CM-06-03-037DATE: March 2, 2006 SUBJECT: City Manager Approval - March 10, 2006 ITEM: Action authorizing the City Manager to execute Change Order No. 1 to the Old Settlers Park Baseball Fields Drainage and Parking Improvements project contract with H. Deck Construction Co. Department: Staff Person: Parks and Recreation Department James Hemenes, Parks Development Manager Ruth Haberman, P.E., Engineer - EDS Justification: This Change Order is to adjust the scope of the project. There is a need to adjust the baseball field grading in Area 5. There is limited funding, and the base bid, which addressed Area 7 only, was valued at nearly the total amount available for the project. In order to accommodate the additional need, we have removed several items from the base bid that can be accomplished by PARD staff at a later date. Funding: Cost: Source of funds: $7,170.55 2002 G.O. Bonds and General Self Financed Construction Fund Outside Resources: H. Deck Construction Co. Background Information: The Project: Sports Capital of Texas Plan was developed last year to plan for the necessary upgrades to our existing sports complexes, at Old Settlers Park at Palm Valley, to make them top notch recreational and tournament facilities. As part of the Project, Sports Capital of Texas Plan, drainage throughout the OSPV Baseball Complex will be improved to allow increased playability on the fields after rain. This project also provides increased parking and upgrades for Fields 1-4. Public Comment: N/A CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER DEPARTMENT: Engineering & Development Services PROJECT: Old Settlers Park Baseball Fields Drainage and Parking Lot Improvements ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $342,795.15 $0.00 $7,170.55 $7,170.55 CHANGE DATA PAGE 1 OF 1 DATE: CHANGE ORDER NO: JUSTIFICATION: 2/27/2006 1 Change of scope. ITEM # DESCRIPTION OF CHANGES UNIT QTY. UNIT PRICE AMOUNT ADDED DAYS CALENDAR/ WORKING 15 2' wide trickle channel SF -982 $5.50 21 12" sediment trap inserts EA 7 $750.00 22 18" sediment trap inserts EA -1 $1,200.00 23 24" sediment trap inserts EA -2 $1,500.00 A2-1 A2-2 Unclassified excavation Non-native seed for erosion control CY 151 $7.25 ($5,401.00) ($5,250.00) ($1,200.00) ($3,000.00) SY 11890 $1.10 A2-3 Silt fence LF 266 $2.30 $1,094.75 $13,079.00 $611.80 15 A2-4 Tree protection LF 760 $3.00 A2-5 8" HDPE culvert LF 38 $12.00 $2,280.00 A2-6 Sloped headwall EA 2 $1,500.00 A2-8 Tree well fill LS 1 $1,500.00 PREPARED BY: PROJECT MANA 2/27/2006 ER Ru h Haberman, P.E. Date H. Deck Construction Company BY: 0,/ CONTRACTOR 4,‘ TITLE: et) APPROVED: 03-0 310-1) CITY OF ROUND ROCK _6t/flys m/69 PE, Cijoi TOTAL: $456.00 $3,000.00 $1,500.00 $7,170.55 15 PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: PREVIOUS CHANGE ORDER: TOTAL % CHANGE: ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $349,965.70 2.09% 0.00% 2.09% constco2tformseilk Request for City Council/City Manager Action City Council City Manager Submit completed form for all City Manager and City Council approvals. RECD MAR 0 9 2006 For Administration Use ONLY Recei Tag #� Department Name: Contact Person: Project Manager/Resource: Project Coordinator: Assigned Attorney: EDS / Parks and Recreation Latha Kumar/Tiffany Calley James Hemenes Ruth Haberman, P.E. Council or City Manager Approval Date: Blue Sheet Wording Original Documents Received: j_ OId Settlers Park Baseball Fields Drainage & Project Name: Parking Lot Improvements ContractorNendor: Funding Source: Amount: Account Number: 3/10/2006 H. Deck Construction Co. j 2002 G.O. Bonds and kQi�rC.�` e t 2073808 ttai di ' . - itA $7,170.55 Action authorizing the City Manager to execute Change Order No. 1 to the OId Settlers Park Baseball Fields Drainage and Parking Improvements project contract with H. Deck Construction Co. Finance Information Is Funding Required? s Yes No 0 0 x Finance Approval Finance EJFinance EJPurchasing Budget Initial Construction Contract Construction Contract Amendment # Change Order Change in Quantity Unforeseen Circumstances Initial Professional Services Agreement Supplemental Professional Svcs. A # Purchasing/Service Agreement Purchase Order Item(s) to be purchased: Amount $7,170.55 Other (Please clearly identify action on lines below) Date Date Date Date Required for Submission of ALL City Cou ci and City Manager Items Project Mgr. Signature: Dept. Director Signature: City Attorney Signature*: City Manager Signature: pproval is required for all items. Date: d,%, Updated 2/16/06 Request for City Council/City Manager Action City Council M City Manager Submit completed form for all City Manager and City Council approvals. Department Name: EDS / Parks and Recreation Contact Person: Latha Kumar/Tiffany Calley Project Manager/Resource: James Hemenes Project Coordinator: Ruth Haberman, P.E. Assigned Attorney: Council or City Manager Approval Date: Blue Sheet Wording For Administration Use ONLY Received: Tag P J Origi al Documents Received: Old Settlers Park Baseball Fields Drainage & Project Name: Parking Lot Improvements ContractorNendor: Funding Source: Amount: Account Number: 3/10/2006 H. Deck Construction Co. $7,170.55 Action authorizing the City Manager to execute Change Order No. 1 to the Old Settlers Park Baseball Fields Drainage and Parking Improvements project contract with H. Deck Construction Co. Finance Information Is Funding Required? ral Yes 1 No Finance Approval ElFinance EJFinance iPurchasing Budget x Initial Construction Contract Construction Contract Amendment # Change Order # 1 Change in Quantity Unforeseen Circumstances Initial Professional Services Agreement Supplemental Professional Svcs. A # Purchasing/Service Agreement Purchase Order Item(s) to be purchased: Amount $7,170.55 Other (Please clearly identify action on lines below) L. Olsen N/A E. Wilson N/A HB N/A CYD Date 3/8/2006 Date 3/8/2006 Date 3/8/2006 Date 3/7/2006 Required for Submission of ALL City Council and City Manager Items Project Mgr. Signature: Dept. Director Signature: City Attorney Signature*: City Manager Signature: * Legal Approval is required for all items. Date: Date: Date: Date: Updated 2/16/06