R-99-11-09-10C3 - 11/9/1999RESOLUTION NO. R -W- 11- 09 -10C3
WHEREAS, the bylaws of the Round Rock Transportation System
Development Corporation ( "RRTSDC ") require that, each year, the Board
of the Corporation shall develop, for the City, a combined
Transporation Capital Improvement Program ( "Program "), including
maintenance and operation costs thereof, and
WHEREAS, the bylaws of the RRTSDC require that said Program be
approved by the City Council, and
WHEREAS, the City Council wishes to approve said Program for
fiscal year 1999 -2000, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Transporation Capital Improvement Program for fiscal year
1999 -2000 for the Round Rock Transportation System Development
Corporation, attached hereto as Exhibit "A ", be hereby approved.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended, and the Act.
RESOLVED this 9th day of Nov
E LAND, City Secretary
K:\ WPOOCS \RESOflUTI \R911O9C3.WPD /scg
ROB RT A. STLUKA, ., Mayor
City of Round Rock, Texas
Project Name
Project Limits
Work Description
Fiscal
Year
in
TCLP
Projected
Contract
Award
Estimated Cost
Greenlawn Extension
From Louis Henna Blvd.
to IH 35 Frontage Road
Construct 4 lane divided arterial
1998
March 1999
$3,500,000
Traffic Signal
Coordination
FM I325/Louis Henna
McNeil/IH 35/RM 620
US 79
Construct and implement coordinated
traffic signal systems
1998
May 2000
$ 100,000
IH 35 Turnarounds
FM 1325/Louis Henna
Hester's Crossing;
Construct frontage road turnarounds
Reconstruct highway to 4 lane divided
highway.
1999
1999
March 2000
December
1999
$3,175,000
$2,550.000
US 79
From CR 195 to 110
South Mays Street
South Mays Street,
Hester's Crossing, Dell
Way, Connection to
Boardwalk, & Gattis
School Road Extension
Realign Streets, Widen Streets, & Extend
Streets-
1999
April 2000 &
FY 2001
$3,307,000
Arterial A
Forest Creek
Double Creek Drive
From US 79 to Forest
Creek Dr.
From Double Creek Drive
to 800' west of Forest
Ridge Subdivision
From Gattis School Rd to
MKT ROW
Preliminary Engineering to establish
alignment and right -of -way requirements.
Protective right -of -way purchase.
2000
N/A
$435,000
1999 TRANSPORTATION CAPITAL IMPROVEMENTS PROGRAM
ROUND ROCK TRANSPORTATION SYSTEM DEVELOPMENT CORPORATION
- TWO YEAR ELEMENT
C: WINDOWS'1 ESKTOP:1ly Briel'caae11999 TRANSPORTATION CAPITAL IMPROVEMENTS PROGRAMI 1599.doc+lwkl -5 99
1
0
Project Name
Project Limits
Work Description
Fiscal
Year
in
TCIP
Projected
Contract
Award
Estimated Cost
Arterial B
From US 79 to Louis
Henna Blvd.
Phase I: Preliminary Engineering
Phase 11: Engineering, Right -of -way, &
1999
N/A
51,940,000
Construction from Louis Henna to 1900'
South along CR 170 (Pflugerville Loop)
Phase III: Right -of -way Acquisition- 4
Tracts (Hardship Purchase)
Phase IV: Engineering, Right -of -way, &
Construction -4 lane divided from Gattis
School Rd to US 79
Phase V: Engineering & Construction -4
lane divided from Gattis School Rd to
Louis Henna Blvd
Eastern Arterial
From US 79 to Louis
Helena Blvd. On one of
the eastern alignments.
Estimated cost of Engineering, Right -of-
Way, & Construction for a 4 lane divided
arterial.
$8,000,000
Hagler- Bailly Study
1. SH 130 Toll Study
2. SH 45 Implementation Strategy
3. Railroad Relocation Feasibility Study
4. Implementation Strategy for 10 -Year
Roadway Plan
N/A
$350,000
Prime Strategies Inc.
Assist City in interagency coordination for
SH 45
2000
FY2000
$100,000
Greenlawn
Interchange
At IH 35
Construct Greenlawn interchange with EH
35
2001
FY 2004
53.400,000
RM 620
At Union Pacific Railroad
Construct Railroad Grade Separation
2001
FY2001
52,500,000
79
From FM 1460 to CR 195
Construct 4 lane divided highway
2000
FY2001
$4,400,000
_US
FM 1460
From US 79 to 1200' N of
US 79
Acquire Right -of -Way for Highway
Relocation
2000
FY2000
5360,000
Arterial C
From RM 620 to Sam
Bass Rd
Acquire Right -of -Way for Arterial C and
Construct Bicycle/Sidewalk Facility to
Access High School and Swimming Pool
2000
FY2001
$800,000
$34,917,000
TWO YEAR ELEMENT TOTAL
C:iWlNDOWS'DESKTOPIMy Briekase. l 999 TRANSPORTATION CAPITAL IMPROVEMENTS PROGRAM I l 599.daecI,s fB•99
2
CAI
m
a co
Ca
N
OD
N
G
IJ
N
DATE: November 5, 1999
SUBJECT: City Council Meeting — November 9, 1999
ITEM: 10.C.3. Consider a resolution adopting the Transportation Capital
Improvement Program for the Transportation System
Development Corporation. The Transportation Capital
Improvement Plan is a two -year spending plan for improvements
to major roads and arterials in the City. Funding for this plan is
provided through the 'A% sales tax established for the purpose of
transportation improvements. Staff Resource Person (s): David
Kautz, Finance Director and Tom Word, Traffic Engineer.