Loading...
CM-2014-472 - 7/25/2014City of Round Rock Agenda Item Summary Agenda Number: Title: Consider executing Change Order No. 2 with Muniz Concrete & Contracting Inc. regarding the Brushy Creek Regional Trail Gap Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 7/25/2014 Dept Director: Rick Atkins, Director Cost: $33,890.15 indexes: General Self -Financed Construction Attachments: 07-25-14 BC Gap_CO2 Muniz, 07-25-2014—PARD—Elizabeth Sherman—City Manager_BCTrail_CO#2, LAF - 07-25-14 CO#2 w- Muniz Concrete Contracting- Brushy Creek Gaps Trail Project (00306093xA08F8) Department: Parks and Recreation Department Text of Legislative File CM -2014-472 Approval of this item allows the contractor to install water gap fencing and various other fencing, match existing ribbon curb on parking lot, install rock filter dams and sediment control fence for water quality, improve an area inlet, and add masonry materials to a retaining wall. The project includes approximately 2 miles of 10' wide concrete trail from A.W. Grimes Blvd to the west end of the existing Brushy Creek East Trail behind the Sonoma subdivision. Additional project improvements include site furnishings, two (2) pedestrian bridges and trail head improvements (parking, bike locker, signage) at Rabb Park. The project has funding from FHWA/TxDOT ($2,300,000), Williamson County ($400,000) and the City of Round Rock ($190,000). The construction contract is for 270 calendar days which corresponds to construction completion in Summer 2014. Staff recommends approval of the item. City or Round Rock Page 1 Printed on 712312014 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCILICITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: PARD Project.MgrlResogrce: Aileen Dryden Council Action: Q ORDINANCE 0 Agenda Wording 0 City Manager Approval Project Name: Brushy Greek.Reglonal Trail Gap ContractorNendOO Moritz Concrete &'.Conlractino Inc. RESOLUTION CMA Wording Consider executing Change Order No. 2 with Muniz Concrete & ContractingInc. regarding the,Brushy Creek. Regional Trail Gap Project: Attorney Approval Attorney Date O:\wdox1SCClnts\0199\0001\MISC\00306093.XLS Updated 613108 Form R 0/11)L CONSTRUCTION CONTRACT CHANGE ORDER NUMBER: 2 Page loft — ,.CONTRACTOR: Munlz Concrete&Contracting Inc. 2. Change Order Work Limits: Sta. 3+00 to Ste. 30+00 3. Type of Change (an federal -aid non-exempt projects): Minor (Major/Minor) 4. Describe the change and the reason for the change order. When necessary, Include exceptions to this agreement. CO # 2Includes:2 EA Water Gaps In the chain Link Fence,1 Ped Gate, changing 1 foot ribbon curb to 1S Inch Ribbon Curb to match adjacent Parking Lot, Erosion Control Item Overruns, Adding additional Contract Time, Elevated Sidewalk for Parking Lot Drainage, Inlet No.2 Riser, Machine Standby I]me, Re -stake Parking Lot, Remove/Replace Wet Subgrade 5. New or revised plan sheet(s) are attached and numbered: n/a Each signatory herebywanards that each has the authority to execute this Change Order. By slgning this change order, the contractor agrees to welve any and all Balms for additlonaioompensaeon duets anyand all other expenses, addlnonalchanges for time, overhead and progporlost cfmmpensatbn as a result fthis change. Fusthep the contractor agrees that IN, agreement Is made in accordancewith Item 4 andtheeontract. Exceptions should be noted In the response for 45 above. THE CONTRACTOR Date 06/10/14 By 9c-..iJ d • Z Typed/Printed Name Lonny D. Rodriguez Typed/Printed Title Vice President CCSJ: Project: Highway: County: District: Contract Number: The following Information must be provided Time Ext. #: 2 Days added on this C.O.: 102 Amt added by this change order: Days Participating: Amount participating: Signature Date R OMMENDED FOR EXECUTION: Name/ I 4t W' ,,,t L ,� 1_ Date Name/ritle Date �'s -• - r-`m"`^s'v [sj" ROWD F1 REQUEST APPROVAL Name/Title Date Name tie Date 7/aI N e/Tltle I Date' Engineer's Seal: CM -2014-472 Name/Title Date ]APPROVED [J REQUEST APPROVAL Name/ilt a Date ❑APPROVED 1-1 REQUEST APPROVAL Name/fitle Date F-JAPPROVED CONSTRUCTION CONTRACT CHANGE ORDER NUMBER: 2 Estimated Cost $33,890.15 TABLE A: Force Account Work and Materials Placed into Stock TABLE B: Contract Items CCSJ: Paid by Invoice? ( 0Yes E] No ) TXDOT Form 2146-L TAB (Rev. 10/11) Pagel oft ORIGINAL + PREVIOUSLY REVISED NEW ITEM DESCRIPTION UNIT UNIT PRICE QUANTITY ITEM COST QUANTITY ITEM COST OVERRUN/ UNDERRUN 1 Furnish& install 6'Galy. Chain Link IS 1,618.75 0.00 1.00 1,618.75 1,618.75 Water Gap No. l Sta 29+83 Trail A 2 Furnish& install 6'Galy. Chain Link LF 2,368.75 0.00 1.00 2,368.75 2,368.75 Water Gap No. 2 Sta 22+19 Trail A 3 Furnish & install 6' Galy. Chain Link EA 298.75 0.00 1.00 298.75 298.75 Ped Gate, UX 5' Sta 30+25 Trail A 4 Concrete Ribbon Curb (1001))(18") LF 15.00 0.00 921.00 13,815.00 13,815.00 5 Deduct qty of Concrete Curb 12.00 921.00 11,052.00 0.00 - 11,052.00 (Ribbon)(MOD)(12") 6 Rock Filter Dams (Install) (Type 2) 26.00 0.00 - 47.00 1,222.00 1,222.00 7 Rock Filter Dams (Remove) 15.00 0.00 47.00 705.00 705.00 8 Temp Sed Cntrl Fence (Install) 2.25 0.00 264.00 594.00 594.00 9 Temp Sed Cntrl Fence (Remove) 0.25 0.00 - 264.00 66.00 - 66.00 TOTALS 11,052.00 20,688.25 9,636.25 TXDOT Form 2146-L TAB (Rev. 10/11) Pagel oft CONSTRUCTION CONTRACT CHANGE ORDER NUMBER: 2 TABLE B: Contract Items (Continued) CCSJ: TXDOT Form 2146-L TAB (Rev. 10/11) Page 2 oft ORIGINAL + PREVIOUSLY REVISED NEW ITEM DESCRIPTION UNIT UNIT PRICE QUANTITY ITEM COST QUANTITY ITEM COST OVERRUN/ UNDERRUN 10 ALdd 46 Calendar Days Due to chedule Delays (Contract Time My) 11 levated Sidewalk 2,735.65 0.0c 1.0c 2,735.65 2,735.6 12 Install Cast -in-place Riser on New LS 3,125.00 0.0c 1.00 3,125.00 3,125.0 Area Inlet Box 13 Add 44 Calendar Days Due to Schedule Delays (Contract Time Only) 14 Machine Standby Time, CAT 953 LS 6,572.5C 0.0c 1.0c 6,572.5C 6,572.5 rack Loader 15le-stake Revised Parking Lot LS 1,943.75 0.0c 1.0c 1,943.75 1,943.7 eplace Wet Subgrade with Flex ase (Parking Lot)(Exist Unit Prices) 16 Excavation CY 16.00 0.00 77.00 1,232.00 1,232.0 17 Flex Base CY 65.00 0.00 77.00 5,005.0c 5,005.0 18 Retaining Wall (Quarry Cut SF 26.00 0.00 140.00 3,640.00 3,640.0 imestone Blocks 4'X 2'X 2') The "Totals" from Table B of the previous work sheet TOTALS 11,052.0 11,052.0 20,688.2 44,942.1 9,636.2 33,890.1 jq TXDOT Form 2146-L TAB (Rev. 10/11) Page 2 oft INSTRUCTIONS FOR PREPARING THE CHANGE ORDER (Local Agency) The following information is provided to assist you in preparing the Change Order (CO). 1 Insert the Contractor's name as it appears in the contract. 2 Insert the work limits for the Change Order. 3 Indicate if a change is major or minor. 4 Give a narrative of the revised work being authorized in the change order. If the CO affects pedestrian elements, state in the narrative that a copy of this CO must be sent to the Field Coordination Section of the Design Division. Address time by one of the following methods: 1) Add the time extension number and time in the box provided. 2) State in the narrative that no time is added by this CO. 3) State in the narrative that time will be addressed later in the project when the time impact of the change order is better known. Methods 1 and 2 are preferred. Method 3 should not be a normal practice. If time can not be agreed on with the contractor upon execution of a CO, method 3 is acceptable. In this case, time associated with this CO will be non- participating until the time justification is provided. 5 Attach any new/revised plan sheet(s). 6 For TxDOT use only. The TxDOT representative must designate if this change order is participating by providing a value for the days and amount participating. If the change order is non -participating, enter a zero "D" in the fields. 7 Direct the contractor to sign in the contractor's signature block. 8 Affix the seal of the authorized local representative in the space located at the left corner of the bottom of the CO Form. Adhere to Change Order Approval Policy of local agency. TXDOT Form 2146-L INSTR (Rev. 10/11) Page i of 1