R-99-09-23-10E7 - 9/23/1999Mayor
Robert A. Stlata, Jr
Mayor Pro -tem
Martha A. Chavez
Council Members
Tom Nielson
Earl M. Hairston
Rick Stewart
Earl Palmer
Jimmy Joseph
City Manager
Robert L Bennett, Jr.
City Attorney
Stephan L Sheets
October 7, 1999
Matous Construction, Co., Ltd.
P.O. Box 5258
Temple, Texas 76505
Dear Sirs:
221 East Main Street
Round Rock. Texas 78664
512 -218 -5400
The Round Rock City Council approved Resolution No. R- 99- 09- 23 -10E7 at their
regularly scheduled meeting on September 23, 1999. This resolution approves Change
Order No. 1 for the modifications to Well Site No. 9.
Enclosed is a copy of the resolution and Change Order for your files. If you have any
questions, please do not hesitate to contact Steve Miller at 218 -5555.
Si cerely,
Joanne Land
Assistant City Manager/
City Secretary
Enclosures
Fax: 512- 218 -7097
1-800-735-2989 TDD 1 -800- 735 -2988 voice
www.ci.rouad- rock.tx.us
RESOLUTION NO. R- 99- 09- 23 -10E7
WHEREAS, the City of Round Rock has previously entered into a
contract ( "Contract ") with Matous Construction Company for the
modifications to Well Site No. 9, and
WHEREAS, it has been determined that it is necessary to change
said Contract in accordance with the attached Contract Change Order No.
1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Contract Change Order No. 1 to the Contract with
Matous Construction Company for modifications to Well Site No. 9.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended, and the Act.
RESOLVED this 23rd day of September, 1999.
ATTEST:
KA WPOOCS \RESOLUTI \R90923E].WPD /acg
City Secretary
i
RO= RT A. S UKA, . , Mayor
City of Round Rock, Texas
CPR No-
Item and Description of Changes
Contract Price
Contract Time
Decrease
Increase
Decrease
Increase
1
Provide new metal doors on the existing CMU block
building.
0
1,357.00
0
2
2
Provide new PCMCIA card, ammonia pump status
relay and switch for station, and SCV -001 position
indication.
0
2,874.00
0
6
3
Provide solenoid control valve for flushing total
chlorine sample line.
0
1,984.00
0
5
sub-Tote
Difference Net
0
6,215.00
0
13
0
86,215.00
0
13
hD3
Project Name:
City of Round Rock Water System Improvements
Well Site No. 9 Modifications
Project Owner: (Name, Address)
City of Round Rock, Texas
2008 Enterprise Dr.
Round Rock, Texas 78664
Project Contractor: blame, Address)
Matous Construction Co., Ltd.
P.O. Box 5258
Temple, Texas 76505
It is agreed to modify the Contract referred to above as follows:
1 3198,000.00
Net Increase (decrease) of this Change Order
1 3204,215.00
Revised Contract Price with at approved Change Orders
1 3204,215.00
The changes included in this Change Order are to be accomplished in accordance with the terms, stipulations and conditions of the
original ontract as t u n clud erein.
original / 2 -4 1 9
Summary: It is agreed to modify the Contract referred to above as follows:
Contract Price prior to this Change Order Contract Time prior to this Change Order
Accepted for Contractor by Date
pproved for 0
Recommend )!d for ppro l Ey((HDR Engineering. Inc.)
ner by:
Appro'! ithey - when required)
Distribution:
FORM 111- 5020 -2 (Version 1.0 Oci 90)
Copyright 1991 11DR Engineering, Inc.
Owner
Attest Date
//. A 9 `" � .
( Contractor
Task 5020
1-10P Project No.:
07225 - 036 - 039
Owner's Project No.:
N/A
Date of Issuance: August 18, 1999
Date of Contract: May 24, 1999
Contract Period: 120 Days
Change Order No. 1
!October 24, 1999 (120 days)
Net Increase (decrease) of this Change Order
1 13 days
Revised Contract Time with all approved Change Orders
1 November 6, 1999 (133 days)
Date
Date
(Field
8 -2)4 7
4 -13 -99
'Other
H1-5020-2
067.23/99 07:22 '21S 5563 PUBLIC WORKS
-- ,� n wrvai �1G 'y11 J1'ki
Project Nome:
City of Round Rock Water System Imp.
Well Site No. 9 Modifications
Project owner: City of Round Rock, Texas
non Prager no.: 0722 -036 6 ; (�
CeeVaam:
Matous Construction Co., Ltd.
P.U. BOX 525S
Temple, Texas 76605
Attention:
The following change In the contract on this project is proposed.
• A breakdown of cost.SHALL be attached.
• Work shalt not commence until euthori5ed by the Owner.
Description or the Proposed Chance;
A nueseee _ 0...e...4 _ Unrheno.d
by Z calendar days.
It-1 WV o u . ..c.c..tip
cm.c cem,>ae.
1 D0. Co -2.L -
Fnem 41-5010-) pun 90)
Dwrdah 99) 9059 Entine Inc.
D a M.jeet I99 DO ..Olic.bb):
0.9WStory Agency wopa ne. IIf 99010.91.4:
!Pealed by:
By
All work shall be In accordance with the terms, stipulations. and NOR Recommondetlen:
COndltions of the original Contract Documents. If the work herein
provided for ie Approved by Change Order, the time of completion
w,l1 0e:
X En•e.., _ Cene.ne
�pwornnan DP Recommend
Ate.ptaxv M ee I I �
ey: 400 Eneine my, Inc. I
I '. / t 1
Parc
This change willr eee oed..• _ not CJ gnu. Owner . ACtion:
151 r
3 LA � / � 1'(C.Pt.d
aye Owe/ t � X/
Z002 /002
NO. 979 .P02
Change Proposal
Request No. 1
(Not a Change Order)
Provide all labor, materials, and equipment to add or delete the Work identified within this CPR. Provide
proposal identifying costs associated with labor, materials. Contractor's Overhead and Profit all separately
identified.
1. Provide and install new metal doors and frames to be installed within the existing CMU block building.
Doors should be provided in accordance with Division 8 of the Southeast Elevated Pump Station
technical specifications on should be coated in accordance with Se. ion 09905.
To)) 5040 11130403
Contractor.
atous Construction Co., Ltd.
O. Box 5258
emple, Texas 76505
Attention:
The fallowing change in the contract on this project is proposed.
A breakdown of cost SHALL be attached.
• Work shall not commence untll authorized by the Owner.
Description of the Proposed Change;
Provide all labor, materials, and equipment to add or delete the Work identified within this CPR. Provide
a proposal identifying costs associated with labor, materials, Contractor's Overhead and Profit Ml
separately identified.
_ 1. Provide, Install, and transfer logic to an additional PCMCIA card for the Magelis unit so City may have
an additional back -up should something happen to the original card.
2. Provide a relay to convey pump status for the ammonia metering pump and provide programming and
logic to convey this information to the PLC and SCADA. Relay should be tied to the receptacle that
will energize the metering pump and be sized so as to handle the system and the 3.5 -amp current
draw from the pump.
_ 3. Provide equipment to show the position of the solenoid control valve used to flush the line should
turbidity readings exceed a specified value. Provide programming and logic to read this signal into
the PLC and the SCADA system.
4. Provide a switch in the ammonia building to control which metering pump is energized for use.
Install conduit and wring to each purnp.
200 r
-06/99 09:22
Protect Name;
ity of Round Rock Water System Imp.
Well Site No. 9 Modifications
on prop No.: 07225 -039 -036
Owner 'a erolect No. 111 90911 a /1V
o , l0tory Agency Prajeat No. flf eppllcable11
llilialad
FORM 111- 5010.3 (Jun 90)
Cupyr491. 1991 HOR enruxeriny. lac
$218 5563 PUBLIC WORKS
Job Number o I r
� ( p
A. B. C. D. E. e _, 3
F.G.H.1.J K.
L. M.
Copy to:
Requested by: R,p
Post - it® Fax Note 7671
Tufk 5010
by:
W1001/002
Change Proposal
Request No. 2
(Not a Change Order)
era;
X Engineer _ Conp,,crer ' Rev. 7/26
11.5010.3
08406/99 09:23 e218 5563 PUBLIC WORKS
, FD.a
All work shell be in accordance with the terms, stipulations, and
conditions of the original Contract Documents. If the work herein
provided for is Approved by Change Order, the time of completion
will be:
increased _ Decreeaed _ Undlenged ay: NDA Enolnee
FORM 11.1-501 0-3 (Jw 901 Tv4 5010
Coprrigla 1991 IrDR Engineering, Inc,
HDR Recommendation:
Z002/002
Change Proposal
Request No. 2
(Not a Change Order)
Recommended
ACCeptsnce
by calendar days.
Z,,,
Dare
This change will: ✓a _ Oaduut _ Not Change Owner s Actium
s Z a �-4-- ✓prod
I �nere Contractor ."'�' Lief, . 1 G � 12 e:V/1
By: Owner
Not Accepted
lI �.
I Dete Cam,} 1.4-t J (Ci
111-501C.3
tOD�j
XVI LS =ET NON 66/9Z/L0
July 26, 1999
Mr. Brad Castleberry
UDR Engineering, Inc.
2211 S. 1H 35, Suite 300
Austin, Texas 78741 -3842
MATOUS CONSTRUCTION, LTD.
GENERAL CONTRACTORS
lomimmizi P.O. Box 5258 • Temple, Texas 76505 • Office 254 -780 -1400 • FAX: 254 -780 -2599
Re: City of Round Rock Water System Imp.
Well Site No. 9 Modifications
CPR — No. 2
Dear Mr. Castleberry:
As per your request we offer the following for your consideration:
Lump Sum of $341.00
lob Number 79— °310
A._B.__C. s D. E._3_
F. G.H.1.1.K._
L. M.
Copy to:
Requested by:_�
Provide, install and transfer logic to an additional PCMCIA card for the Magelis
unit so the City may have an additional back -up should something happen to the
original card.
2. Provide a relay to convey pump status for the ammonia metering pump. This
change also includes programming the Magelis and the SCADA system which
will indicate if the pump is on or off.
Lump Sum of $898.00
3. Provide equipment to show position of solenoid valve on the Megelis or SCADA
system.
Lump Sum of $1,190.00
4. Add a switch in the ammonia building to control which ammonia metering pump
is being used. This change also includes installing conduit and wire to second
ammonia metering pump.
Lump Sum of $445.00
Please advise Owner's decision on the above and we will proceed accordingly.
Should you have any questions, please do not hesitate to contact us.
Sincerely, zt,
Don R. Schuch
2 00 re
08/19/99 15:02 $218 5583 PUBLIC WORKS
• Post -1V Fax Note 7671 oats t Pe t
�drt Change Proposal
" 1 - 1.,.%Y�te F •41119
Co °I So Request No. 3
° ° • (Not a Change Order)
d:
Phone .
+rehet lua,s: City
Well Site No. 9 Modification
o_.r City of Round Reek, Tssas
n99 Pepet 14o.: 07215.O
MatoU5 Construction Co, Ltd •
P.O. Des 5258
Temple, Tilsit 1650S
PA9.91 n:
Tl•e f0II x .e Stange 41 Y. e0nvact DP tbie prelim is prpDmed•
• A breakdown of east SMAL_ be ettoehed.
. wore shall not eammene0 ante suP5o fsod a the O.r.ne..
De.er.OtlO't 01 the Proeesed Chanile
rovadc ell labor, materiels, end equipment to add or delete the work Identified within this CPR. Provide
roposal identifying costs eseoeiated with labor, materiels, Contractor's Overhead and Profit all separately
dentified. 17. r_— 'ls It S 19
Pro a and i stall jea ring an� 1
w nsulaa far c ri nd so t line t is Ypose s it U7s into \10
dlsch c side f the l Pump. Proved ' Blas rtc to Iationn.VC lac tried, A tnsuo g
dustri or eq . ��
Z. Provide a 1'IS' solenoid control valve. Wa model ystem for or eq o tiel shall ee c chlorine sample
tine and flush the sample line upon engaging the
normally olosed end energized to open for duration of 1 •minute. Provide ama u Bali valve
and all required piping- AB piping, misc. valves, and pipe s • ports to be pr o
Specifications. Provide 1pgic and programming to tie to PLC and SCAO:i .
— � n►J-
All .6l t shall be is eee4rdanee with the terms. stiprrlatt00 000 r4DR g
cordiebris al the oripinel Contmet Documents. it he work Amin
provided 101 is A99. d by Change Wet. the time of aompl0Yrn ee
- Ammo...
- :....ease - o.vr.� - Jnenanad
ey , 5 COICneer days.
This Change .,at: I..m
M
rmmte 1e690 tr-9101
e.s..Yeet 1101 MI Tpncli� rwr.
Fax
/ a-4-
Fax
- V /io'r— g iCS
rlrsib°r Ammo, r.d.ct no. P .pPtle.art:
Sal: safe
1d Dv:
1g100
ern POI rnelnar:.•,, Inc
0..
• AttiOn:
/ sce.prd _ Mel
e r
0
0140los
%b3 sr 43N 66%9/80
DATE: September 17, 1999
SUBJECT: City Council Meeting — September 23, 1999
ITEM: 10.E.7. Consider a resolution authorizing the Mayor to execute Change Order
No. 1, for the modifications to Well Site No. 9 by Matous Construction
Company. These changes involved replacing the old doors on the well
house, addition of instrumentation for ammonia system to aid in control
and installation of a solenoid valve for flushing the sample chlorine line
prior to testing. The amount of the change order is $6,215.00 with an
additional 13 days. Staff recommends approval. Staff Resource Person:
Jim Nuse, Public Works Director.