CM-07-03-038Mar 06 07 02:30p John Bethel 517-622-4882 p.2
Change Order No. 1
•
Project Name: 2006-2008 Tank Rehabilitation '
Consultants Project No.:
Project Owner City of Round Rock
212 Commerce Cove, Round Rock, TX 78664
Date of Issuance: February 26, 2007
Project Contractor: MK Painting, Inc.
4157 Seventh
Wyandotte, MI48192
Date of Contract:
February 09, 2007
Date of Notice to Proceed:
February 09, 2007
Original Completion Date:
August 08, 2007
Contract Period 180
It is agreed to modify the Contract referred to above as follows:
CPR #
ITEM AND DESCRIPTION OF CHANGES
CHANGE IN
CONTRACT PRICE
CHANGE IN
CONTRACT TIME
Delete bid item number 12 — paint logo on tank
($12,000)
-0-
Difference Net
($12,000)
-0-
Summary: It is agreed to modify the Contract referred to above as follows:
Contract Price prior to this Change Order Contract Time prior to this Change Order
$ 430.650
Net Increase (decrease) of this Change Order
($12,000)
180 cd - August 08. 2007
Net Increase (decrease) of this Change Order
Number of dans -0-
Revised Contract Price with all approved Change Orders Revised Contract Time with afl approved Change Orders
$ 418.650
180 cd - August 08. 2007
The changes included in this Change Order ars to be accomplished in accordance with the terms, stipulations
and conditions of the original Contract as though included therein.
Acce Contractor Johnir- II, MK Painting, Inc. Date:
(Utilities Administration):
d for Owner by manager)
Attest
N/A
re4uiredf :John Konzen, HOT Inspection Services, Inc.
Distribytion•
01-00-0 39
0 Contractor 0 Office
March 6, 2007
Date:
March 6, 2007
Date:
3-9-07
Date:
3-6-07
❑ Field ❑ Other
DATE: March 5, 2007
SUBJECT: City Manager Approval - March 9, 2007
ITEM: Action authorizing the City Manager to execute Change Order No. 1
with MK Painting for the 2006-2008 Tank Rehabilitation Project.
Department: Water and Wastewater Utilities
Staff Person: Michael Thane, P.E., Director of Utilities
Justification:
The MK Painting construction contract is for the rehabilitation of the Bowman and Vista
Heights Tanks. The rehabilitation cost for both tanks was originally $430,650.00 including
$12,000 for painting a logo on the Vista Heights tank on behalf of Texas State University.
The logo will be paid for by Texas State University. The bid amount for this item was
considered too high by the university; therefore, the city is obtaining bids from other
contractors to paint the logo at a later date for a lower cost. MK Painting's contract will now
be for $418,650.
Funding:
Cost: ($12,000)
Source of funds: Utility Self Finance Construction - Water
Outside Resources: John H. Konzen - HOT Inspection Services
Background Information:
The Texas Commission for Environmental Quality (TCEQ) requires rehabilitation for water
storage tanks in compliance with state rules which includes annual inspections of all water
storage tanks within our distribution system. With the information from inspections we
schedule each water tank in the city's system for repairs and painting, based on its present
condition. In general, steel tanks need re -painting about 15 years. The Bowman tank and
Vista Heights tank were previously painted in 1989 and 1985, respectively.
Public Comment: N/A
Blue Sheet Format
Updated 01/20/04