R-99-04-22-10D1 - 4/22/1999RESOLUTION NO. R- 99- 04- 22 -10D1 WHEREAS, the City of Round Rock has previously entered into a contract ( "Contract ") with Chasco Contracting, Inc. for the Downtown Storm Drainage and Street Improvement Project, and WHEREAS, it has been determined that it is necessary to change said Contract in accordance with the attached Contract Change Order No. 5, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized and directed to execute on behalf of the City Contract Change Order No. 5 to the Contract with Chasco Contracting, Inc. for Downtown Storm Drainage and Street Improvement Project. The City Council hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Oper. Meetings Act, Chapter 551, Texas Government Code, as amended, and the Act. RESOLVED this 22nd day of Apri 411 LJL IA / E LAND, City Secretary �WP000S \ RESOI.UT? \R9092201 /scg CHARLES CULPEP'PER, Mayor City of Round Rock, Texas tqt- RECEIVFn A" 1 F 1000 Project Title: Downtown Storm Drainage and Street Improvements Project No.: 702 -02A/B Contract No.: SUN 201719 Contract Date:May 28, 1998 Contractor: Chasco Contracting The following changes are hereby made to the Contract Documents: DRAWINGS 23 & 24 (MILAM) FROM STA. 3 +20 TO 7+00 SHAPE ANV I LF ' tAwsriucr and exchange proposed 2" HMAC overlay by 3" HMAC. Item No. Work Description Quantity Unit Price Amount 201 Sub -grade Reparation 1075 S.Y. $1.00 $1,075.00 340 -B3 3" HMAC Type D 1075 S.Y. $5.80 $6,235.00 340 -B1 2" HMAC Type D 935 S.Y. $4.00 $3,740.00 CR SUBTOTAL $3,570.00 Justification: Changes are due to existing pavement structure being destroyed for different utility trenches crossing the road. Base course was only from 2" to 4" thick, additional HMAC course will increase the life expectancy of the street. Item No. Work Description Quanitity Unit Price Amount 510 -A16 4" PVC SCH 40, 6" PVC Sleeve, and C. Out L.S. $2,928.00 $2,928.00 506 -WW2 Adjust drop manhole and reconnect L.S. 5600.00 $600.00 SUBTOTAL $3,528.00 TOTAL $7,098.00 Justification: Additional work items due to existing utilities. DRAWING 31 (SPRING) CHANGE TO CONTRACT PRICE Original Contract Price: $1,075,693.45 Current Contract Price as adjusted by previous change orders: Change Order No. 1: $27,200.00 Change Order No. 2: $46,985.75 Change Order No. 3: $4,760.00 Change Order No. 4: $22,541.60 TOTAL: $1,177,180.80 The Contract Price due to this change order will be [increased] [decreased] by $7,098.00 The new Contract Price due to this Change Order will be $1,184,278.80. Change Order No. 5 Date: 03/03/1999 CHANGE TO CONTRACT TIME Additional calendar days for previous Change Orders No. 1 + 5, No. 2 + 18, No. 3 + 5, No. 4 +12. The Contract Time for this change order will be [increased] [decreased] by 4 calendar days. The date for completion of all work under the contract will be July 4, 1999. Approvals required: To be effective, this order must be approved by the Owner if it changes the scope or objective of the project, or as may otherwise be required under the terms of the Supplementary General Conditions of the Contract. Requested by: Roberto O. Martinez, MWM, Inc. 3 /3� Signature: fe at - � 0 . oZ-� Date: Accepted by: Al ille Ci o Round ' ock Signature: ' .4lPi'l Date: 43_0 q' Accepted by: Chasco Contractin 1 27 / I Signature: ' /Ai7 / , Date: 3 • 30 • Approved: / y. Date: axles Culpepper y -aa -99 IL/: SS 3/3/9 DATE: April 16, 1999 SUBJECT: City Council Meeting — April 22, 1999 ITEM: 10.D.1. Consider a resolution authorizing the Mayor to execute Contract Change Order No.5 to Chasco Contracting for the Downtown Storm Drainage and Street Improvement Project. This change order provides for an increase from 2 inches to 3 inches in the Hot Mix Asphaltic Concrete overlay construction on Milam Street to compensate for the weakened condition of the existing roadway structure due to the utility work. The change also provides for the lowering and sleeve of a wastewater service line, which was in conflict with the concrete box storm sewer construction at the intersection of Spring Street and Pecan Street. This change order, which is an increase of $7,098.00, makes the current contract amount $1,184,278.80. The funding source is the 1996 General Obligation Bond Program. Staff recommends approval. Staff Resource Person: Jim Nuse, Public Works Director.