CM-06-09-179Project:
(Name. Address)
To:
(contractor)
Rock 'N River Aquatic Center
3300 Palm Valley Blvd
Round Rock, Texas
Chasco Constructors
P.O. Box 1057
Round Rock, Texas 78680
The Contract is changed as follows:
Credit for balance hardware allowance addition
Addition for tree bubbler irrigation
Change Order No.: 6
Initiation Date: 8/29/2006
Architect's Project No.:
Contract For. Rock N' River
Contract Date: 10/25/2005
($2,970.00)
$5,444.00
TOTAL: $2,474.00
This Change Order is not in effect and will not be Included in the Contract Documents until signed by the Owner, Architect and
Contractor. Changes included herein are subject to all conditions affecting them under the substitution specification section.
SUMMARY
The original (Contract Sum) was $ 2,720,152.00
Net change by previously authorized Change Orders $ 28,704.00
The (Contract Sum) prior to this Change Order was $ 2,748,856.00
The (Contract Sum) will be increased by this Change Order $ 2,474.00
The new (Contract Sum) including the Change Order will be n$ 2,751,330.00
The Contract Time will be (unchanged) by ( ) Days $
(unchanged) by ( ) Days
The Date of Substantial Completion as of the date of this Change Order therefore is
Changes Included in the summary above (do)(do not) include modifications which have been authorized by Construction
Change Directive(s).
Arctwted
Address
Chasco Constructors
contractor
P.O. Box 1057
Rs and Rock, T: as 78680
Authorized:
City of Round Rock
Owner
221 E. Main Street
Address
Round Rock, Texas 78664
BY
Date
(m -Gu- - (71
4"..)(. 220(o
Dae
Date
HASCO
ONCTRUCTORS
27 June 2006
Kimley-Hom and Associates, Inc.
12700 Park Central Drive
Dallas, Texas 75251
P.O. Box 1057
Round Rock, Texas 78680
(512) 244-0600
1-800-441-4109
Fax: (512) 244-0489
mail@chasco.com
RE: Rock'n River Family Aquatic Center CP 009 (KMA RFP N/A) — Add Tree Bubblers
Dear Mr. Mark Hatchel:
We hereby submit our proposal for your consideration and approval to execute a change
to the contract for the above referenced project. For your review, we have provided
pricing for labor, equipment and material to add tree bubblers per the request of the City
of Round Rock.
Changes per attached CP No. 009 Pricing Sheet dated 27 June 2006: $5,444.00
If approved, this change will result in a change to the Contract Amount by the sum of
$5,444.00. This work is complete at this time. If approved, this CP will act as an Owner
Change Order.
Re
pectfully,-f APPROVED BY:
Owner Date
JJm Free an
Project Manager
cc: File: 05235 — 112-009
Architect Date
ac )
Chasco Contracting
Rock'n River Family Aquatic Center
Project No: 05235
Est. No:
CP -009
Description: Add tree bubblers per CoRR requirements and direction.
Date: 27 June 2006
Prepared by: Jim Freeman
Pricing Sheet
1
Add tree bubblers
1
LS
0.00
$0
4605.00
$4,605
$4,605
SSee Attached Sub Proposal)
0.00
$0
$0
$0
$0
SUBTOTALS
$0
$0
$4,605
$4,605
Theming Allowance Summary:
Overhead
Sales Tax Materials (only)
SUBTOTAL
Fee
SUBTOTAL
Insurance
PSP Bond
GRAND TOTAL
10.00%
0.00%
5.00%
$461
$0
$5,066
$253
$5,319
1.25% $66
1.10% $59
$5,444
JUN -26-2006 MON 10:47 AM UTZ ENVIRONMWNTAL SVCS FAX No. 5125289698 P. 001
LANDSCAPB • IRRIGATION • HYDROMULCH
'TO: Jim Freeman
'Cuzco Constructors
. FROMI • Chris Uta • •
Utz Enviromnentaf Services
PATE:, lune 26, 2006 .. .
: REQ • • Rodc'n River Family Aquatic Center.
Provide all maierial, labor and equipment for the folbwk:ge
1. Instoll irrigation bubblers on oil trees
•
• Note: Price -valid for'thirty Boys from date of proposal. •
• Eicdusioriss .
1. No Bond; if necessary Add .3%
2. Sales Tax •
3. Writer Meter •• •
• . • 4. 110V Power to Controller
Agreed,
4/4/.' ChrisK. Utz . • •
• • • Licensed 'Irrigator, #5625
$1,605.00
The Tgxos Conmmission or) Eamronmental Ouolity.regulates irrigation in Tesxos
' • P.O. Box 13087, Austin, TX 78711-3087 ..• .
DALLAS: 2355 N.:HIGHWAY 3b0 #514 • GkAND PRAIRIE, TEXAS 75050 ! EAX •(817) 627-2888
AUSTIN: 36M. COUNTY ROAD 272: • LEANDER, TEXAS, 78641 'BPS: (51.2) 528:-9696
• • .• .:www. utxelivilronrnentals'ervices:.com
AUG' 16-2006 WED 06 23 PM UTZ ENVIRONNWNTAL SVCS FAX No. 5125289698 P. 001
TO:
LANDSCAPE • IRRIGATION • I-IYDROMULCH
Jim Freeman
Chas<o Constructors
FROM: Chris Utz
Utz Environmenta[ Services
DATE: August 16, 2006
Rock'h River Family Aquatic .Center
Tree Bubbler Addition:
REI
Scbae:
Quantity
Description
Unit
1,200
'h tn. PVC Pipe
LF
400
3/4 in. PVC Pipe
LF
400
1 In. PVC Pipe
LF
23
Rain Bird 1300 Bubblers
Ea.
1
Rain Bird 2 In. PEB Valve
Ea.
1
Concrete Valve Box
Ea.
330
14 Gauge Wire
LF
.Note; The installation required the removal and replacement of all plant material and mulch In the Islands In
order to access the sleeves.
Agreed,
ChrR! L. Utz
Licensed Irrigator, #5625
The Texas Commission an Environmental Quality regulates irrigation in Texas
P.O. Box 130E17, Austin, TX 76711-3067
1094$ E. CRYSTAL FALLS PARKWAY • LEANDER, TEXAS 78641 • BUS: (512) 52$_9696 • FAX: (512) 528-9698
www.utzenvironmentahervices.com
DATE:
SUBJECT:
ITEM:
August 30, 2006
City Manager Approval - September 8,2006
Action authorizing the City Manager to execute Change Order No. 6
with Chasco Contracting for Rock'n River Family Aquatic Center..
Department: Engineering and Development Services
Staff person: Tom Word, Chief of P.W. Operations
Larry Madsen, Construction Manager
Justification:
Upon completion of Aquatic Center a balance of $2,970.00 was left in the
allowance budget for hardware. This is returned as a credit. Tree bubblers were
left out of original landscape plans and were added at a cost of $5,444.00. The
total for this change order is an addition to the contract in the amount of
$2,474.00.
Funding:
Cost: $2,474.00
Source of funds: 2002 G.O Bonds
Outside Resources: N/A
Background Information: N/A
Public Comment: N/A