherwise,
such additional work shall be paid for as provided under Extra Work. In case the Owner
shall make such changes or alterations as shall make useless any work already done or
material already furnished or used in said work, then the Owner shall recompense the
Contractor for any material or labor so used, and for any actual loss occasioned by such
change, due to actual expense incurred in preparation for the work as originally planned.
2.16 Inspectors
The Engineer may provide one (or more) field inspectors at the work site for the limited
purpose of observing the work in progress and reporting back to the Engineer on the
extent, nature, manner and performance of the work so that the Engineer may more
effectively perform his duties hereunder. Such inspectors may also communicate between
Engineer and Contractor their respective reports, opinions, questions, answers and
clarifications concerning the plans, specifications and work but shall not be deemed the
agent of the Contractor for all purposes in communicating such matters.
Such inspector may confer with the Contractor or Contractor's superintendent concerning
the prosecution of the work and its conformity with the plans and specifications but shall
never be, in whole or part, responsible for, charged with, nor shall he assume, any
authority or responsibility for the means, methods or manner of completing the work or
of the superintendence of the work or of the Contractor's employees. It is expressly
understood and agreed that any such inspector is not authorized by the Engineer or
Owner to independently act for either or answer on behalf of either, any inquiries of the
Contractor concerning the plans, specifications or work. No inspector's opinion; advice;
interpretation of the plans or specifications of this contract; apparent or express approval
of the means, methods or manner of Contractor's performance of work in progress or
GC -11
completed; or discovery or failure to discover or object to defective work of materials
shall release Contractor from his duty to complete all work in strict accordance with the
plans and specifications or stop the Owner or Engineer from requiring that all work be
fully and properly performed including, if necessary, removal of defective or otherwise
unacceptable work and the re -doing of such work.
3. General Obligations and Responsibilities
3.01 Keeping of Plans and Specifications Accessible
The Engineer shall furnish the Contractor with an adequate and reasonable number of
copies of all plans and specifications without expense to him and the Contractor shall
keep one (1) copy of the same constantly accessible on the work, with the latest revisions
noted thereon.
3.02 Ownership of Drawings
All drawings, specifications and copies thereof furnished by the Engineer shall not be
reused on other work, and, with the exception of the signed contract sets, are to be
returned to him on request, at the completion of the work. All models are the property
of the Owner.
3.03 Adequacy of Design
It is understood that the Owner believes it has employed competent engineers and
designers. It is therefore agreed that the Owner shall be responsible for the adequacy of
the design, sufficiency of the Contract Documents, the safety of the structure and the
practicability of the operations of the completed project; provided the Contractor has
complied with the requirements of the said Contract Documents, all approved
modifications thereof, and additions and alterations thereto approved in writing by the
Owner. The burden of proof of such compliance shall be upon the Contractor to show
that he has complied with the said requirements of the Contract Documents, approved
modification thereof and all approved additions and alterations thereto.
3.04 Right of Entry
The Owner reserves the right to enter the property or location of which the works herein
contracted for are to be constructed or installed, by such agent or agents as he may elect,
for the purpose of inspecting the work, or for the purpose of constructing or installing
such collateral work as said Owner may desire.
GC -12
1 3.05 Collateral Contracts
The Owner agrees to provide by separate contract or otherwise, all labor and material
essential to the completion of the work specifically excluded from this contract, in such
manner as not to delay the progress of the work, or damage said Contractor, except
where such delays are specifically mentioned elsewhere in the Contract Documents. The
Owner will attempt to coordinate the collateral work of utility companies regulated by
City franchises, but the City shall not be responsible for delays or other damages to the
Contractor which may result from their acts or omissions.
3.06 Discrepancies and Omissions
The Contractor shall provide written notice to the Engineer of any omissions or
1 discrepancies found in the contract. It is further agreed that it is the intent of this
contract that all work must be done and all material must be furnished in accordance with
the generally accepted practice for construction, and in the event of any discrepancies
' between the separate contract documents, the priority of interpretation defined under
"Contract Documents" shall govern. In the event that there is still any doubt as to the
meaning and intent of any portion of the contract, specifications or drawings, the
' Engineer shall define which is intended to apply to the work.
3.07 Equipment, Materials and Construction Plant
The Contractor shall be responsible for the care, preservation, conservation, and
protection of all materials, supplies, machinery, equipment, tools, apparatus, accessories,
facilities, all means of construction, and any and all parts of the work, whether the
Contractor has been paid, partially paid, or not paid for such work, until the entire work
is completed and accepted.
1 3.08 Damages
' In the event the Contractor is damaged in the course of completion of the work by the
act, neglect, omission, mistake or default of the Owner or Engineer, thereby causing loss
to the Contractor, the Owner agrees that he will reimburse the Contractor for such loss.
' In the event the Owner is damaged in the course of the work by the act, negligence,
omission, mistake or default of the Contractor, or should the Contractor unreasonably
delay the progress of the work being done by others on the job so as to cause loss for
which the Owner becomes liable, then the Contractor shall reimburse the Owner for such
loss.
3.09 Protection Against Accident to Employees and the Public
1 The Contractor shall at all times exercise reasonable precautions for the safety of
employees and others on or near the work and shall comply with all applicable provisions
g cood.m.u,p« GC -13
geoeood.mal/pa
of Federal, State, and Municipal safety laws and building and construction codes. All
machinery and equipment and other physical hazards shall be guarded in accordance with
the "Manual of Accident Prevention in Construction" of the Associated General
Contractors of America except where incompatible with Federal, State, or Municipal
laws or regulations. The Contractor shall provide such machinery guards, safe
walkways, ladders, bridges, gangplanks, and other safety devices. The safety
precautions actually taken and their adequacy shall be the sole responsibility of the
Contractor, acting at his discretion as an independent contractor.
In the event there is an accident involving injury to any individual on or near the work,
the Contractor shall immediately notify the Owner and Engineer of the event and shall
be responsible for recording the location of the event and the circumstances surrounding
the event through photographs, interviewing witnesses, obtaining of medical reports and
other documentation that defines the event. Copies of such documentation shall be
provided to the Owner and the Engineer for their records.
3.10 Performance and Payment Bonds
Unless otherwise specified, it is further agreed by the Parties to the Contract that the
Contractor will execute separate performance and payment bonds, each in the sum of one
hundred (100 %) percent of the total contract price, in standard forms for this purpose,
guaranteeing faithful performance of the work and the fulfillment of any guarantee
required, and further guaranteeing payment to all persons supplying labor and materials
or furnishing him any equipment in the execution of the Contract. If the contract price
is less that $50,000.00, a letter of credit may be furnished in lieu of a performance bond.
It is agreed that the Contract shall not be in effect until such performance bond or letter
of credit, and payment bond are furnished and approved by the owner.
Unless otherwise specified, the cost of the premium for the performance bond or letter
of credit, and payment bond shall be included in the price bid by the Contractor for the
work under this Contract, and no extra payment for such bond or letter of credit will be
made by the Owner.
Unless otherwise approved in writing by the Owner, the surety company underwriting
the bonds or letter of credit shall be acceptable according to the latest list of companies
holding certificates of authority from the Secretary of the Treasury of the United States
and shall be licensed to write such bonds or letters of credit in the State of Texas.
3.11 Losses from Natural Causes
Unless otherwise specified, all loss or damage to the Contractor arising out of the nature
of the work to be done, or from the action of the elements, or from any unforeseen
circumstance in the prosecution of the same, or from unusual obstructions or difficulties
which may be encountered in the prosecution of the work, shall be sustained and borne
GC -14
Qeumd.matlpee
by the Contractor at his own cost and expense.
3.12 Protection of Adjoining Property
The said Contractor shall take proper means to protect the adjacent or adjoining property
or properties in any way encountered, which might be injured or seriously affected by
any process of construction to be undertaken under this Agreement, from any damage
or injury by reason of said process of construction; and he shall be liable for any and all
claims for such damage on account of his failure to fully protect all adjoining property.
The Contractor agrees to indemnify, save and hold harmless the Owner and Engineer
against any claim or claims for damages due to any injury to any adjacent or adjoining
property, arising or growing out of the performance of the contract regardless of whether
or not it is caused in part by a party indemnified hereunder, but any such indemnity shall
not apply to any claim of any kind arising solely out of the existence or character of the
work.
3.13 Protection Against Claims of Subcontractors, Laborers, Materialmen and
Furnishers of Machinery, Equipment and Supplies
The Contractor agrees that he will indemnify and save the Owner and Engineer harmless
from all claims growing out the lawful demands of Subcontractors, laborers, workers,
mechanics, materialmen and furnishers of machinery and parts thereof, equipment, power
tools, and all supplies, including commissary, incurred in the furtherance of the
performance of this contract. When so desired by the Owner, Contractor shall furnish
satisfactory evidence that all obligations of the nature hereinabove designated have been
paid, discharged or waived. If the Contractor fails to do so, then the Owner may at the
option of the Contractor either pay directly any unpaid bills, of which the Owner has
written notice, or withhold from the Contractor's unpaid compensation a sum of money
deemed reasonably sufficient to liquidate any and all such lawful claims until satisfactory
evidence is furnished that all liabilities have been fully discharged, whereupon payments
to the Contractor shall be resumed in full, in accordance with the terms of this contract,
but in no event shall the provisions of this sentence be construed to impose any obligation
upon the Owner by either the Contractor or his Surety.
3.14 Protection Against Royalties or Patented Invention
The Contractor shall pay all royalties and license fees, and shall provide for the use of
any design, device, material or process covered by letter patent or copyright by suitable
legal agreement with the patentee or owner. The contractor shall defend all suits or
claims for infringement of any patent or copyright rights and shall indemnify and save
the Owner and Engineer harmless from any loss on account thereof, except that the
Owner shall defend all such suits and claims and shall be responsible for all such loss
when a particular design, device, material or process or the product of a particular
manufacturer or manufacturers is specified or required by the Owner; provided, however,
GC -15
if choice of alternate design, device, material or process is allowed to the Contractor,
then Contractor shall indemnify and save Owner harmless form any loss on account
thereof. If the material or process specified or required by the Owner is known by the
Contractor to be an infringement, the Contractor shall be responsible for such loss unless
he promptly gives such information to the Owner.
3.15 Laws and Ordinances
The Contractor shall at all times observe and comply with all Federal, State and local
laws, ordinance and regulations, which in any manner affect the contract or the work,
and shall indemnify and save harmless the Owner and Engineer against any claim arising
from the violation of any such laws, ordinances, and regulations whether by the
Contractor or his employees, except where such violations are called for by the
provisions of the Contract Documents. If the Contractor observes that the plans and
specifications are at variance therewith, he shall promptly notify the Engineer in writing,
and any necessary changes shall be prepared as provided in the contract for changes in
the work. If the Contractor performs any work knowing it to be contrary to such laws,
ordinances, rules and regulations, and without such notice to the Engineer, he shall bear
all costs arising therefrom. In case the Owner is a body politic and corporate, the law
from which it derives its powers, insofar as the same regulates the objects for which, or
the manner in which, or the conditions under which the Owner may enter into contract,
shall be controlling, and shall be considered as part of this contract, to the same effect
as though embodied herein.
3.16 Assignment and Subletting
The Contractor further agrees that he will retain personal control and will give his
personal attention to the fulfillment of this contract and that he will not assign by Power
of Attorney, or otherwise, or sublet said contract without the written consent of the
Engineer, and that no part or feature of the work will be sublet to anyone objectionable
to the Engineer or the Owner. The Contractor further agrees that the subletting of any
portion or feature of the work, or materials required in the performance of this contract,
shall not relieve the Contractor from his full obligations to the Owner, as provided by
this Agreement.
3.17 Indemnification
The Contractor shall defend, indemnify and hold harmless the Owner and the Engineer
and their respective officers, agents and employees, from and against all damages,
claims, losses, demands, suits, judgements and costs, including reasonable attorneys' fees
and expenses, arising out of or resulting from the performance of the work, provided that
any such damages, claim, loss, demand, suit, judgment, cost or expense:
GC -16
;eoeand.matirycc
1. Is attributable to bodily injury, sickness, disease or death to any person including
Contractor's employees and any Subcontractor's employees and any Sub -
Subcontractor's employees or to injury to or destruction of tangible property
including Contractor's property (other than the work itself) and the property of
any Subcontractor of Sub - Subcontractor including the loss of use resulting
therefrom; and,
2. Is caused in whole or in part by any intentional or negligent act or omission of
the Contractor, any Subcontractor, any Sub - subcontractor or anyone directly or
indirectly employed by any one of them or anyone for whose acts any of them
may be liable, regardless of whether or not it is caused in part by a party
indemnified hereunder.
The obligation of the Contractor under this Paragraph shall not extend to the liability of
the Engineer, his agents or employees arising out of the preparation of maps, plans,
reports, surveys, Change Orders, designs or specifications, or the approval of maps,
plans, reports, surveys, Change Orders, designs or specifications or the issuance of or
the failure to give directions or instructions by the Engineer, his agents or employees,
provided such is the sole cause of the injury or damage.
In any and all claims against the Owner or the Engineer or any of their agents or
employees by any employee of the Contractor, any Subcontractor, any Sub -
Subcontractor, anyone directly or indirectly employed by any of them or anyone for
whose acts any of them may be liable, the indemnification obligation under Paragraph
3.17 shall not be limited in any way by any limitation on the amount or type of damages,
compensation or benefits payable by or for the Contractor or any Subcontractor or Sub -
Subcontractor under workmen's compensation acts, disability benefit acts or other
employee benefit acts.
3.18 Insurance
The Contractor shall vary insurance as follows for the duration of this contract.
A. Statutory Workmen's Compensation.
B. Comprehensive General Liability Insurance with minimum Bodily Injury limits
of $300,000 for each occurrence including like coverage for acts and omissions
of Subcontractors and contractual liability coverage.
C. Property Damage Insurance with minimum limits of $50,000 for each occurrence
including like coverage for acts and omissions of Subcontractors and contractual
liability coverage.
GC -17
amccad.mu/yKe
D. Automobile Liability Insurance for all owned, non - owned, and hired vehicles with
minimum limits for Bodily Injury of $100,000 for each person and $300,000 for
each occurrence and Property Damage minimum limits of $50,000 for each
occurrence. Contractor shall require subcontractors to provide Automobile
Liability Insurance with same minimum limits.
The Contractor shall not commence work at the site under this contract until he has
obtained all required insurance and until such insurance has been approved by the Owner
and Engineer. The Contractor shall not allow any Subcontractors to commence work
until all insurance required has been obtained and approved. Approval of the insurance
by the Owner and Engineer shall not relieve or decrease the liability of the contractor
hereunder.
The required insurance must be written by a company licensed to do business in Texas
at the time the policy is issued. In addition, the company must be acceptable to the
Owner and all insurance (other than Workmen's compensation) shall be endorsed to
include the Owner as an additional insured thereunder.
The Contractor shall not cause any insurance to be cancelled nor permit any insurance
to lapse. All insurance certificates shall include a clause to the effect that the policy shall
not be cancelled or reduced, restricted or limited until ten (10) days after the Owner has
received written notice as evidenced by return receipt of registered or certified letter.
Certificates of Insurance shall contain transcripts from the proper office of the insurer,
evidencing in particular those insured, the extent of the insurance, the location and the
operations to which the insurance applies, the expiration date, and the above mentioned
notice of cancellation clause.
3.19 Final Clean -up
Upon the completion of the work and before acceptance and final payment will be made,
the Contractor shall clean and remove from the site of the work, surplus and discarded
materials, temporary structures and debris of every kind. He shall leave the site of the
work in a neat and orderly condition at least equal to that which originally existed.
Surplus and waste materials removed from the site of the work shall be disposed of at
locations satisfactory to the Engineer.
In the event Contractor fails or refuses to clean and remove surplus materials and debris
as above provided, the Owner or Engineer may do so, or cause same to be done, at the
Contractor's expense and the reasonable cost thereof shall be deducted from the final
payment.
3.20 Guarantee Against Defective Work
The contractor warrants the materials and workmanship and that the work is in
GC -18
3.21 Testing of Materials
gcncccd.m,uryu
conformance with the plans and specifications included in this contract for a period of
one year from the date of acceptance of the project. Said warranty binds the contractor
to correct any work that does not conform with such plans and specifications or any
defects in workmanship or materials furnished under this con tract which may be
discovered within the said one year period. The Contractor shall at his own expense
correct such defect within thirty days after receiving written notice of such defect from
the Owner or Engineer by repairing same to the condition called for in the contract
documents and plans and specifications. Should the Contractor fail or refuse to repair
such defect within the said thirty day period or to provide acceptable assurances that such
repair work will be completed within a reasonable time thereafter, the Owner may repair
or cause to be repaired any such defect at the Contractor's expense.
Unless otherwise specified, testing of all materials to be incorporated into the project will
be as directed by the Engineer at the expense of the Owner. All retesting for work
rejected on the basis of test results will be at the expense of the Contractor and the extent
of the retesting shall be determined by the Engineer. The Engineer may require
additional testing for failing tests and may require two passing retests before acceptance
will be made by the Owner. The testing laboratory will be designated by the Owner.
All materials to be incorporated into the project must meet the requirements of these
specifications. For manufactured materials such as reinforcing steel, expansion joint
materials, concrete pipe, cement, miscellaneous steel, cast iron materials, etc. , the
Contractor will be required to furnish a manufacturer's certificate stating that the material
meets the requirements specified for this project.
3.22 Wage Rates
Contractors are required to pay the prevailing wage rates to laborers, workmen and
mechanics employed on behalf of the city engaged in the construction of public works.
The wage rate for these jobs shall be the general prevailing wage rates for work of a
similar character. This applies to contractors and subcontractors. The contractor and
subcontractors shall keep and make available records of workers and their wages.
Prevailing wage rates are published by the U. S. Department of Labor, Bureau of Labor
Statistics, Southwestern Division and the Texas Employment Commission for the Austin
Job Bank Area. The wage rate shall not be less than the minimum wage rates set by the
U. S. Department of Labor, Employment Standards Administration, Wage and Hour
Division. There is penalty of $10.00 per worker per day or portion of a day that the
prevailing wage rate is not paid by the contractor or any subcontractor.
GC -19
1
1 4. Prosecution and Progress
4.01 Time and Order of Completion
It is the meaning and intent of this contract, unless otherwise herein specifically
1 provided, that the Contractor shall be allowed to prosecute his work at such times and
seasons, in such order of precedence, and in such manner as shall be most conducive to
economy of construction; provided, however, that the order and the time of prosecution
shall be such that the work shall be substantially completed as a whole and in part, in
accordance with this contract, the plans and specifications, and within the time of
completion designated in the Proposal: provided, also, that when the Owner is having
other work done, either by contract or by his own force, the Engineer may direct the
time and manner of constructing the work done under this contract, so that conflict will
be avoided and the construction of the various works being done for the Owner shall be
harmonized.
' The Contractor shall submit, at such times as may reasonably be requested by the
Engineer, schedules which shall show the order in which the Contractor proposes to
carry on the Work, with dates at which the Contractor will start the several parts of the
' work, and estimated dates of completion of the several parts.
4.02 Extension of Time
' Should the Contractor be delayed in the completion of the work by any act or neglect of
the Owner or Engineer, or of any employee of either, or by other contractors employed
' by the Owner, or by changes ordered in the work, or by strikes, lockouts, fires, and
unusual delays by common carriers, or unavoidable cause or causes beyond the
Contractor's control, or by any cause which the Engineer shall decide justifies the delay,
then an extension of time shall be allowed for completing the work, sufficient to
compensate for the delay, the amount of the extension to be determined by the Engineer,
provided, however, that the Contractor shall give the Engineer prompt notice in writing
of the cause of such delay. Adverse weather conditions will not be justification for
extension of time on "Calendar Days" contracts.
4.03 Hindrances and Delays
No claims shall be made by the Contractor for damages resulting from hindrances or
1
delays from any cause (except where the work is stopped by order of and for the
convenience of the Owner) during the progress of any portion of the work embraced in
' this contract. In case said work shall be stopped by the act of the Owner, then such
expense as in the judgment of the Engineer is caused by such stoppage of said work shall
be paid by the Owner to the Contractor.
1 ecm.m.u.Q« GC -20
5. Measurement and Payment
5.01 Quantities and Measurements
5.02 Estimated Quantities
gacad.mstl.pcc
No extra or customary measurements of any kind will be allowed, but the actual
measured and/or computed length, area, solid contents, number and weight only shall be
considered, unless otherwise specifically provided.
This agreement, including the specifications, plans and estimate, is intended to show
clearly all work to be done and material to be furnished hereunder. Where the estimated
quantities are shown for the various claccFs of work to be done and material to be
furnished under this contract, they are approximate and are to be used only as a basis for
estimating the probable cost of the work and for comparing the proposals offered for the
work. It is understood and agreed that the actual amount of work to be done and
material to be furnished under this contract may differ somewhat from these estimates,
and that where the basis for payment under this contract is the unit price method,
payment shall be for the actual amount of such work done and material furnished.
Where payment is based on the unit price method, the Contractor agrees that he will
make no claim for damages, anticipated profits or otherwise on account of any
differences which may be found between the quantities of work actually done, the
material actually furnished under this contract and the estimated quantities contemplated
and contained in the proposal; provided, however, that in case the actual quantity of any
major item should become as much as 20% more than, or 20% less than the estimated
or contemplated quantity for such items, then either party to this Agreement, upon
demand, shall be entitled to revised consideration upon the portion of the work above or
below 20% of the estimated quantity.
A "Major Item" shall be construed to be any individual bid item incurred in the proposal
that has a total cost equal to or greater that five (5) percent of the total contract cost,
computed on the basis of the proposal quantities and the contract unit prices.
Any revised consideration is to be determined by agreement between the parties,
otherwise by the terms of this Agreement, as provided under "Extra Work ".
5.03 Price of Work
In consideration of the furnishing of all the necessary labor, equipment and material, and
the completion of all work by the Contractor, and on the completion of all work and on
the delivery of all material embraced in this Contract in full conformity with the
specifications and stipulations herein contained, the Owner agrees to pay the Contractor
the prices set forth in the Proposal hereto attached, which has been made a part of this
GC -21
contract. The Contractor hereby agrees to receive such prices in full for furnishing all
material and all labor required for the aforesaid work, also for all expense incurred by
him, and for well and truly performing the same and the whole thereof in the manner and
according to this Agreement.
5.04 Partial Payments
ameu"d.m.Upx
On or before the 1st day of each month, the Contractor shall submit to the Engineer a
statement showing the total value of the work performed up to and including the 25th day
of the preceding month. The statement shall also include the value of all sound materials
delivered on the job site and to be included in the work and all partially completed work
whether bid as a lump sum or a unit item which in the opinion of the Engineer is
acceptable. The Engineer shall examine and approve or modify and approve such
statement.
The Owner shall then pay the Contractor on or before the 20th day of the current month
the total amount of the approved statement, less 10 percent of the amount thereof, which
10 percent shall be retained until final payment, and further less all previous payments
and all further sums that may by retained by the Owner under the terms of this
Agreement. It is understood, however, that in case the whole work be near to
completion and some unexpected and unusual delay occurs due to no fault or neglect on
the part of the Contractor, and Owner may - upon written recommendation of the
Engineer - pay a reasonable and equitable portion of the retained percentage to the
Contractor; or the Contractor at the Owner's option, may be relieved of the obligation
to fully complete the work and, thereupon, the Contractor shall receive payment of the
balance due him under the contract subject only to the conditions stated under "Final
Payment ".
5.05 Use of Completed Portions
The Owner shall have the right to take possession of and use any completed or partially
completed portions of the work, notwithstanding the time for completing the entire work
or such portions may not have expired but such taking possession and use shall not be
deemed an acceptance of any work not completed in accordance with the Contract
Documents. If such prior use increases the cost of or delays the work, the Contractor
shall be entitled to such extra compensation, or extension of time, or both, as the
Engineer may determine.
The Contractor shall notify the Engineer when, in the Contractor's opinion, the contract
is "substantially completed" and when so notifying the Engineer, the Contractor shall
furnish to the Engineer in writing a detailed list of unfinished work. The Engineer will
review the Contractor's list of unfinished work and will add thereto such items as the
Contractor has failed to include. The "substantial completion" of the structure or facility
shall not excuse the Contractor from performing all of the work undertaken, whether of
GC -22
a minor or major nature, and thereby completing the structure or facility in accordance
with the Contract Documents.
5.06 Final Completion and Acceptance
Within ten (10) days after the Contractor has given the Engineer written notice that the
work has been completed, or substantially completed, the Engineer and the Owner shall
inspect the work and within said time, if the work be found to be completed in
accordance with the Contact Documents, the Engineer shall issue to the Owner and the
Contractor his Certificate of Completion, and thereupon it shall be the duty of the Owner
to issue a Certificate of Acceptance of the work to the Contractor or to advise the
Contractor in writing of the reason for non - acceptance.
5.07 Final Payment
Upon the issuance of the Certificate of Completion, the Engineer shall proceed to make
final measurements and prepare final statement for the value of all work performed and
materials furnished under the terms of the Agreement and shall certify same to the
Owner, who shall pay to the Contractor on or before the 30th day, and before the 35th
day, after the date of the Certificate of Completion, the balance due the Contractor under
the terms of this contract; and said payment shall become due in any event upon said
performance by the Contractor. Neither the Certificate of Acceptance nor the final
payment, nor any provision in the Contract Documents, shall relieve the Contractor of
the obligation for fulfillment of any warranty which may be required.
5.08 Payments Withheld
geocood.mst/spcc
The Owner may, on account of subsequently discovered evidence, withhold or nullify the
whole or part of any certificate to such extent as may be necessary to protect himself
from loss on account of:
a) Defective work not remedied or other obligations hereunder not done.
b) Claims filed or reasonable evidence indicating probable filing of claims.
c) Failure of the Contractor to make payments properly to subcontractors or for
material or labor.
d) Damage to the Owner or another contractor's work, material or equipment.
e) Reasonable doubt that the work can be completed for the unpaid balance of the
contract amount.
GC -23
f) Reasonable indication that the work will not completed within the contract time.
g) Other causes affecting the performance of the contract.
When the above grounds are removed or the Contractor provides a Surety Bond
satisfactory to the Owner, which will protect the Owner in the amount withheld, payment
shall be made for amounts withheld because of them.
5.09 Delayed Payments
Should the Owner fail to make payment to the Contractor of the sum named in any
partial or final statement, when payment is due, then the Owner shall pay to the
Contractor, in addition to the sum shown as due by such statement, interest thereon at
the rate of 6% per annum, unless otherwise specified, from date due as provided under
'partial payments' and final 'payments,' until fully paid, which shall fully liquidate any
injury to the Contractor growing out of such delay in payment. It is expressly agreed
that delay by the Owner in making payment to the Contractor of the sum named in any
partial or final statement shall not constitute a breach of this contract on the part of the
Owner nor an abandonment thereof nor shall it to any extent or for any time relieve the
Contractor of his obligations to fully and completely perform hereunder.
6. Extra Work and Claims
6.01 Change Orders
Without invalidating this Agreement, the Owner may, at any time or from time to time,
order additions, deletions or revisions to the work; such changes will be authorized by
Change Order to be prepared by the Engineer for execution by the Owner and the
Contractor. The Change Order shall set forth the basis for any change in contract price,
as hereinafter set forth for Extra Work, and any change in contract time which may
result from the change.
In the event the Contractor shall refuse to execute a Change Order which has been
prepared by the Engineer and executed by the Owner, The Engineer may in writing
instruct the Contractor to proceed with the work as set forth in the Change Order and the
Contractor may make claim against the Owner for Extra Work involved therein, as
hereinafter provided.
6.02 Minor Changes
amcwd.mw,p«
The Engineer may authorize minor changes in the work not inconsistent with the overall
intent of the Contract Documents and not involving an increase in Contract Price. If the
GC -24
Contractor believes that any minor change or alteration authorized by the Engineer
involves Extra Work and entitles him to an increase in the Contract Price, the Contractor
shall make written request to the Engineer for a written Field Order.
In such case, the Contractor by copy of his communication to the Engineer or otherwise
in writing shall advise the Owner of his request to the Engineer for a written Field Order
and that work involved may result in an increase in the Contract Price.
Any request by the Contractor for a change in Contract Price shall be made prior to
beginning the work covered by the proposed change.
6.03 Extra Work
sencand.aul/yea
It is agreed that the basis of compensation to the Contractor for work either added or
deleted by a Change Order or for which a claim for Extra Work is made shall be
determined by the unit prices upon which this contract was bid to the extent such work
can be fairly classified within the various work item descriptions and for work items that
cannot be so classified by one or more of the following methods:
Method (A)
By agreed unit prices; or
Method (B)
By agreed lump sum; or
Method (C)
If neither Method (A) nor Method (B) be agreed upon before the Extra
Work is commenced, then the Contractor shall be paid the "actual field
cost" of the work, plus fifteen (15) percent.
In the event said Extra Work be performed and paid for under Method (C), then the
provisions of this paragraph shall apply and the "actual field cost" is hereby defined to
include the cost to the Contractor of all workmen, such as foreman, timekeepers,
mechanics and laborers, and materials, supplies, trucks, rentals on machinery and
equipment, for the time actually employed or used on such Extra Work, plus actual
equipment, for the time actually employed or used on such Extra Work, plus actual
transportation charges necessarily incurred, together with all power, fuel, lubricants,
water and similar operating expenses, also all necessary incidental expenses incurred
directly on account of such Extra Work, including Social Security, Old Age Benefits and
other payroll taxes, and, a rateable proportion of premiums on Performance and Payment
Bonds and Maintenance Bonds, Public Liability and Property Damage and Workmen's
GC -25
Compensation, and all other insurance as may be required by any law or ordinance, or
directed by the Owner, or by them agreed to. The Engineer may direct the form in
which accounts of the "actual field cost" shall be kept and the records of these accounts
shall be made available to the Engineer. The Engineer or Owner may also specify in
writing, before the work commences, the method of doing the work and the type and
kind of machinery and equipment to be used; otherwise these matters shall be determined
by the Contractor. Unless otherwise agreed upon, the prices for the use of machinery
and equipment shall be determined by using 100 per cent, unless otherwise specified, of
the latest schedule of Equipment Ownership Expense adopted by the Associated General
Contractors of America. Where practicable the terms and prices for the use of
machinery and equipment shall be incorporated in the Written Extra Work Order. The
fifteen (15 %) percent of the "actual field cost" to be paid the Contractor shall cover and
compensate him for his profit, overhead, general superintendence and field office
expense, and all other elements of cost and expense not embraced within the "actual field
cost" as herein defined, save that where the Contractor's Camp or Field Office must be
maintained primarily on account of such Extra Work; then the cost to maintain and
operate the same shall be included in the "actual field cost."
No claim for Extra Work of any kind will be allowed unless ordered in writing by the
Engineer. In case any orders or instructions, either oral or written, appear to the
Contractor to involve Extra Work for which he should receive compensation or an
adjustment in the construction time, he shall make written request to the Engineer for
written order authorizing such Extra Work. Should a difference of opinion arise as to
what does or does not constitute Extra Work, or as to the payment therefor, and the
Engineer insists upon its performance, the Contractor shall proceed with the work after
making written request for written order and shall keep an accurate account of the "actual
field cost" thereof, as provided under Method (C). The Contractor will thereby preserve
the right to submit the matter of payment to arbitration, as hereinbelow provided.
6.04 Time of Filing Claims
geecmd.mWpee
It is further agreed by both parties hereto that all questions of dispute or adjustment
presented by the Contractor shall be in writing and filed with the Engineer within thirty
(30) days after the Engineer has given any directions, order or instruction to which the
Contractor desires to take exception. The Engineer shall reply within thirty (30) days
to such written exceptions by the Contractor and render his final decision in writing. In
case the Contractor should appeal from the Engineer's decision, any demand for
arbitration shall be filed with the Engineer and the Owner in writing within ten (10) days
after the date of delivery to Contractor of the Engineer's final decision. It is further
agreed that final acceptance of the work by the Owner and the acceptance by the
Contractor of the final payment shall be a bar to any claims by either party, except
claims by Owner for defective work or enforcement of warranties and except as noted
otherwise in the contract documents.
GC -26
1
6.05 Continuing Performance
The Contractor shall continue performance of the contract during all disputes or
disagreements with the Owner. The production or delivery of goods, the furnishing of
services and the construction of projects or facilities shall not be delayed, prejudiced or
postponed pending resolution of any disputes or disagreements, except as the Owner may
otherwise agree in writing.
6.06 Arbitration
All questions of dispute under this Agreement shall be submitted to arbitration at the
' request of either party to the dispute. The parties may agree upon one arbiter, otherwise,
there shall be three, one named in writing by each party, and the third chosen by the two
arbiters so selected; or if the arbiters fail to select a third within ten (10) days, he shall
be chosen by a District Judge serving the County in which the major portion of the
project is located, unless otherwise specified. Should the party demanding arbitration fail
to name an arbiter within ten (10) days of the demand, his right to arbitrate shall lapse,
' and the decision of the Engineer shall be final and binding on him. Should the other
party fail to choose an arbiter within ten (10) days, the Engineer shall appoint such
arbiter. Should either party refuse or neglect to supply the arbiters with any papers or
' information demanded in writing, the arbiters are empowered by both parties to take ex
parte proceedings.
The arbiters shall act with promptness. The decision of any two shall be binding on both
parties to the contract. The decision of the arbiters upon any questions submitted to
arbitration under this contract shall be a condition precedent to any right of legal action.
The decision of the arbiter or arbiters may be filed in court to carry it into effect.
The arbiters, if they deem the case demands it, are authorized to award the party whose
contention is sustained, such sums as they deem proper for the time, expense and trouble
incident to the appeal, and if the appeal was taken without reasonable cause, they may
' award damages for any delay occasioned thereby. The arbiters shall fix their own
compensation unless otherwise provided by agreement, and shall assess the cost and
charges of the arbitration upon either or both parties. The award of the arbiters must be
made in writing.
1 7. Abandonment of Contract
7.01 Abandonment by Contractor
In case the Contractor should abandon and fail or refuse to resume work within ten (10)
days after written notification from the Owner, or the Engineer, or if the Contractor fails
' eeac m.u. GC -27
acxood.m t/ px
to comply with the orders of the Engineer, when such orders are consistent with the
Contract Documents, then, and in that case, where performance and payment bonds
exist, the Sureties on these bonds shall be notified in writing and directed to complete
the work, and a copy of said notice shall be delivered to the Contractor.
After receiving said notice of abandonment the Contractor shall not remove from the
work any machinery, equipment, tools, materials or supplies then on the job, but the
same, together with any materials and equipment under contract for the work, may be
held for use on the work by the Owner or the Surety on the performance bond, or
another contractor in completion of the work; and the Contractor shall not receive any
rental or credit therefor (except when used in connection with Extra Work, where credit
shall be allowed as provided for under Section 6, Extra Work and Claims), it being
understood that the use of such equipment and materials will ultimately reduce the cost
to complete the work and be reflected in the final settlement.
Where there is no performance bond provided or in case the Surety should fail to
commence compliance with the notice for completion hereinbefore provided for, within
ten (10) days after service of such notice, then the Owner may provide for completion
of the work in either of the following elective manners:
(1) The Owner may thereupon employ such force of men and use such
machinery, equipment, tools, materials and supplies as said Owner may
deem necessary to complete the work and charge the expense of such
labor, machinery, equipment, tools, materials and supplies to said
Contractor, and expense so charged shall be deducted and paid by the
Owner out of such moneys as may be due, or that may thereafter at any
time become due to the Contractor under and by virtue of this Agreement.
In case such expense is less than the sum which would have been payable
under this contract, if the same had been completed by the Contractor,
then said Contractor shall receive the difference. In case such expense is
greater than the sum which would have been payable under this contract,
if the same had been completed by said Contractor, then the Contractor
and/or his Surety shall pay the amount of such excess to the Owner, or
(2) The Owner under competitive bids, taken after notice published as
required by law, may let the contract for the completion of the work under
substantially the same terms and conditions which are provided in this
contract. In case there is any increase in cost to the Owner under the new
contract as compared to what would have been the cost under this
contract, such increase shall be charged to the Contractor and the Surety
shall be and remain bound therefor. However, should the cost to
complete any such contract prove to be less than would have been the cost
to complete under this contract, the Contractor and /or his Surety shall be
credited therewith.
GC -28
When the work shall have been substantially completed the Contractor and his Surety
shall be so notified and Certificates of Completion and Acceptance, as provided in
Paragraph 5.06 hereinabove, shall be issued. A complete itemized statement of the
contract accounts, certified to by the Engineer as being correct, shall then be prepared
and delivered to the Contractor and his Surety, whereupon the Contractor and/or his
Surety, or the Owner as the case may be, shall pay the balance due as reflected by said
statement, within fifteen (15) days after the date of such Certificate of Completion.
In the event the statement of accounts shows that the cost to complete the work is less
than that which would have been the cost to the Owner had the work been completed by
the Contractor under the terms of this contract; or when the Contractor and /or his Surety
shall pay the balance shown to be due by them to the owner, then all machinery,
equipment, tools, materials or supplies left on the site of the work shall be turned over
to the Contractor and/or his Surety. Should the cost to complete the work exceed the
contract price, and the Contractor and/or his Surety fail to pay the amount due the Owner
within the time designated hereinabove, and there remains any machinery, equipment,
tools, materials or supplies on the site of the work, notice thereof, together with an
itemized list of such equipment and materials, shall be mailed to the Contractor and his
Surety at the respective addresses designated in this contract, provided, however, that
actual written notice given in any manner will satisfy this condition. After mailing, or
other giving of such notice, such property shall be held at the risk of the Contractor and
his Surety subject only to the duty of the Owner to exercise ordinary care to protect such
property. After fifteen (15) days from the date of said notice the Owner may sell such
machinery, equipment, tools, materials or supplies and apply the net sum derived from
such sale to the credit of the Contractor and his Surety. Such sale may be made at either
public or private sale, with or without notice, as the Owner may elect. The Owner shall
release any machinery, equipment, tools, materials, or supplies, which remain on the
work, and belong to persons other than the Contractor or his Surety, to their proper
owners. The books on all operations provided herein shall be opened to the Contractor
and his Surety.
7.02 Abandonment by Owner
gmccod.msthca
In case the Owner shall fail to comply with the terms of this contract, and should fail to
comply with said terms within ten (10) days after written notification by the Contractor,
then the Contractor may suspend or wholly abandon the work, and may remove
therefrom all machinery, tools and equipment, and all materials on the site of work that
have not been included in payments to the Contractor and have not been wrought into the
work. And thereupon the Engineer shall make an estimate of the total amount earned
by the Contractor, which estimate shall include the value of all work actually completed
by said Contractor (at the prices stated in the attached proposal where unit prices are
used), the value of all partially completed work at a fair and equitable price, and the
amount of all Extra Work performed at the prices agreed upon, or provided for by the
terms of this contract, and a reasonable sum to cover the cost of any provisions made by
GC -29
the Contractor to carry the whole work to completion and which cannot be utilized. The
Engineer shall then make a final statement of the balance due the Contractor by deducting
from the above estimate all previous payments by the Owner and all other sums that may
be retained by the Owner under the terms of this Agreement and shall certify same to the
Owner who shall pay to the Contractor on or before thirty (30) days after the date of the
notification by the Contractor the balance shown by said final statement as due the
Contractor, under the terms of this Agreement.
8. Subcontractors
8.01 Award of Subcontracts for Portions of the Work
pevcood.ouUrycc
Unless otherwise specified in the Contract Documents or in the Instructions to Bidders,
the Contractor, as soon as practicable after the award of the Contract, shall furnish to the
Engineer in writing for acceptance by the Owner and the Engineer a list of the names of
the Subcontractors proposed for the principal portions of the work. The Engineer shall
promptly notify the Contractor in writing if either the Owner or the Engineer, after due
investigation, has reasonable objection to any Subcontractor on such list and does not
accept him. Failure of the Owner or Engineer to make objection promptly to any
Subcontractor on the list shall constitute acceptance of such Subcontractor.
The Contractor shall not contract with any Subcontractor or any person or organization
(including those who are to furnish materials or equipment fabricated to a special design)
proposed for portions of the work designated in the Contract Documents or in the
Instructions to Bidders or, if none is so designated, with any Subcontractor proposed for
the principal portions of the work who has been rejected by the Owner and the Engineer.
The Contractor will not be required to contract with any Subcontractor or person or
organization against whom he has a reasonable objection.
If the Owner or Engineer refuses to accept any Subcontractor or person or organization
on a list submitted by the Contractor in response to the requirements of the Contract
Documents or the Instructions to Bidders, the Contractor shall submit an acceptable
substitute and the Contract amount shall be increased or decreased by the difference in
cost occasioned by such substitution and an appropriate change order shall be issued;
however, no increase in the Contract amount shall be allowed for any such substitution
unless the Contractor has acted promptly and responsively in submitting for acceptance
any list or lists of names as required by the Contract Documents or the Instructions to
Bidders.
If the Owner or the Engineer requires a change of any proposed Subcontractor or person
or organization previously accepted by them, the Contract amount shall be increased or
decreased by the difference in cost occasioned by such change and an appropriate Change
Order shall be issued.
GC -30
The Contractor shall not make any substitution for any Subcontractor or person or
organization who has been accepted by the Owner and the Engineer, unless the
substitution is acceptable to the Owner and the Engineer.
8.02 Subcontractual Relations
All work performed for the Contractor by a Subcontractor shall be pursuant to an
appropriate written agreement between the Contractor and the Subcontractor (and where
appropriate between Subcontractors and Sub - subcontractors) which shall contain
provisions that:
(1) preserve and protect the rights of the Owner and Engineer under the
Contract with respect to the work to be performed under the subcontract
so that the subcontracting thereof will not prejudice such rights;
(2) require that such work be performed in accordance with the requirements
of the Contract Documents;
(3) require submission to the Contractor of the applications for payment under
each subcontract to which the Contractor is a party, in reasonable time to
enable the Contractor to apply for payment in accordance with this
contract;
(4) require that all claims for additional costs, extensions of time, damages
for delays or otherwise with respect to subcontracted portions of the work
shall be submitted to the Contractor (via any Subcontractor or Sub -
subcontractor where appropriate) in sufficient time so that the Contractor
may comply in the manner provided in the Contract Documents for like
claims by the Contractor upon the Owner;
(5) obligate each subcontractor specifically to consent to the provisions of this
section.
A copy of all such Subcontract Agreements shall be filed by the Contractor with the
Engineer before the Subcontractor shall be allowed to commence work.
8.03 Payments to Subcontractors
The Contractor shall pay each Subcontractor, upon receipt of payment from the Owner,
an amount directly based upon the value of the work performed and allowed to the
Contractor on account of such Subcontractor's work, less the percentage retained from
payments to the Contractor. The Contractor shall also require each Subcontractor to
make similar payments to his subcontractors.
If the Engineer fails to approve a payment for any cause which is the fault of the
Contractor and not the fault of a particular Subcontractor, the Contractor shall pay the
Subcontractor on demand, made at any time after the Certificate for Payment should
otherwise have been issued, for his work to the extent completed, less the retained
GC -31
percentage.
The Engineer may, on request and at his discretion, furnish to any Subcontractor, if
practicable, information regarding percentages of completion certified to the Contractor
on account of work done by such Subcontractors.
Neither the Owner nor the Engineer shall have any obligation to pay or to see to the
payment of any moneys to such Subcontractor except as may otherwise be required.
9. Separate Contracts
9.01 Owner's Right to Award Separate Contracts
The Owner reserves the right to award other contracts in connection with other portions
of the project under these or similar conditions of the Contract.
When separate contracts are awarded for different portions of the Project, "The
Contractor" in the contract documents in each case shall be the contractor who signs each
separate contract.
9.02 Mutual Responsibility of Contractors
Qencmd.mst/yx
The Contractor shall afford other contractors reasonable opportunity for the introduction
and storage of their materials and equipment and the execution of their work, and shall
properly connect and coordinate his work with theirs.
If any part of the Contractor's work depends for proper execution or results upon the
work of any other separate contractor, the Contractor shall inspect and promptly report
to the Engineer any apparent discrepancies or defects in such work that render it
unsuitable for such proper execution and results. Failure of the Contractor to so inspect
and report shall constitute an acceptance of the other contractor's work as fit and proper
to receive his Work, except as to defects which may develop in the other separate
contractor's work after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property of any separate contractor
on the project, the Contractor shall, upon due notice, settle with such other contractor
by agreement or arbitration, if he will so settle. If such separate contractor sues the
Owner or initiates an arbitration proceeding on account of any damage alleged to have
been so sustained, the Owner shall notify the Contractor who shall defend such
proceedings at the Contractor's expense, and if any judgment or award against the Owner
arises therefrom the Contractor shall pay or satisfy it and shall reimburse the Owner for
all attorney's fees and court or arbitration costs which the Owner has incurred.
GC -32
9.03 Cutting and Patching under Separate Contracts
The Contractor shall be responsible for any cutting, fitting and patching that may be
required to complete his work except as otherwise specifically provided in the Contract
Documents. The Contractor shall not endanger any work of any other contractors by
cutting, excavating or otherwise altering any work and shall not cut or alter the work of
any other contractor except with the written consent of the Engineer.
Any costs caused by defective or ill-timed work shall be borne by the party responsible
therefor.
10. Protection of Persons and Property
10.01 Safety Precautions and Programs
The Contractor shall be responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the work.
10.02 Safety of Persons and Property
The Contractor shall take all reasonable precautions for the safety of, and shall provide
all reasonable protection to prevent damage, injury, or loss to:
erncood.msvgec
(1) all employees on the work and all other persons who may be affected
thereby:
(2) all the work and all materials and equipment to be incorporated therein,
whether in storage or off the site, under the care, custody or control of the
Contractor or any of his Subcontractors or Sub - Subcontractors; and
(3) other property at the site or adjacent thereto, including trees, shrubs,
lawns, walks, pavements, fences, roadways, structures and utilities not
designated for removal, relocation or replacement in the course of
construction.
The Contractor shall comply with all applicable laws, ordinances, rules, regulations and
lawful orders of any public authority having jurisdiction for the safety of persons or
property or to protect them from damage, injury or loss. He shall erect and maintain,
as required by existing conditions and progress of the work, all reasonable safeguards for
safety and protection, including posting danger signs and other warnings against hazards,
promulgating safety regulations and notifying owners and users of adjacent utilities.
When the use or storage of explosives or other hazardous materials or equipment is
necessary for the execution of the work, the Contractor shall exercise the utmost care and
shall carry on such activities under the supervision of properly qualified personnel.
GC -33
`eacoad.mNgx
All Blasting, including methods of storing and handling explosives and highly
inflammable materials, shall conform to Federal, State, Local Laws and Ordinances. All
City Ordinances shall be complied with even though some or all of the blasting is done
outside the City Limits unless the applicable Ordinance is in conflict with the law of the
jurisdiction where the action is being taken.
The following is a list of requirements in addition to Federal, State, and Local Laws and
Ordinances.
1. The Contractor shall furnish the City of Round Rock with a Certificate of
Blasting Insurance in the amount of $300,000.00 for each contract, at least
twenty-four hours prior to using explosives. A blasting permit must be
obtained from the City at least five (5) days prior to use of explosives.
If Blasting is covered under the Contractors General Insurance Certificate
for each contract, a separate blasting certificate will not be required.
2. The following public utility companies and City Department will be
notified by the Contractor, on every occasion, at least twenty-four (24)
hours prior to the use of explosives: Water and Wastewater, Electric, Gas,
Telephone and the City Engineering Department.
3. Explosive materials to be used shall be limited to blasting agents and
dynamite, unless prior approval of other materials is obtained in writing
from the Engineering Department.
4. During blasting, all reasonable precautions shall be taken to protect
pedestrians, passing vehicles, and public or private property. Blasting
mats or protective cover shall be used when required by the City
Inspector, the permit, or by safe blasting practices.
5. All explosives shall be stored in accordance with Chapter 5, Section
5.200, of the City Code.
6. The Director of Engineering or his representative shall have the right to
limit the use of explosives and/or blasting methods which in his opinion
are dangerous to the public or nearby property of any kind.
7. The Contractor, at his expense, shall promptly repair or replace all items
known to be damaged as a result of blasting. All claims of damage shall
be investigated by the City or by Consulting Firms approved by the City.
8. The Contractor shall maintain accurate records throughout the Blasting
operations showing the type explosive used, number of holes, pounds per
hole, depth of hole, total pounds per shot, delays used, date and time of
GC -34
P.ond mstiMa
blast and initials of the Inspector. The Contractor is fully responsible for
all claims resulting from his blasting operation.
All damage or loss to any property referred to in this article caused in whole or in part
by the Contractor, any Subcontractor, any Sub - subcontractor, or anyone directly or
indirectly employed by any of them, or by anyone for whose acts any of them may be
liable, shall be remedied by the Contractor, except damage or loss attributable solely to
faulty Drawings or Specifications or solely to the acts or omissions of the Owner or
Engineer or anyone employed by either of them, and not attributable in any degree to the
fault or negligence of the Contractor.
The contractor shall designate a responsible member of his organization at the site whose
duty shall be the prevention of accidents. This person shall be the Contractor's
superintendent unless otherwise designated in writing by the Contractor to the Owner and
the Engineer.
10.03 Location and Protection of Utilities
Notwithstanding any other provision of this contract, the Contractor shall be solely
responsible for the location and protection of any and all public utility lines and utility
customer service lines in the work area. The Contractor shall exercise due care to locate
and to mark, uncover or otherwise protect all such lines in the construction zone and any
of the Contractor's work or storage areas. Upon request, the Owner shall provide such
information as it has about the location and grade of water, sewer, gas, and telephone
and electric lines and other utilities in the work area but such information shall not
relieve or be deemed to be in satisfaction of the Contractor's obligation hereunder, which
shall be primary and nondelegable. Any such lines damaged by the Contractor's
operations shall be immediately repaired by the Contractor or he shall cause such damage
to be repaired at his expense.
GC -35
5.0 SPECIAL CONDITIONS
SECTION 01- INFORMATION
01 - 01 ENGINEER
The word "Engineer" in these Specifications shall be understood as
referring to Bury & Pittman, Inc., 3345 Bee Caves Road, Suite 200,
Austin, Texas 78746, Engineer of the Owner, or the Engineer's authorized
representative to act in any particular position for the Owner.
01 -02 COPIES OF PLANS AND SPECIFICATIONS FURNISHED
01 -05 LOCATION
The Agreement will be prepared in not less than five (5) counterpart
(original signed) sets. Owner will furnish Contractor two (2) sets of
conforming Contract Documents and Specifications and four (4) sets of
Plans free of charge, and additional sets will be obtained from the
Engineer at commercial reproduction rates plus 20% for handling.
01 - 03 GOVERNING CODES
All construction as provided for under these Plans and Specifications shall
be governed by any existing Resolutions, Codes and Ordinances, and any
subsequent amendments or revisions thereto as set forth by the Owner.
01-04 LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE ON
TIME
The Contractor agrees that time is of the essence for this Contract and that
the definite value of damages which would result from delay would be
incapable of ascertainment and uncertain, so that for each day of delay
beyond the number days of herein agreed upon for the completion of the
work herein specified and contracted for, after due allowance for such
extension of time as is provided for under the provisions of Section 4.02
of the General Conditions, the Owner may withhold permanently from the
Contractor's total compensation, not as penalty but as liquidated damages,
the sum of $100.00 per calendar day.
The location of work shall be as mentioned in the Notice to Bidders and as
indicated on Plans.
specond.mst/spec SC -1
1
01-06 USAGE OF WATER
All water used during construction shall be provided by the City. The City
shall specify the location from which the Contractor is to procure water.
The Contractor shall be responsible for providing all apparatus necessary
1 for procuring, storing, transporting and using water during construction.
The Contractor shall strive to use that amount of water which is reasonable
to perform the work associated with this contract and shall endeavor to
avoid excessive waste. The Contractor will be required to pay for all water
used if it is found that unnecessary or excessive waste is occurring during
construction.
01-07 PAY ESTIMATES
1 If pay estimates from the Contractor are not received by the Engineer on
or before the time specified in Section 5.04 of the General Conditions, then
1 the pay estimate will not be processed and will be returned to Contractor.
1
SECTION 02- SPECIAL CONSIDERATIONS
1 02 -01 CROSSING UTILITIES
1 Prior to commencing the work associated with this contract, it shall be the
Contractor's responsibility to make arrangements with the Owners of such
utility companies to uncover their particular utility lines or otherwise
' confirm their location. Certain utility companies perform such services at
their own expense, however, where such is not the case, the Contractor will
cause such work to be done at his own expense.
02 -02 UTILITY SERVICES FOR CONSTRUCTION
The Contractor will be responsible for providing his own utility services
while performing the work associated with this contract. No additional
1 payment will be made for this item.
02 -03 GUARANTEES
The Contractor warrants the materials and workmanship and that the work
1 is in conformance with the plans and specifications included in this contract
specond.mst/spec SC -2
1
for the period that the Maintenance Bond, as outlined in Section 04 of the
Special Conditions, is in effect. Upon notice from Owner, the Contractor
shall repair defects in all construction or materials which develop during
specified period and at no cost to Owner. Neither final acceptance,
Certificate of Completion, final payment nor any provision in Contract
Documents relieves Contractor of above guarantee. Notice of observed
defects will be given with reasonable promptness. Failure to repair or
replace defect upon notice entitles Owner to repair or replace same and
recover reasonable cost thereof from Contractor.
02 MINIMUM WAGE SCALE
Minimum wage scale as specified in section 3.22 of the General Conditions
and in accordance with State of Texas and Federal Government regulations.
02 - 05 LIMIT OF FINANCIAL RESOURCES
The Owner has a limited amount of financial resources committed to this
Project; therefore, it shall be understood by all bidders that the Owner may
be required to change and /or delete any items which he may feel is
necessary to accomplish all or part of the scope of work within its limit of
financial resources. Contractor shall be entitled to no claim for damages
anticipated profits on any portion of work that may be omitted. At any
time during the duration of this contract, the Owner reserves the right to
omit any work from this contract. Unit prices for all items previously
approved in this contract shall be used to delete or add work per change
order.
02 CONSTRUCTION REVIEW
The Owner shall provide a project representative to review the quality of
materials and workmanship.
02 - 07 LIMITS OF WORK AND PAYMENT
It shall be the obligation of the Contractor to complete all work included in
this Contract, so authorized by the Owner, as described in the contract
documents and technical specifications. All items of work not specifically
paid for in the bid proposal shall be included in the unit price bids. Any
question arising as to the limits of work shall be left up to the interpretation
specond.mst/spec SC -
of the Engineer.
02-08 PAYMENT FOR MATERIALS ON HAND
Owner will not pay for materials on hand. Payment will be made for work
completed in accordance with monthly estimate procedure stipulated in the
General Conditions of the Agreement.
02-09 "AS- BUILT" DRAWINGS
The Contractor shall mark all changes and revisions on all of his copies of
the working drawings during the course of the Project as they occur. Upon
completion of the Project and prior to final acceptance and payment, the
Contractor shall submit to the Engineer one set of his working drawings,
dated and signed by himself and his project superintendent and labeled as
"As- Built ", that shows all changes and revisions outlined above and that
shows field locations of all above ground appurtenances including but not
limited to valves, fire hydrants and manholes. These as -built drawings shall
become the property of the Owner. Each appurtenance shall be located by
at least two (2) horizontal distances measured from existing, easily
identifiable, immovable appurtenances such as fire hydrants or valves.
Property pins can be used for as- builts tie -ins provided no existing utilities
as previously described are available. Costs for delivering as -built drawings
shall be subsidiary to other bid items.
02 - 10 LAND FOR WORK
Owner provides, as indicated on Drawings, land upon which work is to
done, right -of -way for access to same and such other lands which are
designated for use of Contractor. Contractor provides, at his expense and
without liability of Owner, any additional land and access thereto that may
be required for his construction operations, temporary construction
facilities, or for storage of materials.
02 -11 DEVIATIONS OCCASIONED BY UTILITY STRUCTURES
specond.mst/spec
Whenever existing utilities, not indicated on Plans, present obstructions to
grade and alignment of proposed improvements immediately notify
engineer, who without delay, will determine if existing utilities are to be
relocated, or grade and alignment of proposed improvements changed.
Where necessary to move existing services,poles, guy wires, pipelines, etc.,
SC-4
as determined by the Engineer, the Contractor will make arrangements with
the owner of the utility to be moved and have it moved. The costs of any
utility relocations will be at the Contractor's sole expense. Owner will not
be liable for relocations costs or damages on account of delays due to
changes made by owners of privately owned utilities which hinder progress
of the work.
02 -12 CONSTRUCTION STAKING
All construction staking required to complete the work associated with this
contract shall be provided by the Contractor. The Contractor shall be
responsible for determining the layout and extent of staking necessary to
construct the improvements to the lines and grades shown in the Plans.
This item shall not be paid for separately and shall be considered subsidiary
to other bid items.
SECTION 03- TRAFFIC CONTROL
Access shall be.provided for residents and emergency vehicles at all times.
When it becomes necessary to restrict access, the Contractor shall notify all
applicable agencies (ie. Fire Department, E.M.S., Public Works, etc.). At
the end of each day two lanes of traffic shall be opened to the public. The
Contractor shall be responsible for all maintenance, signing and safety
precautions necessary for traffic control. This item shall be considered
subsidiary to other bid items and no additional compensation shall be given
for complying with this Special Condition.
SECTION 04-MAINTENANCE BOND
Per City of Round Rock Ordinances, a two (2) year Maintenance Bond
naming the City of Round Rock as obligee will be required for public
streets constructed without lime stabilization of subgrade material when the
Plasticity Index of the subgrade is above 24. Maintenance Bond shall
remain in effect for two (2) years from date of City of Round Rock
acceptance of improvements.
A one (1) year Maintenance Bond in the amount of one hundred (100%)
specoad.msuspec SC -5
SECTION 5 INSURANCE
specond.mst/spec
percent of the contract price will be required for all other improvements
and shall be submitted prior to final payment. Such bonds shall be from an
approved surety company holding a permit from the State of Texas to act
as surety (and acceptable according to the latest list of companies holding
certificates of authority from the Security of the Treasury of the United
States) or other surety or sureties acceptable to the Owner prior to final
payment.
Section 3.18 of the General Conditions of the Agreement is hereby amended
to include the following:
3.18 Insurance
Contractor shall carry insurance in the following types and amounts for the
duration of this Contract, which shall include items owned by Owner in
care, custody and control of Contractor prior and during construction and
warranty period, and furnish Certificates of Insurance along with copies of
policy declaration pages and all policy endorsements as evidence thereof:
a. Statutory Worker's Compensation and minimum $100,000
Employers Liability Insurance.
b. Commercial General Liability Insurance with minimum limits of
$500,000 per occurrence and $1,000,000 Aggregate or $500,000 for
this designated project and $100,000 Fire Damage.
c. Automobile Liability Insurance for all owned, nonowned and hired
vehicles with minimum limits for Bodily Injury of $250,000 for each
person and $500,000 for each occurrence and Property Damage
limits of $100,000 or Combined Single Limit of $600,000.
d. On all new or remodeling building projects: All Risk Builders Risk
Insurance for insurable building projects shall be insured in the
amount of the contract price for such improvements. Owner and
Contractor waive all rights against each other for damages caused by
fire or other perils to the extent covered by Builders Risk Insurance
required under this section, except as to such rights as they may
SC -6
specond.mst/spec
have in the proceeds of such insurance. Contractor shall require
similar waivers by Subcontractors and Sub - subcontractors.
e. Owner and Contractor's Protective Policy. The Contractor shall
provide and maintain during the life of this contract and until all
work under said contract has been completed and accepted by the
Owner, an Owner's and Contractor's Protective Policy which co-
insures the Owner and the Owner's agents and employees with the
same Commercial General Liability coverage as described above,
entitled "Commercial General Liability Insurance."
When offsite storage is permitted, policy will be endorsed for transit and
off site storage in amounts sufficient to protect property being transported
or stored.
This insurance shall include, as insured, City of Round Rock, Contractor,
Subcontractors and Sub - subcontractors in the work, as their respective
interest may appear.
If insurance policies are not written for amount specified in b. and c.
above, Contractor is required to carry an Excess Liability Insurance Policy
for any difference in amounts specified.
Contractor shall be responsible for deductibles and self insured retentions,
if any, stated in policies. Any self insured retention shall not exceed ten
percent of minimum required limits. All deductibles or self insured
retentions shall be disclosed on Certificate of Insurance required above.
Contractor shall not commence work at site under this Contract until he has
obtained required insurance and until such insurance has been reviewed by
Owner's Contract Administration Office. Contractor shall not allow any
Subcontractors to commence work until insurance required has been
obtained and approved. Approval of insurance by Owner shall not relieve
or decrease liability of Contractor hereunder.
Insurance to be written by a company licensed to do business in the State
of Texas at the time policy is issued and acceptable to owner.
SC -7
specond.msUspec
Contractor shall produce an endorsement to each effected policy:
1. Naming City of Round Rock, 221 East Main Street, Round Rock,
Texas 78664 as additional insured (except Workers' Compensation
and Builders Risk).
2. That obligates the insurance company to notify Joanne Land, City
Secretary, City of Round Rock, 221 East Main Street, Round Rock,
Texas 78664 of any and all changes to policy 30 days prior to
change.
3. That the "other" insurance clause shall not apply to Owner where
City of Round Rock is an additional insured shown on policy. It is
intended that policies required in this agreement, covering both
Owner and Contractor, shall be considered primary coverage as
applicable.
Contractor shall not cause any insurance to be canceled nor permit any
insurance to lapse during term of this Contract or as required in the
Contract.
If Contractor is underwritten on a claim -made basis, the retroactive date
shall be prior to, or coincident with, the date of this Contract and the
Certificate of Insurance shall state that coverage is claims made and also the
retroactive date. Contractor shall maintain coverage for duration of this
Contract and for two years following completion of this Contract.
Contractor shall provide the City annually a Certificate of Insurance as
evidence of such insurance. It is further agreed that Contractor shall
provide Owner a 30 day notice of aggregate erosion, an advance of the
retroactive date, cancellation and /or renewal.
It is also agreed that Contractor will invoke the tail option at request of
Owner and the Extended Reporting Period (ERP) premium shall be paid by
Contractor.
Owner reserves the right to review insurance requirements of this section
during effective period of the Contract and to make reasonable adjustments
to insurance coverages and their limits when deemed necessary and prudent
SC -8
by Owner based upon changes in statutory law, court decisions or the
claims history of the industry as well as Contractor.
Owner shall be entitled, upon request, and without expense, to receive
copies of policies and all endorsements thereto and may make any
reasonable requests for deletion or revision or modification of particular
policy terms, conditions, limitations or exclusions, except where policy
provisions are established by law or regulation binding upon either of the
parties hereto or the underwriter on any of such policies.
Actual losses not covered by insurance as required by the section shall be
paid by Contractor.
(continue with Special Conditions as necessary)
specond.mst/spec SC -
6.0 TECHNICAL SPECIFICATIONS
1
ITEM 1 GENERAL DESCRIPTION
1.01 SCOPE OF WORK
The work covered by these Specifications consists of furnishing all labor,
equipment, appliances, materials and performing all operations in
connection with the installation of water and wastewater system
improvements complete in accordance with the Plans, and subject to the
terms and conditions of the Contract Documents.
1.02 GOVERNING TECHNICAL SPECIFICATIONS
NOTE: The item number designation shown in parentheses adjacent to
captions herein is a reference to City of Austin Standard Specifications.
STREET. WATER, SEWER AND DRAINAGE IMPROVEMENTS
The current City of Austin Standard Specifications as adopted and amended
' by the City of Round Rock and the current City of Austin Erosion and
Sedimentation Control Manual are hereby referred to and included in this
contract as fully and to the same extent as if copied at length herein and
1 they shall be applied to this project except as modified in these
Specifications and on the Plans. Note that copies of the Austin
Specifications governing the major items of work are attached at the end of
1 this section for ease of reference.
Wherever the term "City of Austin" is used in the Austin Specifications, it
shall be construed to mean the City of Round Rock.
Wherever the term "Engineer" is used in the Austin Specifications, it shall
be construed to mean Bury & Pittman, Inc, 3345 Bee Caves Road, Suite
' 200, Austin, Texas 78746.
IE I1 2 CONTROL OF WORK
2.01 CLEAN -UP
' 2.01.1 CONSTRUCTION SITE
During construction the Contractor shall coordinate all activities with
Russell Garner of White Construction Company currently providing
construction activities on the site area.
techspec.scp /dh TS -1
2.01.2 BACKWORK
2.02 GRADING
The contractor shall keep the site free and clean from his own rubbish and
debris originating from construction activity and shall clean-up the site
promptly when notified to do so by the Engineer.
The Contractor shall, at his own expense, maintain the streets and roads
free from dust, mud, excess earth or debris originating from construction
activities which constitutes a nuisance or danger to the public using the
thoroughfare, or the occupants of adjacent properties.
Care shall be taken to prevent spillage on streets and roads over which
hauling is done, and any such spillage or debris deposited on streets, due
to the Contractor's operations, shall be immediately removed.
The Contractor shall coordinate his operations in such a manner as to
prevent the amount of clean -up and completion of back works from
becoming excessive. Should such a condition exist, the Engineer may order
all or portions of the work to cease and refuse to allow any work to
commence until the back work is done to the Engineer's satisfaction.
The Contractor shall do such grading in and adjacent to the construction
area associated with this contract as may be necessary to leave such areas
in a neat and satisfactory condition approved by the Engineer.
ITEM 3 EXAMINATION AND REVIEW
3.01 EXAMINATION OF WORK
The work covered under this Contract shall be examined and reviewed by
the Engineer, representatives of all governmental entities which have
jurisdiction, and the Owner's authorized representative. The quality of
material and the quality of installation of the improvements shall be to the
satisfaction of the Engineer. It shall be the Contractor's responsibility for
the construction methods and safety precautions in the undertaking of this
Contract.
techspec.scp /dh TS -
1
3.02 NOTIFICATION
The Engineer and Owner must be notified a minimum of 24- hours in
advance of beginning construction, testing, or requiring presence of the
Engineer, project representative, or Owner's representative.
3.03 CONSTRUCTION STAKING
The Engineer shall furnish the Contractor reference points and benchmarks
for construction as necessary.
' 3.04 PROTECTION OF STAKES. MARKS. ETC.
' All engineering and surveyor's stakes, marks, property corners, etc., shall
be carefully preserved by the Contractor, and in case of destruction or
removal during the course of this project, such stakes, marks, property
' corners, etc., shall be replaced by the Contractor at the Contractor's sole
expense.
1
ITEM 4 PROTECTION AND PRECAUTION
4.01 WORK IN FREEZING WEATHER
Portions of the work may continue as directed by the Engineer.
1 4.02 PROTECTION OF TREES. PLANTS AND SHRUBS
1 The Contractor shall take necessary precautions to preserve all existing
trees, plants and shrubs but where it is justifiable and necessary the
' Contractor may remove trees and plants for construction right -of -way but
only with approval of the Engineer.
1
1
1
1
techspec.scp/dh TS -
4.03 TRAFFIC CONTROL MEASURES AND BARRICADES
Traffic control measures and barricades shall be installed in accordance with
the Texas Manual of Uniform Traffic Control Devices and in other
locations deemed necessary by the Engineer, for the protection life and
property. Under no circumstances will any existing road be permitted to
remain closed over a weekend. No separate pay will be made for this item.
Costs for this item shall be subsidiary to other items of work.
4.04 PROPERTY LINES AND MONUMENTS
The Contractor shall be responsible for the protection, reference and
resetting of property corner monuments if disturbed.
4.05 DISPOSAL OF SURPLUS MATERIAL
The Contractor shall at his own expense, make arrangement for the disposal
of surplus material, such as rock, trees, brush and other unwanted backfill
materials.
4.06 CONTRACTOR'S USE OF PREMISES
The Contractor shall, at his own expense, provide additional space as
necessary for his operations and storage of materials.
The contractor shall coordinate use of the premises with White Construction
Company. The contractor shall not interfere with construction activities
being undertaken by White Construction Company or any of their
subcontractors.
ITEM 5 MATERIALS
5.01 TRADE NAMES
Except as specified otherwise, wherever in the specifications an article or
class of material is designated by a trade name or by the name or catalog
number of any maker, patentee, manufacturer, or dealer, such designations
shall be taken as intending to mean and specify the articles described or
another equal thereto in quality, finish, and serviceability for the purpose
intended, as may be determined and judged by the Engineer in his sole
discretion.
techspec.scp /dh TS-4
5.02 MATERIALS AND WORKMANSHIP
No material which has been used by the Contractor for any temporary
purpose whatever is to be incorporated in the permanent structure without
the written consent of the Engineer. Where materials or equipment are
specified by a trade or brand name, it is not the intention of the owner to
discriminate against an equal product of another manufacturer, but rather
to set a definite standard of quality for performance, and to establish an
equal basis for the evaluation of bids. Where the words "equivalent ",
"proper" or "equal to" are used, they shall be understood to mean that the
item referred to shall be "proper ", the "equivalent" of, or "equal to" some
other item, in the opinion or judgement of the Engineer. Unless otherwise
specified, all materials shall be the best of their respective kinds and shall
be in all cases fully equal to approved samples. Notwithstanding that the
words "or equal to" or other such expressions may be used in the
specifications in connection with a material, manufactured article or
process, the material, article or process specifically designated shall be
used, unless a substitute is approved in writing by the Engineer, and the
Engineer will have the right to require the use of such specifically
designated material, article or process.
ITEM 6 GRADING. RESTORATION. REVEGETATION. AND EROSION
CONTROL MEASURES (series 600)
This item shall govern the furnishing, placing, maintaining and removal of
all erosion control measures, site work, restoration work, grading, shaping,
seeding and sodding for all disturbed areas and in accordance with the
plans.
EROSION CONTROL
Temporary erosion control measures shall include but not be limited to: Silt
Fences, Rock Berms, Land Grading and Storm Inlet Sediment Traps.
The Contractor is alerted to the fact that his construction operations may
cause undue sedimentation at various locations and erosion of the land in
and around the construction area. Such areas of erosion and sedimentation
are difficult to predict and are best determined in the field as construction
progresses. The Contractor should be aware that such areas of erosion and
techspec.scp /dh TS -
sedimentation generally include but are not limited to: drainage outlets,
steep slopes and in areas where vegetation has been removed. The
Contractor should be prepared to take remedial measures and to install
erosion and sedimentation control devices as necessary to correct all adverse
erosion and sedimentation.
The extent and location of erosion control measures shall be as determined
in the field by the Engineer or his designated representative. The
Contractor shall be responsible for providing all materials, labor and
equipment necessary for the construction of erosion control measures. The
Contractor shall maintain all erosion control measures until final acceptance
and shall remove them after final acceptance of the project.
This item will not be measured and paid for separately. Costs for this item
shall be subsidiary to other items of work.
RESTORATION AND REVEGETATION
Unless otherwise directed by the Engineer:
All unpaved areas disturbed during construction shall be graded and shaped
to conform to the topography existing prior to construction. Said areas
shall then be restored by providing topsoil and vegetation or by providing
surface material that existed prior to construction (ie. peagravel, flexible
base, etc.). The type of vegetation or surface material provided shall equal
or exceed the type of vegetation or surface material which existed prior to
construction unless otherwise requested by the property owner. This item
shall be measured and paid for as one lump sum.
EXISTING SHRUBS AND TREES
It is the intent of the Owner to preserve as many existing trees and shrubs
within the construction area as possible. The Contractor shall not remove,
trim or otherwise disturb existing trees and shrubs unless otherwise directed
by the Engineer. The Contractor, at his sole expense and without
compensation from the Owner, shall be responsible for replacing all trees
and shrubs damaged where in the opinion of the Engineer, such damage
was avoidable.
techspec.scp /dh TS -
When directed by the Engineer, the Contractor shall carefully excavate
existing shrubs that conflict with proposed construction and properly re-
plant said shrubs within the right -of -way in a location determined by the
Engineer after he has conferred with the respective property owner. The
Contractor will not be responsible for guaranteeing the success of the re-
planted shrubs provided he has exercised proper care and followed
appropriate re- planting procedures. No separate pay will be made for this
item.
Costs for this item shall be subsidiary to other items of work. All shrubs
unduly damaged during excavation or re- planting shall be replaced at the
Contractor's sole expense without compensation from the Owner.
ITEM 7 CONSTRUCTION AND TRAFFIC CONTROL WITHIN HIGHWAY
RIGHT -OF -WAY
All construction performed, all traffic controls and all warning signs within
any right -of -way of the State of Texas shall be in accordance with any
rules, regulations and policies of the State Department of Highways and
Public Transportation.
techspec.scp /dh TS -
X6.1 Description
This item shall govern constriction of manholes complete in place and the materials used
therein, including excavation, installation, backfilling and surface restoration. It shall
also include furnishing and installing rings, covers, appurtenances and any pumpiRg, and
drainage necessary to complete the wont. Wastewater manholes shall be acceptance tested by the
Contractor. Rater and Wastewater Standard Products Lists form a part of the Specifications.
Should the Contractor elect to use any materials from these lists, they should be completely
and clearly identified when submitted.
506.2 Materials and Caponents
(1) Concrete and Cement Stabilized Sand: All concrete shall conform to nom N0. 403
CiNCREIE FOR SERLCTURE4. Cast in place concrete shall be Class A, and precast
concrete shall be Class I All interior surfaces of wastewater manholes shall have
an approved mating or be otherwise acceptably protected from the acidic effects of
municipal wastewater. Concrete for backfill of averexcavated arms shall. be Class
A or Class J as indicated. Cement stabilized sand for bedding or backfilling,
where indicated or required, shall contain 2 be of Portland Cement per cubic
yard; sand shall be as defined for "Fine Aggregate" in Uf21 403 CONCRETE FOR
S1i L ITEES.
(2) Mortar: Mortar shall be composed of one part Portland Cement, one part masonry
cement (or 1/4 part hydrated lime), and sand equal to 2 -1/2 to 3 times the sun of
the volumes of the cements and lime used. The sand shall meet the requirements for
"Fine Aggregate" as given in ITEM 403 CRETE FOR STR=ZTURES.
(3)
(4) Brick.: Brick for ring adjustment courses and for stormwater manholes shall be of
first quality, sand, hard burned, perfectly shaped brick conforming to the
requirements of ASTM C 62 Grade SW or concrete brick meeting the requirements of
ASTM C 55, Grade N-1.
(5)
506 08/17/92
(6) R.01d:eanis: Bulkheads shall meet the requirements of ITEM N0. 507 BULKHEADS.
Item 506
Manholes
Peinfor it: Reinforcing steel shall conform to the requirements of ITEM NO. 406
REINFOKING STEEL. Secodary, nal- structural steel may be replaced by approved
collated fibrillated polypropylene fibers in cast -in -place stormwater manholes.
Ringss and Comore, 24-In di Inside Diameter. Rings and covers shall conform to the
requirements of ITEM NO. 503 FRAMES, GRATES, RIGS AND COVERS.
(7) Precast Base Sections, Riser Sections, and Canes: Precast concrete base sections,
riser sections, and cones shall conform to the requi.renents of ASTM C 478. Joints
for wastewater base sections, riser sections, and cones shall conform to the
requirements of ASTM C 443. Additionally, joint dimensions for 48 -inch inside
diameter wastewater manhole sections and cones shall comply with STANDARD W.
506-12 0-RIND JOINT LETAIL or N0. 506-13 WEDGE SEAL JOINT DETAIL. Precast bases
for 48 inch inside diameter manholes shall have preformed inverts. Approved inserts
shall be embedded in the concrete all of the manhole sections to facilitate
handling; through holes for lifting will not be permitted.
(8) Precast Junction Booms: Precast junction boxes shall be allowed only where
indicated an the plans or approved by the Engineer. Joints for wastewater junction
boxes shall conform to the requirements of ASH 43.
Page 1 Manholes
(9) Pipe -to -Mari e/Junctim Box Assemblies- Precast basses and precast junction booms
shall have flexible, resilient and non-corrosive approved boot connectors or ring
waterstops conforming to the requirements of ASIM C 923 on all wastewater pipe
connections.
(10) Precast Flat-Slab Transition/Junction Box Lids: Precast slab transitions and lids
shall be designed to safely resist pressures resulting fran leads which might
result from any combination of forces imposed by an HS-20 Loading as defined by the
American Association of State Highway and Transportation Officials (AASHTO). The
joints of precast slab transitions and of lids for wastewater applications shall
conform to the requirements of ASIM 0443.
(11) Precast - Prefabricated Tea Manholes: Tee manholes shall be allowed only where
indicated on the plans or approved by the Engineer. The Hain pipe section shall_
conform to the requirements of TIFS1 NO. 510 PIPE. The vertical manhole portion
(tee) above the main pipe shall conform to the requires nts of the precast
coapanents•
The manhole tee shall have a minimm inside diameter of 48 inches and shall rise
vertically centered or tangent to the Hain pipe, as indicated or approved. An
access hole less than 48- inches in diameter shall be cut into the main pipe to
all a ledge for support of access ladders. Unless otherwise specified, the main
pipe portion of the tee manhole shall be paid subsidiary to the emit tee manhole
price.
(12) Precast Grade Rings, 24-1/2 Inch Inside Illieter: Rings shall be reinforced !'lace
A or I concrete 6 inches wide with a thidaness of 3 to 6 inches.
(13) Waterproofing Joint Materials: 0 -rings and wedge seals for the joints of all
wastewater manholes, and for stormrater manholes when indicated, shall conform to
the requirements of ASIM C443. Cold applied pteforned plastic gaskets for
stomnwater manholes shall be as specified in ITEM U. 510 PIPE. Connections
between reinforcer) concrete wastewater manhole structures and pipes shall meet the
requirements of ASIM C923.
506.3 Construction
All manholes shall have a mint= inside diameter of 48 inches. Manhole base dimensions
shall be appropriately increased to accommodate all converging pipe. A miniamn
horizontal clearance of 12 inches shall be maintained between pipe walls at the
sprirglines of adjacent pipes. Pipe ends within the manhole base walls shall not be
relied upon to support overlying manhole dead and live load weights. All wastewater
branch connections to new or existing mains shall be made at manholes with the influent
pipe crown installed at the effluent pipe crown elevation. Where the springline of an
influent pipe is 24 inches or more above the springline of the effluent pipe, a drop
manhole shall be used. Construction of extensions to existing systems shall require
p1acerent of bulkheads at locations indicated or directed by the Engineer. Unless
otherwise indicated, stoomwater manholes shall have eccentric cones; wastewater
manholes shall have concentric cores, except on manholes over large rains where an
eccentric cone shall be situated to provide access to an invert ledge. Eccentric cones
may be used where conflicts with other utilities dictate. Flat -slab tops may be used
where clearance problems exist; see 506.2(10) above.
Manholes shall be founded at the established elevations on uniformly stable subgrade.
Unstable subgrade shall be over-excavated a minimm of 12 inches and replaced with an
506 08/17/92
Page 2 Manholes
approved material. Precast base units shall be founded and leveled on a 6 inch coarse
aggregate bedding. A pipe section with a prefabricated tee manhole and half the length
of the adjoining pipe sections on each side shall be founded on a minimum of 6 inch
unueinforced Class A concrete. The cast -in -place concrete cradle shall be poured
against undisturbed trench walls up to the pipe's springline.
Cast -in -place foundations shall have a minimum depth of 12 inches at the invert
flowline. The lowermost riser section may be set in the concrete while still green,
after which the foundation shall be cured a minimum of 24 hours prior to proceeding with
construction of the manhole up to 12 feet in depth. The foundation shall be cured an
additional 24 hours prior to continuing construction above the 12 foot level. Manhole
depth shall be measured from the invert flowline to the finish surface elevation.
Wastewater pipes, except polyvinyl chloride ( PVC), may be laid through the manholes and
the top half of the pipes removed to facilitate invert construction. The manhole bottom
shall rise from the springl.ine elevation of the pipe, approximately one inch for each 12
inches of rum (8X). Wastewater manholes with lines larger than 18 inches shall require
precast bases; manholes constructed over in- service maims however, may be built on
cast -in -place foundations if the flow cannot be interrupted. Precast and cast -in -place
wastewater ju=nction boxes shall be allowed only where indicated on the plans or approved
by the Engineer. The floors of stonawater manholes also, shall rise outwardly from the
springline on a slope of 1:12 (8X).
Wastewater lines, except reinforced concrete pipe, set in cast -in -place foundations,
shall require an approved waterstop seal or gasket around the outside perimeter of the
pipe. It shall be approximately centered under the manhole section wall.
Cast -in -place storseater manholes, junction boxes and flat -slab transitions shall be
reinforced, r1a¢s A concrete. All structural concrete work shall conform to 11FM N0.
410 =REM STRUCTURES. Formes will be required for all cast -in -place walls above the
foundation. Where the surrounding material can be trimmed to a smooth vertical face,
outside forms may be omitted.
All manholes with precast grade rings or brick adjustment courses may have a muds=
vertical rise of 24 inches (the maximum includes the depth of the ring casting). All
manholes not located in paved areas shall have bolted covers.
Backfilling for manholes shall conform to the density requirements of ITEM 510 PIPE.
Manhole construction in roadways may be staged to facilitate base construction.
Manholes constructed to interim elevations shall be covered with steel plates of
sufficient thickness to support vehicular traffic. Steel plates on wastewater manholes
shall be set in mortar to minimize inflow. Manholes shall be completed to finish
elevation prior to placement of the roadway's finish surface. The excavation for
completion of manhole construction shall be berkfilled with cement stabilized sand (2
sacks per cubic yard) up to the bottom of Portland Cement pavement slabs or to within
two (2) inches of finish elevation of asphaltic concrete pavements. The cement
stabilized sand shall be a minims of 12 inches thick.
506.4 Acceptancelesth4rof Wastewater Manholes:
Manholes shall be tested separately and independently of the wastewater lines.
(1) Test by the &fzlriatica Method
All backfilling and compaction are to be colleted prior to the commencement of testing.
506 08/17/92
Page 3 Manholes
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 506
(a) Procedures:
1. Manhole section interiors shall be carefully inspected; units found to have
through -mall lift holes, or and penetration of the interior surface by inserts
provided to facilitate handling, mill not be accepted.
2. After cleannirg the interior surface of the manhole, the Contractor shall place and
inflate pneumatic plugs in all of the connecting pipes to isolate the manhole;
sealing pressure within the plugs shall be as recommended by the plug naraufacturer.
3. Concrete manholes shall be filled with eater or otherwise thoroughly wetted for a
period of 24 hairs prior to testing.
4. At the start of the test, the manhole shall be filled to the top with water. The
test time shall be 1 hour (60 minutes). The Construction Inspector must be present
for observation during the entire time of the test. Permissible loss of water in
the 1 hour test time is 0.025 gallons per diameter foot, per foot of manhole depth.
For a 4 foot diameter manhole, this quantity converts to a madjun permissible drop
in the water level (from the top of a 24" diameter manhole cone) of 0.05 inches per
foot of manhole depth (0.5 inches for a 10 foot deep manhole).
(2) That by the Vaasa Method:
At the discretion of the Engineer, the Contractor may substitute the Vacuum Method of
testing for the Exfiltration test described in 506.4(1) above. The vacuum method may be
used by the contractor prior to beckfilling, but only for his convenience so that
defects may be located and repaired. Final acceptance testing shall be done after all
6eckfilling, and compaction are complete.
(a) Equipment:
1. Manhole vacua tester shall be by P.A. Glazier, Inc., Quern Industries, or other
approved manufacturer.
2. Pipe sealing plugs shall have a load resisting capacity equal to or greater than
that required for the size of the connected pipe to be sealed
(b) Procedures — applicable to new 4' -0" diameter manholes.
1. Manhole section interiors shall be carefully inspected; units found to have
through -wall lift holes, or any penetration of the interior surface by inserts
provided to facilitate handling, will not be accepted.
2. After cleaning the interior surfaces of the manhole, the Contractor shall place and
inflate pneumatic plugs in all of the connecting pipes to isolate the manhole;
sealing pressure within the plugs shall be as recommended by the plug manufacturer.
Plugs -and the ends of pipes connected by flemdble boots —shall be blocked to
prevent their movement during the vacuum test.
3. The vacuum test head shall be placed at the inside of the top of the manhole cone
section, and the compression seal band inflated to the pressure recamended by its
manufacturer. The vacuum pump shall be connected to the outlet port with the valve
open. Zen a vacuum of 10 inches of mercury ( -5 psig) has be attained, the valve
shall be closed and the time noted.
08/17/92 Page 4 Manholes
4. The manhole shall have passed the test if the vacum does not drop below 9 inches
of nnercury (-4.5 psig) within three (3) minutes of the time the valve as closed.
The actual vacuun shall be recorded at the end of the three (3) minutes during
which the valve was closed.
(3)-- Failure to Pass -the Test — Meanie: of Teets
If the manhole fails to pass the test by either the exfiltration or the vacuum method as
described in (1) and (2) above, or if visible groundwater leakage into the manhole is
observed, the Contractor shall locate the leek, make repairs acceptable to the E
and retest. Records of all manhole tasting shall be made available to the Engineer at
the close of each working day, or as otherwise directed.
(4) Inspection:
The Engineer shall make a visual inspection of each manhole after it has passed the
testing requirements and is considered to be in its final condition. The inspection
shall determine the completeness of the manhole; any defects shall be corrected to the
EYngineer'a satisfaction.
506.5 Measurement:
All junction boxes and manholes of the type indicated shall be measured as units
complete in place.
New msnilnles constructed to interim elevations to facilitate stage construction shall be
measured as one unit re ardless of the number of interim elevations constructed. All
labor, materials and other expanses necessary for the stage construction shall be
considered subsidiary to the completed unit.
506.6 Payment:
Paymennt for completed junction boxes and manholes of the type indicated shall be made at
the unit price bid for each including all labor,equipnait, materials, time and
incidentals necessary to complete the work.
The intended use of cosh item shall be designated by a two code (Wastewater = WW;
Stormwater = SW) in the spaces provided after the pay item number:
1. Pay Item No. 506 M_: Manhole, Dia. Per Each
2. Pay Item No. 506 S • Special Manhole, Dia. Per Each
3. Pay Item No. 506 DWW: Drop Mannhole, Dia. Per Each
4. Pay Item No. 506 C : Centered Tee Manhole, -- Dia. x _ Dia. Per Each
5. Pay Item No. 506 T : Tangent Tee Manhole, Dia. x Dia. Per Each
6. Pay Item No. 506 J : Junction Box, _ Ft x _ Ft Per Each
END
Applicable Pefe na se: ,
Standard Specifications Manual: Item Nos. 403, 406, 410, 503, 507, 510
Standards Manual: Standard Detail Nos. 100 -1, 503-2, 503-3, 506-1, 506-3, 506-5, 506-7, 506-8,
506-9, 506 -10, 506 -11, 506 -12, 506-13
Utilities Manual: Section 2, Water and Wastewater Design Criteria
506 06/17/92
Page 5 Manholes
509.1 Description
This item consists of designing, furnishing. installing, dewatenng, maintaining and removing safety systems for
trench excavations as determined by Contractor's Trench Safety Engineer and/or Contractor's Competent
Person(s). This includes special clearing. excavation and backfiiling for safely systems. At a minimum. this
work shall conform to United States Department of Labor Rules 29 CFR, Part 1926 (OSHA).
509.2 Trench Safety System Plan Submittal
Prior to, or at the Pre - Construction Conference, the Contractor shall submit to Owner a Trench Safety System
Plan sealed by a Professional Engineer registered in the State of Texas Notice To Proceed with construction
will not be issued by Owner until Contractor has submitted a Trench Safety System Plan to Owner. The Trench
Safety System Plan at a minimum, shall conform to OSHA standards for sloping of sides, utilization of trench
boxes. and/or utilization of shoring. sheeting and bracing methods. Contractor shall be responsible for obtaining
the necessary geotechnical information to design the Trench Safety System Plan; however, if geotechnical
information was obtained by Owner for the design of the improvements (normally taken at 500 foot intervals
along the proposed centerline to a depth not exceeding five feet below proposed fowline), it shall be provided to
Contractor for information purposes subject to the provisions of Section 00220 Soil Investigation Data.
The Trench Safety System Plan submittal shall include:
(1) A plait or other designation of areas in which each type of system is to be used, including length of
trench to be opened. length of time trench to remain opened, means of egress, storage of materials,
allowable loads on trench walls. methods for filling /compacting beddingrbackfill within the safety of the
system. removal of system and equipment restrictions.
(2) Drawings or manufacturer's data describing various elements of Trench Safety System with sufficient
detail for workers to properly install Trench Safety System, as applicable.
(3) Recommendations and limitations for using systems.
(4) Sealed engineering calculations and /or equipment manufacturer's certifications. as applicable. showing
that systems designed to withstand anticipated loadings and can be fully installed in designated space
within the street right of way or easement provided by Owner.
(5) Certificate of Insurance of Trench Safety Engineer's Professional Liability Insurance coverage written by
a company acceptable to Owner and authonzed to do business in State of Texas at time policy is issued.
Contractor's Trench Safety Engineer shall carry and maintain coverage with mi nimum limits of 5500,000.
509.3 Trench Safety System Plan Review
Item No. 509
Trench Safety Systems
Review of the Trench Safety System Plan by Owner is only for general conformance to OSHA standards and
regulations. Owner's failure to note exception(s) to the submittal does not relieve Contractor of any or all
responsibility or liability for the Trench Safety System Plan. Contractor remains solely and completely
responsible for all trench safety systems and for the means, methods, procedures, and materials therefor.
509.4 Construction Methods
Contractor's Competent Person(s) shall maintain a copy of and implement OSHA trenching safety regulations at
the worksite. Trenching shall be completed to lines and grades indicated or as specified in various technical
specification items requinng excavation and trenching and/or backfilling. Contractor shall perform all trenching in
a safe manner and maintain safety systems to prevent death or injury to personnel or damage to structures,
utilities or property in or near excavation.
If evidence of possible cave -ins or slides is apparent or an installed trench safety system is damaged, work in
trench shall immediately cease and personnel evacuated from hazardous area and Owner notified. Personnel
shall not re -enter excavation until necessary repairs or replacements are completed, inspected and approved by
5119 112/19/93 1 Trench Safety Systems
'Contractor's Competent Person(s). Repair and replacement of damaged safety system shall be at Contractor's
sole expense.
1 509.5 Changed Conditions
When changed conditions require modifications to the Trench Safety System, Contractor shall provide a new
"d esign or an alternate Trench Safety System designed by Contractor's Trench Safety Engineer adequate for
'conditions encountered. Copies thereof shall be provided to Owner in accordance with 509.2 'Trench Safety
Plan Submittal A copy of the most current Trench Safety System shall be maintained on site and made
(
variable to inspection and enforcement officials at all times
hanges to the Trench Safety System Plan initiated by Contractor for operational efficiency or by changed
conditions that could be reasonably anticipated will not be cause for contract time extension or cost adjustment
't hereof When changes to the Trench Safety System Plan are the result of severe and uncharacteristic natural
conditions or other conditions totally out of the control of Contractor. Contractor may make a wntten request to
Owner for a Change Order to address said work. Contractor shall notify Owner in wnting Immediately, but no
later than 24 hours, whenever changed conditions are encountered that Contractor may claim for additional
ompensallon. Only that work that Contractor deems Immediately necessary to protect the safety of workers and
public, equipment or materials may be accomplished until Contractor makes the written request for a Change
Order and Owner has a reasonable opportunity to investigate and respond in wnting to the request.
1 509.6 Measurement
Trench Safely Systems shall be measured by linear foot through manholes and other appurtenances along the
'centerline of trench conforming to Contractor's plans and specifications.
509.7 Payment
'Payment for Trench Safety Systems, measured as prescribed above. will be made at unit price bid per centerline
linear foot of trench per Contractor's plan and specifications which price shall include designing, furnishing,
i nstalling. dewatering, maintaining. replacing and removing the Trench Safety Systems, sloping, special clearing,
nd excavation necessary to safely implement the Trench Safety System Plan.
Payment will be made under the following
' Pay Item No. 509 - 1: Trench Safety Systems (all depths) Per Linear Foot.
I ND
ef: 104, 110. 111, 120, 130, 401, 414, 501, 502, 504, 506, 508, 510, 511, 551, 558, 559, 591, 593, 594
1)2/19/93 2 Trench Safety Systems
509.6 Measurement
Trench Safety Systems shall be measured by linear foot through manholes and
other appurtenances along the centerline of trench conforming to
Contractor's plans and specifications.
509.7 Payment
Payment for Trench Safety Systems, measured as prescribed above, will be
made at unit price bid per centerline linear foot of trench per
Contractor's plan and specifications which price shall include designing,
furnishing, installing, dewatering, maintaining, replacing and removing the
Trench Safety Systems, sloping, special clearing, and excavation necessary
to safely implement the Trench Safety System Plan.
Payment will be made under the following:
END
Pay Item No. 509 -1: Trench Safety Systems (all depths) Per Linear
Foot.
Ref: 104, 110, 111, 120, 130, 401, 414, 501, 502, 504, 506, 508, 510, 511,
551, 558, 559, 591, 593, 594
509 08/28/89 Page 3 Trench Safety Systems
$0.1 Description
Item No. 510
Pipe
This item shall consist of furnishing all pipe and /or materials for
constructing pipe mains, severs, laterals, stubs, inlet leads, service
connections and culverts, including all applicable work such as excavating,
bedding, jointing, backfilling materials, tests, concrete trench cap,
concrete cap and encasement, etc., prescribed under this item in accordance
with the provisions of the Edwards Aquifer Protection Ordinance, when
applicable and Specification "Cuts in Public Right of Way" for existing
streets. The pipe shall be of the sizes, types, class and dimensions
indicated or as designated by the Engineer and shall include all joints or
connections to new or existing mains, pipes, severs, manholes, inlets,
structures, etc., as may be required to complete the work in accordance
with specifications and published standard practices of the trade
associations for the material specified and to the lines and grades
indicated. This item shall consist of any pumping, bailing, drainage and
Item No. 509, "Trench Safety Systems" for trench walls, when indicated.
Mess otherwise provided, this item.shall consist of the removal and
disposition of trees, stumps and other obstructions, old structures or
portions thereof such as house foundations, old sewers, masonry or concrete
lolls, the plugging of the ends of abandoned piped utilities cut and left
in place and the restoration of existing utilities damaged in the process
of excavation, cutting and restoration of pavement and base courses, the
furnishing and placing of select bedding, backfilling and cement or lime
stabilized backfill, the hauling and disposition of surplus materials,
bridging of trenches and other provisions for maintenance of traffic or
access as indicated.
510.2 Materials
bee Contractor shall submit descriptive information and evidence that the
arerials and equipment the Contractor proposes for incorporation into the
murk is of the kind and quality that satisfies the specified functions and
Qsality. Water and Wastewater Standard Products Lists form a part of the
Specifications. Should the Contractor elect to use any materials from
tiese lists, they should be completely and clearly identified when
submitted.
(1) Concrete
Concrete shall conform to Item No. 403, "Concrete for Structures ".
(2) Coarse Aggregate
Coarse aggregate shall conform to Item No. 403, "Concrete for
Structures" or one of the following:
510 06/09/88 Page 1 Pipe
(a) Pipe Bedding Stone
Pipe bedding stone shall be clean gravel, crushed gravel or
crushed limestone, free of mud, clay, vegetation or other
debris, conforming to AST)! C 33 for stone quality. Size
gradation shall conform to ASTH C -33 No. 57 or No. 67 or the
following Table:
(b) Foundation Rock
SIEVE SIZE PERCENT RETAINED BY VEIGBT
1 1/2" 0
1" 0 -10
1/2" 40 -85
*4 90 -100
*8 95 -100
Foundation rock shall be well graded coarse aggregate ranging
in size from 2 to 8 inches.
(c) Flexible Base
Flexible base shall conform to Item No. 210, "Flexible Base ".
(3) Fine Aggregate
(a) Concrete and Mortar Sand
Fine aggregate shall be Grade 1 and shall conform to Item No.
403, "Concrete for Structures ".
(b) Bedding Sand
Sand for use as pipe bedding shall be clean, granular and
homogeneous material composed mainly of mineral matter, free
of mud, silt, clay lumps or clods, vegetation or debris. The
material removed by decantation SDHPT Test Method Tex - 406 -A,
plus the weight of any clay lumps, shall not exceed 4.5
percent by weight.
The average electrical resistance when eater- saturated shall
be at least 1,800 ohm /cm by the single probe method, with no
single test reading lower than 1,500 ohm /cm. Size gradation
of sand for bedding shall be as follows:
510 06/09/88 Page 2 Pipe
(4) Soil Cement
GRADATION TABLE
SIEVE SIZE PERCENT RETAINED BY 'WEIGHT
1/4" 0
#60 75 - 100
#100 95 -100
Soil cement bedding shall consist of a mixture of approved soil,
cement, eater and approved admixtures. The soil cement mixture
shall have a minimum 14 day compressive strength of 120 psi and a
maximum shrinkage of 5 percent. The mix design and the results of
mix testing, both done by an independent testing laboratory
acceptable to the Owner, shall be submitted to the Engineer for
approval prior to construction.
The water content shall not exceed that required to provide a mix
that will flow, can be pumped and vill maintain the soil in
suspension while being placed. The soil cement bedding shall be
placed such that all voids are filled. Soil for the soil cement
bedding shall meet the following requirements:
a. A minimum of 80 percent by dry weight shall pass a *4
sieve.
510 06/09/88
b. Between 5 percent and 30 percent shall pass a #200
sieve.
c. The soil material shall have a plasticity index of 3 or
less.
d. The maximum size of any clay balls in the soil shall be
1/2 inch.
Class C or Class F fly ash may be used as an admixture. The fly
ash shall meet the requirements of ASTM C 595, C 618 and the
supplier's certificate as to the analysis and composition shall
be furnished.
Batching equipment shall be provided to obtain the proper weights
of soil, cement, eater and admixture. All measuring devices shall
be sensitive to a 2 percent variation above or below the actual
weights required.
The mixers used for mixing the soil cement bedding shall be
designed and operated so that the soil cement discharged from the
mixer is uniform in compaction and consistency throughout each
batch.
Page 3
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(5) Pea Gravel
SIEVE SIZE PERCENT RETAINED BY WEIGHT
3/4" 0
1/2" 0 -25
1/4" 90 -100
(6) Select Backfill or Borrow
This material shall consist of borrov or suitable material
excavated from the trench which has a plasticity index of less
than 20, a moisture content vhich does not exceed 2 percent from
optimum as determined in accordance with SDHPT Test Method
Tex -114 -E and free of stones or rocks over 8 inches.
All suitable materials from excavation operations not required for
backfilling the trench shall be placed in embankments, if
applicable. All unsuitable materials should be dried or modified
to make them suitable for use, as required.
(7) Cement Stabilized Backfill
When indicated or directed by the Engineer, all backfill shall be
with cement - stabilized backfill rather than the usual materials.
Unless otherwise indicated, cement stabilized backfill material
shall consist of a mixture of the dry constituents described for
Class J Concrete. The cement and aggregates shall be thoroughly
dry mixed vith no eater added to the mixture except as may be
directed by the Engineer.
(8) Pipe
Pea gravel bedding shall be clean washed material, hard and
insoluble in vater, free of mud, clay, silt, vegetation or other
debris. Stone quality shall meet ASTM C 33. Size gradation shall
be as follovs:
General
Fire line leads and fire hydrant leads shall be ductile iron.
Domestic water services shall not be supplied from fire service
leads, unless the domestic and fire connections are on separately
valved branches with an approved backflov prevention device in the
fire service branch. All wastewater force mains shall be
constructed of ductile iron pipe of the class indicated, Thickness
Class 50 minimum.
Water pipe in or near structures and in vehicular traffic areas
within utility easements on private property shall be Ductile Iron
Pipe, Thickness Class 52 wrapped as indicated, except for sizes
over 24 inches, Concrete Pressure Pipe, steel cylinder type,
conforming to the requirements of AVVA C -301 will be acceptable.
510 06/09/88 Page 4 Pipe
There may be no service connections to Concrete Pressure Pipe
installed in these areas. All service tubing (3/4 inch thru 2
inches) installed in any such private property shall be 150 psi
annealed seamless Type K copper tubing with no sweat or soldered
joints.
The quality of materials, the process of manufacture and the
finished pipe shall be subject to inspection and approval by the
Engineer at the pipe manufacturing plant and at the project site
prior to and during installation.
(a) Reserved
(b) Iron Pipe
Iron pipe shall be ductile iron pipe conforming to the
specifications below:
AVVA C -151 For push -on ar mechanical joint piple.
AVVA C - 115
For flanged pipe, flanges must be ductile iron
(gray iron is not acceptable) Class 125 ANSI
B16.1 and must be fabricated and attached to
the pipe barrels by the original pipe
manufacturer.
AVVA C -104 All pipe interiors shall be cement - mortar
lined and seal coated accordingly; pipe
exteriors shall be coated as required by the
applicable pipe specification.
Except as described above for easements, and where not
otherwise indicated, ductile iron pipe shall meet the
following minimum physical requirements:
Thickness Class 50
Tensile Strength 60,000 psi
Yield Strength 42,000 psi
1. Ductile Iron and Gray Iron Fittings
Fittings shall be push -on, flanged or mechanical joint
as indicated or approved and shall conform to the
following specifications:
Sizes 4 inch through 12 inch: AVVA C - 110 or
AVVA C - 153
Sizes larger than 12 inch: AVVA C -110
510 06/09/88 Page 5 Pipe
1
1
1
J
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
AVVA C -104:
2. Joint Materials
The interior of all fittings shall
be cement - mortar lined and coated as
per C -104; exterior coating shall be
as required by the applicable
fitting specification.
Gaskets for mechanical joints shall conform to ANSI /IOVA
A21.11 /C -111.
Joining of slipjoint iron pipe shall, without exception,
be accomplished with the natural or synthetic rubber
gaskets of the manufacturer of that particular pipe
being used. A joint lubricant shall be used and
applicable recommendations of the manufacturer shall be
followed.
Gaskets for flanged joints shall be bonded continuous
full face gaskets, of 1/8 inch minimum thickness of
natural or synthetic rubber, cloth- reinforced rubber,
neoprene or asbestos composition material, preferably of
deformed cross section design and shall meet all
applicable requirements of ANSI /AVVA A21.11 /C -111 for
gaskets. They shall be manufactured by, or satisfy all
recommendations of, the manufacturer of the
pipe /fittings being used and be fabricated for use with
Class 125 ANSI B16.1 flanges.
Tee -head bolts, nuts and washers for mechanical joints
shall be high strength, low alloy, corrosion resistant
steel stock equal to "COR -TEN A" or alloyed ductile iron
conforming to ASTM A 536, fabricated in accordance with
the ANSI /AWVA A21.11 /C - 111.
Hex head bolts and nuts shall satisfy the chemical and
mechanical requirements of ASTM A 307 Grade B and shall
be fabricated in accordance with ASTH B 18.2 with UNC
Class 2 rolled threads.
Hex bolts, nuts and washers shall be stainless steel or
hot -dip zinc or hot -dip aluminum coated. Either hex or
tee head bolts, nuts and washers with bonded
fluoropolymer corrosion resistant coating may be used
where specifically approved.
All threadea fasteners shall be marked with a readily
visible symbol cast, forged or stamped on each nut and
bolt, which will identify the fastener grade /material
and the producer and the supplier shall provide adequate
literature to facilitate such identification. Painted
markings are not acceptable.
510 06/09/88 Page 6 Pipe
3. Polyethylene Film Wrap
All iron pipe, fittings and accessories shall be wrapped
with 8 mil (minimum) polyethylene film conforming to
AWVA C - 105, with all edges overlapped and taped securely
with duct tape to provide a continuous wrap to prevent
contact between the piping and the surrounding backfill.
Repair all punctures of the polyethylene vith duct tape
to restore the continuous protective wrap before
backfilling.
4. Marking
(c) Concrete
Each pipe joint shall be marked with the pipe class,
manufacturer's identification, year manufactured and
"Ductile" or "DI ".
1. General
Pipe shall conform to AST( C 76 for Circular Pipe.
Concrete pipe smaller than 12 inches in diameter shall
conform to AST( C 14, Extra Strength. All pipe shall be
machine made or cast by a process which will provide
uniform placement of the concrete in the form and
compaction by mechanical devices which will assure a
dense concrete. Concrete shall be mixed in a central
batch plant or other approved batching facility from
which the quality and uniformity of the concrete can be
assured. Transit mixed concrete will not be acceptable
for use in precast pipe. The pipe shall be Class III or
the class indicated. Storm sewer pipe shall be of the
tongue and groove or 0 -ring joint design. Wastewater
pipe shall be of the 0 -ring joint design.
2. Marking
Each joint of pipe shall be marked with the pipe class,
the date of manufacture, the manufacturer's name or
trade mark, diameter of pipe and orientation, if
required.
Pipe marking shall be waterproof and conform to ASTM C
76. Harking of Life Design shall be included on
wastewater pipe.
3. Minimum Age for Shipment
Pipe shall be considered ready for shipment when it
conforms to the tests specified in ASTM C 76.
510 06/09/88 Page 7 Pipe
1
1
1
1
1
1
1
t
1
1
1
1
1
1
I
1
1
1
4. Joint Materials
When constructing storm sewers, the Contractor shall
have the option of making joints with either of the
following materials:
a. Hortar
Mortar for joints shall meet the requirements
set forth below in "Mortar".
b. Cold Applied Preformed Plastic Gaskets
Cold Applied Plastic Gaskets shall be suitable
for sealing joints of tongue and groove
concrete pipe. The gasket sealing the joint
shall be produced from blends of refined
hydrocarbon resins and plasticizing compounds
reinforced with inert mineral filler and shall
contain no solvents, irritating fumes or
obnoxious odors. The gasket joint sealer
shall not depend on oxidizing, evaporating or
chemical action for its adhesive or cohesive
strength and shall be supplied in extruded
rope form of suitable cross section. The size
of the plastic gasket joint sealer shall be in
accordance with the manufacturer's
recommendations and sufficient to obtain
squeeze -out around the joint. The gasket
joint sealer shall be protected by a suitable
removable wrapper that may be removed
longitudinally without disturbing the joint
sealer to facilitate application.
The chemical composition of the gasket joint
sealing compound as shipped shall meet the
following requirements:
Composition Test Method Typical Analysis
Bitumen (petroleum ASTM D 4 50 -70
plastic content)
(Y by weight)
Ash -inert Mineral Water Tex -526 -C 30 -50
(Z by weight)
Volatile Matter (at 325 F) Tex -506 -C 2.0 Maximum
(Z by weight)
The gasket joint sealing compound when immersed for
30 days at ambient room temperature separately in 5
percent solution of caustic potash, a mixture of 5
percent hydrochloric acid, a 5 percent solution of
510 06/09/88 Page 8 Pipe
5. Beds
510 08/24/93
sulfuric acid and a saturated F2S solution shall show no visible deterioration.
The physical properties of the gasket joint sealing compound as shipped shall meet the
following requirements:
ProPertY
Specific Gravity at 77 F
Ductility at 77F (cm) Minim=
Softening point Penetration:
32 F (300 g) 60 sec
77 F (150 g) 5 sec
115 F (150 g) 5 sec
Flashpoint C.O.C. F
Fire Point C.O.C. F
Test Typical Analysis
Method Minimise Maxim
ASDI D 71
Tex -503 -C
Tex -505 -C
Tex -502-C
Tex -502 -C
Tex -502 -C
Tex-504 -C
Tex-504-C
1.20 1.35
5.0
275 F
75
50 120
150
600 F
625 F
When constructing wastewater lines, the contractor shall use rubber gasket joints conforming to
ASIM C 443. Just before :raking a joint, the ends of the pipe shall be clean, dry, free of
blisters or foreign matter and shall be wire brushed. For 0 -ring joints, the gasket and the
inside surface of the bell shall be lubricated with a light film of soft vegetable soap
compound to facilitate assembly of the joint. The rubber O-ring gasket shall be stretched
uniformly in the joint. Wedge seal type ( "Forsheda" pre- lubricated) gaskets may be used if
joint details submitted are approved; installation of such gaskets shall be in strict
accordance with the manufacturer's rer miadatic s, and shall be the sole element depended upon
to make the joint flexible and watertight.
In wastewater lines no horizontal or vertical angles in the alignment of pipes shall be
permitted unless indicated. The spigot shall be centered in the bell, the pipe pushed
uniformly home and brought into true alignment. Bedding material shall be placed and tamped
against pipe to secure the joint.
When horizontal or vertical angles in the alignment of storm sewers are indicated, the
bed or angle shall be constructed by cutting on a bias one or both pipes as may be
required for the aligr=mt indicated.
The pipe cut shall be sufficiently long to allow exposing the reinforcement, which
shall be bent, welded and incorporated into the pipe bed and reinforced concrete
collar to maintain the structural integrity. The collar shall be 6 inches minimum,
reinforced with #4 bars anal foot center both directions. Builder's hardware cloth
may be used on the outside of the joint to aid in holding cementing materials in place.
Plywood, fiberboard or other materials placed an the inside of the pipe as formwork
shall be re oved as soon as the joint materials have obtained initial set, after which
the inside surface of the pipe joint shall be finished smooth and true to the line and
grade
Page 9 Pipe
510
established. The Contractor may use prefabricated bends
meeting the specification requirements in lieu of field
fabricated bends. All bends shall be watertight, have a
smooth floe line and be equal or greater in strength to
the adjacent pipe.
Horizontal or vertical bends in wastewater lines shall
be accomplished by use of manholes. Vith the Engineer's
approval, bends may be constructed using beveled radius
pipe joints or deflected straight pipe meeting the
manufacturer's recommended minimum radius of curvature.
6. Sulfide and Corrosion Control
All concrete pipe used for wastewater installations
shall be protected from sulfide and corrosion damage by
using limestone aggregate or wall thickness pipe which
meets the 100 year life design.
(d) Concrete Steel Cylinder (CSC) Pipe
1. General Requirements
The Contractor shall submit to the Engineer for approval
along with other required data a tabulated layout
schedule with reference to the stationing and grade
lines to be used.
The manufacturer shall furnish all fittings and special
pieces required for closures, bends, branches, manholes,
air valves, blovoffs and connections to main line valves
and other fittings as indicated.
Each pipe length, fitting and special joint shall have
plainly marked on the bell end of the pipe, the head
condition for which it is designed. In addition,
marking will be required to indicate the location of
each pipe length or special joint in the line and such
markings will be referenced to the layout schedules and
drawings and submitted for approval.
Hydrostatic testing of concrete steel cylinder fittings
during fabrication will not be required.
2. Design and Inspection
Vhere not otherwise indicated, concrete steel cylinder
pipe shall be Class 150, designed to withstand a vacuum
of not less than 28 feet of water in addition to other
loads. Valve reducers, tees and outlets from a pipe run
shall be designed and fabricated so that all stresses
are carried by the steel forming the fitting or outlet.
06/09/88 Page 10
Pipe
Concrete steel cylinder pipe shall meet one of the
following specifications:
AVWA C -301 - Any Size
AWA C -303 - 24 inch maximum size
All pipe flanges shall conform to AWVA C -207,
requirements for standard steel flanges of pressure
classes corresponding to the pipe class.
Pipe to be installed in a tunnel or encasement shall be
manufactured with 1 inch thick by 24 inch wide skid
bands of mechanically impacted mortar in addition to the
normal coating.
All concrete steel cylinder fittings shall be
constructed of steel plate of adequate strength to
'withstand both internal pressure and external loading.
Rod reinforcing shall not be used to figure the required
steel area. The fittings shall have a concrete lining
and 1 inch minimum coating of cement mortar, except that
centrifugally spun lining need not be reinforced.
Minimum lining thickness shall be 1/2 inch for 16 inch
pipe and 3/4 inch for sizes larger than 16 inch pipe.
Vhere it is impractical to place such concrete
protection on interior surfaces of small outlets, 2
coats of "Situmastic Tank Solution" shall be applied.
No fitting shall be made by cutting of standard pipe,
except that outlets of less than 75 percent of the pipe
diameter may be placed in a standard pipe. Beveled
spigots may be placed on standard pipe.
3. Joint Materials
Joints shall be of the rubber gasket type conforming to
the applicable standards. The inside and outside
recesses between the bell and spigot shall be completely
filled with Cement Grout in accordance vith the pipe
manufacturer's recommendations. Grout materials for
jointing such pipe, unless otherwise indicated, shall be
as described herein.
(e) In Place Pipe Rehabilitation
1. In Place Sliplining With or Vithout Pipe
Destruction /Replacement
This item shall consist of installing a high density
polyethylene pipe by use of a pipe insertion machine,
such as Expand -A -Line or approved equal, into an
existing line.
510 06/09/88 Page 11 Pipe
a. Material Requirements
The polyethylene pipe shall meet the following
specifications:
ASTM F 714
Plastic Pipe Institute PE3408
Unless otherwise specified, the Contractor shall
furnish the polyethylene pipe in accordance with
the following table:
Depth of Cover
Expressed in Feet SDR of Pipe
0 - 16
16.1 -
b. Functional Requirements
17
11
The polyethylene pipe shall be assembled and
joined at the site using the thermal butt fusion
method. All equipment and procedures shall be in
strict compliance with the manufacturer's
recommendations. Fusing shall be accomplished by
personnel certified as fusion technicians by a
manufacturer of polyethylene pipe and /or fusing
equipment.
The complete joint shall be in true alignment and
have a uniform double roll back bead resulting from
the use of proper temperature and pressure. The
joint shall be allowed adequate cooling time before
removal of pressure. Joints shall be smooth on the
inside vith a maximum projection of the veld bead
of approximately 3/16 inch. The fused joint shall
be watertight and shall have a tensile strength
equal to that of the pipe. All joints shall be
subject to acceptance by the Engineer or his /her
representative prior to placement. All defective
joints shall be cut out and replaced.
Any section of the pipe with a gash, abrasion, nick
or scar greater in depth than 10 percent of the
wall thickness, or containing concentrated ridges,
discolorization, excessive spot roughness, pitting,
variable wall thickness, or any other defect of
manufacturing or handling as determined by the
Engineer or his /her representative, shall be
discarded and removed from the site.
Terminal sections of pipe that are joined within
the insertion pit shall be connected with a full
circle pipe repair clamp with a minimum length of
510 06/09/88 Page 12 Pipe
one and one half times the nominal inside pipe
diameter, in accordance with Water and Wastewater
OPL No. 271. The butt gap between pipe ends shall
not exceed 1 /10 of the nominal inside diameter of
the pipe.
c. Installation Procedure
The Contractor shall carry out his operations in
strict accordance with all OSHA and manufacturer's
safety requirements. Particular attention is drawn
to those safety requirements involving entering
confined spaces and trench safety.
The Contractor, when required, shall provide for
the flow of water around the section or sections of
pipe designated for rehabilitation including active
services in the rehabilitation section. The bypass
shall be made by plugging the line at an existing
upstream manhole or adjacent system. The pump and
bypass lines shall be of adequate capacity and size
to handle the flow. The Contractor shall take all
necessary steps to prevent flooding of any private
property and shall be liable for damages incurred
by the flooding.
Nev polyethylene pipe shall be inserted immediately
behind the boring equipment in accordance with the
manufacturer's procedures. The boring machine
shall be specifically designed and manufactured by
Expand -A -Line or approved equal. The boring
machine shall be equipped with all controls
necessary to place the pipe on proper line and
grade according to the plans.
The Contractor shall install all pulleys, rollers,
bumpers, alignment control devices and other
equipment required to protect existing manholes and
to protect the pipe from damage during
installation.
Lubrication may be used as recommended by the pipe
manufacturer. Under no circumstances shall the
pipe be stressed beyond its elastic limit.
All active service connections shall be identified
by video inspection or other means and connected to
the new main in accordance with the plan details.
Upon commencement, insertion, from manhole to
manhole, shall be continuous without interruption
except as approved by the Engineer.
510 06/09/88 Page 13 Pipe
The installed pipe shall be allowed the
manufacturer's recommended amount of time, but not
less than 12 hours, to provide for complete
' shrinkage or relaxation of the pipe prior to any
connection of service lines, sealing of the annular
space where the pipe enters the manhole, or
' backfilling of the insertion pit. Sufficient
excess length of pipe shall be allowed to provide
for this shrinkage.
' The pipe bedding in the insertion pit shall be
either pea gravel or pipe bedding stone. Bedding
and backfill shall conform to the specifications
contained herein. All street repairs and pavement
replacement shall conform to Item No. 500, "Cuts in
Public Right of Way ".
' The relaxed pipe shall be cut so that it projects 4
inches inside of the manhole and any annular space
shall be sealed. Sealing shall be with material
' approved by the Engineer. The sealant shall
completely fill the void between the pipe and the
manhole .a11 and shall extend 3 inches beyond the
' annulus on the inside wall of the manhole. The
sealant shall form a smooth transition from the
pipe onto the manhole. The complete joint shall be
uniform and watertight. A concrete invert shall be
' poured in place and shaped to form a smooth flow
channel through the manhole.
2. Cured Resin Pipe Lining
This item shall consist of installing a resin
impregnated flexible felt tube by an inversion
reconstruction method, such as Insicuform or equal, into
an existing pipe. Curing shall be accomplished by
circulating hot vater or other approved method to cure
' the resin into a hard impermeable pipe lining.
Insituform is a patented process installed by licensed
installers.
a. Material Requirements
The fiber felt tube shall be fabricated to a size
that when installed will neatly fit the internal
circumference of the conduit specified by the
Engineer.
' The minimum length shall be that deemed necessary
by the Contractor to effectively span the distance
from the inlet to the outlet of the respective
manholes unless otherwise specified. The
Contractor shall verify the lengths in the field
before impregnation. Individual inversion runs can
' l 510 06/09/88 Page 14 Pipe
P
be made over one or more manhole sections as
determined in the field by the Contractor, subject
to approval by the Engineer.
Unless otherwise specified, the Contractor shall
furnish a general purpose unsaturated polyester
resin and catalyst system that meets the finished
cured physical strengths listed below:
Flexural Stress (ASTM D 790) 4,500 psi_
Tensile Stress (ASTM D 368) 2,500 psi
Modulus of Elasticity (ASTM D 790) 250,000 psi
If so directed,.the Contractor shall furnish, prior
to use of the materials, satisfactory written
certification of his compliance with the above
standards.
b. Installation Procedure
The Contractor shall carry out his operations in
strict accordance with all OSHA and manufacturer's
safety requirements. Particular attention is drawn
to those safety requirements involving working with
scaffolding and entering confined spaces.
When required, cleaning and repair of the pipe line
shall be performed by City of Austin Water and
Wastewater Utility. Inspection of pipe line by the
Contractor shall be performed by experienced
personnel trained in locating breaks, obstacles
and service connections by closed circuit
television. The interior of the pipe shall be
carefully inspected to determine the location of
any conditions which may prevent proper
installation into the pipe and these conditions
shall be corrected. A video tape and log shall be
made by the Contractor and kept for later reference
by the Owner.
The Contractor, when required, shall provide for
the flow of water around the section or sections of
pipe designated for rehabilitation including active
services in the rehabilitation section. The bypass
shall be made by plugging the line at an existing
upstream manhole and pumping the flow into a
downstream manhole or adjacent system. The pump
and bypass lines shall be of adequate capacity and
size to handle the flow. The Contractor shall take
all necessary steps to prevent flooding of any
private property and shall be liable for any
damages incurred by the flooding.
510 06/09/88 Page 15 Pipe
510
It shall be the responsibility of che City of
Austin to clear the lines of obstructions such as
solids, dropped joints, protruding service
connections or collapsed pipe that will prevent the
insertion of Insituform.
The Contractor shall designate a location where the
uncured resin in the original containers and the
unimpregnated fiber -felt tube shall be vacuum
impregnated prior to installation. The Contractor
shall alloy the Engineer to inspect the materials
and "vet out" procedure. The quantities of the
liquid thermosetting materials shall be per
manufacturer's standards to provide the wall
thickness specified.
Water for the work shall be furnished by the City.
Contractor shall use a double -check valve assembly
to prevent backflow in the event of pressure
failure. The wet out fiber -felt tube shall be
inserted through an existing manhole or other
approved access by means of an inversion process
and the application of a hydrostatic bead
sufficient to fully extend it to the next
designated manhole.
The impregnated tube material shall be inserted
into the vertical inversion standpipe with the
impermeable plastic membrane side out. At the
lover end of the inversion standpipe, the felt tube
shall be turned inside out and attached to the
standpipe so that a leakproof seal is created. The
inversion head will be adjusted to be of sufficient
height to cause the impregnated tube to invert from
manhole to manhole and hold the tube tight to the
pipe wall, produce dimples at side connections and
flared ends at manholes. The use of a lubricant is
recommended and, if used, such lubricant shall be
as approved by manufacturer's standards. The
manufacturer's standards shall be closely followed
during the elevated curing temperature so as not to
over stress the felt -fiber and cause damage or
failure prior to cure. (If prior approval is
obtained from the owner, the Contractor may elect
to use a Top Inversion. In this method the
fiber -felt tube is preinverted to a distance that
corresponds to che minimum inversion head and
instead of attaching to 'am elbow at the base of the
vertical inversion standpipe, it is attached to a
top ring and the standpipe is formed from the felt
tube itself.)
After inversion is completed the Contractor shall
supply a suitable heat source and water
06/09/88 Page 16
Pipe
recirculation equipment. The equipment shall be
capable of delivering hot eater throughout the
section by means of a prestrung hose, which has
been perforated per manufacturer's recommendations,
to uniformly raise the eater temperature above the
temperature required to effect a cure of the resin.
This temperature shall be determined by the
resin /catalyst system employed.
The heat source shall be fitted with suitable
monitors to gauge the temperature of the incoming
and outgoing water supply. Another such gauge
shall be placed between the impregnated felt tube
and the pipe invert at the remote manhole to
determine the temperature during cure. Water
temperature in the line during the cure period
shall not be less than 150 F or more than 200 F as
measured at the heat source return line.
Initial cure shall be deemed to be completed when
inspection of the exposed portions of pipe liner
appear to be hard and sound and the remote
temperature sensor indicated that an exotherm had
occurred. The cure period shall be of a duration
recommended by the resin manufacturer, as modified
for the manufacturer's process during which time
the recirculation of the water and cycling of the
head exchanger to maintain the temperature
continues.
The Contractor shall cool the hardened pipe liner
to a temperature below 100 F before relieving the
static head in the inversion standpipe. Cool -down
may be accomplished by the introduction of cool
eater into the inversion standpipe to replace
water being drained from a small hole made in the
downstream end.
Care shall be taken in the release of the static
head so that a vacuum will not be developed that
could damage the newly installed pipe liner.
The fir`shed pipe liner shall be continuous over
the ent_re length of an inversion run between two
manholes and be free from visual defects such as
foreign inclusions, dry spots or voids.
Any defect which will affect, in the foreseeable
future, or warranty period, the integrity or
strength of the pipe liner shall be repaired at the
Contractor's expense, in a manner specified by the
Engineer.
510 06/09/88 Page 17 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
After the pipe liner has been cured in place, the
Contractor shall connect new services or reconnect
existing service connections as designated and
identified by the proposal. This shall generally
be done without excavation, from the interior of
the pipeline by means of a television camera and a
cutting tool. The eater- tightness of the pipe
liner shall be-gauged while curing and under a
positive head. To ascertain that there is no
leakage, the eater pressure inside the pipe should
hold at 6 pounds per square inch for a duration of
at least 4 hours testing time. After the work is
completed the Contractor will provide the Engineer
with a video tape showing both the before and after
conditions including the restored connections.
(f) Polyethylene Tubing
1. General
If, due to broken or misaligned pipe at a manhole
wall, the pipe liner failed to make a tight seal,
the Contractor shall apply a seal at that point.
The seal shall be of a resin mixture compatible
with pipe liner.
All polyethylene (PE) plastic tubing shall be high
density, high molecular weight plastic tubing, pressure
rated at 200 psi working pressure and must bear the
National Sanitation Foundation seal of approval for
potable eater service.
When tested for Environmental Stress Cracking, the PE
tubing shall not shoe any loss of pressure in the 6
specimens tested for 3 hours in accordance with the
requirements of ASTM 0 2737 using the test pressure of
400 psi at 73.4 F.
The minimum burst pressure shall be 630 psi at 73.4 F
determined in accordance with ASTM D 1599, latest
revision. The time of testing of each specimen shall be
between 60 and 70 seconds.
The tubing shall not fail, balloon, burst or veep as
defined in ASTM D 1598, latest revision, when tested in
accordance with the Sustained Pressure Test Method of
ASTH D 2737 but under the following test conditions:
Temperature Time Pressure
73.4 F 1,000 hours 400 psi
100 F 1,000 hours 330 osi
510 06/09/88 Page 18 Pipe
2. Markings
Permanent marking an the tubing shall include the
following at intervals of not more than 5 feet:
3. Tube Size
Nominal tubing size.
The type of plastic material, i.e., PE 3408.
The Standard Dimension Ratio (SDR) and the pressure
rating in psi for water at 73.4 F (e.g., SDR -9, 200
psi).
ASTM D 2737 designation.
The manufacturer's name or trademark, code and seal
of approval (NSF mark) of the National Sanitation
Foundation.
PE tubing shall be standard copper tube size outside
diameter, with Standard Dimension Ratio (SDR) of 9.
Standard sizes, dimensions and tolerances shall be as
follows:
Nominal Outside Diameter Wall Thickness
Tube Size Average Tolerance Minimum Tolerance
(inches) (inches) (inches) (inches) (inches)
3/4 0.875 +0.004 0.097 +0.010
1 1.125 +0.005 0.125 0.012
1 1/4 1.375 +0.005 0.153 + 0.015
1 1/2 1.625 +0.006 0.181 +0.018
2 2.125 +0.006 0.236 +0.024
(g) Copper Tubing
All copper service tubing shall be annealed seamless Type K
water tube rated at 150 psi vorking pressure. The tubing
shall be homogenous throughout and free from cracks, holes,
crimping, foreign inclusions or other defects. It shall be
uniform in density and other physical properties.
Nominal
Tube Size Outside Diameter Wall Thickness
(inches) (inches) (inches)
1/2 0.625 +0.0025 0.049 +0.004
3/4 0.875 ±0.003 0.065 ± 0.0045
1 1.125 *0.0035 0.065 +0.0045
1 1/4 1.375 +0.004 0.065 +0.0045
1 1/2 1.625 +0.0045 0.072 ±0.005
2 2.125 ±0.005 0.083 ±0.007
510 06/09/88 Page 19 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
(h) Service Connection Fittings
All fittings used in cus
mains, connecting meters
the Vater and Wastewater
in the Standard Installa
Connection Guide section
(i) Brass Goods
tomer service connection - tapping
, etc. - must be currently listed on
Standard Products List or called for
tion Details in the Service
of the City of Austin Standards.
All brass stops, couplings, bends, connections, nipples and
miscellaneous brass pipe fittings and accessories used in
meter connections, copper service lines, air release piping
assemblies and wherever needed in the eater distribution
system, shall conform to the Standards, Vater and Wastewater
Standards product list and AWVA C -800, except as herein
modified or supplemented.
Unless otherwise noted, the goods described herein shall be
fabricated of standard.Red Brass (Waterworks Brass)
consisting of 85 percent copper and 5 percent each of tin,
lead and zinc.
Exposed threads shall be covered with plastic caps or
sheeting to protect the threads.
Brass goods of each type and class shall be compatible with
other fittings in common usage for similar purposes. Where
not otherwise indicated, all such materials shall meet the
following requirements:
Corporation stop thread (where used) shall conform to
Table 1, Figure 1, AWA C -800, commonly called the
Hueller,Thread. Corporation stops with iron pipe
threads are also permitted. Iron pipe threads shall
conform to ANSI B2, 1 - 1969 and Table 9, Figure 9 of AWVA
C -800.
Copper fittings threads shall conform to Table 2 and 3,
Figure 2 and 3 of AWA C -800 and ANSI 81.1960 with
approximate tolerance of Class 2.
Flanges shall conform to ANSI 816.1, Class 125 (or Class
250 where so noted), as to dimensions, drillings, etc.
Brass pipe shall conform to the weight and dimensions of
Table 2 in the Appendix for AWA C -800.
All fittings shall be suitable for use at hydrostatic
working pressures up CO 150 psi.
06/09/88 Page 20 Pipe
(j) PVC - Plumbing Pipe
1. General
Polyvinyl chloride pipe and fittings shall be Type I,
Grade 1, schedule 40, 200 psi conforming to the City of
Austin plumbing code, CS 270 and PS 21.
2. Physical Requirements
Pipe shall be extruded from 100 percent virgin
unplasticized Type 1, Normal Impact Polyvinyl Chloride
(PVC) to conform to the following minimum physical
properties:
Specific Gravity 1.36 -1.40
Tensile Strength at 78 F
(PSI) 7,500
Compression Strength
(PSI) 9,400
Modulus of Elasticity 410,000
Coefficient of
Linear Expansion 6.70K/Cx10 -5
Izod Impact at 78 F
(ft. lbs. /in. notch) 0.7 -1.5
Burning Rate Self
Extinguishing
Heat Distortion at
264 PSI
4. Dimensions and Tolerance
160 F
3. Visual Inspection
Pipe shall be homogenous throughout and free from
visible cracks, holes or foreign materials. Pipe shall
be free from blisters, wrinkles and dents. This
inspection shall be made on each length of pipe.
Dimensional measurements of plastic pipe will be made on
the outside diameter, wall thickness and
out -of- roundness. Pipe not meeting these requirements
shall be rejected. Dimensions and tolerances shall be
in accordance with Commercial Standard CS 256 - 63.
5. Marking and Identification
All PVC pipe shall be continuously and permanently
marked with the following information: manufacturer's
name, pipe size, class or schedule, type of pipe and
material. When used for potable eater line, the pipe
shall bear the seal of the National Sanitation
Foundation for potable water pipe.
510 06/09/88 Page 21 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
6. PVC Pipe Fittings
All fittings shall be of schedule 40 or heavier
plasticized polyvinyl chloride.
7. Inspection and Testing of Materials
Test certificates from a testing laboratory and /or
guarantee by the manufacturer satisfactory to the
Engineer shall be furnished for the pipe and fittings to
be incorporated in the work. As required by the
Engineer, certificates shall be submitted for other
materials to be incorporated in the work. These
certificates, stating that the materials meet the
requirements of the specifications, will be required
before permission is given to incorporate such materials
in the work.
The cost of this inspection and testing will be paid for
by the Contractor and shall be included in his price bid
for such materials complete in place.
Any material brought on the ground for use in the work
and deemed by the Engineer as unsuitable or not in
conformity with the specifications shall be removed from
the site of the work by the Contractor upon receipt of
written notice from the Engineer to that effect.
8. Handling of PVC Pipe and Fittings
The Contractor is cautioned to exercise care in
handling, loading, unloading and storing PVC pipe and
fittings. All PVC pipe and fittings will be stored
under cover before using and will be transported in a
vehicle with a bed long enough to allow the length of
pipe to lay flat so as not to be subject to undue
bending or concentrated external load at any point. Any
section of pipe that has been dented or damaged will be
discarded until said section of pipe is cut out and
rejoined with a coupling.
9. Threaded Connections
On PVC to metal connections, the Contractor shall work
the metal connections first. A nonhardening pipe dope
such as Permatex #2 or equal shall be used on all
threaded PVC to metal joints and light wrench pressure
is all that should be used.
Vhere threaded PVC connections are required, use
threaded PVC adapters into which the pipe may be welded
510 06/09/88 Page 22 ri e
P
(k) Polyvinyl Chloride Water Pipe
1. General
All polyvinyl chloride (PVC) vater pipe shall be of the
rigid (UNPLASTICIZED) type and must bear the National
Sanitation Foundation seal of approval for potable vater
pipe. Each joint of pipe shall consist of single
continuous extrusion; bells or other components attached
by solvent welding are not acceptable. Pipe shall be
pressure rated at 200 psi (SDR -14) or 150 psi (SDR -18)
as indicated.
Pipe shall have push -on, rubber gasket joints of the
bell and spigot type vith thickened integral bells or of
the double spigot type vith thickened coupling sleeves
vith rubber gasket joints. The vall thickness of each
pipe bell and joint coupling must be greater than the
standard pipe barrel thickness. Clearance must be
provided in every gasket joint for both lateral pipe
deflection and for linear expansion and contraction.
Concrete thrust blocking shall be placed behind bends
and tees. Unless the granular bedding envelope
material is pipe bedding stone, concrete support
blocking shall also be placed between the bottom of the
fitting and the undisturbed trench bottom.
2. Applicable Specifications
Except as modified or supplemented herein, PVC pipe
shall meet the following standards:
AVVA C -900, SDR 18 or SDR 14 for PVC Pressure Pipe,
in 4, 6, 8 and 12 inch nominal sizes, having Cast
Iron Pipe size outside diameters.
Fittings used vith PVC Pressure pipe shall be AVVA
C -110 or AVVA C -153 cast iron fittings.
Standard sizes, dimensions and tolerances shall be
as follows:
SDR -18 SDR -14
Nominal Outside Diameter Wall Thickness Wall Thickness
Size Avg. Tolerance Min. Tolerance Min. Tolerance
(inches) (inches) (inches) (inches) (inches) (inches) (inches)
4 4.800 , 0.009 0.267 .0.032 0.343 .0.041
6 6.900 .0.011 0.383 0.046 0.493 .0.059
8 9.050 .0.015 0.503 .0.060 0.646 .0.078
12 13.200 .0.015 0.733 0.088 0.943 .0.113
510 06/09/88 Page 23 Pipe
(1)
All pipe 4 inches and larger must be approved
Underwriter's Laboratories for use in buried eater
supply and fire protection systems.
3. Material Requirements
All pipe and fittings shall be made from clean, virgin,
NSF approved, Class 12454B PVC. Clean reworked
materials generated from the manufacturer's own
production may be used within the current limits of the
referenced AVVA C - 900.
4. Marking
Permanent marking on each joint of pipe shall include
the following at intervals of not more than 5 feet:
2. Joint Material
3. Pipe Markings
Nominal pipe size and OD base (e.g., 4 CIPS).
The type of plastic material (e.g., PVC 12454 -B).
The standard Dimension Ratio and the pressure
rating in psi f " r water at 73 F (e.g., SDR 18, 150
psi).
The AWWA or ASTM designation with which the pipe
complies (e.g., AWVA C 900).
The manufacturer's name or code and the National
Sanitation Foundation (NSF) mark.
Polyvinyl Chloride (PVC) Pipe (Nonpressure) and Fittings
1. General
Where PVC sewer or wastewater pipe is indicated, it shall
conform to the requirements of ASTM D 3034, SDR 35 or ASTM
F 679, having T -1 wall thickness. Minimum cell
classification shall be 12354 -B as defined by ASTM D1784.
PVC pipe and fitting shall have elastomeric gasket joints
conforming to ASTM D 3212; gaskets to ASTM F 477.
Permanent marking on the pipe shall include the following
at intervals of not more than 5 feet:
Manufacturer's name and /or trademark.
510 02/20/92 Page 24 Pipe
Nominal pipe size.
PVC cell classification per ASTM D 1784 (Min. 12354_3)
ASTM designation and legend:
-For pipe 6 inch to 15 inch size;
ASTM D3034, type PSM, SDR -35 PVC sever pipe
-For pipe 18 inch and larger:
ASTM F 679, T -I vall PVC sever pipe.
4. Fitting Markings
Fittings shall be clearly marked as follows:
Manufacturer's name or trademark,
Nominal size,
The material designation "PVC ",
PSM, and
This designation, "Specification D3034 ".
(m) Steel Pipe
1. Standard Weight
ASTM A 53, Schedule 40.
2. Extra Heavy Weight
Seamless ASTM A 53, Schedule 80.
3. Encasement Pipe
Welded or Seamless pipepiles ASTM A -252,
Grade 2
4. Fittings
Nipples and fillings extra strong Federal Specification
WW -N 351 or WW -P 521.
5. Coatings
Black or galvanized as indicated.
(n) Welded Steel Pipe and Fittings for Water -Pipe
1. General Reference Standards Specification.
a. Specifications of the American Water Works
Association (AWWA) listed below shall apply to this
Section.
510 02/20/92 Page 25 Pipe
510
3. Job Conditions
C -200 Steel Water Pipe 6 inches and larger.
C -205 Cement- Mortar Protective Lining and Coating
for Steel Vater Pipe, 4 inches and larger, Shop
Applied.
C -206 Field Welding of Steel Water Pipe.
C -207 Steel Pipe Flanges for Vatervorks Services,
Sizes 4 inches through 144 inches.
C -208 Dimensions for Steel Vater Pipe Fittings.
C -602 Cement - Mortar Lining of Water Pipelines, 4
inches and larger in Place.
2. Submittals
a. Furnish shop dravings, product data, design
calculations and test reports as described below:
(1) Certified copies of mill tests confirming the
type of materials used in steel plates, mill
pipe flanges and bolts and nuts to shoe
compliance vith the requirements of the
applicable standards.
(2) Complete and dimensional working dravings of
all pipe layouts. Shop drawings shall include
the grade of material, size, vall thickness of
the pipe and fittings, type and location of
fittings and the type and limits of the lining
and coating systems of the pipe and fittings.
(31 Product data to shov compliance of all
couplings, supports, fittings, coatings and
related items.
a. The internal design pressure of all steel pipe and
fittings shall be as indicated.
b. The interior of all steel pipe for potable eater, 4
inches and larger, shall be cement- mortar lined.
4. Manufacturing
a. Description
Pipe shall comply with AVVA C -200.
06/09/88 Page 26
Pipe
510
Nominal pipe diameter shall be the inside
diameter of lining or pipe barrel, unless
otherwise designated in Job Conditions.
b. Wall Thickness
5. Fittings
a. Welded
(1) Circumferential deflection of all pipe
in -place shall not exceed 2.0 percent of pipe
diameter.
(2) Diameter
(1) Steel pipe.vall thickness shall be designed
for the internal and external loads specified
in this section. The cylinder thickness
needed to resist internal pressure shall be
based on an allowable stress in the steel
equal to 1/2 the minimum yield stress of the
material used.
Fabricated steel fittings shall be of the same
material as pipe and shall comely with AWA C -208.
6. Flanges
a. Flanges shall comply with the requirements of AWA
C - 207, Class D or Class E. The class shall be
based on operating conditions and mating flanges of
valves and equipment.
b. Gaskets shall be cloth- inserted rubber, 1/8 inch
thick.
c. Flanges shall be flat faced with a serrated finish.
7. Pipe Joints
a. Lap Joints for Field Welding
(1) Lap joints for field welding shall conform to
AWA C -206. This item applies only to pipes
72 inches in diameter and larger.
(2) The bell ends shall be formed by pressing on a
hydraulic expander or a plug die. After
forming, the minimum radius of curvature of
the bell end at any point shall not be less
than 15 times the thickness of the steel
shell. Bell ends shall be formed in a manner
to avoid impairment of the physical properties
06/09/88 Page 27 Pipe
P
510 06/09/88
of the steel shell. Joints shall permit a lai
at least 1 1/2 inches when assembled. The
longitudinal or spiral weld on the inside of
the bell end and the outside of the spigot end
on each section of pipe shall be ground flush
with the plate surface. The inside edge of
the bell and the outside edge of the spigot
shall be scarfed or lightly ground to remove
the sharp edges or burrs.
b. Bell and Spigot Joints with 0 -Ring Gasket
(1) Bell and.spigot joints with rubber gasket
shall conform to AVVA C - 200.
(2) The bell and spigot ends shall be so designed
that when the joint is assembled, it will be
self- centered and the gasket will be confined
to an annuler space in such manner that
movement of the pipe or hydrostatic pressure
cannot displace it. Compression of the gasket
when the joint is completed shall not be
dependent upon water pressure in the pipe and
shall be adequate to ensure a watertight seal
when subjected to the specified conditions of
service. Bell and spigot ends shall be welded
on preformed shapes. The bell and spigot ends
shall conform to the reviewed shop drawings.
8. Interior and Exterior Protective Surface Coatings
a. Exterior Surface to be mortar coated shall conform
to AVVA C -205 for shop application and AVVA C -602
for field application. Pipe materials shall be the
product of an organization which has had not less
than 5 years successful experience manufacturing
pipe materials and the design and manufacture of
the pipe, including all materials, shall be the
product of one company.
b. All surfaces except as noted in c and d below shall
receive shop application of mortar lining and
coating.
c. Field Welded Joints. After installation, clean,
line and coat unlined or uncoated ends adjacent to
welded field joints, including the veld proper, as
specified for pipe adjacent to the veld.
d. Machined Surfaces. Shop coat machined surfaces
with a rust preventative compound. After jointing
surfaces, remaining exposed surfaces shall be
coated per a and b above.
Page 28 Pipe
(o) Corrugated Metal Pipe
1. General
Pipe shall be corrugated continuous lock or welded seam
helically corrugated pipe. Corrugated metal pipe may be
galvanized steel, aluminized steel or aluminum
conforming to the following:
Galvanized Steel AASHTO M 218
Aluminized Steel AASHTO M 274
Aluminum AASHTO M 197
where reference is made herein to gage of metal, the
reference is to U.S. Standard Gage for uncoated sheets.
Tables in AASHTO M 218 and AASHTO M 274 list thicknesses
for coated sheets in inches. The Tables in AASHTO H 197
list thicknesses in inches for clad aluminum sheets.
Sampling and testing of metal sheets and coils used for
corrugated metal pipe shall be in accordance with SDHPT
Test Method Tex - 708 -I.
Damaged spelter coating shall be repaired by thoroughly
vire brushing the damaged area and removing all loose,
cracked or veld burned spelter coating. The cleaned
area shall be painted 'with a zinc dust -zinc oxide paint
conforming to Federal Specifications TT -P 641b. Damaged
pipe shall be rejected and removed from the project.
Damaged aluminized coating shall be repaired in
accordance with the manufacturer's recommendations.
The following information shall be clearly marked on
each section of pipe:
Thickness and corrugations
Trade Hark of the manufacturer
Specification compliance
2. Fabrication
a. Steel Pipe
Galvanized or aluminized steel pipe shall be full
circle or arch pipe conforming to AASHTO M 36, Type
I or Type II as indicated.
It may be fabricated with circumferential
corrugations, lap joint construction with riveted
or spot welded seams or it may be fabricated with
helical corrugations with continuous helical lock
510 06/09/88 Page 29 Pipe
P
seam or ultra high frequency resistance butt - velded
seams.
b. Aluminum Pipe
Pipe shall conform to AASHTO M 196, Type I,
circular pipe or Type II, pipe arch as indicated.
It may be fabricated with circumferential
corrugations, lap joint construction with riveted
or spot welded seams or it may be fabricated with
helical corrugations with a continuous helical lock
seam.
Portions of aluminum pipe that are to be in contact
with high chloride concrete or metal other than
aluminum, shall be insulated from these materials
by a coating of bituminous material. The coating
applied to the pipe or pipe arch to provide an
insulation between the aluminum and other material
shall extend a minimum distance of 1 foot beyond
the area of contact.
3. Selection of Gages
The pipe diameter, permissible corrugations and required
gauges shall be as indicated.
510 06/09/118 Page 30 Pipe
510
TABLE I
Corrugated Steel
2 2/3 inches by 1/2 inch Corrugations
Pull Circle Pipe
Minimum
Cover, Thickness
Top of
Pipe to
Pipe Top of 0.064 In. 0.079 In. 0.109 In. 0.138 In. 0.168 In.
Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage
Inches Maximum Fill 8eight Above Top of Pipe in Feet *
12 12 112 122 157 164 171
15 12 90 97 125 131 137
18 12 75 81 104 109 114
21 12 64 70 82 94 98
24 12 56 60 69 78 86
27 12 50 54 60 67 73
30 12 49 51 55 59 65
33 12 41 44 52 55 59
36 12 37 41 49 52 55
42 12 41 45(57) 46(90) 49(94) 50(98)
48 12 43(50) 44(78) 46(82) 47(86)
54 12 - 43 43(70) 44(73) 45(76)
-60 12 - 43(63) 43(66) 44(69)
66 12 - - - 43(60) 43(62)
72 12 - - 43(55) 43(57)
78 12 - - 42(53)
84 12 - - - - 42(49)
Fill heights in ( ) apply when pipe is 5 percent vertically
longated prior to installation.
Note: Thickness in inches, as shown above, refers to the coated
metal after galvanizing.
06/09/88 Page 31
Pipe
The line in the gage columns is drawn below the maximum
diameter allowed for that gage.
Table II
Corrugated Steel
3 inches x 1 inch or 5 inches x 1 inch
Full Circle Pipe
Minimum
Cover, Thickness
Top of
Pipe to
Pipe Top of 0.064 In. 0.879 In. 0.109 In. 0.138 In. 0.168 In.
Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage
Inches Maximum Pill Height Above Top of Pipe in Feet *
48 12 48 52(60) 56(89) 61(107) 60(118)
54 12 43 48(53) 52(79) 55(95) 58(105)
60 12 38 46(48) 49(71) 51(85) 53(95)
66 12 35 43 47(65) 48(78) 50(86)
72 12 32 40 45(59) 47(71) 48(79)
78 12 29 36 44(54) 45(66) 46(73)
84 12 34 43(51) 44(61) 45(68)
90 12 - 32 43 44(57) 44(63)
96 12 - 30 43 43(53) 44(59)
102 24 - 28 42 43(50) 43(56)
108 24 - - 39 42 43(53)
114 24 - - 37 42 42(50)
120 24 - - 35 42 42
* Fill heights in ( ) apply when pipe is 5 percent vertically
elongated prior to installation.
Note: Thickness in inches, as shown above, refers to the coated
metal after galvanizing.
The line in the gage columns is drawn below the maximum
diameter allowed for that gage.
510 06/09/88 Page 32 Pipe
510
Table III
Corrugated Aluminum
2 2/3 inches x 1/2 inch Corrugations
Full Circle Pipe
Minimum
Cover, Thickness
Top of
Pipe to
Pipe Top of 0.060 In. 0.075 In. 0.105 In. 0.135 In. 0.164 In.
Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage
Inches Maximum Fill Height, Above Top of Pipe in Feet *
12 12 45 45 77 - -
15 12 36 37 56 -
18 12 28 30 36 43 49
24 12 22 23 25 28 31
27 12 20 21 23 25 27
30 12 18 18 21 23 24
33 12 16 17 20 21 22
36 12 - 15 19 20 21
42 12 - 19 19 20
48 15 - - 18 18 19
54 16 - - 17 18 18
60 16 - - - 16 18
66 18 - - 12 15
72 20 - - 18 11
78 20 - - - 9
84 20 - - 7
* Fill heights in ( ) apply when pipe is 5 percent vertically
elongated prior to installation.
Note: Thickness in inches, as shown above, refers to the clad
sheet.
The line in the gage columns is drawn below the maximum
diameter alloyed for that gage.
06/09/88 Page 33
Pipe
510
Table IV
Corrugated Aluminum
3 inches x 1 inch or 6 inches x 1 inch Corrugations
Pull Circle Pipe
Minimum
Cover, Thickness
Top of
Pipe to
Pipe Top of 0.060 In. 0.075 In. 0.105 In. 0.135 In. 0.164 In.
Diameter Subgrade 16 Gage 14 Gage 12 Gage 10 Gage 8 Gage
Inches Maximum Pill Height Above Top of Pipe in Peet *
30 12 27 30 35 41 46
36 12 23 24 28 30 34
42 14 21 22 24 26
28
48 16 20 20 22 23 24
54 18 19 19 20 21 22
60 20 18 19 20 20 21
66 22 - 18 19 19 20
72 24 - 17 19 19 19
78 26 - - 18 18 19
84 26 - 15 18 18
90 24 - _ 16 18
96 24 14 16
102 30
— - 14
108 30 _
12
114 30
10
120 30 _
06/09/88 Page 34
8
* Fill heights in ( ) apply when pipe is 5 percent vertically
elongated prior to installation.
Note: Thickness in inches, as shown above, refers to the clad
sheet.
The line in the gage columns is drawn below the maximum
diameter allowed for that gage.
Pipe
510
For pipe arch, rtie design size and permissible
corrugations only will be indicated, since the shape
and minimum gage for pipe arch 'shall be as designated
in Tables A, 8, C or D for the specified design size
and corrugation for metal pipe.
Table A
Steel Pipe Arch
2 2/3 Inch by 1/2 Inch Corrugations
H - Loading
Equivalent
Min. Min. Coated Diameter
Design *Span *Rise Cover Gage Thickness Full Cir.
Size Inches Inches Inches Required Inches Pipe Inches
1 17 13 12 16 0.064 15
2 21 15 12 16 0.064 18
3 28 20 12 16 0.064 24
4 35 24 12 16 - 0.064 30
5 42 29 12 14 0.079 36
6 49 33 12 14 0.079 42
7 57 38 12 12 0.109 48
8 64 43 12 12 0.109 54
9 71 47 12 10 0.138 60
* The fill heights for all sizes of pipe arch are limited to a
maximum of 7 feet.
A tolerance of plus or minus 1 inch or 2 percent of equivalent
circular diameter, whichever is greater, will be permissible in
span and rise, with all dimensions measured from the inside crests
of the corrugations.
Table B
Steel Pipe Arch
3 Inch by 1 Inch Corrugations
H -20 Loading
Min. Min. Coated Diameter
nt
Design *Span *Rise Cover Gage Thickness Pull Cir.
Size Inches Inches Inches Required Inches Pipe Inches
7 53 41 12 12 0.109 48
8 60 46 12 12 0.109 54
9 66 51 12 12 0.109 60
10 73 55 12 12 0.109 66
11 81 59 12 12 0.109 72
12 87 63 12 12 0.109 78
13 95 67 12 12 0.109 84
14 103 71 18 12 0.109 90
15 112 75 18 12 0.109 96
16 117 79 18 12 0.109 102
17 128 83 24 12 0.109 108
18 137 87 24 10 0.138 114
19 142 91 24 10 0.138 210
06/09/88 Page 35 Pipe
510
* The fill heights for all sizes of pipe arch are limited to a
maximum of 10 feet.
A tolerance of plus or minus 1 inch or 2 percent of equivalent
circular diameter, whichever is greater, will be permissible in
span and rise, with all dimensions measured from the inside crests
of the corrugations.
Table C
Steel Pipe Arch
5 Inch by 1 Inch Corrugations
H -20 Loading
Equivalent
Min. Min. Coated Diameter
Design
Size Inches *Rise Cover Gage Inches Required Thickness Pipe Inches
11 81 59 12 12 0.109 72
12 87 63 12 12 0.109 78
13 95 67 12 12 0.109 84
14 103 71 18 12 0.109 90
15 112 75 18 12 0.109 96
16 117 79 18 12 0.109 102
1 7 128 83 24 10 0.138
108
18 137 87 24 10 0.138 114
19 142
91 24 10 0.138 120
* The fill heights for all sizes of pipe arch are limited to a
maximum of 10 feet.
A tolerance of plus or minus 1 inch or 2 percent of equivalent
circular diameter, whichever is greater, will be permissible in
span and rise, with all dimensions measured from the inside crests
of the corrugations.
Table D
Aluminum Pipe Arch.
2 2/3 Inch by 1/2 Inch Corrugations
8 Loading
Equivalent
Min. Min. Coated Diameter
Design *Span *Rise Cover Gage Thickness Full Cir.
Size Inches Inches Inches Required Inches Pipe Inches
1 17 13 12 16 0.060 15
2 21 15 12 16 0.060 18
3 28 20 12 14 0.075 24
4 35 24 12 14 0.075 30
5 42 2 9 18 12 0.105 36
6 49 33 18 12 0.105 42
7 57 38 18 10 0.135 48
8 64 4 3 18 10 0.135 54
9 71 47 18 8 0.164 60
06/09/88 Page 36. Pipe
P
* A11 dimensions are measured from the inside crests of the
corrugations. A tolerance of plus or minus 1 inch or 2 percent of
the equivalent circular diameter, whichever is greater will be
permissible in span and rise.
The fill heights for all sizes of pipe arch are limited to a
maximum of 7 feet.
4. Joint Material
Except as otherwise indicated, coupling bands and other
hardware for galvanized or aluminized steel pipe shall
conform to AAS8T0 H 36 for steel pipe and AAS8TO M 196
for aluminum pipe. Field joints for each type of
corrugated metal pipe shall maintain pipe alignment
during construction and prevent infiltration of soil
material during the life of the installation.
Coupling bands shall be not more than 3 nominal sheet
thicknesses lighter than the thickness of the pipe to be
connected and in no case lighter than 0.052 inch for
steel or 0.048 inch for aluminum.
Coupling bands shall be made of the same base metal and
coating (metallic or otherwise) as the pipe.
Coupling bands shall lap equally on each of the pipes
being connected to form a tightly closed joint after
installation.
Pipes furnished with circumferential corrugations shall
be field jointed with corrugated locking bands. This
includes pipe vith helical corrugations which has
reformed circumferential corrugations on the ends. The
locking bands shall securely fit into at least one full
circumferential corrugation on each of the pipe ends
being coupled. The minimum width of the corrugated
locking bands shall be as shown below for the
corrugation which corresponds to the end circumferential
corrugations on the pipes being joined:
10 1/2 inches vide for 2 2/3 inches x 1/2 inch
corrugations.
12 inches vide for 3 inches x 1 inch or 5 inches
x 1 inch corrugations.
Helical pipe without circumferential end corrugations
will be permitted only when it is necessary to join a
new pipe to an existing pipe which vas installed with no
circumferential end corrugations. In this event pipe
furnished with helical corrugations at the ends shall be
field jointed with either helically corrugated bands or
510 06/09/88 Page 37 Pipe
510
with bands with projections or dimples. The minimum
width of helically corrugated bands shall conform to the
following:
12 inches wide for pipe diameters up to and
including 72 inches.
14 inches wide for 1 inch deep helical end
corrugations.
Bands with projections shall have circumferential rows
of projections with one projection for each corrugation.
The width of bands with projections shall be not less
than the following:
12 inches wide for pipe diameters up to and
including 72 inches.
The bands shall have 2 circumferential rows of
projections.
16 1/4 inches wide for pipe diameters of 78 inches
and greater. The bands shall have 4
circumferential rows of projections.
Unless otherwise indicated, all bolts for coupling bands
shall be 1/2 inch diameter. Bands 12 inches wide or
less will have a minimum of 2 bolts and bands greater
than 12 inches vide shall have a minimum of 3 bolts.
Galvanized bolts may be hot dip galvanized conforming to
AASHTO M 232, mechanically galvanized to provide the
same requirements as AASHTO M 232 or electrogalvanized
per ASTM A 164 Type RS.
5. Additional Coatings or Linings
a. Bituminous Coated
Bituminous Coated pipe or pipe arch shall be as
indicated both as to base metal and fabrication and
in addition shall be coated inside and out with a
bituminous coating which shall meet the performance
requirements set forth herein. The bituminous
coating shall be 99.5 percent soluble in carbon
bisulphide. The pipe shall be uniformly coated
inside and out to a minimum thickness of 0.05 inch,
measured on the crests of the corrugations.
The bituminous coating shall adhere to the metal
tenaciously, shall not chip off in handling and
shall protect the pipe from deterioration as
evidenced by samples prepared from the coating
06/09/88 Page 38 Pipe
P
510
material successfully meeting the Shock Test and
Flow Test in accordance with Test Method Tex - 522 -C.
b. Paved Invert
tihere a Paved Invert is indicated, the pipe or pipe
arch, in addition to the fully coated treatment
described above, shall receive additional
bituminous material of the same specification as
above, applied to the bottom quarter of the
circumference to for a smooth pavement with a
minimum thickness of 1/8 inch above the crests of
the corrugations.
c. Cement Lined
(1) General
Except as modified herein, pipe shall conform
to AASHTO M 36 for lock seam or welded
helically corrugated steel pipe. Pipe shall
be of full circle and shall be fabricated with
two annular corrugations for purposes of
joining pipes together with band couplers.
Lock seams shall develop the seam strength as
required in Table 3 of AASHTO M 36. Concrete
lining shall conform to the following:
Composition
Concrete for the lining shall be composed
of cement, fine aggregate and water that
are well mixed and of such consistency as
to produce a dense, homogenous,
nonsegregated lining.
Cement
Portland Cement shall conform to AASHTO M
85.
Aggregates shall conform to AASHTO M 6
except that the requirements for
gradation and uniformity of gradation
shall not apply.
Mixture
The aggregates shall be sized, graded,
proportioned and thoroughly mixed with
such proportions of cement and eater as
will produce a homogenous concrete
mixture of such quality that the pipe
will conform to the design requirements
06/09/88 Page 39 Pipe
P
510
indicated. In no case, however, shall
the proportions of Portland Cement,
blended cement or Portland Cement plus
pozzolanic admixture be less than 470
lb /cu. yd of concrete.
Thickness
The lining shall have a minimum thickness
of 1/8 inch above the crest of the
corrugations.
Lining Procedures
The lining shall be plant applied by a
machine traveling through a stationary
pipe. The rate of travel of the machine
and the rate of concrete placement shall
be mechanically regulated so as to
produce a homogenous nonsegregated lining
throughout.
Surface Finish
The lining machine shall also
mechanically trovel the concrete lining
as the unit moves through the pipe.
Certification
Furnish manufacturer's standard
certification of compliance upon request
of the purchaser.
Joints
Pipe shall be joined together vith
coupling bands made from steel sheets to
an in :icated thickness of 0.064 inch (12
ga.). Coupling bands shall be formed
with two corrugations that are spaced to
provide seating in the third corrugation
of each pipe end vithout creating more
than 1/2 inch ± annular space between
pipe ends vhen joined together.
Bands shall be drawn together by two 1/2
inch galvanized bolts through the use of
a bar and strap suitably welded to the
band.
When 0 -ring gaskets are indicated they
shall be placed in the first corrugation
of each pipe and shall be compressed by
06/09/88 Page 40
Pipe
1 .
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
(2)
d. Fiber Bonded
tighrpning the coupling hand. Rubber
O -ring gaskets shall conform to Section
5.9, ASTM C 361.
Causes for Rejection
Pipe shall be subject to rejection on account
of failure to conform to any of the
indications. Individual sections of pipe may
be rejected because of any of the following:
Damaged ends, where such damage would
prevent making satisfactory joint.
Defects that indicate poor workmanship
and could not be easily repaired in the
field.
Severe dents or bends in he metal
itself.
If concrete lining is broken out, pipe
may be rejected or at the discretion of
the Engineer, repaired in the field in
accordance with the manufacturer's
recommendation. Hairline cracks or
contraction cracks in the concrete lining
is to be expected and does not constitute
cause for rejection.
Vhere fiber bonded pipe is indicated, the pipe or
pipe arch shall be formed from sheets vhose base
metal shall be as indicated. In addition, the
sheets shall have been coated with a layer of
fibers, applied in sheet form by pressing them into
a molten metallic bonding. If a paved invert is
indicated it shall be in accordance with the
procedure outlined above. The test for spelter
coating above is waived for fiber bonded pipe.
6. Slotted Drain Storm Severs
The pipes for the slotted drain and slotted drain
outfall shall be helically corrugated, lock seam or
welded seam pipe. Materials and fabrication shall be in
accordance with the above. The metal thickness shall be
a minimum 16 gage.
The chimney assemblies shall be constructed of 3/16 inch
welded plate or machine formed 14 gage galvanized steel
sheets. The height of the chimney required will be as
indicated. Metal for the welded plate slot shall meet
06/09/88 Page 41 Pipe
P
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510 06/09/88
Veld areas and the heat affected zones where the slot is
welded to the corrugated pipe shall be thoroughly
cleaned and painted vith a good quality asphalt base
aluminum paint.
7. Mortar
the requirements of ASTM A 36 and the completed plate
slot shall be galvanized after fabrication in accordance
vith ASTM A 123.
Mortar shall be composed of 1 part Type I Portland
Cement and 2 parts clean, sharp mortar sand suitably
graded for the purpose and conforming in other respects
to the provisions for fine aggregate of Item No. 403,
"Concrete
maybeeaddedrtotthet mix, butHinrnoecasemshallliteexceed
10 percent by weight of the total dry mix.
(p) Vitrified Clay Pipe
Vitrified Clay Pipe shall conform to ASTM C 700, extra
strength clay pipe. The joint material for vitrified clay
pipe shall conform to ASTM C 425 compression joints for
vitrified clay bell and spigot pipe.
510.3 Construction Methods
(1) General
Prior to commencing this work, all erosion control and tree
protection measures required shall be in place and all utilities
located and protected as sec forth in "General Conditions of
Agreement ". Clearing the site shall conform to Item No. 102,
"Clearing and Grubbing ". Maintenance of environmental quality
protection shall comply with all requirements of "General
Conditions of Agreement" and Item No. 601, "Salvaging and Placing
Topsoil ".
The-Contractor shall conduct his work such that a reasonable
minimum of disturbance to existing utilities will result.
Particular care shall be exercised to avoid the cutting or
breakage of all existing utilities. If at any time the Contractor
damages the utilities in place through his operations, the
Contractor shall immediately notify the owner of the utility to
make the necessary repairs. When active wastewater sewer lines
are cut in the trenching operations, temporary flumes shall be
provided across the trench while open and the lines shall be
restored when the backfilling has progressed to the original
bedding lines of the sever so cut.
The Contractor shall inform utility owners sufficiently in advance
of the Contractor's operations to enable such utility owners to
reroute, provide temporary detours or to make other adjustments to
utility lines in order that the Contractor may proceed with his
Page 42
Pipe
work with a minimum of delay and expense. The Contractor shall
cooperate with all utility owners concerned in effecting any utility
adjustments necessary and shall not hold the City liable for any
expense due to delay or additional work because of conflicts arising
from existing utilities.
The Contractor shall do all trenching in accordance with the
provisions and the directions of the Engineer as to the amount of
trench left unfilled at any time. All excavation and backfilling
shall be accomplished as indicated and in compliance with State
Statutes.
Where excavation for a pipe line is required in an existing City
street, a street cut permit is required and control of traffic shall
be as indicated in accordance with the Texas Manual on Uniform
Traffic Control Devices.
Wherever existing utility branch connections, sewers, drains,
conduits, ducts, pipes or structures present obstructions to the
grade and alignment of the pipe, they shall be permanently
supported, removed, relocated or reconstructed by the Contractor
through cooperation with the owner of the utility, structure or
obstruction involved. In those instances where their relocation or
reconstruction is impractical, a deviation from line and grade will
be ordered by the Engineer and the change shall be made in the
manner directed. —
Adequate temporary support, protection and maintenance of all
underground and surface utility structures, drains, sewers and other
obstructions encountered in the progress of the work shall be
furnished by the Contractor, at his expense and as approved by the
Engineer.
Where traffic must cross open trenches, the Contractor shall provide
suitable bridges. For trenches less than 2 feet in width, sheet
steel plates having a minimum thickness of 1/2 inch shall be used.
For trenches up to 4 feet in width, sheet steel plates having a
minimum thickness of 3/4 inches shall be used. In all cases, the
plates shall overlay the top of the trench a minimum of 18 inches on
both sides and secured by asphalt. Adequate provisions shall be
made for the flow of sewers, drains and watercourses encountered
during construction and any structures which may have been disturbed
shall be satisfactorily restored upon completion of work.
When rainfall or runoff is occurring or is forecast by the U.S.
Weather Service, the Contractor shall not perform or attempt any
excavation or other earth moving work in or near the flood plain of
any stream or watercourse or on slopes subject to erosion or runoff,
unless given specific approval by the Engineer. When such
conditions delay the work, an extension of time for working day
contracts will be allowed in accordance with "General Conditions of
Agreement ".
510 06/09/88 Page 43 Pipe
1
t
1
1
1
1
1
1
1
1
i
1
1
1
1
(2) Water Line /New Wastewater Line Separation
Installation of new water or wastewater lines shall conform
to the following:
Where feasible, water and wastewater lines shall be no
closer to each other than 9 feet between outside diameters
in all directions and shall be in separate trenches.
If the 9 foot separation cannot be achieved, any portion
of a new gravity wastewater line within 9 feet in any
direction (between OD's) of a potable water line, shall be
in a separate trench and constructed of ductile iron
(thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated
PVC in sizes to 12 inch or AWWA C -905 (SDR -25) 165 psi
rated PVC in sizes larger than 12 inches.
If the lines are parallel, they shall not be closer than 4
feet horizontally or 2 feet vertically between OD's with
the wastewater lower than the water line. If the lines
cross, they may be no closer than 6 inches vertically
between OD's with the sewer below the water line and one
standard 20 foot length of ductile iron (thickness Class
50), AWWA C -900 (SDR -18) 150 psi rated PVC in sizes to 12
inch or AWVA C -905 (SDR -25) 165 psi rated PVC in sizes
larger than 12 inches.
Unless wastewater manholes and the connection to the sewer
can be made completely watertight and tested for no
leakage, they must be installed so as to provide a minimum
of 9 feet of horizontal clearance from an existing or
proposed water line.
All force mains shall be ductile iron pipe, of the class
indicated, Thickness Class 50 minimum.
(3) Utility and Storm Sewer Crossings
When the Contractor installs a pipe that crosses under a
utility structure or storm sewer and the top of the pipe is
within 18 inches of the bottom of the utility structure, the
pipe shall be encased as specified in Item
No. 505, "Concrete Encasement and Encasement Pipe ", for a
distance of at least 1 foot on either side of the ditch line
of the utility structure or the storm sewer. Unless
otherwise specified by the Engineer, concrete encasement will
not be required for ductile iron (thickness Class 50), AWWA
C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWWA
C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12
inches. When the Contractor installs a pipe that crosses
over a utility structure or storm sewer and the top of the
utility structure or storm sewer is within 18 inches of the
bottom of the pipe, the pipe shall be either ductile iron
(thickness Class 50), AWWA C -900 (SDR -18) 150 psi rated PVC
in sizes to 12 inch or AWWA C -905 (SDR -25) 165 psi rated PVC
in sizes larger than 12 inches, unless otherwise specified by
the Engineer.
Where trenches wider than 12 inches cross under existing
wastewater lines, the sewer lines shall be replaced with one
20 foot joint of ductile iron (thickness Class 50), AWWA
C -900 (SDR -18) 150 psi rated PVC in sizes to 12 inch or AWWA
C -905 (SDR -25) 165 psi rated PVC in sizes larger than 12
inches, centered over the trench.
510 05/24/91 Page 44 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
(4) Trench Excavation
Underground piped utilities to be constructed in an open cut in
accordance with Federal regulations, applicable State Statutes
conforming to Item Yo. 509, "Trench Safety Systems" and with a
trench width and depth described below. When pipe is to be
constructed in fill above the natural ground, Contractor to
construct embankment to an elevation not less than one foot above
tope of pipe, after which trench is excavated. Required vertical
sides shall be sheeted and braced as indicated to maintain the
sides of the required vertical excavation throughout the
construction period. Adequacy of the design of sheeting and
bracing shall be the responsibility of design professional.
Contractor shall be responsible for installation as indicated.
After the pipe has been laid and the backfill placed and compacted
to 12 inches above the top of the pipe, any sheeting, shoring and
bracing required may be removed with special care to insure that
the pipe is not disturbed. As each piece of sheeting is removed,
the space left by its removal must be thoroughly filled and
compacted with suitable material and provisions made to prevent
the sides of the trench from caving until the backfill has been
completed. Any sheeting left in place will not be paid for and
shall be considered subsidiary to the pipe item bid.
(5) Trench Width
Trenches for water and wastewater lines shall have a minimum vidth
of 6 inches and a maximum width of 1 foot on each side beyond the
outside surfaces of the pipe bell or coupling.
Trenches for Storm Sewers up co 42 inches shall have a width of 1
foot on each side beyond the outside surfaces of the pipe. Pipes
more than 42 inches shall have a trench width not to exceed 18
inches on each side beyond the outside surfaces of the pipe.
If trench width within the pipe zone exceeds this maximum, the
entire pipe zone shall be refilled with approved backfill
material, thoroughly compacted to a minimum of 95 percent of
maximum density as determined by SDHPT Test Method Tex -114_E and
then re- excavated to the proper grade and dimensions. Excavation
along curves and bends shall be so oriented that the trench and
pipe are approximately centered on the centerline of the curve,
using short lengths of pipe and /or bend fittings if necessary.
For all utilities co be constructed in fill above natural ground,
the embankment shall first be constructed to an elevation• not less
than 1 foot above the top of the utility, after which excavation
for the utility shall be made.
(6) Trench Depth and Depth of Cover
All pipe and in -line appurtenances shall be laid to the grades
indicated. The depth of cover shall be measured from the
established finish grade, natural ground surface, subgrade for
06/09/88 Page 45
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
staged construction, street or other permanent surface to the top
or uppermost projection of the pipe.
(a) Where not otherwise indicated, all water piping shall be laid
to the following minimum depths:
1. Water piping installed in undisturbed ground in
easements of undeveloped areas which are not within
existing or planned streets, roads or other traffic
areas shall be laid with at least 36 inches of cover.
2. Water piping installed in existing streets, roads or
other traffic areas shall be laid with at least 48
inches of cover below finish grade.
3. Unless approved by the Engineer, installation of water
piping in proposed new streets will not be permitted
until paving and drainage plans have been approved and
the roadway traffic areas excavated to the specified or
standard paving subgrade, with all parkways and sidewalk
areas graded according to any applicable provisions of
the drainage plans or sloped uniformly from the curb
line to the right of way line. Piping and appurtenances
installed in such proposed streets shall be laid with at
least 36 inches of cover below the actual subgrade.
(b) Where not otherwise indicated, all wastewater piping shall be
laid to the following minimum depths:
1. Wastewater piping installed in natural ground in
easements or other undeveloped areas which are not
within existing or planned streets, roads or other
traffic areas shall be laid with at least 42 inches of
cover.
2. Wastewater piping installed in existing streets, roads
or other traffic areas shall be laid with at least 66
inches of cover.
3. Wastewater piping installed in such proposed streets
shall be laid with at least 48 inches of cover below the
actual subgrade.
(7) Classification of Excavation
Excavation will not be considered or paid for as a separate item
of work, so excavated material vill not be classified as to type
or measured as to quantity. Full payment for all excavation
required for the construction shall be included in the various
unit or lump sum contract prices for the various items of work
installed, complete in place. No extra compensation, special
treatment or other consideration will be allowed due to rock,
pavement, caving, sheeting and bracing, falling or rising water,
06/09/88 Page 46
Pipe
1
1 -
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
(9)
working under and in the proximity of trees or any other handicaps
to excavation.
(8) Devatering Excavation
Underground piped utilities shall not be constructed or the pipe
laid in the presence of water. All water shall be removed from
the excavation prior to the pipe placing operation to insure a dry
firm granular bed on which to place the underground piped
utilities and shall be maintained in such unwatered condition
until all concrete and mortar is set. Removal of water may be
accomplished by bailing, pumping or by a well -point installation
as conditions - :arrant.
In the event that the excavation cannot be dewatered to the point
where the pipe bedding is free of mud, a seal shall be used in the
bottom of the excavation. Such seal shall consist of Class B
concrete, conforming to Item No. 403, "Concrete for Structures ",
with a minimum depth of 3 inches.
Trench Conditions
Before attempting to lay pipe, all water, slush, debris, loose
material, etc., encountered in the trench must be pumped or bailed
out and the trench must be kept clean and dry while the pipe is
laid and backfilled. Where needed, sump pits shall be dug
adjoining the trench and pumped as necessary to keep the
excavation devatered.
Backfilling shall closely follow pipe laying so that no pipe is
left exposed and unattended after initial assembly. All open
ends, outlets or other openings in the pipe shall be protected
from damage and shall be properly plugged and blocked watertight
to prevent the entrance of trench water, dirt, etc. The interior
of the pipeline shall at all times be kept clean, dry and
unobstructed.
Where the soil encountered at established footing grade is a
quicksand, saturated or unstable material, the following procedure
shall be used unless other methods are indicated:
All unstable soils shay_ be removed to a depth of a minimum 2
feet below bottom of piped utility or as required to
stabilize the trench foundation. Such excavation shall be
carried out for the entire trench width.
All unstable soil so removed shall be replaced with a
concrete seal, foundation rock or coarse aggregate materials
placed across the entire trench width in uniform layers not
to exceed 6 inches, loose .measure and compacted by mechanical
tamping or other means which will provide a stable foundation
for the utility.
r)5/09/ 8p, Page 47
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
Forms, sheathing and bracing, pumping, additional excavation
and backfill required in unstable trench conditions shall be
subsidiary to pipe bid.
(10) Blasting
All blasting shall conform to the provisions of "General
Conditions of Agreement ".
(11) Removing Old Structures
When out of service masonry structures or foundations are
encountered in the excavation, such obstructions shall be removed
for the full width of the trench and to a depth of 1 foot belov
the bottom of the trench. When abandoned inlets or manholes are
encountered and no plan provision is made for adjustment or
connection to the new sewers, such manholes and inlets within the
construction limits shall be removed completely to a depth 1 foot
below the bottom of the trench. In each instance, the bottom of
the trench shall be restored to grade by backfilling and
compacting by the methods provided above. Where the trench cuts
through storm or vastevater severs which are known to be
abandoned, these sewers shall be cut flush with the sides of the
trench and blocked with a concrete plug in a manner satisfactory
to the Engineer. When old structures are encountered, vhich are
not visible from the existing surface and are still in service,
they shall be protected and adjusted as required to the finished
grade.
(12) Lines and Grades
Grades, lines and levels shall conform to Section No. 00341,
"Grades, Lines and Levels ". Any damage to the above by the
Contractor shall be re- established at the Contractor's expense.
The location of the lines and grades indicated may be changed only
by direction of the Engineer and it is understood that the
Contractor vill be paid on the basis of his unit contract prices
bid for such work actually performed and will make no claim for
damages or loss of anticipated profits due to the change of
location or grade.
The Contractor shall furnish, at his expense, all necessary batter
boards or electronic devices for controlling the work. Batter
boards shall be of adequate size material and shall be supported
substantially. The boards and all location stakes must be
protected from possible damage or change of location. The
Contractor shall furnish good, sound twilled lines for use in
achieving lines and grades and the necessary plummets and
graduated poles.
The Contractor shall submit to the Engineer at least 6 copies of
any layout plans from the pipe manufacturer for review and
approval. The Contractor shall submit the layout plans at least
06/09/88 Page 48
Pipe
USE/PIPE MATERIAL
CEMENT
STAB
B[CEIIL
SAID
PEA
GRAVEL
PIPE BEDDING SICKE
Uncrushed
Gravel
Crushed
Gravel
Crushed
Stone
WATERNELDED STEEL
x
X
VATER/PILMIllt
X
X
WA'IIR/ALL OIffiRS UP 1O
15 INCH ID
x
x
x
x
x
VA'IIR/ALL OTHERS LARGER
THAN 15BXHID
x
x
x
x
WASTEWATER/ ALL UP TO
15IIJ_1ID
X
X
X
X
X
WASIEWATER/ALL LARGER
THAN 15DU ID
X
X
X
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 510
1
30 days in advance of any actual construction of the project. The E ngineer will forward
all comments of the review to the Contractor for revision. Revisions shall be made and
forwarded to the Engineer for his acceptance. Prior to commencement of the Project,
reviewed layout plans will be sent to the Contractor marked for construction.
Should the Contractor's procedures not produce a finished pipe placed to grade and
alignment, the pipe shall be removed and relayed and the Contractors procedures modified
to the satisfaction of the Engineer. NO additional compensation shall be paid for the
removal and relaying of pipe required above.
(13) Sirplis Excavated materials: Excess material or material which cannot be node suitable
for use in enbanknaits will be declared surplus by the Engineer and shall became the
property of the Contractor to dispose of off site at a permitted fill site, without injury
to the City or any individual. Such surplus material shall be removed from the cork site
promptly following the completion of the portion of the utility involved.
(14) Pipe Bedding Envelope: Pipe shall be installed in a continuous bedding envelope. The
envelope shall extend for the full trench width to a depth of 6 inches below the pipe.
The envelope shall rise to springline of stormwater pipe and to 12 inches above water and
wastewater pipe.
The following requirements and limitations shall govern bedding material selection. The
compatibility of the bedding envelope with the excavated and backfill materials shall be
ensured to minimize particle migration into pea gravel and pipe bedding stone envelopes.
Measures taken to minimize migration shall be subsidiary to the pipe, unless specifically
provided by the bid items, for pipe with sand as an approved bedding material. Specific
measures for other pipes shall be as agreed upon by change order unless otherwise provided
by the contract.
(a) Standard Bedding Materials
SI7ATER/O0tErE
STCRMWATER/METAL
05/0L90
Page 49
X X
X j X X
X
X
Pipe
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(b) Requirements & Limitations
(1) Lnpervious cut -off walls of compacted clay or other approved methods shall be used to
isolate sand beddings from pea gravel or stone beddings
(2) Pea gravel or pipe bedding stone shall be used in blasted trenches.
(3) Crushed gravel or crushed stone shall not be used with polyethylene tubing or
polyethylene film wrap.
510 05/01/90
(4) Uncrushed gravel may be used with polyethylene film wrap in trenches up to 6 feet in
depth and in deeper trenches where ample trench width, a trenie, or other conditions
will allow controlled placement of the gravel without damaging the polyethylene wrap.
(5) Sand, alone, shall not be used in watercourses, in trenches where groundwater is
present, or in trenches with grades greater than 5 percent.
(6) Pea gravel and pipe bedding stone, alone, shall not be used in trenches with soils
prone to vibratory or hydraulic particle migration. Pea gravel or pipe beddirr stone
mixed with sand, stabilized backfill, filter fabric envelopment of the bedding
materials, or other approved materials or means shall be used wherever
non- cemaitatious, silty, or sandy soils as determined by the Engineer are encountered
with plasticity indices less than 20.
(7) Pea gravel and pipe bedding stone, alone, shall not be used in street right - of-way
within 5 feet of subgrade elevation in trenches 3 feet or wider.
(8) When pea gravel or pipe bedding stone is premixed with sand, a sufficient volume of
sand shall be used to fill all voids within the bedding envelope. The mixture shall
be mechanically compacted in place.
(9) Sand bedding envelopes shall be compacted to a minimum of ninety percent (909.') of the
density as determined in accordance with test method ASIM D 698.
(15) laying Pipe: No pipe shall be installed in the trench until excavation has been
completed, the bottom of the trench graded and the trench completed as indicated.
Laying of corrugated metal pipes on the prepared foundation shall be started at the outlet
ad with the separate sections firmly joined together, with outside laps of
circumferential joints pointing upstream and with longitudinal l ps on the sides Any
metal in joints which is not protected by galvanizing shall be coated with a suitable
asphaltum paint. Proper facilities shall be provided for hoisting and lowering the
sections of pipe into the trench without damaging the pipe or disturbing the prepared
Page 50 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
foundation and the sides of the trench. Any pipe which is not in
alignment or which shows any undue settlement after laying or is
damaged, shall be taken up and relaid without extra compensation.
Multiple installations of corrugated pipe or arches shall be laid
with the centerlines of individual barrels parallel. When not
otherwise indicated, clear distances of 2 feet between outer
surfaces of adjacent pipes shall be maintained.
No debris =hall remain in the drainvays or drainage structures.
All backfill in streets and under structures will be tested by the
City and must satisfy the specified density requirements
conforming to Section 00344, "Testing Laboratory Services" before
final acceptance )f or payment for the work.
All recommendations of the manufacturer shall be carefully
observed during handling and installation of each material.
Unless otherwise indicated, all materials shall be delivered to
the project by the manufacturer or" agent and unloaded as directed
by the Contractor. Each piece shall be placed facing the proper
direction near :o where it :ill be installed.
The interior of all pipe, fittings and other accessories shall be
kept free from dirt and foreign matter at all times and stored in
a manner that will protect them from damage. Stockpiled materials
shall be stacked so as to minimize entrance of foreign matter.
The interior of all pipeline components shall be clean, dry and
unobstructed -hen installed.
Piping materials shall not be skidded or rolled against other
pipe, etc. and under no circumstances shall pipe, fittings or
other accessories be dropped or jolted.
During handling and placement, materials shall be carefully
observed and inspected and any damaged, defective or unsound
materials shall be marked, rejected and removed from the job site.
Minor damage shall be marked and repaired in a manner satisfactory
tc the Engineer. Joints which have been placed but not joined,
backfilled, etc., shall be protected in a manner satisfactory to
the Engineer.
(16) Assembling of Pipe
Angular spacing of all joints shall meet the manufacturer's
recommendations for the pipe and accessories being used. Side
outlets shall be rotated so that the operating stems of valves
will be vertical when the valves are installed. Pressure pipe
shall be laid with bell ends Facing the direction of pipe
installation. Pipe end bells shall be placed upgrade for all
wastewater lines.
06/09/88 Page 51
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Orientation marks, when applicable, shall be in their proper
position before pipe is seated.
Before joining any pipe, all foreign matter, lumps, blisters,
excess coal tar coating, oil or grease shall be removed from the
ends of each pipe and the pipe ends shall then be wire brushed and
wiped clean and dry. Pipe ends shall be kept clean until joints
are made.
Every precaution shall be taken to prevent foreign material from
entering the pipe during installation. No debris, tools, clothing
or other materials shall be placed in the pipe.
(17) Joints
(a) Mortar
Pipe ends shall be clean, free of asphalt or other
contaminants which will inhibit the bond of the mortar to the
pipe. The pipe ends shall be moistened immediately prior to
placing the mortar in the joint.
(b) Cold Applied Preformed Plastic Gaskets
The pipe ends shall be clean and the joint material applied
to the dry pipe. In cold weather, the joint material shall
be heated to facilitate the seal of the joint.
(c) 0 - Ring
Just before making a joint the ends of the pipe shall be
clean, dry, free of any foreign matter, lump blisters,
excessive coal tar coating and grease or oil and shall be
wire brushed. The gasket and the inside surface of the bell
shall be lubricated with a light film of soft vegetable soap
compound to facilitate assembly of the joint. The rubber
gasket shall be stretched uniformly as it is placed in the
spigot groove to insure a uniform volume of rubber around the
circumference of the groove. The spigot shall be centered in
the bell, the pipe pushed home uniformly and brought into
true alignment. Bedding material shall be placed and tamped
against pipe to secure the joint.
(d) Push -on Joints
Just before making a joint, the bell and spigot rings shall
be clean and dry. The gasket and the inside surface of the
bell shall be lubricated with a light film of soft vegetable
soap compound (Flax Soap) to facilitate telescoping the
joints. The rubber gasket if not factory installed shall be
stretched uniformly as it is placed in the spigot groove to
insure a uniform volume of rubber around the circumference
of the groove. The spigot shall be centered in the bell, the
pipe pushed home and brought into true alignment. It shall be
510 06/09/88 Page 52 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
secured • - ere :. n oecdinq material vhicn is carefully
under and m
on each side o: e tamped
hoe. Care should oe taken to
prevent d`.:t or foreign • - entering tae _Dirt space.
(e) 3olted Joints
All flarced. , .,e__a:.-_: or other Doi :ad joints shall be
joir.ec - n h
high nuts , :: • 'oh cf hig strength, low alloy,
Y, -
re::: an: _c.._nless steel or be coated as
a =c.e ii Iron :.pea
(f) Sc .•e --- - For olumSir.a - :pe.
(18) Press':_.. PiLa -aging
(a) 't:` --, ..:,hare:. -- Cy Pipe (CSC) and Welded Steel
Aggregate cement, _ 57.11_ -_ a_ indicated in
"Mortar"
herein __
. _ -doss between the bell and
c: the , c' and contained by a joint
w t - cJer =ce :ea::-meaaan by the pipe manufacturer. The
wrapper s`.eii have a minimum width cf 7 inches for 30 inch
and s maller and 9 inches for larger pipe, secured
to the pipe by "3and Iron' steel straps. The grout shall be
poured in one continuous cperaticn in such manner that after
shrinkage and curing the joint recess .i11 be completely
filled.
Mortar for :ne inside recess s' be of consistent of
pia ^ter. The inside races; between the bell and spigot shall
be filled 'wit: mortar after the pipe joint on either side of
the recess has been backfilied and well tamped with no less
than one pipe joint installed ahead of the pipe forming the
re -less. The mortar shall completely fi :1 the recess and
shall be trowelled and packed into place and finished off
s-ooch *with the irsid- ,f :he p
The Contra =to- ;!ail - - - tint aft the r ae mortar has
sec and make repairs of any pocl'ets, crac r c. other
defects
caused by shrinkage to the satisfaction of the Engineer. The
inside surface shall ;.e c_ea :ed of any mortar droppings,
cement, eater, slurry, etc., before they have become set and
shall be cleared of any o :her tcreign ratter. The inside
surface of the pipe shall be left clean and smooth.
Pipe shall be handled at all times with ride nonabrassive
slings, belts or other equipment designed to prevent damage
to the coating and all zu ^h ee.ipr.ent shall be kept in such
repair that Its •_J•• use is not injurious to the
Coating. The use of ton
q ^, bare pinch-oars, chain slings,
rope slings vt:hou; ranvaf .0 'e ;s. _anvis or composition belt
510 06/09/38 ". Pipe .p e
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 .
1
1
1
1
010
slings with protruding rivets, pipe hooks without proper
padding or any other handling equipment which the Engineer
deems to be injurious to the coating shall not be permitted.
The spacing of pipe supports required to handle
pipe shall be adequate to prevent cracking or damage to the
he
cement mortar lining.
(19) Placing Pipe in Tunnels
Piping installed as a carrier pipe in a tunnel, encasement pipe,
etc., shall have uniform alignment, grade, bearing and conform to
the reviewed shop drawings. All necessary skid blocks, rails,
bedding material, grout cradle or paving, bracing, blocking, etc.,
as stipulated by the Contract or as may be required to provide and
maintain the required pipe alignment and grade, shall be provided
by the Contractor at no cost except as provided by the Bid Items.
This shall include at least 1 scree -type hold down jack per joint
of pipe to prevent flotation of the pipe, unless otherwise
indicated. Such carrier piping shall have flexible bolted or
gasketed push -on joints or Concrete Steel Cylinder pipe installed
as follows:
(a) 21 Inch Pipe and Smaller
Prior to placing the pipe in the tunnel, the inside
joint recess at the bell shall be buttered with cement
mortar.
After the joint is engaged, the excess mortar shall be
smoothed by pulling a tight fitting swab through the
joint. The pipe joints shall then be welded rigid by
placing 3 segments of veld, having a minimum length of 9
inches each and equally spaced around the joint. Cement
mortar protection shall then be placed in the normal
manner to the exterior of the joint and allowed to
harden sufficiently to avoid dislodgement during
installation. If time is of the essence, a quick
setting compound may be used.
(b) 24 Inch Pipe and Larger
Each length of pipe shall be pushed into the tunnel as
single units. A flexible mastic sealer shall be applied
to the exterior of the joint prior to joint engagement.
The surfaces receiving the mastic sealer shall be
cleaned and primed in accordance with the manufacturer's
recommendation. Sufficient quantities of the mastic
sealer shall be applied to assure complete protection of
all steel in the joint area. The interior of the joint
shall be filled with cement mortar in the normal manner
after the pipe is in its final position within the
tunnel.
06/09/88 Page 54
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
(20) Temporary Pipe Plugs, Caps, Bulkheads and Trench Caps
Temporary plugs, caps or plywood bulkheads shall be installed to
close all openings of the pipe and fittings when pipeline
construction is not in progress.
Standard plugs shall be inserted into the bells of all dead ends
of pipes, tees or crosses and spigot ends shall be capped. All
end plugs or caps shall be secured to the pipe as provided under
Item No. 507, "Bulkheads ".
Trench caps shall be reinforced Class D concrete as indicated.
(21) Corrosion Control
(a) Protective Covering
Unless otherwise indicated, all flanges, nuts, bolts,
threaded outlets and all other iron or steel components
buried and in contact with earth or backfill shall be wrapped
with 8 -mil (minimum) polyethylene film meeting ANSI /AVVA
C -105 to provide a continuous wrap.
(b) Corrosion ;'onitoring System
1. ' If indicated the corrosion monitoring system shall be
furnished and installed to meet the following
requirements:
a. Bonds shall be provided between steel cylinders of
adjacent pipe sections and all noninsulating joints
as necessary to assure electrical continuity except
where electrical isolation is required. The joint
bonds shall be designed:
(1) with sufficient slack to allow for a total
joint displacement of 1/2 inch.
(2) Using insulated copper cable metallurgically
bonded to adjacent cylinders. All bare copper
and steel at the connection shall be insulated
by an approved means.
b. Intermediate bonds for the prestress vire of
embedded cylinder prestressed concrete pipe shall
also be provided as required to minimize
attenuation. The intermediate bonds shall be in
the form of steel straps, embedded in the outer
surface of the concrete core directly upon which
the prestress wire is tightly wound. The size and
number of straps shall be designed to provide
uniform current distribution to all embedded
metallic surfaces of the pipe.
06/09/88 Page 55
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
c. Electrical isolarinn in the form of either flexible
or rigid insulating fittings as specified herein
shall be provided as required to obtain electrical
discontinuity.
d. Flexible insulating fittings required shall be
style 39 insulating couplings as manufactured by
Dresser Industries, 41 Fisher Avenue, Bradford, PA
16701 or equal.
e. Rigid insulating fittings required shall be
insulated vith fullface gaskets and combination
bolt sleeves and washers for flanges as
manufactured by Central Plastics Co., P.O. Box 762,
Shawnee, OK 74801 or equal.
f. Corrosion test stations shall be installed on the
pipeline at:
(1) All buried line crossings.
(2) The beginning and end of the portions of the
• pipeline to be monitored.
a. Both sides of insulating fittings.
b. Intermediate locations along the line,
such that the test stations are no more
than 1,000 feet apart.
c. For the embedded cylinder prestressed
concrete pipe alternative, test stations,
with wires originating at the prestress
wire at the midpoint of the pipelaying
length at the above locations, shall also
be provided.
g. Test stations shall be of the two -vire type with
one of the vire being sized (No. 6 AVG or larger)
such that it can be used for bonding. The other
vire, for determining pipe -to -soil potentials,
shall be No. 12 AVG or larger. Both leads shall be
continuous (without splices) and laid with
sufficient slack to prevent stress. The leads
shall be insulated with 600 -volt rated insulation
suitable for direct burial. Prior to backfilling,
the insulation shall be inspected for defects. All
defects shall be repaired by approved methods.
h. Test stations shall be of the flush type (terminal
below grade) or the above surface type, protected
as required for permanency. The flush type shall
be installed in developed, urban areas (streets,
alleys, sideways, etc.) and the above- surface type
06/09/88 Page 56 Pipe
P
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(mounted on a post) shall be installed in
cross - country areas (rangeland, farmland, etc.).
'Mere practicable, test stations shall be located
at or closely adjacent to clearly identifiable
topographical features (fence line, road
intersection, section line, etc.) of the pipeline
right of way.
i. The Contractor shall perform tests as required to
determine the following and correct the
corrosion - monitoring system to comply with these
specifications:
3•
1. Pipeline electrical continuity.
2. Effectiveness of insulating joints.
3. Test station integrity.
4. Static pipe -to -soil potentials at each
test station.
5. Soil resistivity at each test station.
All design, installation and testing shall be
consistent with sound corrosion engineering
practice.
(22) Pipe Anchorage, Support and Protection
Pressure pipeline tees, plugs, caps and bends exceeding 22 1/2
degrees; other bends as directed shall be securely anchored by
suitable concrete thrust blocking or by approved metal harness.
Unless otherwise indicated, on 24 inch or larger piping, all bends
greater than 11 1/4 degrees shall be anchored as described herein.
Storm severs on steep grades shall be lugged as indicated.
(a) Concrete Thrust Blocking
Concrete for use as reaction or thrust blocking shall be
Class B conforming to Item No. 403, "Concrete for
Structures ".
Concrete blocking shall be placed between solid ground and
the fitting to be anchored. The area of bearing on the pipe
and on the ground shall be as indicated or directed by the
Engineer. The blocking shall, unless otherwise indicated, be
so placed that the pipe, fittings and joints will be
accessible for repair.
The trench shall be excavated at least 6 inches outside the
outermost projections of the pipe or appurtenance and the
trench walls shaped or undercut according to the detail
510 06/09/88 Page 57 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
drawings or as required to provide adequate space and bearing
area for the concrete.
The pipe and fittings shall be adequately weighted and
laterally braced to prevent floating, shifting or straining
of the pipeline while the concrete is being placed and taking
initial set. The Contractor shall be solely responsible for
the sufficiency of such restraints.
(b) Hetal Thrust Restraint
Fabricated thrust restraint systems such as those described
below may be approved for use instead of concrete blocking.
To obtain approval, the project plans must include sufficient
drawings, notes, schedules, etc., to assure that the proposed
restraints as installed will be adequate to prevent
undesirable movement of the piping components. Such
restraint systems may only be used where and as specifically
detailed and scheduled on approved project plans.
1. Thrust Harness
A metal thrust harness of tie rods, pipe clamps or lugs,
turnbuckles, etc., may be approved. All carbon steel
components of such systems, including nuts and washers,
shall be hot -dip galvanized; all other members shall be
cast ductile iron. After installation, the entire
assembly shall be wrapped with 8 mil polyethylene film,
overlapped and taped in place vith duct tape to form a
continuous protective wrap.
The number, size and arrangement of rods, lugs, etc.,
shall be specifically detailed on the approved plans.
2. Restrained Joints
Piping or fitting systems utilizing integral
mechanically restrained joints may be approved. All
components of such systems shall be standard
manufactured products fabricated from cast ductile iron,
hot -dip galvanized steel, brass or other corrosion
resistant materials and the entire assembiy'shall be
protected with a continuous film wrap as described for
1. above.
Location, configuration and description of such products
shall be specifically detailed on the plans. (Add -on
attachments such as retainer glands, all- thread rods,
etc., are not acceptable.)
(c) Concrete Encasement, Cradles, Caps and Seals •
When trench foundation is excessively wet or unstable or
installation of eater or wastewater pipe will result in less
06/09/88 Page 58
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
than 30 inches of cover, Contractor shall notify Engineer.
Engineer may require Contractor to install a concrete seal,
cradle, cap, encasement or other appropriate action.
All concrete cap, etc., shall be continuous and begin and end
within 6 inches of pipe joints. Concrete cap, cradle and
encasement shall conform to City of Austin Standards No.
510 -1, 510 -9 and 510 -7 respectively. The pipe shall be well
secured to prevent shifting or flotation while the concrete
is being placed.
(d) Anchorage Bulkheads
Concrete bulkheads keyed into the undisturbed earth shall be
placed as indicated to support and anchor the pipe and /or
backfill, against end thrust, slippage on slopes, etc.
Concrete material and placement shall be Class A, Item No.
403, "Concrete for Structures ".
(e) Trench Caps, Concrete Rip -Rap and Shaped Retards
Vhere called for by the Contract or as directed by the
Engineer, concrete trench caps, concrete rip -rap and /or
shaped retards shall be placed as detailed by the standard
drawings as protection against erosion. Concrete material
and placement shall be Class B, Item No. 403, "Concrete for
Structures ".
(23) Wastewater Connections
(a) Connections to Mains 12 Inches and Smaller
All branch connections of nev main lines shall be made by use
of manholes.
•
Service stubs shall be installed as indicated. Minimum grade
shall be 1 percent and minimum over shall be 4 1/2 feet at
the curb. Standard plugs shall be installed in the dead end
before backfilling.
Vhere a service connection to a main 12 inches or smaller is
indicated, a vye, tee or double vye shall be installed.
Where a service connection to a main 15 inches or larger is
indicated, a field tap may be made vith the pipes installed
crovn to crovn. The tap should be made conforming to the
pipe manufacturer's recommendations vith the Engineer's
approval.
Vhere not otherwise indicated, service connections to mains
shall be installed at an angle approximately 45 degrees above
the horizontal.
510 06/09/88 Page 59 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(b) Connections to the Existing Systea
Unless otherwise specified by the Engineer, all connections
made to existing mains shall be made at manholes with the
crown of the inlet pipe installed at the same elevation as
the crown of the existing pipe. Service stubs installed on
the existing system shall be installed by use of tapping
saddles unless otherwise approved by the Engineer. Extreme
care shall be exercised to prevent material from depositing
in the existing pipe as the taps are being made.
When connections to existing mains are made, a temporary plug
approved by the Engineer must be installed dovnstream in the
manhole to prevent water and debris from entering the
existing system before final acceptance. These plugs shall
be removed after the castings are adjusted to finish grade or
when final acceptance is given.
(24) Water System Connections
The Contractor shall, at his expense, make all necessary connections of
new piping or accessories to the existing water system. To minimize
any inconvenience from outages, the Contractor shall schedule all such
connections in advance and such schedule must be approved by the
Engineer before beginning any work.
(a) Shutoffs
The City will make all shutoffs on existing water mains. The
Contractor will be required to notify the Engineer's field
representative on the job at least 72 hours prior to the desired
time for any shutoff. The Engineer's field representative shall
notify any affected utility customers at least 24 hours prior to
the shutoff. The Water Utility will make the shutoff after
ensuring that all appropriate measures have been taken to protect
the water system, customers and employees.
The City will operate all valves to fill existing mains. Where a
newly constructed main has not been placed in service and has only
one connection to the public water supply, the contractor may
operate one valve to fill the main after approval has been
obtained from the Water Utility. The operation of the valve is to
be conducted under the immediate supervision of the Engineer's
field representative.
(b) Wet Connections to Existing Water System
The Contractor shall make all wet connections called for by the
Contract or required to complete the work. A wet connection shall
include draining and cutting into existing piping and connecting a
new pipeline or other extension into the existing pressure piping,
forming an addition to the water transmission and distribution
network.
510 11/22/91 Page 60 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
The contract price for vet connections shall be full payment for
all necessary shutoffs, excavation, removing plugs and fittings,
pumping eater to drain the lines, cutting in new fittings,
blocking and anchoring piping, bedding and backfilling, placing
the lines and service and all site cleanup.
No water containing detectable amounts of chlorine may be drained,
released or discharged until specific planning and appropriate
preparations to handle, dilute and dispose of such chlorinated
eater are approved in advance by the City and the disposal
operations shall be witnessed by an authorized representative from
the City.
(c) Pressure Taps to Existing Vetter System
The Contractor shall make all pressure taps called for by the
Contract Documents or required to complete the work. A pressure
tap shall consist of connecting new piping to the existing water
system by drilling into the existing pipe while it is carrying
water under normal pressure without taking the existing piping out
of service.
Unless otherwise provided by the Contract, the Contractor shall,
at his expense, perform all necessary excavation, furnish and
install the tapping sleeve, valve and accessories, provide the
tapping machine, drill the tap (unless otherwise indicated) and
shall block, anchor and backfill the piping, valve and all
accessories, place the new piping in service and perform all site
cleanup. Where that the City will make the tap, City forces are
not obligated or expected to perform any work except to provide
tapping machine and drill the actual hole. If City crews are to
make the tap, fiscal arrangements must be made in advance at the
Taps Office, Avante Plaza, 625 East 10th Street.
If a private contractor makes the tap, a W -WW inspector must be
present. "Size on size" taps will not be permitted, unless made by
use of an approved full circle gasket tapping sleeve. Concrete
blocking shall be placed behind and under all tap sleeves 24 hours
prior to making the wet tap.
(d) Service Connections
Tapping of PVC or AC pipe for service connections may be made
using either a service clamp or saddle or a tapping sleeve
recommended by the manufacturer and approved as satisfactory by
the Engineer. Direct tapping will not be permitted.
All service connections shall be installed so that the outlet is
at an angle of approximately 45 degrees above horizontal at the
main line.
Precautions should be taken to ensure that the tapping saddle or
sleeve is placed on the pipe straight to prevent any binding or
deformation of the PVC pipe. The mounting chain or U -bolt strap
must be tight.
510 11/22/91 Page 61 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Tapping shall be performed with a sharp shell type cutter so
designed that it will smoothly penetrate heavy walled PVC DR14 and
200 psi AC and will retain and extract the coupon from the pipe.
(25) Backfilling
(a) General
Special emphasis is placed upon the need to obtain uniform density
throughout the backfill material. The maximum lift of backfill shall
be determined by the compaction equipment selected and in no case shall
it exceed 18 inches, loose measurement.
No heavy equipment, which might damage pipe, will be allowed over the
pipe until sufficient cover has been placed and compacted. All
internal pipe bracing installed or recommended by the manufacturer
shall be kept in place until the pipe bedding and trench backfill have
been completed over the braced pipe section. Testing of the completed
backfill in streets and under and around structures shall meet the
specified density requirements. Initial testing shall not be at
Contractor's expense and shall conform to Section 00344, "Testing
Laboratory Services."
(b) General Corrugated Metal Pipe
After the corrugated metal pipe structure has been completely assembled
on the proper line and grade and headwalls constructed where indicated;
selected material free from rocks over 8 inches in size from excavation
or borrow, as approved by the Engineer, shall be placed along both
sides of the completed structures equally, in uniform layers not
exceeding 6 inches in depth (loose measurement), sprinkled if required
and thoroughly compacted between adjacent structures and between the
structures and the sides of the trench or for a distance each side of
the structures equal to the diameter of the pipe if pipe is laid above
the existing ground.
Backfill material shall be compacted to the same density requirements
as indicated for the adjoining sections of embankment in accordance
with the governing specifications thereof. Above the 3/4 point of the
structure, the fill shall be placed uniformly on each side of the pipe
in layers not to exceed 12 inches, loose measure.
Prior to adding each new layer of loose backfill material, until a
minimum of 12 inches of cover is obtained over the crown of the pipe,
an inspection will be made of the inside periphery of the corrugated
metal structure to determine if
510 11/22/91 Page 62 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
any floating, local or unequal deformation has occurred as a
result of improper construction methods.
(c) Backfill Materials
The Engineer may approve any of the following well graded
materials:
1. Select trench material
2. Sand
3. Crushed rock cuttings
4. Rock cuttings
5. Foundation Rock
6. Blasted material with fines and rock
7. Cement stabilized material
8. Borrow
Within the 100 year flood plain, sand will not be permitted
for backfilling. The Engineer shall approve the topsoil for
areas to be seeded or sodded.
(d) Backfill in Street Right of Way
Placement of backfill under pavement structures and within 2
feet of any structures shall be compacted to the required
density using any method, type and size of equipment which
will give the required compaction without damaging the pipe
or bedding. Placement of backfill greater than 2 feet beyond
structures in Right of Way shall be conform to (g) belov.
The depth of layers, prior to compaction, shall depend upon
the type of sprinkling and compacting equipment used and the
test results thereby obtained. Prior to and in conjunction
vith the compaction operation, each layer shall be brought to
the moisture content necessary to obtain the required density
and shall be kept level to insure uniform compaction over the
entire layer. Testing for density will be in accordance vith
Test Method Tex -114 -E and Test Method Tex - 115 -E.
Each layer of backfill must provide the density as required
herein. Swelling soils (soils with plasticity index of 20 or
more) shall be sprinkled as required to provide not less than
optimum moisture nor more than 2 percent over optimum
moisture content and compacted to the extent necessary to
provide not less than 95 percent nor more than 102 percent of
the density as determined in accordance with Test Method
Tex - 114 - E. Nonsvelling soils (soils with plasticity index
less than 20) shall be sprinkled as required and compacted to
510 06/09 Page 63 Pipe
510
the extent necessary to provide not less rhan 95 percent of
the density as determined in accordance with Test Method
Tex- 114 -E.
After each layer of backfill is complete, tests may be made
by the Engineer. If the material fails to meet the density
indicated, the course shall be reworked as necessary to
obtain the indicated compaction and the compaction method
shall be altered on subsequent work to obtain indicated
density and conform to Section 00344, "Testing Laboratory
Services ".
At any time, the Engineer may order proof rolling to test the
uniformity of compaction of the backfill layers. All
irregularities, depressions, weak or soft spots which develop
shall be corrected immediately by the Contractor.
Should the backfill, due to any reason, lose the required
stability, density or finish before the pavement structure is
placed, it shall be recompacted and refinished at the sole
expense of the Contractor. Excessive loss of moisture in the
subgrade shall be prevented by sprinkling, sealing or
covering with a subsequent backfill layer or granular
material. Excessive loss of moisture shall be construed to
exist when the subgrade soil moisture content is more than 4
percent below the optimum of compaction ratio density.
Backfill shall be placed from the top of the bedding material
to the existing grade, base course, subgrade or as indicated.
The remainder of the street backfill shall be Flexible Base,
Concrete or Hot Mix Asphalt Concrete as indicated or to
replace in kind the surface removed to construct the pipe.
(e) Backfill in County Street or State Highway Right of Way
All work within the right of way must meet the requirements
of (d) above, as a minimum and shall meet the requirements of
the permit issued by the County when their requirements are
more stringent. Prior to the start of construction, the
Contractor will be responsible for contacting the appropriate
SDHPT office or County Commissioner's Precinct Office and for
coordinating his activities with the operating procedures in
effect for utility cut permits and pavement repair under
their jurisdiction. Approval for all completed work in the
State or County right of way must be obtained from the
appropriate Official prior to final payment by the Owner.
(f) Backfill in Railroad Right of Way
All work within the railroad right of way must meet the
requirements of (d) above, as a minimum and shall meet the
requirements of the permit issued by the Railroad Owner when
their requirements are more stringent. Approval for all
completed work in the railroad right of way must be obtained
from the Railroad prior to final acceptance.
06/09/88 Page 64
Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(g) Backfill in Easements
Where not otherwise indicated, Contractor may select whatever
methods and procedures may be necessary to restore entire
work area to a safe, useful and geologically stable condition
with a minimum density of 85 percent or a density superior to
that prior to constructs
In and near flood plain of all streams and watercourses,
under or adjacent to utilities, structures, etc., all
backfill shall be compacted to a density of not less than 95
percent conforming to SDRPT Test Method Tex - 114 -E, unless
otherwise directed by Engineer.
All soil areas disturbed by construction shall be covered
with top soil and seeded conforming to Item No. 604, "Seeding
for Erosion Control ". All turf, drainvays and drainage
structures shall be constructed or replaced to their original
condition or better. No debris shall remain in the drainvays
or drainage structures.
(26) Quality Testing for Installed Pipe
(a) Wastewater Pipe Acceptance Testing
After construction is complete, Engineer shall determine
whether the pipeline is to be tested for infiltration,
exfiltration or by the low pressure air test method.
Wastewater pipe installed in the City of Austin and its ETJ
areas shall be tested for exfiltration or infiltration as
described belov in "Exfiltration Test" and "Infiltration
Test" or by acceptable low pressure air test, as described
below. At the conclusion of either test series, the work
shall be further tested for pipeline settlement as described
below. The Contractor shall be solely responsible for making
proper repairs to those elements which do not pass these test
- requirements.
(b) Exfiltration Test
The pipeline shall be completely filled with water for its
complete length or by sections as determined by the Engineer.
If tested for its complete length, the maximum head at any
point shall not exceed 25 feet unless otherwise indicated.
If tested in sections, the manholes in the test section shall
be completely filled with water. After the pipeline has been
filled and allowed to stand for 24 hours, the amount of
exfiltration shall be calculated. Any amount in excess of
200 gallons per inch of inside pipe diameter per mile per day
shall be cause for rejection.
510 06/09/AR
Page 65
Pipe
(c) Infiltration Test
When the pipe placed in easements is completed, the upper
portion of the ditch backfill shall be removed to a depth of
not less than 18 inches below the finished surface and width
equal to the original trench width. The trench shall then be
flooded with eater until it is completely saturated and eater
stands in the ditch a minimum of 12 inches deep. In cases of
steep terrain, earthen dikes shall be used to assure that
water will stand over the trench. After it is apparent that
the trench is completely saturated, the main shall then be
inspected with closed- circuit television for infiltration.
Any section of the main or any service stub that indicates
excessive infiltration shall be cause for rejection.
This procedure shall not be used for pipes installed in areas
where the P.Z. of the surrounding material is 20 or higher or
where the backfill material has a P.I. of 20 or more.
(d) Pipeline Settlement Test
During the infiltration test or after the exfiltration test,
the pipe will be TV inspected for possible settlement. When
air testing has been used, water shall be flowed into the
pipe to permit meaningful observations. Any pipe settlement
which causes excessive ponding of water in the pipe shall be
cause for rejection.
(e) Low Pressure Air Test of Gravity Flow Wastewater Lines
(1) General
Wastewater lines in sizes for which the City has testing
equipment may, at the discretion of the Engineer, be air
tested between manholes. Backfilling to grade shall be
completed before the test and all laterals and stubs
shall be capped or plugged by the Contractor so as not
to alloy air losses which could cause an erroneous test
result. Manholes are to be plugged so they are isolated
from the pipe and cannot be included in the test.
All plugs used to close the sewer for the air test must
be capable of resisting the internal pressures and must
be securely braced. Place all air testing equipment
above ground and alloy no one to enter a manhole or
trench where a plugged sever is under pressure. Release
all pressure before the plugs are removed. The testing
equipment used must include a pressure relief device
designed to relieve pressure in the sewer under test at
10 psi or less and must alloy continuous monitoring of
the test pressures in order to avoid excessive pressure.
Use care to avoid the flooding of the air inlet by
infiltrated ground eater. (Inject the air at the upper
plug if possible.) Use only qualified personnel to
conduct the test.
510 06/09/88 Page 66 Pipe
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
510
(2) Ground water
Since the presence of ground water will affect the test
results, test holes shall be dug to the pipe zone at
intervals of not more than 100 feet and the average
height of ground eater above the pipe (if any) shall be
determined before starting the test.
(3) Test Procedure
The Engineer may, at any time, require a calibration
check of the instrumentation used. Use a pressure gauge
having minimum divisions of 0.10 psi and an accuracy of
0.0625 psi. (One ounce per square inch.) All air used
shall pass through a single control panel. Clean the
sever to be tested and remove all debris where
indicated. Jet the sewer prior to testing. The average
back pressure of any groundwater shall be determined
(0.433 psi) for each foot of average water depth (if
any) above the sever.
Add air slowly to the section of sewer being tested
until the internal air pressure is raised to 4.0 psig
greater than the average back pressure of any ground
water that may submerge the pipe.
After the internal test pressure is reached, alloy at
least 2 minutes for the air temperature to stabilize,
adding only the amount of air required to maintain
pressure. After the temperature stabilization period,
disconnect the air supply.
Determine and record the time in seconds that is
required for the internal air pressure to drop from 3.5
psig to 2.5 psig greater than the average back pressure
of any ground eater that may submerge the pipe.
Compare the time recorded with the time required as
follows:
Pipe Size (Inches)6 8 10 12 15 18 21 24
Time (Minutes) 3 4 5 6 7.5 9 10.5 12
Any drop in pressure, from 3.5 psig to 2.5 psig, in a
time less than that required by the above table shall be
cause for rejection. Vhen the line tested includes more
than one size pipe, the minimum time shall be that given
for the largest size pipe included.
When lines are air tested, manholes are to be tested
separately by exfiltration or infiltration.
06/09/88 Page 67 Pipe
510
(27) Pressure Pipe Hydrostatic Testing
After the pipe has been installed and backfilled and all service
laterals, fire hydrants and other appurtenances installed and
connected, a pressure test, followed by a leakage test, will be
conducted by the City. The City will furnish the pump and gauges
for the tests. The Contractor will be present and shall furnish
all necessary assistance for conducting the tests. The specified
test pressures will be based on the elevation of the lowest point
of the line or section under test. Before applying the specified
test pressure, all air shall be expelled from the pipe. If
permanent air vents are not located at all high points, the
Contractor shall install corporation cocks at such points.
All service laterals and fire hydrant leads, with the hydrant
valves closed and nozzle caps open, shall be included in the
tests.
(a) Pressure Test
The entire project or each valved section shall be tested, at
a pressure of 200 psi for a sufficient period (approximately
10 minutes) to discover all leaking or defective materials.
Repairs shall be made by the Contractor to correct any
leaking or defective materials.
(b) Pressure Pipe Leakage Test
A leakage test will follow the pressure test and be conducted
on the entire project or each valved section. The leakage
test shall be at 150 psi for at least 1 hour.
(1) Allowable Leakage
Leakage shall be defined as the quantity of eater that
must be supplied into any test section of pipe to
maintain the specified leakage test pressure (see above,
"Pressure Pipe Leakage Test ") after the air in the
pipeline has been expelled and the pipe has been filled
with water.
No pipe installation will be accepted if the leakage
exceeds 25 gallons /24 hours /mile of pipe /inch nominal
pipe diameter.
( 25 gpd )
(in. - mi.)
(28) Service Charges for Testing
No charge will be made to the Contractor for the City's test
equipment, inspection, etc., when the test results shov that
leakage is within the indicated allowable limits.
06/09/88 Page 68
Pipe
1
_
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
For each test, either for leakage or for pressure, which fails to
meet the indicated requirements, the City's flat charge of S50.00
for such tests will be charged to the Contractor and will be
deducted from any funds due the Contractor.
(29) Sterilization of Potable Water Lines
The Contractor shall protect all piping materials from
contamination during storage, handling and installation. Prior to
disinfection, the pipeline interior shall be clean, dry and
unobstructed. All dirt, debris, gasket lubricant, etc., shall be
washed from the line by swabbing with hypochlorite solution and /or
flushing with clean vater.
The City, at its expense, will supply the test gauges and the
concentrated disinfecting material and City personnel will
supervise and direct the overall sterilization procedure. The
Contractor, at his expense, shall provide all other equipment,
supplies and the necessary labor to perform the sterilization
under general supervision of the City.
(a) Procedure and Dosage
All valves shall be arranged to prevent the strong
disinfecting dosage from floving back into the existing water
supply piping. The new pipeline shall then be completely
filled with disinfecting solution by feeding the concentrated
chlorine and approved water from the existing system
uniformly into the new piping in such proportions that every
part of the line has minimum concentration of 50 parts per
million (50 ppm or 50 mg /liter) available chlorine.
Unless otherwise indicated,, all quantities called for herein
refer to measurements by the testing procedures in the
current edition of "Standard Methods ". The chlorine
concentration of each step in the sterilization procedure
shall be verified by chlorine residual determinations. This
disinfecting solution shall be retained in the piping for at
least 24 hours and all valves, hydrants, etc., shall be
operated to disinfect all their parts. After this retention
period, the water shall contain no less than 25 parts per
million chlorine throughout the treated section of the
pipeline.
This heavily chlorinated water shall then be carefully
flushed from the line until the chlorine concentration is no
higher than the residual generally prevailing in the existing
distribution system or approximately one part per million.
Proper planning and appropriate preparations to handle,
dilute and dispose of this strong chlorine solution without
causing injury or damage to the public, the water system or
the environment must be approved by the City before flushing
of the line may begin and the flushing shall be witnessed by
an authorized representative of the City.
510 06/09/88 Page 69 Pipe
(b) Bacteriological Testing
After final flushing of the strong disinfecting solution,
eater samples from the line shall be tested for
bacteriological quality by the City and must be found free of
coliform organisms before the pipeline may be placed in
service. One test sample shall be drawn from the end of the
main and additional samples collected at intervals of not
more than 1000 feet along the pipeline.
The Contractor, at his expense, shall install sufficient
sampling taps at proper locations along the pipeline. Each
sampling tap shall consist of a standard corporation cock
installed in the line and extended with a copper tubing
gooseneck assembly. After samples have been collected, the
gooseneck assembly may be removed and retained for future
use.
Samples for bacteriological analysis shall be collected only
from suitable sampling.taps in sterile bottles treated with
sodium thiosulfate. Samples shall not be drawn from hoses,
fire hydrants, etc. The City, at its expense, vill furnish
the sterile sample bottles and may, at its discretion,
collect the test samples with City personnel.
_= the initial disinfection fails to produce acceptable
sample tests, the disinfection procedure shall be repeated
(without extra compensation) until satisfactory test results
have been obtained before the piping may be placed in
service.
(30) Cleanup and Restoration
It shall be the Contractor's responsibility to keep the
construction site neat, clean and orderly at all times.
Cleanup shall be vigorous and continuous to minimize traffic
hazards or obstructions along the streets and to driveways.
Trenching, backfill and cleanup shall be coordinated as directed
by the City. The Engineer shall regulate the amount of open ditch
and may halt additional trenching if cleanup is not adequate to
alloy for orderly traffic floe and access.
Materials at the site shall be stored in a neat and orderly manner
so as not to obstruct pedestrian or vehicular traffic. All damaged
material shall be removed from the construction site immediately
and disposed of in a proper manner. All surplus excavated
materials become the property of the Contractor for disposal at
his expense. After trenching, the Contractor shall immediately
remove all excavated materials unsuitable for or in excess of,
backfill requirements. Immediately following the pipe laying work
as it progresses, the Contractor shall backfill, grade and compact
all excavations as provided elsewhere and shall immediately clean
510 06 /09 /88 Page 70 Pipe
510.4 lfeastuement
510.5 Payment
up and remove all taused soil, waste and debris and restore all surfaces and
iniprovenents to a condition equal or superior to that before construction began and to
an appearance which cariplenetts the surroundings. The Contractor shall grade and dress
the top 6 inches of earth surfaces with soil or other material similar and equal to
the surrounding, fill and smooth any visible tracks or ruts, replace and reestablish
all damaged or disturbed turf or other vegetation and otherwise make every effort to
Encourage the return of the entire surface and all impruvenents to a pleasant
appearance and useful condition appropriate and complementary to the surrotadings and
equal or similar to that before construction began.
Pipe will be measured by the linear foot for the various types, sizes and classes Parallel
lines will be measured individually.
Where a line ties into an existing system, the length of the new line shall be measured fran
the visible end of the existing system at the canpleted joint. Unless otherwise indicated, the
length of water and wastewater Lines shall be measured along pipe horizontal centerline
stationing through fittings, valves, manholes, and other appurtenances. Unless otherwise
provided, fitting sizes less than 16 -inch shall be measured by the ton; 16 -inch and larger
sizes shall be subsidiary to the pipe. Stornaater pipe shall be measured along the slope of
the pipe. Where drainage pipe ties into inlets, headwalls, catch basins, manholes, junction
boxes or other structures, that length of pipe tying into the structure wall will be included
for measurement but no other portion of the structure length or width will be so included.
Pipe depth shall be measur from the existing ground surface in easenetts and fran existing
ground surface or proposed street subgrade in the right -of -way, whichever is less, over the
centerline of the pipe to the flowline elevation.
When pay items are provided for the other canixnents of the system, measurement will be made as
addressed hereunder.
Payment for pipe, measured as prescribed above, will be made at the unit price bid per linear
foot for the various sizes of pipe, of the materials and macs indicated, unless unstable
material is encountered or trench excavation and backfill is bid as a separate item.
The concrete seal, foundation rock or coarse aggregate shall be paid for at the unit price bid
per cubic yard, which shall be full payment for all excavation and removal of unsuitable
material and furnishing, placing and compacting the foundation rock, coarse aggregate or other
approved material all canplete in place.
Excavation and beckfill, when included as a separate pay item, will be measured by Pay Iten No.
510-E or F.
Excavation and backfill, when included as pipe installation will not be measured as such but
shall be included in the unit price bid for constructing pipe and measured as pipe complete in
place including
510 05/01/90
Page 71
Pipe
(3)
excavation and bnckfill. As established in the bid, pipe including excavation and backfill may
be either (1) payment for any and all depths or (2) payment in 2 foot incremental depth.
Paymment for pipe excavation will be included in the Bid to be measured
methods of measurement uremt and payment methods indicated above aor and paid as s "Structural
of the
may be measured
Excavation and Rackfill" as indicated.
Payment shall be full compensation, in accordance with the pay it set in the bid. For
excavation, furnishing, hauling and placing pipe including lugs and all incidental and
subsidiary materials and work; preparing, shaping, dewatering and shoring of trenches; hauling,
planing and preparing bedding; for cconnecting to new or existing systems or structures; for
hauling, moving, placing and compacting backfill materials and for all other mincidentais
necessary to complete the pipe installation as indicated.
(1) Pipe
Payment for pipe, measured as prescribed above, will be made at the unit price bid per
lineal foot complete- in -pta,o as designed and represented in the plans and other contract
documents. The bid price per lineal foot of pipe shall include all clearing, embankment,
excavation, bedding materials, particle migration measures, fittings, field constructed
joints, collars. temporary plugs, pumping, caps or bulkheads, all necessary lugs, rods or
braces, pipe coatings and protection, connections to existing systems, concrete blocking
and thrust blocks, disposal of surplus excavated material, laying of pipe, beckfilling,
temporary pavement repairs and maintenance, cleanup and all other incidental ccmpon nts
necessary to complete the work. Payment will also represent compensation for removal and
replacement of pavement, curb, drainage structures, driveways, sidewalks and any other
improvements damaged or removed during construction. Pipe shall be paid at the contract
unit price for any and all depths or at two foot incremental depths in accordance with the
selected method of Pay Item No. 510-A.
Items listed above as subsidiary to the pipe will be paid individually only when provided
by the bid.
No separate payment will be made for welded or harnessed joints required for thrust
restraint which are scheduled, indicated, generally required for the pipe material used,
or otherwise accepted as an industry standard. Steel cylinder concrete pipe and welded
steel pipe fittings shall be subsidiary to the pipe pay item.
(2) Concrete Cradles and Seals
When called for in the Bid, concrete seals or cradles shall be paid for at the unit
contract price bid per linear foot for the size of pipe specified, complete in place.
Cmc ete Retards
When called for in the Bid, Concrete retards shall be paid under Item No. 593, "Concrete
Retards."
510 05/01/90 Page 72 Pipe
1
--
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(4) Boring, Jacking and Tunneling
When called for in the Bid, boring, jacking and tunneling shall be
paid under Item No. 501, "Jacking or Boring" or Item No. 502,
"Tunneling ".
(5) Vet connections to Water Mains
Wet connections shall be paid for at the unit price bid per each,
complete in place, according to the size of the main that is in
service and shall be full compensation for all work required to
make the connection and place the pipe in service. Cast iron
fittings shall be paid for as a separate item.
(6) Fittings
Cast iron and ductile iron fittings of the class indicated,
furnished in accordance with these specifications will be paid for
at the unit price bid per ton, complete in place, according to
scheduled weights for mechanical joint fittings furnished,
including giands,•bolts and gaskets, as published in the following
standards:
AVVA C -153 for all fittings in 4 inch through 12 inch sizes,
regardless of whether AWVA C -110 or AVVA C -153 fittings are
furnished or the type of end connections supplied.
AWVA C - 110 for all fittings larger than 12 inch size.
Steel cylinder concrete pipe fittings and welded steel pipe
fittings will not be paid for separately. The Contractor shall
include these in his bid for pipe.
(7) Concrete Trench Cap and Encasement
Where the distance between the top of the concrete encasement and
the top of the trench cap is less than 36 inches, the concrete cap
and encasement will be poured as one unit and paid for under this
bid item at the contract price bid per linear foot. When the
distance above is greater than 36 inches or when the trench cap is
placed separately, the trench cap shall be paid for as a separate
item, per linear foot, complete in place.
(8) Cement Stabilized Backfill
Cement - stabilized backfill shall be paid for at the unit price bid
per linear foot and shall be full payment to the Contractor for
furnishing and installing the required material, mixed, placed and
cured complete in place.
(9) Concrete Encasement
When called for in the Bid, Concrete Pipe Encasement shall be paid
under Item No. 505, "Concrete Encasement and Encasement Pipe ".
510 06/09/88 Page 73 Pipe
(10) Pressure Taps
Pressure taps will be paid for at the unit price bid, complete in
place, according to the size tap made and the size main tapped and
shall be full payment for furnishing all necessary materials,
making the tap, testing and placing the connection in service.
(11) Trench Safety Systems
vhen called for in Bid, Trench Safety Systems will conform to Item
No. 509, "Trench Safety Systems ".
(12) In -Place Sliplining vith or without In -Place Pipe
Destruction /Replacement
As called for in the corresponding bid items, pipe sliplining with
or without in -place pipe destruction /replacement shall be paid for
at the contract price per linear foot for the specified liner and
pipe size and type pipe, at all depths, complete in place.
Installation of new services, or reconnection of existing
services, to the liner will be paid for at the contract price per
each for the specified size and type of service, at all depths,
complete in place.
(13) Cured Resin Pipe Lining
'Men called for in the bid, cured resin pipe lining will be paid
for per linear foot, for the size and type of pipe lined, at all
depths, complete in place including all equipment set - ups, video
inspection and cleaning of existing pipe. Installation of new
services or reconnection of existing services to the relined pipe
will be paid for per each, for the specified size and type of
service, at all depths, complete in place.
Payment, when included as a contract pay item, will be made under one of
the following:
Pay Item 510 -A:
Pay Item No. 510 -A:
Pay Item No. 510 -B:
Pipe, Dia. (all depths), including
Excavation and Backfill - per Linear Foot.
Pipe, Dia. ( to depths),
including Excavation and Backfill - per Linear
Foot.
In -Place Sliplining without In -Place Pipe
Destruction /Replacement ( Dia. Pipe
Lining in Dia. Existing Pipe) - per Linear
Foot.
Pay Item No. 510 -C: In -Place Sliplining with Pipe
Destructiion /Replacement ( Dia.
Replacement Pipe in Dia. Existing Pipe) - per
Linear Foot.
510 06/09/88 Page 74 Pipe
End
Pay No. 510 -D: _Installing or Reconnecting Lateral Service to
Relined or Replaced Pipe ( Dia. Service)
in Dia. Pipe - per Each.
Pay Item No. 510 -E: Pipe Excavation, Ft. Width - Per Linear
Foot.
Pay Item No. 510 -F: Pipe Trench 3ackfill, Ft. width - per Liner
Foot.
Pay Item No. 510 -G: Concrete Seal or Cradle, Dia. Pipe - Per
Linear Foot.
Pay Item No. 510 -E: Concrete Trench Cap, Ft. Width - Per Linear
Foot.
Pay Item No. 510 -I: Concrete Cap and Encasement, Dia. Pipe - Per
Linear Foot.
Pay Item No. 510 -K: Cement Stabilized Backfi'_1, Dia. Pipe - per
Linear Foot.
Pay Item No. 510 -M: Foundation Rock - Per Cubic Yard.
Pay Item No. 510 -N: Cured Resin Pipe Lining (for Dia. Pipe) - per
Linear Foot.
Pay Item No. 510 -0: Coarse Aggregate - Per Cubic Yard.
Pay Item No. 510 -P: Installing or Reconnecting Lateral Service to Cured
Resin Lined Pipe, Dia. Service (for
Dia. Main) - per Each.
Pay Item No. 510 -T: Pressure Taps, _ Dia. X _ Dia. - Per Each.
Pay Item No. 510 -V: wet Connections, _ Dia. x Dia. - Per Each.
Pay Item No. 510 -1: Cast Iron or Ductile Iron Fittings - Per Ton.
A "W" after the pay item indicates the use for water.
A "WV" after the pay item indicates the use for wastewater.
Ref: 102, 210, 403, 501, 502, 505, 507, 593, 601, 604
510 Page 75 Pipe
511.1 Description
This item to consist of valves furnished and installed as indicated. Unless otherwise indicated, all valves 4
inches and larger shall be AWWA -type valves of suitable design and fully equipped for service buned in the
earth, without need for further modification and shall be wrapped with 8 -mil polyethylene film with all edges and
laps securely taped to provide a continuous wrap. Where not indicated, the Contractor may use valves with any
type end -joint allowed for fittings of the pipe class being used. Unless otherwise indicated, all valve stems shall
be adjusted to situate the operating nut not less than 30 inches nor more than 36 Inches below the proposed
ground or paving surface of the finished project.
511.2 Materials
Contractor to submit descriptive information and evidence that materials and equipment Contractor proposes for
incorporation into work is of the kind and quality that satisfies the specified functions and quality. Because City
of Austin water has a relatively high pH, bronze parts of valves shall not contain over 16% zinc. Through
previous investigation, testing and usage. certain types, brands and models of materials have established a
record of prior approval and satisfactory service. Water and Wastewater Standard Products Lists form a part of
these Specifications. Should Contractor elect to use any materials from these lists, they should be completely
and clearly identified when submitted.
(1) Samples, Inspection and Testing Requirements:
All tests and inspections called for by the applicable standards shall be performed by the manufacturer.
Upon request, results of these tests shall be made available to the purchaser.
(2) Other Requirements:
.511.3 Valves
Item No. 511
Water Valves
Each bid shall be accompanied by
Complete data covering the operator, including type and size, model number, etc., the manufactuier's
name and address of his nearest service facility, the number of turns to fully open or close the valve.
detailed instructions for calibrating the limit stops for open and closed positions and any other information
which may be necessary to operate and maintain the operator.
Complete dirnensional data and installation instructions for the valve assembly as it is to be installed.
including the operator.
Complete replacement parts lists and drawings, identifying every part for both the valve and operator
(1) Iron - Body Gate Valves
Unless otherwise indicated, Iron Body Gate Valves, 4" to 12 " -- including Tapping Valves —shall conform to
AWWA C509, "Resilient Seated Gate Valves for Water and Sewerage Systems ".
Iron Body Gate Valves larger than 12" — including Tapping Valves —shall be double disc, parallel seat
valves meeting the requirements of AWWA C500.
(a) Stem Seals: All valves shall have approved O -nng type stem seals. At least two O -rings shall be in
contact with the valve stem where it penetrates the valve body.
(b) Operation: All valves shall have non -nsing stems with a 2" square operating nut, or with a spoke type
handwheel when so ordered, tuming clockwise to close.
511 02/19/93 1 Water Vahcs
(c) Gearing. Double disc gate valves in 16" and larger sizes shall oe geared and. when necessary for
proper bury depth and cover, shall be the honzontal bevel- geared type enclosed in a lubncated gear
case.
(d) Bypass Unless otherwise indicated, 16 inch and larger gate valves shall be equipped with a bypass
of the nonrrsing stem type which meets the same AWWA standard required for the main valve.
(e) Valve Ends. Valve ends shall be push -on. flanged or mechanical joint, as indicated or approved.
Tapping valves shall have inlet flanges conforming to MSS SP -60, with boll holes drilled per ANSI
B16.1 Class 125. Seat nngs and body casting shall be over -sized as required to accommodate full
size cutters; the outlet end shall be constructed and dolled to allow the dnlling machine adapter to be
attached directly to the valve.
(f) Gear Case. All geared valves shall have enclosed gear cases of the extended type, attached to the
valve bonnet in a manner that makes it possible to replace the stem seal without disassembly and
without disturbing the gears, bearing or gear lubricant. Gear cases shall be designed and fabricated
with an opening to atmosphere so that valve leakage past the stem seal does not enter the gear case.
(g) Valve Body: Double disc gate valves in 16" and larger sizes installed in the horizontal position shall
have bronze rollers. tracks, scrapers, etc.
(2) Butterfly Valves: Unless otherwise indicated, all valves shall conform to the current "AWWA" Standard
C - 504, "Rubber Seated Butterfly Valves ", Class 1506, except as modified or supplemented herein.
(a) Functional Requirements
1. Valves shall be the snort body design and shall have flanged connections on both ends unless
otherwise called for.
2. Valves shall be of such design that the valve discs will not vibrate or flutter when operated in a
throttled position. Valve discs shall be secured to the shafts by means of keys or pins so arranged
that the valve discs can be readily removed without damage thereto. All keys and pins used in
securing valve discs to shafts shall be stainless steel or monel. Valve discs shall be stainless steel
or ductile iron. ASTM A 536. Grade 65 45 - 12, seating edge shall be stainless steel or other
corrosion resistant material.
3. Valve shafts shall be constructed of wrought stainless steel or monel. The ends of the shaft shall be
permanently marked to indicate the position of the disc on the shaft
4. All buried valves shall have approved manufacturer's 0-ring type or split V type "Chevron" shaft
seals When 0-ring seals are used, there shall be at least two 0-rings in contact with the valve
shaft where it penetrates the valve body.
On 24 inch and larger valves. the seat shall be completely replaceable and /or adjustable with
common hand tools without disassembling the valve from the pipeline.
Rubber seats located on the valve disc shall be mechanically secured with stainless steel retainer
rings and fasteners.
5. Unless otherwise indicated, valves shall be provided with manual operators with vertical stems and 2
inches square operating nut tuming clockwise to close and equipped with a valve disc position
indicator. All keys or pins shall be stainless steel or monel. Buried valves shall have the valve
stems extended or adjusted to locate the top of the operating nut approximately 30 inches to 36
inches below finish grade.
6. Unless otherwise indicated, motorized butterfly valves shall be equipped with 230/460 volt, 3 -phase
reversing motor operators, extended as required to locate the center line of the operator shaft
approximately 4 feet to 4 feet, 6 inches above finish grade. Operators shall be equipped with cast
iron or malleable iron manual override hand wheel with a valve position indicator, local push button
controls, lighted status /position indicator, torque and travel limit switches and all switches, relays
511 112 /19/93 2 Water Vahcs
and controls (except extemal power and signal wrong) necessary for both local and remote
operation
(b) Performance Requirements
1. Unless otherwise indicated. valve operators shall be sized to seat. unseat. open and close the valve
with 150 psi shutoff pressure differential across the disk and allow a flow velocity of 16 feet per
second valve second past the disc in either direction.
2. Motorized valve motors shall be capable of producing at least 140 percent of the torque required to
operate the valves under conditions of maximum nonshock shutoff pressure without exceeding a
permissible temperature rise of 55 degrees Celsius over 40 degrees Celsius ambient; they shall
have a duty rating of not less than 15 minutes and shall be capable of operating the valve through 4
1/2 cycles against full unbalanced pressure without exceeding the permissible temperature nse.
Motors shall be suitable for operating thee valve under maximum differential pressure when voltage
to motor terminals is 80 percent of nominal voltage. Motor bearings shall be permanently lubricated
and sealed.
(3) Brass (Bronze) Valves: Unless otherwise indicated, brass gate valves shall be those makes and
models included in the Standard Product List (SPL WW -174). Brass globe valves by the same
manufacturers will be acceptable when required.
(4) Air- Vacuum Release Valves
(a) Valves shall be combination air- release. air- vacuum units having small and large onfice units
contained and operating within a single body or assembled unit.
The small onfice system shall automatically release small volumes of air while the pipe is
operating under normal conditions. The large air- vacuum onfice system shall automatically
exhaust large volumes of air while the pipe is being filled and shall permit immediate re -entry
of air while being drained.
Valves shall be rated for at least 150 psi maximum normal service pressure.
(b) Material Requirements:
Valve exterior bodies and covers shall be cast iron.
Internal bushings, hinge pins, float guide and retaining screws. pins, etc, shall be stainless
steel or bronze. Orifice seats shall be Buna -N rubber.
Floats shall be stainless steel, rated at 1000 psi.
Unless otherwise indicated, these valves shall be as included in the Standard Products List
(SPL WW -367 for water. WW -462 for wastewater force mains).
(5) Fire Hydrants: All fire hydrants shall be Dry Barrel, Traffic Model (break- away), Post Type having
Compression Type Main Valves (5 1/4" opening). closing with line pressure. Approved models are listed
on QPL WW -3 of the Water and Wastewater Utility Standard Products List.
(6) Pressure /Flow Control Valves: All control valves to regulate pressure, flow, etc., in City lines shall be
models listed in Water and Wastewater Standard Products List.
(7) Drain Valves: Drain valve materials and installation shall conform to City of Austin Standard Detail No.
511 -9 or 511 -17.
511 112 /19/93 3 Water Valscs
1
1 11.4 Construction Methods
11) Setting Valves, Drains and Air Releases:
Unless otherwise indicated, main line valves, drain valves and piping, air and vacuum release
assemblies and other miscellaneous accessones shall be set and jointed in the manner described for
cleaning, laying. and jointing pipe.
Unless otherwise indicated. valves shall be set in line with the radius point and the corresponding point of
curvature or point of tangency of adjacent curbs or nght of way lines. Valves shall be installed so that
the tops of operating stems will be at the proper elevation required for the piping at the location indicated
above. Valve boxes and valve stem casings shall be firmly supported and maintained, centered and
aligned plumb over the valve or operating stem. with the top of the box or casing installed flush with the
finished ground or pavement in existing streets. and installed with the top of the box or casing
approximately 6 inches below the standard street subgrade in streets which are excavated for paving
construction or where such excavation is scheduled or elsewhere as directed by the Engineer.
Drainage branches or air blowoffs shall not be connected to any sanitary sewer or submerged in any
stream or be installed in any other manner that will permit back siphonage into the distribution system
(see "Standard Detail Drawings"). Every drain line and every air release line shall have a full sized
independent gate valve flanged directly to the main. Flap - valves, shear gates. etc.. will not be accepted.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
(2) Setting Fire Hydrants:
Fire hydrants shall be located in a manner to provide accessibility and in such a manner that the
possibility of damage from vehicles or injury to pedestrians will be minimized Unless otherwise directed,
the setting of any hydrant snail conform to the following.
Hydrants between curb and sidewalk on public streets, shall be installed as shown on Standard 511 -17,
with outermost point of large nozzle cap 6" to 18" behind back of curb. Where walk abuts curb, and in
other public areas or in commercial areas. dimension from gutter face of curb to outermost part of any
nozzle cap shall be not less than 3 feet. nor more than 6 feet. except that no part of a hydrant or its
nozzle caps shall be within 6 inches of any sidewalk. Any fire hydrant placed near a street corner shall
be no less than 20 feet from the curb line intersection.
All hydrants shall stand plumb. those near curbs shall have the 4" nozzle (the large one) facing the curb
and perpendicular to it. The hydrant bury mark shall be located at ground or other finish grade. nozzles
of all new hydrants shall be approximately 18 inches above grade. Lower barrel length shall not exceed
5 feet. Barrel extensions are not permitted unless approved by the Engineer. Each hydrant shall be
connected to the main by 6" ductile iron pipe, a 6 inch gate valve shall be installed in the line for
Individual shutoff of each new hydrant
Below each hydrant, a drainage pit 2 feet in diameter and 2 feet deep shall be excavated and filled
compactly with coarse gravel or broken stone mixed with coarse sand under and around the blow of the
hydrant. except where thrust blocking is situated and to a level 6 inches above the hydrant drain opening.
No hydrant drainage pit shall be connected to a sanitary sewer. Cover drain gravel with filter fabric to
prevent blockage of voids in the gravel by migration of backfill material. The bowl of each hydrant shall
be well braced against unexcavated earth at the end of the trench with concrete thrust blocking (taking
care not to obstruct the hydrant drain holes) or it shall be tied to the pipe with approved metal harness
rods and clamps. Hydrants shall be thoroughly cleaned of dirt or foreign matter before setting.
Fire hydrants on mains under construction shall be securely wrapped with a poly wrap bag or envelope
taped into place and removed when the mains are accepted and placed in service.
(3) Pressure Taps: Refer to Item No. 510.3(24), "Pipe ".
(4) Plugging Dead Ends: Standard plugs shall be inserted into the bells of all dead ends of pipes,
tees or crosses and spigot ends shall be capped. All end plugs or caps shall be secured to the pipe
conforming to Item No. 510.3 (22), "Pipe ".
511 02/19/93 4 Water Vakin
1
1
1
1
1
1
1
1
1
1
1
1
1
(5) Protective Covering: Unless otherwise indicated, all flanges, nuts, bolts, threaded outlets and all
other steel component shall be coal tar coated and shall be wrapped with 8 -mil (minimum)
polyethylene film meeting ANSI /AWWA Specification C- 105 - current. with all edges and laps taped
securely to provide a continuous and watertight wrap.
(6) Valve Box, Casing and Cover. Stems of all buried valves shall be protected by valve box
assemblies as shown on City of Austin Standard No. 511 -10. Valve box castings shall conform to
ASTM A 48. Class 308. Testing shall be verified by the manufacturer at the time of shipment. Each
casting shall have cast upon it a distinct mark identifying the manufacturer and the country of origin.
(7) Drain Valve Installations: Refer to City of Austin Standards.
(8) Air Release Assemblies: Refer to City of Austin Standards.
(9) Pressure /Flow Control Valves: Assemblies shall be installed as indicated.
(10) Connections to Existing System: Refer to Item No 510, 'Pipe" for connections to the existing
system.
(11) Shutoffs: Refer to Item No. 510, 'Pipe" for shutoffs.
511.5 Measurement
All types of valves will be measured per each. Fire hydrants and drain valves will be measured per each. Fire
Hydrant and Drain Valve barrel extensions will be measured per vertical foot. Pressure /Flow control valve
assemblies and both manual and automatic air release assemblies will be measured per each.
511.6 Payment
Payment shall be full compensation in accordance with the pay item set in the bid, for excavation, furnishing.
hauling and placing valves and barrel extensions including anchorage and all Incidental and subsidiary materals
and work; preparing, shaping, dewatering, shoring of trenches, bedding, placing and compacting backfill
materials and for all other incidentals necessary to complete the installation, as indicated, complete in place.
Payment for iron fittings and for wet connections are covered in Item No. 510.6. 'Pipe ".
(1) Valves: Valves will be paid for at the unit price bid for the size and type valve Installed, including valve
stem casing and cover, excavation and backfill, setting, adjusting to grade, anchoring In place, and other
appurtenances necessary for proper operation.
(2) Fire Hydrants: Fire Hydrants Installation shall be paid for at the unit pnce bid, including fittings.
between the main line and the fire hydrant, setting, adjusting to grade, anchoring in place, and other
appurtenances necessary for proper operation; but shall not include pipe and valve between the main
line and fire hydrant.
(3) Fire Hydrant and Drain Valve Barrel Extensions: Barrel extensions will be paid for at the pnce bid
measured by the vertical foot for bury depths greater than 5 feet, including stem extensions, bolts and all
other required accessories.
(4) Pressure /Flow Control Assemblies: Pressure control and flow control valve assemblies will be paid
for at the unit price bid, including box or vault, setting, adjusting to grade, anchonng in place, adjusting
the control device to the required conditions, providing other appurtenances necessary for proper
operation, and placing in operation.
(5) Drain Valve Assemblies: Drain valve installation shall be paid for at the unit price bid, including
fittings between the main line and the drain valve, setting, adjusting to grade, anchoring in place, and
other appurtenances necessary for proper operation; but shall not include pipe and valve between the
main line and drain hydrant.
511 112/17/93 5 Water Va■es
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
END
Ref: 510
(6) Manual Air Release: Manual air release installations will be paid for at the unit puce bid and shall
include valves, fittings, pipe, tapping the main, box and cover, and other appurtenances necessary for
proper operation.
(7) Automatic Air- Vacuum Valves: Automatic air - vacuum release assemblies will be paid for at the unit
price bid and will include the main line tap or outlet, all pipe, valves, fittings, box or vault and cover, and
other appurtenances necessary for proper operation.
Payment, when included as a contract pay item, will be made under one of the following:
Pay Item No. 511-A: Valves, Type, Dia. - Per Each.
Pay Item No. 511-8: Fire Hydrants - Per Each.
Pay Item No. 511-C: Fire Hydrant Bartel Extensions - Per Vertical Foot.
Pay Item No. 511 -0: Pressure or Flow Control Valve Assemblies - Per Each.
Pay Item No. 511-E: Drain Valve Assemblies - Per Each.
Pay Item No. 511-F: Manual Air Release Assemblies Dia. - Per Each.
Pay Item No. 511-G: Automatic Combination Air and
Vacuum Release Valve Assemblies. Dia. - Per Each.
511 112/17/73 6 Water Vxhcs