CM-06-07-150Project:
(Nerve, Address)
To:
(Contractor)
Round Rock Fire Station #2
200 West Bagdad Avenue
Round Rock, Texas 78664
Royce Tschatchula
1801 Whip 0 Will
Round Rock, TX 78681
Change Order No.: 1
Initiation Date: June 22, 2006
Architect's Project No.: A72011.02
Contract For: General Construction
Contract Date: March 23, 2006
The Contract is changed as follows:
1. Lower existing 8" water line below proposed waste water line.
This Change Order is not in effect and will not be Included In the Contract Documents until signed by the Owner, Architect and
Contractor. Changes included herein are subject to all conditions affecting them under the substitution specification section.
SUMMARY
The original (Contract Sum) was
Net change by previously authorized Change Orders $ 1,155,949.00
The (Contract Sum) prior to this Change Order was $ 0
The (Contract Sum) will be (increased) by this Change Order $ 1,155,949.00
The new (Contract Sum) including the Change Order will be 18,545.84
The Contract Time will be (unchanged) by ( 0) Days "$ 1,174,494.84
� 1,174,484.$4
The Date of Substantial Completion as of the date of this Change Order therefore is 330 days
Changes included in the summary above (do)(do not) Include, modifications which have been authorized by Construction
Change Directive(s).
-PBS&J
Architect
1120 Capital of Texas Hwy. S
--A-daress
Bldg. 3, Suite 100, Aus 'n TexaQ
Authorized:
Royce Construction Co. Inc The City of Round Rock, Texas
contract°,
1801 Whip 0 Will
Address
Owner
221 East Main Street
Round Rock, Texas 78664
Oi1u/co 7- iso
2-101P
1 rOl 7040 d ?OW
Rae. effee Rade, 7exaa ?5681
5/23,3004 ai
gece
z• Lower Existing 8" water line
Undemeath proposed waste water line
General Contractor Mark-up o
10%
Total
$16,862.84
1 683.00
$ 18,545.84
Smith Contracting Co., Inc.
CHANGE ORDER PROPOSAL
ROUND ROCK FIRE STATION
6/1/2006
DESCRIPTION: Lower existing 8" DI water line underneath prop waste water line
LABOR:
MATERIAL:
EQUIPMENT:
TOTAL
=ani
Hours
40
40
40
Rate Total
$30.00
$18.00
$12.00
1111.1111111111
$1200.00
$720.00
$1,440.00
$3,360.00
GC COST
LABOR BURDEN (Labor only)
SUBTOTAL
GC OH & PROFIT (Material)
TOTAL
55%
25%
$13,495.90
$1,848.00
$15,343.90
$1,518.94
$18,862.84
DATE: July 7, 2006
SUBJECT: City Manager Approval July 14, 2006
ITEM: Action authorizing the City Manager to execute
change order No. 1 with Royce Construction for
relocation of existing 8 inch waterline on Blair Street
for Fire Station No. 2.
Department: Engineering & Development Services
Staff Person:
Tom Word, Chief of P.W. Operations
Larry Madsen, Liaison Construction Manager
Justification:
Existing 8 inch waterline must be lowered for the new sewer Zine to
service Fire Station No. 2. The 8 inch waterline was not in location or
of depth shown in City plans for this area on Blair Street.
Funding:
Cost: $18,545.84
Source of funds: 2002 GO Bonds
Outside Resources: N/A
Background Information: N/A