R-99-06-10-10E3 - 6/10/1999RESOLUTION NO. R- 99- 06- 10 -10E3
WHEREAS, the City of Round Rock has previously entered into a
contract ( "Contract ") with Nelson Lewis, Inc. for the South Creek
Waterline Replacement Project, and
WHEREAS, it has been determined that it is necessary to change
said Contract in accordance with the attached Contract Change Order No.
1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Contract Change Order No. 1 to the Contract with
Nelson Lewis, Inc. for the South Creek Waterline Replacement Project.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended, and the Act.
RESOLVED this 10th day of June, 1999.
ATTEST:
ANNE LAND, City Secretary
K.\ WP POCS \RESOLUTI \R90610E3_WPU /scg
ROBERT A. STLUKA, J , Mayor
City of Round Rock, Texas
ITEM #
DESCRIPTION OF
CHANGES
UNIT
QTY.
UNIT
PRICE
AMOUNT
ADDED DAYS
cA.ENDARI
WORKING
1
Remove and replace long side
double service
EA
-11
51,100.00
($12,100.00)
-3
IA
Remove and replace short side
double service
EA
-15
$700.00
($10,500.00)
-5
7
Remove and replace long side
quadruples service
EA
11
$1,800.00
$19,800.00
4
7
Remove and replace short side
quadruple service
EA
15
$1,300.00
$19,500100
7
.
TOTAL:
$16,700.00
3
DEPARTMENT: Public Works
PROJECT: Southcreek Waterline Replacements
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
PREPARED BY: Alysha Girard
ENGINEERING ASSISTANT
CONTRACTO - Nelson Le -, Inc.
BY:
TITLE:
APPRO - •= h
-44'd
`�''1YOFR%
CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
a
NO R
$318,801.00
$0.00
$16,700.00
$16,700.00
CHANGE DATA
5/27/99
DATE
PAGE: 1 OE 1
DATE: 6/2/99
CHANGE ORDER NO: 1
JUSTIFICATION: Services are quadruples
as opposed to doubles_
PERCENT Of ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER: 5.24%
PREVIOUS CHANGE ORDER
TOTAL % CHANGE:
ORIGINAL CONTRACT PRICE
PLUS CHANGE ORDERS!
seenenpe ontnakbuthereeldproject spy
0
5.24%
$335,501.00
DATE: June 4, 1999
SUBJECT: City Council Meeting, June 10, 1999
ITEM: 10.E.3. Consider a resolution authorizing the Mayor to execute Contract Change
Order No. 1 with Nelson Lewis, Inc. for the South Creek Waterline
Replacement Project in the amount of $16,700. The original contract with
Nelson Lewis, Inc. was for $318,801. The Change Order allows for the
replacement of the non - standard quadruple services. Staff recommends
approval. Staff Resource Person: Jim Nuse, Public Works Director.