Contract - JD Ramming Paving - 6/26/2014Contract Quantity Adjustment/Change Order
MV, CW12
Department: Transportation
Project
Name: 2012 Street Maintenance Project Overlay
City Project
ID Number MNT12
Justification
Date: 5/21/14
Change Order/Quantity
Adjustment No. 1
Pagc I of 3
quantity Adjustment/Change Order * 1 is needed to adjust finall quanities that was required to complete nessesary work for the project,
additional work included; a deduct in asphalt overlay, level -up and minor repair. There was an increase In concrete fiat work including
additional sidewalk, driveways and curb & gutter that was required to replaced associated with the project, specifically In the Eagles Nest area.
SUMMARY
Amount
% Change
Original Contract Price:
$4,771,800.00 =
Previous Quantity Adjustment(s):
$0.00
This Quantity Adjustment.
$273,762.80
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
$4,771,800.00
Previous Change Order(s):
0.00
This Change Order:
$0.00
0.00
Total Change Order(s) To Date:
0.00
Adjusted Contract Price [Original Contract Price Plus
-
1.
Quantity Adjustments) Phis Change Order(s)]:
$5,0451562.80
Difference behmnn Original and Adjusted Contract Primo:
$273,782.80
Original Contract Time:
325
Time Adjustment by previous Quan. Adj./Change Order.
Time Adjustment by this Quan. Adj./Change Order.
240
New Contract Time:
565
'Sdbm1tbW,&r A ji6io al
City Project
Manager:
Mayor/City In,�
Manager
Signature
R-2014-1533
W
.26 .
—/.C/
Contract Quantity Adjustment/Change Order
- �+`nwcxrcxw
ter,:}911i
Project Name: 2012 Street Maintenance Project Overlay
Quan. Adj./Change Order No.:
Chan®e Order Data
Page 2 of 3
Contract
rime
Adjustment
M it
Page 3 of 3
Contract Quantity Adjustment/Change Order
rer, �AIrY
Project Name: 2012 Street Maintenance Project Overlay
Quart. Adj./Change Order No.:
Ouanttty Adiustment Data
Bid item # item Description
Unit Qty.
Unit Price
Contract
Time
Amount Adjustment
;.
f
1 2" Overlay Type D HMAC
-6130.4 $
86.00
-$527,216.00
2 Pavement Repairs
500 $
100.00
$50,000.00
3 Minor Repairs
-250 $
150.00
-$37,500.00
4 Level U
-100 $
150.00
-$15,000.00
5 Ede Millin
-4820 $
1.55
-$7,471.00
6 Surface Millin
-8180 $
4.50
-$36,810.00
7 Remove & Replace Curb & Gutter
4172 $
45.00
$187,740.00
8 Remove & Replace Driveway
9369 $
24.00
$224,856.00
9 Remove & Replace Sidewalk
34970 $
14.50
$507,065.00
10 Manhole Adjustment
-108 $
450.00
-$48,600.00
11 Valve Adjustment
-5 $
125.00
-$625.00
12 Concrete Curb Ram
4 $
2.200.00
$8,800.00
13 Remove & Replace Valley Gutter
-543 $
40.00
-$21,720.00
14 Traffic Control
0 0 $
4.500.00
$0.00
IS Thermoplastic Pavement Markin
-10818 $
0.90
-$9,736.20 240