CM-06-08-166Project: (Name, Address) To: (Contractor) Round Rock Fire Station #2 200 West Bagdad Avenue Round Rock, Texas 78664 Royce Tschatchula 1801 Whip 0 Will Round Rock, Texas 78681 The Contract is changed as follows: 1. Increase fire main connection from 4" to 6" diameter line. Change Order No.: 2 Initiation Date: August 3, 2006 Architect's Project No.: A72011.02 Contract For: General Construction Contract Date: March 23, 2006 This Change Order is not in effect and will not be included in the Contract Documents until signed by the Owner, Architect and Contractor. Changes included herein are subject to all conditions affecting them under the substitution specification section. SUMMARY The original (Contract Sum) was $ 1,155,949.00 Net change by previously authorized Change Orders $ 18,545.84 The (Contract Sum) prior to this Change Order was $ 1,174,494.84 The (Contract Sum) will be (increased) by this Change Order $ 4,900.65 The new (Contract Sum) including the Change Order will be e,$ 1,179,395.49 The Contract Time will be (unchanged) by ( 0 ) Days o$ 1,179,395.49 The Date of Substantial Completion as of the date of this Change Order therefore is 330 Changes included in the summary above (do)(do not) include modifications which have been authorized by Construction Change Directive(s). PBS&J mrteci 1120 Capital of Texas Hwy. S. Bldg. 3, Suite 100 Austin Texas by Royce Construction Co. Inc. Cectracwr 1801 Whip 0 Will Authorized: The City of Round Rock, Texas Owner 221 East Main Street RRod Rock, Teps 7:681 Round Rock, Texas 78664 IYY bate fr/v/at 86/22/2006 10:50 5129907855 Poat4P Fax Note 7671 On W% Z'. !Rise 1 n Sant J4QY bin. cow °°�'rtiutdF�, Fnm•. • Fx• �agG-1 % Furl DESCRIPTION: LABOR; MATERIAL: EAUIPM SMITH CONTRACTING CO PAGE 01 Smith Contracting Co., Inc. Round Rock Fire Station 8/2212006 linitis Total ForemanA,avouttoerypnator 1 14 $30.00 1420.00 °parser 1 14 510.00 $2$2.00 Laborer 1 48 112.00 5576.00 TOTAI Yalta/ 1,248.00 Pipe and Mande 1 I-5 I -. ,w 11,663.00 $1,863.00 4' tapping sleeve 1 LS 5460.00 $450-00 TOTAI TOTAL 2,313. • Backhoe y 1 went HRS mous $76.00 675.00 TOTAI GC COST TABOR BURDEN (Labor only) SUBTOTAL GC ON 8. PROFIT Malarial) TOTAL 65% 25% 175.00 63.636.00 $686.40 64.322.40 6578.25 au;900.65 DATE: SUBJECT: ITEM: August 7, 2006 City Manager Approval August 11, 2006 Action authorizing the City Manager to execute change order No. 1 with Royce Construction to increase fire main connection for Fire Station No. 2. Department: Engineering & Development Services Staff Person: Justification: Tom Word, Chief of P.W. Operations Larry Madsen, Liaison Construction Manager Increase building fire sprinkler line from a four -inch to a six-inch line from the water main to the building. This is required due to water pressure that is available on the water main along Blair Street at Bagdad. There is not a contractor mark-up, this is an actual price from sub -contractor. Funding: Cost: $4,900.65 Source of funds: 2002 GO Bonds Outside Resources: N/A Background Information: N/A Public Comment: N/A