CM-06-06-133STATE OF TEXAS COUNTY OF WILLIAMSON SUPPLEMENTAL AGREEMENT NO. 6 TO CONTRACT FOR ENGINEERING SERVICES FIRM: Baker-Aicklen & Associates, Inc. ("Engineer") ADDRESS: 507 W. Liberty Avenue, Round Rock, TX 78664 PROJECT: Red Bud Lane (CR 122) Phases I & II This Supplemental Agreement No. 6 to Contract for Engineering Services is made by and between the City of Round Rock, Texas, hereinafter called the "City" and Baker-Aicklen & Associates, Inc., hereinafter called the "Engineer". WHEREAS, on the 13th day of May, 1999, the City and Engineer executed a Contract for Engineering Services, hereinafter called the "Agreement", for the Red Bud Lane (CR 122) Phases I & II in the amount of $170,600.00; and WHEREAS, on the 26th day of April, 2001, the City and Engineer executed Supplemental Agreement No. 1 to extend the Contract Period from January 31, 2000 to April 30, 2002, to modify the scope of services, and to increase the compensation by $10,900 for a total of $181,500; and WHEREAS, on the 13th day of September, 2001, the City and Engineer executed an Additional Services Authorization to the Agreement to modify the scope of services and to increase the compensation by $1,400.00 for a total of $182,900.00; and WHEREAS, on the 25th day of April, 2002, the City and Engineer executed Supplemental Agreement No. 2 to extend the Contract Period from April 30, 2002 to October 31St, 2003, to modify the scope of services, and to increase the compensation by $900.00 for a total of $183,800.00; and WHEREAS, on the 9th day of January, 2003, the City and Engineer executed Supplemental Agreement No. 3 to extend the Contract Period from October 31St, 2003 to October 31, 2004, to modify the scope of services, and to increase the compensation by $134,657.31 for a total of $318,457.31; and WHEREAS, on the 23rd day of September, 2004, the City and Engineer executed Supplemental Agreement No. 4 to modify the provisions for the scope of services, to increase the compensation by $8,345.00 to a total of $326,802.31, to extend the Agreement, and to modify the provision for notices to proceed; and Supplemental Contract baker-aicklen-redbudph2; STO2CR122; 100166 CM---C(v-- /33 Rev.03/02/04 84275 WHEREAS, on the 14th day of April, 2005, the City and Engineer executed Supplemental Agreement No. 5 to modify the provisions for the scope of services and to increase the compensation by $14,120.00 to a total of $340,922.31; and WHEREAS, it has become necessary to amend the Agreement to modify the provisions for the scope of services and to increase the compensation by $2,030.00 to a total of $342,952.31; and NOW THEREFORE, premises considered, the City and the Engineer agree that said Agreement is amended as follows: I. Article 2, Scope Of Services To Be Performed By Engineer and Exhibit B, Services To Be Performed By The Engineer shall be amended as set forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. II. Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by $2,030.00 the lump sum amount payable under the Agreement for a total of $342,952.31, as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental Agreement in duplicate. BAKER -AI KLEN & ASSOCIATES, INC. By: /d Date CITY OF ROUND ROCK By: Date l_p-Q-QLD APP ;32 VED S T 1 FORM: JA rnE 5 Q, MUSE P.. E P.E. Steph . n L. Sheets, City Attorney CIYy mgNA6e K. Supplemental Contract baker-aicklen-redbudph2; ST02CRI22; 100166 2 Rev.03/02/04 84275 ADDENDUM TO EXHIBIT B Engineering Services The changes to the scope of this project are as follows: 1. Field survey CR 122 right-of-way from CR 123 to Evergreen to tie HDR parcels. 2. Field locate 2 — 24" RCP headwalls at Forest Ridge. 3. Revise CAD file to reflect HDR right-of-way as surveyed. ADDENDUM TO EXHIBIT C Work Schedule The changes to the Work Schedule for this project are as follows: Action Item Completion Date 1. Additional surveying and engineering not anticipated in original agreement. See Exhibit B. May 12th, 2006. ADDENDUM TO EXHIBIT D Fee Schedule The changes to the fee schedule for this project are as follows: EXHIBIT D FEE SCHEDULE Task Personnel Hours Rate Total 1. Review Plans for possible revisions Engineer 8 $110.00 $880.00 Technician 2 $60.00 $120.00 2. Make revisions to base line, plan views, Engineer 10 $110.00 $1,100.00 erosion , survey control, drainage, Technician 55 $60.00 $3,300.00 and cross section sheets 3. Quality Control Review Engineer 4 $110.00 $440.00 4. Attend meetings to discuss and Engineer 5 $110.00 $550.00 review revisions 5. Plot, scan and run plan sets Technician 4 $60.00 $240.00 6. Prepare Change Order & Meet with Engineer 2 $110.00 $220.00 Contractor Clerical 1 $45.00 $45.00 7. Attend Utility Relocation Meetings Engineer 7 $110.00 $770.00 8. Water line revisions due to SBC conflicts Engineer 12 $110.00 $1,320.00 Sr. Technician 25.5 $60.00 $1,530.00 Draftsman 1 $45.00 $45.00 9. R.O.W. issues, field survey recovery of Woodhollow Subdivision pins. Engineer 4 $110.00 $440.00 2 Man Crew 4 $95.00 $380.00 Survey Technician 4 $70.00 $280.00 10. Roadway & Drainage Design alternative (due to SBC conflicts). Prepare plan sheets. Engineer 6 $110.00 $660.00 Sr. Technician 16 $60.00 $960.00 11. Meet with City of Round Rock & Contractor Engineer 4 $110.00 $440.00 12. Reimbursables $400.00 Grand Total For This Supplemental Agreement $14,120.00 EXHIBIT D SUPPLEMENTAL AGREEMENT No. 6 - RED BUD LANE CR 122 Phase I & II Street Improvements SCOPE OF SERVICES AND MANHOUR PROJECTION Task: Red Bud Lane CR 122 Phase I & II Street Improvements (Forest Creek to Brushy Creek) Additional Survey and Engineering Services completed. TOTAL M r' L() M a- N 0 O O M O N vi 2 D Q STAFF SURVEYOR 1- N O $95.00 $570.001 2 MAN CREW CO CO $95.001 0 O O t0 r. Eft 3 Man CREWS M M 0 O O N Ea $360.001 SCT N N 0 O O CO Ea 0 O O N a- CA Q W LU d g a N $110.00' 0 O O N N Efk IO:\0601-2-058 \Fee Schedule manhourprojections.doc 4-17-06 Field Survey CR 122 right-of-way from CR 123 to Evergreen to tie HDR parcels. Field locate 2 - 24" RCP headwall at Forest Ridge. Revise CAD file to reflect HDR right-of- way as surveyed. 'TOTAL MANHOURS 'HOURLY RATE 'TOTALS 'Reimbursables (Estimated Amount) a- N M CERTIFICATE OF LIABILITY INSURANCE PRODUC:E7t Brookshire Insurance Agency PO Box 830 , TX 76574 Date: March 29, 2006 COMPANIES AFFORDING COVERAGE A St Paul Travelers B c: Ba er-Aicklen & Associates Inc. D 507 W. Liberty Ave, Round Rock, TX 78664 THIS IS TO CERTIFY THAT the Insured named above is insured by the Companies listed above with resp�eci pa it bis operations hereinafter &scribed, for the types of insurance and in accordance witb the provisions of` d standard policies used by the companies, and further hereinafter descri'bcd. Exceptions to the policies arc noted below. LTR - A ems uA cry BK02187571 3-20-06 3-20-07 ?ROD*)[TSOMP/OT AGG. PERSONAL 4 AM, itiILAY ACH OCCURRENCE FIRE DAMAGE (Any urns Ca.) MEn. EXPENSE (Any one prion) $2,000,000 s2,000,000 51,000,000 51,000,000 s 300,000 s 10,000 - A AUTcz1 BA02187834 3-20-06 3-20-07 COMBINED SINGLE war • DILY iN)VRY (Pur wan) BODUX 1 4JURY ors rci dei ) PRorERTY DAMAGE 51,000,000 s $ t B102187571 3-20-06 -20-07 EACH OcCURR NcL t 2,000,000 AGGREGATE 5 B 0218757 3-20-06 3-20-0 7sTATUTOICY uwrs EACH ACCIDENT D - POLICY LWT DISEASE . EACH EMPLOYEE 11,000,000 $1,000,000 51,000,000 G:. as 'absurd vela set to d any of the more assailed policies company will anal tlditY (3t)) days +vratteaa name to the certificate holder toned below. C RTIF/CATE 00650 - 7/2003 City City of Retool Rock 221E.. Meda meet Rand Reek Texas 78664 Page 1 Typed R. Brent Kriegel iabitty Insurance CR 123 vs N N r V V Z J m O W ATTIS SCHOO RD Red Bud Lane Phases 1 & 2 DATE: May 25, 2006 SUBJECT: City Manager Action — June 9, 2006 ITEM: Consider a resolution authorizing the Mayor to execute Supplemental Agreement No.6 with Baker-Aicklen & Associates for the design of roadway improvements on Red Bud Lane (CR122) from Forest Creek Drive to Brushy Creek. Department: Transportation Services Staff Person: Thomas G. Martin, P. E., Director of Transportation Services Justification: Under the scope of services for this Supplemental Agreement No. 6, Baker-Aicklen & Associates will provide the following continued engineering services for the Red Bud Lane Project from CR 123 to Gattis School Road: (1) review plans for possible revisions; (2) make revisions to base line, plan reviews, erosion, survey control, drainage, and cross section sheets; (3) quality control review; (4) attend meetings to discuss and review revisions; (5) plot, scan and run plan sets; (6) prepare change orders and meet with contractor; (7) attend utility relocation meetings; (8) water line revisions due to SBC conflicts; (9) ROW issues, field survey recovery of Woodhollow subdivision pins; (10) roadway and drainage design alternative due to SBC conflicts, prepare plan sheets; and (11) meet with City of Round Rock and contractor. Funding: Cost: $2,030.00 Source of Funds: 98 GO Bonds Outside Resources: Baker-Aicklen & Associates, Inc. Background Information: This supplemental agreement will enable Baker-Aicklen & Associates to continue to provide design for the Red Bud Project, CR 123 to Gattis School Road. The original professional services agreement with Baker-Aicklen was executed in January of 2000. Public Comment: N/A