R-99-11-23-13C4 - 11/23/1999 HKS
CHANGE ORDER
PROJECT: ROUND ROCK CONVENTION CENTER CHANGE ORDER NO:03
COMPLEX Package"B"
TO: Alamo Steel Company INITIATION DATE: 10-Nov-99
321 Old Dallas Rd. ARCHITECTS PROJECT NO.: 6407
Waco, TX 76705 CONTRACT FOR: Steel Order
CONTRACT DATE: 5/13/99
The Contract is changed as follows:
Incorporate the work described in the following Items.All appropriate back up information is attached.
See Attachment'A'for Items included in this Change Order
This Change Order Is not In effect and will not be Included In the Contract Documents until signed by the Owner,Architect and
Contractor.Changes Included herein are subject to all conditions affecting them under the substitution specification section.
SUMMARY
The original Contract Sum was:................................................................................... $1.187,392.00
Net change by previously authorized Change Orders..... ...................................... $2,894.00
The Contract Sum prior to this Change Order was:..................................................... $1,190,286.00
The Contract Sum will be Increased by this Change Order
......................................................................................................................I............... $16.875.00
The new Contract Sum including this Change Order will be:....................................... $1,207,161.00
The Contract Time will be Unchanged by (0)Days
The Date of Substantial Completion as of the date of this Change Order therefore is 04-Oct-99
Changes included in the summary above do not include modifications which have been authorized by
Construction Change Directive(s). Authorized:
HKS INC. Alamo Steel Company Round Rock Express Baseball Club
1919 McKINNEY AVENUE 321 Old Dallas Rd. 3400 E.Palm Valley
DALLAS, 2 Waco, TX 76705 Rounk,"=4
By: Mr. Kevin A.Taylor By: Mrd�Marvin Turner By: Mr. R.D. Sneed
Date: 11/10/99 Date: 11/11/99 Date: //)/"-3 49
HKS INC. Dallas/Los Angeles/Orlando!Richmond/Tampa C HKS 701-1995
City of Round Rock
2008 Enterprise Dr.
Round Rock, TX 78664
Mr
m aayor
Date:
jr
HKS
CHANGE ORDER NO. 03 ATTACHMENT'A'
Project: ROUND ROCK CONVENTION CENTER
COMPLEX Package"B"
HKS Project# 6407
Incorporate the work described in the following Items.All appropriate back up information is attached.
DATE of
Days CONTRACTOR
CHANGE M COST: DESCRIPTION: Added PROPOSAL:
Alamo Steel $4,400.00 Structural Changes-Joist and Detail 0 8/18/99
CO-3
PC-14(Alamo $12,475.00 Steel Clarifications 0 11/8199
Steel)
TOTAL: $16,875.00 TOTAL DAYS THIS CHANGE ORDER: 0
Page 1 of 1
IOv. 8.1999 12:12PM 2 HKS 2149693397 N0.595 P.1/6
HKS
TRANSMITTAL
Date. 1118199 VIA:Fax
Fax Pages Including Cover Sheet: 8
T0: Mr. Steve Gladding Mr. Larry Madsen
Hansel Phelps Construction Co. City of Round Rock
3400 E.Palm Valley 2008 Enterprise Dr.
Round Rock, TX 78664 Round Rock, TX 78664
P(512)733-2212 F(512)733-2204 P(512)218-5552 F(512)218.5563
Mr. R.D. Sneed Mr. Marvin Turner
Round Rock Express Baseball Club Alamo Steel Company
3400 E.Palm Valley 321 Old Dallas Rd.
Round Rock, TX 78664 Waco, TX 76705
P(512)733-2212 F(512)733-2204 P(254)799-2471 F(254)799-6227
SUBJECT ROUND ROCK CONVENTION CENTER COMPLEX
Package"B"
HKS Project* 6407 Owner's Project*
WE ARE TRANSMITTING:
❑ Prints/Copies ❑ Samples ❑ Computer Media
❑ Originals ❑ Specifications ❑ Other
9 For Your Checking and Approval ❑ For Your Disposition
NO.COPIES DESCRIPTION
Please review HKS Recommendations on Alamo steels request.
1. Alamo Steels change order no.3-Structural Changes-Joist and Detail
Alamo request-C.O.no.3-Total-$10,486.00
HKS recommendation Is Total-$4,400.00
2. PC-14-Alamo request-$15.041 new request$12,4791116199.
HKS recommendation Is Total$12,479
Total-$16,879.00
Please advise on the issue of Change Order No.3
to include Alamos CO.03 and PC-14(steel only).
REMARKS
CC Greg Davenport By: Kevin A. Taylor
HKS INC. 1919 McKINNEY AVENUE DALLAS,TX 75201.1753 21419695599
®HKS 7�fl.1flfl5
[;*V. 6.1999 12:12PM 2 WS 2149693397 NO.595 P.2/6
Hf S
KeAn A.Taylor
November 08,1999
Mr. Larry Madsen
City of Round Rock
2008 Enterprise Dr.
Round Rock, TX 78664
Re: ROUND ROCK CONVENTION CENTER
COMPLEX Package"D"
HKs Project#: 6407 Ownef s Project No. .
Proposed Change#PC-14(Alamo Steel)
Dear Mr. Madsen:
Please find attached,the contractor's sued proposal for all items included in PC-14(Alamo Steel). As you are aware,
this Proposed Change was submitted to incorporate the following change to the contract documents:
Steel Clarifications
In accordance with the General Conditions of the Contract for Construction,HKS and our consultants have reviewed this
proposal and to the best of our knowledge and belief,a cost of$12,475.00 represents a fair and reasonable proposal. We
therefore recommend your approval.
Please review die Proposed Change at your earliest convenience and notify all parties of your approval or rejection,so that
we may prepare a Change Order(if necessary)to incorporate this work into the contract.
Should you have any questions,please contact us any tune.
Sincerely,
Kevin A. Taylor
Construction Contract Administrator
Attachments
Copy: Mr. Marvin Turner
Mw �n SNt�EIo
MKS INC. 1979 McKINNEY AVENUE DAU.AS,TX 75201.1753 2141959-5599
r,
CITY OF ROUND ROCK
221 Fast Main Street
Round Rock,Texas 78664
��HUiitttr 512-218-5400
December 21,1999
Mr.Kevin A.Taylor
HKS,Inc.
1919 McKinney Avenue
Dallas,Texas 75201-1753
Dear Mr.Taylor:
The Round Rock City Council approved Resolution No. R-99-11-23-1304 at their
regularly scheduled meeting on November 23, 1999. This resolution approves Change
Order No. 3 to the purchase order with CMC Steel Fabricators d/b/a Alamo Steel
Company for the fabrication of steel (Package `B") for the construction of the
Convention Center Complex/Stadium.
Enclosed is a copy of the resolution and change order for your files. If you have any
questions,please do not hesitate to contact Larry Madsen at 218-5555.
Sincerely,
n
U
Joanne Land
Mayor Assistant City Manager/
Robert A.Sriuka,Jr
City Secretary
Mayor Pro-tem
MonhaA.Ch—e, .
Council Members
Tom Nielson Enclosures
Earl M.Hairston
Rick Stewart
Earl Palmer
Jimmy Joseph
City Manager
Robert L Bennett,Jr
City Attorney Fax 512-218-7097 1-800-735-2989 TDD 1-800-735-2988 Voice
Stephan L Sheers www.ci.round-rock.mus
a�W CITY OF ROUND ROCK
!. - 221 Fast Main Street
e ���CCC"' ��''�44 - - Round Rock Texas 78664 -
!a e'•itltPt - 512-218-5400
December 21,1999
Mr.Marvin Turner
Alamo Steel Company
321 Old Dallas Road
Waco,Texas 76705
Dear Mr.Turner:
The Round Rock City Council approved Resolution No. R-99-11-23-13C4 at their
regularly scheduled meeting on November 23, 1999. This resolution approves Change
Order No. 3 to the purchase order for the fabrication of steel (Package `B") for the
construction of the Convention Center Complex/Stadium.
Enclosed is a copy of the resolution and change order for your files. If you have any
questions,please do not hesitate to contact Larry Madsen at 218-5555.
Sincerely,
Joanne Land
Assistant City Manager/
Mayor City Secretary
Roben A.Stiuka,Jr.
Mayor Pr tern
Murtha A.Ch—
Council Members Enclosures
'Tam Nielson
Earl M.Hairston
Rick Srewan -
Earl Palmer
Jinmry Joseph
City Manager
RabertL Bennett,Jr -
CityAttomey Fax 512-218-7097 1-800-735-2989 Ton 1-800.735-2988 Voice
Siephan L Sleets —.&round-rock,tx,us
AM, CITY OF ROUND ROCK
221 Fast Main Street
Round d Rock.Texas 78664
s.'.......'. t
�eiNrprt 512-218-5400
December 21,1999
Mr.R.D.Sneed
Round Rock Express Baseball Club
3400 E.Palm Valley Boulevard
Round Rock,Texas 78664
Dear Feed:
The Round Rock City Council approved Resolution No. R-99-11-23-13C4 at their
regularly scheduled meeting on November 23, 1999. This resolution approves Change
Order No. 3 to the purchase order with CMC Steel Fabricators d/b/a Alamo Steel
Company for the fabrication of steel (Package "B") for the construction of the
Convention Center Complex/Stadium.
Enclosed is a copy of the resolution and change order for your files. If you have any
questions,please do not hesitate to contact Larry Madsen at 218-5555.
Sincerely,
11
Mayor Joanne Land .
Robert A.Straka.Jr Assistant City Manager/
Mayorga-w° City Secretary
Mantra A.Chavez
Council Members
Tom Nielson
Earl M.Hairstom Enclosures
Rick Stevan .
Earl Palmer
Jimmy Joseph
City Manager
Roben L Bennett.Jr.
City Attorney Fax:512-218-7097 1-800-735-2989 TDD 1-800-735-2988 Voice
Stephan L Sheets www.ci.round-rockdx.us
RESOLUTION NO. R-99-11-23-13C4
WHEREAS, the City of Round Rock has previously issued a purchase
order to CMC Steel Fabricators d/b/a Alamo Steel Company for the
fabrication of steel (Package "B") for the construction of the
Convention Center Complex/Stadium, and
WHEREAS, it has been determined that it is necessary to change
said purchase order in accordance with the attached Change Order No. 3,
Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Change Order No. 3 to the purchase order with CMC
Steel Fabricators d/b/a Alamo Steel Company for the fabrication of
steel (Package "B") for the construction of the Convention Center
Complex/Stadium.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended, and the Act.
RESOLVED this 23rd day of Nov r, 1999.
C49RT A. STLUKA R., Ma
A ST: City of Round Roc Texas yor
J E LAND, City Secretary
%:\WPOOCS\RSSOLU I\R91133C4.WPD/119
HKS
CHANGE ORDER
PROJECT: ROUND ROCK CONVENTION CENTER CHANGE ORDER NO:03
COMPLEX Package"B"
TO: Alamo Steel Company INITIATION DATE: 10-Nov-99
321 Old Dallas Rd. ARCHITECTS PROJECT NO.: 6407
Waco, TX 76705 CONTRACT FOR: Steel Order
CONTRACT DATE: 5/13/99
The Contract is changed as follows:
Incorporate the work described in the following Items.All appropriate back up information is attached.
See Attachment'A'for Items included in this Change Order
This Change Order Is not In effect and will not be Included In the Contract Documents until signed by the Owner,Architect and
Contractor.Changes Included herein are subject to all conditions affecting them under the substitution specification section.
SUMMARY
The original Contract Sum was:................................................................................... $1,187,392.00
Net change by previously authorized Change Orders................................................... $2,894.00
The Contract Sum prior to this Change Order was:..................................................... $1,190,286.00
The Contract Sum will be Increased by this Change Order
...................................................................................................................................... $16,875.00
The new Contract Sum including this Change Order will be:....................................... $1,207,161.00
The Contract Time will be Unchanged by (0)Days
The Date of Substantial Completion as of the date of this Change Order therefore is 04-Oct-99
Changes included in the summary above do not include modifications which have been authorized by
Construction Change Directive(s). Authorized:
HKS INC. Alamo Steel Company Round Rock Express Baseball Club
1919 McKINNEY AVENUE 321 Old Dallas Rd. 3400 E.Pal alley
DALLAS,TX 75201-1753 Waco, TX 76705 R7 R X 864
By: Mr. Kevin A. Taylor By: Mr. Marvin Turner By: Mr. R. Sneed
Date: 11/10199 Date:-11111199 Date:
HKS INC. Dallas I Los Angeles I Orlando 1 Richmond/Tampa ®HKS 701-1995
City of Round Rock
2008 Enterprise Dr.
Round Rock, TX 78664
Mr. ob ,J yor
Date:
HKS
CHANGE ORDER NO. 03 ATTACHMENT'A'
Project: ROUND ROCK CONVENTION CENTER
COMPLEX Package"B"
HKS Project#6407
Incorporate the work described in the following Items.All appropriate back up information is attached.
DATE of
Days CONTRACTOR
CHANGE M COST: DESCRIPTION: Added PROPOSAL:
Alamo Steel $4,400.00 Structural Changes-Joist and Detail 0 8/18/99
GO-3
PC-14(Alamo $12,475.00 Steel Clarifications 0 11/8199
Steel)
TOTAL: $16,875.00 TOTAL DAYS THIS CHANGE ORDER: 0
Page 1 of 1
NOV. 5.1999 12:12PM 2 HKS 2149693397 N0.595- P.1/E
HKS
TRANSMITTAL
Date: 11/8199 VIA:Fax
Fax Pages including Cover Sheet: 8
TO; Mr. Steve Gladding Mr. Larry Madsen
Hensel Phelps Construction Co. City of Round Rock
3400 E.Palm Valley 2008 Enterprise Dr.
Round Rock, TX 78664 Round Rock, TX 78664
P(512)733-2212 F(512)733-2204 P(512)218-5552 F(512)218-5563
Mr. R.D. Sneed Mr. Marvin Tumor
Round Rock Express Baseball Club Alamo Steel Company
3400 E.Palm Valley 321 Old Dallas Rd,
Round Rock, TX 78664 Waco, TX 76705
P(512)733-2212 F(512)733-2204 P(254)799-2471 F(254)799-6227
SUBJECT ROUND ROCK CONVENTION CENTER COMPLEX
Package"B"
HKS Project#; 6407 Owner's Project#:
WE ARE TRANSMITTING:
❑ Prints/Copies ❑ Samples ❑ Computer Media
F-1 Originals ❑ Specifications ❑ Other
R For Your Checking and Approval ❑ For Your Disposition
NO.COPIES DESCRIPTION
Please review HKS Recommendations on Alamo Steels request,
1. Alamo Steels change order no.3-Structural Changes-Joist and Detail
Alamo request-C.O.no.3-Total-$10,486.00
HKS recommendation Is Total-$4,400.00
2. PC-14-Alamo request-$15.041 new request$12,4791118199.
HKS recommendation is Total$12,479
Total-$16,879.00
Please advise on the Issue of Change Order No.3
to include Alamo's CO-03 and PC-14(steel only).
REMARKS
CC Greg Davenport By: Kevin A. Taylor
RKS INC. 1919 MoKINNEY AVENUE DALLAS,TX 75201-1753 2141969-5599
0 MKS 749.1 D95
NOV. 6.4999 12:12PM 2 HKS 2149693397 N[0.595. P.2/e
HKS
Kavin A.Taylor
November 09,1999
Mr. Larry Madsen
City of Round Rock
2008 Enterprise Dr.
Round Rock, TX 78664
Re: ROUND ROCK CONVENTION CENTER
COMPLEX Package"H"
HKS Project#: 6407 Owner's Project No. .
Proposed Change#PC-14(Alamo Steel)
Dear Mr. Madsen:
Please find attached,the contractor's signed proposal for all items included in PC-14(Alamo Steel). As you are aware,
this Proposed Change was submitted to incorporate the following change to the contract documents:
Steel Clarifications
In accordance with the General Conditions ofthe Contract for Construction,HICS and our consultants have reviewed this
proposal and to the best of our knowledge and belief,a cost of$12,475.00 represents a fair and reasonable proposal. We
therefore recommend your approval.
Please review the Proposed Change at your earliest convenience and notify all parties of your approval or rejection,so that
we may prepare a Change Order(if necessary)to incorporate this work into the contract.
Should you have any questions,please contact us any time.
sincerely,
Kevin A. Taylor
Construction Contract Administrator
Attachments
Copy: Mr. Marvin Turner
Mir #=c p1tb
HKS INC. 1919 McKINNEY AVENUE DALLAS,TX 75201.1753 214/969-5599
DATE: November 16,1999
SUBJECT: City Council Meeting—November 23,1999
ITEM: 13.C.4. Consider a resolution authorizing the Mayor to execute Change
Order No.3 to the Purchase Order to CMC Steel Fabricators dba
Alamo Steel Co.for steel fabrication(Package B)for the
Convention Center Complex/Stadium project. Change Order No.3
increased the contract by$16,875.00 and includes additions and
changes to the steel package as found needed on the plans after
review. HKS,Project Architect,and Round Rock Express Baseball
Club agree with this change. Staff recommends approval. Staff
Resource Person:Jim Nuse,Public Works Director.