Request for City Council/City Manager Action
Please submit this form when placing items on the council agenda or when submitting an item to the City Manager for approval.
Department: Engineering and Developmental Services Project Manager/Resource: Michael Thane
Contact Person: Latha or Laura (Kathy) Council Meeting Date: NA
Project Name: South Creek Channel Improvement Funding Source: Capital Project Funds (G.O. 2001)
ContractorNendor Name: Epsey Consultants, Inc.
Amount:
Assigned Attorney: Steve Sheets / Rose
$7.962.00 (contract, agreement,amendment,change order, purchase order,etc.)
Is Funding Required? Yes
Council Agenda Item Yes
Submission to City Manager - Yes
X
X
No
No n
No
Rsittu--J�, �t3 LIEU LUU44
(see required signatures below before submission to the City Manager)
▪ Initial Construction Contract
▪ Construction Contract Amendment
Change Order #
n Change in Quantity
El Unforeseen Circumstances
▪ Initial Professional Services Agreement
Amount
▪ Supplemental Professional Svcs. Agr. # 1 $7,962.00
Purchasing/Service Agreement
▪ Purchase Order
Item(s) to be purchased:
▪ Other (Please clearly identify action on lines below)
Agenda Wording: Consider an action by the City Manager to execute Supplemental Agreement # 1 to the Agreement for
Engineering Services with Espey Consultants, Inc. for the South Creek Channel Improvement Project.
For Submission to City Mana•er On!
Project Mgr. Signature:b . /jj rte,,. Date: 441/S /o1
Dept. Director Signature: _L _ .— if- Date: / Z%/5104—
City Attorney Signature: `\ ' • �; i of 1 Date: 4 d
City Manager Signature: Date: /
* Le al pproval is required for all items requesting City Manager's approval.
Finance Approval El Finance -Date and Signature: L. Olsen 12-15-04
Purchasing -Date and Signature:
XO Budget -Date and Signature: N/A ESW 12/15/04
g/administration/cmgr-council action.xls 11-1-04
DATE: December 10, 2004
SUBJECT: City Manager Approval
ITEM: Consider an action by the City Manager to execute
Supplemental Agreement No. 1 to the Agreement for
Engineering Services with Espey Consultants, Inc. for the
South Creek Channel Improvement Project.
Department: Engineering and Development Services
Staff Person: Michael Thane, Sr. Engineer/Engineering Manager
Justification:
Espey Consultants is designing improvements to channel and drainage systems in
the interest of flood control, appearance, and to facilitate maintenance for the Dry
Branch Tributary No.1 channel that extends from A.W. Grimes Boulevard easterly
through the South Creek Subdivision. A 24 -inch wastewater line currently extends
across the channel where the proposed improvements will occur. Because of
conflicts with the flow lines, the City has requested that Espey investigate
alternative alignments for the existing wastewater line as it crosses Dry Branch
Tributary No. 1.
This Supplemental Agreement No. 1 includes Espey analyzing several alignment
alternatives, including rerouting upstream, use of sag sewers, and installing sag
drains. Espey will design and provide plans, specifications, and a cost estimate
using the selected wastewater alignment from the analysis. Espey will incorporate
the wastewater line design into the existing plans for the channel improvements.
Funding:
Cost: $7,962.00
Source of funds: Capital Project Funds (GO Bond 2001)
Outside Resources: Espey Consultants, Inc.
Background Information:
Dry Branch Tributary No. 1 channel traversing through South Creek subdivision is
difficult to maintain and is critical for carrying flood waters safely through the
subdivision. This same channel is experiencing stabilization problems near its
intersection with Gattis School Road. Also, there have been flooding problems in the
Greenslopes Subdivision just west of Dry Branch Tributary No. 1 near the northern
intersection of Greenlawn Blvd. and Parkside Circle. This project will provide design
of channel improvements that will increase channel capacity and improve the
appearance and maintainability of Dry Branch Tributary No. 1. The City Manager
approved the original agreement with Espey Consultants, Inc. on September 10,
2004.
Public Comment: N/A
STATE OF TEXAS
COUNTY OF WILLIAMSON
SUPPLEMENTAL AGREEMENT NO. 1
TO AGREEMENT FOR ENGINEERING SERVICES
FIRM: Espey Consultants, Inc. ("Engineer")
ADDRESS: 3809 South 2nd Street, Suite B-300, Austin, TX 78704
PROJECT: South Creek Channel Improvements
This Supplemental Agreement No. 1 to Agreement for Engineering Services is made by and
between the City of Round Rock, Texas, hereinafter called the "City" and Espey Consultants,
Inc., hereinafter called the "Engineer".
WHEREAS, the City and Engineer executed an Agreement for Engineering Services,
hereinafter called the "Agreement", on the 10th day of September, 2004 for the South Creek
Channel Improvements Project in the amount of $12,754.00; and
WHEREAS, it has become necessary to amend the Agreement to modify the provisions for the
scope of services, to increase the compensation by $7,962.00 to a total of $20,716.00, and to
modify the provision for notices to proceed; and
NOW THEREFORE, premises considered, the City and the Engineer agree that said
Agreement is amended as follows:
I.
Article 2, Scope Of Services To Be Performed By Engineer and Exhibit B, Services To Be
Performed By The Engineer shall be amended as set forth in the attached Addendum To Exhibit
B.
II.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$7,962.00 the lump sum amount payable under the Agreement for a total of $20,716.00, as
shown by the attached Addendum to Exhibit D.
Supplemental Agreement
Espey-south creek channel improve; 78075
Rev.03/02/04
64836
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Agreement in duplicate.
ESPEY CONSULTANTS, INC.
By:
Date
CITY OF ROUND ROCK
By:
es R. Nuse, P.E., City Manager
Z- 20-041
Date
Supplemental Agreement
Espey-south creek channel improve; 78075
2
APP
VED AS TO ORM:
1
Steph n L. Sheets, City Attorney
Rev.03/02/04
64836
ADDENDUM TO EXHIBIT B
Services to be Performed by the Engineer
The changes to the scope of this project are as follows:
EXHIBIT B
Engineering Services
Work Breakdown Structure
1. Alignment Alternatives Analysis — EC will investigate alignment alternatives for the existing 24"
wastewater line as it crosses Dry Branch Creek. We anticipate analyzing 4 to 5 alignment
alternatives, including rerouting upstream, use of sag sewers, and installing sag drains. Analysis
will also include iterative HEC -RAS modeling of Dry Branch Creek Tributary No. 1 as
necessary. Approximately two project meetings and five conference calls will be necessary to
complete the analysis. EC will verbally recommend a design solution to the City of Round Rock.
No written report will be prepared.
2. Wastewater Line Design — EC will design and provide plans, specifications, and a cost estimate
using the selected wastewater alignment from the previous analysis. EC will incorporate the
wastewater line design into the existing plan and profile sheets; however, additional details and
sections will be required to accurately describe the proposed work. This work will be included in
the next submittal to the City (anticipated to be the 90%). It is anticipated that this design will not
include any additional survey or geotechnical investigations.
ADDENDUM TO EXHIBIT D
Fee Schedule
The changes to the fee schedule for this project are as follows:
EXHIBIT D
Fee Schedule
Budget Estimate
A budget breakdown by task is included in the following table. The total estimated fee is $7,962, which
includes an estimated $50 for expenses. The total authorization for this project is increased to $20,716.00.
LABOR COST DETAIL
Description
1 Alignment Alternatives Analysis
2 Wastewater Line Design
subtotals:
average raw labor rate:
subtotal by labor classification:
COST SUMMARY
Labor
Man -Hour Estimate by Labor Classification
Project Engineering
Principal Manager Staff Technician Admin
1 16 16 8 1
1 8 24 8 1
2 24 40 16 2
$ 50.00 $ 43.00 $ 30.00 $ 16.50 $ 15.00
$ 100 $ 1,032 $ 1,200 $ 264 $ 30
Subtotals
Time Cost
(hrs) ($)
42 $ 1,365
42 $ 1,261
84 $ 2,626
Direct Labor Overhead Rate (Fringe Benefit) 31% x Labor $ 814
General and Administrative Overhead Rate 138% x Labor $ 3,624
Profit (12% of Total Labor Cost) $ 848
Total Labor Cost (Incl. Profit) $ 7,912
Expenses (mileage, courier, reproduction, etc.):
$ 50
TOTAL: $ 7,962