CM-07-02-020CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
DEPART Parks & Recretaion
PROJEC Round Rock West Park Improvement
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
PAGE 1 OF 2
DATE: 2/1/2007
CHANGE ORDER NO: 1
JUSTIFICATION:
$52,050.96 Restrooms at pavilion
$0.00 are not in compliance with ADA standard.
$8,715.72
$0.00
CHANGE DATA
PREPARED BY: FOIPON HASSAN
ENGINEER
DATE
2/2/2007
NAME OF CONTRACTOR
SIGNATURE: 1-4.
PRINT NAME/TITLE: '4 1�RL- i fZAM�c
APPROVED:
011(01301
OF ROUND ROCK
UA- 01 -0a -ow)
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER:
PREVIOUS CHANGE ORDER:
TOTAL % CHANGE:
ORIGINAL CONTRACT PRICE PLUS
CHANGE ORDERS: $60,766.68
16.80°%
0
16.80°%
c onstco2/forms6flk
ITEM #
DESCRIPTION OF
CHANGES
UNIT
QTY.
UNIT
PRICE
AMOUNT
ADDED DAYS
CALENDAR/
WORKING
1-
2-
3-
Demo existing wall divider in both
Men and Women restroom
Remove and replace existing toilets,
sinks with approved fixtures per ADA
Install Grab bars behind all toilets
FOR THE LUMP SUM OF
$8,715.72
TOTAL:
$8,715.72
20 days
PREPARED BY: FOIPON HASSAN
ENGINEER
DATE
2/2/2007
NAME OF CONTRACTOR
SIGNATURE: 1-4.
PRINT NAME/TITLE: '4 1�RL- i fZAM�c
APPROVED:
011(01301
OF ROUND ROCK
UA- 01 -0a -ow)
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER:
PREVIOUS CHANGE ORDER:
TOTAL % CHANGE:
ORIGINAL CONTRACT PRICE PLUS
CHANGE ORDERS: $60,766.68
16.80°%
0
16.80°%
c onstco2/forms6flk
DATE:
SUBJECT:
ITEM:
February 5, 2007
City Manager Approval - February 9, 2007
Consider a resolution authorizing the City Manager to
approve a proposal for Construction Services with Ceda -
Tex Services for the Round Rock West Park Development
Project.
Department:
Staff Person:
Justification:
PARD
Rick Atkins, Parks and Recreation Director
Upon the TDLR accessibility inspection, the restroom
facilities were found to be out of compliance. This
proposal will bring the restrooms into full compliance with
the standard ADA regulations.
Funding: $70,000
Cost: $8,715.72
Source of funds: 2000 C.O. Bond
General Self -Financed Construction
Outside Resources: N/A
Background Information: This project will replace the existing restroom
facilities with new accessible units.
Public Comment: N/A