Loading...
CM-06-04-096Change Order No. 2 Project Name: East Water Transmission Line, Phase 3A-2 HDR Project No.: 07225-16810 Project Owner: City of Round Rock 212 Commerce Cove, Round Rock, TX 78664 Date of Issuance: April 13, 2006 Project Contractor: FT Woods Construction Services 1966 S. Austin Ave., Georgetown, TX 78626 Date of Contract: June 06, 2005 Date of Notice to Proceed: August 22, 2005 Original Completion Date: March 20, 2006 Contract Period: 210 Calendar Days It is agreed to modify the Contract referred to above as follows: CPR # ITEM AND DESCRIPTION OF CHANGES CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME 3 Install 12" Tapping Sleeve and Valve $ 5,098.51 2 Deduct for items not exercised under CPR No. 2 for Landscaping, sidewalks, and two 45 degree bends ($2,862.01) 0 Difference Net $ 2,236.50 2 Summary: It is agreed to modify the Contract referred to above as follows: Contract Price prior to this Change Order Contract Time prior to this Change Order $ 778,816.91 220 days - March 30, 2006 Net Increase (decrease) of this Change Order Net Increase (decrease) of this Change Order $ 2,236.50 2 Revised Contract Price with all approved Change Orders Revised Contract Time with all approved Change Orders $ 781,053.41 222 days - April 1, 2006 The changes included in this Change Order are to be accomplished in accordance with the terms, stipulations and conditions of the original Contract as though included therein. Accepted for Corwtra for by: Recommended for Approval bHDR Engineering, Inc.): Approved for Owner &lirae aig, oved: (Other - when required) Date: ylit fob Date: '7/376,10 Attest: a Date: OILLRtn 4-214)4Q Distribution: 0 Owner 0 Contractor 0 Office 0 Field ❑ Other DATE: April 24, 2006 SUBJECT: City Council Meeting - May 11, 2006 ITEM: Action authorizing the City Manager to execute Change Order Number Two to the Contract with F.T. Woods Construction Services, Inc. for the construction of the East Water Transmission Line, Phase 3A-2 Project. Department: Water and Wastewater Utilities Staff Person: Tom Clark, Director of Utilities Justification: This Change Order is to provide a 12" tapping Sleeve and Valve at the intersection of Highway 79 and Redbud Lane. Rather than cutting in a 12" Tee per the plans, this change was required because we were unable to get complete closure on an existing valve. Funding: Cost: $2,236.50 Source of funds: Utility Self -Financed Const. -Water Outside Resources: F.T. Woods Construction Services, Inc. Background Information: Change Order Number Two is for additional costs associated installing a 12" tapping Sleeve and Valve rather than cutting in a Tee per the plans. This change order includes a deduct of $2,862.01 for items not used for landscaping and two 45 degree bends not used. Public Comment: N/A Request for City Council/City Manager Action City Council E] City Manager finF For Administration Use ONLY Receiv : : Tag # -tCp,04-0q Submit completed form for ALL City Manager and City Council approvals. Original Documents Received: 76 Department Name: Contact Person: WANW Utility Lathe Kumar/Tiffany Calley Project Manager/Resource: Don Rundell Project Coordinator: Tom Clark Assigned Attorney: Council or City Manager ApprovaUAgenda Date: 4/28/2006 Blue Sheet Wording Project Name: East Water Transmission Line, Phase 3A-2 ContractorNendor: F.T. Woods Construction Services Funding Source: Utility Self -Financed Const. -Water Amount: $2,236.50 Action authorizing the City Manager to execute Change Order Number Two to the Contract with F.T. Woods Construction Services, Inc. for the construction of the East Water Transmission Line, Phase 3A-2 Project. Finance Information Is Funding Required? El Yes 0 No xx Initial Construction Contract Construction Contract Amendment Change Order # 2 Change in Quantity Unforeseen Circumstances Initial Professional Services Agreement Supplemental Professional Svcs. Agr. # Purchasing/Service Agreement Purchase Order Item(s) to be purchased: Amount $2,236.50 Other (Please clearly identify action on lines below) Finance Approval Finance Finance Purchasing Budget % Date For Submission to ALL City Co'cil • i ane r Action Items Project Mgr. Signature: dIA ' Date: V-02 eoc, Dept. Director Signature*: i i ' / Date: el --,77 c/—e, 4, City Attomey Signature*: Date: 146 •-ele City Manager Signature: Date: q -D.8.0(.0 Dept Director end L ; f Approval and is required for ALL items requesting City ManagsMClty Council approval. Updated 6-9-05 Request for City Council/City Manager Action City Council 0 City Manager Submit completed form for ALL City Manager and City Council approvals. Department Name: Contact Person: W/WW Utility Latha Kumar/Tiffany Calley Project Manager/Resource: Don Rundell Project Coordinator: Tom Clark Assigned Attorney: Council or City Manager Approval/Agenda Date: 4/28/2006 Blue Sheet Wording For Administration Use ONLY Received: Tag # Original Documents Received: Project Name: East Water Transmission Line, Phase 3A-2 ContractorNendor: F.T. Woods Construction Services Funding Source: Utility Self -Financed Const. -Water Amount: $2,236.50 Action authorizing the City Manager to execute Change Order Number Two to the Contract with F.T. Woods Construction Services, Inc. for the construction of the East Water Transmission Line, Phase 3A-2 Project. Finance Information Is Funding Required? ED Yes C No xx Initial Construction Contract Construction Contract Amendment Change Order # 2 Change in Quantity Unforeseen Circumstances Initial Professional Services Agreement Supplemental Professional Svcs. Agr. # Purchasing/Service Agreement Purchase Order Item(s) to be purchased: Amount $2,236.50 Other (Please clearly identify action on lines below) Finance Approval DFinance L. Olsen 4/26/2006 EJFinance N/A E. Wilson 4/26/2006 Purchasing N/A HB 4/26/2006 El Budget N/A CYD Date 4/25/2006 For Submission to ALL City Council and City Manager Action Items Project Mgr. Signature: Date: Dept. Director Signature*: Date: City Attorney Signature: Date: City Manager Signature: Date: * Dept. Director and Legal Approval and is required for ALL items. requesting City Manager/City Council opp Updated 6-9-05