CM-06-07-150Project: (Nerve, Address) To: (Contractor) Round Rock Fire Station #2 200 West Bagdad Avenue Round Rock, Texas 78664 Royce Tschatchula 1801 Whip 0 Will Round Rock, TX 78681 Change Order No.: 1 Initiation Date: June 22, 2006 Architect's Project No.: A72011.02 Contract For: General Construction Contract Date: March 23, 2006 The Contract is changed as follows: 1. Lower existing 8" water line below proposed waste water line. This Change Order is not in effect and will not be Included In the Contract Documents until signed by the Owner, Architect and Contractor. Changes included herein are subject to all conditions affecting them under the substitution specification section. SUMMARY The original (Contract Sum) was Net change by previously authorized Change Orders $ 1,155,949.00 The (Contract Sum) prior to this Change Order was $ 0 The (Contract Sum) will be (increased) by this Change Order $ 1,155,949.00 The new (Contract Sum) including the Change Order will be 18,545.84 The Contract Time will be (unchanged) by ( 0) Days "$ 1,174,494.84 � 1,174,484.$4 The Date of Substantial Completion as of the date of this Change Order therefore is 330 days Changes included in the summary above (do)(do not) Include, modifications which have been authorized by Construction Change Directive(s). -PBS&J Architect 1120 Capital of Texas Hwy. S --A-daress Bldg. 3, Suite 100, Aus 'n TexaQ Authorized: Royce Construction Co. Inc The City of Round Rock, Texas contract°, 1801 Whip 0 Will Address Owner 221 East Main Street Round Rock, Texas 78664 Oi1u/co 7- iso 2-101P 1 rOl 7040 d ?OW Rae. effee Rade, 7exaa ?5681 5/23,3004 ai gece z• Lower Existing 8" water line Undemeath proposed waste water line General Contractor Mark-up o 10% Total $16,862.84 1 683.00 $ 18,545.84 Smith Contracting Co., Inc. CHANGE ORDER PROPOSAL ROUND ROCK FIRE STATION 6/1/2006 DESCRIPTION: Lower existing 8" DI water line underneath prop waste water line LABOR: MATERIAL: EQUIPMENT: TOTAL =ani Hours 40 40 40 Rate Total $30.00 $18.00 $12.00 1111.1111111111 $1200.00 $720.00 $1,440.00 $3,360.00 GC COST LABOR BURDEN (Labor only) SUBTOTAL GC OH & PROFIT (Material) TOTAL 55% 25% $13,495.90 $1,848.00 $15,343.90 $1,518.94 $18,862.84 DATE: July 7, 2006 SUBJECT: City Manager Approval July 14, 2006 ITEM: Action authorizing the City Manager to execute change order No. 1 with Royce Construction for relocation of existing 8 inch waterline on Blair Street for Fire Station No. 2. Department: Engineering & Development Services Staff Person: Tom Word, Chief of P.W. Operations Larry Madsen, Liaison Construction Manager Justification: Existing 8 inch waterline must be lowered for the new sewer Zine to service Fire Station No. 2. The 8 inch waterline was not in location or of depth shown in City plans for this area on Blair Street. Funding: Cost: $18,545.84 Source of funds: 2002 GO Bonds Outside Resources: N/A Background Information: N/A